A construction method for masonry sandwich decorative wall

Through the construction method of masonry sandwich decorative walls, the buried main bonding ribs are welded with structural columns, and combined with the masonry of aerated concrete blocks and shale sintered bricks, an inner and outer leaf wall is formed and an air layer is left, which solves the problems of hollowing, peeling and falling off of existing exterior wall decoration methods, and improves the safety and aesthetics of the building.

CN116104225BActive Publication Date: 2025-04-18SHANXI NO 8 CONSTR GRP
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310095074.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-02-10
Publication Date
2025-04-18
Estimated Expiration
2043-02-10

AI Technical Summary

Technical Problem

Existing exterior wall decoration methods are prone to quality problems such as hollowing, peeling, and falling off, and there is a risk of falling objects from high altitudes.

Method used

The construction method of masonry sandwich decorates the wall is adopted. By welding the embedded main body tie bars and structural columns, combining the masonry of aerated concrete blocks and shale sintered bricks, an inner and outer leaf wall is formed and an air layer is left to ensure the fixed connection of the tied steel mesh.

Benefits of technology

It solves the problem of hollowing, peeling and falling off the exterior wall decorative layer, avoids the risk of falling objects at high altitudes, and enhances the safety and aesthetics of the building through overall earthquake resistance, lightning protection and shielding networks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116104225B_ABST
    Figure CN116104225B_ABST
Patent Text Reader

Abstract

The present invention specifically relates to a construction method for a masonry sandwich decorative wall, which solves the quality problems of the existing decorative methods, such as hollowing, peeling, and falling off of the exterior wall decorative layer. A construction method for a masonry sandwich decorative wall, which is achieved by the following steps: Step S1: casting structural columns and pre-embedded main body tie bars; Step S2: masonry inner leaf walls; Step S3: moisture-proof leveling treatment; Step S4: installing insulation boards; Step S5: masonry outer leaf walls; Step S6: cleaning the outer leaf walls, grouting, and spraying protective liquid. The present invention uses shale sintered bricks as the outer leaf walls, which are effectively tied to the inner leaf walls, solves the quality problems of the existing exterior wall decorative layers, such as hollowing, peeling, and falling off, and avoids the risk of falling objects from high altitudes; the structural design of the ring beam and the unloading cantilever eaves combined into one can strengthen the strength of the entire building, and at the same time can bear the load of the part of the outer leaf wall that has been unloaded, and further has the advantages of being neat and beautiful.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of wall construction, in particular to a construction method of a masonry type sandwich decorative wall. Background Art

[0002] Traditional methods of decorating the exterior walls of public buildings mainly include paint decoration, dry hanging or stone or tile decoration, curtain wall decoration, etc. However, in the long-term use process, the exterior wall decoration layer is prone to quality problems such as hollowing, peeling, and falling off. Even due to the large-scale falling off of the exterior wall decoration layer, objects falling from high altitudes may occur, thus causing irreversible safety accidents.

[0003] Therefore, it is necessary to provide a construction method for a masonry type sandwich decorative wall to solve the above problems. Summary of the invention

[0004] In order to solve the quality problems of the existing decoration method that the exterior wall decoration layer is prone to hollowing, peeling, shedding and the like, the present invention provides a construction method for a masonry type sandwich decoration wall.

[0005] The present invention is achieved by adopting the following technical solutions:

[0006] A construction method for a masonry sandwich decorative wall is achieved by the following steps:

[0007] Step S1: Casting the structural column, embedding a plurality of main tie bars arranged in the horizontal direction and evenly distributed vertically during the casting process, and welding and fixing the main tie bars to the main vertical steel bars in the structural column;

[0008] Step S2: build an inner leaf wall between two structural columns, using aerated concrete blocks as masonry units, and in the masonry process, weld and fix the two ends of the horizontally arranged seismic steel bars to the two main tie bars that match the positions, and weld and fix the horizontally arranged rectangular tie steel mesh to the two main tie bars that match the positions, and then build the seismic steel bars, the main tie steel bars and the tie steel mesh together between two adjacent layers of aerated concrete blocks that match the positions; at this time, the tie steel mesh exceeds the inner leaf wall;

[0009] When the masonry reaches the middle of each floor, a ring beam is cast on the aerated concrete blocks, and a load-relief eaves is cast on the outside of the ring beam;

[0010] Step S3: After the inner leaf wall is built, a plaster layer is applied on the outer side of the inner leaf wall for moisture-proof and leveling treatment;

[0011] Step S4: installing an insulation board on the outer side of the plaster layer, fixing the top end of the insulation board to the tie steel mesh located on the upper side, and fixing the bottom end of the insulation board to the tie steel mesh located on the lower side;

[0012] Step S5: building an outer leaf wall on the outside of the insulation board, using shale sintered bricks as the masonry unit, and during the masonry process, the tie steel mesh that exceeds the inner leaf wall is built between two adjacent layers of shale sintered bricks that match the position; at this time, an air layer is left between the outer leaf wall and the insulation board;

[0013] When the masonry reaches the middle of each floor, shale fired bricks are laid on the lower surface, upper surface and side surfaces of the unloading eaves, and the weight of the shale fired bricks above the unloading eaves is unloaded onto the unloading eaves;

[0014] Step S6: Clean the outer blade wall, and fillet the outer blade wall and spray the protective liquid.

[0015] The structural design of the present invention is reasonable and reliable. It uses shale sintered bricks as the outer leaf wall and effectively connects them with the inner leaf wall, which solves the quality problems of hollowing, peeling, and falling off of the existing outer wall decoration layer, and avoids the risk of falling objects from high altitudes. The lightning protection mesh is connected with the main tie bars, the main vertical steel bars, the seismic steel bars and the tie steel mesh into a whole to achieve the purpose of seismic resistance, lightning protection and shielding network of the entire building. The structural design of combining the ring beam and the unloading eaves can enhance the strength of the entire building, and at the same time can unload the part of the load-bearing of the outer leaf wall. Further, it has the advantages of being neat and beautiful. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a structural schematic diagram of the present invention.

[0017] Figure 2 It is a schematic diagram of the casting state of the ring beam and the unloading eaves in the present invention.

[0018] Figure 3 It is a schematic diagram of the laying state of shale fired bricks at the door and window openings or the awning position in the present invention.

[0019] Figure 4 It is a structural schematic diagram of the triangular pyramid wall in the present invention.

[0020] In the figure: 1-structural column, 2-main body tie bar, 3-inner leaf wall, 4-aerated concrete block, 5-seismic steel bar, 6-tie steel mesh, 7-ring beam, 8-unloading cantilever, 9-insulation board, 10-outer leaf wall, 11-shale sintered brick, 12-structural cantilever, 13-triangular wall, 14-triangular pyramid wall, 15-U-shaped channel, 16-doors and windows, 17-pipe hole. DETAILED DESCRIPTION

[0021] A construction method for a masonry sandwich decorative wall is achieved by the following steps:

[0022] Step S1: Casting the structural column 1, embedding a plurality of main tie bars 2 arranged in the horizontal direction and evenly distributed vertically during the casting process, and welding and fixing the main tie bars 2 to the main vertical steel bars in the structural column 1;

[0023] Step S2: build an inner leaf wall 3 between two structural columns 1, and use aerated concrete blocks 4 as masonry units. During the masonry process, the two ends of the horizontally arranged seismic steel bars 5 are welded and fixed to the two main tie bars 2 that match the positions, and the horizontally arranged rectangular tie steel mesh 6 is welded and fixed to the two main tie bars 2 that match the positions, and then the seismic steel bars 5, the main tie bars 2 and the tie steel mesh 6 are built together between two adjacent layers of aerated concrete blocks 4 that match the positions; at this time, the tie steel mesh 6 exceeds the inner leaf wall 3; the size of the aerated concrete block 4 is 600mm*200mm*240mm; the tie steel mesh 6 is made of galvanized steel bars with a diameter of 4mm, and the overhanging length of the tie steel mesh 6 is 200mm;

[0024] When the masonry reaches the middle of each floor, a ring beam 7 is cast on the aerated concrete blocks 4, and a load-relief cantilever 8 is cast on the outside of the ring beam 7; the cantilever length of the load-relief cantilever 8 is 165mm and the cantilever thickness is 100mm;

[0025] Step S3: After the inner leaf wall 3 is built, a plaster layer is applied on the outer side of the inner leaf wall 3 for moisture-proof and leveling treatment; the plaster layer is a cement mortar mixed with 5% waterproof powder and a water-sand ratio of 1:2.5, and the thickness of the plaster layer is 20 mm;

[0026] Step S4: Install the insulation board 9 on the outer side of the plaster layer, fix the top of the insulation board 9 to the tie steel mesh 6 located on the upper side, and fix the bottom of the insulation board 9 to the tie steel mesh 6 located on the lower side, and use insulation expansion nails to fix the connection; the insulation board 9 is a Class A fireproof and hydrophobic rock wool insulation board 9 with a thickness of 80 mm and a width modulus of 500 mm;

[0027] Step S5: build an outer leaf wall 10 on the outside of the insulation board 9, using shale sintered bricks 11 as masonry units, and during the masonry process, build the tie steel mesh 6 that exceeds the inner leaf wall 3 between two adjacent layers of shale sintered bricks 11 that match the position; at this time, an air layer is left between the outer leaf wall 10 and the insulation board 9; the thickness of the air layer is 20 mm; the insulation layer and the air layer can block the transmission of sound waves, which can effectively reduce the transmission of sound waves by more than 95%;

[0028] Before building the outer leaf wall 10, a pull-out test is performed on the tie steel mesh 6; the size of the shale sintered brick 11 is 240mm*112mm*52mm;

[0029] When the masonry reaches the middle of each floor, shale fired bricks 11 are laid on the lower surface, upper surface and side surface of the unloading eaves 8, and the weight of the shale fired bricks 11 above the unloading eaves 8 is unloaded onto the unloading eaves 8;

[0030] Step S6: clean the outer leaf wall 10, and perform grouting and spraying of protective liquid on the outer leaf wall 10; the grouting adopts a flat seam form, and the thickness of the mortar seam recessed into the outer leaf wall 10 is 8mm~10mm; the depth of the grouting is consistent.

[0031] As attached Figure 1 As shown, in the steps S1 and S2, the lightning protection mesh is connected to the main body tie bars 2, the main body vertical steel bars, the seismic steel bars 5 and the tie steel mesh 6 to form a whole, forming the functions of the seismic resistance, lightning protection and shielding network of the entire building.

[0032] Especially when used in scientific research buildings, it can realize the electrostatic shielding function of precision laboratories against external interference signals and magnetic radiation, and play a protective role in the accuracy of precision experimental instruments, electrostatic short circuits of circuit boards, and the accuracy of test data.

[0033] As attached Figure 2 As shown, in step S5, the "three-in-one" masonry method is adopted when the outer leaf wall 10 is built, and the two layers of aerated concrete blocks 4 of the inner leaf wall 3 correspond to the eight layers of shale sintered bricks 11 of the outer leaf wall 10, ensuring that the tie steel mesh 6 is accurately pressed into the mortar joints with matching positions.

[0034] During the masonry, the problem of inconsistent elevations of the horizontal mortar joints of the inner leaf wall 3 and the outer leaf wall 10 is solved by adjusting the mortar joint width.

[0035] As attached Figure 3 As shown, in the step S5, when the shale sintered bricks 11 are built to the door and window openings or the awning position, the eaves of the structure eaves 12 are built in a vertical manner, and the shale sintered bricks 11 are cut into L-shape or C-shape. When laying, the cut shale sintered bricks 11 are hung on the eaves of the structure eaves 12; the eaves are completely covered; no secondary closing is required, and the outer leaf wall 10 is decorated in a seamless manner, which is beautiful and atmospheric.

[0036] In step S5, the outer leaf wall 10 is built by horizontal or vertical laying of shale sintered bricks 11; when vertical laying is adopted, a false joint matching the shape of the mortar joint is opened on a shale sintered brick 11 at the inner corner or outer corner, and is filled with grout.

[0037] A groove with a depth of 20 mm is cut on the surface layer of the shale fired brick 11 as a false seam, and the outer leaf wall 10 after treatment is neat and beautiful.

[0038] As attached Figure 4As shown, when the outer leaf wall 10 is the outer leaf wall 10 of the scientific research building, a number of gas cylinder rooms close to the ground are built on the outer side of the outer leaf wall 10, and a triangular wall 13 arranged vertically is built on one side of the top of each gas cylinder room, and a triangular pyramid wall 14 arranged vertically is built on the other side, and the top of the triangular wall 13 and the top of the triangular pyramid wall 14 are jointly built with a U-shaped channel 15 that is close to the outer leaf wall 10 and opens to the outside; a pipe hole 17 is opened on the upper surface of the gas cylinder room.

[0039] When the triangular pyramid wall 14 is built, ordinary bricks are laid inside the triangular pyramid wall 14, and 240mm sintered shale bricks 11 are laid outside the ordinary bricks, which are integrated with the outer leaf wall 10; the oblique part of the triangular pyramid wall 14 is gradually retreated upwards and built to the bottom of the U-shaped channel 15;

[0040] The gas cylinder room is used to place inflammable and explosive gas cylinders. The pipelines of the inflammable and explosive gas cylinders are laid into each laboratory through the pipeline hole 17 and the U-shaped channel 15. When the inflammable and explosive gas cylinder explodes, the explosion shock wave is directed toward the outside of the scientific research building, ensuring the safety of the researchers in the laboratory.

[0041] During the specific implementation process, when the inner leaf wall 3 is built, the pre-buried main tie bars 2 are first straightened, and then the masonry position line of the structural base is determined according to the sizes of the aerated concrete blocks 4 and the shale sintered bricks 11; then the base is leveled with premixed mortar, and skin number rods are set on both sides of the inner leaf wall 3 to control the height direction positions of the masonry mortar joints, door and window openings, and eaves; then two layers of aerated concrete blocks 4 are built according to the positions of the skin number rods; then the galvanized steel mesh 6 is pressed into the mortar joints, and the galvanized steel mesh 6 is welded to the main tie bars 2 to form an integral structure.

[0042] In the description of the present invention, it is necessary to understand that the indicated orientation or positional relationship is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0043] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A construction method for a masonry sandwich decorative wall, characterized in that: The method is implemented by the following steps: Step S1: Casting the structural column (1), pre-embedding a plurality of main tie bars (2) arranged in a horizontal direction and evenly distributed vertically during the casting process, and welding and fixing the main tie bars (2) to the main vertical steel bars in the structural column (1); Step S2: building an inner leaf wall (3) between two structural columns (1), using aerated concrete blocks (4) as building units, and during the building process, welding and fixing the two ends of the horizontally arranged seismic steel bars (5) to the two main tie bars (2) that match the positions, and welding and fixing the horizontally arranged rectangular tie steel mesh (6) to the two main tie bars (2) that match the positions, and then building the seismic steel bars (5), the main tie bars (2) and the tie steel mesh (6) together between two adjacent layers of aerated concrete blocks (4) that match the positions; at this time, the tie steel mesh (6) exceeds the inner leaf wall (3); When the masonry reaches the middle of each floor, a ring beam (7) is cast on the aerated concrete blocks (4), and a load-relief cantilever (8) is cast on the outer side of the ring beam (7); Step S3: After the inner leaf wall (3) is completed, a plaster layer is applied to the outer side of the inner leaf wall (3) for moisture-proof and leveling treatment; Step S4: installing a heat-insulating plate (9) on the outer side of the plaster layer, fixing the top end of the heat-insulating plate (9) to the tie steel mesh (6) located on the upper side, and fixing the bottom end of the heat-insulating plate (9) to the tie steel mesh (6) located on the lower side; Step S5: building an outer leaf wall (10) on the outer side of the insulation board (9), using shale sintered bricks (11) as a building unit, and during the building process, building the tie steel mesh (6) that exceeds the inner leaf wall (3) between two adjacent layers of shale sintered bricks (11) that match each other; at this time, an air layer is left between the outer leaf wall (10) and the insulation board (9); When the masonry reaches the middle of each floor, shale fired bricks (11) are laid on the lower surface, upper surface and side surfaces of the unloading eaves (8), and the weight of the shale fired bricks (11) above the unloading eaves (8) is unloaded onto the unloading eaves (8); Step S6: cleaning the outer blade wall (10), and grouting and spraying protective liquid on the outer blade wall (10); In the steps S1 and S2, the lightning protection mesh is connected to the main body tie bars (2), the main body vertical steel bars, the seismic steel bars (5) and the tie steel mesh (6) to form a whole, so as to form the functions of the seismic resistance, lightning protection and shielding network of the entire building; When the outer leaf wall (10) is the outer leaf wall (10) of a scientific research building, a plurality of gas cylinder rooms that are close to the ground are built on the outer side of the outer leaf wall (10), and a triangular wall (13) arranged vertically is built on one side of the top of each gas cylinder room, and a triangular pyramid wall (14) arranged vertically is built on the other side, and a U-shaped channel (15) that is close to the outer leaf wall (10) and opens to the outside is built on the top of the triangular wall (13) and the top of the triangular pyramid wall (14); and a pipe hole (17) is opened on the upper surface of the gas cylinder room.

2. The construction method of a masonry-type sandwich decorative wall according to claim 1, characterized in that: In the step S5, the outer leaf wall (10) is built using a "three-in-one" building method, where two layers of aerated concrete blocks (4) of the inner leaf wall (3) correspond to eight layers of shale sintered bricks (11) of the outer leaf wall (10), ensuring that the tie steel mesh (6) is accurately pressed into the mortar joints with matching positions.

3. The construction method of a masonry-type sandwich decorative wall according to claim 1, characterized in that: In the step S5, when the shale fired bricks (11) are laid to the door and window openings or the position of the rain shelter, the shale fired bricks (11) are laid in a vertical manner at the eaves portion of the structural eaves (12), the shale fired bricks (11) are cut into L-shapes or C-shapes, and the cut shale fired bricks (11) are hung and laid at the eaves portion of the structural eaves (12) during the laying process; the eaves portion is completely covered.

4. The construction method of a masonry-type sandwich decorative wall according to claim 1, characterized in that: In step S5, the outer leaf wall (10) is built by horizontally or vertically laying shale sintered bricks (11); when the vertical laying method is adopted, a false joint matching the shape of the mortar joint is opened on a shale sintered brick (11) at the inner corner or the outer corner, and is filled with grout.

Citation Information

Patent Citations

  • Shale decoration brick and shale insulating brisk combined building clean water composite wall and combined building method

    CN103981979A

  • Connecting structure of earthenware brick curtain wall and construction method of connecting structure

    CN113585489A