A method for repairing leakage of an anti-seepage system of an operating solid waste landfill
By drilling grouting holes and using a combination method of polyurethane foaming agent, organic bentonite and acid-resistant cement slurry, the problem of leakage in the anti-seepage system of solid waste landfill site is solved, and more efficient leakage repair effect and cost savings are achieved. Adapted to the complex environment of landfills.
Patent Information
- Application Number
- CN202211708419.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-29
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-12-29
AI Technical Summary
The existing solid waste landfill anti-seepage system is prone to leakage problems during operation. The traditional repair method excavation work is large and the risks are high. The slurry ratio and grouting pressure are difficult to control, making it difficult to ensure the repair effect.
Drilling grouting holes to form a penetration channel, first pre-blocking with polyurethane foaming agent, then inject organic bentonite, and finally reinforce the use of acid-resistant cement slurry to form a sealing layer to prevent leakage, and ensure the material by burying the flower tube and grouting tube. Fully permeate and solidify.
It effectively improves the anti-seepage effect, reduces the repair cost, ensures the sealing and repairing effect of the leakage channel, adapts to the complex physical and chemical environment of the landfill, and plays a supporting role after reinforcement of acid-resistant cement slurry, and prevents subsequent collapse and settlement.
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of solid waste landfill anti-seepage, and in particular to a method for repairing leakage of an anti-seepage system of an already operating solid waste landfill. Background Art
[0002] At present, there are more than 650 domestic waste landfills and more than 100 hazardous waste landfills in urban construction across the country, as well as a large number of general industrial solid waste landfills. These landfills are built with anti-seepage systems in accordance with current national standards and specifications, but during the landfill operation process, they are inevitably damaged and pollutants seep out to pollute the environment. After the construction is completed, most landfills have leakage problems, and the leakage points can be several kilometers or more away from the landfill.
[0003] At present, the most effective method for landfill leakage repair is to find the leakage point or leakage area and then accurately repair the leakage point or leakage area. At present, the repair method mostly adopts direct excavation and repair, which has a large excavation workload and forms a deep foundation pit with high risks; the traditional geotechnical engineering grouting method is not easy to control the slurry ratio, grouting pressure, process, etc., and it is difficult to control the slurry repair path and ensure the repair effect.
[0004] Therefore, how to use new materials and technologies to repair leakage in the current solid waste landfill anti-seepage system is an urgent problem to be solved. Summary of the invention
[0005] The embodiment of the present application provides a method for repairing leakage of an anti-seepage system of an already operating solid waste landfill, which can better adapt to the complex physical and chemical environment of the landfill and ensure the anti-seepage effect. The technical solution is as follows:
[0006] The present application provides a method for repairing leakage of an anti-seepage system of an already operating solid waste landfill, comprising the following steps: drilling grouting holes, drilling a plurality of grouting holes in a leakage area to form a seepage channel; injecting anti-seepage materials, comprising the following steps: pre-plugging grouting, using a polyurethane foaming agent to pre-plug the seepage channel; anti-seepage grouting, injecting organic bentonite to plug the leakage channel; reinforcement grouting, injecting acid-resistant cement slurry, which plays a supporting and reinforcing role after solidification.
[0007] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the drilling depth of the grouting hole is 2.5-3.5 m below the anti-seepage layer, and the bottom surface of the grouting hole is located 1 m below the bottom of the leachate contaminated area.
[0008] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the drilling depth of the grouting hole is 3 m below the anti-seepage layer, and the aperture of the grouting hole is not less than 100 mm.
[0009] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, a grouting hole is drilled every 1-2 m in the leakage area, and a grouting hole is drilled every 1-2 m on the boundary of the leakage area, and a permeation channel is formed between the grouting holes.
[0010] For example, in a method for repairing leakage of an anti-seepage system of an operating solid waste landfill provided in one embodiment, after drilling the grouting hole, the following steps are also included: burying a flower pipe: burying a flower pipe between the bottom of the grouting hole and the top surface of the anti-seepage layer; burying a grouting pipe: burying a grouting pipe in each of the grouting holes, and providing an anti-blocking component at the slurry outlet of the grouting hole; sealing the hole: sealing the gap between the grouting pipe and the grouting hole to form a sealing layer; removing the leachate in the flower pipe: after the sealing layer solidifies, pumping out the leachate in the flower pipe and discharging it, and then injecting the anti-seepage material through the grouting pipe.
[0011] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the height of the plugging layer is not less than 1 m, and the top of the plugging layer is located 0.2-0.3 m below the top surface of the anti-seepage layer.
[0012] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the sealing layer material is cement mortar, and the grouting pipe is a steel pipe.
[0013] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, during pre-plugging grouting, the foaming time, injection pressure and termination conditions of the polyurethane foaming agent are adjusted according to the permeability of the permeation channel to ensure that the polyurethane foaming agent fully penetrates into the pores.
[0014] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, during the anti-seepage grouting process, organic bentonite is injected into the infiltration channel by pressure, and the water-cement ratio, injection pressure and termination conditions of the organic bentonite are adjusted according to the permeability of the infiltration channel to ensure the anti-seepage effect.
[0015] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, during the reinforcement grouting process, the initial setting time, water-cement ratio, injection pressure and termination conditions of the acid-resistant cement slurry are adjusted according to the permeability of the infiltration channel to ensure the anti-seepage effect.
[0016] The beneficial effects of a leakage repair method for an operational solid waste landfill anti-seepage system provided in some embodiments of the present application are as follows: the present application adopts a method of pre-blocking with a polyurethane foaming agent, then anti-seepage with organic bentonite, and finally reinforcement with acid-resistant cement slurry. When the acid-resistant cement slurry is injected, it can further promote the organic bentonite to better penetrate into small infiltration channels, further improving the anti-seepage effect. By pre-blocking the leakage channels, the repair cost is greatly saved compared to the existing repair methods, and the repair effect is improved. DETAILED DESCRIPTION
[0017] The following will be combined with the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0018] Unless otherwise defined, the technical terms or scientific terms used in the present disclosure should be understood by people with ordinary skills in the field to which the present disclosure belongs. The "first", "second" and similar words used in the present disclosure do not indicate any order, quantity or importance, but are only used to distinguish different components. "Include" or "comprise" and similar words mean that the elements or objects appearing before the word cover the elements or objects listed after the word and their equivalents, without excluding other elements or objects. "Connect" or "connected" and similar words are not limited to physical or mechanical connections, but can include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0019] The present application provides a method for repairing leakage of an anti-seepage system of an already operating solid waste landfill, comprising the following steps:
[0020] Drill grouting holes. Drill several grouting holes in the leakage area to form a permeable channel.
[0021] Burying the flower pipe: burying the flower pipe between the bottom of the grouting hole and the top surface of the anti-seepage layer;
[0022] Burying a grouting pipe: burying a grouting pipe in each of the grouting holes, and providing an anti-blocking component at the grouting outlet of the grouting hole;
[0023] Sealing the hole: sealing the gap between the grouting pipe and the grouting hole to form a sealing layer;
[0024] Remove the leachate from the flower tube: after the plugging layer solidifies, remove the leachate from the flower tube and discharge it, and then inject the anti-seepage material through the grouting pipe;
[0025] Injecting the impermeable material includes the following steps:
[0026] Pre-blocking grouting, using polyurethane foaming agent to pre-block the penetration channel;
[0027] Anti-seepage grouting, injecting organic bentonite to block the leakage channel;
[0028] Reinforcement grouting, injecting acid-resistant cement slurry, which plays a supporting and reinforcing role after solidification.
[0029] Finally, the effects are monitored, pollution indicators of monitoring wells are continuously tested, and the restoration effects are monitored to ensure that pollution indicators continue to decrease until they meet the standards.
[0030] The present application adopts a method of pre-blocking with polyurethane foaming agent, then anti-seepage with organic bentonite, and then reinforcement with acid-resistant cement slurry. When grouting with acid-resistant cement slurry, it can further promote the better penetration of organic bentonite into small permeable channels, further improving the anti-seepage effect. During grouting in traditional geotechnical engineering, the slurry is easy to flow along the leakage channel. If the grouting pressure is not well controlled, the slurry is easy to run around, and it is difficult to achieve the blocking effect. The grouting material needs to have a certain strength and flexibility, and can resist deformation without destroying the anti-seepage function. The material is also required to be acid-resistant and alkali-resistant, and resist the influence of multiple pollutants. In addition, the leakage channel is too large, the material consumption is uncontrollable, and the cost is high. Therefore, it is very important to quickly block the leakage channel first, that is, pre-block the leakage channel. The leakage repair method of the anti-seepage system of the solid waste landfill in operation in this application greatly saves the repair cost compared with the existing repair method.
[0031] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the drilling depth of the grouting hole is 2.5-3.5 m below the anti-seepage layer, and the bottom surface of the grouting hole is located 1 m below the bottom of the leachate contaminated area.
[0032] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the drilling depth of the grouting hole is 3 m below the anti-seepage layer, and the aperture of the grouting hole is not less than 100 mm.
[0033] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, a grouting hole is drilled every 1-2 m in the leakage area, and a grouting hole is drilled every 1-2 m on the boundary of the leakage area, and a permeation channel is formed between the grouting holes.
[0034] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the height of the plugging layer is not less than 1 m, and the top of the plugging layer is located 0.2-0.3 m below the top surface of the anti-seepage layer.
[0035] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, the sealing layer material is cement mortar, and the grouting pipe is a steel pipe.
[0036] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, during pre-plugging grouting, the foaming time, injection pressure and termination conditions of the polyurethane foaming agent are adjusted according to the permeability of the permeation channel to ensure that the polyurethane foaming agent fully penetrates into the pores. According to the above embodiment, the use of polyurethane foaming agent and the adjustable foaming time can ensure full penetration into the pores; the use of polyurethane foaming agent for foaming pre-plugging of larger permeation channels can greatly improve the subsequent grouting effect, and at the same time, after the large leakage channel is blocked, the subsequent anti-seepage materials can be greatly saved.
[0037] For example, in a method for repairing leakage of an operational solid waste landfill anti-seepage system provided in one embodiment, during the anti-seepage grouting process, organic bentonite is injected into the permeation channel by pressure, and the water-cement ratio, injection pressure and termination conditions of the organic bentonite are adjusted according to the permeability of the permeation channel to ensure the anti-seepage effect. According to the above embodiment, the organic bentonite has better chemical stability and environmental adaptability, can better adapt to the complex physical and chemical environment of the landfill, give play to its low permeability characteristics, and can ensure the anti-seepage effect by being injected into the permeation channel by pressure.
[0038] For example, in a leakage repair method for an operational solid waste landfill anti-seepage system provided in one embodiment, during the reinforcement grouting process, the initial setting time, water-cement ratio, injection pressure and termination conditions of the acid-resistant cement slurry are adjusted according to the permeability of the permeation channel to ensure the anti-seepage effect. According to the above embodiment, the initial setting time of the acid-resistant cement is adjustable, which can ensure sufficient grouting. The acid-resistant cement can better adapt to the environment of the landfill and ensure a good reinforcement effect, so that the repaired grouting material is closely combined with the original anti-seepage layer to prevent subsequent collapse and settlement of the leakage point. The acid-resistant cement slurry plays a supporting skeleton role after solidification. The grouting process further squeezes the organic bentonite to seal the pores for anti-seepage.
[0039] Although the implementation scheme of the present application has been disclosed as above, it is not limited to the applications listed in the specification and implementation modes, and it can be fully applicable to various fields suitable for the present application. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present application is not limited to specific details.
Claims
1. A method for repairing leakage of an anti-seepage system of an operating solid waste landfill. It is characterized in that The following steps are involved: Drilling grouting holes: Drilling several grouting holes in the leakage area to form a permeable channel. After drilling the grouting holes, the following steps are also included: Burying the flower pipe: burying the flower pipe between the bottom of the grouting hole and the top surface of the anti-seepage layer; Burying a grouting pipe: burying a grouting pipe in each of the grouting holes, and providing an anti-blocking component at the grouting outlet of the grouting hole; Sealing the hole: sealing the gap between the grouting pipe and the grouting hole to form a sealing layer; Remove the leachate from the flower tube: after the plugging layer solidifies, remove the leachate from the flower tube and discharge it, and then inject the anti-seepage material through the grouting pipe; Injecting the impermeable material includes the following steps: First, pre-block grouting is performed, and polyurethane foaming agent is used to pre-block the penetration channel; Then carry out anti-seepage grouting, inject organic bentonite to block the leakage channel; Finally, reinforcement grouting is carried out by injecting acid-resistant cement slurry, which plays a supporting and reinforcing role after solidification.
2. The method for repairing leakage of the anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that The drilling depth of the grouting hole is 2.5-3.5m below the anti-seepage layer, and the bottom surface of the grouting hole is located 1m below the bottom of the leachate contaminated area.
3. The method for repairing leakage of the anti-seepage system of an operating solid waste landfill according to claim 2, It is characterized in that The drilling depth of the grouting hole is 3m below the anti-seepage layer, and the hole diameter of the grouting hole is not less than 100mm.
4. The method for repairing leakage of the anti-seepage system of an operating solid waste landfill according to claim 3, It is characterized in that A grouting hole is drilled every 1-2m in the leakage area, and a grouting hole is drilled every 1-2m on the boundary of the leakage area to form a permeable channel between the grouting holes.
5. The method for repairing leakage of the anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that The height of the blocking layer is not less than 1 m, and the top of the blocking layer is located 0.2-0.3 m below the top surface of the anti-seepage layer.
6. The method for repairing leakage of the anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that The material of the blocking layer is cement mortar, and the grouting pipe is a steel pipe.
7. The method for repairing leakage of an anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that During pre-plugging grouting, the foaming time, injection pressure and termination conditions of the polyurethane foaming agent are adjusted according to the permeability of the permeation channel to ensure that the polyurethane foaming agent fully penetrates into the pores.
8. The method for repairing leakage of an anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that During the anti-seepage grouting process, the organic bentonite is injected into the permeable channel by pressure, and the water-cement ratio, injection pressure and termination conditions of the organic bentonite are adjusted according to the permeability of the permeable channel to ensure the anti-seepage effect.
9. The method for repairing leakage of an anti-seepage system of an operating solid waste landfill according to claim 1, It is characterized in that During the reinforcement grouting process, the initial setting time, water-cement ratio, injection pressure and termination conditions of the acid-resistant cement slurry are adjusted according to the permeability of the permeable channel to ensure the anti-seepage effect.