An apparatus and method for preparing a precast roadway of a similar model

By designing the mold box and pull-out device, and combining jacks and hydraulic pumps, the problems of high resistance and jamming during the removal of tunnel molds in large similar models were solved, enabling the straight removal of tunnel molds and improving preparation efficiency.

CN116141470BActive Publication Date: 2025-12-12CCTEG COAL MINING RES INST +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202211538361.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-12-01
Publication Date
2025-12-12
Estimated Expiration
2042-12-01

AI Technical Summary

Technical Problem

In large, similar models, the removal resistance of the tunnel mold is relatively high, and it is easy to get stuck when the pulling direction is incorrect, making removal difficult.

Method used

The system employs a mold box, tunnel mold, and pull-out device. By using jacks and hydraulic pumps, it ensures that the tunnel mold is pulled out straight. The mold is fixed by mounting bases and clamps to reduce the risk of jamming.

Benefits of technology

The method enables the straight removal of tunnel molds, solving the difficulty of mold removal in large similar models and improving preparation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116141470B_ABST
    Figure CN116141470B_ABST
Patent Text Reader

Abstract

The application provides a preparation device and method for a similar model prefabricated roadway, comprising: a mold box, which is configured with a containing cavity and is provided with mounting holes on opposite sides; a roadway mold, which is provided through the opposite two mounting holes at two ends, and one end of the roadway mold is located outside the mold box through the corresponding mounting hole; and a pulling-out device, which comprises a mounting seat and a jack; the mounting seat is sleeved on the extending end of the roadway mold. The preparation device for the similar model prefabricated roadway provided by the application has the following advantages: the two ends of the roadway mold are provided through the opposite two mounting holes of the mold box, one end of the roadway mold is located outside the mold box through the corresponding mounting hole, the mounting seat is sleeved on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold along the extending direction of the roadway mold, and thus when the roadway mold needs to be pulled out of the mold box, the piston rod can be directly connected with the roadway mold, so that the roadway mold can be pulled out straight and does not get stuck.
Need to check novelty before this filing date? Find Prior Art

Description

TECHNICAL FIELD

[0001] The present application relates to the technical field of coal mine safety mining, in particular to a preparation device and method of a similar model precast roadway. BACKGROUND

[0002] Similar simulation test is an important means to study geotechnical engineering problems, and has the advantages of being intuitive, feasible, and convincing compared with theoretical analysis and numerical simulation, and similar model preparation is the key and difficulty of similar simulation test.

[0003] In the similar simulation research of geotechnical and coal mine engineering, the size of the similar model has a trend of large-scale. In the preparation of the similar model, the method of precasting the roadway by embedding the roadway mold (such as hollow square steel, hollow round steel), laying or pouring the model, and then removing the roadway mold is usually used. However, in a large similar model, due to the large size of the model, the contact area between the model and the roadway mold is large, and the model is bonded and compacted to the roadway mold, so the pulling-out resistance is large, and when the pulling-out direction is not correct, the model is easily stuck, so it is extremely difficult to remove the roadway mold. SUMMARY

[0004] The present application provides a preparation device and method of a similar model precast roadway to solve the problem of large resistance when removing the roadway mold, and easy to be stuck when the pulling-out direction is not correct.

[0005] The present application provides a preparation device of a similar model precast roadway, comprising:

[0006] A mold box is constructed with a receiving cavity, and the opposite side of the mold box is provided with a mounting hole;

[0007] A roadway mold is provided, and the two ends of the roadway mold are arranged in the two opposite mounting holes, wherein one end of the roadway mold passes through the corresponding mounting hole and is located outside the mold box;

[0008] A pulling-out device is provided, comprising a mounting seat and a jack; the mounting seat is sleeved on the protruding end of the roadway mold, the mounting seat is connected with the mold box, and the piston rod of the jack is retractable along the extension direction of the roadway mold and is arranged opposite to the protruding end of the roadway mold.

[0009] According to the preparation device of a similar model precast roadway provided by the present application, the pulling-out device further comprises a clamping piece and a connecting plate;

[0010] The clamping piece is provided with a mounting position, the clamping piece is connected with the mounting seat through the connecting plate, and the jack is arranged in the mounting position.

[0011] The preparation device for the similar model prefabricated roadway provided by the application comprises a connecting plate, a clamping piece and a pulling-out device.

[0012] The top end of the clamping piece is connected with the top end of the mounting seat through the first connecting plate, and the bottom end of the clamping piece is connected with the bottom end of the mounting seat through the second connecting plate.

[0013] The preparation device for the similar model prefabricated roadway provided by the application comprises a connecting plate, a clamping piece and a pulling-out device.

[0014] The preparation device for the similar model prefabricated roadway provided by the application comprises a connecting plate, a clamping piece and a pulling-out device.

[0015] A hydraulic pump, wherein an oil outlet of the hydraulic pump is communicated with the jack, and a control switch for controlling the hydraulic pump is arranged on the hydraulic pump.

[0016] The preparation device for the similar model prefabricated roadway provided by the application comprises a connecting plate, a clamping piece and a pulling-out device.

[0017] The method for pouring a model provided by the application comprises the following steps.

[0018] The roadway mold is arranged in the accommodating cavity through the mounting hole, and one end of the roadway mold is arranged outside the mold box.

[0019] Pouring is performed in the accommodating cavity.

[0020] The pulling-out device is arranged on the mold box, the mounting seat is sleeved on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected with the roadway mold.

[0021] The roadway mold is removed by using the pulling-out device, and the pulling-out device and the mold box are removed, so that a pouring model containing the roadway is constructed.

[0022] The method for pouring a model provided by the application comprises the following steps.

[0023] After the pouring model is removed, the connecting piece of the roadway mold is disassembled, the mounting seat is sleeved on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected with one side plate.

[0024] According to the method for preparing a similar model precast roadway provided by the application, the step of removing the roadway mold by using the pulling device comprises:

[0025] By operating the hydraulic pump, the piston rod of the jack is extended, and the side plates are pulled out by the jack and the hydraulic pump;

[0026] The piston rod is connected with the remaining side plates, and the remaining side plates are pulled out one by one by the jack and the hydraulic pump.

[0027] According to the method for preparing a similar model precast roadway provided by the application, the step of arranging the roadway mold in the accommodating cavity through the mounting holes further comprises:

[0028] The mold box and the roadway mold are assembled, and lubricant is applied at the contact positions of the side plates of the roadway mold.

[0029] The preparation device and method for a similar model precast roadway provided by the application, by arranging the two ends of the roadway mold in the two mounting holes of the mold box, and arranging one end of the roadway mold outside the mold box through the corresponding mounting hole, using the mounting seat to cover the extended end of the roadway mold, arranging the piston rod of the jack along the extension direction of the roadway mold, and arranging the piston rod opposite to the extended end of the roadway mold, so that when the roadway mold needs to be pulled out of the mold box, the piston rod can be directly connected with the roadway mold, thereby ensuring that the roadway mold is pulled out straight and does not get stuck, and solving the difficulty of removing the roadway mold. BRIEF DESCRIPTION OF DRAWINGS

[0030] In order to more clearly illustrate the technical solutions in the application or prior art, the following will briefly introduce the drawings needed to be used in the embodiments or prior art description. Obviously, the drawings in the following description are some embodiments of the application, and other drawings can be obtained by those skilled in the art without creative labor.

[0031] Figure 1 is a schematic diagram of the preparation device for a similar model precast roadway provided by the embodiment of the application;

[0032] Figure 2 is a schematic diagram of the mold box and the roadway mold provided by the embodiment of the application;

[0033] Figure 3 is a schematic diagram of the roadway mold provided by the embodiment of the application;

[0034] Figure 4 is a schematic diagram of the pulling device provided by the embodiment of the application;

[0035] Figure 5A flowchart of a method for preparing a similar model pre-prepared roadway by the preparation device of the present application is shown in the figure;

[0036] Figure 6 A structural diagram of a control system of a pouring method according to an embodiment of the present application is shown in the figure;

[0037] Figure 7 A structural diagram of an electronic device according to an embodiment of the present application is shown in the figure;

[0038] Reference signs:

[0039] 1, mold box; 11, mounting hole; 2, roadway mold; 21, side plate; 22, connecting piece; 3, pulling-out device; 31, mounting seat; 32, jack; 33, clamping piece; 34, first connecting plate; 35, second connecting plate; 36, supporting leg; 37, hydraulic pump; 610, control module; 710, processor; 720, communication interface; 730, memory; 740, communication bus. DETAILED DESCRIPTION

[0040] The embodiments of the present application will be further described below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present application, but cannot be used to limit the scope of the present application.

[0041] In the description of the embodiments of the present application, the terms "first", "second" are used only for the purpose of description, and cannot be understood as indicating or implying relative importance.

[0042] In the description of the embodiments of the present application, it should be noted that, unless otherwise explicitly specified and limited, the terms "connected", "connected" should be understood broadly, for example, it can be fixedly connected, or it can be detachably connected, or integrally connected; it can be mechanically connected, or it can be electrically connected; it can be directly connected, or it can be indirectly connected through an intermediate medium. For those skilled in the art, the specific meaning of the above terms in the embodiments of the present application can be understood according to the specific circumstances.

[0043] In the description of the present application, the description of the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In the present application, the illustrative description of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art can combine and combine the different embodiments or examples described in the present application and the features of the different embodiments or examples without contradiction.

[0044] The application is described below in combination with Figure 1 , Figure 2 , Figure 3 and Figure 4 , a preparation device for a similar model prefabricated roadway provided by an embodiment of the application is described, which comprises a mold box 1, a roadway mold 2 and a pulling-out device 3.

[0045] As shown in Figure 1 and Figure 2 , the mold box 1 is configured with a receiving cavity, the top of the mold box 1 is provided with an open mouth of the receiving cavity, and the opposite side of the mold box 1 is provided with a mounting hole 11, that is, two mounting holes 11 are arranged on the mold box 1, and the two mounting holes 11 are arranged oppositely.

[0046] As shown in Figures 1 to 3 , the roadway mold 2 adopts a cuboid structure, the two ends of the roadway mold 2 are arranged in the opposite two mounting holes 11, and the length of the roadway mold 2 is greater than the length of the corresponding side of the two mounting holes 11 of the mold box 1. Thus, it can be ensured that one end of the roadway mold 2 is located outside the mold box 1 through the corresponding mounting hole 11. If the roadway mold 2 is relatively long, the two ends of the roadway mold 2 can also be arranged outside the mold box 1 through the corresponding mounting holes 11.

[0047] In this embodiment, the opposite sides of the mold box 1 are provided with corresponding mounting holes 11. The mold box 1 is assembled by four side plates and two bottom plates and connected by bolts, and the mounting holes 11 of the roadway mold 2 are reserved at the designed roadway position, and the roadway mold is arranged through the mounting holes 11 and mounted on the mold box 1.

[0048] As shown in Figure 1 and Figure 4 , the pulling-out device 3 comprises a mounting seat 31 and a jack 32. The mounting seat 31 is sleeved on the protruding end of the roadway mold 2, and the mounting seat 31 is connected with the mold box 1. Thus, the mounting seat 31 can be used to limit the moving direction of the roadway mold 2 when the roadway mold 2 is supported and removed, and it can be ensured that the roadway mold is pulled out straight and does not get stuck. The piston rod of the jack 32 is telescopic along the extension direction of the roadway mold 2, and the jack 32 is arranged opposite to the protruding end of the roadway mold 2. Thus, when the roadway mold 2 is removed by using the jack 32, the stress direction of the roadway mold 2 when pulled out can be ensured, and the problem that the roadway mold 2 has a large resistance and is easily stuck when pulled out in an incorrect direction can be solved.

[0049] Specifically, in the whole process of pouring the model, after the mold box 1 and the roadway mold 2 are assembled, the roadway mold 2 is arranged in the receiving cavity through the mounting hole 11, and it is ensured that one end of the roadway mold 2 is outside the mold box 1.

[0050] After the main structure of the preparation device of the similar model prefabricated roadway is installed, the preparation device of the similar model prefabricated roadway is hoisted in the water tank, so that a large amount of water generated in the model forming process can be conveniently treated. Meanwhile, in order to ensure the flatness of the pouring model, a level meter can be placed in the mold box 1, and the level of the mold box 1 can be checked by adjusting the height of the leveling pad iron around the bottom.

[0051] After the preparation device of the similar model prefabricated roadway is completed, pouring is performed in the accommodating cavity.

[0052] The pulling-out device 3 is arranged on the mold box 1, the mounting seat 31 is sleeved on the protruding end of the roadway mold 2, the piston rod of the jack 32 is opposite to the protruding end of the roadway mold 2, and the piston rod is connected with the roadway mold 2. When the roadway mold 2 is removed by using the jack 32, the stress direction when the roadway mold 2 is pulled out can be ensured.

[0053] The pulling-out device 3 is used to remove the roadway mold 2, and after the roadway mold 2 is removed, the pulling-out device 3 and the mold box 1 are removed. Since the roadway mold 2 is pre-buried in the mold box 1 during pouring, a pouring model containing a roadway can be constructed.

[0054] The preparation device of the similar model prefabricated roadway provided by the application is characterized in that the two ends of the roadway mold 2 are arranged in the two opposite mounting holes 11 of the mold box 1, one end of the roadway mold 2 is arranged outside the mold box through the corresponding mounting hole 11, the mounting seat 31 is sleeved on the protruding end of the roadway mold 2, the piston rod of the jack 32 is telescopic along the extension direction of the roadway mold 2, and the piston rod is arranged opposite to the protruding end of the roadway mold 2. When the roadway mold 2 needs to be pulled out of the mold box, the piston rod can be directly connected with the roadway mold 2, so that the roadway mold 2 can be pulled out straight and does not get stuck, and the difficulty of removing the roadway mold 2 is solved.

[0055] In one example, as shown in Figure 1 and Figure 4 The pulling-out device 3 further includes a clamping piece 33 and a connecting plate. The clamping piece 33 is provided with a mounting position, and the specific structure of the mounting position can be set as required. The clamping piece 33 is connected with the mounting seat 31 through the connecting plate, and the jack 32 is arranged in the mounting position.

[0056] In this embodiment, the connecting plate includes a first connecting plate 34 and a second connecting plate 35 arranged at intervals. The top end of the clamping piece 33 is connected with the top end of the mounting seat 31 through the first connecting plate 34, and the bottom end of the clamping piece 34 is connected with the bottom end of the mounting seat 31 through the second connecting plate 35.

[0057] Specifically, the clamping piece 33 is divided into a first clamping piece and a second clamping piece which are buckled to each other. An installation position is configured between the first clamping piece and the second clamping piece, and the jack 32 is arranged in the installation position. The first clamping piece is connected to the top end of the mounting seat 31 through a first connecting plate 34, and the second clamping piece is connected to the bottom end of the mounting seat 31 through a second connecting plate 35. Thus, the fixing of the jack 32 can be completed by using the clamping piece 33 and the connecting plate.

[0058] Since the weight of the jack 32 is large, in order to improve the stability of the overall structure when the roadway mold 2 is pulled out, as shown in Figure 1 and Figure 4 , the pulling-out device 3 further comprises a supporting leg 36. The first end of the supporting leg 36 is connected to the second connecting plate 35 or the clamping piece 33, or the first end of the supporting leg 36 is simultaneously connected to the second connecting plate 35 and the clamping piece 33. The second end of the supporting leg 36 is used to support the ground. By arranging the supporting leg 36, on the one hand, the supporting leg 36 is used to support the roadway mold 2, and on the other hand, the jack 32 and the roadway mold 2 can be ensured to be in alignment and centered.

[0059] According to needs, the number of the supporting leg 36 can be adjusted, and one or more supporting legs 36 are arranged to further ensure the stability of the overall structure.

[0060] Based on the above embodiment, in one embodiment, as shown in Figure 1 and Figure 4 , the pulling-out device 3 further comprises a hydraulic pump 37. The oil outlet of the hydraulic pump 37 is communicated with the jack 32, and the hydraulic pump 37 is provided with a control switch for controlling the hydraulic pump. Thus, the movement of the piston rod in the jack 32 can be controlled by the hydraulic pump 37, and the jack 32 is used to move the roadway mold 2 out of the mold box 1.

[0061] Based on the above embodiment, in one embodiment, as shown in Figure 3 , the roadway mold 2 comprises a plurality of side plates 21 and connecting pieces 22. The plurality of side plates 21 are sequentially spliced to form an internally hollow roadway cavity, and adjacent side plates 21 are fixed through the connecting pieces 22.

[0062] Among them, the side plate 21 can adopt a steel plate, and the assembled roadway mold 2 is spliced by four steel plates, and the adjacent steel plates are firmly connected to each other through the connecting pieces 22 and bolts at the joint positions of the adjacent steel plates. The connecting piece 22 is a cuboid steel block, two bolt holes are respectively formed on two faces of the connecting piece 22, and the adjacent steel plates are firmly connected through the connecting piece 22 and the bolts at the joint positions of the adjacent steel plates. Four connecting pieces 22 are respectively arranged at the two ends of the roadway mold.

[0063] The present application also proposes a method for pouring a mold of a preparation device for a similar model prefabricated roadway, and the structure of the preparation device for the similar model prefabricated roadway is as shown in Figures 1 to 4 .

[0064] The method of pouring the model comprises the following steps as shown in the figure: Figure 5

[0065] Step S501: The roadway mold is arranged in the accommodating cavity through the installation hole, and one end of the roadway mold is ensured to be outside the mold box.

[0066] After the mold box and the roadway mold are assembled, the roadway mold is arranged in the accommodating cavity through the installation hole, and one end of the roadway mold is ensured to be outside the mold box.

[0067] After the main structure of the whole similar model precast roadway preparation device is installed, the similar model precast roadway preparation device is hoisted in the water tank to facilitate the processing of a large amount of water precipitated in the model forming process. At the same time, in order to ensure the flatness of the pouring model, a level meter can be placed on the mold box, and the height of the leveling pad iron around the bottom is adjusted to check the levelness of the mold box.

[0068] Step S502: Pouring in the accommodating cavity.

[0069] After the setting of the similar model precast roadway preparation device is completed, pouring is performed in the accommodating cavity. The pouring raw materials include solid materials and liquid materials. The solid materials include aggregate talcum powder and solidifying agent sodium fluorosilicate, and the liquid material is cementing material water glass.

[0070] Step S503: The pulling-out device is arranged on the mold box, the mounting seat sleeve is arranged on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected to the roadway mold.

[0071] The pulling-out device is arranged on the mold box, the mounting seat sleeve is arranged on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected to the roadway mold. When the roadway mold is removed by using the jack, the stress direction of the roadway mold when pulled out can be ensured.

[0072] Step S504: The roadway mold is removed by using the pulling-out device, and the pulling-out device and the mold box are removed to construct the pouring model containing the roadway.

[0073] The roadway mold is removed by using the pulling-out device, and after the roadway mold is removed, the pulling-out device and the mold box are removed. Since the roadway mold is pre-embedded in the mold box during pouring, the pouring model containing the roadway can be constructed.

[0074] ​The method for pouring a model provided by the embodiment of the present application comprises the following steps: the two ends of the roadway mold are arranged in the two mounting holes of the mold box, one end of the roadway mold is arranged outside the mold box through the corresponding mounting hole, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged in the extending direction of the roadway mold, and the extending end of the roadway mold is arranged opposite to the piston rod, so that the piston rod can be directly connected with the roadway mold when the roadway mold needs to be pulled out of the mold box, and the roadway mold can be pulled out straight and cannot be stuck, thereby solving the difficulty in removing the roadway mold.

[0075] Based on the above embodiment, in one embodiment, the pulling-out device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the step of connecting the piston rod with the roadway mold comprises the following steps: after the mold is removed, the connecting piece of the assembled side plate of the roadway mold is removed, the mounting seat is arranged on the extending end of the roadway mold, and the piston rod of the jack is connected with one side plate.

[0076] Specifically, after the mold is removed, the connecting piece of the assembled side plate of the roadway mold is removed, the roadway mold is divided into four independent side plates, but the form is still an integral whole. The mounting seat is arranged on the extending end of the roadway mold, the mounting seat is firmly connected with the mold box through bolts, the supporting legs are fixed, the jack and the roadway mold are ensured to be in the same horizontal plane and be centered, and the piston rod is connected with one side plate.

[0077] Based on the above embodiment, in one embodiment, the step of removing the roadway mold by using the pulling-out device comprises the following steps: the piston rod of the jack is extended by operating the hydraulic pump, and the side plate is pulled out by the jack and the hydraulic pump; the piston rod is connected with the remaining side plates, and the remaining side plates are pulled out one by one by the jack and the hydraulic pump.

[0078] Specifically, the piston rod of the jack is extended by operating the hydraulic pump, one side plate is connected with the piston rod, and the side plate is pulled out by the hydraulic pump and the jack. After one side plate is pulled out, the remaining side plates are connected with the piston, and the remaining side plates are pulled out one by one by the jack and the hydraulic pump. After the roadway mold is removed, the pulling-out device and the mold box are removed, the roadway mold is pre-embedded in the mold box during pouring, and thus a pouring model containing a roadway can be constructed.

[0079] Based on the above embodiment, in one embodiment, the roadway mold is arranged in the accommodating cavity through the mounting hole, and before ensuring that one end of the roadway mold is outside the mold box, the following steps are further included: the mold box and the roadway mold are assembled, and lubricant is applied at the contact positions of the side plates of the roadway mold.

[0080] Specifically, before setting the roadway mold, the mold box is assembled first, and butter is applied on the side wall of the mold box to increase the lubrication of the mold box and reduce the difficulty of disassembly. Then the roadway mold is assembled, and butter is applied on the contact position of each side plate of the roadway mold to increase the lubrication of the roadway mold and reduce the difficulty of disassembly.

[0081] In one specific embodiment, the pouring model containing the roadway pouring process includes the following steps: (1) assembling the mold box. (2) After the mold box is assembled, the roadway mold is assembled through the connecting piece and the bolt, butter is applied on the contact position of the steel plate in the roadway mold to increase the lubrication. (3) The assembled roadway mold is installed through the installation hole of the large mold box, and it is ensured that the roadway mold has a certain amount of extension outside the mold box. (4) The large mold box is laid or poured into the model, and the assembled roadway mold is buried in the model. (5) After the pouring model can be disassembled, the connecting piece of the assembled roadway mold is removed, and the roadway mold is disassembled into four independent steel plates, but it is still a whole in form. (6) The roadway mold is pulled out of the device through the installation seat on the exposed end of the roadway mold, the installation seat and the mold box are firmly connected through the bolt, the support leg is fixed, and it is ensured that the jack and the roadway mold are flush and centered. (7) The piston rod of the jack is extended by operating the hydraulic pump, one of the steel plates of the roadway mold is connected with the piston rod of the jack through the mechanical structure, and the steel plate is pulled out through the hydraulic pump. (8) Repeat step 6 to pull out the steel plates of the roadway mold one by one. (9) Remove the pull-out device to construct the pouring model containing the roadway.

[0082] The control system of the pouring method provided by the embodiment of the application is described below, and the control system of the pouring method described below can be correspondingly referred to the method described above.

[0083] As shown in Figure 6 The control system of the pouring method includes a control module 610.

[0084] The control module 610 is used to set the roadway mold in the accommodation cavity through the installation hole, to ensure that one end of the roadway mold is outside the mold box; to pour in the accommodation cavity; to set the pull-out device on the mold box, to set the installation seat on the extension end of the roadway mold, to arrange the piston rod of the jack opposite to the extension end of the roadway mold, and to connect the piston rod with the roadway mold; to disassemble the roadway mold by using the pull-out device, and to disassemble the pull-out device and the mold box to construct the pouring model containing the roadway.

[0085] Figure 7 An example of a schematic diagram of the physical structure of an electronic device is shown in Figure 7As shown, the electronic device can include a processor 710, a communications interface 720, a memory 730 and a communications bus 740, wherein the processor 710, the communications interface 720 and the memory 730 complete the communication among each other through the communications bus 740. The processor 710 can call the logical instructions in the memory 730 to execute the method, which includes: arranging the roadway mold through the mounting hole in the accommodating cavity, ensuring that one end of the roadway mold is outside the mold box; pouring in the accommodating cavity; arranging the pulling-out device on the mold box, arranging the seat sleeve at the protruding end of the roadway mold, arranging the piston rod of the jack opposite to the protruding end of the roadway mold, and connecting the piston rod and the roadway mold; and removing the roadway mold by using the pulling-out device, and removing the pulling-out device and the mold box to construct the pouring model containing the roadway.

[0086] It should be noted that the electronic device in the embodiment can be a server, a PC or other devices, as long as it includes the processor 710, the communications interface 720, the memory 730 and the communications bus 740 as shown in the structure, wherein the processor 710, the communications interface 720 and the memory 730 complete the communication among each other through the communications bus 740, and the processor 710 can call the logical instructions in the memory 730 to execute the above method. Figure 7 As shown, the electronic device can include a processor 710, a communications interface 720, a memory 730 and a communications bus 740, wherein the processor 710, the communications interface 720 and the memory 730 complete the communication among each other through the communications bus 740. The processor 710 can call the logical instructions in the memory 730 to execute the method, which includes: arranging the roadway mold through the mounting hole in the accommodating cavity, ensuring that one end of the roadway mold is outside the mold box; pouring in the accommodating cavity; arranging the pulling-out device on the mold box, arranging the seat sleeve at the protruding end of the roadway mold, arranging the piston rod of the jack opposite to the protruding end of the roadway mold, and connecting the piston rod and the roadway mold; and removing the roadway mold by using the pulling-out device, and removing the pulling-out device and the mold box to construct the pouring model containing the roadway.

[0087] In addition, the logical instructions in the memory 730 can be implemented in the form of a software functional unit and sold or used as an independent product, which can be stored in a computer readable storage medium. Based on such understanding, the technical solutions of the present application essentially or the part that contributes to the prior art or part of the technical solutions can be embodied in the form of a software product. The computer software product is stored in a storage medium, including a plurality of instructions to make a computer device (which can be a personal computer, a server, or a network device, etc.) execute all or part of the steps of the method described in the embodiments of the present application. The foregoing storage medium includes: a U disk, a mobile hard disk, a read-only memory (ROM, Read-Only Memory), a random access memory (RAM, Random Access Memory), a magnetic disk or an optical disk, and various program code storage media.

[0088] Further, the embodiment of the present application discloses a computer program product, the computer program product comprises a computer program stored on a non-transitory computer readable storage medium, the computer program comprises program instructions, when the program instructions are executed by a computer, the computer can execute the method provided by the above-mentioned method embodiments, the method comprises: setting the roadway mold through the mounting hole in the accommodating cavity, ensuring that one end of the roadway mold is outside the mold box; pouring in the accommodating cavity; setting the pulling device on the mold box, the mounting seat is arranged on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected with the roadway mold; the roadway mold is removed by using the pulling device, and the pulling device and the mold box are removed, so as to construct the pouring model containing the roadway.

[0089] In another aspect, the embodiment of the present application also provides a non-transitory computer readable storage medium, which stores a computer program, and the computer program is executed by a processor to implement the method provided by the above-mentioned embodiments, the method comprises: setting the roadway mold through the mounting hole in the accommodating cavity, ensuring that one end of the roadway mold is outside the mold box; pouring in the accommodating cavity; setting the pulling device on the mold box, the mounting seat is arranged on the protruding end of the roadway mold, the piston rod of the jack is opposite to the protruding end of the roadway mold, and the piston rod is connected with the roadway mold; the roadway mold is removed by using the pulling device, and the pulling device and the mold box are removed, so as to construct the pouring model containing the roadway.

[0090] The device embodiments described above are only schematic, wherein the units illustrated as separate components may or may not be physically separate, and the components illustrated as units may or may not be physical units, i.e., may be located in one place or may be distributed on a plurality of network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the embodiment. Those skilled in the art can understand and implement without creative labor.

[0091] Those skilled in the art can clearly understand the method for implementing the embodiments by means of software and necessary universal hardware platforms from the above description of the embodiments, and of course, the method can also be implemented by hardware. Based on such understanding, the above technical solutions can be embodied in the form of a software product, which can be stored in a computer readable storage medium, such as a ROM / RAM, a magnetic disk, an optical disk, etc., and includes a plurality of instructions for causing a computer device (which can be a personal computer, a server, or a network device, etc.) to execute the methods described in the embodiments or some parts of the embodiments.

[0092] It should be pointed out finally that the above embodiments are only used to illustrate the technical solutions of the present application, but not to limit the same; and although the present application has been described in detail with reference to the foregoing embodiments, it should be appreciated by those skilled in the art that the technical solutions recorded in the foregoing embodiments can be modified, or some technical features thereof can be replaced equivalently; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application.

Claims

1. A method for preparing a model for casting a model for a similar model precast roadway, characterized in that, The preparation device of the similar model precast roadway comprises: A mold box is configured with a receiving cavity, and opposite sides of the mold box are provided with mounting holes; A roadway mold is arranged at two ends of the roadway mold and is arranged in the two mounting holes, and one end of the roadway mold is arranged outside the mold box through the corresponding mounting hole; A pulling device comprises a mounting seat and a jack, the mounting seat is arranged on the extending end of the roadway mold, the mounting seat is connected with the mold box, and the piston rod of the jack is arranged opposite to the extending end of the roadway mold along the extending direction of the roadway mold; the pulling device further comprises a clamping piece and a connecting plate, the clamping piece is provided with a mounting position, the clamping piece is connected with the mounting seat through the connecting plate, and the jack is arranged in the mounting position; the connecting plate comprises a first connecting plate and a second connecting plate arranged at intervals, the top end of the clamping piece is connected with the top end of the mounting seat through the first connecting plate, and the bottom end of the clamping piece is connected with the bottom end of the mounting seat through the second connecting plate; The method comprises: The roadway mold is arranged in the receiving cavity through the mounting hole, and one end of the roadway mold is arranged outside the mold box; Pouring is carried out in the receiving cavity; The pulling device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with the roadway mold; The roadway mold is removed by using the pulling device, and the pulling device and the mold box are removed to form a pouring model comprising a roadway.

2. The method of claim 1, wherein the model is casted by using a similar model precast tunnel manufacturing device. The pulling device further comprises a supporting leg, one end of the supporting leg is connected with the second connecting plate and / or the clamping piece, and the other end of the supporting leg is used for supporting the ground.

3. The method of preparing a model for a similar model precast roadway according to claim 1 or 2, wherein, The pulling device further comprises: A hydraulic pump, an oil outlet of the hydraulic pump is communicated with the jack, and a control switch for controlling the hydraulic pump is arranged on the hydraulic pump.

4. The method of claim 1 or 2, wherein the method is characterized by, The roadway mold comprises a plurality of side plates and connecting pieces, a plurality of the side plates are sequentially connected to form an internal hollow roadway cavity, and adjacent side plates are fixed through the connecting pieces.

5. The method of casting a model of claim 1, wherein, The pulling device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with the roadway mold. After the pouring model is removed, the connecting pieces of the roadway mold are disassembled, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with one of the side plates.

6. The method of casting a model according to claim 5, wherein, The pulling device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with the roadway mold. The pulling device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with the roadway mold. The pulling device is arranged on the mold box, the mounting seat is arranged on the extending end of the roadway mold, the piston rod of the jack is arranged opposite to the extending end of the roadway mold, and the piston rod is connected with the roadway mold.

7. The method of casting a model of claim 1, wherein, The step of setting the gallery mold in the accommodating cavity through the mounting hole, ensuring that one end of the gallery mold is outside the mold box, further comprises: Assembling the mold box and the gallery mold, and smearing lubricant at the contact position of each side plate of the gallery mold.

Citation Information

Patent Citations

  • Preparation method of glass fiber reinforced plastic-fiber reinforced concrete composite pipe

    CN104401019A