High-rise modular steel structure building nodes and construction methods suitable for high-intensity areas

By designing a combination of pull rod shear locks and rubber injection pipes in high-rise modular steel structure buildings, the problems of insufficient shear bearing capacity and low construction efficiency in buildings in high-intensity areas are solved, and efficient and economical lateral constraints are achieved. Protected by tension overload, it meets the seismic resistance needs of high-rise buildings.

CN115749024BActive Publication Date: 2024-11-15SOUTH CHINA UNIV OF TECH

Patent Information

Application Number
CN202210895912.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-27
Publication Date
2024-11-15
Estimated Expiration
2042-07-27

AI Technical Summary

Technical Problem

The existing modular steel structure buildings lack reliable lateral constraint mechanisms, tension overload protection mechanisms and cost-effective assembly and connection mechanisms in high-rise buildings in high-intensity areas, resulting in insufficient shear bearing capacity, low construction efficiency and high connection costs.

Method used

A high-rise modular steel structure building node including tie rod shear lock, anchor, sleeve, limit nut and rubber pipe is designed. The tie rod shear lock provides high-strength lateral constraints as shear keys to realize the shaft. Transmitting and being protected by tension overload, and injecting epoxy resin glue into the injection pipe to fill the installation gaps, simplifying the construction process.

Benefits of technology

It provides reliable lateral constraints and tension overload protection, reduces connection costs, improves construction efficiency, meets the seismic resistance needs of high-rise buildings in high-intensity areas, and realizes rapid assembly and disassembly between modules.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115749024B_ABST
    Figure CN115749024B_ABST
Patent Text Reader

Abstract

The present invention provides a high-rise modular steel structure building node and construction method suitable for high-intensity areas. The building node includes an upper unit column, a lower unit column, an upper unit bottom beam, a lower unit ceiling beam, an upper connection box, a lower connection box, a connection plate, an upper anchor, a lower anchor, an upper sleeve, a lower sleeve, a pull rod shear lock, a limit nut, and a glue injection pipe. The lower anchor is fixedly connected to the top plate of the lower connection box; the lower limit nut is fixedly connected to the lower anchor; one end of the lower sleeve is fixedly connected to the lower anchor, and the other end is fixedly connected to the top plate of the lower connection box; the bottom of the upper sleeve is fixedly connected to the bottom plate of the upper connection box. The present invention can realize rapid assembly between upper and lower modules indoors without reserving holes on the floor or beams; when the modular steel structure building is affected by disasters such as strong earthquakes or hurricanes, the anchor, sleeve, and pull rod shear lock can efficiently transmit horizontal and vertical loads; when the building is finished serving, the module unit can be quickly recovered by simply disassembling the connection node.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This design involves the field of earthquake resistance of building structures, and specifically involves a high-rise modular steel structure building node and construction method suitable for high-intensity areas in a modular steel structure building. Background Art

[0002] As a highly integrated prefabricated building, modular steel structure buildings play an important role in epidemic prevention and control, disaster prevention and emergency response, etc. This type of building has the advantage of being highly integrated, so the construction of connections between modules has become the main part of on-site construction. Therefore, for different types of buildings, targeted designs need to be made for the connections between modules.

[0003] At present, modular buildings are mainly used for temporary buildings or permanent low-rise buildings. However, due to the advantages of modular buildings being highly integrated, their on-site construction speed is much higher than that of general prefabricated buildings, and this feature perfectly matches the high turnover characteristics of the current construction industry, so they are gradually developing towards high-rise permanent buildings. In addition, modular buildings have a high degree of standardization, so they are very suitable for use as permanent buildings in high-rise residential buildings, high-rise apartments, and hotels.

[0004] In addition, my country has now completely eliminated non-seismic zones, and more than half of the regions are located in high-intensity zones of 7 degrees or above, which poses new challenges to modular steel structure buildings built in high-intensity zones. Existing modular steel structure buildings that are targeted for low-rise permanent buildings only require the axial force transmission of the columns through the vertical pressure-bearing connection between modules, and the shear force transmission of the columns through the horizontal friction force of the connection between modules. When existing modular steel structure buildings are applied to high-rise buildings in high-intensity zones, the following problems will arise:

[0005] (1) Lack of reliable lateral restraint mechanism between upper and lower module units:

[0006] At present, the on-site connections of modular steel structure buildings mostly adopt dry operation to ensure the speed of on-site construction, and provide the shear bearing capacity between modules through the mutual lateral constraints at the connection between modules. There are currently two main lateral constraint mechanisms: 1) Using the friction between the upper and lower module units to provide lateral constraints: The principle of this mechanism is to rely on the local coupling of axial force and shear bearing capacity, that is, to rely on the positive pressure at the interface of the upper and lower module units provided by the axial force, and then provide lateral friction. However, for high-rise modular steel structure buildings built in high-intensity areas, the side columns and corner columns of the bottom floors located outside the building will have a relatively significant pull-out force under the action of earthquakes, thereby significantly reducing the positive pressure at the module interface, thereby weakening the lateral constraints, resulting in insufficient lateral constraints and shear bearing capacity between the upper and lower modules. 2) Use shear keys such as bolts and latches to mechanically lock the upper and lower module units: The principle of this mechanism is to use the mechanical locking effect of shear keys such as bolts and pins to provide high-strength lateral constraints, but a certain installation gap (about 5mm) must be left around the shear keys between the modules to facilitate on-site installation between the modules. Such installation gaps will make the shear keys only play a shear role after a certain degree of horizontal sliding occurs between the upper and lower units, resulting in a significant weakening of the integrity and lateral stiffness of high-rise modular steel structure buildings built in high-intensity areas, increasing the lateral displacement and the amplification effect of dynamic loads, and even causing lateral shear damage to the nodes.

[0007] (2) Lack of tensile overload protection mechanism between upper and lower module units:

[0008] As mentioned earlier, more than half of my country's regions are located in high-intensity zones of 7 degrees or above, and earthquakes are highly uncertain. Once the connection between the upper and lower units yields in tension and produces residual deformation in the tensile direction under a super-large earthquake that exceeds the design expectations, the connection between the modules will be unable to form secondary tensile stiffness and secondary tensile bearing capacity after being closed under compression, posing a huge hidden danger to the seismic safety of modular buildings in high-intensity areas.

[0009] (3) Lack of economical and efficient assembly connection mechanism between upper and lower module units:

[0010] As mentioned above, one of the driving forces for the development of modular steel structure buildings towards high-rise buildings is its advantages of high integration and fast on-site construction speed, which allows the high cost of module production to be offset by the low construction cost of rapid on-site assembly and rapid turnover. The connections between modules currently developed for temporary buildings or permanent low-rise buildings generally include wet connection and dry connection.

[0011] Large-scale wet work on site (concrete pouring) will significantly slow down the construction speed, making it impossible to achieve fast and efficient assembly on site, and unable to give full play to the significant advantages of dry work on steel structures. Dry work connections currently mainly include mechanical self-locking connections, prestressed tendon full-building connections, bolt connections and weld connections, among which:

[0012] 1) Mechanical self-locking connection involves a lot of complex precision machining. Although on-site connection is efficient, the connection cost is too high;

[0013] 2) For the prestressed reinforcement to be connected throughout the building, zippers must be arranged along the entire length of the building, and the zippers must be connected with sleeves on site, which places high demands on construction accuracy and will affect the efficiency of on-site construction to a certain extent. Zippers arranged throughout the entire building also significantly increase the connection cost;

[0014] 3) Bolt connection needs to be implemented outside the module box or in a completely enclosed space between boxes. Therefore, it is necessary to partially cut the maintenance wall, floor or floor to leave the construction space required for on-site connection, and partially backfill the cut part after construction, which makes it difficult to achieve standardization of building components and rapid on-site assembly;

[0015] 4) Welding connections need to be completed on site, but the quality of on-site welding is difficult to guarantee, and the welds need to be inspected after welding, which significantly affects the efficiency of the overall modular building construction speed.

[0016] Obviously, the existing modular steel structure buildings cannot meet the usage requirements. Summary of the invention

[0017] In order to solve the problems existing in the prior art, the present invention provides a high-rise modular steel structure building node and a construction method suitable for high-intensity areas, which can realize rapid assembly between upper and lower modules indoors. When the modular steel structure building is affected by disasters such as strong earthquakes or hurricanes, the anchors, sleeves, and pull rod shear locks in the connection can efficiently transfer horizontal and vertical loads; when the building ends its service, the module units can be quickly recovered by simply disassembling the connection nodes.

[0018] In order to achieve the purpose of the present invention, the present invention provides a high-rise modular steel structure building node suitable for high-intensity areas, which is used to connect upper and lower module units, including an upper unit column, a lower unit column, an upper unit bottom beam, a lower unit ceiling beam, an upper connection box, a lower connection box, a connection plate, an upper anchor, a lower anchor, an upper sleeve, a lower sleeve, a pull rod shear lock, a limit nut and a glue injection pipeline.

[0019] The upper unit column, the upper connection box, the connection plate, the lower connection box and the lower unit column are arranged in sequence from top to bottom, one end of the upper unit bottom beam is fixedly connected to the side wall of the upper connection box, and one end of the lower unit ceiling beam is fixedly connected to the side wall of the lower connection box. Specifically, the bottom end of the upper unit column is fixedly connected to the top plate of the upper connection box, one end of the upper unit bottom beam is fixedly connected to the side plate of the upper connection box, the top end of the lower unit column is fixedly connected to the bottom plate of the lower connection box, the upper connection box is located above the lower connection box, and the connection plate is clamped between the upper connection box and the lower connection box;

[0020] The upper anchor is arranged on the upper part of the upper connection box and is located in the upper unit column, the bottom end of the upper anchor is fixedly connected to the top plate of the upper connection box, and the top end of the lower anchor is fixedly connected to the bottom surface of the top plate of the lower connection box;

[0021] The upper anchor, the top plate and bottom plate of the upper connection box, the connection plate, the top plate of the lower connection box and the lower anchor are all provided with positioning slots, and all the positioning slots are located on the same vertical line.

[0022] Upper limiting nuts are fixedly arranged on both sides of the top plate of the upper anchor respectively, and lower limiting nuts are fixedly arranged on the bottom surface of the lower anchor. The bottom of the upper sleeve is fixedly connected to the bottom plate of the upper connection box, the bottom end of the lower sleeve is fixedly connected to the inner top surface of the lower anchor, and the top end is fixedly connected to the top plate of the lower connection box;

[0023] The pull rod shear lock comprises an upper connecting section, a first transition section, a tension control section, a second transition section and a shear control section. The ends of the upper connecting section and the shear control section are respectively provided with an upper thread and a lower thread. The pull rod shear lock sequentially passes through the positioning slot on the upper anchor, the positioning slot on the top plate and the bottom plate of the upper connecting box, the upper sleeve, the positioning slot on the connecting plate, the positioning slot on the top plate of the lower connecting box, the lower sleeve and the positioning slot on the lower anchor. The upper thread is threadedly connected to the upper limiting nut, and the lower thread is threadedly connected to the lower limiting nut fixed to the lower anchor. , wherein the top end of the tie rod shear lock passes through the upper anchor, and the top plate of the upper anchor is clamped between the two limit nuts. This arrangement allows the axial pressure of the upper unit column to be transmitted to the tie rod shear lock through the upper anchor; the bottom surface of the lower anchor is welded to the limit nut on the lower anchor. This arrangement allows the axial pressure transmitted from the upper unit column to the tie rod shear lock to be transmitted to the lower anchor and the lower unit column, thereby enabling the node to achieve self-reset under the action of the deadweight of the structure when there is residual tensile deformation;

[0024] Installation gaps are left between the shear control section of the pull rod shear lock and the upper sleeve, the positioning slots on the bottom plate of the upper connecting box, the positioning slots on the connecting plate, the positioning slots on the top plate of the lower connecting box, and the lower sleeve, and the glue injection pipe is used to pass epoxy resin glue into the installation gap.

[0025] Furthermore, a pre-tightening force is applied to the pull rod shear lock through the upper limiting nut.

[0026] Furthermore, a gap is left between the upper portion of the pull rod shear lock and the inner wall of the positioning slot in the upper connecting box.

[0027] Furthermore, the diameter of the tension control section in the pull rod shear lock is smaller than the diameter of the shear control end. The tension control section is weakened relative to the shear control section and the connecting section. Such a design can control the tension damage area of ​​the pull rod shear lock, which is conducive to realizing the tensile overload protection of the node.

[0028] Furthermore, the side plate of the upper unit column and the side opposite to the side plate of the upper anchor are both provided with operation windows. This arrangement can avoid changing the local arrangement of the wall and floor slab on site to meet the structural assembly requirements, thereby improving assembly efficiency.

[0029] Furthermore, a column reinforcement plate is provided on the side plate of the upper unit column and located at the west periphery of the operation window, and the column reinforcement plate is fixedly connected to the outer wall of the upper unit column.

[0030] Furthermore, it also includes a reinforcing stiffening rib, which is arranged in the upper unit column and located above the operation window, and the reinforcing stiffening rib is fixedly connected to the inner wall of the upper unit column.

[0031] Furthermore, a glue injection hole is provided on the side plate of the lower connection box, one end of the glue injection pipe is connected to the glue injection hole, and the other end passes through the side plate of the lower connection box, the lower anchor and the lower sleeve in sequence, and is fixed to the lower sleeve. This design is to facilitate the glue injection operation and is beneficial to improving the efficiency of node assembly. Epoxy resin glue is injected into the installation gap between the shear control section of the pull rod shear lock and the upper sleeve, the positioning slot in the bottom plate of the upper connection box, the positioning slot in the connection plate, the positioning slot in the top plate of the lower connection box, and the lower sleeve through the glue injection pipe. The epoxy resin glue can be injected into the gap from the glue injection hole through the glue injection pipe and fill it. This arrangement is to eliminate the installation gap.

[0032] Furthermore, a certain gap is left between the upper portion of the pull rod shear lock and the inner slot of the upper connecting box.

[0033] Furthermore, the upper unit column is welded to the top plate of the upper connection box, and the bottom end of the upper anchor is welded to the bottom plate of the upper connection box; one end of the upper unit bottom beam is welded to the side plate of the upper connection box; the bottom of the upper sleeve is welded to the bottom plate of the upper connection box; the top end of the lower anchor is welded to the top plate of the lower connection box, and the bottom surface of the lower anchor is welded to the limiting nut on the lower anchor; the upper end of the lower sleeve is welded to the top plate of the lower connection box, and the lower end of the lower sleeve is welded to the bottom plate of the lower anchor; the top end of the lower unit column is welded to the bottom surface of the lower connection box, and one end of the lower unit ceiling beam is welded to the side plate of the lower connection box.

[0034] The invention provides a construction method for high-rise modular steel structure building nodes suitable for high-intensity areas, comprising the following steps:

[0035] (1) Reserve positioning slots for the top plate and bottom plate of the upper connection box, the connection plate, the top plate of the lower connection box, the upper anchor, and the lower anchor in the factory;

[0036] (2) In the factory, the lower anchor is fixedly connected to the lower sleeve, and a hole for the glue injection pipe is reserved, and the glue injection pipe is installed. A lower limit nut is set at the lower part of the lower anchor, and the lower limit nut is fixedly connected to the lower anchor; the upper sleeve is fixedly connected to the bottom plate of the upper connection box;

[0037] (3) In the factory, the lower anchor is fixedly connected to the bottom surface of the top plate of the lower connection box, and the upper anchor is fixedly connected to the top surface of the upper connection box;

[0038] (4) In the factory, the bottom plate, top plate, front plate, and rear plate of the upper and lower connection boxes are welded to their left and right side plates to form an upper connection box and a lower connection box respectively;

[0039] (5) After the lower unit is hoisted at the construction site, place the connection plate with the reserved positioning slots on the top plate of the lower connection box, and align the centers of the positioning slots in the connection plate and the positioning slots in the top plate of the lower connection box;

[0040] (6) The pull rod shear lock is passed through the connecting plate, the top plate of the lower connecting box, the lower sleeve and the lower anchor from top to bottom, and is threadedly fixedly connected to the lower limit nut located on the bottom surface of the lower anchor;

[0041] (7) The upper unit is hoisted and placed on the lower unit. At this time, the pull rod shear lock passes through the bottom plate and the top plate of the upper connection box in sequence;

[0042] (8) When the top of the pull rod shear lock passes through the top plate of the upper connection box but does not pass through the upper anchor, suspend the lifting, tighten the upper limit nut located at the bottom of the upper anchor, and then start the lifting again;

[0043] (9) When the top end of the pull rod shear lock passes through the upper anchor and the lifting operation is completed, tighten the upper limit nut located on the upper part of the upper anchor and apply preload force through the nut;

[0044] (10) After the preload force is applied, epoxy resin glue is injected into the installation gap around the shear control section of the tie rod shear lock through the glue injection pipe, and the node installation is completed.

[0045] Furthermore, the above method further comprises the following steps:

[0046] Epoxy resin glue is injected into the gaps between the shear control section of the pull rod shear lock and the upper sleeve, the inner slot hole of the upper connecting box bottom plate, the positioning slot hole in the connecting plate, the positioning slot hole in the top plate of the lower connecting box, and the lower sleeve through the glue injection pipeline.

[0047] Compared with the prior art, the present invention has the following beneficial effects:

[0048] The present invention provides a modular steel structure building connection node to solve a series of key problems faced by such buildings when applied to high-intensity earthquake-resistant areas and high-rise building scenarios, such as insufficient shear bearing capacity, inability to bear secondary tensile loads after overload, high cost of connection between modules and inefficient construction. The building node provided by the application has the following functions:

[0049] 1) Provide reliable lateral constraints for upper and lower module units:

[0050] like Figure 1 As shown, by setting the tie rod shear lock as the shear key of the upper and lower module units, the locking effect of the component is relied on to provide high-strength lateral constraints, and epoxy resin glue is filled into the installation gap of the shear-bearing area of ​​the tie rod shear lock (shear key) through the glue injection pipeline, thereby eliminating the installation gap, eliminating the horizontal slip of the module under earthquake, and meeting the high load-bearing and high stiffness requirements of the connection between the module units.

[0051] 2) Provide tensile overload protection for upper and lower module units:

[0052] like Figure 1 As shown, by setting a tie rod shear lock connecting the upper and lower unit columns, the axial tension is transmitted between the upper and lower units, and the tension control section of the tie rod shear lock is relatively weakened (the diameter of the tension control section is smaller than the diameter of the shear control end) (as shown in Figure 4 ), so that the tensile damage of the node connecting the upper and lower units when subjected to an earthquake beyond the design expectation can be controlled within this area, realizing the tensile overload protection of the node, and the two ends of the tie rod shear lock are fixedly connected between the upper and lower module units without separation, so that the node can be self-reset through the reverse compression of the structure's own weight after tensile yielding, and form secondary tensile stiffness and secondary tensile bearing capacity.

[0053] 3) Provide a cost-effective assembly connection mechanism

[0054] The modules are connected only by locally installed tie rod shear locks without the need for full-length zip locks, which greatly saves connection costs. On site, only the tie rod shear locks need to be tensioned, and there is no wet work or welding. The connection part is located in the area inside the box where there are no walls or floors. By reserving operation holes in the column wall with operation space, economical and efficient assembly and connection can be achieved on site. BRIEF DESCRIPTION OF THE DRAWINGS

[0055] Figure 1 It is a schematic diagram of the three-dimensional structure when the connection node of an embodiment of the present invention is used for a corner column.

[0056] Figure 2 yes Figure 1 A top view of the connection node shown.

[0057] Figure 3 yes Figure 2 The schematic cross-sectional view of the connection node along the AA section is shown.

[0058] Figure 4 It is a schematic diagram of the pull rod shear lock.

[0059] In the figure:

[0060] 1-upper unit column; 2-lower unit column; 3-upper unit bottom beam; 4-lower unit ceiling beam; 5-upper connection box; 6-lower connection box; 7-connecting plate; 8-reinforcement stiffening ribs; 9-upper anchor; 10-lower anchor; 11-upper sleeve; 12-lower sleeve; 13-pull rod shear lock, upper connection section 131, first transition section 132, tension control section 133, second transition section 134, shear control section 135, upper thread 136, lower thread 137; 14-upper limiting nut; 15-lower limiting nut; 16-glue injection pipe; 17-epoxy resin glue; 18-column reinforcement plate; 19-beam reinforcement plate; 20-operating window; 21-glue injection hole. DETAILED DESCRIPTION

[0061] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0062] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0063] Figure 1 , Figure 2 , Figure 3 The invention shows a high-rise modular steel structure building node suitable for high-intensity areas, including an upper unit column 1, a lower unit column 2, an upper unit bottom beam 3, a lower unit ceiling beam 4, an upper connection box 5, a lower connection box 6, a connection plate 7, a reinforcing stiffening rib 8, an upper anchor 9, a lower anchor 10, an upper sleeve 11, a lower sleeve 12, a pull rod shear lock 13, an upper limiting nut 14, a lower limiting nut 15, a glue injection pipe 16, epoxy resin glue 17, a column reinforcement plate 18, a beam reinforcement plate 19, an operation opening 20, and a glue injection hole 21.

[0064] The upper unit column 1 is welded to the top plate of the upper connecting box 5, and the bottom end of the upper anchor 9 is welded to the top plate of the upper connecting box 5; one end of the upper unit bottom beam 3 is welded to the side plate of the upper connecting box 5; the top end of the lower anchor 10 is welded to the top plate of the lower connecting box 6, and the bottom surface of the lower anchor 10 is welded to the lower limiting nut 15; the upper end of the lower sleeve 12 is welded to the top plate of the lower connecting box 6, and the lower end of the lower sleeve 12 is welded to the bottom plate of the lower anchor 10; the bottom of the upper sleeve 11 is welded to the bottom plate of the upper connecting box 5; the top end of the lower unit column 2 is welded to the bottom surface of the lower connecting box 6, and one end of the lower unit ceiling beam 4 is welded to the side plate of the lower connecting box 6.

[0065] The top plate, bottom plate, connection plate 7 of the upper connection box 5, the top plate, upper anchor 9 and lower anchor 10 of the lower connection box 6 are all provided with positioning slots.

[0066] The upper connection box 5 is located above the lower connection box 6 , and the connection plate 7 is sandwiched between the upper connection box 5 and the lower connection box 6 .

[0067] The pull rod shear lock 13 includes an upper connecting section, a first transition section, a tension control section, a second transition section and a shear control section. The ends of the upper connecting section and the shear control section are respectively provided with an upper thread and a lower thread. The tension control section is weakened relative to the shear control section and the connecting section. In some embodiments of the present invention, please refer to Figure 4 The diameters of the upper connection section and the shear control section are the same, the diameter of the tension control section is smaller than the diameter of the shear control section, and the diameters of the first transition section connecting the upper connection section and the tension control section and the second transition section connecting the shear control section and the tension control section gradually decrease. The pull rod shear lock 13 passes through the positioning slot on the upper anchor 9, the positioning slots on the top plate and bottom plate of the upper connection box 5, the upper sleeve 11, the positioning slot on the connection plate 7, the positioning slot on the top plate of the lower connection box 6, the lower sleeve 12 and the positioning slot on the lower anchor 10 in sequence. The bottom end of the pull rod shear lock 13 passes through the lower anchor 10 and is connected to the lower limit nut 15 fixed to the lower anchor 10 through the lower thread.

[0068] The glue injection hole 21 is provided on the side plate of the lower connection box 6, one end of the glue injection pipe 16 is connected to the glue injection port 21, and the other end passes through the side plate of the lower connection box 6, the lower anchor 10 and the lower sleeve 12 in sequence and is fixed to the lower sleeve 12, communicating with the installation gap;

[0069] The upper anchor 9 is arranged on the upper part of the upper connecting box 5 and is located in the upper unit column 2. The bottom end of the upper anchor 9 is fixedly connected to the top plate of the upper connecting box 5. The top end of the pull rod shear lock 13 passes through the upper anchor 9. Upper limiting nuts 14 are respectively arranged on both sides of the top plate of the upper anchor 9. The upper part of the pull rod shear lock 13 is threadedly connected to the upper limiting nut 14.

[0070] Furthermore, a certain installation gap is left between the shear control section of the pull rod shear lock 13 and the upper sleeve 11, the positioning slot in the bottom plate of the upper connecting box 5, the positioning slot in the connecting plate 7, the positioning slot in the top plate of the lower connecting box 6, and the lower sleeve 12; a certain gap is left between the upper part of the pull rod shear lock 13 and the internal positioning slot of the upper connecting box 5.

[0071] When the upper connection box 5 is subjected to horizontal force, the locking effect of the pull rod shear lock 13 can be converted into shear stress resistance of the pull rod shear lock 13 .

[0072] When the upper unit column 1 is subjected to vertical tension, the tension can be transmitted to the lower unit column 2 through the upper anchor 9 , the pull rod shear lock 13 , and the lower anchor 10 .

[0073] An operation window 20 for workers to operate the upper limit nut 14 is provided on the same side of the side plate of the upper unit column 1 and the upper anchor 9 .

[0074] In some embodiments of the present invention, a column reinforcement plate 18 is provided on the side plate of the upper unit column 1 and around the operation window. In other embodiments, a flip plate or decorative plate can also be installed at the operation window of the upper unit column 1 after the building node is installed.

[0075] The building of this embodiment is suitable for the connection between units and between units and foundations of building forms such as high-rise modular steel structure buildings in high-intensity areas, especially node areas such as corner columns and side columns where axial force changes significantly under horizontal or vertical action.

[0076] In some embodiments of the present invention, there is also provided a method for assembling the above-mentioned connection node, comprising the following steps:

[0077] (1) In the factory, the top plate and bottom plate of the upper connection box 5, the connection plate 7, the top plate of the lower connection box 6, the upper anchor 9, and the lower anchor 10 are pre-positioned with positioning slots to avoid collision with the pull rod shear lock 13;

[0078] (2) The lower anchor 10 is welded to the lower sleeve 12 in the factory, and a hole is reserved, and a glue injection pipe 16 is installed. A lower limit nut 15 is set at the lower part of the lower anchor 10, and the nut is welded to the lower anchor 10;

[0079] (3) In the factory, the lower anchor 10 is welded to the bottom surface of the top plate of the lower connection box 6, the upper anchor 9 is welded to the top surface of the upper connection box 5, and the upper sleeve 11 is welded to the bottom plate of the upper connection box 5;

[0080] (4) The bottom plate, top plate, front plate, and rear plate of the upper connection box 5 and the lower connection box 6 are welded to their left and right side plates in the factory to form the upper connection box 5 and the lower connection box 6 respectively;

[0081] (5) After the lower unit is hoisted at the construction site, place the connection plate 7 with the reserved positioning slots on the top plate of the lower connection box 6, and align the centers of the positioning slots in the connection plate 7 and the positioning slots in the top plate of the lower connection box 6;

[0082] (6) The pull rod shear lock 13 is passed through the connecting plate 7, the top plate of the lower connecting box 6, and the lower anchor 10 from top to bottom, and is threadedly fixedly connected with the lower limit nut 15 provided at the lower part of the lower anchor 10;

[0083] (7) The upper unit is hoisted and placed on the lower unit. At this time, the top of the pull rod shear lock 13 passes through the bottom plate of the upper connection box 5 and the top plate of the upper connection box 5 in sequence;

[0084] (8) When the top end of the pull rod shear lock 13 passes through the top plate of the upper connection box 5 but does not pass through the upper anchor 9, suspend the lifting, tighten the upper limit nut 14 located below the upper anchor 9, and then start the lifting again;

[0085] (9) When the top end of the pull rod shear lock 13 passes through the upper anchor 9 and the lifting operation is completed, the upper limit nut 14 above the upper anchor 9 is tightened and a pre-tightening force is applied through the upper limit nut 14.

[0086] (10) After the preload force is applied, epoxy resin glue 17 is injected into the gap around the shear control section of the tie rod shear lock 13 through the glue injection hole 21, and the node installation is completed.

[0087] Steps (1) to (4) are processed and assembled in the factory, and steps (5) to (10) are completed at the project site.

[0088] Through the specific structure and construction method of the building node described above, the building node provided by the embodiment of the present invention can meet the following advantages required in the engineering project:

[0089] 1. Through reasonable design and reliable construction, the tie rod shear lock 13 can be set as the shear key of the upper and lower module units, and the locking effect of the component can be relied on to provide high-strength lateral constraints; and epoxy resin glue 17 is added to the installation gap of the tie rod shear lock 13 (shear key) through the glue injection pipe 16 to eliminate the installation gap and eliminate the horizontal slip of the module under earthquake, thereby providing sufficient lateral stiffness. So far, reliable lateral constraints are provided for the upper and lower module units.

[0090] 2. Through reasonable design and reliable construction, the axial tension can be transmitted between the upper and lower units by setting the tie rod shear lock 13 connecting the upper and lower unit columns, and the tension control section of the tie rod shear lock 13 is relatively weakened (such as Figure 4 ) to realize the tensile overload protection of the node.

[0091] 3. Through reasonable design and reliable construction, the connection can be designed inside the column and operation holes can be reserved on the column to achieve full bolt connection on site, effectively avoiding opening holes in walls and floors or external operations, and effectively avoiding large-scale wet operations, ultimately achieving efficient and economical assembly on site.

[0092] By applying the nodes provided in the aforementioned embodiments to engineering projects, rapid assembly between upper and lower modules can be achieved indoors without reserving holes in the floor slabs or beams. When modular steel structure buildings are hit by disasters such as strong earthquakes or hurricanes, the anchors, sleeves, and tie rod shear locks in the connections can efficiently transfer horizontal and vertical loads. When the service life of the building ends, the module units can be quickly recovered by simply disassembling the building nodes.

[0093] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. Suitable for high-rise modular steel structure building nodes in high-intensity areas, characterized by: It includes upper unit column, lower unit column, upper unit bottom beam, lower unit ceiling beam, upper connection box, lower connection box, connection plate, upper anchor, lower anchor, upper sleeve, lower sleeve, tie rod shear lock, limit nut and glue injection pipe. The upper unit column, the upper connection box, the connection plate, the lower connection box and the lower unit column are arranged in sequence from top to bottom, one end of the upper unit bottom beam is fixedly connected to the side wall of the upper connection box, and one end of the lower unit ceiling beam is fixedly connected to the side wall of the lower connection box; The upper anchor is fixed on the top plate of the upper connection box and is located in the upper unit column, and the lower anchor is fixed on the top plate of the lower connection box; The upper anchor, the top plate and bottom plate of the upper connection box, the connection plate, the top plate of the lower connection box and the lower anchor are all provided with positioning slots, and all the positioning slots are located on the same vertical line. Upper limiting nuts are fixedly arranged on both sides of the top plate of the upper anchor respectively, the lower limiting nut is fixedly arranged on the bottom surface of the lower anchor, the upper sleeve is fixedly arranged on the bottom plate of the upper connection box, and the lower sleeve is fixedly arranged between the top plate of the lower connection box and the lower anchor; The pull rod shear lock comprises an upper connecting section, a first transition section, a tension control section, a second transition section and a shear control section, the ends of the upper connecting section and the shear control section are respectively provided with an upper thread and a lower thread, the pull rod shear lock sequentially passes through the positioning slot on the upper anchor, the positioning slot on the top plate and the bottom plate of the upper connecting box, the upper sleeve, the positioning slot on the connecting plate, the positioning slot on the top plate of the lower connecting box, the lower sleeve and the positioning slot on the lower anchor, and the upper thread is threadedly connected to the upper limit nut, and the lower thread is threadedly connected to the lower limit nut; Installation gaps are left between the shear control section of the pull rod shear lock and the upper sleeve, the positioning slots on the bottom plate of the upper connecting box, the positioning slots on the connecting plate, the positioning slots on the top plate of the lower connecting box, and the lower sleeve, and the glue injection pipe is used to pass epoxy resin glue into the installation gap.

2. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 1 is characterized in that: A pre-tightening force is applied to the pull rod shear lock through the upper limiting nut.

3. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 1 is characterized in that: A gap is left between the upper part of the pull rod shear lock and the inner wall of the positioning slot hole in the upper connecting box.

4. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 1 is characterized in that: The diameter of the tension control section in the pull rod shear lock is smaller than the diameter of the shear control end.

5. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 1 is characterized in that: An operation window is provided on the side plate of the upper unit column and on the side of the upper anchor opposite to the side plate.

6. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 5 is characterized in that: A column reinforcement plate is arranged on the side plate of the upper unit column and located at the west periphery of the operation window, and the column reinforcement plate is fixedly connected to the outer wall of the upper unit column.

7. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 5 is characterized in that: It also includes a reinforcing stiffening rib, which is arranged in the upper unit column and above the operating window.

8. The high-rise modular steel structure building node suitable for high-intensity areas according to claim 1 is characterized in that: A glue injection hole is opened on the side plate of the lower connection box, one end of the glue injection pipe is connected to the glue injection hole, and the other end passes through the side plate of the lower connection box, the lower anchor and the lower sleeve in sequence, and is fixed on the lower sleeve.

9. The high-rise modular steel structure building node suitable for high-intensity areas according to any one of claims 1 to 8, characterized in that: The upper unit column is welded to the top plate of the upper connection box, and the bottom end of the upper anchor is welded to the bottom plate of the upper connection box; one end of the upper unit bottom beam is welded to the side plate of the upper connection box; the bottom of the upper sleeve is welded to the bottom plate of the upper connection box; the top end of the lower anchor is welded to the top plate of the lower connection box, and the bottom surface of the lower anchor is welded to the limiting nut on the lower anchor; the upper end of the lower sleeve is welded to the top plate of the lower connection box, and the lower end of the lower sleeve is welded to the bottom plate of the lower anchor; the top end of the lower unit column is welded to the bottom surface of the lower connection box, and one end of the lower unit ceiling beam is welded to the side plate of the lower connection box.

10. The construction method of high-rise modular steel structure building nodes suitable for high-intensity areas according to any one of claims 1 to 9, characterized in that: The following steps are involved: (1) Reserve positioning slots for the top plate and bottom plate of the upper connection box, the connection plate, the top plate of the lower connection box, the upper anchor, and the lower anchor in the factory; (2) In the factory, the lower anchor is fixedly connected to the lower sleeve, and a hole for the glue injection pipe is reserved, and the glue injection pipe is installed. A lower limit nut is set at the lower part of the lower anchor, and the lower limit nut is fixedly connected to the lower anchor; the upper sleeve is fixedly connected to the bottom plate of the upper connection box; (3) In the factory, the lower anchor is fixedly connected to the bottom surface of the top plate of the lower connection box, and the upper anchor is fixedly connected to the top surface of the upper connection box; (4) In the factory, the bottom plate, top plate, front plate, and rear plate of the upper and lower connection boxes are welded to their left and right side plates to form an upper connection box and a lower connection box respectively; (5) After the lower unit is hoisted at the construction site, place the connection plate with the reserved positioning slots on the top plate of the lower connection box, and align the centers of the positioning slots in the connection plate and the positioning slots in the top plate of the lower connection box; (6) The pull rod shear lock is passed through the connecting plate, the top plate of the lower connecting box, the lower sleeve and the lower anchor from top to bottom, and is threadedly fixedly connected to the lower limit nut located on the bottom surface of the lower anchor; (7) The upper unit is hoisted and placed on the lower unit. At this time, the pull rod shear lock passes through the bottom plate and the top plate of the upper connection box in sequence; (8) When the top of the pull rod shear lock passes through the top plate of the upper connection box but does not pass through the upper anchor, suspend the lifting, tighten the upper limit nut located at the bottom of the upper anchor, and then start the lifting again; (9) When the top end of the pull rod shear lock passes through the upper anchor and the lifting operation is completed, tighten the upper limit nut located on the upper part of the upper anchor and apply preload force through the nut; (10) After the preload force is applied, epoxy resin glue is injected into the installation gap around the shear control section of the tie rod shear lock through the glue injection pipe, and the node installation is completed.

11. The construction method of high-rise modular steel structure building nodes suitable for high-intensity areas according to claim 10 is characterized in that: Glue injection holes are opened on the lower sleeve, the lower anchor and the side plate of the lower connecting box to set up glue injection pipelines, and epoxy resin glue is injected into the installation gap between the shear control section of the pull rod shear lock and the upper sleeve, the positioning slot in the bottom plate of the upper connecting box, the positioning slot in the connecting plate, the positioning slot in the top plate of the lower connecting box and the lower sleeve through the glue injection pipeline.

Citation Information

Patent Citations

  • Structural element for thermal insulation

    CA2204699A1

  • Full-fabricated assembly overall reinforced concrete house and building method thereof

    CN101806095A

  • Pull rod type prestress connecting method of steel structure modular building

    CN106703208A

Cited By

  • Modular steel structure building friction horizontal connecting plate and construction method thereof

    CN120819165A

  • Modular steel structure building friction horizontal connecting plate and construction method thereof

    CN120819165B