A frequency conversion control system and control method for a central air-conditioning primary refrigeration pump
Through temperature sensor detection and optimized control, the instability problem of the primary freezing pump frequency control in the secondary freezing pump system is solved, reducing energy consumption and improving system stability.
Patent Information
- Application Number
- CN202211345866.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-31
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2042-10-31
AI Technical Summary
In the existing technology, the stability and reliability of the frequency conversion control of the primary freezing pump in the secondary freezing pump system are poor, resulting in large waste of energy consumption and the lack of effective control methods.
Temperature sensors are used to detect the temperatures of primary water supply pipes, secondary return water pipes and primary return water pipes. The optimal set value is calculated through the primary return water temperature optimization controller, and the primary freezing pump frequency converter is controlled to adjust the freezing pump frequency and indirectly adjust the water in the balance pipe. flow to achieve frequency conversion control of the primary freezing pump.
It improves the stability and reliability of the frequency conversion control of the primary freezing pump, reduces energy consumption, solves the instability problem of the frequency conversion control of the primary freezing pump in the secondary pump system, and achieves savings in energy consumption of the primary freezing pump.
Smart Images

Figure CN115597133B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of air-conditioning energy-saving control, and in particular to a central air-conditioning primary refrigeration pump frequency conversion control system and a control method thereof. Background Art
[0002] Saving building operation energy consumption is an important way to reduce carbon emissions. In the building operation energy consumption, the energy consumption of the central air-conditioning system accounts for more than 40%, and it is the main energy-saving target in the field of building energy conservation. At present, there are many energy-saving measures and control methods for central air-conditioning systems, such as using refrigeration station refrigeration pump variable frequency control, cooling pump variable frequency control and cooling tower variable frequency control.
[0003] Large public buildings, parks, factories, etc. usually use a two-stage chilled water pump system due to factors such as long chilled water distribution distances and large differences in branch resistance. Compared with the one-stage chilled water pump system, the two-stage chilled water pump system has more equipment, a more complex system structure, and greater difficulty in operation and control. In the two-stage chilled water pump system, the secondary chilled water pump is usually frequency-controlled, and the primary chilled water pump is operated at a fixed frequency, but this control method wastes a lot of energy. Therefore, in recent years, designers have begun to try to frequency-control the primary chilled water pump of the two-stage chilled water pump system, but there has been no good control method. The commonly used primary chilled water pump frequency control is based on the size of the bypass water flow of the balance pipe between the primary system and the secondary system, that is, directly controlling the bypass water flow of the balance pipe. However, the water flow meter usually has low measurement accuracy, is easily disturbed, and has large fluctuations in the measured value, which makes this method less stable and reliable in actual engineering applications. Summary of the invention
[0004] In order to overcome the above technical problems, the purpose of the present invention is to propose a central air-conditioning primary refrigeration pump variable frequency control system and a control method thereof, which reduces the energy consumption of the primary refrigeration pump while ensuring the stability of the variable frequency control of the primary refrigeration pump, so as to solve the instability problem of the variable frequency control of the primary refrigeration pump in the secondary pump system, thereby achieving energy saving of the primary refrigeration pump.
[0005] The present invention provides the following technical solutions:
[0006] A central air-conditioning primary refrigeration pump frequency conversion control system comprises a refrigeration main unit (1), wherein the refrigeration main unit (1) is connected to a primary water supply pipe (11), a secondary refrigeration pump (3), a secondary water supply pipe (13), a terminal air-conditioning unit (4), a return pipe, and a primary refrigeration pump (2) in sequence, wherein the primary refrigeration pump (2) is connected to the refrigeration main unit (1) to form a loop; a primary refrigeration pump frequency converter (9) is provided on the primary refrigeration pump (2) to perform frequency conversion regulation on the primary refrigeration pump (2); a bypass is provided at the front end where the primary water supply pipe (11) is connected to the secondary refrigeration pump (3), namely, a balance pipe (15), wherein the balance pipe (15) is connected to the return pipe, wherein the return pipe between the air-conditioning unit (4) and the balance pipe (15) is the secondary return pipe (14), and wherein the return pipe between the balance pipe (15) and the primary refrigeration pump (2) is the primary return pipe (12);
[0007] The primary water supply pipe (11) is provided with a first temperature sensor (6), the secondary water return pipe (14) is provided with a second temperature sensor (7), and the primary water return pipe (12) is provided with a third temperature sensor (8); the first temperature sensor (6) and the second temperature sensor (7) are electrically connected to a primary return water temperature optimization controller (5); and the primary return water temperature optimization controller (5), the third temperature sensor (8) and the primary refrigeration pump inverter (9) are all electrically connected to a primary refrigeration pump inverter controller (10);
[0008] The first temperature sensor (6) and the second temperature sensor (7) respectively transmit temperature detection signals T1 and T2 in the corresponding pipeline to the primary return water temperature optimization controller (5) in real time, and the primary return water temperature optimization calculation module of the primary return water temperature optimization controller (5) calculates the primary return water temperature optimization setting value T according to T1 and T2. 3,set , and the primary return water temperature is optimized to set value T 3,set The primary refrigeration pump frequency conversion control module of the primary refrigeration pump frequency conversion controller (10) receives the temperature signal T3 of the primary return water pipe (12) and the primary return water temperature optimization setting value T3 transmitted by the third temperature sensor (8) through the electrical signal transmission to the primary refrigeration pump frequency conversion controller (10). 3,set , calculate the primary refrigeration pump frequency value, and transmit the primary refrigeration pump frequency value to the primary refrigeration inverter (9), thereby controlling the primary refrigeration pump (2) to perform frequency conversion according to the primary refrigeration pump frequency value.
[0009] In the above implementation, the temperature of each pipeline is detected by a temperature sensor to calculate the optimal setting value of the primary return water temperature and the frequency of the primary refrigeration pump, and the frequency conversion control of the primary refrigeration pump is performed to adjust the actual primary return water temperature in the primary return water pipe according to the setting value. This replaces the technical defects of the high cost and poor accuracy of the traditional flow meter for adjusting the temperature. Under the premise of ensuring the stability and reliability of the frequency conversion control of the primary refrigeration pump, the energy consumption of the primary refrigeration pump is reduced, and the energy-saving purpose of reducing the energy consumption of the primary refrigeration pump is achieved.
[0010] Among them, the primary return water temperature optimization calculation module is a program module or operation module built into the primary return water temperature optimization controller, the primary refrigeration pump frequency conversion control module is a program module or operation module built into the primary refrigeration pump frequency conversion controller, the primary return water temperature optimization calculation module calculates the primary return water temperature optimization setting value according to T1 and T2; the primary refrigeration pump frequency conversion control module performs the calculation of the required primary refrigeration pump frequency value. The primary return water temperature optimization controller and the primary refrigeration pump frequency conversion controller can be selected from independent operation units, or can be integrated in one operation unit, wherein the operation unit can be selected from an existing single-chip microcomputer, PLC or DDC controller.
[0011] The temperature sensor is used to collect the water temperature of the primary water supply pipe, the secondary return pipe and the primary return pipe to replace the flow meter to detect the water volume of the balance pipe and use the flow to adjust the frequency of the primary refrigeration pump. The temperature detection of the existing temperature sensor is more accurate and reliable than the flow meter. The primary return water temperature optimization controller calculates the primary return water pipe optimization temperature setting value, and the primary refrigeration pump frequency value is calculated according to the actual detected primary return water pipe temperature by the primary refrigeration pump frequency conversion controller, and the primary refrigeration pump frequency value frequency signal is transmitted to the primary refrigeration pump frequency converter, thereby adjusting the water flow in the balance pipe, adjusting the temperature of the primary return water pipe to the optimized temperature setting value, and indirectly realizing the precise control of the water flow in the balance pipe and energy saving through the temperature control of the primary return water pipe. Among them, through the calculation of the primary return water temperature optimization calculation module, the bypass water volume control target in the balance pipe is transmitted to the primary return water temperature optimization setting value.
[0012] Furthermore, the primary return water temperature optimization setting value T 3,set The calculation formula is as follows:
[0013] T 3,set =KT1+(1-K)T2
[0014] In the above formula, K is the bypass water volume ratio of the balancing pipe (15), that is, the percentage of the bypass water volume passing through the balancing pipe (15) to the water volume passing through the primary water supply pipe (11); K is a custom target value, and its value range is greater than or equal to 0 and less than or equal to 0.3.
[0015] According to the above implementation, the K value is a weight value and also a control target value of the bypass water flow rate. The larger the K value is, the larger the bypass water volume is, and the larger the redundancy that the secondary pump can draw, but the corresponding energy waste of the primary pump is greater. The staff can customize this weight value according to the actual production needs on site. The temperature value obtained by setting K to the above formula is the optimized temperature setting value of the primary return pipe, and the temperature of the primary return pipe is controlled according to this value. The beneficial effect of setting the K value at 0 to 0.3 is to ensure an appropriate amount of bypass water, which can ensure a stable water supply temperature of the system, and at the same time reduce the energy consumption of the primary pump. The K value is preferably 0.1. When the K value is 0.1, that is, the bypass water volume accounts for 10% of the total water volume, it can ensure that the secondary pump has a certain amount of redundancy, ensure the stability of the system water supply temperature, and reduce the energy waste of the primary pump as much as possible.
[0016] Furthermore, the primary return water temperature optimization setting value T 3,set It has a certain range, which is 10℃~20℃. When the calculated optimal setting value of the primary return water temperature is less than 10℃, T 3,set =10℃, when the calculated optimal setting value of primary return water temperature is greater than 20℃, then T 3,set =20℃.
[0017] The present invention also provides a control method for the frequency conversion control system, comprising the following steps:
[0018] S1: according to the operating state of the chilled water system, the bypass water volume ratio K value of the balance pipe (15) is preset; the first temperature sensor (6) and the second temperature sensor (7) respectively collect the temperature of the water in the primary water supply pipe (11) and the secondary water return pipe (12), and then transmit the temperature signal to the primary return water temperature optimization controller (5);
[0019] S2: The primary return water temperature optimization controller (5) calculates the primary return water temperature optimization setting value of the current system through the built-in primary return water temperature optimization calculation module, and sends the calculated primary return water temperature optimization setting value to the primary refrigeration pump frequency conversion controller (10) through an electrical signal;
[0020] S3: The primary refrigeration pump frequency conversion control module of the primary refrigeration pump frequency conversion controller (10) compares the received primary return water temperature optimization setting value with the real-time primary return water temperature detected by the third temperature sensor (8), and calculates the required primary refrigeration pump frequency according to the deviation value, and sends it to the primary refrigeration pump frequency conversion device (9) through an electrical signal to realize the frequency conversion control of the primary refrigeration pump (2), and then adjusts the water flow in the balance pipe (15) so that the primary return water pipe temperature reaches the primary return water temperature optimization setting value.
[0021] In the above implementation, in step S3, the precise control of the water flow in the balance pipe and the purpose of energy saving are achieved indirectly by controlling the temperature of the primary return pipe.
[0022] Furthermore, the primary return water temperature optimization controller (5) adopts periodic calculation when calculating the primary return water temperature optimization setting value.
[0023] In the above-mentioned implementation mode, the periodic calculation is performed in order to avoid the primary return water temperature optimization controller (5) from frequently entering into the calculation.
[0024] Furthermore, the period is 15 to 35 minutes.
[0025] In the above embodiment, the shorter the cycle, the more frequently the primary return water temperature optimization controller (5) calculates, the more accurate the bypass water volume control is, but the corresponding primary pump frequency adjustment is more frequent, which is not conducive to the stable operation of the system. The cycle is preferably 30 minutes, which can ensure the accuracy of bypass water volume control and avoid frequent adjustment of primary pump frequency, thereby ensuring the stability of system operation.
[0026] Compared with the prior art, the present invention has the following beneficial effects:
[0027] The central air-conditioning primary refrigeration pump variable frequency control system and control method provided by the present invention overcome the technical problems in the prior art of low measurement accuracy of water flow meters, susceptibility to interference, large fluctuations in measured values, and poor stability and reliability. Temperature sensors with high accuracy and stability are used to respectively measure the temperatures of the primary water supply pipe, the secondary water return pipe and the primary water return pipe. While ensuring the stability and reliability of the variable frequency control of the primary refrigeration pump, the energy consumption of the primary refrigeration pump is reduced to solve the instability problem of the variable frequency control of the primary refrigeration pump in the secondary pump system, thereby achieving energy saving of the primary refrigeration pump.
[0028] The control method steps of the control method of the present invention are also relatively simple. According to the calculation model of the primary return water temperature optimization setting value, the optimal primary return water temperature optimization setting value can be conveniently calculated. It is suitable for installation and commissioning of actual projects and can be widely used in building air-conditioning systems.
[0029] The overall structure of the present invention is simple and the construction is convenient. The cost of the temperature sensor is much lower than that of the flow meter, and the installation is also more convenient than that of the flow meter, and the total construction cost is low. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 A schematic diagram of an embodiment of the present invention;
[0031] The reference numerals in the accompanying drawings are:
[0032] 1. Refrigeration main unit; 2. Primary refrigeration pump; 3. Secondary refrigeration pump; 4. Terminal air-conditioning unit; 5. Primary return water temperature optimization controller; 6. First temperature sensor; 7. Secondary temperature sensor; 8. Third temperature sensor; 9. Primary refrigeration pump inverter; 10. Primary refrigeration pump frequency conversion controller; 11. Primary water supply pipe; 12. Primary return pipe; 13. Secondary water supply pipe; 14. Secondary return pipe; 15. Balance pipe. DETAILED DESCRIPTION
[0033] The present invention is described in detail below in conjunction with the embodiments and drawings, but it should be understood that the embodiments and drawings are only used to exemplify the present invention and do not constitute any limitation on the protection scope of the present invention. All reasonable changes and combinations within the scope of the inventive concept of the present invention fall within the protection scope of the present invention.
[0034] The present invention will be further described below in conjunction with the accompanying drawings.
[0035] like Figure 1 As shown, the control objects of a central air-conditioning secondary pump primary refrigeration pump frequency conversion control system include a refrigeration host 1, a primary refrigeration pump 2, a primary refrigeration pump frequency converter 9 for frequency conversion control of the primary refrigeration pump 2, a secondary refrigeration pump 3, and a terminal air conditioning unit 4. The chilled water produced by the refrigeration host 1 passes through the primary water supply pipe 11, a part of which enters the secondary refrigeration pump 3, and a part of which enters the balance pipe 15. The chilled water entering the secondary refrigeration pump 3 is pressurized by the secondary refrigeration pump 3 and enters the terminal air conditioning unit 4 through the secondary water supply pipe 13 to exchange heat with the circulating air, and then passes through the secondary return water pipe 14 and the bypassed chilled water of the balance pipe 15. Then, it enters the primary return water pipe 12, and returns to the refrigeration host 1 after being pressurized by the primary refrigeration pump 2, completing the chilled water cycle.
[0036] The control device includes a primary refrigeration pump frequency conversion device 9; a first temperature sensor 6 installed on the primary water supply pipe 11; a second temperature sensor 7 installed on the secondary water return pipe 14; a third temperature sensor 8 installed on the primary water return pipe 12; a primary return water temperature optimization controller 5 and a primary refrigeration pump frequency conversion controller 10. The primary refrigeration pump frequency conversion device 9 performs frequency conversion control on the primary refrigeration pump 2, thereby adjusting the bypass water flow of the balance pipe 15; the first temperature sensor 6 measures the water temperature in the primary water supply pipe 11 in real time and collects real-time temperature signals; the second temperature sensor 7 measures the water temperature in the secondary water return pipe 14 in real time and collects real-time temperature signals; the third temperature sensor 8 measures the water temperature in the primary water return pipe 12 in real time and collects real-time temperature signals; the real-time temperature signals collected by the first temperature sensor 6 and the second temperature sensor 7 are transmitted to the primary return water temperature optimization controller 5, and the primary return water temperature optimization controller 5 is electrically connected to the primary refrigeration pump frequency conversion controller 10; the primary return water temperature optimization controller 5 adjusts the water flow rate of the balance pipe 15 according to the collected temperature signals , calculate the optimal setting value of the primary return water temperature, and transmit the optimal setting value signal of the primary return water temperature to the primary refrigeration pump frequency conversion controller 10; the third temperature sensor 8 transmits the measured water temperature signal in the primary return water pipe 12 to the primary refrigeration pump frequency conversion controller 10; the primary refrigeration pump frequency conversion controller 10 takes the optimal setting value of the primary return water temperature as the target, calculates the operating frequency of the primary refrigeration pump 2 according to the real-time temperature of the primary return water pipe 12, that is, the temperature value signal transmitted by the third temperature sensor 8, and outputs the calculated frequency electrical signal to the primary refrigeration pump frequency converter 9 to control the operating frequency of the primary refrigeration pump 2, and adjusts the bypass water flow of the balance pipe 15 to adjust the temperature of the primary return water pipe 12 to the optimal setting value of the primary return water temperature. By controlling the primary return water temperature, that is, controlling the temperature of the primary return water pipe 12, the precise control of the water flow in the balance pipe and the variable frequency energy-saving operation control of the primary refrigeration pump are indirectly achieved.
[0037] The primary return water temperature optimization controller 5 and the primary refrigeration pump frequency conversion controller 10 of the present invention are respectively built with a primary return water temperature optimization calculation module and a primary refrigeration pump frequency conversion control module. These two modules can also be built into one control module, that is, the primary return water temperature optimization controller and the primary refrigeration pump frequency conversion controller are combined to form a control module.
[0038] The control method of the central air-conditioning primary refrigeration pump variable frequency control system provided by the present invention comprises the following steps:
[0039] S1: According to the operating state of the chilled water system, the bypass water volume ratio K value of the balance pipe 15 is preset; the first temperature sensor 6 and the second temperature sensor 7 respectively collect the temperature of the water in the primary water supply pipe 11 and the secondary return water pipe 12, and then transmit the temperature signal to the primary return water temperature optimization controller 5;
[0040] S2: The primary return water temperature optimization controller 5 calculates the primary return water temperature optimization setting value of the current system through the built-in primary return water temperature optimization calculation module, and sends the calculated primary return water temperature optimization setting value to the primary refrigeration pump frequency conversion controller 10 through an electrical signal;
[0041] S3: The primary refrigeration pump frequency conversion control module of the primary refrigeration pump frequency conversion controller 10 compares the received primary return water temperature optimization setting value with the real-time primary return water temperature detected by the third temperature sensor 8, and calculates the required primary refrigeration pump frequency according to the deviation value, and sends it to the primary refrigeration pump frequency conversion device 9 through an electrical signal to realize the frequency conversion control of the primary refrigeration pump 2, and then adjust the water flow in the balance pipe 15 so that the primary return water pipe temperature reaches the primary return water temperature optimization setting value.
[0042] According to the above control method, the precise control of the water flow in the balance pipe and the purpose of energy saving are achieved indirectly through the temperature control of the primary return pipe.
[0043] In the above control method, the primary return water temperature optimization algorithm is executed by the primary return water temperature optimization calculation module; the calculation of the primary refrigeration pump frequency is calculated by the primary refrigeration pump frequency conversion control module. The primary return water temperature optimization controller 5 uses periodic calculation when calculating the primary return water temperature optimization setting value, and the calculation period is preferably 30 minutes.
[0044] The calculation formula for the optimal setting value of the primary return water temperature is as follows:
[0045] T 3,set =KT1+(1-K)T2
[0046] In the above formula, K is the bypass water ratio of the balance pipe 15, that is, the percentage of bypass water volume in the total water volume of the primary system, which is a user-defined target value, and its value is greater than or equal to 0 and less than or equal to 0.3; T1 is the primary water supply temperature; T2 is the secondary return water temperature; T 3,set is the optimal primary return water temperature setting value, where T1, T2 and T 3,set The unit is ℃.
[0047] Optimized setting value of primary return water temperature T 3,set With a certain range, such as 10℃-20℃, when the calculated optimal setting value of the primary return water temperature is less than 10℃, T 3,set =10℃, when the calculated optimal setting value of primary return water temperature is greater than 20℃, then T 3,set =20℃.
[0048] The primary refrigeration pump frequency conversion control module in the primary refrigeration pump frequency conversion controller 10 may adopt a PID control algorithm.
[0049] Embodiment 1
[0050] The primary water supply temperature T1 of the central air-conditioning primary refrigeration pump variable frequency control system provided by the present invention remains unchanged, such as 7°C, and the secondary refrigeration water pump 3 controls the secondary circuit supply and return water temperature difference through variable frequency regulation. When the load of the air-conditioning unit 4 changes, the operating frequency of the secondary refrigeration pump 3 will be adjusted to maintain the secondary return water temperature T2 unchanged, such as maintaining 12°C. At this time, the bypass water volume ratio in the balance pipe 15 will increase or decrease and deviate from the K value set by the user. If the K value is set to 0.1, the corresponding primary return water temperature T3 will change and deviate from the primary return water optimization setting value T 3,set , T is calculated by the primary return water temperature optimization controller 5 3,set When the return water temperature T3 is controlled at the set value T 3,set When the bypass water volume in the balance pipe 15 is reduced, the bypass water volume ratio will also be maintained at the set value K.
[0051] Embodiment 2
[0052] The water volume of the secondary chilled water system remains unchanged. When the primary water supply temperature T1 of the variable frequency control system provided by the present invention changes by, for example, 7°C or the load of the air conditioning unit 4 changes, the secondary return water temperature T2 will also change, and the corresponding primary return water temperature T3 will change accordingly. However, at this time, because the water volume of the secondary chilled water system remains unchanged, the bypass water volume ratio in the balance pipe 15 remains unchanged at the K value, and the primary return water temperature optimization setting value T calculated by the primary return water temperature optimization controller 5 is 3,set It changes accordingly and is the same as the actual primary return water temperature T3, so the primary refrigeration pump operating frequency value output by the primary refrigeration pump variable frequency controller 10 does not change.
[0053] To summarize the above embodiments, in the control method of the present variable frequency control system, only when the secondary chilled water flow rate changes, causing the bypass water volume ratio in the balance pipe 15 to change, the operating frequency of the primary chilled pump will be adjusted accordingly, and the bypass water volume ratio in the balance pipe 15 can be maintained unchanged by controlling the primary return water temperature.
[0054] The central air-conditioning primary refrigeration pump frequency conversion control system and control method provided by the present invention use temperature sensors to measure the temperatures of the primary water supply pipe, the secondary water return pipe and the primary water return pipe. The accuracy and stability of the temperature sensor are higher than those of the flow meter, while its procurement cost is lower than that of the flow meter. Compared with using flow as the control target, using temperature as the control target is more stable and reliable, has higher control accuracy and lower cost.
[0055] The above embodiments are only preferred implementations of the present invention, and the protection scope of the present invention is not limited to the above embodiments. All technical solutions under the concept of the present invention belong to the protection scope of the present invention. It should be pointed out that for ordinary technicians in this technical field, improvements and modifications without departing from the principle of the present invention should also be regarded as the protection scope of the present invention.
Claims
1. A central air conditioning primary refrigeration pump frequency conversion control system, comprising a refrigeration main unit (1), wherein the refrigeration main unit (1) is connected to a primary water supply pipe (11), a secondary refrigeration pump (3), a secondary water supply pipe (13), a terminal air conditioning unit (4), a return pipe, and a primary refrigeration pump (2) in sequence, wherein the primary refrigeration pump (2) is connected to the refrigeration main unit (1) to form a loop; a primary refrigeration pump frequency converter (9) is provided on the primary refrigeration pump (2) to perform frequency conversion regulation on the primary refrigeration pump (2); a bypass is provided at the front end where the primary water supply pipe (11) is connected to the secondary refrigeration pump (3), the balancing pipe (15) is connected to the return pipe, the return pipe between the air conditioning unit (4) and the balancing pipe (15) is the secondary return pipe (14), and the return pipe between the balancing pipe (15) and the primary refrigeration pump (2) is the primary return pipe (12), characterized in that: The primary water supply pipe (11) is provided with a first temperature sensor (6), the secondary water return pipe (14) is provided with a second temperature sensor (7), and the primary water return pipe (12) is provided with a third temperature sensor (8), the first temperature sensor (6) and the second temperature sensor (7) are electrically connected to a primary return water temperature optimization controller (5), and the primary return water temperature optimization controller (5), the third temperature sensor (8) and the primary refrigeration pump inverter (9) are all electrically connected to the primary refrigeration pump inverter controller (10); The first temperature sensor (6) and the second temperature sensor (7) respectively transmit temperature detection signals T1 and T2 in the corresponding pipeline to the primary return water temperature optimization controller (5) in real time, and the primary return water temperature optimization calculation module of the primary return water temperature optimization controller (5) calculates the primary return water temperature optimization setting value T according to T1 and T2. 3,set , and the primary return water temperature is optimized to set value T 3,set The primary refrigeration pump frequency conversion control module of the primary refrigeration pump frequency conversion controller (10) receives the temperature signal T3 of the primary return water pipe (12) and the primary return water temperature optimization setting value T3 transmitted by the third temperature sensor (8) to the primary refrigeration pump frequency conversion controller (10). 3,set , calculating a primary refrigeration pump frequency value, and transmitting the primary refrigeration pump frequency value to a primary refrigeration frequency converter (9), thereby controlling the primary refrigeration pump (2) to perform frequency conversion according to the primary refrigeration pump frequency value; The optimal setting value of the primary return water temperature T 3,set The calculation formula is as follows: , In the above formula, K is the bypass water volume ratio of the balancing pipe (15), that is, the percentage of the bypass water volume passing through the balancing pipe (15) to the water volume passing through the primary water supply pipe (11); K is a custom target value, and its value range is greater than or equal to 0 and less than or equal to 0.
3.
2. The frequency conversion control system according to claim 1, characterized in that: The optimal setting value of the primary return water temperature T 3,set has a certain range, which is 10℃~20℃. When the calculated optimal setting value of the primary return water temperature is less than 10℃, T 3,set =10℃, when the calculated optimal setting value of primary return water temperature is greater than 20℃, then T 3,set =20℃.
3. The control method of the frequency conversion control system according to any one of claims 1 to 2, characterized in that: The following steps are involved: S1: according to the operating state of the chilled water system, the bypass water volume ratio K value of the balance pipe (15) is preset; the first temperature sensor (6) and the second temperature sensor (7) respectively collect the temperature of the water in the primary water supply pipe (11) and the secondary water return pipe (14), and then transmit the temperature signal to the primary return water temperature optimization controller (5); S2: the primary return water temperature optimization controller (5) calculates the primary return water temperature optimization setting value of the current system through a built-in primary return water temperature optimization calculation module, and sends the calculated primary return water temperature optimization setting value to the primary refrigeration pump frequency conversion controller (10) through an electrical signal; S3: The primary refrigeration pump frequency conversion control module of the primary refrigeration pump frequency conversion controller (10) compares the received primary return water temperature optimization setting value with the real-time primary return water temperature detected by the third temperature sensor (8), and calculates the required primary refrigeration pump frequency according to the deviation value, and sends it to the primary refrigeration pump frequency converter (9) through an electrical signal to realize the frequency conversion control of the primary refrigeration pump (2), and then adjusts the water flow in the balance pipe (15) so that the primary return water pipe temperature reaches the primary return water temperature optimization setting value.
4. The control method according to claim 3, characterized in that: The primary return water temperature optimization controller (5) adopts periodic calculation when calculating the primary return water temperature optimization setting value.
5. The control method according to claim 4, characterized in that: The period is 15 to 35 minutes.
Citation Information
Patent Citations
Real-time frequency conversion control method and controller for water pump of central air conditioner
CN113915719A
Once reach secondary pump variable energy -saving control system
CN206369306U
Air conditioning heat source system
JP2005337594A
Cold-water circulating system
JP2011179755A
Control method, cooling apparatus system, cooling apparatus controller, cooling tower system, cooling tower controller, water pump system, and water pump controller
WO2016197849A1