Tunnel drainage board paving trolley and construction method thereof

By designing tunnel drainage board laying trolleys, the automation system is used to solve the problems of low laying efficiency and poor quality in the existing technology, and efficient and automated drainage board laying is achieved to adapt to the construction needs of tunnels of different diameters and specifications, and improve the construction needs of tunnels. Construction efficiency and quality.

CN117072234BActive Publication Date: 2024-11-19GUANGDONG NO 2 HYDROPOWER ENGINEERING COMPANY LTD +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211155762.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-22
Publication Date
2024-11-19
Estimated Expiration
2042-09-22

AI Technical Summary

Technical Problem

The existing drainage board laying project is inefficient. Although the quality of manual fitting is high, the efficiency is low. The compression structure after mechanical laying is poor, resulting in low laying quality.

Method used

A tunnel drainage plate laying trolley was designed, using frames, rollers, hydraulic cylinders, drive motors and climbing motors and other components. The automatic system can quickly lay and press the drainage plate to adapt to tunnels of different diameters and specifications. It has the characteristics of high efficiency, automation and mechanization.

Benefits of technology

It realizes rapid, automated and efficient laying of drainage plates, strong applicability, and can be laid on a large area in deep buried long-distance water supply tunnels. The paving quality is high, adapting to the transition of tunnels of different diameters and specifications, and improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117072234B_ABST
    Figure CN117072234B_ABST
Patent Text Reader

Abstract

A tunnel drainage board paving trolley and a construction method thereof, the paving trolley is provided with a lifting hydraulic cylinder and a second roller, the lifting of the lifting hydraulic cylinder can drive the second roller to lift up and down to lift the frame, when the paving trolley moves to a tunnel with a sudden change in specifications, the paving trolley can be smoothly transitioned by lifting, and has the characteristics of high mechanization, strong applicability, and high efficiency. In addition, the paving trolley is also provided with a sliding guide rail, a sliding frame, and a climbing motor, the sliding guide rail is annular and similar to the shape of the tunnel wall, the climbing motor drives the sliding frame to move along the sliding guide rail to achieve the initial paving of the drainage board on the tunnel wall, the top pressure hydraulic cylinder is arranged in an annular shape, the top pressure hydraulic cylinder is connected to a pressing plate, and the top pressure hydraulic cylinder drives the pressing plate to move outward to achieve the pressing of the drainage board on the tunnel wall. The paving trolley is highly practical, highly automated, and has a good paving effect, and can be used for large-area drainage board paving in deep buried long-distance water supply shield tunnels.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel operation, and in particular to a tunnel drainage board paving trolley and a construction method thereof. Background Art

[0002] Drainage boards are made of polystyrene (HIPS) or polyethylene (HDPE) plastic base plates that are stamped into conical protrusions or convex points with stiffening ribs (or hollow cylindrical porous). They are used in greening projects, municipal projects, construction projects; water conservancy projects, transportation projects, etc. In the construction of water supply tunnels, it is necessary to lay drainage boards on the walls of tunnel segments, and then install the lining steel pipes and pour self-compacting concrete. The laying of drainage boards needs to be 240° along the tunnel plan according to the process requirements. Because the laying area of ​​drainage boards is large, the laying efficiency directly affects the construction period of the lining steel pipe installation and the pouring of self-compacting concrete.

[0003] Existing drainage board paving projects are usually done by manual lamination. Although this method has low overall efficiency, there are fewer mistakes in manual paving and the paving quality is relatively high. The other part is done by mechanical paving. Although the existing paving device is efficient, the compaction structure after machine paving is poor and manual compaction is often required, which makes the paving quality relatively low. Summary of the invention

[0004] In view of the shortcomings of the prior art, the present invention provides a tunnel drainage board paving trolley and a construction method thereof. The paving trolley is highly practical, highly automated, and has a good paving effect. It can be used for large-area drainage board paving in deeply buried, long-distance water supply shield tunnels. In addition, the paving trolley can also realize mobile transition between tunnels of different diameters and specifications, and has the characteristics of high mechanization, strong applicability, and high efficiency.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is:

[0006] A tunnel drainage board paving trolley is provided, comprising a frame, a first roller, a second roller, a driving motor, a lifting hydraulic cylinder, a top pressure hydraulic cylinder and a climbing motor, wherein the first roller is arranged at the bottom of the frame, the lifting hydraulic cylinder is respectively arranged vertically at the front and rear sides of the trolley, the second roller is arranged at the bottom of the lifting hydraulic cylinder, and the lifting and lowering of the lifting hydraulic cylinder can drive the second roller to lift the frame, the driving motor is respectively connected to the first roller and the second roller, and the first roller and the second roller are driven to rotate by the driving motor to realize the movement of the frame; The frame is provided with an annular sliding guide rail, and a sliding frame is slidably connected to the sliding guide rail. The sliding frame is respectively provided with a rotating roller and an output roller. The rotating roller is provided with a drainage board roll, and the drainage board roll is connected to the output roller for output. The climbing motor is installed on the sliding frame to drive the sliding frame to move so that the drainage board is attached to the tunnel wall; the top pressure hydraulic cylinder is arranged in a ring on the frame along a direction parallel to the sliding guide rail, and the top pressure hydraulic cylinder is connected to a clamping plate, which is used to drive the clamping plate to move outward so that the drainage board is pressed against the tunnel wall.

[0007] As a further improvement of the present invention, the lifting hydraulic cylinder is downwardly connected to a lifting frame, and the second roller is arranged at the lower part of the lifting frame.

[0008] As a further improvement of the present invention, it also includes a telescopic sleeve and a sliding rod, the telescopic sleeve is fixed on the frame, the sliding rod is slidably sleeved in the telescopic sleeve, the top pressure hydraulic cylinder is connected to the sliding rod to drive the sliding rod to extend the telescopic sleeve outward, and the sliding rod is connected to the clamping plate.

[0009] As a further improvement of the present invention, the climbing motor is connected to a climbing gear, a transmission rack is provided on the sliding guide rail along its length direction, and the climbing gear is meshed with the transmission rack.

[0010] As a further improvement of the present invention, a first ejection hydraulic cylinder and a first ejection sleeve are provided on the sliding frame, a first push rod is slidably sleeved in the first ejection sleeve, the first ejection hydraulic cylinder is connected to the first push rod and is used to drive the first push rod to extend outward from the first ejection sleeve, and the first push rod is detachably connected to the rotating roller.

[0011] As a further improvement of the present invention, a second ejection hydraulic cylinder and a second ejection sleeve are provided on the sliding frame, a second push rod is slidably sleeved in the second ejection sleeve, the second ejection hydraulic cylinder is connected to the second push rod and is used to drive the second push rod to extend outward from the second ejection sleeve, and the second push rod is connected to the output roller.

[0012] As a further improvement of the present invention, a base frame is provided on the frame, a folding rod and a folding hydraulic cylinder are provided on the base frame, the top of the folding rod is connected to a lifting platform for placing a spare drainage board roll, the folding hydraulic cylinder is connected to the folding rod to drive the folding rod to open or close to push the lifting platform to lift, and a conveyor belt is also provided on the frame, the feed end of the conveyor belt extends to the lifting platform, and the discharge end extends to the sliding frame.

[0013] The present invention also includes a construction method of the above-mentioned tunnel drainage board paving trolley, comprising the following steps:

[0014] S1. Start the drive motor to drive the entire trolley to move to the set position, then stop the drive motor and start the second push-out hydraulic cylinder, the second push-out hydraulic cylinder pushes the second push rod out to drive the output roller to stick to the tunnel wall, and then the drainage plate is output through the output roller and stuck to the tunnel wall;

[0015] S2. Start the climbing motor, which drives the sliding frame to move on the sliding guide rail to drive the output roller to roll on the tunnel wall, so that the output roller continuously outputs the drainage board and continuously lays the drainage board on the tunnel wall;

[0016] S3. As the sliding frame completes a one-way stroke movement, the drainage board is attached to the tunnel wall, and then the top pressure hydraulic cylinders are started to drive the pressing plate to move outward, so that the pressing plate presses the drainage board on the tunnel wall, completing the laying of a section of drainage board.

[0017] As a further improvement of the present invention, when the trolley moves into a tunnel of changed specifications, the lifting hydraulic cylinders on the front and rear sides of the frame are respectively started to drive the second roller to move downward until the second roller contacts the ground to lift the frame to a set height position, and then the drive motor is started to drive the entire frame forward through the second roller until the entire frame enters a tunnel of another specification, and the lifting hydraulic cylinders on the front and rear sides of the frame are retracted to drive the entire frame to move downward until the first roller of the frame contacts the ground.

[0018] As a further improvement of the present invention, when the drain board roll needs to be replaced, the folding hydraulic cylinder is started to push the folding rod to open, thereby pushing the lifting platform and the spare drain board roll on the lifting platform to the feed end of the conveyor belt, and then transported to the sliding frame through the conveyor belt, and then the rotating roller is removed from the first push rod, and the rotating roller is inserted into the new drain board roll, and finally the position of the first ejection hydraulic cylinder and the climbing motor is controlled to reconnect the rotating roller to the first push rod.

[0019] The beneficial effects of the present invention are:

[0020] 1. The paving trolley is provided with an annular sliding guide rail. The sliding guide rail is similar in shape to the tunnel wall. The climbing motor drives the sliding frame to move to initially lay the drainage board on the tunnel wall. Finally, the top pressure hydraulic cylinder drives the pressing plate to move outward to press the drainage board on the tunnel wall, completing the laying of the drainage board on a section of the tunnel wall, realizing the rapid laying of the drainage board, and the laying process has a high degree of automation, high efficiency, high laying quality and strong practicality.

[0021] Second, the paving trolley can realize the mobile transition between tunnels of different diameters and specifications to adapt to tunnels of different diameters and specifications, and has the characteristics of high mechanization, strong applicability and high efficiency. The paving trolley is provided with a first roller, a second roller, a lifting hydraulic cylinder and a driving motor. The conventional movement of the paving trolley is realized by the first roller. When the paving trolley moves to a tunnel with a sudden change in specifications, the lifting hydraulic cylinder drives the second roller to lift the paving trolley, and at the same time, the second roller is used to realize the movement of the trolley, thereby realizing a fast and smooth transition of the paving trolley to facilitate the subsequent paving of drainage boards. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 The overall structure of the present invention is three-dimensional Figure 1 .

[0023] Figure 2 The overall structure of the present invention is three-dimensional Figure 2 .

[0024] Figure 3 for Figure 2 A partial enlarged view of point A in the middle.

[0025] Figure 4 for Figure 2 A partial enlarged view of point B in the middle.

[0026] Figure 5 The overall structure of the present invention is three-dimensional Figure 3 .

[0027] Figure 6 for Figure 5 A partial enlarged view of point C in the middle.

[0028] Figure 7 It is a front view of the present invention.

[0029] Figure 8 It is a side view of the present invention.

[0030] Fig. 9 It is a top view of the present invention.

[0031] Among them, 1 is a frame, 11 is a base frame, 12 is a folding rod, 13 is a folding hydraulic cylinder, 14 is a lifting platform, 15 is a conveyor belt, 2a is a first roller, 2b is a second roller, 21 is a driving motor, 22 is a lifting hydraulic cylinder, 221 is a lifting frame, 31 is a top pressure hydraulic cylinder, 32 is a clamping plate, 33 is a telescopic sleeve, 331 is a sliding rod, 41 is a climbing motor, 411 is a climbing gear, 42 is a sliding guide rail, 421 is a transmission rack, 43 is a sliding frame, 44 is an output roller, 451 is a first push-out hydraulic cylinder, 452 is a first push-out sleeve, 453 is a first push rod, 454 is a rotating roller, 461 is a second push-out hydraulic cylinder, 462 is a second push-out sleeve, 463 is a second push rod, and 5 is a drainage board roll. DETAILED DESCRIPTION

[0032] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0033] See attached Figure 1 To Attachment Fig. 9 As shown, a tunnel drainage board paving trolley includes a frame 1, a first roller 2a, a second roller 2b, a driving motor 21, a lifting hydraulic cylinder 22, a top pressure hydraulic cylinder 31 and a climbing motor 41.

[0034] Four first rollers 2a are respectively arranged at four sides of the bottom of the frame 1. Four lifting hydraulic cylinders 22 are respectively arranged vertically at the front and rear sides of the frame 1, and the lifting hydraulic cylinders 22 on the same side are arranged at intervals from left to right. Four second rollers 2b are respectively arranged at the bottom of the four lifting hydraulic cylinders 22, and the lifting and lowering of the lifting hydraulic cylinders 22 can drive the second rollers 2b to rise and fall to lift the frame 1. Eight driving motors 21 are respectively connected to the first rollers 2a and the second rollers 2b, and the first rollers 2a and the second rollers 2b are driven to rotate by the driving motors 21 to realize the movement of the frame 1. In this embodiment, the connection between the second roller 2b and the lifting hydraulic cylinder 22 adopts the following structure: the lifting hydraulic cylinder 22 is connected downwardly to a lifting frame 221, and a second connecting frame 222 is arranged at the bottom of the lifting frame 221, and the second roller 2b is connected to the bottom of the lifting frame 221, and the lifting frame 221 is driven to rise and fall by the lifting hydraulic cylinder 22, thereby driving the second roller 2b to rise and fall.

[0035] Two annular sliding rails 42 are arranged at intervals on the frame 1, and sliding frames 43 are slidably connected to the two sliding rails 42, and a rotating roller 454 and two output rollers 44 are connected together through the two sliding frames 43. The rotating roller 454 is equipped with a drain plate roll 5. The two output rollers 44 are arranged up and down, and a gap is left between the two for the drain plate to pass through. The drain plate roll 5 passes through the gap between the two output rollers 44 for output. The climbing motor 41 is installed on one of the sliding frames 43, and is used to drive the sliding frame 43 to move along the sliding rail 42 to achieve the purpose of attaching the drain plate to the tunnel wall.

[0036] There are two groups of top-pressing hydraulic cylinders 31, both of which are located between two sliding guide rails 42 and are arranged at equal intervals from front to back. The top-pressing hydraulic cylinders 31 in the same group are arranged in a ring on the frame 1 along a direction parallel to the sliding guide rails 42. Each top-pressing hydraulic cylinder 31 is connected to a clamping plate 32, and the top-pressing hydraulic cylinder 31 drives the clamping plate 32 to move outward to press the drainage plate against the tunnel wall. In other embodiments, more than two groups of top-pressing hydraulic cylinders 31 may be provided.

[0037] The above-mentioned paving device is provided with an annular sliding guide rail 42. The sliding guide rail 42 is similar in shape to the tunnel wall. The climbing motor 41 drives the sliding frame 43 to move to achieve the initial paving of the drainage board on the tunnel wall. Finally, the top pressure hydraulic cylinder 31 drives the pressing plate 32 to move outward to achieve the pressing of the drainage board on the tunnel wall.

[0038] In this embodiment, the following connection structure is adopted between the top pressure hydraulic cylinder 31 and the clamping plate 32: each top pressure hydraulic cylinder 31 is provided with a telescopic sleeve 33 and a sliding rod 331. The telescopic sleeve 33 is fixed on the frame 1, and the sliding rod 331 is slidably sleeved in the telescopic sleeve 33. The top pressure hydraulic cylinder 31 is connected to the sliding rod 331 to drive the sliding rod 331 to extend outward from the telescopic sleeve 33, and the sliding rod 331 is connected to the clamping plate 32. This structure can enhance the stability of the clamping plate 32 when it moves outward to prevent deviation.

[0039] In this embodiment, the movement of the sliding frame 43 is achieved by the following structure: a climbing gear 411 is connected to the climbing motor 41, and a transmission rack 421 is arranged on the sliding guide rail 42 along its length direction. The climbing gear 411 is meshed with the transmission rack 421. When the climbing motor 41 rotates, the climbing gear 411 cooperates with the transmission rack 421 to drive the sliding frame 43 to move along the sliding guide rail 42.

[0040] In this embodiment, the following connection structure is adopted between the sliding frame 43 and the rotating roller 454: the two sliding frames 43 are provided with a first push-out hydraulic cylinder 451 and a first push-out sleeve 452, the first push-out sleeve 452 is slidably sleeved with a first push rod 453, the first push-out hydraulic cylinder 451 is connected to the first push rod 453 to drive the first push rod 453 to extend outward from the first push-out sleeve 452, the first push rod 453 is provided with a groove for the rotating roller 454 to be placed and rotated, and the rotating roller 454 is supported by the grooves on the two first push rods 453. Since the roll diameter of the drain board roll 5 will continue to decrease during use, the position of the rotating roller 454 can be adjusted through this structure, so as to adjust the position according to the roll diameter of the drain board roll 5. In addition, this structure also facilitates the disassembly and installation between the rotating roller 454 and the first push rod 453, and the rotating roller 454 can be directly taken out from the groove on the first push rod 453.

[0041] In this embodiment, the following connection structure is adopted between the sliding frame 43 and the output roller 44: two second push-out hydraulic cylinders 461 and two second push-out sleeves 462 are arranged on the two sliding frames 43, a second push rod 463 is slidably sleeved in the second push-out sleeve 462, the second push-out hydraulic cylinder 461 is connected to the second push rod 463 to drive the second push rod 463 to extend outward from the second push-out sleeve 462, and every two second push rods 463 are rotatably connected to an output roller 44. Through this structure, the position of the output roller 44 can be adjusted so that the output roller 44 can move outward or inward, thereby adapting to tunnel walls of different sizes.

[0042] Due to the limited space in the tunnel, the laying device will cause obstacles when installing steel pipes, affecting the cross-operation of laying the drainage board and installing the steel pipe, resulting in low work efficiency. After adopting the above structure, the laying device has a telescopic function, which can solve the impact of the cross-operation of laying the drainage board and installing the steel pipe, that is, according to the construction needs, the device can be retracted and put into the steel pipe, reducing the impact of the cross-operation of the two and improving the work efficiency.

[0043] In this embodiment, a base frame 11 is provided on the frame 1, and two pairs of folding rods 12 and two folding hydraulic cylinders 13 are hinged on the base frame 11. The two pairs of folding rods 12 are arranged at intervals, and a lifting platform 14 for placing the spare drainage board roll 5 is hinged on the top. The two folding hydraulic cylinders 13 are respectively hinged to the two pairs of folding rods 12 to drive the folding rods 12 to open or close to push the lifting platform 14 to rise and fall. A horizontal conveyor belt 15 is also provided on the frame 1, and the feeding end of the conveyor belt 15 extends to the lifting platform 14, and the discharging end extends to the sliding frame 43.

[0044] In this embodiment, the board pasting process is as follows:

[0045] S1. Start the drive motor 21 on the first roller 2a to drive the entire trolley to move to the set position, then stop the drive motor 21, and start the second push-out hydraulic cylinder 461, the second push-out hydraulic cylinder 461 pushes the second push rod 463 out to drive the two output rollers 44 to stick to the tunnel wall, and then the drainage board is output through the two output rollers 44 and stuck to the tunnel wall;

[0046] S2. Start the climbing motor 41, the climbing motor 41 drives the climbing gear 411 to rotate, and the climbing gear 411 meshes with the transmission rack 421 to drive the sliding frame 43 to move on the sliding guide rail 42, so that the output roller 44 rolls on the tunnel wall, and the drainage plate is continuously output by the output roller 44 and continuously laid on the tunnel wall;

[0047] S3. As the sliding frame 43 completes a one-way stroke movement (i.e., moves from one end of the sliding guide rail 42 to the other end), the drainage board is attached to the tunnel wall, and then the top pressure hydraulic cylinder 31 is started to drive the clamping plate 32 to move outward, so that the clamping plate 32 presses the drainage board on the tunnel wall, completing the laying of a section of drainage board.

[0048] When the paving trolley moves into a tunnel of changed specifications, the lifting hydraulic cylinders 22 on the front and rear sides of the frame 1 are respectively started to drive the lifting frame 221 and the second roller 2b to move downward until the second roller 2b contacts the ground to lift the frame 1 to a set height position, and then the drive motor 21 is started to drive the entire frame 1 forward through the second roller 2b until the entire frame 1 enters a tunnel of another specification, and the lifting hydraulic cylinders 22 on the front and rear sides of the frame 1 are retracted to drive the entire frame 1 to move downward until the first roller 2a of the frame 1 contacts the ground, thereby completing the transfer transition of the paving trolley.

[0049] When the drain board roll 5 needs to be replaced, the folding hydraulic cylinder 13 is started to push the folding rod 12 to open, thereby pushing the lifting platform 14 and the spare drain board roll 5 on the lifting platform 14 to the feeding end of the conveyor belt 15, and then transported to the sliding frame 43 through the conveyor belt 15, and then the rotating roller 454 is removed from the groove of the first push rod 453, and the rotating roller 454 is inserted into the new drain board roll 5, and finally the position of the first ejection hydraulic cylinder 451 and the climbing motor 41 is controlled to reinstall the rotating roller 454 onto the groove of the first push rod 453, thereby completing the replacement of the drain board roll 5.

[0050] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.

Claims

1. A tunnel drainage board paving trolley, comprising a frame (1), a first roller (2a), a second roller (2b), a drive motor (21), a lifting hydraulic cylinder (22), a top pressure hydraulic cylinder (31) and a climbing motor (41), characterized in that: The first roller (2a) is arranged at the bottom of the frame (1); the lifting hydraulic cylinder (22) is respectively arranged vertically on the front and rear sides of the trolley; the second roller (2b) is arranged at the bottom of the lifting hydraulic cylinder (22); the lifting and lowering of the lifting hydraulic cylinder (22) can drive the second roller (2b) to rise and fall to lift the frame (1); the driving motor (21) is respectively connected to the first roller (2a) and the second roller (2b); the driving motor (21) drives the first roller (2a) and the second roller (2b) to rotate to realize the movement of the frame (1); The frame (1) is provided with an annular sliding guide rail (42), a sliding frame (43) is slidably connected to the sliding guide rail (42), a rotating roller (454) and an output roller (44) are respectively provided on the sliding frame (43), a drainage plate roll (5) is installed on the rotating roller (454), and the drainage plate roll (5) is connected to the output roller (44) for output, the climbing motor (41) is installed on the sliding frame (43), and is used to drive the sliding frame (43) to move so as to attach the drainage plate to the tunnel wall; the top pressure hydraulic cylinder (31) is arranged on the frame (1) in an annular manner along a direction parallel to the sliding guide rail (42), and the top pressure hydraulic cylinder (31) is connected to a pressing plate (32), and is used to drive the pressing plate (32) to move outward so as to press the drainage plate against the tunnel wall.

2. A tunnel drainage board paving trolley according to claim 1, characterized in that: The lifting hydraulic cylinder (22) is downwardly connected to a lifting frame (221), and the second roller (2b) is arranged at the lower part of the lifting frame (221).

3. A tunnel drainage board paving trolley according to claim 1, characterized in that: It also includes a telescopic sleeve (33) and a sliding rod (331), wherein the telescopic sleeve (33) is fixed on the frame (1), and the sliding rod (331) is slidably sleeved in the telescopic sleeve (33), and the top pressure hydraulic cylinder (31) is connected to the sliding rod (331) to drive the sliding rod (331) to extend outward from the telescopic sleeve (33), and the sliding rod (331) is connected to the clamping plate (32).

4. A tunnel drainage board paving trolley according to claim 1, characterized in that: The climbing motor (41) is connected to a climbing gear (411), and a transmission rack (421) is provided on the sliding guide rail (42) along its length direction, and the climbing gear (411) is meshed with the transmission rack (421).

5. The tunnel drainage board paving trolley according to claim 1, characterized in that: The sliding frame (43) is provided with a first ejection hydraulic cylinder (451) and a first ejection sleeve (452); a first push rod (453) is slidably sleeved in the first ejection sleeve (452); the first ejection hydraulic cylinder (451) is connected to the first push rod (453) to drive the first push rod (453) to extend outward from the first ejection sleeve (452); and the first push rod (453) is detachably connected to the rotating roller (454).

6. A tunnel drainage board paving trolley according to claim 5, characterized in that: The sliding frame (43) is provided with a second ejection hydraulic cylinder (461) and a second ejection sleeve (462); a second push rod (463) is slidably sleeved in the second ejection sleeve (462); the second ejection hydraulic cylinder (461) is connected to the second push rod (463) for driving the second push rod (463) to extend outward from the second ejection sleeve (462); and the second push rod (463) is connected to the output roller (44).

7. A tunnel drainage board paving trolley according to claim 6, characterized in that: The frame (1) is provided with a base frame (11), the base frame (11) is provided with a folding rod (12) and a folding hydraulic cylinder (13), the top of the folding rod (12) is connected with a lifting platform (14) for placing a spare drainage plate roll (5), the folding hydraulic cylinder (13) is connected with the folding rod (12) and is used to drive the folding rod (12) to open or close so as to push the lifting platform (14) to rise and fall, and the frame (1) is also provided with a conveyor belt (15), the feeding end of the conveyor belt (15) extends to the lifting platform (14), and the discharging end extends to the sliding frame (43).

8. A construction method for a tunnel drainage board paving trolley as claimed in claim 7, characterized in that The following steps are involved: S1. Start the drive motor (21) to drive the entire trolley to move to the set position, then stop the drive motor (21) and start the second push-out hydraulic cylinder (461), the second push-out hydraulic cylinder (461) pushes the second push rod (463) to extend, so as to drive the output roller (44) to stick to the tunnel wall, and then the drainage plate is output through the output roller (44) and stuck to the tunnel wall; S2. Start the climbing motor (41), the climbing motor (41) drives the sliding frame (43) to move on the sliding guide rail (42), so as to drive the output roller (44) to roll on the tunnel wall, so that the output roller (44) continuously outputs the drainage board and continuously lays the drainage board on the tunnel wall; S3. As the sliding frame (43) completes a one-way stroke movement, the drainage board is attached to the tunnel wall, and then the top pressure hydraulic cylinder (31) is started to drive the pressing plate (32) to move outward, so that the pressing plate (32) presses the drainage board on the tunnel wall, and a section of drainage board is laid.

9. The construction method of a tunnel drainage board paving trolley according to claim 8, characterized in that: When the trolley moves into a tunnel of a changed specification, the lifting hydraulic cylinders (22) on the front and rear sides of the frame (1) are respectively started to drive the second roller (2b) to move downward until the second roller (2b) contacts the ground to lift the frame (1) to a set height position, and then the drive motor (21) is started to drive the entire frame (1) forward through the second roller (2b) until the entire frame (1) enters a tunnel of another specification, and the lifting hydraulic cylinders (22) on the front and rear sides of the frame (1) are retracted to drive the entire frame (1) to move downward until the first roller (2a) of the frame (1) contacts the ground.

10. The construction method of a tunnel drainage board paving trolley according to claim 8, characterized in that: When the drain plate roll (5) needs to be replaced, the folding hydraulic cylinder (13) is started to push the folding rod (12) to open, thereby pushing the lifting platform (14) and the spare drain plate roll (5) on the lifting platform (14) to the feeding end of the conveyor belt (15), and then transported to the sliding frame (43) through the conveyor belt (15), and then the rotating roller (454) is removed from the first push rod (453), and the rotating roller (454) is inserted into the new drain plate roll (5), and finally the position of the first ejection hydraulic cylinder (451) and the climbing motor (41) is controlled to reconnect the rotating roller (454) to the first push rod (453).