A method and system for intelligently controlling the production rhythm of steel refining process
By using intelligent control methods and historical data and the status of the continuous casting machine, the timing of vacuum treatment is automatically adjusted, which solves the problem of improper production rhythm in steelmaking and achieves stable and efficient continuous casting production.
Patent Information
- Application Number
- CN202211472689.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-11-17
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2042-11-17
AI Technical Summary
In the steelmaking process, improper control of the production rhythm from the vacuum refining furnace to the continuous casting process leads to poor billet quality, and problems such as vacuum furnace treatment being too early or too late, interruption of molten steel pouring in continuous casting, and unstable casting speed exist.
By analyzing historical big data to predict processing and transfer times, and combining this with the production status of the continuous casting machine, the system automatically calculates the start and end times of vacuum processing, recommends equipment operations, and achieves intelligent control of the production rhythm.
It improves the automation level of steelmaking production, avoids human judgment errors, ensures continuous casting, and improves production stability and billet quality.
Smart Images

Figure CN115740383B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of steelmaking production, and more specifically, to an intelligent control method and system for the production rhythm of a steel refining process. Background Art
[0002] The RH vacuum refining (RH vacuum cycle degassing refining) process is taken as the research object. RH vacuum refining uses the molten steel from the primary refining furnace and the LF (Ladle Furnace) refined molten steel as raw materials. Through vacuum extraction, oxygen blowing decarburization, alloying, wire feeding and other process operations, the purpose of vacuum decarburization, degassing, deoxidation, and adjustment of the temperature and chemical composition of the molten steel is achieved. After the vacuum refining furnace is produced, the final molten steel will go through the continuous casting process, and the casting will be formed after cooling. LF is the ladle refining furnace, which uses electrode heating to adjust the composition and temperature. LF is mainly used for desulfurization and temperature adjustment, and can be equipped with rotary and electric furnaces. There are generally two process paths from vacuum refining furnace to continuous casting:
[0003] (1) After vacuum refining, the steel is directly hoisted by a crane to the continuous casting (CCM) for pouring (vacuum straight up). This continuous casting process is a continuous casting of multiple furnaces of molten steel. The molten steel supply cannot be interrupted. Therefore, before the current casting furnace is finished, the crane must hoist the molten steel that has been processed in the previous process and reach the molten steel temperature requirement for continuous casting. Otherwise, a pouring interruption accident will occur.
[0004] (2) After vacuum refining, it is hoisted by a crane to the LF refining furnace for refining, and then hoisted by a crane to the continuous casting and pouring. This vacuum refining treatment must not only meet the requirements of the temperature and composition of the molten steel at the outlet of this process, but also meet the production rhythm requirements of the continuous casting and LF furnace. Of course, in the production process, if the molten steel in the previous process cannot reach the continuous casting, it is possible to consider reducing the continuous casting speed, but this will lead to unstable continuous casting speed, affect the quality of the ingot, and fail to meet the typical constant pulling speed requirements. When there are water changes or other abnormal problems in continuous casting, and the pulling speed must be adjusted, the previous process must adjust the outlet temperature according to the pulling speed.
[0005] In summary, in the current steelmaking production process, especially in the process from vacuum refining furnace to continuous casting, there are the following technical problems that need to be solved urgently:
[0006] (1) The vacuum furnace is treated too early, and the waiting time is too long during continuous casting, resulting in the pouring temperature not meeting the casting requirements.
[0007] (2) The vacuum furnace is treated too late and for too long, resulting in the interruption of continuous casting molten steel.
[0008] (3) When an abnormal reduction in pulling speed occurs, the target temperature at the exit is automatically predicted and a vacuum refining adjustment plan is recommended.
[0009] (4) Generally, the production rhythm is controlled manually or semi-automatically in real time, which not only affects the concentration of vacuum furnace operation, but also may lead to wrong decisions due to various other matters, resulting in unstable production in the steel plant. Summary of the invention
[0010] The present invention aims at the technical problem that in the steelmaking production process in the prior art, the quality of the casting billet is poor due to poor production rhythm control from the vacuum refining furnace to the continuous casting process.
[0011] The present invention provides a method for intelligently controlling the production rhythm of a steel refining process, comprising the following steps:
[0012] S1, through historical big data analysis, the estimated processing time and transfer time of the current arriving heat A steel grade under different subsequent processes are obtained;
[0013] S2, according to the pouring plan, obtain the weight of all the furnaces with the same pouring sequence between the current arriving furnace A and the current production furnace B of the continuous casting machine; calculate the remaining total pouring time T1 required for all furnaces from A to B;
[0014] S3, through the smelting production path from A to B, calculate the remaining time for the start of processing and the remaining time for closing processing of furnace A at the station;
[0015] S4, according to the real-time production status of continuous casting and each process furnace, automatically calculates the time to start vacuum treatment when arriving at the station, recommends or controls the equipment to start treatment, and automatically calculates the time to end vacuum treatment during the treatment process, recommends or controls the equipment to end treatment.
[0016] Preferably, all heats between the currently arriving heat A and the currently produced heat B of the continuous casting machine include: RH and / or LF.
[0017] Preferably, the remaining total pouring time T1 includes: the processing time and transportation time of all furnaces from A to B.
[0018] Preferably, the smelting production path is:
[0019] Converter-CCM, or
[0020] Converter-RH-CCM, or
[0021] Converter-LF-CCM, or
[0022] Converter-LF-RH-CCM, or
[0023] Converter - RH-LF-CCM.
[0024] Preferably, the S2 specifically includes:
[0025] S21, first calculate the pouring speed of the continuous casting machine, through the following formula
[0026] ;
[0027] Sn is the casting speed of the continuous casting machine, in m / min; L1 is the casting section width of the continuous casting machine, in mm; L2 is the casting section thickness of the continuous casting machine, in mm; P is the density of the steel billet cast by the continuous casting machine, in kg / m3; W3 is the minute casting volume of the continuous casting machine;
[0028] S22, then calculate the remaining total pouring time T1=(W1+W2) / W3 according to the following formula;
[0029] W1 and W2 are the weights of all heats that need to be sent to the continuous casting machine for CMM.
[0030] Preferably, the S3 specifically includes:
[0031] When the smelting production path is straight up steel grade, i.e. converter-RH-CCM:
[0032] T2 = T1-T3-T4
[0033] T8 = T1 -T4
[0034] When the smelting production path is non-straight-up steel grade, i.e. converter-RH-LF-CCM:
[0035] T2 = T1-T3-T5-T6-T7
[0036] T8 = T1 -T4-T5-T6-T7
[0037] Among them, T2 is the remaining main valve opening time of RH, T3 is the RH processing time, T4 is the RH calming time, T5 is the LF processing time, T6 is the LF calming time, T7 is the transfer time between RH and LF, and T8 is the remaining main valve closing time of RH.
[0038] Preferably, the S4 specifically includes: before reaching B, controlling the end point temperature of the previous process of the continuous casting machine according to the casting speed of the continuous casting machine, and the end point temperature is directly proportional to the casting speed.
[0039] The present invention also provides an intelligent control system for the production rhythm of a steel refining process, wherein the system is used to implement the steps of the intelligent control method for the production rhythm of a steel refining process, specifically including:
[0040] The historical data module is used to obtain the estimated processing time and transfer time of the current arriving heat A steel grade under different subsequent processes through historical big data analysis;
[0041] The calculation module is used to obtain the weight of all furnaces with the same pouring sequence between the current furnace A arriving at the station and the current production furnace B of the continuous casting machine according to the pouring plan; calculate the remaining total pouring time T1 required for all furnaces from A to B; calculate the remaining time for furnace A to start processing and the remaining time for closing processing through the smelting production path from A to B;
[0042] The control module automatically calculates the timing for starting vacuum treatment according to the real-time production status of continuous casting and each process furnace, and recommends or controls the equipment to start treatment. During the treatment process, it automatically calculates the timing for ending vacuum treatment, and recommends or controls the equipment to end treatment.
[0043] The present invention also provides an electronic device, including a memory and a processor, wherein the processor is used to implement the steps of the intelligent control method of the production rhythm of the steel refining process when executing a computer management program stored in the memory.
[0044] The present invention also provides a computer-readable storage medium on which a computer management program is stored. When the computer management program is executed by a processor, the steps of the intelligent control method for the production rhythm of a steel refining process are implemented.
[0045] Beneficial effects: The present invention provides an intelligent control method and system for the production rhythm of a steel refining process, wherein the method includes: obtaining the estimated processing time and transfer time of the current arriving furnace A steel type in different subsequent processes through historical big data analysis; calculating the total remaining pouring time T1 required for all furnaces from A to B; calculating the remaining time for starting processing and the remaining time for closing processing of furnace A after arriving at the station through the smelting production path of furnaces from A to B. According to the real-time production status of continuous casting and furnaces in each process, it is recommended or controlled that the equipment start processing, and it is recommended or controlled that the equipment end processing. According to the real-time production status of continuous casting, the temperature forecast model can also be combined to control the outlet temperature. Avoid accidents of continuous casting interruption caused by negligence of personnel. The scheme has a high degree of automation and can efficiently realize continuous casting without pouring, which has broad practical significance for production. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] Figure 1 A flow chart of an intelligent control method for production rhythm of a steel refining process provided by the present invention;
[0047] Figure 2 A schematic diagram of the hardware structure of a possible electronic device provided by the present invention;
[0048] Figure 3 A schematic diagram of the hardware structure of a possible computer-readable storage medium provided by the present invention;
[0049] Figure 4 The smelting production roadmap provided by the present invention. DETAILED DESCRIPTION
[0050] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0051] refer to Figure 1 and Figure 4 , an embodiment of the present invention provides a method for intelligently controlling the production rhythm of a steel refining process, comprising the following steps:
[0052] S1, through historical big data analysis, the estimated processing time and transfer time of the current arriving furnace A steel type under different subsequent processes are obtained; the specific processes include: RH, LF, CCM, and the transfer time includes the sum of all transfer times from each process to CCM. Each process will correspond to a processing time. The transfer process between RH and LF has a transportation time. The process from RH or LF directly to the continuous casting CCM is a calming process, corresponding to the calming time. The transfer time is the sum of the transportation time and the calming time.
[0053] S2, according to the pouring plan, obtain the weight of all the furnaces with the same pouring sequence between the current arriving furnace A and the current production furnace B of the continuous casting machine; calculate the total remaining pouring time T1 required for all furnaces from A to B; start processing from the arriving furnace to the end of the continuous casting machine, there may be multiple pours being processed in the middle, such as RH, LF and CCM may all be being processed, so it is necessary to calculate the total time T1 for all pours to be processed. All furnaces between the current arriving furnace A and the current production furnace B of the continuous casting machine include: RH and / or LF. For example, if the smelting production path is converter-RH-LF-CCM, then the current arriving furnace A is RH, and all furnaces between the current production furnace B to CCM include RH and LF.
[0054] S3, through the smelting production path from A to B, calculate the remaining time for the start of processing and the remaining time for closing processing of furnace A. The smelting production path is roughly: converter-CCM, or converter-RH-CCM, or converter-LF-CCM, or converter-LF-RH-CCM, or converter-RH-LF-CCM. After determining the smelting production path from A to B, for example, converter-RH-LF-CCM, the remaining total pouring time T1 can be calculated through step S2.
[0055] S4, according to the real-time production status of continuous casting and each process furnace, automatically calculates the time to start vacuum treatment when arriving at the station, recommends or controls the equipment to start treatment, and automatically calculates the time to end vacuum treatment during the treatment process, recommends or controls the equipment to end treatment.
[0056] Taking the rhythm intelligent control of the RH process as an example, the specific implementation process of the method is as follows:
[0057] Through historical big data analysis, the estimated processing time and transfer time of the current RH arrival furnace A steel type under different subsequent processes are obtained; according to the pouring plan, the weight of all furnaces with the same pouring sequence between the current RH arrival furnace and the current production furnace B of the continuous casting machine is obtained; the total remaining pouring time T1 required for all furnaces from A to B is calculated; through the smelting production path of furnaces from A to B, the remaining time for furnace A to start processing and the remaining time for closing processing are calculated. According to the real-time production status of continuous casting and LF furnace, the time to start vacuum treatment is automatically calculated when arriving at the station, and the equipment is recommended or controlled to start processing. During the processing, the time to end vacuum treatment is automatically calculated, and the equipment is recommended or controlled to end processing. According to the real-time production status of continuous casting, the temperature forecast model can also be combined to control the exit temperature. Avoid continuous casting interruption accidents caused by negligence of personnel. This solution has a high degree of automation and can efficiently realize continuous casting without pouring, which has broad practical significance for production.
[0058] According to the production plan and the current real-time data of continuous casting (casting speed, cross section, number of streams, bag weight, etc.), the start and end processing time of the upcoming RH furnace can be calculated to meet the production rhythm of the steel plant and guide production in an orderly manner.
[0059] Trigger timing 1: When arriving at the station, scan the record of 1 in the first-level communication event table (indicating that the tracking program has been processed), and then start the rhythm model calculation;
[0060] Correction timing 1: From the time the ladle arrives at the station to the start of processing, correction is made every 5 seconds. After the processing start signal is detected, the calculation stops.
[0061] 1. The planning information is accurate and the production path is complete.
[0062] 2. The real-time data of continuous casting obtained is accurate.
[0063] 3. Except for the actual weight of the ladle at the continuous casting pouring position and the furnace weight after RH, the other weights that cannot be obtained shall be calculated according to the empirical value of 260t.
[0064] The specific process is as follows:
[0065] (1) Sorting out the current status of production rhythm control and application scenarios of the RH process;
[0066] (2) Establish standard smelting time models for different processes;
[0067] (3) Establish a temperature control model, including a temperature prediction model from the refining process to the continuous casting process and a temperature control model for this process.
[0068] (4) Based on the application scenario, the rhythm intelligent control method is used to calculate the start time of vacuum processing to see whether it is applicable to each scenario.
[0069] (5) Based on the application scenario, the rhythm intelligent control method is used to calculate the end time of vacuum treatment to see whether it is applicable to each scenario.
[0070] (6) Based on the application scenario, the rhythm intelligent control method is integrated with the temperature control model to automatically adjust the target endpoint temperature and recommend subsequent smelting operation plans for this process.
[0071] The present invention belongs to the field of steel production technology and information technology, and relates to intelligent control of the production rhythm of the vacuum refining process in a steelmaking workshop. According to the real-time production status of continuous casting and LF furnace, the time to start vacuum treatment is automatically calculated when arriving at the station, and the equipment is recommended or controlled to start treatment. During the treatment, the time to end vacuum treatment is automatically calculated, and the equipment is recommended or controlled to end treatment. According to the real-time production status of continuous casting, the outbound target temperature is automatically adjusted, and the outbound temperature is predicted in real time in combination with the temperature control model, and related operations for adjusting the RH furnace temperature are recommended.
[0072] In a specific implementation scenario, the total weight W1 of molten steel to be poured from the current pouring heat produced by the corresponding first continuous casting machine to the current RH arrival station to produce this furnace is calculated, in units of t, that is, w1 is all the heats that need to be CMMed at the first continuous casting machine. For example: the current RH arrival heat is AAA, after continuous casting No. 1, the planned pouring sequence is 11. The heat being poured by continuous casting No. 1 is BBB, and the planned pouring sequence is 8. There are two other heats 9 and 10 in the middle that need to be poured by continuous casting machine No. 1. 9 and 10 have not yet been cast. The weights of these two heats are W(9) and W(10) respectively. At this time, W1=W(9)+W(10). The specific calculation process is as follows:
[0073] S21, first calculate the pouring speed of the continuous casting machine, through the following formula
[0074] ;
[0075] Sn is the casting speed of the continuous casting machine, in m / min; L1 is the casting section width of the continuous casting machine, in mm; L2 is the casting section thickness of the continuous casting machine, in mm; P is the density of the steel billet cast by the continuous casting machine, in kg / m3; W3 is the minute casting volume of the continuous casting machine;
[0076] S22, then calculate the remaining total pouring time T1=(W1+W2) / W3 according to the following formula;
[0077] W1 and W2 are the weights of all heats that need to be sent to the continuous casting machine for CMM.
[0078] The S3 specifically includes:
[0079] When the smelting production path is straight up steel grade, i.e. converter-RH-CCM:
[0080] T2 = T1-T3-T4
[0081] T8 = T1 -T4
[0082] When the smelting production path is non-straight-up steel grade, i.e. converter-RH-LF-CCM:
[0083] T2 = T1-T3-T5-T6-T7
[0084] T8 = T1 -T4-T5-T6-T7
[0085] Among them, T2 is the remaining main valve opening time of RH, T3 is the RH processing time, T4 is the RH calming time, T5 is the LF processing time, T6 is the LF calming time, T7 is the transfer time between RH and LF, and T8 is the remaining main valve closing time of RH.
[0086] In a preferred solution, S4 specifically includes: before reaching B, the terminal temperature of the previous process of the continuous casting machine is controlled according to the pulling speed of the continuous casting machine, and the terminal temperature is directly proportional to the pulling speed. According to the length of time that the boiler is more or less than the normal furnace during the continuous casting process, the increase and decrease of the outlet temperature compared to the normal furnace is calculated to establish a temperature control model. The overall relationship of the temperature control model is to calculate the RH terminal temperature, and the relationship with the pulling speed is that the greater the pulling speed than the typical pulling speed, the lower the target terminal temperature of RH, and the lower the pulling speed, the higher the terminal temperature. For example, the temperature of the molten steel to CCM is related to the pulling speed of CCM. If the pulling speed is reduced by 0.5, the temperature will drop by 5 degrees.
[0087] Specifically, the pulling speed of each continuous casting stream, the net weight of the ladle of molten steel at the pouring position and waiting position of the continuous casting ladle turntable, the process path of the arriving furnace, and the planned scheduling data are obtained. Combined with the overhead crane lifting time, the processing time of the steel type in the vacuum furnace, the processing time of the steel type in the LF furnace and the molten steel temperature drop model in historical big data, the start time, end time and terminal temperature of the current vacuum treatment furnace are reversely inferred.
[0088] The embodiment of the present invention further provides an intelligent control system for the production rhythm of a steel refining process, the system is used to implement the steps of the intelligent control method for the production rhythm of a steel refining process as described above, specifically including:
[0089] The historical data module is used to obtain the estimated processing time and transfer time of the current arriving heat A steel grade under different subsequent processes through historical big data analysis;
[0090] The calculation module is used to obtain the weight of all furnaces with the same pouring sequence between the current furnace A arriving at the station and the current production furnace B of the continuous casting machine according to the pouring plan; calculate the remaining total pouring time T1 required for all furnaces from A to B; calculate the remaining time for furnace A to start processing and the remaining time for closing processing through the smelting production path from A to B;
[0091] The control module automatically calculates the timing for starting vacuum treatment according to the real-time production status of continuous casting and each process furnace, and recommends or controls the equipment to start treatment. During the treatment process, it automatically calculates the timing for ending vacuum treatment, and recommends or controls the equipment to end treatment.
[0092] See also Figure 2 Schematic diagram of an electronic device provided by an embodiment of the present invention. Figure 2 As shown, an embodiment of the present invention provides an electronic device, including a memory 1310, a processor 1320, and a computer program 1311 stored in the memory 1310 and executable on the processor 1320. When the processor 1320 executes the computer program 1311, the following steps are implemented: S1, obtaining the estimated processing time and transportation time of the current arriving heat A steel grade under different subsequent processes through historical big data analysis;
[0093] S2, according to the pouring plan, obtain the weight of all the furnaces with the same pouring sequence between the current arriving furnace A and the current production furnace B of the continuous casting machine; calculate the remaining total pouring time T1 required for all furnaces from A to B;
[0094] S3, through the smelting production path from A to B, calculate the remaining time for the start of processing and the remaining time for closing processing of furnace A at the station;
[0095] S4, according to the real-time production status of continuous casting and each process furnace, automatically calculates the time to start vacuum treatment when arriving at the station, recommends or controls the equipment to start treatment, and automatically calculates the time to end vacuum treatment during the treatment process, recommends or controls the equipment to end treatment.
[0096] See also Figure 3 Schematic diagram of an embodiment of a computer-readable storage medium provided by the present invention. Figure 3 As shown, this embodiment provides a computer-readable storage medium 1400 on which a computer program 1411 is stored. When the computer program 1411 is executed by a processor, the following steps are implemented: S1, obtaining the estimated processing time and transportation time of the current arriving heat A steel grade under different subsequent processes through historical big data analysis;
[0097] S2, according to the pouring plan, obtain the weight of all the furnaces with the same pouring sequence between the current arriving furnace A and the current production furnace B of the continuous casting machine; calculate the remaining total pouring time T1 required for all furnaces from A to B;
[0098] S3, through the smelting production path from A to B, calculate the remaining time for the start of processing and the remaining time for closing processing of furnace A at the station;
[0099] S4, according to the real-time production status of continuous casting and each process furnace, automatically calculates the time to start vacuum treatment when arriving at the station, recommends or controls the equipment to start treatment, and automatically calculates the time to end vacuum treatment during the treatment process, recommends or controls the equipment to end treatment.
[0100] Compared with the prior art, the present invention has the following advantages and positive effects:
[0101] 1) The present invention can realize automatic control of the start and end of vacuum treatment and meet the rhythm requirements of continuous casting and its own process production requirements, avoiding errors caused by manual calculation and manual verification.
[0102] 2) The present invention combines the production rhythm of continuous casting to automatically adjust the end temperature of this process to meet the production requirements of continuous casting and reduce the error of manual judgment.
[0103] 3) The present invention can be used in all pre-processes of continuous casting, adapt to the rhythm of steelmaking production, improve the continuous casting draw rate, and reduce the accident rate of continuous casting production.
[0104] It should be noted that in the above embodiments, the description of each embodiment has its own emphasis, and for parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0105] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.
[0106] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A method for intelligently controlling the production rhythm of a steel refining process, characterized in that: The following steps are involved: S1, through historical big data analysis, obtain the estimated processing time and transfer time of the current arriving heat A steel grade under different subsequent processes; S2, according to the pouring plan, obtain the weight of all the furnaces with the same pouring sequence between the current arriving furnace A and the current production furnace B of the continuous casting machine; calculate the remaining total pouring time T1 required for all furnaces from A to B; S3, through the smelting production path from furnace A to furnace B, calculate the remaining time for furnace A to start processing and the remaining time for closing processing; S4, according to the real-time production status of continuous casting and each process furnace, automatically calculates the time to start vacuum treatment when arriving at the station, recommends or controls the equipment to start treatment, and automatically calculates the time to end vacuum treatment during the treatment process, recommends or controls the equipment to end treatment; All heats between the current arriving heat A and the current production heat B of the continuous casting machine include: RH and / or LF; The remaining total pouring time T1 includes: the processing time and transfer time of all furnaces from A to B; The smelting production path is: Converter-CCM, or Converter-RH-CCM, or Converter-LF-CCM, or Converter-LF-RH-CCM, or Converter-RH-LF-CCM; The S2 specifically includes: S21, first calculate the pouring speed of the continuous casting machine, through the following formula ; Sn is the casting speed of the continuous casting machine, in m / min; L1 is the casting section width of the continuous casting machine, in mm; L2 is the casting section thickness of the continuous casting machine, in mm; P is the density of the steel billet cast by the continuous casting machine, in kg / m3; W3 is the minute casting volume of the continuous casting machine; S22, then calculate the remaining total pouring time T1=(W1+W2) / W3 according to the following formula; W1 and W2 are the weights of all the heats that need to be CMMed at the continuous casting machine; The S3 specifically includes: When the smelting production path is straight up steel grade, i.e. converter-RH-CCM: T2 = T1-T3-T4 T8 = T1 -T4 When the smelting production path is non-straight-up steel grade, i.e. converter-RH-LF-CCM: T2 = T1-T3-T5-T6-T7 T8 = T1 -T4-T5-T6-T7 Among them, T2 is the remaining main valve opening time of RH, T3 is the RH processing time, T4 is the RH calming time, T5 is the LF processing time, T6 is the LF calming time, T7 is the transfer time between RH and LF, and T8 is the remaining main valve closing time of RH; The S4 specifically includes: before reaching B, controlling the end point temperature of the previous process of the continuous casting machine according to the casting speed of the continuous casting machine, and the end point temperature is in direct proportion to the casting speed.
2. An intelligent control system for the production rhythm of steel refining process, characterized in that: The system is used to implement the steps of the intelligent control method for the production rhythm of the steel refining process according to claim 1, specifically including: The historical data module is used to obtain the estimated processing time and transfer time of the current arriving heat A steel grade under different subsequent processes through historical big data analysis; The calculation module is used to obtain the weight of all furnaces with the same pouring sequence between the current furnace A arriving at the station and the current production furnace B of the continuous casting machine according to the pouring plan; calculate the remaining total pouring time T1 required for all furnaces from A to B; calculate the remaining time for furnace A to start processing and the remaining time for closing processing through the smelting production path from A to B; The control module automatically calculates the timing for starting vacuum treatment according to the real-time production status of continuous casting and each process furnace, and recommends or controls the equipment to start treatment. During the treatment process, it automatically calculates the timing for ending vacuum treatment, and recommends or controls the equipment to end treatment.
3. An electronic device, characterized in that: It comprises a memory and a processor, wherein the processor is used to implement the steps of the intelligent control method for the production rhythm of the steel refining process as claimed in claim 1 when executing the computer management program stored in the memory.
4. A computer-readable storage medium, characterized in that: A computer management program is stored thereon, and when the computer management program is executed by the processor, the steps of the intelligent control method for the production rhythm of the steel refining process as claimed in claim 1 are implemented.