A concrete connection device of different types and its connection process
By using the combined device of nail rod and socket head in concrete connection, the problem of insufficient bond strength in the connection of new and old concrete is solved, efficient connection strength improvement and structural repair effect are achieved, and the construction process is simplified.
Patent Information
- Application Number
- CN202311696141.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-11
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2043-12-11
AI Technical Summary
The existing technology has insufficient bonding strength in the connection between old and new concrete, resulting in improper stress transmission and interface debonding, which cannot effectively ensure the structural repair effect. Moreover, the existing repair and reinforcement technology has problems with material fatigue aging, protective layer shedding, and reduced bearing capacity.
Different types of concrete connecting devices are used, including nail rods and socket heads. The gelling agent such as epoxy resin is loaded into the nail rod and injected into the old concrete surface, and the inertia of the nail gun is used to make the gelling agent from the nail gun. It flows out from the hole, and after solidification, the nail rod and the old concrete are bonded. At the same time, gel material is poured into the sleeve or new concrete is penetrated, and the sleeve and the new concrete are tightly connected through the expansion plate.
It improves the connection strength between the new and old concrete, enhances the pull-out performance of the nail rod and the old concrete, ensures the tight connection between the new and old concrete, extends the service life of the structure, and simplifies the installation process.
Smart Images

Figure CN117822746B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of concrete connection structures, and in particular to a concrete connection device of different models and a connection process thereof. Background Art
[0002] Concrete is a traditional material widely used in construction, transportation, water conservancy and other projects. Concrete not only has high strength, but also fire resistance and corrosion resistance. While concrete structures are widely used, they also face many problems. In the construction and repair process of concrete structure engineering, the connection treatment method for new and old concrete has an important impact on the safety and durability of the engineering structure. For concrete structures with large construction projects that need to be poured in batches, it is crucial to control the connection strength of the new and old concrete interface and the temperature shrinkage of the new and old concrete at different stages. Under various loads and long-term service in adverse working environments, existing concrete structures have also experienced material fatigue aging, protective layer shedding and damage, and reduced bearing capacity. For damaged concrete structures, timely and scientific repair work is needed to extend their service life. Among the existing developed repair and reinforcement technologies, covering with new concrete is the preferred technology. The strength of the original structure and the newly poured repair material is easier to control, but the bonding interface between the two is usually regarded as the weakest part of the entire composite material. If the bonding strength between the new and old concrete is weak, improper stress transfer will result in interface debonding, and the structural repair effect cannot be well guaranteed. Summary of the invention
[0003] The purpose of the present invention is to provide a concrete connection device of different models and a connection process thereof to solve one or more technical problems existing in the prior art and at least provide a beneficial choice or create conditions.
[0004] The technical solutions adopted to solve the above technical problems are:
[0005] The present invention provides a concrete connection device of different models, comprising: a nail rod, a sleeve is provided on the top of the nail rod, the bottom end of the nail rod is conical, the nail rod is provided with a nail cavity, the nail rod is provided with a plurality of nail holes connected with the nail cavity, the sleeve is provided with a top cavity, and the side wall of the sleeve is provided with a plurality of sleeve holes connected with the top cavity.
[0006] The beneficial effects of the present invention are:
[0007] Epoxy resin and other gelling agents are loaded into the nail cavity of the nail rod, and then the nail rod is nailed into the surface of the old concrete with a nail gun. When the nail rod is shot into the concrete, it stops moving due to the friction of the concrete, but the gelling agent in the nail cavity continues to move forward due to inertia and flows out of the nail hole. After the gelling material solidifies, the nail rod is bonded to the original structure, and the anti-pullout performance of the nail is improved. Then the gel material is poured into the sleeve or new concrete is penetrated. At the same time, the new concrete material flows out of the sleeve hole and solidifies, so the sleeve and the new concrete are tightly connected. The sleeve and the nail rod are tightly connected, so the new and old concrete can be effectively connected through this device.
[0008] As a further improvement of the above technical solution, a piston is slidably provided on the top of the nail shooting chamber. When the nail shooting rod is shot into the concrete, it stops moving forward due to the friction resistance of the concrete, but the piston and gelling agent in the nail shooting chamber continue to move forward due to inertia and flow out of the nail shooting hole. The piston can better squeeze the gelling agent to make it flow out of the nail shooting hole.
[0009] As a further improvement of the above technical solution, a gel is provided in the nail shooting cavity. The gel is built into the nail shooting cavity and can be directly used by shooting with a nail gun when in use.
[0010] As a further improvement of the above technical solution, the top edge of the sleeve is connected with an extension plate extending outward. The top extension plate realizes a tight connection between the sleeve and the new concrete, further improving the connection effect between the sleeve and the new concrete.
[0011] As a further improvement of the above technical solution, the sleeve is cylindrical and the extension plate is ring-shaped, so as to further improve the connection effect between the sleeve and the new concrete.
[0012] As a further improvement of the above technical solution, the nail-shooting rod is clamped with the sleeve head, so as to facilitate the nail-shooting gun to shoot the nail-shooting rod.
[0013] As a further improvement of the above technical solution, a nail head is provided on the top of the nail rod, and the sleeve is provided with a mounting hole. After the nail rod passes through the mounting hole, the nail head abuts against the sleeve, which is convenient for installation.
[0014] The present invention also provides a connection process for different types of concrete connection devices, including:
[0015] Place the sleeve on the surface of the old concrete structure;
[0016] Use a nail gun to pass the nail rod through the sleeve and nail it into the old concrete, so that the sleeve is fixed to the old concrete and the gelling agent flows out of the nail rod;
[0017] Fix multiple nail rods and sockets on the old concrete surface;
[0018] Pour gel material or inject new concrete into the top cavity of the sleeve so that the gel material or new concrete flows out from the sleeve hole;
[0019] Fill new concrete onto multiple nail rod and head surfaces.
[0020] The inertia brought by the shooting of the nail gun can strengthen the connection strength between the nail rod and the old concrete, and can strengthen the contact between the sleeve and the post-casting material when pouring new concrete or bonding materials on the outside. Through the combined effect of bonding materials and specially designed connecting nails, a tight connection between the new and old concrete is achieved. It has the advantage of simple and convenient installation.
[0021] As a further improvement of the above technical solution, before placing the sleeve, the surface of the old concrete structure is first scrubbed and roughened to remove loose concrete and protruding stones at the damaged part, so that the new concrete can be better bonded to the surface of the old concrete and the connection strength can be improved.
[0022] As a further improvement of the above technical solution, after waiting for the nail rod to be nailed in for a preset time, gel material is poured into the top cavity of the sleeve or new concrete is injected, and the gel agent is completely solidified, so that the connection between the nail rod and the old concrete is more firmly established. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] The present invention will be further described below in conjunction with the accompanying drawings and embodiments;
[0024] Figure 1 It is a structural schematic diagram of one embodiment of a concrete connection device of different models provided by the present invention;
[0025] Figure 2 It is a side view schematic diagram of one embodiment of a concrete connection device of different models provided by the present invention;
[0026] Figure 3 It is a cross-sectional schematic diagram of a concrete connection device of different models provided by the present invention, and an embodiment thereof;
[0027] Figure 4 It is a top view schematic diagram of a concrete connection device of different models provided by the present invention, one embodiment thereof;
[0028] Figure 5 The present invention provides a concrete connection device of different types, and a schematic diagram of one embodiment thereof. DETAILED DESCRIPTION
[0029] This section will describe in detail the specific embodiments of the present invention. The preferred embodiments of the present invention are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present invention, but it cannot be understood as a limitation on the scope of protection of the present invention.
[0030] In the description of the present invention, if there are words such as "several", it means one or more, "more" means more than two, greater than, less than, exceed, etc. are understood as not including the number, and above, below, within, etc. are understood as including the number.
[0031] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.
[0032] Although new materials for existing concrete repair have developed rapidly and have achieved phased breakthroughs, if we only rely on the bonding force generated by the adhesive and the friction between the new and old surfaces to connect the new and old concrete, the quality of the material itself and the on-site construction operation are high. If mistakes occur during the grouting process, the connection between the new and old concrete will be weakened, and effective repair connections cannot be guaranteed. When the adhesive fails and the new and old joint surfaces crack and peel off, there is no other connection structure to prevent the cracks from developing. If daily inspections are not timely, the entire piece of new concrete at the repair site may slide off, which may easily lead to accidents. In addition, there is still a certain gap between my country and foreign countries in terms of material uniformity and key technologies, and we still need to strengthen investment in scientific research and funds.
[0033] Although the steel bar groove embedded connection structure utilizes the design of the lock structure, it is necessary to first groove the original structure to set up the transverse groove and then place the steel bars. This not only causes great damage to the original structure, but also the construction of the transverse groove is more difficult. The overall project has many steps, a large amount of work, is time-consuming and labor-intensive, and is not economical.
[0034] The conduit glue injection sealing structure requires manual drilling of small holes on the inside of the original structural concrete, which is time-consuming and labor-intensive, and is not suitable for situations where rapid repairs are required. In addition, the conduit design requirements are high, requiring not only strength to meet the connection requirements but also suitability for operation.
[0035] The waterproof lining grouting connection between the new and old concrete structures is a solution to the water seepage problem caused by the failure of the waterproof structure at the weak points of the construction joints of underground engineering structures such as subways. The problem of preventing groundwater from seeping into the parallel joints is only achieved by increasing the shape and size of the contact surface between the new and old concrete. The connection still mainly relies on the friction and bonding force between the gel repair adhesive material and the original structural material, and no other auxiliary components are used for reinforcement.
[0036] The new and old concrete connection structures using a locking mechanism have more requirements for the original structure. It needs to be suitable for the opening to form a protruding structure, and is more suitable for brick structures of building construction. It cannot be used for concrete repairs of bridge piers.
[0037] The I-shaped reinforcement lap joint of old and new concrete connection structure is mainly aimed at the field of road maintenance and repair. The original structure needs to have a relatively neat staggered section. There are many requirements for the original structure and the application field is relatively narrow.
[0038] In view of the above shortcomings, the purpose of the present invention is to provide a device for connecting new and old or different types of concrete surfaces, which is easy to operate, quick to construct and has better connection performance. In the following embodiments, new and old concrete are used as an illustration, and new and old concrete can also be understood as two different types of concrete, which is not limited to this.
[0039] Therefore, refer to Figures 1 to 5 The present invention provides a concrete connection device of different types and makes the following embodiments:
[0040] In some embodiments, a different type of concrete connection device includes: a nail rod 100, a sleeve 200 is clamped on the top of the nail rod 100, and when shooting, the nail rod 100 is shot with a nail gun to fix the sleeve 200 on the surface of the old concrete 400. Specifically in this embodiment, a nail head 120 is provided on the top of the nail rod 100, and the sleeve 200 is provided with a mounting hole 202. After the nail rod 100 passes through the mounting hole 202, the nail head 120 abuts against the sleeve 200, which is easy to install. In some other embodiments, the sleeve 200 can also be directly fixedly connected to the head of the nail rod 100, and is taken into the old concrete 400 together with the nail gun. In some other embodiments, the sleeve 200 may not be provided with the mounting hole 202. The nail rod 100 directly pierces the sleeve 200 and fixes the sleeve 200 to the surface of the old concrete 400. This requires a higher piercing strength of the nail rod 100, which needs to pierce into the sleeve 200 and the old concrete 400 at the same time.
[0041] The bottom end of the nail rod 100 is conical, which is convenient for the nail rod 100 to be nailed into the old concrete 400. The nail rod 100 is provided with a nail cavity 110, and the nail cavity 110 is used to contain a gel. The gel can be directly poured into the nail cavity 110 during production, which is more convenient during installation. Alternatively, the gel can be poured into the nail cavity 110 during installation, which can effectively prevent the gel from solidifying and facilitate the storage and transportation of the device.
[0042] The nail rod 100 is provided with a plurality of nail holes 111 connected to the nail cavity 110. When the nail rod 100 is shot into the old concrete 400, the gel flows out from the nail holes 111 and solidifies to improve the connection strength between the nail rod 100 and the old concrete 400. The plurality of nail holes 111 are evenly spaced on the side wall of the nail rod 100 to further improve the connection strength between the nail rod 100 and the old concrete 400;
[0043] The sleeve 200 is cylindrical, and is provided with a cylindrical top cavity 210, and the side wall of the sleeve 200 is provided with a plurality of sleeve holes 201 connected with the top cavity 210. The top inner cavity of the sleeve 200 is poured with gel material or penetrated with new concrete, and the new concrete material flows out from the sleeve holes 201 and solidifies, so as to achieve a tight connection between the sleeve 200 and the new concrete. It should be noted that the sleeve 200 can be in other shapes, such as a column with a rectangular cross section.
[0044] Furthermore, the extension plate 220 is in a ring shape, and the top extension plate 220 realizes a tight connection between the sleeve 200 and the new concrete, further improving the connection effect between the sleeve 200 and the new concrete. In some other embodiments, the top edge of the sleeve 200 is connected to an extension plate 220 extending outward, and the extension plate 220 can be in various shapes. It can be known that the larger the area of the extension plate 220, the higher the connection strength.
[0045] As a further improvement, a piston 300 is slidably provided on the top of the nail chamber 110. When the nail rod 100 stops moving due to the friction of the concrete after being shot into the concrete, the piston 300 and the gelling agent in the nail chamber 110 continue to move forward due to inertia and flow out of the nail hole 111. The piston 300 can better squeeze the gelling agent to make it flow out of the nail hole 111.
[0046] The specific construction process is:
[0047] The original structure surface of the cast-in-place concrete, that is, the structure surface of the old concrete 400, is first scrubbed and roughened to remove loose concrete and protruding stones at the damaged part. This allows the new concrete to better adhere to the surface of the old concrete and improve the connection strength. If there are some loose stones, after the stones fall off, the falling position is not connected, that is, the connection surface between the old concrete 400 and the new concrete is reduced, and the connection strength is weakened.
[0048] Place the sleeve 200 at an appropriate position on the surface of the old concrete 400 structure, then put the nail gun into the sleeve 200, and use the nail gun to drive the nail rod 100 into the original structure or the surface of the old concrete 400. The nail gun can directly drive into the mounting hole 202 of the sleeve 200, or directly pierce through the sleeve 200 and the old concrete 400 at the same time.
[0049] On one hand, after the nail rod 100 is driven into the old concrete 400, the sleeve 200 will generate pressure between the contact surface with the nail head 120 of the nail rod 100, and the sleeve 200 is fixed to the original structure or the surface of the old concrete 400 by the nail rod 100. On the other hand, the nail body is provided with a nail chamber 110 for storing a gelling agent such as epoxy resin, and nail holes 111 are provided around the nail head 120, and a piston 300 is provided on the top. When the nail rod 100 is shot into the old concrete 400, it stops moving forward due to the friction resistance of the old concrete 400, and the gelling agent in the nail chamber 110 and the piston 300 continue to move forward due to inertia and flow out from the nail holes 111 around the nail head 120. After the gelling material solidifies, the nail rod 100 is bonded to the original structure or the old concrete 400, and the pull-out resistance of the nail rod 100 is improved.
[0050] Gel material or new concrete is poured into one side of the sleeve 200, and the top extension plate 220 of the sleeve 200 is horizontally extended, similar to an enlarged and widened nail head 120. New concrete flows into the sleeve 200 and flows out of the sleeve hole 201 to solidify, which has a strengthening fixing effect. The sleeve 200 and the new concrete are tightly connected through the sleeve hole 201 and the top extension plate 220.
[0051] Therefore, the new concrete and the sleeve 200, the nail rod 100 and the original structure or the old concrete 400 can be tightly connected, and the sleeve 200 is tightly connected to the nail rod 100 through the nail head 120. Therefore, the new concrete and the old concrete 400 can be effectively connected through the device. The device has the advantages of easy operation and fast construction.
[0052] The present invention also provides an implementation of a connection process for concrete connection devices of different models, including:
[0053] The surface of the old concrete 400 structure is first scrubbed and roughened to remove loose concrete and protruding stones at the damaged part. This allows the new concrete to better bond to the surface of the old concrete 400 and improve the connection strength;
[0054] The sleeve 200 is placed on the surface of the old concrete 400 structure;
[0055] Use a nail gun to pass the nail rod 100 through the sleeve 200 and nail it into the old concrete 400, so that the sleeve 200 is fixed to the old concrete 400 and the gel flows out of the nail rod 100;
[0056] Fix multiple nail rods 100 and sleeves 200 on the surface of old concrete 400, refer to Figure 5 As shown;
[0057] After the gelling agent solidifies for a preset time, the specific length of time is determined according to the solidification time of the gelling agent. After the gelling agent is completely solidified, the connection between the nail rod 100 and the old concrete is more firmly connected, and then the gelling material is poured into the top cavity 210 of the sleeve 200 or new concrete is injected, so that the concrete flows out from the sleeve hole 201;
[0058] New concrete is filled on the surfaces of the plurality of nail rods 100 and the sleeve heads 200 .
[0059] The inertia brought by the shooting of the nail gun can strengthen the connection strength between the nail rod 100 and the old concrete 400, and then when new concrete or bonding material is poured externally, the contact between the sleeve 200 and the post-casting material can be strengthened. Through the combined action of the bonding material and the specially designed connecting nails, a tight connection between the new and old concrete 400 is achieved. It has the advantage of simple and convenient installation.
[0060] The preferred embodiments of the present invention are specifically described above, but the invention is not limited to the embodiments. Those skilled in the art may make various equivalent modifications or substitutions without violating the spirit of the invention. These equivalent modifications or substitutions are all included in the scope defined by the claims of this application.
Claims
1. A concrete connection device of different types, characterized in that: The invention comprises a nail-shooting rod (100), wherein a sleeve (200) is provided at the top of the nail-shooting rod (100), the bottom end of the nail-shooting rod (100) is in a conical shape, the nail-shooting rod (100) is provided with a nail-shooting cavity (110), the nail-shooting rod (100) is provided with a plurality of nail-shooting holes (111) connected to the nail-shooting cavity (110), the sleeve (200) is provided with a top cavity (210), a plurality of sleeve holes (201) connected to the top cavity (210) are provided on a side wall of the sleeve (200), and a piston (300) is slidably provided at the top of the nail-shooting cavity (110). ), the top edge of the sleeve (200) is connected to an extension plate (220) extending outward, and a gel is provided in the nail shooting cavity (110); the sleeve (200) is cylindrical, and the extension plate (220) is ring-shaped; the nail shooting rod (100) is snap-connected with the sleeve (200); a nail head (120) is provided at the top of the nail shooting rod (100), and the sleeve (200) is provided with a mounting hole (202); after the nail shooting rod (100) passes through the mounting hole (202), the nail head (120) abuts against the sleeve (200).
2. A connection process for different types of concrete connection devices, which is applied to the different types of concrete connection devices according to claim 1, characterized in that: include: The sleeve (200) is placed on the surface of the old concrete (400) structure. Before placing the sleeve (200), the surface of the old concrete (400) structure is first brushed and roughened to remove loose concrete and protruding stones at the damaged part; A nail gun is used to pass a nail rod (100) through a sleeve (200) and simultaneously nail the nail rod into the old concrete (400). When the nail rod (100) is shot into the concrete, it stops moving forward due to the frictional resistance of the concrete, but the piston (300) and the gelling agent in the nail chamber (110) continue to move forward due to inertia and flow out of the nail hole (111), so that the sleeve (200) is fixed to the old concrete (400) and the gelling agent flows out of the nail rod (100); Fixing a plurality of nail rods (100) and sleeves (200) on the surface of old concrete (400); After waiting for the nail rod (100) to be nailed in for a preset time, a gel material is poured into the top cavity (210) of the sleeve (200) or new concrete is injected; a gel material is poured into the top cavity (210) of the sleeve (200) or new concrete is injected, so that the gel material or new concrete flows out from the sleeve hole (201); New concrete is filled on the surfaces of the plurality of nail rods (100) and the sleeves (200).