A construction method for self-supporting measures for cantilever structures in high-rise buildings.

By using a self-supporting construction method, and employing temporary triangular supports and unloading supports to install the cantilever structure layer by layer, the problems of low construction efficiency and high cost of large cantilever structures were solved. This enabled efficient and low-cost cantilever structure construction, controlled cantilever deflection, and improved construction progress.

CN117627168BActive Publication Date: 2026-11-17MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311679846.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-08
Publication Date
2026-11-17
Estimated Expiration
2043-12-08

AI Technical Summary

Technical Problem

Existing construction methods for cantilever structures are inefficient, cumbersome, and costly for large cantilever structures, especially when the cantilever floors are high and the structure is heavy, making construction difficult and costly and unable to meet on-site requirements.

Method used

The self-supporting construction method is adopted. Temporary triangular supports and unloading supports are installed on the steel columns. The bottom beam of the cantilever structure is hinged and fixed to the steel column. The cantilever units are installed layer by layer. The cantilever structure is fixed by the top truss. Concrete is poured layer by layer and the joints are welded. Finally, the temporary supports are removed to achieve self-supporting of the load.

Benefits of technology

It improved construction efficiency, reduced costs, simplified operating procedures, solved the problem of difficult control of cantilever deflection, and accelerated the on-site construction progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117627168B_ABST
    Figure CN117627168B_ABST
Patent Text Reader

Abstract

This invention discloses a construction method for a self-supporting structure of a high-rise building's cantilever structure. The steps include: installing temporary triangular supports on steel columns; installing unloading supports on the temporary triangular supports; installing the bottom cantilever beam of the cantilever structure, with the temporary triangular supports providing support and the beams connecting to the steel columns in the cantilever beam being hinged to the steel columns; installing the bottom support columns of the cantilever structure; sequentially installing each cantilever unit; installing a top truss above the cantilever structure; laying floor slabs after removing the unloading supports, pouring concrete layer by layer, and reserving a post-pouring strip at the connection between the cantilever structure and the main structure; welding the connection between the cantilever structure and the main structure; pouring the post-pouring strip; and removing the temporary triangular supports. This invention employs a self-supporting construction method, which is convenient to operate, requires less work, and has high construction efficiency. It not only improves on-site construction progress but also solves the problem of difficult-to-control cantilever deflection through reasonable construction arrangements, showing promising application prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of steel structure construction technology, and to a construction method for a self-supporting measure for a cantilever structure of a high-rise building. In particular, it relates to a construction method for a self-supporting measure for a cantilever structure of a high-rise building that features high installation efficiency, small site occupation, fast construction progress, and convenient control of cantilever unloading and deflection. Background Technology

[0002] In steel structure construction, cantilever structures are often encountered. Depending on the size of the cantilever span and the weight of the structure, and in combination with the actual site conditions, corresponding cantilever construction methods are proposed. Usually, scaffolding support or guide chain inclined tie method is used. However, when the cantilevered floors are high and the overall cantilever structure is heavy, neither scaffolding support nor guide chain inclined tie method can meet the on-site construction requirements. The construction difficulty is too high, the installation cost is too high, and the construction efficiency is too low.

[0003] Therefore, developing a construction method for large cantilever structures that is efficient, cost-effective, and easy to operate is of great practical significance. Summary of the Invention

[0004] In view of the above-mentioned defects in the existing technology, the present invention provides a construction method for large cantilever structures that is efficient, low-cost and easy to operate, and solves the defects of existing cantilever structure construction methods for large cantilever structures, which are characterized by low construction efficiency, cumbersome operation and high cost.

[0005] To achieve the above objectives, the present invention provides the following technical solution:

[0006] A construction method for a self-supporting cantilever structure in a high-rise building includes the following steps:

[0007] (1) Install temporary triangular supports on the steel columns, with the temporary triangular supports located below the target installation height of the cantilever structure;

[0008] (2) Install unloading supports on the temporary triangular supports;

[0009] (3) Install the bottom cantilever beam of the cantilever structure, wherein the cantilever beam is supported by temporary triangular supports and the beams in the cantilever beam that are connected to the steel columns are fixed to the steel columns in a hinged manner.

[0010] (4) Install the support columns at the bottom of the cantilever structure;

[0011] (5) Repeat steps (3) to (4) to install each cantilever unit in sequence until the entire cantilever structure is installed;

[0012] (6) Install a top truss above the cantilever structure, and fix the top truss to both the cantilever structure and the main structure;

[0013] (7) After removing the unloading support, lay the floor deck, pour concrete layer by layer, and reserve a post-pouring strip at the connection between the cantilever structure and the main structure, with the hinged position located in the post-pouring strip.

[0014] (8) Weld the connection between the cantilever structure and the main structure;

[0015] (9) Casting the post-cast strip;

[0016] (10) Remove the temporary triangular supports. Finally, remove the temporary triangular supports. On the one hand, the temporary triangular supports can provide a certain safety redundancy for the cantilever structure during concrete pouring. On the other hand, it can optimize the on-site construction rhythm. After the concrete is poured, the temporary triangular supports are removed. At this time, the number of construction personnel required on site is small, which can greatly improve the construction efficiency.

[0017] Before starting the hoisting of the cantilever structure, temporary triangular supports are first set up at the lower part of the cantilever. After the supports are completed, the cantilever components are hoisted. The cantilever end is set on the temporary supports, and the load of the cantilever components is transferred to the steel columns through the temporary supports. When installing the cantilever components, the steel beams at the root of the cantilever are first connected with bolts. The upper and lower flanges of the steel beams are not welded for the time being. Other beam and column joints are rigidly connected. Each layer of beam and column units is installed in sequence until the installation is completed. At this time, except for the steel beams at the root of the cantilever, all other areas are welded and must pass the flaw detection. After the cantilever structure is installed, the top truss is installed. The truss is welded to the structure. The truss is used to hold the cantilever structure, turning it into a semi-cantilever and semi-suspended structure. At this time, the unloading supports at the lower end of the cantilever structure and the temporary triangular supports are cut off to separate it from the temporary supports. After confirming that everything is correct, the floor decking is laid.

[0018] Before pouring the floor slab, a post-pouring strip is left on the upper flange of the cantilever root. The remaining part is poured with concrete layer by layer. During the process, the deflection value of the cantilever end is monitored at all times. When the pouring is completed and the elevation of the cantilever structure is about to approach the design value, the upper and lower flanges at the steel beam joint at the cantilever root are welded immediately. At this time, the deflection at the end of the cantilever is basically consistent with the design requirements. After the welding is completed, the post-pouring strip at the weld is re-poured and the entire temporary triangular support is removed. At this point, the installation of the entire cantilever structure is completed.

[0019] The construction method of the self-supporting measure for cantilever structures of high-rise buildings of the present invention adopts a self-supporting construction method, which is convenient to operate, requires less work, and has high construction efficiency. It can not only improve the on-site construction progress, but also solve the problem of difficult control of cantilever deflection through reasonable construction arrangement, and has good application prospects.

[0020] As a preferred technical solution:

[0021] The construction method for a self-supporting measure for a cantilever structure of a high-rise building, as described above, involves obtaining the design parameters for the temporary triangular support as follows:

[0022] 1) Based on BIM-related software, a triangular support model was erected after comprehensively considering the load of the cantilever structure;

[0023] 2) After applying the load to the triangular support model, perform verification calculations to ensure that the support structure can successfully transfer the load to the structural steel column.

[0024] The construction method for a self-supporting measure for a cantilever structure of a high-rise building, as described above, includes the following installation process for the temporary triangular bracing:

[0025] a) Process the components of the temporary triangular support, and assemble and weld the components to obtain the temporary triangular support;

[0026] b) Hoist the temporary triangular support to the designated location and install it. Space must be reserved at the designated location for unloading the cantilever structure.

[0027] c) Conduct flaw detection on the temporary triangular supports. After ensuring that all flaw detections are qualified, proceed to the next step of construction.

[0028] The construction method for a self-supporting cantilever structure of a high-rise building, as described above, involves installing the cantilever structure in the order of beams first, followed by columns.

[0029] As described above, in the construction method of a self-supporting cantilever structure for high-rise buildings, when the cantilever structure is installed in step (5), all members in the cantilever structure are fixed by welding except for the beams connected to the steel columns which are fixed to the steel columns in a hinged manner.

[0030] The construction method of the self-supporting measure for the cantilever structure of a high-rise building, as described above, involves removing and unloading the supports and then measuring the deflection value at the cantilever end.

[0031] As described above, in the construction method of a self-supporting measure for a cantilever structure of a high-rise building, during step (7) the deflection of the overall structure after various loads are applied is constantly monitored during the concrete pouring process.

[0032] After the downward deflection stabilizes, the connection between the cantilever structure and the main structure is welded.

[0033] The construction method for a self-supporting cantilever structure in a high-rise building, as described above, specifically involves welding the upper and lower flanges at the root of the cantilever beam at the connection between the cantilever structure and the main structure.

[0034] The construction method of the self-supporting measure for the cantilever structure of a high-rise building as described above, wherein the post-pouring strip is poured after the weld in step (8) has been inspected and the inspection results are qualified.

[0035] The construction method of a self-supporting measure for a cantilever structure of a high-rise building, as described above, wherein the hinge is achieved through a connecting plate and high-strength bolts;

[0036] A corbel is welded and fixed to the steel column. The corbel is fixedly connected to the cantilever beam by a connecting plate. The connecting plate is bolted to both the corbel and the cantilever beam.

[0037] The above technical solution is only one feasible technical solution of the present invention. The scope of protection of the present invention is not limited thereto. Those skilled in the art can reasonably adjust the specific design according to actual needs.

[0038] The above invention has the following advantages or beneficial effects:

[0039] (1) The construction method of the self-supporting measure of the cantilever structure of the high-rise building of the present invention adopts the self-supporting cantilever structure construction method, which uses the structure itself to bear the cantilever load, without the need to erect a frame from the ground, and the triangular support has the advantages of being lightweight and recyclable, which not only reduces the amount of steel used in the frame, but also greatly shortens the time required for the installation and dismantling of the frame support.

[0040] (2) The construction method of the self-supporting measure for cantilever structure of high-rise buildings of the present invention is easy to operate, requires less work, and has high construction efficiency. It can not only improve the on-site construction progress, but also solve the problem of difficult control of cantilever deflection through reasonable construction arrangement, and has good application prospects. Attached Figure Description

[0041] The invention, its features, shape, and advantages will become more apparent from the following detailed description of non-limiting embodiments with reference to the accompanying drawings. Like reference numerals denote like parts throughout the drawings. The drawings are not drawn to scale; the emphasis is on illustrating the gist of the invention.

[0042] Figure 1 This is a construction schematic diagram of the self-supporting measure for cantilever structures in high-rise buildings according to the present invention;

[0043] Figure 2 This is a schematic diagram of the welded joint at the root of the cantilever structure.

[0044] Among them, 1. Temporary triangular support; 2. Unloading support; 3. Cantilever structure; 4. Top truss; 5. Main structure; 6. Steel column; 7. Post-cast strip; 8. Connecting plate; 9. Corbel; 10. Cantilever beam; 11. Floor slab inside the main structure; 12. Floor slab inside the cantilever structure. Detailed Implementation

[0045] The structure of the present invention will be further described below with reference to the accompanying drawings and specific embodiments, but this is not intended to limit the present invention.

[0046] Example 1

[0047] A construction method for a self-supporting cantilever structure in a high-rise building includes the following steps:

[0048] (1) Based on BIM-related software, a triangular support model was erected after comprehensively considering the load of the cantilever structure;

[0049] (2) After applying the load to the triangular support model, perform the verification calculation to ensure that the support structure can successfully transfer the load to the structural steel column;

[0050] (3) The triangular support is disassembled into individual parts, processed by a processing plant and transported to the site;

[0051] (4) Install and weld the components and use a tower crane to lift them to the designated location;

[0052] (5) After installation, reserve unloading space for the cantilever structure at the end of the temporary triangular support;

[0053] (6) Conduct flaw detection on the temporary triangular support. After ensuring that all flaw detections are qualified, proceed to the next step of construction and install unloading support 2 on the temporary triangular support 1.

[0054] (7) Hoist the cantilever beam 10 and hinge the root to the steel column 6. Place the cantilever end on the temporary triangular support 1. The hinge is achieved by connecting plate 8 and high-strength bolts. A bracket 9 is welded and fixed on the steel column 6. The bracket 9 and the cantilever beam 10 are fixedly connected by connecting plate 8. The connecting plate 8 is connected to the bracket 9 and the cantilever beam 10 by bolts.

[0055] (8) Install the steel columns corresponding to the cantilever beams in place, and then install the cantilever beams of the next floor to form a stable unit;

[0056] (9) Install the entire cantilever structure on the first floor in individual units, and finally form a whole;

[0057] (10) After the cantilever installation of the first floor is completed, continue the above construction sequence of beam first and column later until the entire cantilever structure 3 is installed. Weld and fix the ends of the cantilever structure, and only hinge the root for the time being.

[0058] (11) The top truss 4 is installed using the cantilever structure 3. After the top truss is installed, it is welded. At this time, as shown... Figure 1 As shown;

[0059] (12) After all installations are completed, the cantilever structure 3 is unloaded and the deflection value at the cantilever end is measured.

[0060] (13) After unloading, lay the floor deck and pour concrete layer by layer for the cantilever. A post-pouring strip 7 is reserved at the root of each cantilever structure.

[0061] (14) Use the top truss 4 to support the cantilever structure 3, observe the overall structure's deflection after various loads are applied, and begin welding the upper and lower flanges at the cantilever root after the structure has stabilized. (See details below.) Figure 2 As shown;

[0062] (15) After the welding is completed and the flaw detection is qualified, pour the post-pouring strip 7;

[0063] (16) Remove temporary triangular support 1 and complete the installation of cantilever structure and truss.

[0064] Verification has shown that the construction method of the self-supporting cantilever structure for high-rise buildings of the present invention adopts a self-supporting cantilever structure construction method, which utilizes the structure itself to bear the cantilever load, eliminating the need for ground-based scaffolding. Furthermore, the triangular supports are lightweight and reusable, reducing the amount of steel used in the scaffolding and significantly shortening the time required for scaffolding installation and dismantling. The method is convenient to operate, requires less work, and has high construction efficiency. It not only improves on-site construction progress but also solves the problem of difficult-to-control cantilever deflection through reasonable construction arrangements, demonstrating promising application prospects.

[0065] Those skilled in the art should understand that variations can be implemented by combining existing technology with the above embodiments, which will not be elaborated here. Such variations do not affect the essence of the present invention, and will not be elaborated here either.

[0066] The preferred embodiments of the present invention have been described above. It should be understood that the present invention is not limited to the specific embodiments described above, and the devices and structures not described in detail should be understood as being implemented in a conventional manner in the art. Any person skilled in the art can make many possible variations and modifications to the technical solutions of the present invention using the methods and techniques disclosed above, or modify them into equivalent embodiments with equivalent changes, without departing from the scope of the present invention. This does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes, and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the present invention's technical solutions still fall within the protection scope of the present invention.

Claims

1. A construction method of a self-supporting measure of a high-rise building cantilever structure, characterized by: Includes the following steps: (1) Install temporary triangular supports on the steel columns, and the temporary triangular supports are located below the target installation height of the cantilever structure; (2) Install unloading supports on the temporary triangular supports; (3) Install the bottom cantilever beam surface of the cantilever structure, wherein the cantilever beam surface is supported by temporary triangular supports and the beams in the cantilever beam surface that are connected to the steel columns are fixed to the steel columns in a hinged manner; (4) Install the support columns at the bottom of the cantilever structure; (5) Repeat steps (3) to (4) to install each cantilever unit in sequence until the entire cantilever structure is installed; (6) Install a top truss above the cantilever structure, and fix the top truss to both the cantilever structure and the main structure; (7) After removing the unloading support, lay the floor deck, pour concrete layer by layer, and reserve a post-pouring strip at the connection between the cantilever structure and the main structure, with the hinged position located in the post-pouring strip; (8) Weld the connection between the cantilever structure and the main structure; (9) Post-pouring strip; (10) Remove the temporary triangular support.

2. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, The process for obtaining the design parameters of the temporary triangular support is as follows: 1) Based on BIM-related software, a triangular support model was erected after comprehensively considering the load of the cantilever structure; 2) Verify the triangular support model after applying the load.

3. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 2, characterized in that, The installation process of the temporary triangular support is as follows: a) Process the components of the temporary triangular support, assemble and weld the components to obtain the temporary triangular support; b) Hoist the temporary triangular support to the designated location and install it. Space must be reserved at the designated location for unloading the cantilever structure. c) Conduct flaw detection on the temporary triangular supports. After ensuring that all flaw detections are qualified, proceed to the next step of construction.

4. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, The cantilever structure was installed in the order of beams first, then columns.

5. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, When the cantilever structure is installed in step (5), except for the beams connected to the steel columns which are fixed to the steel columns in a hinged manner, all other members in the cantilever structure are fixed by welding.

6. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, After removing the unloading support, the downward deflection value of the cantilever end was measured.

7. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, In step (7), during the concrete pouring process, the overall structure deflection is constantly monitored after each load is applied; After the downward deflection stabilizes, the connection between the cantilever structure and the main structure is welded.

8. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, The welding of the connection between the cantilever structure and the main structure specifically involves welding the upper and lower flanges at the root of the cantilever beam.

9. The construction method for a self-supporting cantilever structure of a high-rise building according to claim 1, characterized in that, The post-cast strip is cast after the weld in step (8) has been inspected and the inspection results are satisfactory.

10. The construction method of a self-supporting measure for a cantilever structure of a high-rise building according to claim 1, characterized in that, The hinge is achieved through a connecting plate and high-strength bolts; A corbel is welded and fixed to the steel column. The corbel is fixedly connected to the cantilever beam by a connecting plate. The connecting plate is bolted to both the corbel and the cantilever beam.

Citation Information

Patent Citations

  • Supporting-free construction method of ultrahigh overhung steel-structure truss

    CN105625732A

  • Jig-frame-free support construction method for steel suspension structure

    CN116335280A