A construction method for lifting a suspension structure

By first splicing into structural beams and then gradually lowering and installing them, the problem of long construction cycle of suspended structural beams is solved, an efficient construction process is achieved, and safety hazards are reduced.

CN116290807BActive Publication Date: 2025-07-29CHINA CONSTR STEEL STRUCTURE ENG CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310085390.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-17
Publication Date
2025-07-29
Estimated Expiration
2043-01-17

AI Technical Summary

Technical Problem

In the prior art, the construction period of suspended structural beams is too long, and steel beams need to be hoisted layer by layer, resulting in low construction efficiency.

Method used

First, the multi-layer steel beams are spliced into structural beams, and then lifted to the highest floor, gradually lowered and installed on each floor, eliminating the repeated lifting process.

Benefits of technology

It greatly shortens the construction cycle, reduces the repeated improvement process, improves construction efficiency, and reduces safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116290807B_ABST
    Figure CN116290807B_ABST
Patent Text Reader

Abstract

The present invention discloses a lifting construction method for a suspension structure, which includes the following steps: S1. Pre-assemble steel beams with X (X>1) floors into a structural beam at the ground and / or the top of the buildings around the building, and lift the structural beam to the first floor, where the first floor is the top floor among the floors to which the steel beams are to be connected; S2. Fix the steel beam at the top layer of the structural beam to the first floor; S3. Lower the remaining steel beams in the structural beam by Y floors, where Y < X; S4. Install the steel beam at the top layer of the remaining steel beams on the corresponding floor; S5. Repeat steps S3 and S4 to install the steel beams on the corresponding floors respectively. First, the steel beams are assembled into a structural beam, then the structural beam is lifted to the first floor, and finally, by lowering the structural beam, the steel beams on the structural beam are gradually installed on each floor, eliminating the construction process of repeated lifting and greatly shortening the construction period.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of building construction, and particularly to a lifting construction method for a suspension structure. Background Art

[0002] In recent years, building structure designs have become increasingly novel. When constructing the upper building, it is necessary to lift multiple steel beams to the required floors, and then assemble the multiple steel beams for construction. After the construction of each floor of the steel beams is completed, a suspended floor structure beam is formed for subsequent pouring of concrete on each floor. In related technologies, when constructing the suspended structure beams of a multi-story building, a small unit of the structure beam is lifted from the ground to the floor to be constructed by a tower crane, and then construction is carried out on it. After the construction is completed, the above steps are carried out for the upper building of the currently constructed floor. That is to say, for the construction of each floor, it is necessary to lift the small unit of the structure beam to this floor by a tower crane after the construction of the lower floor is completed, and continuously repeat the same step to hoist the small unit, which greatly prolongs the construction period. Summary of the Invention

[0003] The present invention aims to solve at least one of the technical problems existing in the prior art. For this purpose, the present invention provides a lifting construction method for a suspension structure, which can shorten the construction period.

[0004] According to an embodiment of the present invention, the lifting construction method for a suspension structure includes the following steps:

[0005] S1. Pre-assemble steel beams with X (X > 1) floors on the ground and / or at the top of the buildings around the building body into a structure beam, and lift the structure beam to the first floor, where the first floor is the top floor among the floors to which the steel beams are to be connected;

[0006] S2. Fix the steel beam at the top layer of the structure beam to the first floor;

[0007] S3. Lower the remaining steel beams in the structure beam by Y layers, where Y ≥ 1;

[0008] S4. Install the steel beam at the top layer of the remaining steel beams on the corresponding floor;

[0009] S5. Repeat steps S3 and S4 so that the steel beams are respectively installed on the corresponding floors.

[0010] The lifting construction method of the suspension structure according to the embodiment of the present invention has at least the following beneficial effects: Compared with the traditional construction method where a steel beam needs to be lifted once from the ground or the top floor of the building for each floor construction, and this process is repeated continuously until the construction is completed. In the present invention, the steel beams are first spliced into a structural beam, then the structural beam is lifted to the first floor, and finally, by lowering the structural beam, the steel beams on the structural beam are gradually installed on each floor, eliminating the repeated lifting construction process and greatly shortening the construction period.

[0011] According to some embodiments of the present invention, there are multiple buildings with different heights around the building body, and the step S1 includes: lifting the structural beam at a lower position to be butt-jointed and fixedly connected to the structural beam of another building with a height closest to it, completing all the butt-joints of the structural beams, and then lifting the butt-jointed structural beam to the first floor.

[0012] According to some embodiments of the present invention, there are Building A and Building B around the building body, and Building A and Building B are adjacent. Among them, the height of Building A is lower than the height of Building B; the step S1 includes:

[0013] S1.1. Assemble the structural beam with X1 floors on the top floor of Building A, denoted as the first structural beam, and assemble the structural beam with X2 floors on the top floor of Building B, denoted as the second structural beam, where X2 ≤ X1;

[0014] S1.2. Lift the first structural beam to the position corresponding to the second structural beam;

[0015] S1.3. Connect the first structural beam and the second structural beam to each other;

[0016] S1.4. Lift the butt-jointed structural beam to the first floor.

[0017] According to some embodiments of the present invention, the building body also includes Building C around it, and Building C is adjacent to Building A or Building B. Among them, the height of Building C > the height of Building B; in the lifting construction method of the suspension structure,

[0018] The step S1.1 further includes: assembling the structural beam with X3 floors on the top floor of Building C, denoted as the third structural beam, where X3 ≤ X2 ≤ X1;

[0019] Between the steps S1.2 and S1.3, it further includes:

[0020] F1. Lift the connected first structural beam and second structural beam to the position corresponding to the third structural beam;

[0021] F2. Connect the third structural beam to the first structural beam or the second structural beam.

[0022] According to some embodiments of the present invention, S1 further includes:

[0023] Prepare a hoist and several ropes, connect each of the ropes to the adjacent steel beam, set the hoist on the top floor of the building, and connect the hoist to the bottom of the structural beam.

[0024] According to some embodiments of the present invention, S1 further includes:

[0025] Prepare a hoist and several connecting rods, connect each of the connecting rods to the adjacent steel beam, set the hoist on the top floor of the building, and connect the hoist to the top of the structural beam.

[0026] According to some embodiments of the present invention, S1 further includes:

[0027] Use a tower crane to lift the steel beam or structural beam located on the ground to the top floor of each building.

[0028] According to some embodiments of the present invention, after S5, it further includes:

[0029] S6. Pour concrete into the steel beams on each floor.

[0030] According to some embodiments of the present invention, S1 includes:

[0031] Place a hanging plate for stacking the structural beams on the ground and / or the top floor of the building, splice the steel beams with X (X>1) layers into the structural beam on the hanging plate, and lift the hanging plate carrying the structural beam to the top first floor among the floors where the steel beams to be connected are located.

[0032] According to some embodiments of the present invention, in S1, set the hoist on the top floor of the building, connect the hoist and the hanging plate with a sling, and lift the hanging plate through the hoist.

[0033] The additional aspects and advantages of the present invention will be partly given in the following description, partly will become obvious from the following description, or be understood through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] The following further describes the present invention in conjunction with the drawings and embodiments, where:

[0035] Figure 1 is a schematic diagram of placing the structural beam on the ground and the top floors of different buildings in the embodiment of the present invention;

[0036] Figure 2 Schematic diagram of lifting the structural beam from the ground to Building A in the embodiment of the present invention;

[0037] Figure 3 Schematic diagram of lifting the structural beam from Building A to Building B in the embodiment of the present invention;

[0038] Figure 4 Schematic diagram of lifting the structural beam from Building B to Building C in the embodiment of the present invention;

[0039] Figure 5 Schematic diagram of lifting the structural beam from Building C to the first floor in the embodiment of the present invention;

[0040] Figure 6 Schematic diagram of lowering the structural beam by Y floors from the first floor in the embodiment of the present invention;

[0041] Figure 7 In the embodiment of the present invention, from Figure 6 Schematic diagram of continuing to lower the structural beam by Y floors from the shown position;

[0042] Figure 8 Schematic diagram of placing the steel beam on each required floor in the embodiment of the present invention;

[0043] Figure 9 Schematic diagram of the structure of the rope cooperating with the steel beam in the embodiment of the present invention;

[0044] Figure 10 Schematic diagram of the structure of the connecting rod cooperating with the steel beam in the embodiment of the present invention;

[0045] Figure 11 Schematic diagram of the structure of the building in the embodiment of the present invention.

[0046] Reference numerals: ground 100, building 200, Building A 210, Building B 220, Building C 230, first floor 240, structural beam 300, steel beam 310, lifter 400, tower crane 500, hanging plate 600, rope 700, connecting rod 800. Detailed implementation manners

[0047] The embodiments of the present invention will be described in detail below. Examples of the embodiments are shown in the drawings, where the same or similar reference numerals denote the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the drawings are exemplary only for explaining the present invention and should not be construed as limiting the present invention.

[0048] In the description of the present invention, it should be understood that with respect to the orientation description, such as the orientation or positional relationship indicated by up, down, front, back, left, right, etc., it is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be construed as a limitation to the present invention.

[0049] In the description of the present invention, the meaning of several is more than one, the meaning of multiple is more than two, and understandings such as greater than, less than, exceeding, etc. do not include the recited number, and understandings such as above, below, within, etc. include the recited number. If there is a description of first and second, it is only for the purpose of distinguishing technical features and cannot be understood as indicating or implying relative importance or implicitly indicating the quantity of the indicated technical features or implicitly indicating the sequence relationship of the indicated technical features.

[0050] In the description of the present invention, unless otherwise clearly defined, terms such as set, install, connect, etc. should be understood in a broad sense, and those skilled in the art can reasonably determine the specific meaning of the above terms in the present invention in combination with the specific content of the technical solution.

[0051] In the description of the present invention, the description with reference to terms such as "one embodiment", "some embodiments", "schematic embodiments", "examples", "specific examples", or "some examples", etc. means that the specific features, structures, materials, or characteristics described in connection with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic descriptions of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials, or characteristics described can be combined in a suitable manner in any one or more embodiments or examples.

[0052] In some embodiments, in order to add steel beams 310 outside multiple floors of the building body 200, refer to Figures 2 - 8 and refer to Figure 1 , the hanging structure lifting construction method includes the following steps:

[0053] S1. Pre-assemble the steel beams 310 with X (X>1) floors into a structural beam 300 on the ground 100 and / or the top of the buildings around the building body 200, and lift the structural beam 300 to the first floor 240, where the first floor 240 is the top floor among the floors to which the steel beams 310 are to be connected;

[0054] S2. Fix the steel beam 310 at the top layer of the structural beam 300 to the first floor 240;

[0055] S3. Lower the remaining steel beams 310 in the structural beam 300 by Y floors, where Y≥1;

[0056] S4. Install the topmost steel beam 310 among the remaining steel beams 310 on the corresponding floor.

[0057] S5. Repeat steps S3 and S4 to install the steel beams 310 on the corresponding floors respectively.

[0058] It should be noted that in the present invention, the steel beams 310 need to be fixed on the required floors in the building body 200 respectively to form the floor steel beam 310 structure. Subsequently, by pouring concrete on the steel beams 310, a cantilever floor is initially formed. The structural beam 300 is formed by splicing multiple layers of steel beams 310, and each layer of steel beam 310 will be applied to different floors; the first floor 240 is the highest floor among the floors to be constructed in the building body 200; X can be selected according to the number of floors to be actually constructed, and X can be 2, 3, 4... The technical personnel can make an adaptive selection according to the floors to be actually constructed; the technical personnel can also select the number of floors Y by which the structural beam 300 is lowered according to actual needs, for example, lowering 1 floor, lowering 2 floors, etc.

[0059] Compared with the traditional construction method where the steel beam 310 needs to be lifted once from the ground 100 or the top floor of the building for each floor construction, and this is continuously repeated until the construction is completed, in the present invention, the steel beams 310 are first spliced into the structural beam 300, then the structural beam 300 is lifted to the first floor 240, and finally, by lowering the structural beam 300, the steel beams 310 on the structural beam 300 are gradually installed on each floor, saving the construction process of repeated lifting and greatly shortening the construction period.

[0060] Specifically, S1. First, splice the steel beams 310 on the ground 100 and / or the top floor of the building into the structural beam 300, and then lift the structural beam 300 to the highest floor (i.e., the first floor 240) of the required cantilever floor; S2. Subsequently, construct the steel beam 310 on the first floor 240 to fix the steel beam 310 of this floor on the first floor 240; S3. Lower the remaining structural beam 300 by X floors; S4. Fix the topmost steel beam 310 of the structural beam 300 lowered to this floor on this floor.

[0061] In some embodiments, referring to Figures 2 - 4 and referring to Figure 1 , there are multiple buildings with different heights around the building body 200. Step S1 includes: lifting the structural beam 300 at a lower position to dock and fixedly connect with the structural beam 300 of another building with the closest height, completing the docking of all structural beams 300, and lifting the docked structural beam 300 to the first floor 240.

[0062] The embodiment of the present invention can be applied to the building body 200 with multiple buildings of different heights, so that the construction period can also be saved when constructing the building body 200 with multiple buildings of different heights.

[0063] Specifically, referring to Figure 1 , in this embodiment, the structural beam 300 located on the ground 100 is lifted to the top floor of building A210 and docked with the structural beam 300 on the top floor of building A210, and then the docked structural beam 300 is lifted to a position where it can be docked with the structural beam 300 on building B220.

[0064] In some embodiments, referring to Figures 2 - 5 and Figure 11 , there are buildings A210 and B220 around the building body 200. Buildings A210 and B220 are adjacent. Among them, the height of building A210 is lower than that of building B220; S1 includes:

[0065] S1.1. Assemble the structural beam 300 with X1 floors on the top floor of building A210, denoted as the first structural beam, and assemble the structural beam 300 with X2 floors on the top floor of building B220, denoted as the second structural beam, where X2 ≤ X1;

[0066] S1.2. Lift the first structural beam to a position corresponding to the second structural beam;

[0067] S1.3. Connect the first structural beam and the second structural beam to each other;

[0068] S1.4. Lift the docked structural beam 300 to the first floor 240.

[0069] It should be noted that since building B220 is higher than building A210, and the structural beam 300 placed on building B220 can only be assembled up to the height from the top floor of building B220 to the first floor 240 at most. Similarly, the structural beam 300 placed on building A210 can be assembled up to the height from the top floor of building A210 to the first floor 240 at most, resulting in the height of the former structural beam 300 being lower than that of the latter structural beam 300. Therefore, X2 ≤ X1.

[0070] Since the steel beams 310 of building A210 and building B220 need to be spliced ​​eventually during the construction of the floor, if the structural beams 300 on building A210 and building B220 are first lifted to the first floor 240 together and then lowered to the respective required construction floors, and then the steel beams 310 above building A210 and the steel beams 310 above building B220 are spliced, there are relatively large potential safety hazards (that is, workers need to move to the splicing point of the two for construction, and this construction point is in a cantilever state). Therefore, in the embodiment of the present invention, the structural beam 300 of building A210 and the structural beam 300 of building B220 are first docked, and then the docked structural beam 300 is lifted to the first floor 240, which facilitates the construction of the staff and reduces the potential safety hazards of the construction.

[0071] It can be understood that in the process of S1.2, since the structural beam 300 of building B220 is located on the top floor of building B220, when connecting the structural beam 300 of building A210 to the structural beam 300 of building B220, the staff can carry out the connecting construction of the structural beams 300 of the two on the top floor of building B220. Since the top floor of building B220 provides relatively stable support for the staff, it can reduce safety hazards in construction.

[0072] It should be noted that the operator can adaptively adjust X1 and X2 according to actual needs. During the docking process, the operator can choose to splice part or all of the steel beams 310 on the first structural beam with part or all of the steel beams 310 on the second structural beam according to actual needs.

[0073] In some embodiments, reference Figures 2 - 5 and Figure 11 Building 200 is surrounded by building C230, which is adjacent to building A210 or building B220. The height of building C230 is greater than the height of building B220. In the suspended structure lifting construction method, S1.1 further includes: assembling a structural beam 300 having X3 layers on the top floor of building C230, which is recorded as the third structural beam 300, where X3≤X2≤X1.

[0074] Also included between S1.2 and S1.3:

[0075] F1. Lift the connected first structural beam and the second structural beam to a position corresponding to the third structural beam 300;

[0076] F2. Connect the third structural beam 300 to the first structural beam or the second structural beam.

[0077] The present invention provides an embodiment further including a building C230 to illustrate the construction process when there are multiple buildings in the building body 200.

[0078] In some embodiments, reference Figure 9 , S1 also includes:

[0079] Prepare a hoist 400 and several ropes 700 , connect each rope 700 to an adjacent steel beam 310 , place the hoist 400 on the top floor of the building 200 , and connect the hoist 400 to the bottom of the structural beam 300 .

[0080] By using the ropes 700 to bind the adjacent steel beams 310 , it is possible to easily assemble the steel beams 310 of each floor, and it is also possible to easily remove the steel beams 310 from the structural beams 300 to fix them on the floors.

[0081] In some embodiments, referring to Figure 10 , S1 further includes: preparing a lifter 400 and a plurality of connecting rods 800, connecting each connecting rod 800 to an adjacent steel beam 310, arranging the lifter 400 on the top floor of the building 200, and connecting the lifter 400 to the top of the structural beam 300.

[0082] Using the connecting rods 800 to assemble adjacent steel beams 310 can prevent the adjacent steel beams 310 from shaking during the lifting of the structural beam 300.

[0083] In some embodiments, referring to Figure 1 , in order to further reduce the construction period, S1 further includes: using a tower crane 500 to lift the steel beam 310 or the structural beam 300 located on the ground 100 to the top floor of each building.

[0084] During the actual construction process, before the lifter 400 lifts the structural beam 300 to the height of one of the buildings, use the tower crane 500 to lift the structural beam 300 that needs to be placed on the top floor of this building to this building, ensuring that the structural beam 300 during the lifting process can be smoothly docked with the structural beam 300 of this floor of the building when it is lifted to the top floor of this building; on the other hand, before the lifter 400 lifts the structural beam 300 to the height of one of the buildings, the tower crane 500 can also be used to lift the steel beam 310 that needs to be placed on the top floor of this building to this building and assemble the steel beam 310 into a structural beam 300. The above settings can also greatly reduce the construction time of the structural beam 300 during the lifting process.

[0085] It can be understood that in order not to affect the lifting work of the lifter 400 on the structural beam 300, the present invention adopts the tower crane 500 technology to lift each steel beam 310 or structural beam 300 located on the ground 100 that needs to be placed on the top floor of the building to the corresponding top floor of the building, enabling the lifter 400 to work together with the tower crane 500 in terms of time, improving the construction efficiency and shortening the construction time.

[0086] In some embodiments, after S5, it further includes: S6, pouring concrete into the steel beams 310 on each floor.

[0087] Pouring concrete into the steel beams 310 fixed on each floor respectively to form a cantilever floor and integrate it with the original floor.

[0088] In some embodiments, referring to Figure 1 , S1 includes: placing a hanging plate 600 for stacking structural beams 300 on the ground 100 and / or the top floor of the building, splicing steel beams 310 with X (X > 1) layers into a structural beam 300 on the hanging plate 600, and lifting the hanging plate 600 carrying the structural beam 300 to the topmost first floor 240 of the floor where the steel beam 310 to be connected is located.

[0089] Due to the arrangement of the suspension plate 600, the lifter 400 only needs to lift the suspension plate 600 to realize the overall lifting of the structural beam 300, which facilitates the lifting of the structural beam 300.

[0090] In some embodiments, in S1, the lifter 400 is arranged on the top floor of the building 200, and the lifter 400 and the suspension plate 600 are connected by a sling, and the suspension plate 600 is lifted by the lifter 400.

[0091] Specifically, the structural beam 300 is placed on the suspension plate 600, and the lifter 400 is connected to the suspension plate 600 through a lifting rope and can stably lift or lower the suspension plate 600 in the vertical direction.

[0092] The embodiments of the present invention have been described in detail above in conjunction with the accompanying drawings. However, the present invention is not limited to the above embodiments, and various changes can be made without departing from the spirit of the present invention within the scope of knowledge possessed by those of ordinary skill in the art. In addition, the embodiments of the present invention and the features in the embodiments can be combined with each other without conflict.

Claims

1. A construction method for lifting a suspension structure, which is used to add steel beams outside multiple floors of a building. The method is characterized in that, The hanging structure lifting construction method includes the following steps: S1. Pre-assemble steel beams with X floors (where X > 1) into a structural beam on the ground and / or at the top of the buildings around the building body, and lift the structural beam to the first floor, where the first floor is the top floor among the floors where the steel beams to be connected are located; S2. Fix the steel beam at the top layer of the structural beam to the first floor; S3. Lower the remaining steel beams in the structural beam by Y floors, where Y ≥ 1; S4. Install the steel beam at the top layer of the remaining steel beams on the corresponding floor; S5. Repeat steps S3 and S4 to install the steel beams on the corresponding floors respectively; There are multiple buildings with different heights around the building body. Step S1 includes: Lift the structural beam at a lower position to be butt-jointed and fixedly connected to the structural beam of another building with a height closest to it, complete all the butt-joints of the structural beams, and lift the butt-jointed structural beam to the first floor; There are Building A and Building B around the building body. Building A and Building B are adjacent. Among them, the height of Building A is lower than the height of Building B; S1 includes: S1.

1. Assemble the structural beam with X1 floors on the top floor of Building A, denoted as the first structural beam, and assemble the structural beam with X2 floors on the top floor of Building B, denoted as the second structural beam, where X2 ≤ X1; S1.

2. Lift the first structural beam to the position corresponding to the second structural beam; S1.

3. Connect the first structural beam and the second structural beam to each other; S1.

4. Lift the butt-jointed structural beam to the first floor; 2. The lifting construction method of the suspension structure according to claim 1, wherein There is also Building C around the building body. Building C is adjacent to Building A or Building B. Among them, the height of Building C > the height of Building B; In the hanging structure lifting construction method, S1.1 further includes: Assemble the structural beam with X3 floors on the top floor of Building C, denoted as the third structural beam, where X3 ≤ X2 ≤ X1; Between S1.2 and S1.3, it further includes: F1. Lift the connected first structural beam and second structural beam to the position corresponding to the third structural beam; F2. Connect the third structural beam to the first structural beam or the second structural beam; 3. The lifting construction method of the suspension structure according to claim 1, characterized in that, S1 further includes: Prepare a hoist and several ropes, connect each rope to the adjacent steel beam, set the hoist on the top floor of the building body, and connect the hoist to the bottom of the structural beam; 4. The lifting construction method of the suspension structure according to claim 1, characterized in that, S1 further includes: Prepare a hoist and several connecting rods, connect each connecting rod to the adjacent steel beam, set the hoist on the top floor of the building body, and connect the hoist to the top of the structural beam; 5. The lifting construction method of the hanging structure according to claim 1, characterized in that, S1 further includes: Use a tower crane to lift the steel beam or structural beam on the ground to the top floors of each building; 6. The lifting construction method of the suspension structure according to claim 1, characterized in that, After S5, it further includes: S6. Pour concrete into the steel beams on each floor; 7. The lifting construction method of the suspension structure according to claim 1, characterized in that, S1 includes: Place a lifting plate for stacking the structural beams on the ground and / or the top floor of the building. On the lifting plate, splice steel beams with X layers into the structural beam, where X > 1, and lift the lifting plate carrying the structural beam to the topmost first floor among the floors where the steel beams to be connected are located.

8. The lifting construction method of the suspension structure according to claim 7, wherein In the step S1, set the hoist on the top floor of the building, connect the hoist and the lifting plate using a sling, and lift the lifting plate through the hoist.

Citation Information

Patent Citations

  • Construction method of high-altitude cantilever steel structure

    CN108457382A

  • Improvements in building method

    GB607826A