A pile driver
By integrating intelligent positioning mechanism, swing adjustment mechanism, rotary mechanism, submerged drilling mechanism and clamping mechanism in the pile driver, the problems of large construction errors, large safety hazards of artificial pile support and single functions are solved, and efficient and accurate pile driving construction is achieved.
Patent Information
- Application Number
- CN202310279020.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-21
- Publication Date
- 2025-04-01
- Estimated Expiration
- 2043-03-21
AI Technical Summary
The existing pile driver has large construction errors, large safety hazards for artificial pile support, single function, and cannot adapt to multiple working conditions, which affects the accuracy and efficiency of construction.
A pile driver including an intelligent positioning mechanism, a swing adjustment mechanism, a slewing mechanism, a submersible drilling mechanism and a clamping mechanism are designed. Through these technical means, precise control of the pile driving angle and position is achieved, fine adjustment is adapted to different working conditions, and pile driving and drilling are integrated.
It improves the accuracy and efficiency of pile driving construction, reduces the safety hazards of manual pile support, has a wide range of application and simple operation, reduces the number of construction equipment, and improves the construction progress.
Smart Images

Figure CN116289926B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pile-driving machinery, and in particular to a pile driver. Background Art
[0002] A pile driver is a pile-driving machine that uses impact force to penetrate piles into the ground. Pile drivers are widely used in pile foundation structures such as highway guardrails, water conservancy, post and telecommunications, and construction.
[0003] The existing pile drivers need to rely on manual experience to judge the angle and position of the piles during the piling construction process, resulting in large construction errors, insufficient pile driving accuracy, and great safety hazards due to manual pile support. The pile drivers have a single function, and when constructing on roadbeds of different hardness or when pile pulling operations are required, it is difficult to complete the piling construction directly, and other equipment is required to assist in piling. The work process is cumbersome, and a large number of construction equipment are introduced again, especially when the working space is relatively small, which seriously affects the construction progress.
[0004] Therefore, it is necessary to develop a pile driver that can meet the current diverse pile driving conditions to improve the efficiency of pile driving construction. Summary of the invention
[0005] 1. Technical issues to be resolved
[0006] In view of the above-mentioned shortcomings and deficiencies of the prior art, the present invention provides a pile driver, which solves the technical problems that the existing pile drivers have large construction errors, great safety hazards of manual pile support, single function, and cannot adapt to various working conditions, thus affecting construction accuracy and efficiency.
[0007] (II) Technical solution
[0008] In order to achieve the above object, the main technical solutions adopted by the present invention include:
[0009] In a first aspect, an embodiment of the present invention provides a pile driver,
[0010] It includes a locomotive, a boom assembly, a positioning mechanism, a hammering mechanism, a clamping mechanism and a swing adjustment mechanism, wherein the boom assembly is installed on the platform of the locomotive, the boom assembly extends parallel to the plane where the platform is located, and the positioning mechanism is arranged at one end of the boom assembly; the hammering mechanism is arranged on the side of the boom assembly away from the locomotive; the clamping mechanism is arranged on one side of the hammering mechanism and connected to the boom assembly, and is used to clamp the pile body; the hammering mechanism can hammer the pile body along the boom assembly in the direction away from the positioning mechanism; the swing adjustment mechanism is hinged inside the boom assembly, and under the instruction of the positioning mechanism, the adjustment mechanism drives the hammering mechanism and the clamping mechanism through the boom assembly to simultaneously pitch and swing relative to the plane where the platform is located, or, swing to both sides of the first plane relative to it; wherein, the first plane is the plane where the pitch trajectories of the hammering mechanism and the clamping mechanism are located.
[0011] Optionally, in the pile driver, the boom assembly includes a first hinge shaft and a second hinge shaft, the first hinge shaft is perpendicular to the first plane and passes through the inside of the boom assembly; the second hinge shaft is located in the first plane and passes through the inside of the boom assembly; the swing adjustment mechanism includes a pitch adjustment component and a yaw adjustment component, the pitch adjustment component drives the hammer mechanism and the clamping mechanism to swing around the first hinge shaft by telescoping; the yaw adjustment component drives the hammer mechanism and the clamping mechanism to swing around the second hinge shaft by telescoping.
[0012] Optionally, the pile driver further includes a slewing mechanism, which is disposed between the boom assembly and the locomotive, and the slewing mechanism can drive the hammering mechanism and the clamping mechanism to rotate relative to itself through the boom assembly.
[0013] Optionally, the pile driver also includes a down-the-hole drilling mechanism, which is parallel to the hammering mechanism and is arranged on a side of the boom assembly away from the locomotive; the down-the-hole drilling mechanism includes a drilling drive assembly and a down-the-hole hammer in sequence along a direction away from the positioning mechanism, and one end of the down-the-hole hammer is connected to the drilling drive assembly.
[0014] Optionally, the pile driver and the down-the-hole drilling mechanism further include a dust catching mechanism, wherein the dust catching mechanism is connected to the boom assembly and sleeved on the free end of the down-the-hole hammer.
[0015] Optionally, in the pile driver, the clamping mechanism includes a bracket, a guide block, a jaw plate, a clamping drive and a swinging drive, wherein one end of the bracket is connected to the arm assembly, and the other end is connected to the guide block; the clamping drive and the swinging drive are arranged on the bracket; the jaw plate is hinged at the free end of the clamping drive; the clamping drive drives the jaw plate to move closer to or away from the guide block for clamping or loosening the pile body; the clamping surface formed by the guide block and the jaw plate is perpendicular to the hammering mechanism; the swinging drive drives the adjustment of the distance between the clamping mechanism and the hammering mechanism.
[0016] Optionally, in the pile driver, the hammering mechanism includes a limiter, and the limiter includes a limit bracket, an adjusting bolt assembly and a guide roller assembly, the limit bracket is an arc structure, both ends of the arc structure are connected to one end of the hammering mechanism away from the positioning mechanism, the plane where the arc structure is located is perpendicular to the hammering mechanism, and the hollow area inside the arc structure is for the pile body to pass through; the adjusting bolt assembly is arranged along the radial direction of the arc structure and distributed on the outer periphery of the arc structure; the guide roller assembly is distributed inside the arc structure along the circumference of the arc structure; the adjusting bolt assembly moves radially along the arc structure to contact the guide roller assembly to adjust the radial reciprocating movement of the guide roller assembly along the arc structure.
[0017] Optionally, the pile driver further includes a pile pulling mechanism; the pile pulling mechanism includes a pile pulling bracket, a lever and a pulling tool; the hammering mechanism further includes a pile driving hammer and a hammer cover; one end of the pile pulling bracket is connected to the side wall of the hammer cover, and the other end is hinged to the middle part of the lever; one end of the lever is detachably clamped to the hammering surface of the pile driving hammer, and the other end is hinged to the pulling tool; the pulling tool is used to fix the pile body to be pulled.
[0018] Optionally, in the pile driver, the pile driving hammer is a hydraulic silent hammer, and the hammering mechanism further includes a sound insulation cover, wherein the sound insulation cover is connected to an end of the hammer cover away from the positioning mechanism.
[0019] Optionally, the positioning mechanism of the pile driver is a radar antenna, which cooperates with a positioning system arranged on the locomotive to control the swing adjustment mechanism to adjust the piling position and angle.
[0020] (III) Beneficial effects
[0021] The beneficial effects of the present invention are as follows: compared with the prior art, the pile driver of the present invention adopts an intelligent positioning mechanism to accurately locate the piling point and the piling angle, and can control the swing adjustment mechanism to adaptively fine-tune the boom assembly according to different construction conditions, thereby adjusting the angle and position of the hammering mechanism and the down-the-hole drilling mechanism on the boom assembly to ensure the accuracy of the position and direction of piling and drilling; at the same time, the slewing mechanism can be used to drive the boom assembly and the hammering mechanism and the down-the-hole drilling mechanism thereon to rotate significantly, so as to realize construction operations at different positions when the locomotive is stationary or the construction space is limited.
[0022] With the clamping mechanism and limiter, the verticality of piling is guaranteed. The clamping mechanism and limiter can be fine-tuned according to the shape and size of different piles, making them more adaptable. At the same time, the pile driver replaces manual pile support, reducing the labor intensity of operators and improving their operating safety.
[0023] The dual-mechanism integrated design of down-the-hole drilling mechanism and hammering mechanism combines drilling and piling in one. It can be applied to a variety of piling methods and cope with piling work on a variety of roadbed sections, getting rid of the limitations of roadbed conditions. It is easy to operate, saves work time, and has a wide range of applications.
[0024] A pile pulling mechanism is arranged on one side of the hammering mechanism, and the pile pulling operation is realized by utilizing the lever principle and the action of the pile hammer, thereby improving the space utilization rate of the equipment and making the operation simple and efficient.
[0025] The hammering mechanism uses a hydraulic silent hammer and an integrated sound insulation device to effectively reduce the noise generated by hammering construction; the down-the-hole drilling mechanism adopts a dust collection mechanism to significantly reduce dust at the drilling site, making the entire machine efficient and environmentally friendly. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a front view schematic diagram of the overall structure of a pile driver in Embodiment 1 of the present invention;
[0027] Figure 2 for Figure 1 A schematic diagram of the overall structure of the pile driver from above;
[0028] Figure 3 for Figure 1 The left side schematic diagram of the overall structure of the pile driver;
[0029] Figure 4 for Figure 1 The overall structural diagram of the clamping mechanism structure of the pile driver;
[0030] Figure 5 for Figure 4 The schematic diagram of the overall structure of the clamping mechanism is from the right;
[0031] Figure 6 for Figure 2 The overall structural diagram of the stopper of the pile driver;
[0032] Figure 7 for Figure 2 Schematic diagram of the overall structure of the pile pulling mechanism of the pile driver.
[0033] [Description of Reference Numerals]
[0034] 1: Boom assembly; 11: First articulated axis; 12: Second articulated axis; 2: Positioning mechanism; 3: Hammering mechanism; 31: Stopper; 311: Limiting bracket; 32: Adjusting bolt assembly; 33: Guide roller assembly; 34: Pile hammer; 35: Hammer cover; 36: Soundproof cover; 37: Chain; 38: Sprocket tightening mechanism; 39: Guide roller support frame; 4: Clamping mechanism; 41: Bracket; 42: Guide block; 43: Jaw plate; 44: Clamping drive ; 45: swing drive member; 5: swing adjustment mechanism; 51: pitch adjustment assembly; 52: yaw adjustment assembly; 6: rotation mechanism; 7: down-the-hole drilling mechanism; 71: drilling drive assembly; 72: down-the-hole hammer; 73: dust collection mechanism; 74: drill rod; 8: pile pulling mechanism; 81: pile pulling bracket; 82: lever; 83: puller; 84: chain; a: first pitch angle; b: second pitch angle; c: first yaw angle; d: second yaw angle. DETAILED DESCRIPTION
[0035] In order to better explain the present invention and facilitate understanding, the present invention is described in detail below in conjunction with the accompanying drawings through specific embodiments. Figure 1 The orientation is used as a reference.
[0036] A pile driver proposed in an embodiment of the present invention adopts an intelligent positioning mechanism to accurately locate the piling point and the piling angle. According to different construction conditions, the swing adjustment mechanism can be controlled to adaptively fine-tune the boom assembly, thereby adjusting the angle and position of the hammering mechanism and the down-the-hole drilling mechanism on the boom assembly to ensure the accuracy of the position and direction of piling and drilling. At the same time, the slewing mechanism can be used to drive the boom assembly and the hammering mechanism and the down-the-hole drilling mechanism thereon to rotate significantly, so as to realize construction operations at different positions when the locomotive is stationary or the construction space is limited. The pile driver solves the technical problems of large construction errors of existing pile drivers, great safety hazards of manual pile support, single function of pile drivers, and inability to adapt to various working conditions, which affects construction accuracy and efficiency.
[0037] In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.
[0038] Embodiment 1:
[0039] Reference Figure 1 and Figure 2 The present embodiment provides a pile driver, including a locomotive, a boom assembly 1, a positioning mechanism 2, a hammering mechanism 3, a clamping mechanism 4 and a swing adjustment mechanism 5; the boom assembly 1 is used to install the positioning mechanism 2, the hammering mechanism 3, the clamping mechanism 4 and the swing adjustment mechanism 5 on the working platform of the locomotive. When not working, the boom assembly 1 is parallel to the working platform as a whole, firstly to realize the supporting function, and secondly to realize the driving function when working, that is, the boom assembly 1 can be a Z-folding shape or other shapes that are convenient for telescopic changes; the hammering mechanism 3 is fixed on the boom assembly 1 along the side of the boom assembly 1 away from the working platform of the locomotive, and the hammering mechanism 3 mainly includes a support frame (not shown in the figure), a pile hammer 34, a hammer cover 35, a chain 37 and a sprocket tightening mechanism 38, wherein the support frame ( The chain 37 is arranged on the support frame (not shown in the figure) and can roll along the support frame. The sprocket tightening mechanism 38 is used to adjust the tightness of the chain 37 in real time to ensure the normal operation of the chain 37. The pile hammer 34 is arranged in the support frame (not shown in the figure) through the chain 37. The chain 37 drives the pile hammer 34 to perform a hammering-retracting cycle operation toward one end of the boom assembly 1 under power drive. The pile hammer 34 performs hammering construction along the boom assembly 1. The hammer cover 35 is sleeved on the outer periphery of the pile hammer 34 and is slidably connected to the support frame (not shown in the figure). The hammer cover 35 moves with the pile hammer 34 to limit the pile hammer 34 from moving along a predetermined track to prevent the pile hammer 34 from swinging at will.
[0040] In order to cooperate with the pile hammer 34 to drive the pile, replace manual pile support, improve the efficiency of pile driving, and avoid the occurrence of safety accidents, a dedicated clamping mechanism 4 is set on one side of the hammering mechanism 3. The clamping mechanism 4 is fixed on the arm assembly 1 and is used to clamp the pile body. When the pile hammer is driving the pile, it plays a role in replacing manual pile support and improves the accuracy of the pile position.
[0041] The swing adjustment mechanism 5 is hinged inside the boom assembly 1, and its main function is to adjust the telescopic changes of the boom assembly 1, thereby driving the hammering mechanism 3 and the clamping mechanism 4 to swing, and then the position of the hammering mechanism 3 can be flexibly adjusted according to the actual working conditions to ensure the accuracy of the piling position and angle; at the same time, the swing adjustment mechanism 5 is hinged inside the boom assembly 1, which ensures the realization of the adjustment function while also streamlining the overall structure of the equipment and saving space.
[0042] The positioning mechanism 2 is arranged at one end of the boom assembly 1, and its position is opposite to the hammering direction of the pile hammer 34. The positioning mechanism 2 is a radar antenna. The radar antenna feeds back positioning information to the on-board positioning system arranged on the locomotive, and draws a pile position map through a computer to achieve accurate positioning of the piling point. Then, a command is issued through the computer to control the swing adjustment mechanism 5 to adjust the piling position and angle of the hammering mechanism 3 through the boom assembly 1. The entire positioning process is intelligent, convenient and accurate.
[0043] Reference Figure 1 and Figure 3 In order to accurately adjust the position of the beating mechanism 3, the arm assembly 1 is provided with a first hinge shaft 11 and a second hinge shaft 12, and the first hinge shaft 11 is perpendicular to the second hinge shaft 12; the swing adjustment mechanism 5 is provided with a pitch adjustment component 51 and a yaw adjustment component 52, and the pitch adjustment component 51 drives the beating mechanism 3 and the clamping mechanism 4 to pitch and swing relative to the locomotive platform around the first hinge shaft 11 through its own telescopic movement, such as Figure 1 As shown, the beating mechanism 3 and the clamping mechanism 4 can realize a continuous large rotation of the second pitch angle b, so as to push the beating mechanism 3 to a vertical state and enter a working state. Then, if it is necessary to further tilt up, the first pitch angle a can be further tilted up under the action of the pitch adjustment component 51, wherein the first pitch angle a is a maximum of 10°, and the second pitch angle b is a maximum of 87°. In this process, fine adjustment of any angle can be performed according to the working conditions. In addition, the yaw adjustment component 52 drives the beating mechanism 3 and the clamping mechanism 4 to swing around the second hinge shaft 12 through its own telescopic movement, as shown in FIG. Figure 3As shown, the hammering mechanism 3 and the clamping mechanism 4 can realize left and right lateral swing, swinging to the left by a first swing angle c, and swinging to the right by a second swing angle d, and the maximum values of the first swing angle c and the second swing angle d are both 10°; in this way, under the instruction of the positioning mechanism 2, the pitch adjustment component 51 and the swing adjustment component 52 can perform adaptive fine-tuning on the hammering mechanism 3 and the clamping mechanism 4 from four directions, for example: when the surface of the pile driving roadbed is inclined by 8°, in order to achieve pile driving in the vertical direction, the second pitch angle b can be adjusted to 82° by the pitch adjustment component 51, so that the hammering mechanism 3 can pile in the vertical direction; when it is necessary to adjust the hammering mechanism 3 to deviate 3° to the left, the first swing angle c can be adjusted to 3° by the swing adjustment component 52; and the needs of the two directions can be met at the same time to meet the needs of pile driving in different directions, thereby ensuring the accuracy of the orientation of the hammering mechanism 3 and improving the overall adaptability of the equipment for use in a variety of different working conditions.
[0044] Among them, the pitch adjustment component 51 and the yaw adjustment component 52 are both telescopic cylinders, and each component can work with a single cylinder alone or with multiple cylinders; at the same time, the telescopic cylinder can also be other structures with similar functions, which are not specifically limited here.
[0045] Reference Figure 1 and Figure 2 In order to further enhance the azimuth adjustment function of the pile driver, a slewing mechanism 6 is arranged between the boom assembly 1 and the locomotive, the slewing mechanism 6 is fixed on the locomotive, and then the boom assembly 1 is installed on the upper side of the slewing mechanism 6, the slewing mechanism 6 drives the boom assembly 1 to complete the slewing action through its own rotation, and can rotate to both sides of the locomotive respectively, and the rotation to one side of the locomotive can achieve a maximum rotation of 90°, that is, the slewing mechanism 6 can drive the hammering mechanism 3 and the clamping mechanism 4 to rotate relative to itself through the boom assembly 1; in this way, it is not only conducive to accurately adjusting the position of the hammering mechanism 3, but also when the locomotive is inconvenient to move or the construction space is limited, it can expand the construction range of the pile driver to a certain extent, and improve the overall flexibility of the equipment.
[0046] Reference Figure 1 and Figure 2In order to further expand the application scope of the pile driver, a down-the-hole drilling mechanism 7 is arranged on the arm assembly 1 in parallel with the hammer mechanism 3. The down-the-hole drilling mechanism 7 is used when the roadbed is relatively hard and it is difficult to directly pile. For example, when the roadbed contains a lot of stone, the down-the-hole drilling mechanism 7 is used to drill holes first, and then the hammer mechanism 3 is used to pile. The down-the-hole drilling mechanism 7 includes a drilling drive assembly 71 and a down-the-hole hammer 72 in sequence along the direction away from the positioning mechanism 2. The drilling drive assembly 71 and the down-the-hole hammer 72 are connected to the down-the-hole hammer through a drill rod 74. 72 is connected, and the drilling drive assembly 71 includes a rotating power part (not shown in the figure) and an impact power part (not shown in the figure). The rotating power part provides rotational power for the down-the-hole hammer 72, and the impact power part provides impact power for the down-the-hole hammer 72, so that the down-the-hole hammer 72 completes the drilling work under the combination of rotation and impact; in addition, the positioning process of the down-the-hole drilling mechanism 7 is the same as the positioning process of the hammering mechanism 3, and the switching between the down-the-hole drilling mechanism 7 and the hammering mechanism 3 is completed by the cooperation of the swing adjustment mechanism 5 and the rotary mechanism 6, which will not be repeated here.
[0047] Reference Figure 1 and Figure 2 In order to prevent the down-the-hole drilling mechanism 7 from generating dust during the drilling process, a dust collecting mechanism 73 is sleeved on the working end of the down-the-hole hammer 72. The dust collecting mechanism 73 is connected to the arm assembly 1. The dust collecting mechanism 73 can be a simple dust collecting hood or an integrated device with an additional water pump, a water tank and a nozzle. The water pump pumps water from the water tank to the dust collecting hood, and sprays it out in an atomized form through the nozzle to achieve the purpose of dust reduction, thereby improving the environmental protection of the equipment.
[0048] Reference Figure 4 and Figure 5 In order to further improve the automation and universality of the clamping mechanism 4, the clamping mechanism 4 is provided with a bracket 41, a guide block 42, a jaw plate 43, a clamping drive 44 and a swinging drive 45; one end of the bracket 41 is connected to the arm assembly 1, and the other end of the bracket 41 is connected to the guide block 42, and the guide block 42 is used to provide a holding space for the pile body; the clamping drive 44 and the swinging drive 45 are arranged on the bracket 41, and the jaw plate 43 is hinged at the upper end of the clamping drive 44, and the clamping drive 44 drives the jaw plate 43 to approach or move away from the guide block 42, so that the jaw plate 43 cooperates with the guide block 42 to clamp Or loosen the pile body; when the guide block 42 and the jaw plate 43 clamp the pile body, the pile body is parallel to the hammering mechanism 3 and is directly below the pile hammer 34; the swing driving member 45 drives to adjust the distance between the clamping mechanism 4 and the hammering mechanism 3. When the clamping mechanism 4 is away from the hammering mechanism 3, the guide block 42 and the jaw plate 43 are separated, and the pile body is loaded therein, and the guide block 42 and the jaw plate 43 are clamped. Then the swing driving member 45 drives the clamping mechanism 4 to be directly below the pile hammer 34, which is convenient for subsequent piling work, that is, the automatic return of the pile body is realized. At the same time, the jaw plate 43 cooperates with the guide block 42 to be suitable for different types of piles.
[0049] Reference Figure 6 In order to further improve the accuracy of the position of the pile body in the hammering mechanism 3, a limiter 31 is set at the end of the hammering mechanism 3. The limiter 31 is used to further limit the position of the pile body. The limiter 31 includes a limit bracket 311, an adjusting bolt assembly 32 and a guide roller assembly 33. The limit bracket 311 is an arc-shaped structure. Both ends of the limit bracket 311 are connected to the supporting frame (not shown in the figure) of the hammering mechanism 3. The hollow area inside the arc-shaped structure is for the pile body to pass through; the adjusting bolt assembly 32 is composed of a plurality of bolt structures, and the plurality of bolt structures are distributed on the periphery of the limit bracket 311 and are all facing the limit bracket 311. Internal hollow area; the guide roller assembly 33 is composed of multiple guide rollers, and the multiple guide rollers are distributed inside the arc structure along the circumference of the limit bracket 311, and the multiple guide rollers are slidably arranged on the guide roller support frame 39, and the roller body wall of the guide roller faces the internal hollow area of the limit bracket 311, that is, it is used to contact the pile body. The setting of multiple guide rollers can achieve the clamping of the pile body while facilitating the falling of the pile body, killing two birds with one stone; at the same time, the bolt assembly 32 is adjusted to movably resist the guide roller to adjust the reciprocating movement of the guide roller on the guide roller support frame 39, thereby adjusting the caliber of the limiter 31 to adapt to different types of pile bodies.
[0050] Reference Figure 7 In order to further enhance the comprehensive functions of the pile driver, a pile pulling mechanism 8 is further provided on the side wall of the hammer cover 35. When pile pulling is required, the pile pulling mechanism 8 is used to perform the pile pulling operation. The pile pulling mechanism 8 comprises a pile pulling bracket 81, a lever 82 and a pulling tool 83. One end of the pile pulling bracket 81 is connected to the side wall of the hammer cover 35, and the other end is hinged to the middle part of the lever 82. One end of the lever 82 is detachably connected to the hammering surface of the pile hammer 34, and the other end is hinged to the pulling tool 83. The pulling tool 83 is used to fix the pile body to be pulled out. When pile pulling is required, one end of the lever 82 is connected to the hammering surface of the pile hammer 34. When the pile hammer 34 performs the pile driving operation, the pulling tool 83 at the other end of the lever 82 is driven, that is, the pile pulling is realized by the principle of the lever 82. When pile pulling is not required, the pile pulling mechanism 8 is hung up by the chain 84 without affecting the pile driving process. The structure is simple, occupies little space, has multiple uses, and is easy to operate.
[0051] Reference Figure 7 In order to effectively reduce construction noise and avoid environmental noise pollution, the pile hammer 34 adopts a hydraulic silent hammer. A sound insulation cover 36 is arranged near the hammering surface of the hydraulic silent hammer. The sound insulation cover 36 is connected to one end of the hammer cover 35. The sound insulation cover 36 is composed of a perforated plate and glass wool, which can effectively reduce the noise by 10-20db. At the same time, a layer of sound insulation cotton can be covered on the pile hammer 34 to further reduce the construction noise.
[0052] The specific operation process of the pile driver in this embodiment is as follows: first, the pile driver is transported to the working position by a locomotive, and then the pile driving position is determined by the positioning mechanism 2, and at the same time, the swing adjustment mechanism 5 and the slewing mechanism 6 are adjusted according to the pile driving position indication, and the swing adjustment mechanism 5 and the slewing mechanism 6 adjust the hammering mechanism 3 and the clamping mechanism 4 to the accurate working position and pitch and yaw angles through the boom assembly 1, and the clamping mechanism 4 grabs the pile body and returns it to its position, and then the aperture is adjusted to adapt to different types of pile bodies through the limiter 31. After double positioning, the hammering mechanism 3 starts to implement pile driving; if drilling is required, the down-the-hole drilling mechanism 7 is called, and the above operation is repeated.
[0053] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0054] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0055] In the present invention, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.
[0056] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0057] Although the embodiments of the present invention have been shown and described above, it is to be understood that the above embodiments are exemplary and are not to be construed as limitations of the present invention. A person skilled in the art may alter, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A pile driver, characterized in that: It comprises a locomotive, an arm assembly (1), a positioning mechanism (2), a hammering mechanism (3), a clamping mechanism (4) and a swing adjustment mechanism (5); The boom assembly (1) is mounted on the platform of the locomotive, the boom assembly (1) extends parallel to the plane where the platform is located, and the positioning mechanism (2) is arranged at one end of the boom assembly (1); The hammering mechanism (3) is arranged on a side of the arm assembly (1) facing away from the locomotive; The clamping mechanism (4) is arranged on one side of the hammering mechanism (3) and connected to the arm assembly (1), and is used for clamping the pile body; The hammering mechanism (3) is capable of hammering the pile body along the boom assembly (1) in a direction away from the positioning mechanism (2); The swing adjustment mechanism (5) is hinged inside the arm assembly (1). Under the instruction of the positioning mechanism (2), the swing adjustment mechanism (5) drives the hammer mechanism (3) and the clamping mechanism (4) through the arm assembly (1) to simultaneously swing in pitch relative to the plane where the platform is located, or to swing in a biased manner to both sides of the first plane relative to the first plane; Wherein, the first plane is the plane where the pitching trajectories of the hammering mechanism (3) and the clamping mechanism (4) are located; The arm assembly (1) comprises a first hinge shaft (11) and a second hinge shaft (12); The first hinge shaft (11) is arranged perpendicular to the first plane and penetrates the interior of the boom assembly (1); The second hinge shaft (12) is located in the first plane and passes through the interior of the boom assembly (1); The swing adjustment mechanism (5) comprises a pitch adjustment component (51) and a yaw adjustment component (52). The pitch adjustment component (51) drives the hammering mechanism (3) and the clamping mechanism (4) to swing around the first hinge shaft (11) by telescoping; The deflection adjustment component (52) drives the hammering mechanism (3) and the clamping mechanism (4) to swing around the second hinge shaft (12) by telescoping; It also includes a slewing mechanism (6); The slewing mechanism (6) is arranged between the arm assembly (1) and the locomotive, and the slewing mechanism (6) can drive the hammering mechanism (3) and the clamping mechanism (4) to rotate relative to itself through the arm assembly (1); The side of the boom assembly (1) facing the locomotive is connected to the slewing mechanism (6) via the second articulated shaft (12) and the yaw adjustment assembly (52) so as to connect the boom assembly (1) to the platform of the locomotive.
2. The pile driver according to claim 1, characterized in that: It also includes a down-the-hole drilling mechanism (7); The down-the-hole drilling mechanism (7) is parallel to the hammering mechanism (3) and is arranged on a side of the boom assembly (1) facing away from the locomotive; The down-the-hole drilling mechanism (7) comprises a drilling drive assembly (71) and a down-the-hole hammer (72) in sequence along a direction away from the positioning mechanism (2). One end of the down-the-hole hammer (72) is connected to the drilling drive assembly (71).
3. The pile driver according to claim 2, characterized in that: The down-the-hole drilling mechanism (7) further comprises a dust collecting mechanism (73); The dust collecting mechanism (73) is connected to the arm assembly (1) and is sleeved on the free end of the down-the-hole hammer (72).
4. The pile driver according to claim 1, characterized in that: The clamping mechanism (4) comprises a bracket (41), a guide block (42), a jaw plate (43), a clamping drive member (44) and a swing drive member (45); One end of the bracket (41) is connected to the arm assembly (1), and the other end is connected to the guide block (42); The clamping drive member (44) and the swing drive member (45) are arranged on the bracket (41); The jaw plate (43) is hinged at the free end of the clamping drive member (44); The clamping drive member (44) drives the jaw plate (43) to move closer to or farther from the guide block (42) to clamp or loosen the pile body; The clamping surface formed by the guide block (42) and the jaw plate (43) is perpendicular to the hammering mechanism (3); The swing driving member (45) drives and adjusts the distance between the clamping mechanism (4) and the hammering mechanism (3).
5. The pile driver according to claim 1, characterized in that: The beating mechanism (3) comprises a limiter (31); The limiter (31) comprises a limit bracket (311), an adjusting bolt assembly (32) and a guide roller assembly (33). The limiting bracket (311) is an arc-shaped structure, the two ends of the arc-shaped structure are connected to one end of the hammering mechanism (3) away from the positioning mechanism (2), the plane where the arc-shaped structure is located is perpendicular to the hammering mechanism (3), and the hollow area inside the arc-shaped structure is for the pile body to pass through; The adjusting bolt assembly (32) is arranged along the radial direction of the arc-shaped structure and distributed on the outer circumference of the arc-shaped structure; The guide roller assembly (33) is distributed inside the arc-shaped structure along the circumference of the arc-shaped structure; The adjusting bolt assembly (32) moves radially along the arc-shaped structure to abut against the guide roller assembly (33), so as to adjust the guide roller assembly (33) to reciprocate radially along the arc-shaped structure.
6. The pile driver according to claim 1, characterized in that: It also includes a pile pulling mechanism (8); The pile pulling mechanism (8) comprises a pile pulling bracket (81), a lever (82) and a pulling tool (83); The hammering mechanism (3) further comprises a pile hammer (34) and a hammer cover (35); One end of the pile pulling bracket (81) is connected to the side wall of the hammer cover (35), and the other end is hinged to the middle part of the lever (82); One end of the lever (82) is detachably clamped to the hammering surface of the pile hammer (34), and the other end is hinged to the puller (83); The pulling tool (83) is used to fix the pile body to be pulled out.
7. The pile driver according to claim 6, characterized in that: The pile hammer (34) is a hydraulic silent hammer. The beating mechanism (3) further comprises a soundproof cover, The sound insulation cover is connected to an end of the hammer cover (35) away from the positioning mechanism (2).
8. The pile driver according to claim 1, characterized in that: The positioning mechanism (2) is a radar antenna, which cooperates with a positioning system arranged on the locomotive to control the swing adjustment mechanism (5) to adjust the piling position and angle.
Citation Information
Patent Citations
Crawler photovoltaic pile driver
CN112962599A
Pile driver automatic positioning and working condition self-adaption method based on multi-sensor fusion
CN114170320A
Vehicular both arms all -in -one of drilling
CN208347686U
Drill rod clamping manipulator
CN212454309U