A hydropower station centralized control auxiliary duty robot
By introducing centralized control auxiliary duty robots into the power grid, and using a combination of virtual and physical robots, intelligent retrieval and strategy recommendation of power grid information is achieved, solving the problems of information flooding and response delays, and improving the efficiency of power grid accident handling.
Patent Information
- Application Number
- CN202310442124.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-23
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-04-23
AI Technical Summary
In the process of monitoring the safe operation of the power grid, a large amount of information is flushed on the screen in the event of an accident, causing important information to be submerged. The time for centralized control personnel on duty to learn abnormal information is delayed, which affects the efficiency of accident handling.
Design a hydropower station centralized control auxiliary duty robot, including virtual robots and physical robots. Through the centralized control expert library, strategy assistance unit and strategy control unit, it can realize intelligent retrieval and strategy recommendation of real-time information and instructions, and shorten the response time.
It realizes intelligent recommendation of strategies for centralized control personnel on duty, reduces repetitive work, improves the efficiency of power grid accident handling, and ensures rapid response.
Smart Images

Figure CN116476090B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of intelligent centralized control of power grids, and in particular relates to a centralized control auxiliary duty robot for a hydropower station. Background Art
[0002] With the development of smart grid technology, the types and number of power equipment in existing smart grids have increased significantly. Especially in the context of the existing power system mostly adopting the centralized control integrated mode, in the process of monitoring the safe operation of the power grid, there is a phenomenon of a large amount of information being displayed on the screen in the event of an accident, which makes it easy for important information to be submerged. When an abnormality occurs in the power grid system, the time for the centralized control duty personnel to obtain the abnormal information is further delayed, and the faulty equipment cannot be quickly identified. The time for reporting to the superior dispatch is difficult to meet the requirements of the power grid dispatch regulations, which will delay the accident handling to a certain extent; therefore, it is necessary to design a hydropower station centralized control auxiliary duty robot to solve the above problems. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a hydropower station centralized control auxiliary duty robot. This solution solves the problem that in the process of monitoring the safe operation of the power grid in the prior art, a large amount of information is refreshed on the screen in the event of an accident, which makes important information easily submerged, and when an abnormality occurs in the power grid system, the time for the centralized control duty personnel to obtain the abnormal information is further delayed. The robot has the function of intelligent retrieval of centralized control business information and rapid accident guidance through the duty robot, and can more reasonably recommend suitable auxiliary strategies to the centralized control duty personnel, which is conducive to shortening the response time of the centralized control duty personnel to the power grid accidents.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A hydropower station centralized control auxiliary duty robot, including a virtual robot and a physical robot;
[0006] The physical robot is deployed at the work site, and is used to provide human-computer interaction services for the centralized control personnel on site, receive real-time operation information on site and centralized control instructions from the centralized control personnel, and send the real-time operation information and centralized control instructions to the virtual robot; the virtual robot is deployed at the centralized control terminal, including a centralized control expert library, a strategy auxiliary unit and a strategy control unit; the centralized control expert library is used to retrieve the first auxiliary strategy that matches the real-time operation information and the second auxiliary strategy that matches the centralized control instruction according to the real-time operation information and the centralized control instruction; the strategy auxiliary unit is used to perform feature comparison on the first auxiliary strategy and the second auxiliary strategy, determine the recommended strategy list and the execution priority of each auxiliary strategy in the recommended strategy list according to the comparison result, generate a strategy list in descending order of execution priority and send it to the physical robot for execution.
[0007] Preferably, the centralized control expert library stores centralized control strategies in a tree structure, the first-level nodes of the tree structure are strategy types, the second-level nodes of the tree structure are centralized control devices, and the third-level nodes of the tree structure are specific centralized control steps of the centralized control devices.
[0008] Preferably, the retrieving, according to the real-time operation information and the centralized control instruction, a first auxiliary strategy matching the real-time operation information and a second auxiliary strategy matching the centralized control instruction respectively comprises:
[0009] Conduct situation analysis on real-time operation information, determine whether an accident has occurred in the power grid and the type of accident based on the analysis results, and determine the matching first-level nodes, second-level nodes, and third-level nodes in the centralized control expert database based on the type of accident;
[0010] Extract keywords from the centralized control instructions, and determine the matching first-level nodes, second-level nodes, and third-level nodes in the centralized control expert database based on the extracted keywords;
[0011] The matched first-level nodes, second-level nodes, and third-level nodes are connected into a tree structure according to a hierarchical relationship, and a first auxiliary strategy and a second auxiliary strategy are generated respectively according to the tree structure.
[0012] Preferably, the centralized control instructions of the centralized control personnel include text instructions and voice instructions.
[0013] Preferably, the feature comparison between the first auxiliary strategy and the second auxiliary strategy and determining a recommended strategy list according to the comparison result includes:
[0014] Performing cluster analysis on the topological features of the tree structures corresponding to the first auxiliary strategy and the second auxiliary strategy to obtain a plurality of cluster sets;
[0015] Filter out cluster sets whose auxiliary strategies are lower than a preset value, and perform deduplication processing on the first auxiliary strategy and the second auxiliary strategy in the remaining cluster sets, and use them as the recommended strategies in the recommended strategy list;
[0016] The recommendation priority in the recommendation strategy list is determined according to the number of third-level nodes in the tree structure of the recommendation strategy, wherein the fewer the number of third-level nodes, the higher the recommendation priority.
[0017] Preferably, the physical robot also includes a strategy control unit, which is used to execute the recommended strategy with the highest priority and monitor the execution results after the centralized control staff on duty verifies the recommended strategy list, and when the execution fails, control the physical robot to execute other recommended strategies in order of recommended priority from high to low.
[0018] Preferably, the virtual robot also includes a centralized control anomaly monitoring unit, which is used to respectively record the matching frequency of the first-level nodes, second-level nodes, and third-level nodes in the tree structure of the centralized control expert library. When the matching frequency exceeds a preset value, an alarm centralized control frequent abnormal prompt information is generated.
[0019] The beneficial effects of the present invention are:
[0020] The present invention can realize the centralized management and governance of data of independent systems such as the electric control monitoring system, the water control automation system, and the ePMS system, solve the problem of integrating multi-source heterogeneous data from different automation systems, realize the global sharing of relevant data of the centralized control of the hydropower station, and thus realize the integrated centralized control of the hydropower station. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the architecture of a hydropower station centralized control auxiliary duty robot provided by the invention. DETAILED DESCRIPTION
[0022] like Figure 1 As shown, this embodiment proposes a hydropower station centralized control auxiliary duty robot, including a virtual robot and a physical robot;
[0023] The physical robot is deployed at the work site to provide human-computer interaction services for the centralized control personnel at the site, receive the real-time operation information at the site and the centralized control instructions from the centralized control personnel, and send the real-time operation information and the centralized control instructions to the virtual robot;
[0024] The virtual robot is deployed in a centralized control terminal, including a centralized control expert library, a strategy auxiliary unit and a strategy control unit;
[0025] The centralized control expert database is used to retrieve a first auxiliary strategy matching the real-time operation information and a second auxiliary strategy matching the centralized control instruction respectively according to the real-time operation information and the centralized control instruction;
[0026] The strategy assisting unit is used to perform feature comparison on the first assisting strategy and the second assisting strategy, determine a recommended strategy list according to the comparison result, and send the recommended strategy list to the physical robot.
[0027] The hydropower station centralized control auxiliary duty robot proposed in this embodiment can make intelligent recommendations on centralized control strategies for centralized control duty personnel, freeing them from a large amount of repetitive work, which is conducive to shortening the response time of centralized control duty personnel to power grid accidents, thereby improving centralized control efficiency.
[0028] In this embodiment, the centralized control expert library stores centralized control strategies in a tree structure, the first-level node of the tree structure is the strategy type, the second-level node of the tree structure is the centralized control device, and the third-level node of the tree structure is the specific centralized control steps of the centralized control device.
[0029] This embodiment displays all the centralized control strategies pre-imported into the centralized control expert database in the form of a tree structure, supports multi-level maintenance of the categories of expert database data, and the fields include: file category, file name, file size, update time, uploader, number of reads, number of downloads, etc. File categories include: power grid and cascade power station regulations, regulations, drawings, fixed value sheets, standard structured forms (generation plan modification application, emergency maintenance application, information report sheet, etc.), standard operation order tickets, on-site disposal plans, technical summaries, abnormal analysis reports, power market operation assessment rules, company-related systems, training question banks, etc.
[0030] On this basis, based on the topological characteristics of the tree structure, the strategy auxiliary unit can subsequently perform recommendation by strategy screening according to the matching results and the recommendation order of each recommended strategy in the recommended strategy list.
[0031] Further, the retrieving, according to the real-time operation information and the centralized control instruction, a first auxiliary strategy matching the real-time operation information and a second auxiliary strategy matching the centralized control instruction respectively includes:
[0032] Conduct situation analysis on real-time operation information, determine whether an accident has occurred in the power grid and the type of accident based on the analysis results, and determine the matching first-level nodes, second-level nodes, and third-level nodes in the centralized control expert database based on the type of accident;
[0033] Extract keywords from the centralized control instructions, and determine the matching first-level nodes, second-level nodes, and third-level nodes in the centralized control expert database based on the extracted keywords;
[0034] The matched first-level nodes, second-level nodes, and third-level nodes are connected into a tree structure according to a hierarchical relationship, and a first auxiliary strategy and a second auxiliary strategy are generated respectively according to the tree structure.
[0035] In this embodiment, the centralized control instructions of the centralized control personnel include text instructions and voice instructions. In the above-mentioned process of extracting keywords from the centralized control instructions, keywords can be extracted from text instructions through existing text segmentation algorithms, and keywords can be extracted from voice instructions through existing voice recognition technology.
[0036] The comparing the features of the first auxiliary strategy and the second auxiliary strategy and determining the recommended strategy list according to the comparison result includes:
[0037] Performing cluster analysis on the topological features of the tree structures corresponding to the first auxiliary strategy and the second auxiliary strategy to obtain a plurality of cluster sets;
[0038] The cluster sets including auxiliary strategies lower than a preset value are filtered out, and the first auxiliary strategies and the second auxiliary strategies in the remaining cluster sets are deduplicated and used as the recommended strategies in the recommended strategy list.
[0039] The purpose of the above process is to compare the similarity between the first auxiliary strategy and the second auxiliary strategy, so as to remove the auxiliary strategies that are obviously irrelevant. For example, when the centralized control staff makes an incorrect centralized control instruction, the second auxiliary strategy matched by the centralized control instruction is also likely to be incorrect. In this case, the first auxiliary strategy matched based on the real-time operation information on site can be regarded as the correct auxiliary strategy, thereby removing the obviously incorrect auxiliary strategies and realizing the intelligent recommendation of centralized control strategies.
[0040] Subsequently, the recommendation priority in the recommendation strategy list is determined according to the number of third-level nodes in the tree structure of the recommendation strategy, wherein the fewer the number of third-level nodes, the higher the recommendation priority.
[0041] This embodiment determines the recommendation priority based on the third-level nodes, that is, the number of specific centralized control steps involved in the recommended strategy. Based on the above, this embodiment preferentially recommends strategies with fewer specific centralized control steps to avoid more complex centralized control steps to the greatest extent.
[0042] In this embodiment, the physical robot also includes a strategy control unit, which is used to execute the recommended strategy with the highest priority and monitor the execution results after the centralized control staff on duty verifies the recommended strategy list. When the execution fails, the physical robot is controlled to execute other recommended strategies in order of recommended priority from high to low.
[0043] In this embodiment, the virtual robot also includes a centralized control abnormality monitoring unit, which is used to respectively record the matching frequency of the first-level nodes, second-level nodes, and third-level nodes in the tree structure of the centralized control expert library. When the matching frequency exceeds the preset value, an alarm centralized control frequent abnormality prompt information is generated.
[0044] The above-mentioned embodiments are only preferred technical solutions of the present invention and should not be regarded as limitations of the present invention. The embodiments and features in the embodiments of the present application can be arbitrarily combined with each other without conflict. The protection scope of the present invention shall be the technical solutions recorded in the claims, including the equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.
Claims
1. A hydropower station centralized control auxiliary duty robot, characterized in that: It includes a virtual robot and a physical robot; the physical robot is deployed at the work site, and is used to provide human-computer interaction services for the centralized control personnel on site, receive the real-time operation information of the site and the centralized control instructions of the centralized control personnel, and send the real-time operation information and the centralized control instructions to the virtual robot; the virtual robot is deployed at the centralized control terminal, and includes a centralized control expert library, a strategy auxiliary unit and a strategy control unit; the centralized control expert library is used to retrieve the first auxiliary strategy matching the real-time operation information and the second auxiliary strategy matching the centralized control instruction according to the real-time operation information and the centralized control instruction; the strategy auxiliary unit is used to perform feature comparison on the first auxiliary strategy and the second auxiliary strategy, determine the recommended strategy list according to the comparison result, and send it to the physical robot; the centralized control expert library stores the centralized control strategy in a tree structure, the first-level node of the tree structure is the strategy type, the second-level node of the tree structure is the centralized control device, and the third-level node of the tree structure is the specific centralized control step of the centralized control device; Comparing the features of the first auxiliary strategy and the second auxiliary strategy, and determining a recommended strategy list according to the comparison result, including the following methods: S401, performing cluster analysis on the topological features of the tree structure corresponding to the first auxiliary strategy and the second auxiliary strategy to obtain a plurality of cluster sets; S402, filtering out cluster sets containing auxiliary strategies lower than a preset value, and performing deduplication processing on the first auxiliary strategy and the second auxiliary strategy in the remaining cluster sets as recommended strategies in the recommended strategy list; S403, determining the recommendation priority in the recommendation strategy list according to the number of third-level nodes in the tree structure of the recommendation strategy, wherein the fewer the number of third-level nodes, the higher the recommendation priority.
2. A hydropower station centralized control auxiliary duty robot according to claim 1, characterized in that: The method of respectively retrieving a first auxiliary strategy matching the real-time operation information and a second auxiliary strategy matching the centralized control instruction according to the real-time operation information and the centralized control instruction comprises the following methods: S301, performing situation analysis on the real-time operation information, determining whether an accident has occurred in the power grid and the type of accident based on the analysis results, and determining the matching primary nodes, secondary nodes, and tertiary nodes in the centralized control expert database based on the type of accident; S302, extracting keywords from the centralized control instruction, and determining matching primary nodes, secondary nodes, and tertiary nodes in the centralized control expert database according to the extracted keywords; S303 , the matched first-level nodes, second-level nodes, and third-level nodes are connected into a tree structure according to a hierarchical relationship, and a first auxiliary strategy and a second auxiliary strategy are generated respectively according to the tree structure.
3. A hydropower station centralized control auxiliary duty robot according to claim 1, characterized in that: The centralized control instructions of the centralized control personnel include text instructions and voice instructions.
4. A hydropower station centralized control auxiliary duty robot according to claim 1, characterized in that: The physical robot also includes a strategy control unit, which is used to execute the recommended strategy with the highest priority and monitor the execution results after the centralized control staff on duty verifies the recommended strategy list. When the execution fails, the physical robot is controlled to execute other recommended strategies in order from high to low recommended priority.
5. The hydropower station centralized control auxiliary duty robot according to claim 1, characterized in that: The virtual robot also includes a centralized control anomaly monitoring unit, which is used to record the matching frequency of the first-level nodes, second-level nodes and third-level nodes in the tree structure of the centralized control expert library respectively. When the matching frequency exceeds the preset value, it generates an alarm centralized control frequent abnormal prompt information.
Citation Information
Patent Citations
Power grid dispatching operation duty shifting aiding device
CN105894216A
Voice control method, system thereof, cloud server and voice device
CN109448721A
An auxiliary decision-making method and system for equipment fault disposal
CN109726214A
Transformer substation inspection robot monitoring method and device and computer equipment
CN115562227A
Control method and system for controlling action of auxiliary shaft cage
CN115793514A