A room-and-pillar stope pillar recovery structure and method
By erecting a filling structure in the goaf and using medium-deep hole blasting technology, the problems of large engineering volume and poor stability in pillar recovery in the room-and-pillar stope were solved, and fast, safe and efficient pillar recovery and environmental management were achieved.
Patent Information
- Application Number
- CN202311723245.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-14
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2043-12-14
AI Technical Summary
The existing room-and-pillar mine pillar recovery method has problems such as large amount of new mining work, long stope preparation time, low recovery efficiency, and poor safety and environmental management effects.
Use the goaf area with multiple ore pillars to set up filling retaining walls, top pillar walls and bottom pillar walls to fill the filling body, and carry out ventilation and transportation through the upper wall return air tunnel and the lower wall air inlet tunnel, and set up electric rake tunnels and chisel tunnels. In rock tunnels, medium and deep hole blasting technology is used to return to the mining pillar to reduce mining ground pressure and the instability of mining and cutting projects.
It achieves fast, safe and efficient pillar recovery, reduces the amount of new mining projects, ensures the balance of mining ground pressure and the stability of mining and cutting projects, and improves the pillar recovery rate and environmental governance effects.
Smart Images

Figure CN117684972B_ABST
Abstract
Citation Information
Patent Citations
Pillar mining method for gentle dip thin ores
CN103967493A
Method for recovering top pillars and middle pillars in bottom-pillar-free shallow-hole shrinkage subsequent filling mining method
CN115163074A