Distributed multi-zone heating real-time regulation method and system

By dividing the heating area into multiple sub-areas and using edge computing servers for personalized adjustments, the problems of low adjustment efficiency and accuracy of the heating system have been solved, thus improving the quality of heating.

CN117870015BActive Publication Date: 2026-11-17BEIJING DISTRICT HEATING GRP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410167776.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-06
Publication Date
2026-11-17
Estimated Expiration
2044-02-06

AI Technical Summary

Technical Problem

The existing heating system's regulation efficiency and accuracy are insufficient to meet the requirements, and centralized regulation servers cannot effectively handle the large-scale heating system, resulting in poor heating quality.

Method used

The heating area is divided into multiple sub-regions, and edge computing servers are used to adjust the heating in different regions. Sub-regions are selected based on the assessment of heating problems, abnormal energy consumption values, and adjustment difficulty, and then personalized adjustments are made.

Benefits of technology

It enables accurate screening and personalized adjustment of sub-areas with significant heating problems, improving the reliability and efficiency of adjustment and avoiding the problem of poor heating quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117870015B_ABST
    Figure CN117870015B_ABST
Patent Text Reader

Abstract

This invention provides a distributed multi-regional heating real-time adjustment method and system, belonging to the field of heating adjustment technology. Specifically, it includes: determining the energy consumption anomalies and energy-abnormal sub-regions based on heating energy consumption data from different sub-regions; determining when the current adjustment method does not meet requirements based on the heating problem assessment quantities and heating problem sub-regions; determining the adjustment difficulty of different sub-regions based on the heating network topology and equipment of different sub-regions; determining the comprehensive assessment quantity and screening sub-regions based on the energy consumption anomalies and heating problem assessment quantities of the sub-regions; setting up separate edge computing servers in the screened sub-regions; and performing heating adjustment in the screened sub-regions based on the edge computing servers, thereby further ensuring the processing efficiency of heating network adjustment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention belongs to the field of heating regulation technology, and in particular relates to a method and system for real-time regulation of distributed multi-region heating. Background Technology

[0002] To ensure the reliability of heating system operation, it is often necessary to monitor the operating parameters of different heating pipe networks in real time and dynamically adjust the operating parameters of the heating pipe networks based on the monitoring results. Since the heating system is relatively large, using a centralized heating regulation server to regulate the heating system may result in insufficient regulation efficiency and accuracy. Therefore, how to divide the heating system and use edge computing servers to perform regional regulation based on the energy consumption data of different heating system areas, so as to ensure the efficiency and accuracy of regulation processing, has become an urgent technical problem to be solved.

[0003] To address the aforementioned technical problems, this invention provides a method and system for real-time regulation of distributed multi-regional heating. Summary of the Invention

[0004] To achieve the objectives of this invention, the following technical solution is adopted: According to one aspect of the present invention, a method for real-time regulation of distributed multi-zone heating is provided.

[0005] A method for real-time regulation of distributed multi-zone heating, characterized in that it specifically includes: S1 divides the heating area into multiple sub-areas based on the distribution of heating stations. Based on the problem heating data of problem heating users in different sub-areas, the heating problem assessment quantity of different sub-areas and the determination of the heating problem sub-areas are carried out. It is determined whether the number of heating problem sub-areas meets the requirements. If yes, proceed to the next step; otherwise, proceed to step S3. S2 acquires heating energy consumption data for different sub-regions, identifies energy consumption anomalies and abnormal sub-regions based on the heating energy consumption data for different sub-regions, and determines the current adjustment method if it does not meet the requirements when combined with the heating problem assessment of different sub-regions and the heating problem sub-regions. Then, proceed to the next step. S3 determines the adjustment difficulty of different sub-regions based on the heating network topology and equipment of different sub-regions, and determines the comprehensive evaluation quantity of the sub-region and screens sub-regions by combining the energy consumption anomaly value and heating problem assessment quantity of the sub-region; S4 sets up a separate edge computing server in the selected sub-region and adjusts the heating of the selected sub-region based on the edge computing server.

[0006] The beneficial effects of this invention are as follows: 1. Based on the heating problem data of users in different sub-regions, the assessment of heating problems in different sub-regions and the identification of sub-regions with heating problems are carried out. This enables accurate assessment of the severity of heating adjustment problems in different sub-regions based on the heating problem situation of users, thereby enabling the screening of sub-regions with larger heating problems and laying the foundation for determining differentiated heating adjustment methods. 2. Based on the adjustment difficulty, energy consumption anomalies, and heating problem assessment, the comprehensive assessment of sub-regions and the selection of sub-regions are determined. This not only considers the differences in adjustment difficulty caused by the complexity of the heating network and the number of equipment in the sub-regions, but also assesses the magnitude of heating problems in different sub-regions through energy consumption anomalies and heating problem assessment. This enables accurate assessment of the selection of sub-regions that require individual heating adjustment from multiple perspectives.

[0007] 3. The heating adjustment of the selected sub-regions is performed based on the edge computing server, which ensures the reliability and efficiency of the heating adjustment in the selected sub-regions with greater adjustment difficulty and heating problems, and avoids the occurrence of technical problems such as poor heating quality due to insufficient adjustment accuracy.

[0008] A further technical solution involves dividing the heating area into multiple sub-areas based on the distribution of heating stations, specifically including: Based on the distribution of heating stations, the corresponding heating sub-regions of different heating stations are determined, and the heating area is divided into multiple sub-regions based on the heating sub-regions.

[0009] A further technical solution is that the problem heating user is determined based on the heating data of different heating users. Specifically, when the heating user's heating output does not meet the heating output threshold requirement, the heating user is determined to be a problem heating user.

[0010] A further technical solution is that the problematic heating data includes the duration of problematic heating for the heating user and the deviation rate of the amount of heat supplied during different problematic heating durations.

[0011] A further technical solution is that when the assessment of the heating problem in the sub-region does not meet the requirements, the sub-region is determined to be a heating problem sub-region.

[0012] A further technical solution is that the abnormal energy consumption value of the sub-region is determined based on the heating energy consumption of the sub-region and the preset heating energy consumption, specifically based on the deviation between the heating energy consumption of the sub-region and the preset heating energy consumption.

[0013] A further technical solution is that the method for determining the energy consumption anomaly sub-region is as follows: When the energy consumption anomaly value of the sub-region does not meet the requirements, the sub-region is determined to be an energy consumption anomaly sub-region.

[0014] On the other hand, the present invention provides a computer system comprising: a memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that: when the processor runs the computer program, it executes the above-described distributed multi-zone heating real-time adjustment method.

[0015] Other features and advantages will be set forth in the description which follows, and will be apparent in part from the description, or may be learned by practicing the invention. The objects and other advantages of the invention are realized and obtained through the structures particularly pointed out in the description and the drawings.

[0016] To make the above-mentioned objects, features and advantages of the present invention more apparent and understandable, preferred embodiments are described below in detail with reference to the accompanying drawings. Attached Figure Description

[0017] The above and other features and advantages of the present invention will become more apparent from a detailed description of exemplary embodiments thereof with reference to the accompanying drawings.

[0018] Figure 1 This is a flowchart of a distributed multi-zone heating real-time adjustment method; Figure 2 This is a flowchart illustrating the method for determining the assessment parameters of heating problems; Figure 3 This is a flowchart illustrating the method for determining the adjustment difficulty of a sub-region. Detailed Implementation

[0019] Exemplary embodiments will now be described more fully with reference to the accompanying drawings. However, these exemplary embodiments can be implemented in many forms and should not be construed as limited to the embodiments set forth herein; rather, they are provided so that the invention will be thorough and complete, and the concept of the exemplary embodiments will be fully conveyed to those skilled in the art. The same reference numerals in the drawings denote the same or similar structures, and therefore their detailed description will be omitted.

[0020] The terms “a,” “one,” “the,” and “the” are used to indicate the existence of one or more elements / components / etc.; the terms “including” and “having” are used to indicate an open-ended meaning of inclusion and that other elements / components / etc. may exist in addition to the listed elements / components / etc.

[0021] Example 1 To solve the above problems, according to one aspect of the present invention, such as Figure 1 As shown, according to one aspect of the present invention, a method for real-time adjustment of distributed multi-zone heating is provided, characterized in that it specifically includes: S1 divides the heating area into multiple sub-areas based on the distribution of heating stations. Based on the problem heating data of problem heating users in different sub-areas, the heating problem assessment quantity of different sub-areas and the determination of the heating problem sub-areas are carried out. It is determined whether the number of heating problem sub-areas meets the requirements. If yes, proceed to the next step; otherwise, proceed to step S3. S2 acquires heating energy consumption data for different sub-regions, identifies energy consumption anomalies and abnormal sub-regions based on the heating energy consumption data for different sub-regions, and determines the current adjustment method if it does not meet the requirements when combined with the heating problem assessment of different sub-regions and the heating problem sub-regions. Then, proceed to the next step. S3 determines the adjustment difficulty of different sub-regions based on the heating network topology and equipment of different sub-regions, and determines the comprehensive evaluation quantity of the sub-region and screens sub-regions by combining the energy consumption anomaly value and heating problem assessment quantity of the sub-region; S4 sets up a separate edge computing server in the selected sub-region and adjusts the heating of the selected sub-region based on the edge computing server.

[0022] Furthermore, based on the distribution of heating stations, the heating area is divided into multiple sub-regions, specifically including: Based on the distribution of heating stations, the corresponding heating sub-regions of different heating stations are determined, and the heating area is divided into multiple sub-regions based on the heating sub-regions.

[0023] Specifically, the problem heating user is determined based on the heating data of different heating users. Specifically, when the heating user's heating output does not meet the heating output threshold requirement, the heating user is determined to be a problem heating user.

[0024] It is understood that the problematic heating data includes the duration of problematic heating for the heating users and the deviation rate of the amount of heat supplied during different problematic heating durations.

[0025] In one possible embodiment, such as Figure 2 As shown, the method for determining the assessment quantity of the heating problem is as follows: Based on the problem heating data of the problem heating users in the sub-region, the over-supply users in the sub-region whose heating supply is greater than the rated heating range and the under-supply users whose heating supply is less than the rated heating range are identified. The abnormal heating value of the over-supply user is determined based on the problem heating duration of the over-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. The abnormal heating value of the under-supply user is determined based on the problem heating duration of the under-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. The assessment of heating problems in the sub-region is determined based on the number of over-supply users and the abnormal heating values ​​of different over-supply users, the number of under-supply users and the abnormal heating values ​​of different under-supply users.

[0026] Furthermore, if the assessment of heating problems in the sub-region does not meet the requirements, then the sub-region is determined to be a heating problem sub-region.

[0027] In another possible embodiment, the method for determining the heating problem assessment quantity is as follows: Based on the problem heating data of the problem heating users in the sub-region, the over-supply users in the sub-region whose heating supply is greater than the rated heating range and the under-supply users whose heating supply is less than the rated heating range are identified. When the number of over-supply users and under-supply users in the sub-region is greater than the preset number of users, the sub-region is determined as a heating problem sub-region, and the heating problem assessment quantity of the sub-region is determined according to the number of over-supply users and under-supply users. When the number of over-supply users and under-supply users in the sub-region is not greater than the preset number of users, the user heating abnormality value of the over-supply users is determined based on the problem heating duration of the over-supply users and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. The user heating abnormality value of the under-supply users is determined based on the problem heating duration of the under-supply users and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. If there are no over-supply or under-supply users in the sub-region whose heating supply abnormality value is greater than the preset abnormal threshold, then the sub-region is determined not to be a problem heating sub-region, and the heating problem assessment quantity of the sub-region is determined according to the number of over-supply and under-supply users. When there are over-supply users or under-supply users in the sub-region whose heating supply anomaly value exceeds a preset anomaly threshold, the heating problem assessment value of the sub-region is determined based on the number of over-supply users and the different heating supply anomaly values ​​of over-supply users, the number of under-supply users and the different heating supply anomaly values ​​of under-supply users.

[0028] In another possible embodiment, the method for determining the heating problem assessment quantity is as follows: S11 uses the problem heating data of the problem heating users in the sub-region to determine the over-supply users in the sub-region whose heating supply is greater than the rated heating range and the under-supply users whose heating supply is less than the rated heating range. It then determines whether the sum of the number of over-supply users and under-supply users in the sub-region is less than the second preset number of users. If yes, proceed to the next step; otherwise, proceed to step S14. S12 determines the abnormal heating value of the over-supply user based on the problem heating duration of the over-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply; and determines the abnormal heating value of the under-supply user based on the problem heating duration of the under-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. S13 determines whether there are over-supply users or under-supply users whose heating supply abnormal value is greater than the preset abnormal threshold. If yes, proceed to the next step. If no, determine that the sub-area does not belong to the problem heating sub-area, and determine the heating problem assessment quantity of the sub-area based on the number of over-supply users and under-supply users. S14 determines the assessment quantity of the heating problem in the sub-region based on the number of over-supply users and the user heating anomaly values ​​of different over-supply users, the number of under-supply users and the user heating anomaly values ​​of different under-supply users.

[0029] Specifically, the abnormal energy consumption value of the sub-region is determined based on the heating energy consumption of the sub-region and the preset heating energy consumption, specifically based on the deviation between the heating energy consumption of the sub-region and the preset heating energy consumption.

[0030] Furthermore, the method for determining the energy consumption anomaly sub-region is as follows: When the energy consumption anomaly value of the sub-region does not meet the requirements, the sub-region is determined to be an energy consumption anomaly sub-region.

[0031] In one possible embodiment, determining whether the current adjustment method meets the requirements is based on the heating problem assessment quantities of different sub-regions and the heating problem sub-regions, specifically including: The comprehensive energy consumption anomaly value is determined based on the average value of energy consumption anomalies in different sub-regions, the number of energy consumption anomaly sub-regions, and the energy consumption anomalies in different energy consumption anomaly sub-regions. The comprehensive heating problem value is determined based on the average value of the heating problem assessment in different sub-regions, the number of heating problem sub-regions, and the energy consumption anomaly values ​​in different heating problem sub-regions. The comprehensive abnormal quantity is determined by the comprehensive heating problem value and the comprehensive energy consumption abnormal value, and the current adjustment method is determined based on the comprehensive abnormal quantity to determine whether it meets the requirements.

[0032] In another possible embodiment, determining whether the current adjustment method meets the requirements by combining the heating problem assessment quantities of different sub-regions and the heating problem sub-regions, specifically includes: If the number of abnormal energy consumption sub-regions does not meet the requirements, then the current adjustment method is determined to be unacceptable. Subregions that simultaneously belong to both the energy consumption anomaly subregion and the heating problem subregion are designated as problem subregions for screening. If the number of problem subregions for screening is insufficient, the current adjustment method is determined to be unsatisfactory. When the number of the selected problem sub-regions meets the requirements, the regional energy consumption anomaly value of the energy consumption anomaly sub-region is determined based on the number of the energy consumption anomaly sub-regions and the energy consumption anomaly values ​​of different energy consumption anomaly sub-regions. When the regional energy consumption anomaly value of the energy consumption anomaly sub-region does not meet the requirements, it is determined that the current adjustment method does not meet the requirements. When the energy consumption anomaly value of the energy consumption anomaly sub-region meets the requirements, the comprehensive problem assessment quantity of the selected problem sub-region is determined based on the number of selected problem sub-regions, the energy consumption anomaly values ​​of different selected problem sub-regions, and the heating problem assessment quantity. When the comprehensive problem assessment quantity of the selected problem sub-region does not meet the requirements, it is determined that the current adjustment method does not meet the requirements. When the comprehensive problem assessment quantity of the screened problem sub-regions meets the requirements, the comprehensive energy consumption anomaly value is determined based on the average value of the energy consumption anomaly value of different sub-regions, the number of energy consumption anomaly sub-regions, and the energy consumption anomaly value of different energy consumption anomaly sub-regions. The comprehensive heating problem value is determined based on the average value of the heating problem assessment quantity of different sub-regions, the number of heating problem sub-regions, and the energy consumption anomaly value of different heating problem sub-regions. The comprehensive anomaly is determined by the comprehensive heating problem value, the comprehensive energy consumption anomaly value, and the comprehensive problem assessment quantity of the screened problem sub-regions. Based on the comprehensive anomaly, it is determined whether the current adjustment method meets the requirements.

[0033] In another possible embodiment, determining whether the current adjustment method meets the requirements by combining the heating problem assessment quantities of different sub-regions and the heating problem sub-regions, specifically includes: Based on the number of energy consumption abnormal sub-regions and the energy consumption abnormal values ​​of different energy consumption abnormal sub-regions, the regional energy consumption abnormal value of the energy consumption abnormal sub-region is determined. It is then determined whether the regional energy consumption abnormal value of the energy consumption abnormal sub-region meets the requirements. If yes, proceed to the next step; otherwise, it is determined that the current adjustment method does not meet the requirements. Based on the number of sub-regions with heating problems and the abnormal energy consumption values ​​of different sub-regions, the comprehensive heating problem value of the sub-regions with heating problems is determined. It is then determined whether the comprehensive heating problem value of the sub-regions with heating problems meets the requirements. If yes, proceed to the next step; otherwise, it is determined that the current adjustment method does not meet the requirements. Subregions that simultaneously belong to both the energy consumption anomaly subregion and the heating problem subregion are designated as screening problem subregions. The comprehensive problem assessment quantity of the screening problem subregions is determined based on the number of screening problem subregions, the energy consumption anomaly values ​​of different screening problem subregions, and the heating problem assessment quantity. It is then determined whether the comprehensive problem assessment quantity of the screening problem subregions meets the requirements. If yes, proceed to the next step; otherwise, it is determined that the current adjustment method does not meet the requirements. The comprehensive energy consumption anomaly value is determined based on the average value of energy consumption anomalies in different sub-regions, the number of energy consumption anomaly sub-regions, and the energy consumption anomalies in different energy consumption anomaly sub-regions. The comprehensive heating problem value is determined based on the average value of heating problem assessment in different sub-regions, the number of heating problem sub-regions, and the energy consumption anomalies in different heating problem sub-regions. The comprehensive anomaly is determined by the comprehensive heating problem value, the comprehensive energy consumption anomaly value, and the comprehensive problem assessment quantity of the screened problem sub-regions. Based on the comprehensive anomaly, it is determined whether the current adjustment method meets the requirements.

[0034] In one possible embodiment, such as Figure 3 As shown, the method for determining the adjustment difficulty of the sub-region is as follows: The length of the heating network in the sub-region is determined based on the heating network of the sub-region, and the network complexity of the heating network in the sub-region is determined by combining the identification results of the topology map of the heating network topology. Based on the heating equipment of the heating network in the sub-region, the number of different types of heating equipment in the heating network in the sub-region is determined, and the adjustment complexity of the sub-region is determined in combination with the adjustment capacity of different heating equipment. The complexity of user adjustment in a sub-region is determined by the number of heating users in that sub-region and the amount of heat supplied by each user. The adjustment difficulty of the sub-region is determined based on the pipeline complexity, adjustment complexity, and user adjustment complexity.

[0035] In another possible embodiment, the method for determining the adjustment difficulty of the sub-region is as follows: If any one of the following factors—the length of the heating network, the number of heating devices, or the number of heating users—does not meet the requirements, the adjustment difficulty of the sub-region is determined by preset adjustment difficulty. When the length of the heating network, the number of heating devices, and the number of heating users in the sub-region all meet the requirements, the length of the heating network in the sub-region is determined based on the heating network of the sub-region, and the network complexity of the heating network in the sub-region is determined in combination with the topology map identification results of the heating network topology. It is then determined whether the network complexity of the heating network in the sub-region meets the requirements. If yes, proceed to the next step; otherwise, determine the adjustment difficulty of the sub-region based on the network complexity. Based on the heating equipment of the heating network in the sub-region, determine the number of different types of heating equipment in the heating network of the sub-region, and determine the adjustment complexity of the sub-region in combination with the adjustment capacity of different heating equipment. Determine whether the adjustment complexity of the sub-region meets the requirements. If yes, proceed to the next step. If no, determine the adjustment difficulty of the sub-region through the adjustment complexity. The user adjustment complexity of the sub-region is determined by the number of heating users in the sub-region and the heating capacity of different heating users. It is then determined whether the user adjustment complexity of the sub-region meets the requirements. If yes, proceed to the next step; otherwise, the adjustment difficulty of the sub-region is determined by the user adjustment complexity. The adjustment difficulty of the sub-region is determined based on the pipeline complexity, adjustment complexity, and user adjustment complexity.

[0036] In one possible embodiment, the method for determining the filtered sub-region is as follows: When the sub-region belongs to the sub-region with abnormal energy consumption or the sub-region with heating problems, the sub-region is determined to be a screening sub-region; When the sub-region does not belong to the energy consumption abnormality sub-region or the heating problem sub-region, and when the adjustment difficulty of the sub-region does not meet the requirements, the sub-region is determined to belong to the screening sub-region. When the adjustment difficulty of the sub-region meets the requirements, the comprehensive problem assessment quantity of the sub-region is determined based on the energy consumption anomaly value and the heating problem assessment quantity of the sub-region. When the comprehensive problem assessment quantity does not meet the requirements, the sub-region is determined to be a screening sub-region. When the comprehensive problem assessment quantity meets the requirements, the comprehensive assessment quantity is determined based on the adjustment difficulty of the sub-region and the comprehensive problem assessment quantity of the sub-region, and the sub-region is determined as a screening sub-region through the comprehensive assessment quantity.

[0037] Example 2 On the other hand, the present invention provides a computer system comprising: a memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that: when the processor runs the computer program, it executes the above-described distributed multi-zone heating real-time adjustment method.

[0038] Through the above embodiments, this application achieves the following technical effects: 1. Based on the problem heating data of users with heating problems in different sub-regions, the heating problem assessment volume of different sub-regions and the identification of heating problem sub-regions are carried out. This enables accurate assessment of the severity of heating adjustment problems in different sub-regions based on the problem heating situation of heating users, thereby enabling the screening of problem sub-regions with larger heating problems and laying the foundation for determining differentiated heating adjustment methods.

[0039] 2. Based on the adjustment difficulty, energy consumption anomalies, and heating problem assessment, the comprehensive assessment of sub-regions and the selection of sub-regions are determined. This not only considers the differences in adjustment difficulty caused by the complexity of the heating network and the number of equipment in the sub-regions, but also assesses the magnitude of heating problems in different sub-regions through energy consumption anomalies and heating problem assessment. This enables accurate assessment of the selection of sub-regions that require individual heating adjustment from multiple perspectives.

[0040] 3. The heating adjustment of the selected sub-regions is performed based on the edge computing server, which ensures the reliability and efficiency of the heating adjustment in the selected sub-regions with greater adjustment difficulty and heating problems, and avoids the occurrence of technical problems such as poor heating quality due to insufficient adjustment accuracy.

[0041] The various embodiments in this specification are described in a progressive manner. Similar or identical parts between embodiments can be referred to mutually. Each embodiment focuses on describing the differences from other embodiments. In particular, the embodiments of apparatus, devices, and non-volatile computer storage media are basically similar to the method embodiments, so the descriptions are relatively simple; relevant parts can be referred to the descriptions of the method embodiments.

[0042] The foregoing has described specific embodiments of this specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recited in the claims may be performed in a different order than that shown in the embodiments and may still achieve the desired result. Furthermore, the processes depicted in the drawings do not necessarily require the specific or sequential order shown to achieve the desired result. In some embodiments, multitasking and parallel processing are possible or may be advantageous.

[0043] The above description is merely one or more embodiments of this specification and is not intended to limit this specification. Various modifications and variations can be made to the one or more embodiments of this specification by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principle of one or more embodiments of this specification should be included within the scope of the claims of this specification.

Claims

1. A method for real-time adjustment of distributed multi-zone heating, characterized in that, Specifically, it includes: S1 divides the heating area into multiple sub-areas based on the distribution of heating stations. Based on the problem heating data of problem heating users in different sub-areas, the heating problem assessment quantity of different sub-areas and the determination of the heating problem sub-areas are carried out. It is determined whether the number of heating problem sub-areas meets the requirements. If yes, proceed to the next step; otherwise, proceed to step S3. S2 acquires heating energy consumption data for different sub-regions, identifies energy consumption anomalies and abnormal sub-regions based on the heating energy consumption data for different sub-regions, and determines the current adjustment method if it does not meet the requirements when combined with the heating problem assessment of different sub-regions and the heating problem sub-regions. Then, proceed to the next step. S3 determines the adjustment difficulty of different sub-regions based on the heating network topology and equipment of different sub-regions, and determines the comprehensive evaluation quantity of the sub-region and screens sub-regions by combining the energy consumption anomaly value and heating problem assessment quantity of the sub-region; S4 sets up a separate edge computing server in the selected sub-region and adjusts the heating of the selected sub-region based on the edge computing server; The method for determining the filtering sub-region is as follows: When the sub-region belongs to the sub-region with abnormal energy consumption or the sub-region with heating problems, the sub-region is determined to be a screening sub-region; When the sub-region does not belong to the energy consumption abnormality sub-region or the heating problem sub-region, and when the adjustment difficulty of the sub-region does not meet the requirements, the sub-region is determined to belong to the screening sub-region. When the adjustment difficulty of the sub-region meets the requirements, the comprehensive problem assessment quantity of the sub-region is determined based on the energy consumption anomaly value and the heating problem assessment quantity of the sub-region. When the comprehensive problem assessment quantity does not meet the requirements, the sub-region is determined to be a screening sub-region. When the comprehensive problem assessment quantity meets the requirements, the comprehensive assessment quantity is determined based on the adjustment difficulty of the sub-region and the comprehensive problem assessment quantity of the sub-region, and the sub-region is determined as a screening sub-region through the comprehensive assessment quantity.

2. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, Based on the distribution of heating stations, the heating area is divided into multiple sub-areas, specifically including: Based on the distribution of heating stations, the corresponding heating sub-regions of different heating stations are determined, and the heating area is divided into multiple sub-regions based on the heating sub-regions.

3. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, The problem heating user is determined based on the heating data of different heating users. Specifically, when the heating user's heating output does not meet the heating output threshold requirement, the heating user is determined to be a problem heating user.

4. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, The method for determining the assessment parameters of the heating problem is as follows: Based on the problem heating data of the problem heating users in the sub-region, the over-supply users in the sub-region whose heating supply is greater than the rated heating range and the under-supply users whose heating supply is less than the rated heating range are identified. The abnormal heating value of the over-supply user is determined based on the problem heating duration of the over-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. The abnormal heating value of the under-supply user is determined based on the problem heating duration of the under-supply user and the deviation rate between the heating supply during the problem heating duration and the rated heating supply. The assessment of heating problems in the sub-region is determined based on the number of over-supply users and the abnormal heating values ​​of different over-supply users, the number of under-supply users and the abnormal heating values ​​of different under-supply users.

5. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, If the assessment of heating problems in the sub-region does not meet the requirements, then the sub-region is determined to be a heating problem sub-region.

6. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, The abnormal energy consumption value of the sub-region is determined based on the heating energy consumption of the sub-region and the preset heating energy consumption, specifically based on the deviation between the heating energy consumption of the sub-region and the preset heating energy consumption.

7. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, Based on the assessment of heating problems in different sub-regions and the sub-regions with heating problems, determine whether the current adjustment methods meet the requirements, specifically including: The comprehensive energy consumption anomaly value is determined based on the average value of energy consumption anomalies in different sub-regions, the number of energy consumption anomaly sub-regions, and the energy consumption anomalies in different energy consumption anomaly sub-regions. The comprehensive heating problem value is determined based on the average value of the heating problem assessment in different sub-regions, the number of heating problem sub-regions, and the energy consumption anomaly values ​​in different heating problem sub-regions. The comprehensive abnormal quantity is determined by the comprehensive heating problem value and the comprehensive energy consumption abnormal value, and the current adjustment method is determined based on the comprehensive abnormal quantity to determine whether it meets the requirements.

8. The distributed multi-zone heating real-time adjustment method as described in claim 1, characterized in that, The method for determining the adjustment difficulty of the sub-region is as follows: The length of the heating network in the sub-region is determined based on the heating network of the sub-region, and the network complexity of the heating network in the sub-region is determined by combining the identification results of the topology map of the heating network topology. Based on the heating equipment of the heating network in the sub-region, the number of different types of heating equipment in the heating network in the sub-region is determined, and the adjustment complexity of the sub-region is determined in combination with the adjustment capacity of different heating equipment. The complexity of user adjustment in a sub-region is determined by the number of heating users in that sub-region and the amount of heat supplied by each user. The adjustment difficulty of the sub-region is determined based on the pipeline complexity, adjustment complexity, and user adjustment complexity.

9. A computer system, comprising: A memory and a processor connected in communication, and a computer program stored in the memory and capable of running on the processor, characterized in that: when the processor runs the computer program, it executes a distributed multi-zone heating real-time adjustment method according to any one of claims 1-8.

Citation Information

Patent Citations

  • Heat supply control method based on energy consumption monitoring

    CN104534556A

  • Method for reducing transmission and distribution energy consumption of regional central heat supply network

    CN104848412A