Transformation method of current merging unit in string of three-quarters connection intelligent substation
By adopting the transformation method of power outage first for incoming lines and power outage first for outgoing lines in two-thirds wiring smart substations, gradual power outages and replacement of current merging units, the problem of simultaneous power outages in the entire string in the existing technology has been solved, and the system operation has been improved. The reliability and power generation efficiency are achieved, and the transformation effect is achieved without additional costs.
Patent Information
- Application Number
- CN202311225460.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-21
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-09-21
AI Technical Summary
In the two-thirds wiring smart substation, when the existing current merging unit is renovated, the incoming and outgoing lines of the entire string need to be powered off at the same time, resulting in a large power outage and reducing the reliability of the system operation and the efficiency of power generation and supply.
Two transformation methods are adopted: power outage first at the incoming line and power outage first at the outgoing line. Through specific safety measures and test sequences, the power is gradually cut off and the current merging unit is remodeled to avoid simultaneous power outage of the entire string and ensure the safety and reliability of the transformation process.
It effectively reduces the scope of power outages during transformation, increases the running time of incoming and outgoing lines, and improves the reliability of system operation and power generation efficiency without additional costs.
Smart Images

Figure CN117424118B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of transformer substation reconstruction, and in particular to a method for reconstructing a current merging unit in a string of a two-thirds-connected intelligent transformer substation. Background Art
[0002] The 500kV substation in the power system is mainly a two-thirds wiring type intelligent substation. The merging unit in the intelligent substation is responsible for digitizing the current and voltage secondary signals and sending them to the protection equipment. When the current merging unit of the two-thirds wiring intelligent substation is modified, it is often necessary to shut down all three circuit breakers in the string where the merged unit to be modified is located, that is, the incoming and outgoing lines at the same time. This modification method has a large power outage range, reduces the operating time of the incoming and outgoing lines of the modified string, reduces the reliability of system operation, and affects the power generation and supply efficiency. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a method for transforming the current merging unit in a string of a two-thirds connection intelligent substation, thereby reducing the scope of power outage during substation transformation, increasing the operating time of the transformed string incoming and outgoing lines, and increasing the reliability of system operation.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A method for transforming a current merging unit in a string of a three-quarters wiring intelligent substation, wherein the single string structure of a three-quarters wiring intelligent substation is as follows: there are three circuit breakers, 1DL, 2DL, and 3DL, between the two bus sections I and II, the incoming line is connected between 1DL and 2DL, and the outgoing line is connected between 2DL and 3DL. Current transformers 11LH and 12LH, 21LH and 22LH, and 31LH and 32LH are arranged on both sides of the three circuit breakers 1DL, 2DL, and 3DL, respectively. The current transformers in the three circuit breaker intervals are connected to three current merging units, 1MU, 2MU, and 3MU, respectively. The current merging unit collects the sampling amount of the current transformer, and after the sampling amount is converted by analog to digital, it is transmitted to the corresponding circuit breaker protection, incoming / outgoing line protection, and busbar protection device for use;
[0006] The transformation method includes two methods: shutting down the incoming line first and shutting down the outgoing line first. The shutting down the incoming line first includes the following steps: Step 1, switch the circuit breakers 1DL and 2DL to the power outage maintenance state, shut down the incoming line, and keep 3DL in operation.
[0007] The outgoing line remains operational;
[0008] Step 2. Execute the safety measures required for the transformation of the 2MU current merging unit of the circuit breaker 2DL on the outgoing line protection, and withdraw the SV soft pressure plate that receives the 2MU;
[0009] Step 3: Remodel and transform the two current combining units 1MU and 2MU, including removing the old device and installing the new device;
[0010] Step 4. Update the configuration files for 1DL protection, incoming line protection, 2DL protection, and I bus protection;
[0011] Step 5. Test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly;
[0012] Step 6, test 2MU to verify that 2DL protection and incoming line protection receive the data sent by 2MU correctly; Step 7, put 1DL into operation, and operate the incoming line power supply, in which the safety measures required for the 2MU current merging unit test of 2DL are executed on the incoming line protection, and the SV soft pressure plate receiving 2MU is withdrawn;
[0013] Step8, 2DL keeps power off for maintenance;
[0014] Step 9, switch 3DL to power-off maintenance state, and shut down the outgoing line;
[0015] Step 10: Remodel and transform the 3MU current merging unit, including dismantling the old device and installing a new one;
[0016] Step 11, update the configuration files for 3DL protection, outgoing line protection, and II busbar protection;
[0017] Step 12, test 3MU to verify that 3DL protection, outgoing line protection, and I bus protection receive the data sent by 1MU correctly;
[0018] Step 13, restore the SV soft pressure plate of the outgoing line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the outgoing line protection receives the data sent by 2MU correctly;
[0019] Step 14, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 7;
[0020] Step 15. Put 2DL and 3DL into operation, and start power transmission. The transformation is completed.
[0021] The above-mentioned outgoing line power-off first transformation method comprises the following steps:
[0022] Step 1, switch 2DL and 3DL to power-off maintenance state, shut down the outgoing line, keep 1DL running, and keep the incoming line running;
[0023] Step 2: Execute the safety measures required for the transformation of the 2MU current merging unit of 2DL on the incoming line protection, and withdraw the SV soft pressure plate that receives the 2MU;
[0024] Step 3: Remodel and transform the two current combining units 2MU and 3MU, including dismantling the old device and installing the new one;
[0025] Step 4. Update the configuration files for 2DL protection, outgoing line protection, 3DL protection, and II busbar protection;
[0026] Step 5. Test 3MU to verify that 3DL protection, outgoing line protection, and II busbar protection receive the data sent by 3MU correctly;
[0027] Step 6, test 2MU to verify that 2DL protection and outgoing line protection receive the data sent by 2MU correctly; Step 7, put 3DL into operation, and run the outgoing line power transmission, in which the safety measures required for the 2MU current merging unit test of 2DL are executed on the outgoing line protection, and the SV soft pressure plate receiving 2MU is withdrawn;
[0028] Step8, 2DL keeps power off for maintenance;
[0029] Step 9, switch 1DL to power-off maintenance state, and shut down the incoming line;
[0030] Step 10, remodel the 1MU current merging unit, including dismantling the old device and installing a new one;
[0031] Step 11, update the configuration files for 1DL protection, incoming line protection, and I bus protection;
[0032] Step 12, test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly;
[0033] Step 13, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the incoming line protection receives the data sent by 2MU correctly;
[0034] Step 14, restore the SV soft pressure plate of the receiving 2MU on the outgoing line protection of Step 7;
[0035] Step 15. Put 1DL and 2DL into operation, supply power to the lines, and the transformation is completed.
[0036] The invention provides a method for transforming a current merging unit in a string of a two-thirds wiring intelligent substation, which has the following beneficial effects:
[0037] 1. No additional cost; this method only needs to change the interval power outage mode of the incoming and outgoing line circuit breakers when the current merging unit in the string is replaced and transformed, and finally achieves the effect of completing the transformation by shutting down the incoming and outgoing lines separately by relying on the execution recovery and test sequence of specific safety measures, without additional cost;
[0038] 2. Widely applicable: The method proposed in this method is widely applicable to smart substations with two-thirds wiring and current merging units. When the current merging units in the string are transformed, it is not necessary to shut down the entire string of incoming and outgoing lines at the same time;
[0039] 3. Increase efficiency: When this method is used to transform the current merging unit of the smart substation with two-thirds wiring, the operating time of the incoming and outgoing lines is effectively increased, the reliability of the system operation is improved, and the efficiency of power generation and supply is guaranteed. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:
[0041] Figure 1 This is a structural diagram of the two-thirds wiring system of the present invention. DETAILED DESCRIPTION
[0042] The technical solution of the present invention is described in detail below in conjunction with the accompanying drawings and embodiments.
[0043] like Figure 1 As shown in, a method for reconstructing a current merging unit in a string of a two-thirds wiring intelligent substation is provided. The single string structure of a two-thirds wiring intelligent substation is as follows: there are three circuit breakers 1DL, 2DL and 3DL between the two bus sections I and II, the incoming line is connected between 1DL and 2DL, and the outgoing line is connected between 2DL and 3DL. Current transformers 11LH and 12LH, 21LH and 22LH, 31LH and 32LH are arranged on both sides of the three circuit breakers 1DL, 2DL and 3DL, respectively. The current transformers in the three circuit breaker intervals are connected to the three current merging units 1MU, 2MU and 3MU, respectively. The current merging unit collects the sampling amount of the current transformer, and after the sampling amount is converted into analog to digital, it is transmitted to the corresponding circuit breaker protection, incoming / outgoing line protection and busbar protection device for use;
[0044] A certain series of bays in a two-thirds wiring smart substation usually have the following operating modes:
[0045] 1) Under normal operation, 1DL, 2DL, and 3DL are in operation, and the incoming lines and incoming line power transmission are in operation.
[0046] 2) Any of the three circuit breakers 1DL, 2DL and 3DL is shut down for maintenance, and the incoming and outgoing lines are powered on.
[0047] 3) 1DL and 3DL are shut down for maintenance, 2DL is in operation, and the incoming and outgoing lines are powered on.
[0048] 4) 1DL and 2DL are shut down for maintenance, the incoming line is shut down, 3DL is in operation, and the outgoing line is powered on.
[0049] 5) 2DL and 3DL are shut down for maintenance, the incoming line is shut down, 1DL is in operation, and the incoming line is powered on.
[0050] 6) The three circuit breakers 1DL, 2DL and 3DL are all shut down for maintenance, and the incoming and outgoing lines are shut down, that is, the entire string is shut down.
[0051] by Figure 1 Taking the transformation of a string of current merging units in a two-thirds wiring intelligent substation as an example, the existing technology is as follows:
[0052] Step 1. Switch 1DL, 2DL and 3DL to power-off maintenance mode, and shut down the incoming and outgoing lines;
[0053] Step 2: Remodel and transform the three current combining units 1MU, 2MU and 3MU, including dismantling the old devices and installing new ones;
[0054] Step 3. Update the configuration files for 1DL protection, 2DL protection, 3DL protection, incoming line protection, outgoing line protection, I bus protection, and II bus protection;
[0055] Step 4. Test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly;
[0056] Step 5. Test 2MU to verify that 2DL protection, incoming line protection, and outgoing line protection receive the data sent by 2MU correctly;
[0057] Step 6. Test 3MU to verify that 3DL protection, outgoing line protection, and II busbar protection receive the data sent by 3MU correctly;
[0058] Step 7. Put 1DL, 2DL and 3DL into operation, and the incoming and outgoing lines are powered on, and the transformation is complete.
[0059] The transformation effect of the existing technology is shown in Table 1:
[0060] Appendix 1: Power outage schedule for existing technology transformation methods (power outages at the same time for incoming and outgoing lines)
[0061]
[0062]
[0063] The transformation method of the present invention includes two methods: shutting down the incoming line first and shutting down the outgoing line first. The shutting down the incoming line first includes the following steps:
[0064] Step 1. Switch the circuit breakers 1DL and 2DL to the power-off maintenance state, shut down the incoming line, keep 3DL in operation, and keep the outgoing line in operation;
[0065] Step 2. Execute the safety measures required for the transformation of the 2MU current merging unit of the circuit breaker 2DL on the outgoing line protection, and withdraw the SV soft pressure plate that receives the 2MU;
[0066] Step 3: Remodel and transform the two current combining units 1MU and 2MU, including removing the old device and installing the new device;
[0067] Step 4. Update the configuration files for 1DL protection, incoming line protection, 2DL protection, and I bus protection;
[0068] Step 5. Test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly;
[0069] Step 6, test 2MU to verify that 2DL protection and incoming line protection receive the data sent by 2MU correctly; Step 7, put 1DL into operation, and operate the incoming line power supply, in which the safety measures required for the 2MU current merging unit test of 2DL are executed on the incoming line protection, and the SV soft pressure plate receiving 2MU is withdrawn;
[0070] Step8, 2DL keeps power off for maintenance;
[0071] Step 9, switch 3DL to power-off maintenance state, and shut down the outgoing line;
[0072] Step 10: Remodel and transform the 3MU current merging unit, including dismantling the old device and installing a new one;
[0073] Step 11, update the configuration files for 3DL protection, outgoing line protection, and II busbar protection;
[0074] Step 12, test 3MU to verify that 3DL protection, outgoing line protection, and I bus protection receive the data sent by 1MU correctly;
[0075] Step 13, restore the SV soft pressure plate of the outgoing line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the outgoing line protection receives the data sent by 2MU correctly;
[0076] Step 14, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 7;
[0077] Step 15. Put 2DL and 3DL into operation, and start power transmission. The transformation is completed.
[0078] The transformation effect of shutting down the incoming power supply first is shown in Table 2:
[0079] Table 2 The transformation method proposed by the present invention (first stop the incoming line and then stop the outgoing line)
[0080]
[0081] The above-mentioned outgoing line power-off first transformation method comprises the following steps:
[0082] Step 1, switch 2DL and 3DL to power-off maintenance state, shut down the outgoing line, keep 1DL running, and keep the incoming line running;
[0083] Step 2: Execute the safety measures required for the transformation of the 2MU current merging unit of 2DL on the incoming line protection, and withdraw the SV soft pressure plate that receives the 2MU;
[0084] Step 3: Remodel and transform the two current combining units 2MU and 3MU, including dismantling the old device and installing the new one;
[0085] Step 4. Update the configuration files for 2DL protection, outgoing line protection, 3DL protection, and II busbar protection;
[0086] Step 5. Test 3MU to verify that 3DL protection, outgoing line protection, and II busbar protection receive the data sent by 3MU correctly;
[0087] Step 6, test 2MU to verify that 2DL protection and outgoing line protection receive the data sent by 2MU correctly; Step 7, put 3DL into operation, and run the outgoing line power transmission, in which the safety measures required for the 2MU current merging unit test of 2DL are executed on the outgoing line protection, and the SV soft pressure plate receiving 2MU is withdrawn;
[0088] Step8, 2DL keeps power off for maintenance;
[0089] Step 9, switch 1DL to power-off maintenance state, and shut down the incoming line;
[0090] Step 10, remodel the 1MU current merging unit, including dismantling the old device and installing a new one;
[0091] Step 11, update the configuration files for 1DL protection, incoming line protection, and I bus protection;
[0092] Step 12, test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly;
[0093] Step 13, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the incoming line protection receives the data sent by 2MU correctly;
[0094] Step 14, restore the SV soft pressure plate of the receiving 2MU on the outgoing line protection of Step 7;
[0095] Step 15. Put 1DL and 2DL into operation, supply power to the lines, and the transformation is completed.
[0096] The transformation effect of powering off the outgoing line first is shown in Table 3:
[0097] Table 3 The transformation method proposed by the present invention (stop the outgoing line first and then stop the incoming line)
[0098]
Claims
1. A method for transforming a current merging unit in a string of a two-thirds connection intelligent substation, characterized in that: The single string structure of the smart substation with two-thirds connection is as follows: there are three circuit breakers 1DL, 2DL and 3DL between the two bus sections I and II, the incoming line is connected between 1DL and 2DL, and the outgoing line is connected between 2DL and 3DL. Current transformers 11LH and 12LH, 21LH and 22LH, 31LH and 32LH are arranged on both sides of the three circuit breakers 1DL, 2DL and 3DL respectively. The current transformers in the three circuit breaker intervals are connected to the three current merging units 1MU, 2MU and 3MU respectively. The current merging units collect the sampling amount of the current transformer, and after the sampling amount is converted by analog to digital, it is transmitted to the corresponding circuit breaker protection, incoming / outgoing line protection, and busbar protection devices for use; The transformation methods include two methods: shutting down the incoming line first and shutting down the outgoing line first. The shutting down the incoming line first includes the following steps: Step 1. Switch the circuit breakers 1DL and 2DL to the power-off maintenance state, shut down the incoming line, keep 3DL in operation, and keep the outgoing line in operation; Step 2. Execute the safety measures required for the transformation of the 2MU current merging unit of the circuit breaker 2DL on the outgoing line protection, and withdraw the SV soft pressure plate that receives the 2MU; Step 3: Remodel and transform the two current combining units 1MU and 2MU, including removing the old device and installing the new device; Step 4. Update the configuration files for 1DL protection, incoming line protection, 2DL protection, and I bus protection; Step 5. Test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly; Step 6. Test 2MU to verify that 2DL protection and incoming line protection receive the data sent by 2MU correctly. Step 7, put 1DL into operation, and supply power to the incoming line. The safety measures required for the 2MU current merging unit test of 2DL are executed on the incoming line protection, and the SV soft pressure plate of the receiving 2MU is withdrawn; Step8, 2DL keeps power off for maintenance; Step 9, switch 3DL to power-off maintenance state, and shut down the outgoing line; Step 10: Remodel and transform the 3MU current merging unit, including dismantling the old device and installing a new one; Step 11, update the configuration files for 3DL protection, outgoing line protection, and II busbar protection; Step 12, test 3MU to verify that 3DL protection, outgoing line protection, and I bus protection receive the data sent by 1MU correctly; Step 13, restore the SV soft pressure plate of the outgoing line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the outgoing line protection receives the data sent by 2MU correctly; Step 14, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 7; Step 15. Put 2DL and 3DL into operation, and start power transmission. The transformation is completed.
2. The method for transforming the current merging unit in a string of a two-thirds connection intelligent substation according to claim 1 is characterized in that: The outgoing line power-off first transformation method comprises the following steps: Step 1, switch 2DL and 3DL to power-off maintenance state, shut down the outgoing line, keep 1DL running, and keep the incoming line running; Step 2: Execute the safety measures required for the transformation of the 2MU current merging unit of 2DL on the incoming line protection, and withdraw the SV soft pressure plate that receives the 2MU; Step 3: Remodel and transform the two current combining units 2MU and 3MU, including dismantling the old device and installing the new one; Step 4. Update the configuration files for 2DL protection, outgoing line protection, 3DL protection, and II busbar protection; Step 5. Test 3MU to verify that 3DL protection, outgoing line protection, and II busbar protection receive the data sent by 3MU correctly; Step 6. Test 2MU to verify that 2DL protection and outgoing line protection receive the data sent by 2MU correctly; Step 7, put 3DL into operation, and start the outgoing line power transmission operation, in which the safety measures required for the 2MU current merging unit test of 2DL are executed on the outgoing line protection, and the SV soft pressure plate of the receiving 2MU is withdrawn; Step8, 2DL keeps power off for maintenance; Step 9, switch 1DL to power-off maintenance state, and shut down the incoming line; Step 10, remodel the 1MU current merging unit, including dismantling the old device and installing a new one; Step 11, update the configuration files for 1DL protection, incoming line protection, and I bus protection; Step 12, test 1MU to verify that 1DL protection, incoming line protection, and I bus protection receive the data sent by 1MU correctly; Step 13, restore the SV soft pressure plate of the incoming line protection receiving 2MU in Step 2, and perform additional tests on 2MU to verify that the incoming line protection receives the data sent by 2MU correctly; Step 14, restore the SV soft pressure plate of the receiving 2MU on the outgoing line protection of Step 7; Step 15. Put 1DL and 2DL into operation, supply power to the lines, and the transformation is completed.