A method for optimizing the stress of a tower area support system
By using support pads and a support system at the steel beam nodes in the tower area, combined with construction monitoring calculations, the coordinated stress distribution of the steel beam and support system was optimized, which solved the problem of increased stress risk in the support system in the tower area, and achieved improved safety and reduced material costs.
Patent Information
- Application Number
- CN202310336640.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-31
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-03-31
AI Technical Summary
With the development of long-span steel truss cable-stayed bridges, the stress risk of the tower area support system has increased, leading to higher design material costs and reduced safety.
By using support blocks, sliding beams, and a support system at the steel beam nodes in the tower area, and combining the construction monitoring calculation results, some blocks were removed to achieve coordinated stress distribution between the steel beam and the support system, thus optimizing the stress distribution of the support system.
This improved the safety of the support under stress and significantly reduced the size of the support design, saving material costs.
Smart Images

Figure CN116561843B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of steel truss cable-stayed bridge construction. More specifically, this invention relates to a method for optimizing the stress distribution of a tower area support system. Background Technology
[0002] With the continuous development of long-span cable-stayed bridges for both road and rail use, the span of cable-stayed bridges is constantly being updated. Steel trusses, due to their superior structural performance and good double-deck traffic performance, have become an important option for crossing rivers and canyons, leading to a corresponding increase in their scale. During the erection of steel truss segments in the tower area, a tower area support system is often needed to support the installation of the steel beams. However, as the scale of the steel truss segments increases, the self-weight and stiffness of the steel truss also increase accordingly. Especially under the cantilever lifting conditions of bridge cranes, the self-weight of the steel truss in the installation area, the load of the bridge crane, and the self-weight of the lifted beam segments require the tower area support system to provide sufficient stiffness and support force. Furthermore, the influence of environmental temperature and wind loads is amplified, inevitably increasing the stress risk of the tower area support system. Moreover, the increased design scale also significantly increases the required design materials and the cost of temporary structures. To mitigate the problem of excessively large support system scale, a method for optimizing the stress on the tower area support system is proposed, thereby reducing the design cost of the tower area support system and improving its stress safety. Summary of the Invention
[0003] The purpose of this invention is to provide a method for optimizing the stress of a tower support system, so as to achieve coordinated stress distribution between the steel beam and the support. This not only improves the safety of the support under stress, but also significantly reduces the design scale of the support and saves material costs.
[0004] The technical solution adopted by this invention to solve this technical problem is: a method for optimizing the stress of a tower area support system, comprising the following steps:
[0005] 1) The steel beams in the tower area are supported by support blocks, sliding beams and bracket system at large nodes. After the steel beam segments in the tower area are installed and the alignment is adjusted to meet the construction monitoring requirements, temporary constraints are applied to the tower beams. The support blocks are composed of several small blocks in the height direction.
[0006] 2) Based on the construction monitoring calculation results, a portion of the small pads at the steel beam joints will be removed in a certain proportion to achieve coordinated stress distribution in the steel beam-support system;
[0007] 3) After the small pad blocks are removed, the steel beam falls back and is supported again at the support position after removal, thus achieving the pre-lowering of both ends of the steel beam.
[0008] Preferably, the steel beams of the tower area are connected to the support system by pads, which are placed on the slide beams, and the pads are connected to the beam segments by compression-only support.
[0009] Preferably, several support systems are fixed around the lower tower column.
[0010] Preferably, before removing the pad in step 2), the steel beam and the pad are separated by jacks at the lifting support point. After separation, according to construction monitoring instructions, different thicknesses (pre-drop heights) of the pads are manually removed at different locations to achieve a pre-drop of the steel beam support point according to a certain proportion.
[0011] Preferably, the thickness of the steel beam node pads is measured before the bridge deck crane is installed.
[0012] Preferably, two or more sets of pad block systems are provided below the steel beam along the transverse bridge direction. The pad block system includes a number of pad blocks, which are spaced apart along the longitudinal bridge direction and symmetrically arranged with respect to the axis of the lower tower column. The pad blocks are supported at the large nodes of the steel beam.
[0013] Preferably, the lower tower column's axis is used as the centerline, and shims are symmetrically removed. The method for determining the removal height of the shims on one side of the lower tower column's axis is as follows: the pre-reduction height of shim A adjacent to the lower tower column's axis in the longitudinal direction of the steel beam is h1, then the removal height of other shims... Where q is the self-weight intensity of the steel beam; E is the elastic modulus of the steel truss beam; I is the equivalent section moment of inertia of the steel truss beam; and L is the distance between the pad to be removed and pad A.
[0014] The present invention has at least the following beneficial effects: it realizes the coordinated force bearing of steel beam and support, which can not only improve the safety of support under stress, but also significantly reduce the design scale of support and save material costs.
[0015] Other advantages, objectives and features of the present invention will become apparent in part from the following description, and in part from those skilled in the art through study and practice of the invention. Attached Figure Description
[0016] Figure 1 This is a schematic diagram of the tower support structure of the present invention;
[0017] Figure 2 This is a schematic diagram of the pad removal of the present invention;
[0018] Figure 3 This is a schematic diagram of the pad structure of the present invention;
[0019] Figure 4 This is a linear graph showing the relationship between the pad height and axial force in this invention.
[0020] Marking description: 1 pad block, 2 bridge deck crane, 3 steel beam, 4 jack, 5 lower tower column, 6 lower crossbeam, 7 tie rod, 8 diagonal brace, 9 wall tie rod, 10 steel pipe column, 11 steel plate, 12 slide beam. Detailed Implementation
[0021] The present invention will now be described in detail and completely with reference to the accompanying drawings. Those skilled in the art will be able to implement the present invention based on these descriptions. Before describing the present invention with reference to the accompanying drawings, it should be particularly noted that the technical solutions and features provided in various parts of the present invention, including the following description, can be combined with each other without conflict.
[0022] Furthermore, the embodiments of the present invention described below are generally only some, not all, of the embodiments of the present invention. Therefore, all other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort should fall within the scope of protection of the present invention.
[0023] The present invention will be further described in detail below with reference to the accompanying drawings and embodiments. The specific implementation process is as follows:
[0024] like Figures 1-4 As shown, the present invention provides a method for optimizing the stress of a tower support system, comprising the following steps:
[0025] 1) The steel beams in the tower area are supported by support blocks, sliding beams and bracket system at large nodes. After the steel beam segments in the tower area are installed and the alignment is adjusted to meet the construction monitoring requirements, temporary constraints are applied to the tower beams. The support blocks are composed of several small blocks in the height direction. In this embodiment, the small blocks are steel plates of different thicknesses (1mm to 100mm) or steel sleepers (1500mm×200mm×150mm) to achieve different extraction heights of the blocks.
[0026] 2) Before the steel beams are mounted on the bridge deck crane, based on the construction monitoring calculations, a portion of the pads at the steel beam joints are removed in a certain proportion. By utilizing the rigidity of the steel beams themselves to generate deflection at the front end, the axial force of the support system columns is reduced. By adjusting the height of the pads, the distribution of the steel truss beam's self-weight and the load on the beam within the support system is achieved, thus realizing the coordinated force distribution between the steel beam and the support system. This not only improves the safety of the support system under stress but also significantly reduces the design scale of the support system, saving material costs.
[0027] 3) After the small pad blocks are removed, the steel beam falls back down and is re-supported at the removed support position, achieving pre-lowering at both ends of the steel beam. As the thickness of the pad blocks changes, the axial force of the support column gradually decreases, while the stress at the front end of the steel beam cantilever gradually increases. By monitoring and calculating the results, a reasonable steel beam-support coordinated stress distribution method is achieved. Among them, the maximum stress σ of the steel beam under various unfavorable combined working conditions is less than the allowable stress of the steel structure [σ]. Figure 4The monitoring and calculation show that as the height of the support increases, the axial force of each column decreases significantly, which is very beneficial for improving the stress on the support structure.
[0028] This technical solution may also include the following technical details to better achieve the technical effect: the steel beams of the tower area are connected to the support system by pads, the pads are placed on the slide beams, and the pads and beam segments are connected by a compression-only support method.
[0029] This technical solution may further include the following technical details to better achieve the technical effect: Several support systems are fixed around the lower tower column. The support system includes tie rods, diagonal braces, wall-mounted rods, and steel pipe columns; the steel pipe columns are connected as a whole by diagonal braces, extending (or inclined or vertically) along the height direction of the lower tower column. The upper end of the steel pipe column is fixed to the tie rod, and the lower end is fixed to the lower tower column. The tie rod is horizontally positioned and fixed to the lower tower column and / or the lower crossbeam. Several wall-mounted rods provide a more stable connection between the support system and the lower tower column. The tie rod is fixed to the slide beam by support members.
[0030] This technical solution may also include the following technical details to better achieve the technical effect: Before the pad is removed in step 2), the steel beam and the pad are separated by jacks at the lifting support point. After separation, according to the construction monitoring instructions, different thicknesses (pre-reduction heights) of different pads are manually removed to achieve a pre-reduction of the steel beam support point according to a certain proportion.
[0031] This technical solution may also include the following technical details to better achieve the technical effect: During the entire process of the support system being stressed, the support system is under the greatest stress during the bridge deck crane hoisting operation. Therefore, the thickness of the steel beam node pad block is extracted before the bridge deck crane is installed.
[0032] This technical solution may also include the following technical details to better achieve the technical effect: two or more sets of pad block systems are provided under the steel beam along the transverse bridge direction, the pad block system includes several pad blocks, the pad blocks are spaced apart along the longitudinal bridge direction and symmetrically arranged with respect to the axis of the lower tower column; the pad blocks are supported at the large nodes of the steel beam.
[0033] This technical solution may also include the following technical details to better achieve the technical effect: The pads located at the two ends along the longitudinal direction of the bridge are used to determine the elevation of the steel beam erection and are generally not removed. Taking the axis of the lower tower column as the centerline, the pads are removed symmetrically. The method for determining the removal height of the pads on one side of the lower tower column axis is as follows (the other side is removed symmetrically): The pre-drop height of pad A adjacent to the axis of the lower tower column in the longitudinal direction of the steel beam is h1, then the removal height of other pads... Where q is the self-weight intensity of the steel beam (equivalent to a line load); E is the elastic modulus of the steel truss beam; I is the equivalent section moment of inertia of the steel truss beam; and L is the distance between the pad to be removed and pad A.
[0034] Example 1
[0035] A method for optimizing the stress distribution of a tower support system includes the following steps:
[0036] (1) The steel beams in the tower area are supported by a support pad at the large node → sliding beam → support system. After the steel beam segments in the tower area are installed and the alignment is adjusted to meet the construction monitoring requirements, temporary constraints are applied to the tower beams. The support system includes tie rods, diagonal braces, wall-mounted rods, and steel pipe columns (column 1, column 2, column 3, column 4, column 5); two sets of pad systems are set along the transverse direction of the bridge, and each set of pad systems along the longitudinal direction of the bridge includes 6 pads. Three pads are set on each side of the lower tower column axis.
[0037] (2) Before the steel beam is placed on the bridge deck crane, based on the construction monitoring calculation results, a portion of each of the pads 1 to 3 at the steel beam joints is removed in a certain proportion, and pads are symmetrically removed on the other side. By utilizing the rigidity of the steel beam itself to generate deflection at the front end, the axial force of the support column is reduced. By adjusting the height of the pads, the self-weight of the steel truss beam and the load on the beam are distributed on the support, so as to achieve the coordinated force of the steel beam and the support. This not only improves the safety of the support under stress, but also significantly reduces the design scale of the support and saves material costs.
[0038] The steel beam-support system was temporarily constrained by the tower beam, meaning that the steel beam nodes at pad 3 and pad 4 can be considered as constrained in both the longitudinal and transverse directions.
[0039] like Figure 2 As shown, the heights of the pads are h1, h2, and h3, respectively. The steel truss beam is equivalent to a cantilever beam bearing a uniformly distributed load, with pads 3 and 4 as the constraint boundaries. Where q is the self-weight intensity of the steel truss (equivalent to a line load); E is the elastic modulus of the steel truss; and I is the equivalent moment of inertia of the steel truss section. (Padded blocks 4, 5, and 6 are symmetrically removed).
[0040] The rules for removing padding blocks are based on the formula described above.
[0041] like Figure 3 As shown, the pads are made of steel plates of different thicknesses (1mm to 100mm) or steel pillows (1500mm×200mm×150mm) to achieve different extraction heights for the pads.
[0042] Pad removal method: By using jacks at the jacking support point, the steel beam is separated from the pad block. After separation, according to the construction monitoring instructions, different thicknesses (pre-drop height) of different pad blocks are manually removed to achieve a pre-drop of the steel beam support point according to a certain proportion.
[0043] (3) After the pad blocks are removed, the jacks are returned to their original positions to allow the steel beam to fall back down. The main steel beam is then re-supported at the removed support position, achieving pre-lowering at both ends of the steel beam. As the thickness of the pad blocks changes, the axial force of the support column gradually decreases, while the stress at the cantilever front end of the main steel beam gradually increases. By monitoring and calculating the results, a reasonable method of coordinated stress distribution between the main steel beam and the support is achieved. Among these, the maximum stress σ of the main steel beam under various unfavorable combined working conditions is less than the allowable stress of the steel structure [σ]. Figure 4 The monitoring and calculation show that as the height of the support increases, the axial force of each column decreases significantly, which is very beneficial for improving the stress on the support structure.
[0044] As the height of the padding increases, the maximum stress of the steel truss increases almost linearly. For every 10mm reduction of padding block 3 (or 4), the stress in the steel truss increases by 10MPa. However, the stress in the tower support decreases significantly; for every 10mm reduction of padding block 3 (or 4), the stress decreases by approximately 30MPa. This indicates that with the increase of padding height, the axial force changes most significantly in columns 1 and 5, followed by columns 2 and 4, while the axial force change in column 3 is the smallest.
[0045] (4) During the entire process of the support being stressed, the support is under the greatest stress during the bridge crane hoisting process. Therefore, the thickness of the steel main beam node pad is extracted before the bridge crane is installed.
[0046] Although embodiments of the present invention have been disclosed above, they are not limited to the applications listed in the specification and embodiments. They can be applied to various fields suitable for the present invention. For those skilled in the art, other modifications can be easily made. Therefore, without departing from the general concept defined by the claims and their equivalents, the present invention is not limited to the specific details and embodiments shown and described herein.
Claims
1. A method for optimizing the stress distribution of a tower support system, characterized in that, Includes the following steps: 1) The steel beams in the tower area are supported by support pads, sliding beams, and a support system at large nodes. Several support systems are fixed around the lower tower column. The support system includes tie rods, diagonal braces, wall-mounted rods, and steel pipe columns. The steel pipe columns are connected into a whole by diagonal braces. The steel pipe columns extend either inclined or vertically along the height direction of the lower tower column. The upper end of the steel pipe column is fixed to the tie rod, and the lower end is fixed to the lower tower column. The tie rod is set horizontally and fixed to the lower tower column and / or the lower crossbeam. Several wall-mounted rods provide a more stable connection between the support system and the lower tower column. After the steel beam segments in the tower area are installed and their alignment is adjusted to meet construction monitoring requirements, temporary constraints are applied to the tower beams. The support blocks consist of several small blocks in the height direction, and are connected to the beam segments using only compression support. Two or more sets of support block systems are installed below the steel beams along the transverse bridge direction. Each support block system includes several blocks, which are spaced apart along the longitudinal bridge direction and symmetrically arranged relative to the axis of the lower tower column. The support blocks are placed at the major nodes of the steel beams. The support blocks located at the two ends along the longitudinal bridge direction are used for steel beam erection elevation control and are not subject to removal. 2) Before the bridge deck crane is installed, based on the construction monitoring calculations, a portion of the pads at the steel beam joints are removed in a certain proportion to achieve coordinated force distribution between the steel beam and the support system. Before removing the pads, the steel beam is detached from the pads by using jacks at the jacking points. After detachment, different thicknesses (pre-drop heights) of different pads are manually removed according to the construction monitoring instructions to achieve a pre-drop of the steel beam support points in a certain proportion. The pads are removed symmetrically along the centerline of the lower tower column. The method for determining the removal height of the pads on one side of the lower tower column axis is as follows: the pre-drop height of pad A adjacent to the lower tower column axis in the longitudinal direction of the steel beam is h1, then the removal height h of other pads is h = h1 + Where q is the self-weight intensity of the steel beam; E is the elastic modulus of the steel truss beam; I is the equivalent section moment of inertia of the steel truss beam; and L is the distance between the pad to be removed and pad A. 3) After the small pads are removed, the steel beam falls back down and is resupported at the removed support position, achieving pre-lowering at both ends of the steel beam and determining the maximum stress of the steel beam under various unfavorable working conditions. Allowable stress of steel structure .