A construction method for node treatment at the joint between structural wall and shear wall under window
By installing horizontal and vertical structural components at the joints between the wall and shear wall under the window, and pouring concrete layer by layer, the cracks caused by concrete shrinkage are solved, the connection strength and stability at the joints are improved, and the The structural stiffness is reduced.
Patent Information
- Application Number
- CN202211095064.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-08
- Publication Date
- 2024-12-20
- Estimated Expiration
- 2042-09-08
AI Technical Summary
When constructing at the joint between the wall under the window and the shear wall, concrete shrinkage leads to cracks. The prior art requires the addition of crack-resistant steel bars to prevent cracks, but this reduces the stiffness of the overall structure.
Install horizontal structure joint assembly before the concrete is initially set, and vertical structural assembly and crack-resistant steel bars are installed between the shear wall and the structural wall. By pouring concrete layer by layer and vibrating, ensure the close integration of each layer of concrete. Double seam assembly is secured to improve joint tightness at the joints.
Effectively prevent concrete cracking, improve the connection strength and stability between the joints between the wall under the window and the shear wall, avoid the overall stiffness of the structure, and ensure the connection tightness during construction and the firmness after forming.
Smart Images

Figure CN115262808B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction at the joint of a structural wall under a window and a shear wall, and more specifically, to a construction method for node treatment at the joint of a structural wall under a window and a shear wall. Background Art
[0002] When aluminum alloy formwork is used in the main structure stage of construction, its high rigidity and strong plasticity are utilized to bring out the masonry structure of the outer wall opening with concrete structure at one time during the construction process. However, this may cause cracks in places such as the wall under the window due to concrete shrinkage.
[0003] The invention patent with patent application publication number CN110424564A discloses a joint connection structure of the exterior wall of an assembled building, including a first exterior wall and a second exterior wall, the top and side end surfaces of the first exterior wall and the second exterior wall are both provided with connecting grooves, a joint is arranged between the first exterior wall and the second exterior wall, a joint connection structure is installed inside the joint, the first exterior wall and the second exterior wall are connected through the joint connection structure, in this invention, a joint is arranged between the first exterior wall and the second exterior wall, a joint connection structure is arranged inside the joint, a first L-shaped bracket and a second L-shaped bracket are respectively arranged on both sides of the joint connection structure, the joint connection structure is connected to the connecting grooves on the first exterior wall and the second exterior wall through the connecting blocks on the first L-shaped bracket and the second L-shaped bracket, so that the joint connection structure is completely independent of the first exterior wall and the second exterior wall, and can be disassembled while ensuring the connection effect, so as to facilitate the later maintenance and disassembly of the wall.
[0004] However, in the above scheme, in order to prevent the occurrence of concrete cracks at the nodes of the wall under the window and the surrounding shear wall of the all-concrete exterior wall, anti-cracking steel bars must be added transversely to the wall under the window, the lower hanging plate, and the anti-slope. The anti-cracking steel bars are extended into the shear wall. At the same time, constructing some masonry structures, such as the wall under the window, into concrete structures will increase the overall stiffness of the structure. The wall under the window and the shear wall are flexibly connected to separate the non-structural body from the structural body, thereby reducing the overall stiffness of the structure. Summary of the invention
[0005] The technical solution of the present invention aims at the technical problem that the existing technical solutions are too single, and provides a solution that is significantly different from the existing technology. In order to overcome the above-mentioned defects of the prior art, the present invention provides a construction method for node treatment at the joint of the structural wall under the window and the shear wall, so as to solve the problem proposed in the above-mentioned background technology that constructing a concrete structure at a position such as the wall under the window will increase the stiffness of the entire structure. The wall part under the window and the shear wall are flexibly connected to separate the non-structural body from the structural body, thereby reducing the overall stiffness of the structure.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a construction method for processing the node at the joint between the structural wall under the window and the shear wall, and the specific construction steps are as follows;
[0007] Step 1: After the upper floor slab concrete pouring is completed, install the horizontal structural joint assembly between the floor slab and the structural wall under the window at the floor slab or beam position before the concrete begins to set, and after the installation is completed, use 22# tie wire to fix it firmly to prevent movement;
[0008] Step 2: When carrying out on-site wall construction, first tie the shear wall reinforcement and the structural wall reinforcement under the window. After the reinforcement is tied, set the vertical structural component between the shear wall and the structural wall, and set the anti-cracking reinforcement between the structural wall and the shear wall. The reinforcement also has the function of fixing the vertical structural component. The anti-cracking tie reinforcement passes through the vertical structural component and is tied and overlapped with the wall reinforcement on both sides. The two sides of the vertical structural component are firmly fixed with wall reinforcement, and then the mobile phone takes a photo and uploads it to the background data computer. The quality supervisor immediately rushes to the site to check the drawings and installation position;
[0009] Step 3: Install the aluminum alloy formwork of the wall as a whole and reinforce it firmly. Before installing the formwork at the joint of the shear wall and the structural wall, confirm the installation position and fixation of the horizontal structural seam assembly again, and ensure that the water stop joints on both sides of the seam plate are placed in the shear wall and the structural wall respectively;
[0010] Step 4. Pour concrete symmetrically in layers on both sides of the structural seam plate and vibrate to make it dense. The pouring height of the first layer should not exceed 500mm, and the pouring height each time thereafter should not exceed 1.0m. When vibrating the second layer of concrete, the vibrating rod should extend 50mm into the previous layer of concrete. In order to ensure a good combination of the newly poured concrete and the already poured concrete, pour a 50-100mm thick layer of mortar with the same composition as the original concrete on the bottom layer before pouring the concrete. During pouring, arrange a special person to check the position of the seam plate to prevent displacement caused by concrete impact and affect the pouring quality. When the concrete is poured to the predetermined elevation of the top of the wall, smooth the surface.
[0011] Preferably, in step one, a tension measuring instrument is used to pull the fixed 22# binding wire with a pressure of 10-20N, and the pulling frequency is not less than three times.
[0012] Preferably, the anti-cracking steel bars in step 2 are of one of the types HRB335, HRB400 and HRB400, and the diameter of the anti-cracking steel bars is five centimeters and they are fixed by cross weaving.
[0013] Preferably, in the step three, the wall aluminum alloy formwork is installed as a whole using two construction workers who are respectively located above and at the side of the wall aluminum alloy formwork. At the same time, an air gun is needed to blow along the edge to check whether there is any air leakage problem in the edge gap. The number of back and forth checks must be greater than five times.
[0014] Preferably, the pouring temperature of the first layer in step 4 shall not exceed 40°C, and it is necessary to wait for 10 minutes after the pouring is completed, and after 10 minutes, a layer of cool water with a thickness of 0.5 cm is sprayed by atomization using a sprinkler.
[0015] Preferably, in step 4, the vibrating rod is reciprocated along the concrete for 3-5 times, and when the vibration is completed, the vibrating rod needs to be moved vertically upwards, and the upward movement is divided into two times, and the dwell time of each time is 5 minutes.
[0016] Preferably, the vertical structure seam pulling assembly includes two limiting support templates, two vertical cross-pull plates are installed between the two limiting support templates, and the interior of the vertical cross-pull plates is provided with a plurality of groups of embedded screws arranged equidistantly from top to bottom, a crossbeam bracket is provided at the top of the limiting support template, a locking nut is threadedly connected to the outside of the embedded screw and located on one side of the vertical cross-pull plate, and two embedded positioning blocks are embedded at the top of each of the vertical cross-pull plates, a fixing bolt is embedded at the top of the embedded positioning block and close to the position of the vertical cross-pull plate, a first locking bolt is embedded at the top of the embedded positioning block and close to the position of the crossbeam bracket, the vertical cross-pull plate is detachably connected to the embedded positioning block by a fixing bolt, and the crossbeam bracket is detachably connected to the embedded positioning block by a first locking bolt.
[0017] Preferably, the horizontal structure seam assembly includes a first horizontal horizontal pull plate, an embedded pull plate is fixed on the top of the first horizontal horizontal pull plate, and an alignment locking support plate is provided inside the embedded pull plate, a plurality of second locking bolts are embedded and penetrated on one side of the alignment locking support plate, and a second horizontal horizontal pull plate is welded to the bottom end of the alignment locking support plate, the alignment locking support plate and the alignment locking support plate are detachably connected by a plurality of second locking bolts, an embedded connecting screw is installed inside the first horizontal horizontal pull plate and at the other side of the embedded pull plate, a positioning nut is provided on the outer wall of the embedded connecting screw and at the top of the first horizontal horizontal pull plate, and the positioning nut is threadedly connected to the embedded connecting screw.
[0018] Technical effects and advantages of the present invention:
[0019] 1. The present invention adopts a horizontal structural seam assembly between a floor slab and a structural wall under a window installed at a floor slab or a beam position before the initial setting of concrete, a vertical structural assembly is arranged between the shear wall and the structural wall after the steel bars are tied, and anti-cracking steel bars are arranged between the structural wall and the shear wall, the steel bars also have the function of fixing the vertical structural assembly of the structure, the anti-cracking tie steel bars pass through the vertical structural assembly and are tied and overlapped with the steel bars of the walls on both sides, so that the connection tightness of the node at the joint of the structural wall under the window and the shear wall can be increased during the construction process, so that not only will cracking not be caused after forming, but also the strength of the node at the joint of the structural wall under the window and the shear wall is improved;
[0020] 2. The first layer of the present invention should not be poured at a height of more than 500mm, and each subsequent pouring height should not exceed 1.0m. When vibrating the second layer of concrete, the vibrating rod should be extended into the upper layer of concrete, so that the newly poured concrete is well combined with the poured concrete. Before pouring the concrete, a layer of mortar with a thickness of -mm and the same composition as the original concrete is poured on the bottom layer. When constructing the node treatment at the joint of the structural wall and the shear wall under the window, ensure that the concrete is constructed in layers to avoid excessive concrete pressure at one time, causing the bottom to expand out, and ensure that each layer of concrete is more firmly combined, has better stability, and is not prone to leakage.
[0021] 3. The present invention adopts a vertical structure seam assembly and a horizontal structure seam assembly. When the node treatment construction is carried out at the joint of the structural wall under the window and the shear wall, two beam brackets can be formed and welded at the upper position of the two limit support templates, and the embedded screws are embedded in the shear wall. The vertical cross-bracing plate is fixed at the connection of the shear wall, and is inserted into the cross-bracing plate and the vertical cross-bracing plate by embedding the positioning support block, so as to ensure that the vertical cross-bracing plate is not easy to deviate when installed on the shear wall. The second locking bolt is used to realize the relative extrusion of the alignment locking support plate and the embedded pull plate. The positioning nut can position and lock the position of the first horizontal cross-bracing plate to ensure the firmness of the first horizontal cross-bracing plate after tightening, forming a horizontal and vertical double tightening gap, showing tightening in different directions, improving the binding tightness of the joint position, and the concrete is more tightly and firmly fitted with the shear wall after forming;
[0022] In summary, through the mutual influence of the above-mentioned multiple effects, the tightness of the connection between the nodes at the joints of the structural wall under the window and the shear wall can be increased during the construction process, so that not only will cracks not be caused after molding, but the binding tightness of the joint position is improved, and the concrete fits more tightly and firmly with the shear wall after molding. In summary, the strength of the nodes at the joints of the structural wall under the window and the shear wall can be improved. After molding, the firmness is better, it is not easy to cause water seepage problems, it will not cause concrete cracks, and the construction stability is higher. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the node processing structure at the joint between the structural wall under the window and the shear wall of the present invention.
[0024] Figure 2 It is a schematic diagram of the external structure of the limiting support template of the present invention.
[0025] Figure 3 It is a schematic diagram of the vertical cross-sectional structure of the vertical cross-braced plate of the present invention.
[0026] Figure 4 For the present invention Figure 2 Enlarged structural diagram at A in the middle.
[0027] Figure 5 It is a schematic diagram of a partially cut-away structure of a vertical cross-bracing plate of the present invention.
[0028] The accompanying drawings are marked as follows: 1. limit support template; 2. beam bracket; 3. vertical cross pull plate; 4. embedded screw; 5. locking nut; 6. embedded positioning support block; 7. fixing bolt; 8. first locking bolt; 9. first horizontal cross pull plate; 10. embedded pull plate; 11. aligned locking support plate; 12. second locking bolt; 13. second horizontal cross pull plate; 14. positioning nut; 15. embedded connecting screw. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] Example
[0031] A construction method for processing the node at the joint between the structural wall and the shear wall under the window, the specific construction steps are as follows;
[0032] Step 1: After the concrete pouring of the upper floor is completed, install the horizontal structural seam assembly between the floor and the structural wall under the window at the floor or beam position before the concrete is initially set, and fix it firmly with 22# tie wire after installation. Use a tension measuring instrument to pull the fixed 22# tie wire with a pressure of 20N, and the number of pulling times is not less than three times to prevent movement;
[0033] Step 2: When carrying out on-site wall construction, first tie the shear wall reinforcement and the structural wall reinforcement under the window. After the reinforcement is tied, set the vertical structural component between the shear wall and the structural wall, and set the anti-cracking reinforcement between the structural wall and the shear wall. The anti-cracking reinforcement is of HRB335 grade. The diameter of the anti-cracking reinforcement is five centimeters and it is fixed by cross weaving. The reinforcement also has the function of fixing the vertical structural component of the structure. The anti-cracking tie reinforcement passes through the vertical structural component and is tied and overlapped with the wall reinforcement on both sides. The two sides of the vertical structural component are firmly fixed with wall reinforcement, and then the mobile phone takes a photo and uploads it to the background data computer. The quality supervisor immediately rushes to the site to check the drawings and installation position.
[0034] Step 3: Install the aluminum alloy formwork of the wall as a whole and reinforce it firmly. The aluminum alloy formwork of the wall is installed as a whole. Two construction workers are respectively located above and on the side of the aluminum alloy formwork of the wall. At the same time, an air gun is needed to blow along the edge to check whether there is any leakage in the edge gap. The number of back and forth inspections must be greater than five times. Before installing the formwork at the joint of the shear wall and the structural wall, confirm the installation position and fixing of the horizontal structure seam assembly again to ensure that the water stop joints on both sides of the seam plate are placed in the shear wall and the structural wall respectively.
[0035] Step 4. The concrete on both sides of the structural seam plate is poured symmetrically in layers and vibrated to make it dense. The pouring height of the first layer should not exceed 500mm, and the pouring temperature of the first layer should not exceed 40℃. After pouring, it is necessary to wait for 10 minutes. After 10 minutes, a layer of cold water with a thickness of 0.5 cm is sprayed by a sprinkler. The pouring height should not exceed 1.0m each time thereafter. When vibrating the second layer of concrete, the vibrating rod should be extended into the upper layer of concrete by 50mm. The vibrating rod moves back and forth along the concrete for 5 times. After the vibration is completed, the vibrating rod needs to be moved vertically upward when moving upward. The upward movement is divided into two times, and the dwelling time is 5 minutes each time. In order to make the newly poured concrete have a good combination with the poured concrete, a 100mm thick layer of mortar with the same composition as the original concrete is poured on the bottom layer before pouring the concrete. During pouring, a special person is arranged to check the position of the seam plate to prevent displacement caused by concrete impact from affecting the pouring quality. When the concrete is poured to the predetermined elevation of the upper mouth of the wall, the surface is smoothed.
[0036] As attached Figure 1-5 A node processing construction method for the joint between the structural wall under the window and the shear wall is shown. The node processing construction method is provided with a horizontal structure seam pulling component and a vertical structure seam pulling component. The setting of each component can improve the stability of the node processing construction at the joint between the structural wall under the window and the shear wall. The specific structural settings of each mechanism and component are as follows:
[0037] In some embodiments, Figure 1-4As shown, the vertical structure seam pulling assembly includes two limiting support templates 1, two vertical cross-pull plates 3 are installed between the two limiting support templates 1, and the interior of the vertical cross-pull plates 3 is provided with a plurality of groups of embedded screws 4 arranged equidistantly from top to bottom, a crossbeam bracket 2 is provided at the top of the limiting support template 1, and a locking nut 5 is threadedly connected to the outside of the embedded screw 4 and located at a side position of the vertical cross-pull plates 3, and the top of each vertical cross-pull plates 3 is embedded with two embedded positioning blocks 6, and a fixing bolt 7 is embedded at the top of the embedded positioning block 6 and near the position of the vertical cross-pull plates 3, and a first locking bolt 8 is embedded at the top of the embedded positioning block 6 and near the position of the crossbeam bracket 2, the vertical cross-pull plates 3 are detachably connected to the embedded positioning block 6 by the fixing bolt 7, and the crossbeam bracket 2 is detachably connected to the embedded positioning block 6 by the first locking bolt 8;
[0038] When the bolt 5 is in the locked position, the two ends of the support rod 2 are locked and the locking nut 5 is locked, so that the locking nut 5 and the locking nut 5 are locked.
[0039] In some embodiments, Figure 5 As shown, the horizontal structure seam pulling assembly includes a first horizontal horizontal pull plate 9, an embedded pull plate 10 is fixed on the top of the first horizontal horizontal pull plate 9, and an alignment locking support plate 11 is provided inside the embedded pull plate 10, a plurality of second locking bolts 12 are embedded and penetrated on one side of the alignment locking support plate 11, and a second horizontal horizontal pull plate 13 is welded to the bottom end of the alignment locking support plate 11, the alignment locking support plates 11 and the alignment locking support plates 11 are detachably connected by a plurality of second locking bolts 12, an embedded connecting screw 15 is installed inside the first horizontal horizontal pull plate 9 and at the other side of the embedded pull plate 10, a positioning nut 14 is provided on the outer wall of the embedded connecting screw 15 and at the top position of the first horizontal horizontal pull plate 9, and the positioning nut 14 is threadedly connected to the embedded connecting screw 15;
[0040] When this embodiment is used, the first horizontal transverse pull plate 9 can be inserted into the vertical transverse pull plate 3, and the second horizontal transverse pull plate 13 can be inserted into the other vertical transverse pull plate 3. In this way, the second locking bolt 12 is rotated, so that the second locking bolt 12 can realize the relative extrusion of the alignment locking support plate 11 and the embedded pull plate 10, the alignment locking support plate 11 and the second horizontal transverse pull plate 13 are driven to move, and the first horizontal transverse pull plate 9 drives the vertical transverse pull plate 3 to move, so as to realize the transverse seam pulling operation of the two shear walls, and when the seam pulling is completed, a hole can be drilled underground, so that the embedded connecting screw 15 can be inserted into the first horizontal transverse pull plate 9 and verified into the hole, and then the positioning nut 14 can be locked on the embedded connecting screw 15, so that the positioning nut 14 can position and lock the position of the first horizontal transverse pull plate 9 to ensure the firmness of the first horizontal transverse pull plate 9 after tightening.
[0041] Finally, a few points should be explained: First, in the description of this application, it should be noted that, unless otherwise specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, which may refer to mechanical connection or electrical connection, or internal communication between two components, or direct connection. "upper", "lower", "left", "right", etc. are only used to indicate relative positional relationships. When the absolute position of the object being described changes, the relative positional relationship may change;
[0042] Secondly: In the drawings of the embodiments disclosed in the present invention, only the structures related to the embodiments disclosed in the present invention are involved, and other structures can refer to the general design. In the absence of conflict, the same embodiment and different embodiments of the present invention can be combined with each other;
[0043] Finally: The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A construction method for node treatment at the joint between the structural wall and the shear wall under the window, characterized in that: The specific construction steps are as follows; Step 1: After the upper floor slab concrete pouring is completed, install the horizontal structural joint assembly between the floor slab and the structural wall under the window at the floor slab or beam position before the concrete begins to set, and after the installation is completed, use 22# tie wire to fix it firmly to prevent movement; Step 2: When carrying out on-site wall construction, first tie the shear wall reinforcement and the structural wall reinforcement under the window respectively. After the reinforcement is tied, a vertical structural seam assembly is set between the shear wall and the structural wall, and anti-cracking reinforcement is set between the structural wall and the shear wall. The reinforcement also has the function of fixing the vertical structural seam assembly. The anti-cracking reinforcement passes through the vertical structural seam assembly and is tied and overlapped with the wall reinforcements on both sides. The two sides of the vertical structural seam assembly are firmly fixed with wall reinforcements, and then the mobile phone takes a photo and uploads it to the background data computer. The quality supervisor immediately rushes to the site to check the drawings and installation positions. Step 3: Install the aluminum alloy formwork of the wall as a whole and reinforce it firmly. Before installing the formwork at the joint of the shear wall and the structural wall, confirm the installation position and fixation of the horizontal structural seam assembly again, and ensure that the water stop joints on both sides of the seam plate are placed in the shear wall and the structural wall respectively; Step 4: The concrete on both sides of the structural seam plate is poured symmetrically in layers and vibrated to make it dense. The pouring height of the first layer should not exceed 500mm, and the pouring height each time thereafter should not exceed 1.0m. When vibrating the second layer of concrete, the vibrating rod should extend 50mm into the upper layer of concrete. In order to ensure a good combination of the newly poured concrete and the already poured concrete, a layer of 50-100mm thick mortar with the same composition as the original concrete is poured on the bottom layer before pouring the concrete. During pouring, a special person is arranged to check the position of the seam plate to prevent displacement caused by concrete impact affecting the pouring quality. When the concrete is poured to the predetermined elevation of the upper end of the wall, the surface is smoothed. The vertical structural seam assembly includes two limit support templates (1). Two vertical cross-bracing plates (3) are installed between the limiting support templates (1), and a plurality of groups of embedded screws (4) are arranged equidistantly from top to bottom inside the vertical cross-bracing plates (3); a cross beam support (2) is provided at the top of the limiting support template (1); a locking nut (5) is threadedly connected to the outside of the embedded screws (4) and located at a position on one side of the vertical cross-bracing plates (3); two embedded positioning blocks (6) are embedded at the top of each vertical cross-bracing plate (3); a fixing bolt (7) is embedded at the top of the embedded positioning block (6) and near the position of the vertical cross-bracing plates (3); and a first locking bolt (8) is embedded at the top of the embedded positioning block (6) and near the position of the cross beam support (2); The vertical transverse pull plate (3) is detachably connected to the embedded positioning support block (6) via a fixing bolt (7), the crossbeam support (2) is detachably connected to the embedded positioning support block (6) via a first locking bolt (8), the horizontal structural seam assembly comprises a first horizontal transverse pull plate (9), an embedded pull plate (10) is fixed to the top of the first horizontal transverse pull plate (9), and an alignment locking support plate (11) is provided inside the embedded pull plate (10), a plurality of second locking bolts (12) are embedded and penetrated on one side of the alignment locking support plate (11), and a second horizontal transverse pull plate (13) is welded to the bottom end of the alignment locking support plate (11), and the alignment locking support plates (11) and the alignment locking support plates (11) are detachably connected via a plurality of second locking bolts (12); A pre-buried connection screw (15) is installed inside the first horizontal cross-pull plate (9) and at a position on the other side of the embedded pull plate (10), and a positioning nut (14) is provided on the outer wall of the pre-buried connection screw (15) and at a top position of the first horizontal cross-pull plate (9), and the positioning nut (14) is threadedly connected to the pre-buried connection screw (15).
2. A construction method for processing nodes at the joints between the structural wall under the window and the shear wall according to claim 1, characterized in that: In the step 1, a tension measuring instrument is used to pull the fixed 22# binding wire with a pressure of 10-20N, and the pulling times are not less than three times.
3. The construction method for processing the node at the joint between the structural wall under the window and the shear wall according to claim 1 is characterized in that: The anti-cracking steel bars in step 2 are of the type HRB335, HRB400, and HRB400. The diameter of the anti-cracking steel bars is five centimeters and they are fixed by cross weaving.
4. A construction method for processing nodes at the joints between the structural wall under the window and the shear wall according to claim 1, characterized in that: In the step three, the wall aluminum alloy formwork is installed as a whole using two construction workers who are respectively located above and to the side of the wall aluminum alloy formwork. At the same time, an air gun is needed to blow along the edge to check whether there is any air leakage in the edge gap. The number of back and forth checks must be greater than five times.
5. The construction method for treating the joint between the structural wall under the window and the shear wall according to claim 1 is characterized in that: The pouring temperature of the first layer in step 4 shall not exceed 40°C, and it is necessary to wait for 10 minutes after the pouring is completed. After 10 minutes, a layer of cool water with a thickness of 0.5 cm is sprayed by a sprinkler.
6. The construction method for treating the joint between the structural wall under the window and the shear wall according to claim 1 is characterized by: In the step 4, the vibrating rod is reciprocated along the concrete for 3-5 times. After the vibration is completed, the vibrating rod needs to be moved vertically upwards when moving upwards. The upward movement is divided into two times, and the dwell time for each time is 5 minutes.