Railway bridge support pad stone integral prefabrication auxiliary tool and operation method thereof

Through the use of the integrated prefabricated auxiliary tools for supporting railings on the railway bridge, the problem of two steps in the installation of railings in the existing technology is solved, and the rapid and accurate installation of railings is achieved, and the construction efficiency is improved.

CN115506257BActive Publication Date: 2025-04-29SHANGHAI CIVIL ENG GRP CO LTD OF CREC +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211234640.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-10
Publication Date
2025-04-29
Estimated Expiration
2042-10-10

AI Technical Summary

Technical Problem

The installation of existing railway bridge support pad stone requires two construction steps, and the fine-tuning positioning time is long, which reduces construction efficiency.

Method used

Provides integrated prefabricated auxiliary tools for supporting stone pads on railway bridges, including stone pads on steel molds, hoisting mechanisms, pier steel molds, auxiliary tooling, transverse positioning rods and transverse positioning plates. Through the cooperation of these components, the axial and transverse limits of stone pads are achieved, simplifying the installation process.

Benefits of technology

With this auxiliary tool, the stone pad can be installed in one step, saving a lot of time, improving construction efficiency, and ensuring the accurate position of the stone pad through the fine-tuning monitoring of the total station.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115506257B_ABST
    Figure CN115506257B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of railway bridge supporting pad stones, and specifically to an integral prefabrication auxiliary tool for railway bridge supporting pad stones and an operation method thereof, wherein the integral prefabrication auxiliary tool for railway bridge supporting pad stones comprises: a pad stone steel mold, a hoisting mechanism, a bridge pier steel mold, an auxiliary tooling, a transverse positioning rod and a transverse positioning plate; the beneficial effects are: a longitudinal limiting block is supported by a limiting spring to limit the longitudinal position of the transverse positioning rod, the transverse positioning plate cooperates with the transverse positioning rod to limit the pad stone steel mold and the pad stone transversely, two groups of auxiliary tooling limit the axial position of the pad stone steel mold, thereby placing the pad stone at a preset position, completing the installation of the pad stone, and driving the transverse positioning rod and the auxiliary tooling to cooperate through the hoisting mechanism to achieve integrated hoisting fine-tuning, saving a lot of time, and improving the construction efficiency of the pad stone, and fine-tuning monitoring is performed through a movable frame to assist in adjusting the pad stone into place.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of railway bridge support pad stones, in particular to an integral prefabrication auxiliary tool for railway bridge support pad stones and an operating method thereof. Background Art

[0002] The function of the pad stone on the bridge is to ensure a close fit with the bearing. The supporting pad stones of railway bridges are now mostly prefabricated, which can improve construction efficiency. The pad stones are centrally prefabricated in the factory, flipped using special tooling, and the positioning tooling is connected to the pier body formwork to form a whole. It is then hoisted to the top of the pier for installation using a hoisting device, and then fine-tuned and positioned using a jack.

[0003] The existing cushion stones are first installed on the top of the pier by a lifting device, and then the position of the cushion stones is fine-tuned by multiple sets of jacks. This requires two construction steps and takes a lot of time to fine-tune the positioning, reducing construction efficiency. Summary of the invention

[0004] The object of the present invention is to provide an integral prefabrication auxiliary tool for supporting pad stones of railway bridges and an operation method thereof, so as to solve the problem that the installation of pad stones requires two construction steps.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] The integral prefabrication auxiliary tool for supporting shims of railway bridges comprises:

[0007] The steel formwork for the pad stone is placed outside the pad stone and located above the bridge pier;

[0008] The hoisting mechanism is arranged on the top of the pad stone steel formwork;

[0009] The pier steel formwork is set on the outside of the pier;

[0010] The auxiliary tooling is fixed on the top surface of the pier steel mold and cooperates with the pad stone steel mold to limit the axial position of the pad stone;

[0011] Transverse positioning rods are fixed on both sides of the steel formwork of the pad stone; and

[0012] The transverse positioning plate is arranged on the surface of the auxiliary tooling and cooperates with the transverse positioning rod to limit the transverse position of the cushion stone.

[0013] Preferably, the auxiliary tooling is hollow and is provided in multiple groups, and one group of pad stones cooperates with two groups of auxiliary tooling, the spacing between the two groups of auxiliary tooling is equal to the length of the pad stone steel formwork, a third reinforcing rib is provided inside the auxiliary tooling for support, and a slot is provided on the surface of the auxiliary tooling, which is connected to the top surface of the pier steel formwork through the slot, and the angle between the transverse positioning rod and the pad stone steel formwork is ninety degrees.

[0014] Preferably, an axial inclined surface is provided at the top of the auxiliary tooling, and the axial inclined surface faces the center of the pier. Fixing grooves are formed on the surfaces of the auxiliary tooling and the axial inclined surface, and the fixing grooves penetrate through the auxiliary tooling and the axial inclined surface. The cross-section of the lower end of the fixing groove is in a "C" shape, and the cross-section of the upper end is in an isosceles trapezoid shape. Two groups of fixing grooves are provided on the surface of a set of auxiliary tooling.

[0015] Preferably, the transverse positioning plate is fixed at the lower end of the fixing groove. A transverse inclined plate is provided at the upper end of the fixing groove, and the transverse inclined plate is connected to the transverse positioning plate. The lengths of the transverse inclined plate and the transverse positioning plate are greater than the thickness of the auxiliary tooling, and they are located on the surface of the auxiliary tooling away from the pier steel form. The included angle between the transverse inclined plate and the transverse positioning plate is an obtuse angle. The transverse positioning plate and the transverse inclined plate are both perpendicular to the auxiliary tooling. Ball bearings are provided on the surfaces of the axial inclined surface and the transverse inclined plate, and the ball bearings are arranged in a matrix.

[0016] Preferably, a second reinforcing rib is provided between the transverse positioning plate and the transverse inclined plate. A limiting groove is formed on the surface of the second reinforcing rib. The cross-section of the limiting groove is in a "C" shape. A limiting spring and a longitudinal limiting block are arranged inside the limiting groove. One end of the limiting spring is connected to the limiting groove, and the other end is connected to the longitudinal limiting block. One end of the longitudinal limiting block connected to the limiting spring is inserted into the limiting groove, and the other end passes through both sides of the transverse positioning plate. A longitudinal limiting inclined surface is formed on the surface of the longitudinal limiting block, and the longitudinal limiting inclined surface faces upward. The transverse length of the longitudinal limiting inclined surface is greater than the length of the longitudinal limiting block extending out of the limiting groove. The distance between the bottom surface of the longitudinal limiting block and the transverse positioning plate is equal to the height of the transverse positioning rod.

[0017] Preferably, fixing blocks are fixed on the side surface of the auxiliary tooling, and there are two groups of fixing blocks. An activity block is arranged inside the two groups of fixing blocks. A rotating shaft is arranged inside the activity block, and the activity block is rotationally connected to the two groups of fixing blocks through the rotating shaft. An activity frame is fixed on the side surface of the activity block, and a total station is arranged inside the activity frame.

[0018] Preferably, a limiting post is provided on the top surface of the fixing block. The limiting post is in a square column shape. A rotating limiting groove matched with the limiting post is formed on the side surface of the rotating shaft close to the limiting post. The limiting post passes through the fixing block and is matched with the rotating limiting groove to limit the rotation of the activity block. A pull rod is provided on the top surface of the limiting post, and the pull rod is in a "T" shape.

[0019] Preferably, a stretching spring is sleeved outside the lower end of the pull rod. One end of the stretching spring is connected to the pull rod, and the other end is connected to the fixing block. A rotating ring is sleeved outside the top end of the pull rod, and the thickness of the rotating ring is greater than the thickness of the top end of the pull rod.

[0020] Preferably, a rotating groove is provided on the side surface of the pull rod, a rotating slider is provided on the inner wall of the rotating ring, and the rotating slider is arranged inside the rotating groove. The cross-sections of the rotating slider and the rotating groove are both "T"-shaped structures, and a limiting rod is connected to the bottom end surface of the rotating ring. A rotating plug-in groove is provided on the top surface of the fixed block to cooperate with the limiting rod, and the depth of the rotating plug-in groove is greater than the depth of the rotating limit groove.

[0021] The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool comprises the following steps:

[0022] Prefabrication: The pad stone is prefabricated through the pad stone steel mold, and the transverse positioning rod is fixed on the side surface of the pad stone steel mold;

[0023] Install the auxiliary tooling: clamp one side of the auxiliary tooling on the top surface of the pier steel formwork through the clamping slot, and then fix the auxiliary tooling on the surface of the pier steel formwork;

[0024] Debugging: The pull rod is driven upward by the rotating ring, so that the limit column and the limit rod are moved upward until the limit column is disengaged from the rotating limit slot and the limit rod is disengaged from the rotating plug-in slot, and then the rotating ring is rotated 90 degrees, and the rotating slide and the rotating slider are used to horizontally limit the rotating ring, and then the limit rod is pressed against the fixed block to cancel the rotation limit of the movable block, and then the total station is driven to rotate to the top of the bridge pier through the movable frame to measure the verticality of the auxiliary tooling and the distance between the two sets of auxiliary tooling, and then the positions of the two sets of auxiliary tooling are adjusted;

[0025] Installing the pad stone: lift the pad stone steel mold and the pad stone through the lifting mechanism until the pad stone is located above the pier and the transverse positioning rod is located above the auxiliary tooling. Then move the pad stone and the pad stone steel mold toward the pier steel mold. The pad stone steel mold first contacts the axial inclined surface and gradually enters between the two sets of auxiliary tooling through the cooperation of the axial inclined surface and the ball. Then the transverse positioning rod contacts the transverse inclined plate and cooperates with the ball through the transverse inclined plate to facilitate the movement of the transverse positioning rod toward the transverse positioning plate. When the transverse positioning rod contacts the longitudinal limiting inclined surface, the longitudinal limiting block is pressed into the limiting groove until the transverse positioning rod contacts the bottom end surface of the transverse positioning plate. The limiting spring holds the longitudinal limiting block to limit the transverse positioning rod longitudinally. The transverse positioning plate cooperates with the transverse positioning rod to limit the pad stone steel mold and the pad stone transversely. The two sets of auxiliary tooling limit the pad stone steel mold axially, thereby placing the pad stone in the preset position to complete the installation of the pad stone.

[0026] Dismantling: After removing the auxiliary tooling and casting the pad stone and the bridge pier as one, the pad stone steel formwork and the bridge pier steel formwork will be dismantled in turn.

[0027] Compared with the prior art, the present invention has the following beneficial effects:

[0028] The present invention drives the pull rod upward by the rotating ring, thereby causing the limit column and the limit rod to move upward until the limit column disengages from the rotating limit groove and the limit rod disengages from the rotating plug-in groove, then the rotating ring is rotated ninety degrees, and the rotating slide groove and the rotating slider cooperate to limit the rotating ring horizontally, and then the limit rod abuts against the fixed block, thereby canceling the rotation limit of the movable block, and then the total station is driven to rotate above the pier through the movable frame, so as to measure the verticality of the auxiliary tooling and the spacing between the two groups of auxiliary tooling, and then the positions of the two groups of auxiliary tooling are adjusted, and the pad stone steel mold and the pad stone are lifted by the lifting mechanism until the pad stone is located above the pier and the transverse positioning rod is located above the auxiliary tooling, and then the pad stone and the pad stone steel mold are moved toward the pier steel mold, and the pad stone steel mold first contacts the axial inclined surface, and is gradually moved by the axial inclined surface and the ball bearing cooperate with each other. It gradually enters between the two sets of auxiliary tooling, and then the transverse positioning rod contacts the transverse inclined plate, and the transverse inclined plate cooperates with the ball bearing to facilitate the transverse positioning rod to move toward the transverse positioning plate. When the transverse positioning rod contacts the longitudinal limit inclined surface, the longitudinal limit block is pressed into the limit groove until the transverse positioning rod contacts the bottom end surface of the transverse positioning plate. The limit spring holds the longitudinal limit block to limit the longitudinal position of the transverse positioning rod. The transverse positioning plate cooperates with the transverse positioning rod to limit the pad stone steel mold and the pad stone laterally. The two sets of auxiliary tooling limit the axial position of the pad stone steel mold, so that the pad stone is placed in the preset position to complete the installation of the pad stone. The transverse positioning rod and the auxiliary tooling are driven by the lifting mechanism to cooperate to achieve integrated lifting and fine-tuning, which saves a lot of time and improves the construction efficiency of the pad stone. The movable frame is used for fine-tuning and monitoring to assist in adjusting the pad stone into place. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a schematic diagram of the main stereoscopic structure of the present invention;

[0030] Figure 2 This is a schematic diagram of the main three-dimensional structure of the auxiliary tooling of the present invention;

[0031] Figure 3 for Figure 2 A magnified schematic diagram of the structure at position A;

[0032] Figure 4 This is a schematic diagram of the main three-dimensional structure of the auxiliary tooling of the present invention;

[0033] Figure 5 It is a schematic diagram of a partially cutaway three-dimensional structure of the auxiliary tooling of the present invention;

[0034] Figure 6 It is a schematic diagram of a partially cutaway three-dimensional structure of the auxiliary tooling of the present invention in a side view;

[0035] Figure 7 for Figure 6 A magnified schematic diagram of the structure at B.

[0036] In the figure: pier 1, pier steel mold 2, pad stone 3, pad stone steel mold 4, lifting mechanism 5, transverse positioning rod 6, first reinforcing rib 7, auxiliary tooling 8, second reinforcing rib 9, total station 10, movable frame 11, movable block 12, third reinforcing rib 13, axial inclined surface 14, transverse positioning plate 15, transverse inclined plate 16, ball 17, longitudinal limit block 18, longitudinal limit inclined surface 19, fixed block 20, pull rod 21, rotating ring 22, limit rod 23, stretching spring 24, limit column 25, rotating plug-in slot 26, card slot 27, limit slot 28, limit spring 29, rotating shaft 30, rotating limit slot 31, rotating slide slot 32, rotating slider 33. DETAILED DESCRIPTION

[0037] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0038] In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "one", "first", "second", "third", "fourth", "fifth", "sixth" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0039] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0040] For the purposes of simplicity and illustration, the principles of the embodiments are mainly described by reference to examples. In the following description, many specific details are set forth to provide a thorough understanding of the embodiments. However, it is apparent that, to those of ordinary skill in the art, these embodiments may not be limited to these specific details in practice. In some instances, well-known methods and structures are not described in detail so as not to unnecessarily obscure these embodiments. Additionally, all embodiments may be used in combination with each other.

[0041] Please refer to Figures 1 to 7 , the present invention provides a technical solution:

[0042] An auxiliary tool for integral prefabrication of a bearing padstone of a railway bridge. The auxiliary tool for integral prefabrication of a bearing padstone of a railway bridge includes: a padstone steel mold 4 sleeved outside the padstone 3 and located above the pier 1; a hoisting mechanism 5 arranged at the top end of the padstone steel mold 4; a pier steel mold 2 sleeved outside the pier 1; an auxiliary tooling 8 fixed on the top surface of the pier steel mold 2 and cooperating with the padstone steel mold 4 to axially limit the padstone 3; a lateral positioning rod 6 fixed on both side surfaces of the padstone steel mold 4; and a lateral positioning plate 15 arranged on the surface of the auxiliary tooling 8 and cooperating with the lateral positioning rod 6 to laterally limit the padstone 3. The auxiliary tooling 8 is in a hollow shape and is provided with multiple groups. One group of padstones 3 cooperates with two groups of auxiliary toolings 8. The distance between the two groups of auxiliary toolings 8 is equal to the length of the padstone steel mold 4. The inside of the auxiliary tooling 8 is provided with a third reinforcing rib 13 for support, and a clamping groove 27 is formed on the surface of the auxiliary tooling 8. The auxiliary tooling 8 is clamped on the top surface of the pier steel mold 2 through the clamping groove 27. The included angle between the lateral positioning rod 6 and the padstone steel mold 4 is 90 degrees. An axial inclined surface 14 is arranged at the top end of the auxiliary tooling 8, and the axial inclined surface 14 faces the center of the pier 1. Fixing grooves are formed on the surfaces of the auxiliary tooling 8 and the axial inclined surface 14, and the fixing grooves penetrate through the auxiliary tooling 8 and the axial inclined surface 14. The cross-section of the lower end of the fixing groove is in a "C" shape structure, and the cross-section of the upper end is in an isosceles trapezoid shape structure. Two groups of fixing grooves are arranged on the surface of one group of auxiliary toolings 8.

[0043] The present invention can be further arranged such that the lateral positioning plate 15 is fixed at the lower end of the fixing groove. A lateral inclined plate 16 is arranged at the upper end of the fixing groove, and the lateral inclined plate 16 is connected to the lateral positioning plate 15. The lengths of the lateral inclined plate 16 and the lateral positioning plate 15 are greater than the thickness of the auxiliary tooling 8 and are located on the surface of the auxiliary tooling 8 away from the pier steel mold 2. The included angle between the lateral inclined plate 16 and the lateral positioning plate 15 is an obtuse angle. Both the lateral positioning plate 15 and the lateral inclined plate 16 are perpendicular to the auxiliary tooling 8. Ball bearings 17 are arranged on the surfaces of the axial inclined surface 14 and the lateral inclined plate 16, and the ball bearings 17 are arranged in a matrix.

[0044] The present invention can be further configured such that a second reinforcing rib 9 is provided between the lateral positioning plate 15 and the lateral inclined plate 16, and a limiting groove 28 is formed on the surface of the second reinforcing rib 9. The cross-section of the limiting groove 28 is in a "C" shape structure, and a limiting spring 29 and a longitudinal limiting block 18 are arranged inside the limiting groove 28. One end of the limiting spring 29 is connected to the limiting groove 28, and the other end is connected to the longitudinal limiting block 18. And one end of the longitudinal limiting block 18 connected to the limiting spring 29 is inserted inside the limiting groove 28, and the other end passes through both sides of the lateral positioning plate 15. And a longitudinal limiting inclined surface 19 is formed on the surface of the longitudinal limiting block 18, the longitudinal limiting inclined surface 19 faces upward, and the lateral length of the longitudinal limiting inclined surface 19 is greater than the length of the longitudinal limiting block 18 extending out of the limiting groove 28, and the distance between the bottom surface of the longitudinal limiting block 18 and the lateral positioning plate 15 is equal to the height of the lateral positioning rod 6.

[0045] The present invention can be further configured such that a fixing block 20 is fixed on the side surface of the auxiliary tooling 8, and there are two groups of fixing blocks 20. An active block 12 is arranged inside the two groups of fixing blocks 20. A rotating shaft 30 is arranged inside the active block 12, and is rotationally connected to the two groups of fixing blocks 20 through the rotating shaft 30. And an active frame 11 is fixed on the side surface of the active block 12, and a total station 10 is arranged inside the active frame 11; a limiting column 25 is arranged on the top surface of the fixing block 20. The limiting column 25 is in a square column structure. A rotating limiting groove 31 matched with the limiting column 25 is formed on the side surface of the rotating shaft 30 close to the limiting column 25. And the limiting column 25 passes through the fixing block 20 and is matched with the rotating limiting groove 31 to limit the rotation of the active block 12. And a pull rod 21 is arranged on the top surface of the limiting column 25. The pull rod 21 is in a "T" shape structure.

[0046] The present invention can be further configured such that a stretching spring 24 is sleeved outside the lower end of the pull rod 21. One end of the stretching spring 24 is connected to the pull rod 21, and the other end is connected to the fixing block 20. And a rotating ring 22 is sleeved outside the top end of the pull rod 21. The thickness of the rotating ring 22 is greater than the thickness of the top end of the pull rod 21; a rotating sliding groove 32 is formed on the side surface of the pull rod 21. A rotating sliding block 33 is arranged on the inner wall of the rotating ring 22, and the rotating sliding block 33 is arranged inside the rotating sliding groove 32. The cross-sections of the rotating sliding block 33 and the rotating sliding groove 32 are both in a "T" shape structure. And a limiting rod 23 is connected to the bottom surface of the rotating ring 22. A rotating insertion groove 26 matched with the limiting rod 23 is formed on the top surface of the fixing block 20. And the depth of the rotating insertion groove 26 is greater than the depth of the rotating limiting groove 31.

[0047] The operation method of the integral prefabrication auxiliary tool for the bearing cushion stone of the railway bridge includes the following steps:

[0048] Prefabrication: The cushion stone 3 is prefabricated through the cushion stone steel mold 4, and the lateral positioning rod 6 is fixed on the side surface of the cushion stone steel mold 4;

[0049] Install the auxiliary tooling 8: clamp one side of the auxiliary tooling 8 to the top surface of the pier steel mold 2 through the clamping slot 27, and then fix the auxiliary tooling 8 to the surface of the pier steel mold 2;

[0050] Debugging: The pull rod 21 is driven to move upward by the rotating ring 22, so that the limit column 25 and the limit rod 23 are moved upward until the limit column 25 is disengaged from the rotating limit groove 31 and the limit rod 23 is disengaged from the rotating plug-in groove 26, and then the rotating ring 22 is rotated ninety degrees, and the rotating slide groove 32 and the rotating slider 33 are used to horizontally limit the rotating ring 22, and then the limit rod 23 is pressed against the fixed block 20, so as to cancel the rotation limit of the movable block 12, and then the total station 10 is driven to rotate to the top of the pier 1 through the movable frame 11, so as to measure the verticality of the auxiliary tooling 8 and the distance between the two sets of auxiliary tooling 8, and then the positions of the two sets of auxiliary tooling 8 are adjusted;

[0051] Install the pad stone 3: lift the pad stone steel mold 4 and the pad stone 3 through the lifting mechanism 5 until the pad stone 3 is located above the pier 1 and the transverse positioning rod 6 is located above the auxiliary tooling 8, then move the pad stone 3 and the pad stone steel mold 4 toward the pier steel mold 2, the pad stone steel mold 4 first contacts the axial inclined surface 14, and gradually enters between the two sets of auxiliary tooling 8 through the cooperation of the axial inclined surface 14 and the ball 17, then the transverse positioning rod 6 contacts the transverse inclined plate 16, and through the cooperation of the transverse inclined plate 16 and the ball 17, it is convenient for the transverse positioning rod 6 to move toward the transverse The positioning plate 15 moves, and when the transverse positioning rod 6 contacts the longitudinal limiting inclined surface 19, the longitudinal limiting block 18 is pressed into the limiting groove 28 until the transverse positioning rod 6 contacts the bottom surface of the transverse positioning plate 15, and the limiting spring 29 supports the longitudinal limiting block 18 to limit the transverse positioning rod 6 longitudinally, and the transverse positioning plate 15 cooperates with the transverse positioning rod 6 to limit the pad stone steel mold 4 and the pad stone 3 laterally, and the two sets of auxiliary tooling 8 limit the pad stone steel mold 4 axially, so that the pad stone 3 is placed in the preset position, and the installation of the pad stone 3 is completed;

[0052] Dismantling: After the auxiliary tooling 8 is dismantled and the cushion stone 3 and the bridge pier 1 are cast into one piece, the cushion stone steel formwork 4 and the bridge pier steel formwork 2 are dismantled in sequence.

[0053] The pull rod 21 is driven upward by the rotating ring 22, so that the limit column 25 and the limit rod 23 are moved upward until the limit column 25 is disengaged from the rotating limit groove 31 and the limit rod 23 is disengaged from the rotating plug-in groove 26, and then the rotating ring 22 is rotated ninety degrees, and the rotating slide groove 32 and the rotating slider 33 are cooperated to horizontally limit the rotating ring 22, and then the limit rod 23 is pressed against the fixed block 20, thereby canceling the rotation limit of the movable block 12, and then the total station 10 is driven to rotate to the top of the pier 1 through the movable frame 11, so as to measure the verticality of the auxiliary tooling 8 and the spacing between the two groups of auxiliary tooling 8, and then the positions of the two groups of auxiliary tooling 8 are adjusted, and the cushion stone steel mold 4 and the cushion stone 3 are lifted by the lifting mechanism 5 until the cushion stone 3 is located above the pier 1 and the transverse positioning rod 6 is located above the auxiliary tooling 8, and then the cushion stone 3 and the cushion stone steel mold 4 are moved toward the pier steel mold 2, and the cushion stone steel mold 4 first contacts the axial inclined surface 14, and through the axial inclined surface 14 and the ball 17 cooperates and gradually enters between the two groups of auxiliary tooling 8, and then the transverse positioning rod 6 contacts the transverse inclined plate 16, and the transverse inclined plate 16 cooperates with the ball 17 to facilitate the transverse positioning rod 6 to move toward the transverse positioning plate 15. When the transverse positioning rod 6 contacts the longitudinal limiting inclined surface 19, the longitudinal limiting block 18 is pressed into the limiting groove 28 until the transverse positioning rod 6 contacts the bottom end surface of the transverse positioning plate 15, and the limiting spring 29 supports the longitudinal limiting block 18 to limit the transverse positioning rod 6 longitudinally. The transverse positioning plate 15 and the transverse positioning rod 6 cooperate to limit the pad stone steel mold 4 and the pad stone 3 laterally. The two groups of auxiliary tooling 8 limit the pad stone steel mold 4 axially, so that the pad stone 3 is placed in the preset position to complete the installation of the pad stone 3. The transverse positioning rod 6 and the auxiliary tooling 8 are driven by the lifting mechanism 5 to cooperate, so as to achieve integrated lifting and fine-tuning, which saves a lot of time and improves the construction efficiency of the pad stone 3. The movable frame 11 is used for fine-tuning and monitoring to assist in adjusting the pad stone into place.

[0054] Although the above describes the illustrative specific implementation methods of the present application so that technicians in this technical field can understand the present application, the present application is not limited to the scope of the specific implementation methods. For ordinary technicians in this technical field, as long as various changes are within the spirit and scope of the present application defined and determined by the attached claims, all application creations using the concept of the present application are protected.

Claims

1. An operating method of an integral prefabrication auxiliary tool for supporting shims of railway bridges, the integral prefabrication auxiliary tool for supporting shims of railway bridges comprising: A cushion stone steel mold (4) is sleeved on the outside of the cushion stone (3) and is located above the bridge pier (1); A hoisting mechanism (5) is arranged on the top of the cushion stone steel mold (4); A bridge pier steel mold (2) is sleeved on the outside of the bridge pier (1); The auxiliary tooling (8) is fixed on the top surface of the pier steel mold (2) and cooperates with the cushion stone steel mold (4) to limit the axial position of the cushion stone (3); Transverse positioning rods (6) are fixed to the surfaces of both sides of the cushion stone steel mold (4); and The transverse positioning plate (15) is arranged on the surface of the auxiliary tool (8) and cooperates with the transverse positioning rod (6) to limit the shim (3) laterally; the method for operating the railway bridge support shim integral prefabrication auxiliary tool comprises the following steps: Prefabrication: prefabricate the pad stone (3) by means of a pad stone steel mold (4), and fix a transverse positioning rod (6) on the side surface of the pad stone steel mold (4); Installing the auxiliary tooling (8): clamping one side of the auxiliary tooling (8) onto the top surface of the pier steel mold (2) through the clamping slot (27), and then fixing the auxiliary tooling (8) onto the surface of the pier steel mold (2); Debugging: The pull rod (21) is driven to move upward by the rotating ring (22), thereby causing the limit column (25) and the limit rod (23) to move upward until the limit column (25) is disengaged from the rotating limit groove (31) and the limit rod (23) is disengaged from the rotating plug-in groove (26), and then the rotating ring (22) is rotated ninety degrees, and the rotating slide groove (32) and the rotating slider (33) are used to horizontally limit the rotating ring (22), and then the limit rod (23) is pressed against the fixed block (20), thereby canceling the rotation limit of the movable block (12), and then the total station (10) is driven to rotate to the top of the bridge pier (1) by the movable frame (11), so as to measure the verticality of the auxiliary tooling (8) and the distance between the two sets of auxiliary tooling (8), and then the positions of the two sets of auxiliary tooling (8) are adjusted; Installation of the cushion stone (3): The cushion stone steel mold (4) and the cushion stone (3) are lifted by the hoisting mechanism (5) until the cushion stone (3) is above the pier (1) and the transverse positioning rod (6) is above the auxiliary tooling (8). Then, the cushion stone (3) and the cushion stone steel mold (4) are moved towards the pier steel mold (2). The cushion stone steel mold (4) first contacts the axial inclined surface (14) and gradually enters between the two sets of auxiliary tooling (8) through the cooperation of the axial inclined surface (14) and the ball (17). Then, the transverse positioning rod (6) contacts the transverse inclined plate (16) and moves towards the transverse positioning plate (15) through the cooperation of the transverse inclined plate (16) and the ball (17). When the transverse positioning rod (6) contacts the longitudinal limiting inclined surface (19), the longitudinal limiting block (18) is pressed into the limiting groove (28) until the transverse positioning rod (6) contacts the bottom surface of the transverse positioning plate (15). The limiting spring (29) holds the longitudinal limiting block (18) to longitudinally limit the transverse positioning rod (6). The transverse positioning plate (15) and the transverse positioning rod (6) cooperate to laterally limit the cushion stone steel mold (4) and the cushion stone (3), and the two sets of auxiliary tooling (8) axially limit the cushion stone steel mold (4), thereby placing the cushion stone (3) at the preset position and completing the installation of the cushion stone (3). Demolition: After the auxiliary tooling (8) is removed and the cushion stone (3) and the pier (1) are cast into one body, the cushion stone steel mold (4) and the pier steel mold (2) are removed in sequence.

2. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 1 is characterized in that: The auxiliary tooling (8) is hollow and there are multiple sets. One set of cushion stone (3) cooperates with two sets of auxiliary tooling (8). The distance between the two sets of auxiliary tooling (8) is equal to the length of the cushion stone steel mold (4). The third reinforcing rib (13) is arranged inside the auxiliary tooling (8) for support. A clamping groove (27) is formed on the surface of the auxiliary tooling (8), and it is clamped on the top surface of the pier steel mold (2) through the clamping groove (27). The included angle between the transverse positioning rod (6) and the cushion stone steel mold (4) is 90 degrees.

3. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 2 is characterized in that: The top of the auxiliary tooling (8) is provided with an axial inclined surface (14), and the axial inclined surface (14) faces the center of the pier (1). Fixing grooves are formed on the surfaces of the auxiliary tooling (8) and the axial inclined surface (14), and the fixing grooves penetrate through the auxiliary tooling (8) and the axial inclined surface (14). The cross-section of the lower end of the fixing groove is in a "匚" - shaped structure, and the cross-section of the upper end is in an isosceles trapezoid structure. Two sets of fixing grooves are arranged on the surface of one set of auxiliary tooling (8).

4. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 3 is characterized in that: The transverse positioning plate (15) is fixed at the lower end of the fixing groove. A transverse inclined plate (16) is arranged at the upper end of the fixing groove, and the transverse inclined plate (16) is connected to the transverse positioning plate (15). The lengths of the transverse inclined plate (16) and the transverse positioning plate (15) are greater than the thickness of the auxiliary tooling (8) and are located on the surface of the auxiliary tooling (8) away from the pier steel mold (2). The included angle between the transverse inclined plate (16) and the transverse positioning plate (15) is an obtuse angle. The transverse positioning plate (15) and the transverse inclined plate (16) are both perpendicular to the auxiliary tooling (8). Ball bearings (17) are arranged on the surfaces of the axial inclined surface (14) and the transverse inclined plate (16), and the ball bearings (17) are arranged in a matrix.

5. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 4 is characterized in that: A second reinforcing rib (9) is arranged between the transverse positioning plate (15) and the transverse inclined plate (16), and a limiting groove (28) is formed on the surface of the second reinforcing rib (9). The cross-section of the limiting groove (28) is in a "C" shape. A limiting spring (29) and a longitudinal limiting block (18) are arranged inside the limiting groove (28). One end of the limiting spring (29) is connected to the limiting groove (28), and the other end is connected to the longitudinal limiting block (18). One end of the longitudinal limiting block (18) connected to the limiting spring (29) is inserted into the limiting groove (28), and the other end passes through both sides of the transverse positioning plate (15). A longitudinal limiting inclined surface (19) is formed on the surface of the longitudinal limiting block (18), and the longitudinal limiting inclined surface (19) faces upward. The transverse length of the longitudinal limiting inclined surface (19) is greater than the length of the longitudinal limiting block (18) extending out of the limiting groove (28). The distance between the bottom surface of the longitudinal limiting block (18) and the transverse positioning plate (15) is equal to the height of the transverse positioning rod (6).

6. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 5 is characterized in that: A fixing block (20) is fixed on the side surface of the auxiliary tooling (8), and there are two groups of fixing blocks (20). An active block (12) is arranged inside the two groups of fixing blocks (20). A rotating shaft (30) is arranged inside the active block (12), and the active block (12) is rotationally connected to the two groups of fixing blocks (20) through the rotating shaft (30). An active frame (11) is fixed on the side surface of the active block (12), and a total station (10) is arranged inside the active frame (11).

7. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 6 is characterized in that: A limiting column (25) is arranged on the top surface of the fixing block (20). The limiting column (25) is in a square column shape. A rotating limiting groove (31) matched with the limiting column (25) is formed on the side surface of the rotating shaft (30) close to the limiting column (25). The limiting column (25) passes through the fixing block (20) and cooperates with the rotating limiting groove (31) to limit the rotation of the active block (12). A pull rod (21) is arranged on the top surface of the limiting column (25), and the pull rod (21) is in a "T" shape structure.

8. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 7 is characterized in that: A tension spring (24) is sleeved outside the lower end of the pull rod (21). One end of the tension spring (24) is connected to the pull rod (21), and the other end is connected to the fixing block (20). A rotating ring (22) is sleeved outside the top end of the pull rod (21), and the thickness of the rotating ring (22) is greater than the thickness of the top end of the pull rod (21).

9. The operating method of the railway bridge support pad stone integral prefabrication auxiliary tool according to claim 8 is characterized in that: A rotating sliding groove (32) is formed on the side surface of the pull rod (21). A rotating sliding block (33) is arranged on the inner wall of the rotating ring (22), and the rotating sliding block (33) is arranged inside the rotating sliding groove (32). The cross-sections of the rotating sliding block (33) and the rotating sliding groove (32) are both in a "T" shape structure. A limiting rod (23) is connected to the bottom surface of the rotating ring (22). A rotating insertion groove (26) matched with the limiting rod (23) is formed on the top surface of the fixing block (20), and the depth of the rotating insertion groove (26) is greater than the depth of the rotating limiting groove (31).

Citation Information

Patent Citations

  • Pad stone and pre-buried bolt hole forming device synchronously constructed with bridge pier caps

    CN107988919A

  • Bridge pier cap and padstone concrete synchronous construction method

    CN110485302A