Construction project cost estimation model and method

By using the quota quantity and material hangar editor and intelligent price group function of the cost management software in engineering projects, the problems of low cost estimation work efficiency and inaccurate data are solved, fast and accurate cost estimation and quota maintenance are achieved, and the cost is reduced Labor and time costs.

CN117522160BActive Publication Date: 2024-10-15GUANGDONG TOONE TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311478799.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-08
Publication Date
2024-10-15
Estimated Expiration
2043-11-08

AI Technical Summary

Technical Problem

In engineering projects, cost estimation work is inefficient and the data cannot be corrected in time, resulting in a large deviation between the actual cost and the calculated cost. Moreover, there is a lack of quota data maintenance tools and high manual maintenance costs.

Method used

Provides a construction project cost estimation model and method, including cost management software, with the functions of quota quantity and material hangar editor, data conversion, intelligent price grouping and data comparison analysis. Users can add and maintain quotas through the quota quantity and material hangar editor. , automatically convert pricing documents into cost documents, and use AI pricing and data comparison analysis functions to improve calculation efficiency.

Benefits of technology

It has realized automatic conversion of cost documents, intelligently and quickly completed pricing, improved the accuracy of cost calculation results, saved labor and time costs, and established an enterprise quota database and pricing plan to provide data support for subsequent cost calculation work.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117522160B_ABST
    Figure CN117522160B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction project cost estimation model and method, including cost management software, which includes a quota material and equipment library editor, data conversion, intelligent pricing and data comparison and analysis functions; users can add, compile and maintain quotas through the quota material and equipment library editor to form enterprise pricing standards, and can repeatedly apply the enterprise pricing standards to different projects; the data conversion is used to convert cost files compiled by standards into cost files priced by enterprise quotas as standards, and the cost files priced by enterprise quotas as standards are cost files; the intelligent pricing includes AI guidance, batch cloning and pricing scheme functions; the data comparison and analysis includes material and equipment comparison and part-item amount comparison functions; this scheme saves enterprises manpower and time costs, and also establishes an enterprise quota library and pricing scheme to provide data support for subsequent cost estimation work.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of engineering project cost estimation, and in particular relates to a construction project cost estimation model and method. Background Art

[0002] In engineering projects, cost estimation helps enterprises better control the bottom line of bidding quotations. However, in actual work, enterprises generally have problems such as weak awareness and backward tools in cost estimation:

[0003] (1) At present, many companies still use spreadsheets, documents and other tools to calculate costs, which leads to low work efficiency due to the large amount of work;

[0004] (2) It is impossible to establish relevant calculation models and timely revise the calculation results when data changes, resulting in inaccurate basic data and a large deviation between actual costs and pricing costs;

[0005] (3) There is a lack of enterprise quota data maintenance tools, and the manual maintenance cost is high and the workload is heavy.

[0006] Therefore, the present invention proposes a construction project cost estimation model and method, which can solve the problem of low work efficiency caused by the large workload of construction project cost estimation. Summary of the invention

[0007] In view of the problems raised by the above background technology, the purpose of the present invention is to provide a construction project cost estimation model and method.

[0008] In order to achieve the above technical objectives, the technical solution adopted by the present invention is as follows:

[0009] Construction project cost estimation model and method, including cost management software, which includes quota material and labor hangar editor, data conversion, intelligent price combination and data comparison and analysis functions;

[0010] Users can add, compile and maintain quotas through the quota material library editor to form enterprise pricing standards, and can repeatedly apply enterprise pricing standards to different projects. The data conversion is used to convert the cost file compiled by the standard into the cost file priced by the enterprise quota as the standard. The cost file priced by the enterprise quota as the standard is the cost file. The intelligent pricing includes AI guidance, batch cloning and pricing scheme functions.

[0011] The data comparison and analysis includes the comparison of labor, materials and machinery and the comparison of amounts by parts and items;

[0012] The following steps are also included:

[0013] Step 1: Convert the pricing file to the cost file with one click. Open the cost management software, select the pricing file compiled by the standard, and convert it to the cost file with one click.

[0014] Step 2: Reuse the basic information, fees, rates and template pricing modules of the pricing file, and then apply the enterprise quota to complete the preparation of the cost file;

[0015] Step 3: AI price combination, establish a data conversion model between standard quota and enterprise quota through Excel table. When the file is converted, the original standard quota will be converted into the original price combination that is not included in the total price;

[0016] Step 4: When compiling the cost file, the original price group is selected, and the cost management software automatically recommends the corresponding enterprise quota, completes the quota addition, and generates the quota price group;

[0017] Step 5: The data comparison and analysis also includes a cost comparison function, which is used by the user to import pricing files and complete data matching and analysis of specific unit prices and total prices;

[0018] Step 6: The user uses the labor, material and machinery comparison function, and the user selects the original component to display the increase or decrease of the labor, material and machinery consumption between the standard quota and the enterprise quota in real time;

[0019] Step 7: It also includes an enterprise quota database, which contains supplementary quotas for highways in various provinces across the country. The enterprise quota database supports the entry, analysis and calculation of labor, material, machinery and equipment data.

[0020] Further limitation also includes the calculation method of the cost document, which is: create a budget estimate file, the budget estimate file includes the total budget estimate amount, the total budget estimate amount includes several sub-item amounts, the sub-item amounts include construction and installation project costs, land use and demolition compensation fees, other project construction costs, contingency funds and construction period loan interest.

[0021] It is further defined that the construction and installation project costs include direct costs, equipment purchase costs, measures costs, business management fees, fees, profits, taxes and special expenses. The direct costs refer to the various costs incurred during the construction process that constitute the project entity and contribute to the formation of the project, including labor costs, material costs and construction machinery usage fees.

[0022] It is further limited to also include fixed-rate construction and installation project fees, which are set according to fixed standards and are actual expenses incurred.

[0023] It is further specified that the cost management software is "Tongwang WEC Cost Management Software V10".

[0024] It is further defined that the standards are compiled based on the "Method for Preparing Budgets and Estimates for Highway Engineering Construction Projects" (JTG / 3830-2018) and "Highway Engineering Budget Quotas" (JTG / 3932-2018) issued by the Ministry of Transport.

[0025] It is further specified that the cost management software also includes a function of batch cloning of enterprise quotas, and the completed quota price groups are batch applied to the same original price groups through the function of batch cloning of enterprise quotas.

[0026] It is further defined that the pricing scheme function is used to support the preservation of sub-items of work at different levels, including the original pricing, the enterprise quotas and the labor, materials and machinery, and also includes supporting free copying and application between one file or different files.

[0027] It is further specified that the cost management software also includes a unit price calculator function, and the user clicks on the unit price calculator function to calculate the comprehensive unit price of multiple sub-items, original group prices or enterprise quotas.

[0028] It is further defined that the enterprise quota library includes two modes, namely, editing mode and preview mode. The enterprise quota library also has an export password, and the user must verify the password before exporting the file.

[0029] Beneficial effects of the present invention:

[0030] 1. This solution can automatically convert cost files and quickly and intelligently complete the price compilation, which is beneficial for cost estimators to improve the compilation efficiency;

[0031] 2. This solution has a data analysis and comparison function, which helps cost engineers quickly identify problematic areas and improve the accuracy of cost calculation results;

[0032] 3. This plan saves the enterprise manpower and time costs, and also establishes an enterprise quota database and pricing plan to provide data support for subsequent cost estimation work. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] The present invention can be further illustrated by the non-limiting examples given in the accompanying drawings;

[0034] Figure 1 This is a one-key conversion to cost file software interface diagram of the construction project cost estimation model and method embodiment of the present invention;

[0035] Figure 2 This is an interface diagram of the AI ​​pricing software for the construction project cost estimation model and method embodiment of the present invention;

[0036] Figure 3 This is an interface diagram of enterprise quota batch cloning software for an embodiment of the construction project cost estimation model and method of the present invention;

[0037] Figure 4 This is a diagram of the price combination scheme software interface of the construction project cost estimation model and method embodiment of the present invention;

[0038] Figure 5 This is a cost comparison software interface diagram of an embodiment of a construction project cost estimation model and method of the present invention;

[0039] Figure 6 This is a diagram of the interface of the labor-material-machine comparison software of the construction project cost estimation model and method embodiment of the present invention;

[0040] Figure 7 This is a unit price calculator software interface diagram of the construction project cost estimation model and method embodiment of the present invention;

[0041] Figure 8 It is a diagram of the enterprise quota library software interface of the construction project cost estimation model and method embodiment of the present invention;

[0042] Fig. 9 This is a diagram of the software interface for adding personnel, materials and machine prices in the construction project cost estimation model and method embodiment of the present invention;

[0043] Fig.10 This is a diagram of adding a human-material-machine software interface for the construction project cost estimation model and method embodiment of the present invention;

[0044] Fig.11 This is a preview mode software interface diagram of an embodiment of a construction project cost estimation model and method of the present invention;

[0045] Fig.12 This is an encryption software interface diagram of an embodiment of a construction project cost estimation model and method of the present invention;

[0046] Fig.13 It is a professional report cover image of the construction project cost estimation model and method embodiment of the present invention;

[0047] Fig.14 This is a diagram of the software interface of the approval form for the construction project cost estimation model and method embodiment of the present invention;

[0048] Fig.15 It is a cost summary table software interface diagram of the construction project cost estimation model and method embodiment of the present invention;

[0049] Fig.16 This is a diagram of the interface of the software for the itemized price list of the construction project cost estimation model and method embodiment of the present invention;

[0050] Fig.17 A diagram showing the interface of the material usage and price list software for the construction project cost estimation model and method embodiment of the present invention;

[0051] Fig.18 This is a software interface diagram of a bridge index summary table for an embodiment of a construction project cost estimation model and method of the present invention. DETAILED DESCRIPTION

[0052] In order to enable those skilled in the art to better understand the present invention, the technical solution of the present invention is further described below in conjunction with the accompanying drawings and embodiments.

[0053] The construction project cost estimation model and method of the present invention includes cost management software, which includes a quota material and labor hangar editor, data conversion, intelligent price combination and data comparison and analysis functions;

[0054] Users can add, compile and maintain quotas through the quota material library editor to form enterprise pricing standards, and can repeatedly apply enterprise pricing standards to different projects. The data conversion is used to convert the cost file compiled by the standard into the cost file priced by the enterprise quota as the standard. The cost file priced by the enterprise quota as the standard is the cost file. The intelligent pricing includes AI guidance, batch cloning and pricing scheme functions, which can help users quickly add enterprise quotas;

[0055] The meaning of data conversion is: a cost file is divided into multiple components, including fees, rates, and materials and machinery. Each component has different conversion rules. The cost file compiled based on the "Method for the Preparation of Budget and Estimation of Highway Engineering Construction Projects" (JTG / 3830-2018) and "Highway Engineering Budget Quotas" (JTG / 3932-2018) (referred to as: 18 budget and estimation files issued by the Ministry of Transport, also called revenue files) can be directly converted into a cost file (referred to as: cost file) priced based on the enterprise quota, saving the time of re-creating files;

[0056] The data comparison and analysis includes the comparison of labor, materials and machinery and the comparison of amounts by parts and items, which can intuitively reflect the differences between income files and cost files and help cost analysis;

[0057] The following steps are also included:

[0058] Step 1 Figure 1 As shown: the pricing file is converted to a cost file with one click. Open the cost management software, select the pricing file compiled by the standard, click to convert it into the enterprise cost pricing basis, and complete the one-click conversion to the cost file;

[0059] Step 2: Reuse the basic information, fees, rates and template pricing modules of the pricing file, and then apply the enterprise quota to complete the preparation of the cost file;

[0060] Step 3 Figure 2As shown: AI price combination, establish a data conversion model between standard quota and enterprise quota through Excel table. When the file is converted, the original standard quota will be converted into the original price combination that is not included in the total price. This is mainly used for data comparison and analysis when applying enterprise quota;

[0061] Step 4: When compiling the cost file, the original price group is selected, and the cost management software automatically recommends the corresponding enterprise quota, completes the quota addition, and generates the quota price group;

[0062] Step 5, such as Figure 5 As shown: the data comparison and analysis also includes a cost comparison function, and the user uses the cost comparison function to import pricing files and complete data matching and analysis of specific unit prices and total prices;

[0063] Step 6, such as Figure 6 As shown: the user uses the labor, material and machinery comparison function, and the user selects the original component to display the increase and decrease of the labor, material and machinery consumption between the standard quota and the enterprise quota in real time;

[0064] Step 7: Figure 8-Figure 10 As shown, it also includes an enterprise quota database, which contains supplementary quotas for highways in various provinces across the country. The enterprise quota database supports the entry, analysis and calculation of labor, material, machinery and equipment data.

[0065] like Figure 13-Figure 18 As shown: In addition, it also includes professional report functions, which have built-in cover pages, approval forms, cost summary tables, sub-item engineering calculation tables, material calculation comparison tables, indicator summary tables and other data calculation tables.

[0066] Preferably, it also includes a calculation method for the cost document, and the calculation method for the cost document is: create a budget estimate file, the budget estimate file includes a total budget estimate amount, the total budget estimate amount includes several sub-item amounts, and the sub-item amounts include construction and installation project costs, land use and demolition compensation fees, other project construction costs, contingency funds and construction period loan interest.

[0067] Preferably, the construction and installation project costs include direct costs, equipment purchase costs, measures costs, business management fees, fees, profits, taxes and special expenses. The direct costs refer to the various costs consumed during the construction process that constitute the project entity and contribute to the formation of the project, including labor costs, material costs and construction machinery usage fees.

[0068] Preferably, it also includes a fixed-rate construction and installation engineering fee, which is set according to a fixed standard and is the actual cost incurred.

[0069] Preferably, the cost management software is "Tongwang WEC Cost Management Software V10".

[0070] Preferably, the standard is compiled as the "Method for Preparing Budgets and Estimates for Highway Engineering Construction Projects" (JTG / 3830-2018) and the "Highway Engineering Budget Quotas" (JTG / 3932-2018) issued by the Ministry of Transport.

[0071] Preferably, Figure 3 As shown, the cost management software also includes a function of batch cloning of enterprise quotas. For completed quota price groups, the enterprise quota batch cloning function is used to batch apply them to the same original price groups.

[0072] Preferably, Figure 4 As shown, the pricing scheme function is used to support the preservation of sub-items of work at different levels, including the original pricing, the enterprise quotas, and the labor, materials, and machinery, and also includes support for free copying and application between one file or different files.

[0073] Preferably, Figure 7 As shown, the cost management software also includes a unit price calculator function. The user clicks on the unit price calculator function to calculate the comprehensive unit price of multiple sub-items, original group prices or enterprise quotas.

[0074] Preferably, Fig.11 , Fig.12 As shown, the enterprise quota library includes two modes, namely, editing mode and preview mode. The enterprise quota library also has an export password, and the user must verify the password before exporting the file.

[0075] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. Anyone familiar with the technology may modify or change the above embodiments without violating the spirit and scope of the present invention. Therefore, all equivalent modifications or changes made by those with ordinary knowledge in the technical field without departing from the spirit and technical ideas disclosed by the present invention should still be covered by the claims of the present invention.

Claims

1. Methods for calculating construction project costs, Features: Including cost management software, the cost management software includes quota material and labor library editor, data conversion, intelligent price combination and data comparison and analysis functions; Users can add, compile and maintain quotas through the quota material and equipment library editor to form enterprise pricing standards, and can repeatedly apply enterprise pricing standards to different projects. The data conversion is used to convert the cost file compiled by the standard into the cost file priced by the enterprise quota as the standard. The cost file priced by the enterprise quota as the standard is the cost file. The intelligent pricing includes AI guidance, batch cloning and pricing scheme functions. The data comparison analysis includes labor, material and equipment comparison and sub-item amount comparison functions; The following steps are also included: Step 1: Convert the pricing file to the cost file with one click. Open the cost management software, select the pricing file compiled by the standard, and convert it to the cost file with one click. Step 2: Reuse the basic information, fees, rates and template pricing modules of the pricing file, and then apply the enterprise quota to complete the preparation of the cost file; Step 3: AI price combination, establish a data conversion model between standard quota and enterprise quota through Excel table. When the file is converted, the original standard quota will be converted into the original price combination that is not included in the total price; Step 4: When compiling the cost file, the original price group is selected, and the cost management software automatically recommends the corresponding enterprise quota, completes the quota addition, and generates the quota price group; Step 5: The data comparison and analysis also includes a cost comparison function, which is used by the user to import pricing files and complete data matching and analysis of specific unit prices and total prices; Step 6: The user uses the labor, material and machinery comparison function, and the user selects the original component to display the increase or decrease of the labor, material and machinery consumption between the standard quota and the enterprise quota in real time; Step 7: It also includes an enterprise quota database, which contains supplementary quotas for highways in various provinces across the country. The enterprise quota database supports the entry, analysis and calculation of labor, material, machinery and equipment data; It also includes a calculation method for the cost file, which is as follows: creating a budget estimate file, the budget estimate file includes a total budget estimate amount, the total budget estimate amount includes several sub-item amounts, the sub-item amounts include construction and installation engineering costs, land use and demolition compensation fees, other engineering construction costs, contingency funds and construction period loan interest; The cost management software also includes a function of batch cloning of enterprise quotas, and the completed quota price groups are batch applied to the same original price groups through the function of batch cloning of enterprise quotas; The pricing scheme function is used to support the preservation of sub-items of work at different levels, including the original pricing, the enterprise quotas, and the labor, materials, and machinery, and also supports free copying and application between one file or different files.

2. The construction project cost estimation method according to claim 1, Features: The construction and installation project costs include direct costs, equipment purchase costs, measures costs, business management fees, fees, profits, taxes and special expenses. The direct costs refer to the various costs incurred during the construction process that constitute the project entity and contribute to the formation of the project, including labor costs, material costs and construction machinery usage fees.

3. The construction project cost estimation method according to claim 1, Features: It also includes fixed-rate construction and installation project fees, which are fixed according to fixed standards and are actual expenses incurred.

4. The construction project cost estimation method according to claim 1, Features: The cost management software mentioned is "Tongwang WEC Cost Management Software V10".

5. The construction project cost estimation method according to claim 1, Features: The standards mentioned above are compiled based on the "Method for Preparing Budgets and Estimates for Highway Engineering Construction Projects" (JTG / 3830-2018) and "Highway Engineering Budget Quotas" (JTG / 3932-2018) issued by the Ministry of Transport.

6. The construction project cost estimation method according to claim 1, Features: The cost management software also includes a unit price calculator function, and the user clicks on the unit price calculator function to calculate the comprehensive unit price of multiple sub-items, original group prices or enterprise quotas.

7. The construction project cost estimation method according to claim 1, Features: The enterprise quota library includes two modes, namely, editing mode and preview mode. The enterprise quota library also has an export password, and the user must verify the password before exporting the file.