Point-supported glass curtain wall installation construction process
By adopting the installation principle of top-to-bottom and vertical-to-horizontal installation during the glass curtain wall installation process, and by using the extension rods and cable trays on the connecting components for adjustment, the problem of inconvenient strength adjustment of glass curtain walls in the prior art has been solved, and the stability and support strength have been improved.
Patent Information
- Application Number
- CN202311025325.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-15
- Publication Date
- 2025-12-30
- Estimated Expiration
- 2043-08-15
AI Technical Summary
When installing existing point-supported glass curtain walls, the use of embedded parts and glass auxiliary panels for auxiliary support makes it difficult to adjust the strength of the glass curtain wall, thus affecting its stability.
The installation follows the principle of top-to-bottom and vertical-to-horizontal installation. Adjustments are made by setting extension rods and cable trays on the connecting components. Adjusting screws and rotating rods are used to raise and lower the cables. Multiple supports are provided by auxiliary glass and support rods to ensure the stability of the glass curtain wall.
This allows for adjustment of the glass curtain wall's strength after installation, improving its stability and support strength, and ensuring installation quality and aesthetics.
Smart Images

Figure CN117071910B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of glass curtain wall installation and construction technology, specifically a point-supported glass curtain wall installation and construction process. Background Technology
[0002] Point-supported glass curtain walls consist of decorative glass panels, connecting components, and supporting structures. They are classified into flat-head and convex-head point-supported glass curtain walls according to their exterior decorative effect, and into glass rib point-supported glass curtain walls, steel structure point-supported glass curtain walls, steel tie rod point-supported glass curtain walls, and steel cable point-supported glass curtain walls according to their supporting structures. The diverse supporting structures can meet the needs of different building structures and decorative effects.
[0003] For example, the Chinese authorized patent with announcement number CN211396169U (an installation structure for a point-supported glass curtain wall) includes two glass panels arranged parallel to the wall surface of the building, a glass rib plate arranged vertically and fixedly connected between the building wall and the glass panels, and a clamp connecting the glass panels and the glass rib plate. The glass rib plate is perpendicular to the glass panels, and the two glass panels are symmetrically distributed along the width center line of the glass rib plate. A gap is provided between the two glass panels. One end of the clamp is provided with a connecting component connecting the two glass panels. The connecting component includes a first fixing plate located on the side of the glass panel away from the glass rib plate, a second fixing plate located on the side of the glass panel closer to the glass rib plate, and a threaded fastener passing through the first fixing plate and threadedly connected to the second fixing plate. The threaded fastener is located within the gap. The other end of the clamp is fixedly connected to the building wall through a pre-embedded part, thereby improving the stability of the glass curtain wall.
[0004] However, the existing point-supported glass curtain walls rely on embedded parts and glass auxiliary plates for auxiliary support during installation. Once fixed, it is inconvenient to adjust the strength of the glass curtain wall to be installed, thus affecting its stability. Therefore, it does not meet the current needs. To address this, we propose a point-supported glass curtain wall installation process. Summary of the Invention
[0005] The purpose of this invention is to provide a point-supported glass curtain wall installation process to solve the problem mentioned in the background art that existing point-supported glass curtain walls rely on embedded parts and glass auxiliary plates for auxiliary support during installation. Once fixed, it is inconvenient to adjust the strength of the glass curtain wall to be installed, thus affecting its stability.
[0006] To achieve the above objectives, the present invention provides the following technical solution: a point-supported glass curtain wall installation construction process, comprising the following steps:
[0007] Step 1: First, lay out the lines to determine the control points. Connect each pair of horizontal control points with guy lines. The connected guy lines form a net in the air. Mark each intersection with a pen to ensure that the intersections of the guy lines remain unchanged during construction. Then, position, install, and inspect the guy lines and suspension rods. The accuracy of the installation and positioning of the suspension rods directly affects whether the glass can be installed according to the design drawings, and affects the flatness of the glass curtain wall after installation, the width of the sealant joint, and the stability of the glass curtain wall. Therefore, the installation sequence, adjustment accuracy, and prestress value of the suspension rods must be strictly controlled in order to effectively control the installation quality of the glass curtain wall.
[0008] Step Two: Installation follows the principle of top-to-bottom and vertical-to-horizontal installation. For vertical cables, the cable length is increased by 1mm-3mm from the top structure, starting from the top. The cables are in a free state. Adjustments are made after all vertical cables are installed, also from top to bottom, adjusting the suspension rods layer by layer according to the size control unit. For horizontal cables, after the vertical cables are installed and adjusted, connect the horizontal cables. Before installation, the horizontal cables should be increased by 1mm-3mm from the length designed in the drawings, in a free state. Install them from top to bottom, layer by layer according to the control unit. Adjust them in place after all installations are completed. Then, the positioning and adjustment of the suspension rods are carried out. During the installation of the suspension rods, the geometric dimensions of the installation positioning of the rods must be checked. The length dimensions of the front and rear cables must be strictly adjusted according to the dimensions in the drawings to ensure the perpendicularity of the suspension connecting rods to the glass plane. The adjustment is based on the unit control point to verify the center position of each suspension rod, ensuring that the front end of each suspension rod is consistent with the glass plane. The overall flatness error is controlled within <5mm / 3m.
[0009] Step 3: Next, conduct a counterweight test. Since the self-weight load of the glass curtain wall and other loads it bears are transferred to the main support structure through the suspended rod structure, in order to ensure that the deformation of the tie rod system is within the allowable range after the glass is installed, a counterweight test must be conducted on the suspended rod. The counterweight test should be set according to the control unit. The weight of the counterweight is the gravity load generated by the glass on the suspended rod multiplied by a coefficient of 1-1.2. The structural deformation after counterweighting should be less than 2mm. During the counterweight test, the counterweight should be applied gradually. The deformation of the suspended rod should be tested after each addition, until all the counterweights are applied to the suspended rod. The deformation value and the reset status after unloading should be measured and recorded in detail.
[0010] Step 4: Before glass installation, check and verify that the verticality, elevation, beam height, and horizontality of the main steel structure support meet the design requirements. Pay special attention to the re-checking of the installation hole positions. Before installation, the surface and bottom of the steel channel must be locally cleaned with a steel brush. Neoprene rubber pads should be added to the U-shaped steel channel at the bottom of the glass joint at 1 / 4 width from the edge of the glass. Before installation, clean the glass and suction cups. Determine the number of suction cups according to the weight of the glass and the specifications of the suction cups. First, check whether the installation position of the connecting claws is accurate. Assemble the connector and glass on the installation platform, and then install it with the connecting claws. To ensure the airtightness and watertightness of the connector, a torque wrench must be used. Determine the torque according to the specific specifications and dimensions of the connecting system. When installing the glass according to the standard, it should always be suspended on the two connectors.
[0011] Step 5: Then install the auxiliary glass onto the connecting assembly for secondary reinforcement and apply adhesive to fix it in place;
[0012] Step Six: Before applying the sealant, clean the glass and steel channel areas with xylene or industrial ethanol and a clean towel. Seal the gap between the bottom of the glass and the steel channel with foam tape to ensure straightness and leave a clearance of 8mm-12mm for the sealant thickness. Apply protective tape to the areas to be sealed, ensuring the tape and sealant joint are straight. Apply the sealant continuously and evenly. The general order of operation is to seal the horizontal joints first and then the vertical joints. Vertical joints should be sealed from top to bottom. After filling the sealant, check for air bubbles, voids, gaps, and impurities. If any are found, deal with them promptly. When applying sealant the next day, clean the sealant head at the joint and cut off the sealant tail from the previous application to ensure a tight connection between the two sealants. After the glass sealant is applied, quickly remove the tape from the glass. After the glass sealant has cured, clean the inside and outside glass and mark the protective areas.
[0013] It also includes a connecting assembly, on which a first fixing frame is provided, an auxiliary glass is installed inside the first fixing frame, a second fixing frame is provided at the front end of the auxiliary glass, a second placement slot is provided inside the second fixing frame, and the front end face of the auxiliary glass is inserted into the second placement slot.
[0014] Preferably, the curtain wall glass is provided in a plurality of pieces, and glass glue is provided between each plurality of curtain wall glass pieces. A first limiting plate is provided at the top and bottom ends of each curtain wall glass piece, and a second limiting plate is provided on both side ends of each curtain wall glass piece. A first placement groove is provided inside the first limiting plate and the second limiting plate, and the curtain wall glass pieces are inserted and connected to the first placement grooves on all four sides.
[0015] Preferably, a fixing block is provided at both the upper and lower ends of the front end face of the curtain wall glass, a first support rod is installed between the fixing blocks, a fixing screw is installed on one side of the fixing block, and a second support rod is installed between the first support rods.
[0016] Preferably, a fixing screw is installed on one side of the first fixing frame and the second fixing frame, and a connecting rod is provided on both end faces of the first fixing frame, and four connecting rods are provided.
[0017] Preferably, an extension rod is provided on one side of the connecting rod, an adjusting screw is installed on the connecting rod, a fixing plate is provided on one side of the extension rod, and four fixing plates are provided.
[0018] Preferably, the fixing plate is provided with a fixing rod, the front end of the fixing rod is provided with a connecting plate, and the top of the connecting plate is provided with a reinforcing screw.
[0019] Preferably, the front end of the second fixing frame is provided with a cable tray, the cable tray is provided with cable grooves on all four sides, the front end face of the cable tray is provided with an installation groove, and the cable tray is provided with a rotating rod inside.
[0020] Preferably, both the first and second support rods are provided with placement slots inside, and both the first and second support rods are provided with connection ports at their connection points.
[0021] Preferably, the front end face of the first support rod is provided with a connecting hole, a rotating disk is installed on the connecting hole, and a handle is installed inside the rotating disk.
[0022] Compared with the prior art, the beneficial effects of the present invention are:
[0023] 1. This invention provides an extension rod on the connecting rods on both sides of the connecting assembly, allowing the fixing plate to extend to different lengths. This enables the connecting rods to be adjusted according to the curtain wall glass, and the extension rods can be fixed using adjusting screws. Simultaneously, a cable tray is provided on the second fixing frame. The cable tray contains longitudinal and transverse cables that pass through cable grooves for connection and fixation. After the curtain wall glass is installed and all cables are installed, adjustments are made by rotating the rotating plate with a lever, which allows the rotating lever to extend and retract the cables, thereby strengthening the support. This solves the problem that existing point-supported glass curtain walls rely on embedded parts and glass auxiliary plates for auxiliary support during installation, making it inconvenient to adjust the strength of the installed glass curtain wall once fixed, thus affecting its stability.
[0024] 2. By setting an auxiliary glass between the first and second fixed frames, multiple supports are provided after installation using cables, connecting components, and the auxiliary glass, ensuring the stability of the glass after installation and guaranteeing the overall support strength.
[0025] 3. By setting up a first support rod and a second support rod, both of which have placement grooves inside, the cable can be placed inside the placement grooves, which not only protects the cable but also ensures the aesthetics of the glass installation. Attached Figure Description
[0026] Figure 1 This is a partial structural diagram of the point-supported glass curtain wall installation according to the present invention;
[0027] Figure 2 This is an enlarged schematic diagram of the point-supported glass curtain wall connection component structure of the present invention;
[0028] Figure 3 This is an enlarged schematic diagram of the point-supported glass curtain wall support component structure of the present invention;
[0029] Figure 4 This is an enlarged schematic diagram of the point-supported glass curtain wall cable fastening structure of the present invention;
[0030] Figure 5 This is an enlarged schematic diagram of the point-supported glass curtain wall structure at point A of the present invention;
[0031] Figure 6 This is a schematic diagram of the installation steps of the point-supported glass curtain wall according to the present invention;
[0032] In the diagram: 1. Curtain wall glass; 2. First limiting plate; 3. Second limiting plate; 4. First placement slot; 5. Fixing block; 6. Fixing screw; 7. First support rod; 8. Second support rod; 9. Connecting assembly; 10. First fixing frame; 11. Auxiliary glass; 12. Fixing plate; 13. Fixing rod; 14. Connecting plate; 15. Reinforcing screw; 16. Connecting rod; 17. Extension rod; 18. Adjusting screw; 19. Placement slot; 20. Connection port; 21. Cable tray; 22. Cable groove; 23. Rotating rod; 24. Connecting hole; 25. Rotating plate; 26. Handle; 27. Second fixing frame; 28. Second placement slot; 29. Installation slot. Detailed Implementation
[0033] The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings of the embodiments of the present invention. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments.
[0034] Please see Figure 1-6 The present invention provides an embodiment of a point-supported glass curtain wall installation construction process, comprising the following steps:
[0035] Step 1: First, lay out the lines to determine the control points. Connect each pair of horizontal control points with guy lines. The connected guy lines form a net in the air. Mark each intersection with a pen to ensure that the intersections of the guy lines remain unchanged during construction. Then, position, install, and inspect the guy lines and suspension rods. The accuracy of the installation and positioning of the suspension rods directly affects whether the glass can be installed according to the design drawings, and affects the flatness of the glass curtain wall after installation, the width of the sealant joint, and the stability of the glass curtain wall. Therefore, the installation sequence, adjustment accuracy, and prestress value of the suspension rods must be strictly controlled in order to effectively control the installation quality of the glass curtain wall.
[0036] Step Two: Installation follows the principle of top-to-bottom and vertical-to-horizontal installation. For vertical cables, the cable length is increased by 1mm-3mm from the top structure, starting from the top. The cables are in a free state. Adjustments are made after all vertical cables are installed, also from top to bottom, adjusting the suspension rods layer by layer according to the size control unit. For horizontal cables, after the vertical cables are installed and adjusted, connect the horizontal cables. Before installation, the horizontal cables should be increased by 1mm-3mm from the length designed in the drawings, in a free state. Install them from top to bottom, layer by layer according to the control unit. Adjust them in place after all installations are completed. Then, the positioning and adjustment of the suspension rods are carried out. During the installation of the suspension rods, the geometric dimensions of the installation positioning of the rods must be checked. The length dimensions of the front and rear cables must be strictly adjusted according to the dimensions in the drawings to ensure the perpendicularity of the suspension connecting rods to the glass plane. The adjustment is based on the unit control point to verify the center position of each suspension rod, ensuring that the front end of each suspension rod is consistent with the glass plane. The overall flatness error is controlled within <5mm / 3m.
[0037] Step 3: Next, conduct a counterweight test. Since the self-weight load of the glass curtain wall and other loads it bears are transferred to the main support structure through the suspended rod structure, in order to ensure that the deformation of the tie rod system is within the allowable range after the glass is installed, a counterweight test must be conducted on the suspended rod. The counterweight test should be set according to the control unit. The weight of the counterweight is the gravity load generated by the glass on the suspended rod multiplied by a coefficient of 1-1.2. The structural deformation after counterweighting should be less than 2mm. During the counterweight test, the counterweight should be applied gradually. The deformation of the suspended rod should be tested after each addition, until all the counterweights are applied to the suspended rod. The deformation value and the reset status after unloading should be measured and recorded in detail.
[0038] Step 4: Before glass installation, check and verify that the verticality, elevation, beam height, and horizontality of the main steel structure support meet the design requirements. Pay special attention to the re-checking of the installation hole positions. Before installation, the surface and bottom of the steel channel must be locally cleaned with a steel brush. Neoprene rubber pads should be added to the U-shaped steel channel at the bottom of the glass joint at 1 / 4 width from the edge of the glass. Before installation, clean the glass and suction cups. Determine the number of suction cups according to the weight of the glass and the specifications of the suction cups. First, check whether the installation position of the connecting claws is accurate. Assemble the connector and glass on the installation platform, and then install it with the connecting claws. To ensure the airtightness and watertightness of the connector, a torque wrench must be used. Determine the torque according to the specific specifications and dimensions of the connecting system. When installing the glass according to the standard, it should always be suspended on the two connectors.
[0039] Step 5: Then install the auxiliary glass onto the connecting assembly for secondary reinforcement and apply adhesive to fix it in place;
[0040] Step Six: Before applying the sealant, clean the glass and steel channel areas with xylene or industrial ethanol and a clean towel. Seal the gap between the bottom of the glass and the steel channel with foam tape to ensure straightness and leave a clearance of 8mm-12mm for the sealant thickness. Apply protective tape to the areas to be sealed, ensuring the tape and sealant joint are straight. Apply the sealant continuously and evenly. The general order of operation is to seal the horizontal joints first and then the vertical joints. Vertical joints should be sealed from top to bottom. After filling the sealant, check for air bubbles, voids, gaps, and impurities. If any are found, deal with them promptly. When applying sealant the next day, clean the sealant head at the joint and cut off the sealant tail from the previous application to ensure a tight connection between the two sealants. After the glass sealant is applied, quickly remove the tape from the glass. After the glass sealant has cured, clean the inside and outside glass and mark the protective areas.
[0041] It also includes a connecting assembly 9, on which a first fixing bracket 10 is provided. An auxiliary glass 11 is installed inside the first fixing bracket 10. A second fixing bracket 27 is provided at the front end of the auxiliary glass 11. A second placement groove 28 is provided inside the second fixing bracket 27, and the front end of the auxiliary glass 11 is inserted into the second placement groove 28. An extension rod 17 on the connecting assembly 9 allows the fixing plate 12 to extend to different lengths, so that the connecting rod 16 can be adjusted according to the curtain wall glass 1, and the extension rod 17 can be fixed by adjusting screws 18. At the same time, the second fixing bracket 27... A cable tray 21 is installed on the 7th section. The cable tray 21 contains longitudinal and transverse cables that pass through the cable groove 22 for connection and fixation. After the curtain wall glass 1 is installed and all cables are installed, adjustments are made. The rotating disc 25 is rotated using the lever 26, which causes the rotating rod 23 to extend and retract the cables, thereby strengthening the support strength. This solves the problem that existing point-supported glass curtain walls rely on embedded parts and glass auxiliary plates for auxiliary support during installation. Once fixed, it is inconvenient to adjust the strength of the glass curtain wall to be installed, thus affecting its stability.
[0042] Please see Figure 1 The curtain wall glass 1 is provided in several pieces, and glass glue is provided between the several curtain wall glass 1 pieces. The upper and lower ends of the curtain wall glass 1 are provided with first limiting plates 2, and the two side end faces of the curtain wall glass 1 are provided with second limiting plates 3. The first limiting plates 2 and the second limiting plates 3 are provided with first placement grooves 4, and the curtain wall glass 1 is inserted and connected to the first placement grooves 4 on all four sides.
[0043] Please see Figure 1 Fixing blocks 5 are provided at the upper and lower ends of the front face of the curtain wall glass 1. First support rods 7 are installed between the fixing blocks 5. Fixing screws 6 are installed on one side of the fixing blocks 5. Second support rods 8 are installed between the first support rods 7. Placement grooves 19 are provided inside the two support rods. The cable can be placed inside the placement grooves 19, which not only protects the cable but also ensures the aesthetics of the glass installation.
[0044] Please see Figure 2 Fixing screws 6 are installed on one side of the first fixing frame 10 and the second fixing frame 27. Connecting rods 16 are provided on both ends of the first fixing frame 10, and there are four connecting rods 16.
[0045] Please see Figure 2 An extension rod 17 is provided on one side of the connecting rod 16, and an adjusting screw 18 is installed on the connecting rod 16. A fixing plate 12 is provided on one side of the extension rod 17, and four fixing plates 12 are provided.
[0046] Please see Figure 2A fixing rod 13 is provided on the fixing plate 12, a connecting plate 14 is provided at the front end of the fixing rod 13, and a reinforcing screw 15 is provided at the top of the connecting plate 14.
[0047] Please see Figure 2 and Figure 4 The front end of the second fixing frame 27 is provided with a cable tray 21. Cable tray 21 is provided with cable grooves 22 on all four sides. The front end face of cable tray 21 is provided with an installation groove 29. The cable tray 21 is provided with a rotating rod 23. After the curtain wall glass 1 is installed and all cables are installed, adjustments are made. The rotating disc 25 is rotated by the handle 26, so that the rotating rod 23 can retract and extend the cables, thereby strengthening the support strength.
[0048] Please see Figure 3 The first support rod 7 and the second support rod 8 are both provided with placement grooves 19, and the connection points of the first support rod 7 and the second support rod 8 are both provided with serial ports 20.
[0049] Please see Figure 1 and Figure 5 The front end face of the first support rod 7 is provided with a connecting hole 24, a rotating disk 25 is installed on the connecting hole 24, and a handle 26 is installed inside the rotating disk 25.
[0050] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from its spirit or essential characteristics. Therefore, the embodiments should be considered in all respects as exemplary and non-limiting, and the scope of the invention is defined by the appended claims rather than the foregoing description. Thus, all variations falling within the meaning and scope of equivalents of the claims are intended to be included within the present invention. No reference numerals in the claims should be construed as limiting the scope of the claims.
Claims
1. A point-supported glass curtain wall installation construction process, characterized in that: It comprises the following steps: Step one: first, the line is laid to determine the good control points as the basis of each pair of horizontal control points with a line connected, the line after connecting the net surface in the air, with a pen to each intersection point marked to ensure that the intersection point of the line does not change during construction, then the positioning, installation and detection of cable and suspended rod; Step two: then the installation of cable, installation according to the principle of first up and down, first vertical, vertical cable installation, according to the design of the cable length plus 1mm-3mm from the top structure, cable in free state, after the installation of vertical cable is completed, adjustment, horizontal cable installation, after the vertical cable installation adjustment in place, connecting horizontal cable, horizontal cable in installation before according to the design of the length size plus 1mm-3mm, in free state, first up and down, according to the control unit layer by layer installation, after the installation is completed, adjustment in place, after the positioning and adjustment of the suspended rod, the installation of the suspended rod must be checked in the process of positioning the geometric size of the rod; Step three: then the counterweight detection, counterweight detection according to the control unit setting, the weight of the counterweight is the weight of the glass on the suspended rod multiplied by 1-1.2 coefficient, the deformation of the structure after counterweight is less than 2mm, when the counterweight detection, the counterweight is gradually applied, every add a level to the deformation of the suspended rod is detected once, until all the counterweight is applied on the suspended rod, the deformation value and reset after unloading are measured, and detailed records are kept; Step four: before the installation of curtain wall glass (1), check the perpendicularity, elevation, height and horizontal degree of steel structure main support, assemble the adapter with glass on the installation platform, and then install the adapter claw, in order to ensure the air tightness and water tightness of the adapter joint, use the torque wrench, according to the specific size of the adapter system to determine the torque; Step five: then install the auxiliary glass on the adapter assembly, reinforce again, and carry out the glue fixing treatment; Step six: before gluing, clean the glass and steel groove gluing parts with industrial alcohol and clean towel, fill the gap between the adapter glass bottom and steel groove with foam tape, ensure flatness, and reserve 8mm-12mm of gluing thickness, after the glass glue is cured, clean the inside and outside glass. Also include the docking assembly (9), the first fixed frame (10) is arranged on the docking assembly (9), the inside of the first fixed frame (10) is mounted with auxiliary glass (11), the front end of the auxiliary glass (11) is provided with the second fixed frame (27), the inside of the second fixed frame (27) is provided with the second placing groove (28), and the front end surface of the auxiliary glass (11) is insertedly connected with the second placing groove (28); The upper and lower ends of the front end surface of the curtain wall glass (1) are provided with fixed blocks (5), the first support rod (7) is mounted between the fixed blocks (5), the fixed screw (6) is mounted on one side of the fixed block (5), and the second support rod (8) is mounted between the first support rod (7); The fixed screw (6) is mounted on one side of the first fixed frame (10) and the second fixed frame (27), the connecting rod (16) is arranged on the two side end surfaces of the first fixed frame (10), and the connecting rod (16) is provided with four; The extension rod (17) is arranged on one side of the connecting rod (16), the adjusting screw (18) is mounted on the connecting rod (16), the fixed disc (12) is arranged on one side of the extension rod (17), and the fixed disc (12) is provided with four.
2. The point-supported glass curtain wall installation construction process of claim 1, wherein: The curtain wall glass (1) is provided with a plurality of curtain wall glasses (1), and the glass glue is arranged between the plurality of curtain wall glasses (1); The upper and lower ends of the curtain wall glass (1) are provided with first limiting plates (2), and the two side end surfaces of the curtain wall glass (1) are provided with second limiting plates (3); The inside of the first limiting plate (2) and the second limiting plate (3) is provided with a first placing groove (4), and the periphery of the curtain wall glass (1) is insertedly connected with the first placing groove (4).
3. The point-supported glass curtain wall installation construction process of claim 1, wherein: The fixed disc (12) is provided with a fixed rod (13), the front end of the fixed rod (13) is provided with a connecting disc (14), and the top of the connecting disc (14) is provided with a reinforcing screw (15).
4. The point-supported glass curtain wall installation construction process of claim 1, wherein: The front end of the second fixed frame (27) is provided with a cable disc (21), the periphery of the cable disc (21) is provided with a cable groove (22), the inside of the front end surface of the cable disc (21) is provided with a mounting groove (29), and the inside of the cable disc (21) is provided with a rotating rod (23).
5. The point-supported glass curtain wall installation construction process of claim 1, wherein: The inside of the first support rod (7) and the second support rod (8) is provided with a placing groove (19), and the connecting portion of the first support rod (7) and the second support rod (8) is provided with a connecting serial port (20).
6. The point-supported glass curtain wall installation construction process of claim 1, wherein: The front end surface of the first support rod (7) is provided with a connecting hole (24), the connecting hole (24) is mounted with a rotating disc (25), and the inside of the rotating disc (25) is mounted with a handle rod (26).
Citation Information
Patent Citations
Mounting structure of point-supported glass curtain wall
CN211396169U
Building glass panel wall mounting structure and construction method thereof
CN111622393A
Construction method of prestressed single-layer two-way cable net structure curtain wall
CN115110672A
Rib connection point support type curtain wall with pull cable
CN200982040Y
Point-supporting glass curtain wall connection claw
CN201459973U