Construction method for earthwork external transportation of super-deep foundation pit

CN117328464BActive Publication Date: 2026-08-28THE SECOND CONSTR OF CHINA CONSTR EIGHTH ENG DIV
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202311306675.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-10
Publication Date
2026-08-28
Estimated Expiration
2043-10-10

AI Technical Summary

Technical Problem

[0003]为了解决基坑外土方外运的问题,本发明提供一种超深基坑土方外运的施工方法

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117328464B_ABST
    Figure CN117328464B_ABST
Patent Text Reader

Abstract

The present application relates to the field of building construction technology, especially to a construction method for earthwork external transportation of super-deep foundation pit. The construction method comprises the following steps: constructing a vertical retaining wall supporting structure at the position of the original slope top of the foundation pit; constructing a soil foundation ramp at one side edge of the foundation pit; and constructing a trestle ramp at the center of the foundation pit, which is connected with the soil foundation ramp and serves as the main outlet channel. The present application solves the problem of too large occupation of the earthwork ramp of the narrow deep foundation pit, which affects the subsequent process, by adopting the U-shaped earthwork ramp, i.e. the soil foundation plus the trestle earthwork mode. The problem of the earthwork ramp of the narrow foundation pit failing to reach the bottom at one time is solved by adopting the arrangement mode of the U-shaped ramp. The present application has the characteristics of high efficiency, excellent quality, safety and reliability, and provides a good experience reference for similar projects, and has received consistent good comments from the construction unit and the supervision unit. The present application also plays a standard demonstration role in the industry and has significant social benefits.
Need to check novelty before this filing date? Find Prior Art

Citation Information

Patent Citations

  • Rapid unearthing construction method by combining trestle with annular road in deep foundation pit

    CN113502824A

  • Foundation pit earth excavation method

    CN113699996A

  • Landing stage structure that fetches earth under deep basal pit annular supports

    CN205475249U