Evaluation method and system for construction progress of main system equipment in nuclear island of nuclear power plant

Through the nuclear island main system equipment list and unified equipment installation point rules based on historical data, the problems of limited scope of application and low accuracy of the construction progress evaluation method of nuclear island main system equipment in nuclear power plants in the existing technology have been solved, and a more accurate method has been achieved. Comprehensive and more accurate construction progress management.

CN117973938BActive Publication Date: 2024-10-25CHINA NUCLEAR IND 23 CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410160761.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2024-10-25
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

The existing methods for evaluating the construction progress of nuclear island main system equipment in nuclear power plants have problems such as limited scope of application, incomplete evaluation, and low accuracy. They cannot effectively adapt to the update of nuclear power reactor types and the upgrade of nuclear safety requirements.

Method used

Based on historical nuclear power project data, determine the list of main system equipment of the nuclear island to be built, including the total number of installation points of main system equipment for various reactor types and the detailed points of each construction sub-item. Complete each construction sub-item according to the installation steps of the main system equipment. , and release the points corresponding to the completed point entries in stages, and formulate unified equipment installation point rules to achieve the balance and unification of each pile type.

Benefits of technology

It expands the applicable scope of evaluation, improves the accuracy of construction progress, ensures the comprehensiveness and accuracy of evaluation, and is suitable for construction progress management of main system equipment of nuclear power plants of different reactor types.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117973938B_ABST
    Figure CN117973938B_ABST
Patent Text Reader

Abstract

The present invention provides a method and system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, and relates to the technical field of nuclear power plant construction. The method comprises: firstly, based on historical nuclear power project data, determining a list of the main system equipment of the nuclear island to be constructed; the list comprises: the total points of the installation of the main system equipment of various reactor types, and the detailed points of each construction sub-item; the main system equipment installation comprises a number of construction sub-items; the point items contained in each construction sub-item correspond to the points to be released when the point items are completed; then, each construction sub-item is completed according to the installation steps of the main system equipment, and the points corresponding to the completed point items are released in stages. By using this method, the technical problems of the limited application scope and low evaluation accuracy of the existing evaluation method for the construction progress of the main system equipment of the nuclear island of a nuclear power plant can be alleviated, and the technical effect of expanding the application scope and improving the evaluation accuracy can be achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of nuclear power plant construction, and in particular to a method and system for evaluating the construction progress of main system equipment of a nuclear island of a nuclear power plant. Background Art

[0002] In the early stage of nuclear power plant construction in my country, the progress of nuclear island installation required a lot of manpower and time to verify the completion of on-site construction, that is, to evaluate it through image projects. However, nuclear island construction involves tens of thousands of equipment with different shapes, sizes, tonnages, and precisions. Evaluation through image projects will consume a large number of statistical personnel and will not be conducive to the evaluation of the overall project completion, remaining volume, and efficiency. It was not until the construction of Daya Bay Nuclear Power Plant around 1990 that the "point system" of the French FRAMATOME / SPIE company was introduced and used, which enabled the efficient evaluation of the nuclear island installation progress, and it has been used ever since.

[0003] With the update and iteration of nuclear power reactor types; the continuous upgrading of nuclear safety requirements; the continuous emergence of new materials, new equipment, new technologies, and new processes; the continuous improvement of nuclear energy construction management level; the problem of regularization of huge differences in main system equipment of different reactor types, etc., the original engineering "point system" method of measuring the installation progress of nuclear island main system equipment has gradually become incomplete, inapplicable, and unreasonable, and the progress evaluation has become distorted and inaccurate. In other words, the existing evaluation method of the construction progress of nuclear island main system equipment of nuclear power plants has technical problems such as limited scope of application, incomplete evaluation, and low accuracy. Summary of the invention

[0004] The purpose of the present invention is to provide a method and system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, so as to alleviate the technical problems existing in the prior art that the evaluation is not comprehensive enough and the accuracy is low.

[0005] In a first aspect, an embodiment of the present invention provides a method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, the method comprising: determining a list of the main system equipment of the nuclear island to be constructed based on historical nuclear power project data; the historical nuclear power project data comprises equipment information of the completed main system of the nuclear island and corresponding equipment installation points; the list comprises: the total points of the installation of the main system equipment of various reactor types and the detailed points of each construction sub-item; wherein the main system equipment installation comprises a plurality of the above-mentioned construction sub-items; the point items contained in each of the above-mentioned construction sub-items correspond to the points to be released when the above-mentioned point items are completed;

[0006] Complete each of the above construction sub-items according to the installation steps of the above main system equipment, and release the points corresponding to the above completed point items in stages.

[0007] In some possible implementations, the main system equipment includes multiple subsystem equipment; the subsystem equipment includes: main loop equipment, reactor equipment and fuel processing system; each of the subsystem equipment includes multiple basic equipment, and each of the basic equipment includes at least one construction sub-item; each of the basic equipment corresponds to points in the quality plan; the points in the quality plan are used to evaluate the acceptance quality of the basic equipment.

[0008] In some possible implementations, the steps of completing each of the above construction sub-items according to the installation steps of the above main system equipment and releasing the points corresponding to the above completed point items in stages include:

[0009] Carry out the construction of each of the above construction sub-items according to the installation steps of each of the above basic equipment;

[0010] After each of the above installation steps is checked and confirmed, the points corresponding to the above point items are released.

[0011] In some possible implementations, the steps of completing each of the above construction sub-items according to the installation steps of the above main system equipment and releasing the points corresponding to the above completed point items in stages also include:

[0012] Carry out the construction of each of the above construction sub-items according to the installation steps of each of the above basic equipment;

[0013] After the above-mentioned basic equipment is completed, the current quality plan corresponding to the above-mentioned basic equipment will be closed, and some points of the above-mentioned quality plan will be released.

[0014] In some possible implementations, the steps of completing each of the above construction sub-items according to the installation steps of the above main system equipment and releasing the points corresponding to the above completed point items in stages also include:

[0015] Carry out the construction of each of the above construction sub-items according to the installation steps of each of the above basic equipment until the above basic equipment is completed;

[0016] After the completion of the above basic equipment, the remaining points will be released after it participates in the unit cold test and succeeds.

[0017] In some possible implementations, the above method further includes: formulating a unified equipment installation point rule for the same equipment in nuclear power plants of different reactor types.

[0018] In some possible implementations, the unified equipment installation point rules include: the point items included in the construction sub-items are the same, the points to be released when the point items are completed are the same, and the points corresponding to the quality plan of the basic equipment are the same.

[0019] In a second aspect, an embodiment of the present invention provides an evaluation system for the construction progress of the main system equipment of the nuclear island of a nuclear power plant, the system comprising: a main system equipment list determination module, which is used to determine the list of the main system equipment of the nuclear island to be constructed based on historical nuclear power project data; the above historical nuclear power project data includes the actual manpower input of the full cycle of the completed nuclear island main system equipment project; the above list includes: the total points of the installation of various reactor types of main system equipment, and the detailed points of each construction sub-item; wherein the main system equipment installation includes several of the above construction sub-items; the point items contained in each of the above construction sub-items correspond to the points to be released when the above point items are completed;

[0020] The point release module is used to complete each of the above construction sub-items according to the installation steps of the above main system equipment, and release the points corresponding to the completed point items in stages.

[0021] In a third aspect, an embodiment of the present invention provides an electronic device, comprising a memory and a processor, wherein the memory stores a computer program executable on the processor, and when the processor executes the computer program, the steps of any one of the methods described in the first aspect are implemented.

[0022] In a fourth aspect, an embodiment of the present invention provides a computer-readable storage medium, wherein the computer-readable storage medium stores machine-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions cause the processor to execute any method described in the first aspect above.

[0023] The present invention provides a method and system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant. The method comprises: firstly, based on historical nuclear power project data, determining a list of the main system equipment of the nuclear island to be constructed; the historical nuclear power project data comprises the equipment information of the completed main system of the nuclear island and the corresponding equipment installation points; the list comprises: the total points of the installation of the main system equipment of various reactor types, and the detailed points of each construction sub-item; the main system equipment installation comprises a number of construction sub-items; the point items contained in each construction sub-item correspond to the points to be released when the point items are completed; then, each construction sub-item is completed according to the installation steps of the main system equipment, and the points corresponding to the completed point items are released in stages. By means of this method, the technical problems of the limited application scope and low evaluation accuracy of the existing evaluation method for the construction progress of the main system equipment of the nuclear island of a nuclear power plant can be alleviated, and the technical effects of expanding the application scope and improving the evaluation accuracy can be achieved. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0025] Figure 1 A schematic flow chart of a method for evaluating the construction progress of main system equipment of a nuclear island of a nuclear power plant provided by an embodiment of the present invention;

[0026] Figure 2 A schematic flow chart of stage release points in a method for evaluating the construction progress of main system equipment of a nuclear island of a nuclear power plant provided by an embodiment of the present invention;

[0027] Figure 3 A schematic diagram of the structure of a system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant provided by an embodiment of the present invention;

[0028] Figure 4 A schematic diagram of the structure of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0029] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0030] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] It should be noted that similar reference numerals and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. Some embodiments of the present invention are described in detail below in conjunction with the drawings. The following embodiments and features in the embodiments can be combined with each other without conflict.

[0032] "Point" is a comprehensive indicator for progress evaluation in nuclear island installation. It essentially reflects the size of the workload. One point refers to the workload completed by one production staff member in one hour under standard working conditions, including the entire construction process, and has the characteristics of multiple technical information. Based on practical experience, the "point system" targets different engineering quantities of various types of equipment, and according to their characteristics or parameters, comprehensively considers construction technology, construction environment, use of tools and equipment, manpower consumption, construction organization and other aspects, and converts each physical quantity into a unified, full-process progress measurement indicator - "point" through certain evaluation and calculation rules. The progress of nuclear island installation is evaluated through "points".

[0033] The "point system" used in the Daya Bay Nuclear Power Station, which was introduced around 1990, was relatively reasonable at the time and could serve the nuclear island construction progress assessment and related engineering management work very well. However, with the continuous development of my country's nuclear power construction, more and more nuclear power reactor types are involved, including M310, VVER, EPR, Hualong One, AP and other reactor types, and the main system equipment is quite different. In addition, when the "point system" is used in the main system equipment of subsequent construction projects, due to limited historical data and low commonality between equipment, it is impossible to unify the calculation rules. The progress instructions of the previous project are often simply used, resulting in unreasonable phenomena in actual application.

[0034] That is to say, with the update and iteration of nuclear power reactor types; the continuous upgrading of nuclear safety requirements; the continuous emergence of new materials, new equipment, new technologies, and new processes; the continuous improvement of nuclear energy construction management level; the problem of regularization of huge differences in main system equipment of different reactor types, etc., the original engineering "point system" method of measuring the installation progress of the main system equipment of the nuclear island has the objective situation of being incomplete, inapplicable, and unreasonable, and the progress evaluation has become distorted and inaccurate. That is, the existing evaluation method of the construction progress of the main system equipment of the nuclear island of nuclear power plants has technical problems such as limited scope of application, incomplete evaluation, and low accuracy.

[0035] Based on this, an embodiment of the present invention proposes a method and system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, mainly elaborating on the improvement and innovation of the professional "point system" construction progress measurement method of the main system equipment of the nuclear island installation project of a nuclear power plant, so as to solve the defects and shortcomings of the original "point system" construction progress measurement method.

[0036] To facilitate understanding of this embodiment, firstly, a method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant disclosed in an embodiment of the present invention is described in detail. Figure 1 The flowchart of a method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant is shown. The method can be executed by an electronic device and mainly includes the following steps S110 to S120:

[0037] S110: Based on historical nuclear power project data, determine the list of main system equipment of the nuclear island to be constructed;

[0038] The historical nuclear power project data may be the actual manpower input in the entire cycle of the completed nuclear island main system equipment project of the nuclear power plant. In this embodiment, the historical nuclear power project data includes the equipment information of the completed nuclear island main system project and the corresponding equipment installation points.

[0039] The list includes: the total points for the installation of main system equipment of various reactor types and the detailed points for each construction sub-item; among them, the installation of main system equipment includes several construction sub-items; the point items contained in each construction sub-item correspond to the points to be released when the point items are completed.

[0040] S120: Complete each construction sub-item according to the installation steps of the main system equipment, and release the points corresponding to the completed point items in stages.

[0041] In one embodiment, the main system equipment includes multiple subsystem equipment; the subsystem equipment includes: main loop equipment, reactor equipment and fuel processing system; each subsystem equipment includes multiple basic equipment, and each basic equipment includes at least one construction sub-item; each basic equipment corresponds to the points of the quality plan; the points of the quality plan are used to evaluate the acceptance quality of the basic equipment.

[0042] In one embodiment, see Figure 2 As shown, S120 completes each construction sub-item according to the installation steps of the main system equipment, and releases the points corresponding to the completed point items in stages, including:

[0043] (S121) performing construction of each construction sub-item according to the installation steps of each basic equipment;

[0044] (S122) After each installation step is checked and confirmed, the points corresponding to the point entry are released.

[0045] In one embodiment, the step of completing each construction sub-item according to the installation steps of the main system equipment and releasing the points corresponding to the completed point items in stages also includes:

[0046] (S121) performing construction of each construction sub-item according to the installation steps of each basic equipment;

[0047] (S123) After the basic equipment is completed, the quality plan corresponding to the current basic equipment is closed, and the points of some quality plans are released.

[0048] Among them, the released points are generally 5% of the total quality plan points corresponding to the basic equipment.

[0049] In one embodiment, the step of completing each construction sub-item according to the installation steps of the main system equipment and releasing the points corresponding to the completed point items in stages also includes:

[0050] (S121) performing construction of each construction sub-item according to the installation steps of each basic equipment until the basic equipment is completed;

[0051] (S124) After the completed basic equipment participates in the unit cold test and succeeds, the remaining points are released.

[0052] In one embodiment, the method further includes: formulating a unified equipment installation point rule for the same equipment in nuclear power plants of different reactor types. The unified equipment installation point rule includes: the point items included in the construction sub-items are the same, the points to be released when the point items are completed are the same, and the points corresponding to the quality plan of the basic equipment are the same.

[0053] Taking the Hualong reactor type as an example, the original "point system" calculation rules include: Hualong One main system professional overall point calculation rules and Hualong One main system professional detailed point calculation rules. Specifically, the overall point distribution of Hualong One main system professional is shown in Table 1 below:

[0054] Table 1- Overall points distribution of Hualong One main system

[0055] Work Package Total points Total EM2.1 main circuit equipment 40626 42.99% EM2.2 Reactor Equipment 38625.5 40.87% EM2.3 Fuel Treatment System 15259.5 16.15% total 94511 100.00%

[0056] The above-mentioned overall point distribution rules have the following defects: (1) The total number of points is unreasonable. Since the total number of points of the main system accounts for a relatively low proportion in the nuclear island installation, in daily project management, people generally pay more attention to the image project of the main system construction, that is, the completion of milestone nodes, and do not pay much attention to the "points".

[0057] (2) In the past 10 years of nuclear power construction, the progress instructions for the main system profession simply followed the instructions for the previous project, and no new comprehensive assessment of the main system profession was conducted, resulting in a low total score. The main system equipment is essentially a mechanical profession, but there is a clear imbalance in the point value level with pipelines, electrical and other professions. This is not conducive to the assessment and evaluation of the overall progress of the project, nor is it conducive to the mobilization of manpower and the control of project costs.

[0058] Taking the Hualong One reactor type as an example, the original point number is subdivided into EM2.1 accounting for 43%, EM2.2 accounting for 40%, and EM2.3 accounting for 16%. Over the years, construction machinery has been continuously developed and innovated, and construction technology has been continuously optimized and improved, which has brought significant efficiency improvements to EM2.1 and EM2.2, and has no obvious impact on EM2.3. In recent years, the design of the internal components of the reactor and the top cover of the pressure vessel has been continuously optimized, and the division of labor between the equipment factory and the on-site construction has become more and more reasonable, which has a great impact on the work content of EM2.2 on site and reduces a lot of workload. Therefore, the division of the number of work packages within the main system is also unreasonable, and at the same time, each reactor type has similar unreasonable places.

[0059] The distribution rules of professional detailed points of the Hualong One main system are as follows:

[0060] The point progress of the main system, i.e. EM2 work package, is calculated, counted and reported according to the different installation work items (or stages) of each construction sub-item. When all the work contents of an installation work item are completed, the point progress of this installation work item can be calculated, counted and reported. The installation stages and corresponding point progress included in each construction sub-item of a unit have been determined and limited in the attached table.

[0061] The total number of quality plans in each EM2 subcontract is a provisional estimate, and the number of closure points for each quality plan is an average. During the actual construction process, adjustments will be made at any time based on the newly calculated total number of quality plans. The following table shows the detailed points of some major system disciplines.

[0062] Table 2- Detailed points of some major system majors

[0063]

[0064]

[0065] The above-mentioned main system professional detailed points rule has the following defects: (1) Since the original main system points are stipulated based on fixed equipment and fixed operations, with the change of reactor type and design improvement, the numerical distribution between items is unreasonable, such as the imbalance between "reactor pressure vessel introduction and installation 1165 points" and "pressure vessel shell insulation 1104 points". (2) The original main system points solidified the equipment that may have construction times and roots, resulting in the inability to report new construction points, such as the first, second, third, and fourth times of the internal components entering and leaving the reactor.

[0066] (3) The original main system's point-based work item division was too general and not detailed enough, resulting in a long construction period before points could be released. As a result, the construction team was working in a balanced manner, but the point release fluctuated violently, which was not conducive to the planning of the task volume and the evaluation of the completion status. For example, the construction of "pressure vessel shell insulation" in "pressure vessel insulation" lasted for 5 months, but there was only one work item that could release points.

[0067] (4) The equipment in work packages EM2.1 and EM2.2 participated in the system pressure test, and manpower was required to prepare technical materials, construction preparation, and on-site construction before, during, and after the test. However, the original main system points did not reflect this work, and there was a lack of progress and workload reflection.

[0068] In view of the defects of the original "point system" engineering progress measurement method for the main system of nuclear energy engineering, the original "point system" was improved by investigating and analyzing the actual situation of the main system equipment of each nuclear power reactor type. That is, the embodiment of the present application provides an evaluation method for the construction progress of the main system equipment of the nuclear island of the above-mentioned nuclear power plant. The main advantages of this method include: balanced and unified professions, balanced and unified reactor types, balanced and reasonable work packages, missing project supplementation, dynamic construction quantity reporting, etc. As a specific example, the improvements of a specific embodiment of the evaluation method for the construction progress of the main system of the nuclear island of a nuclear power plant provided in this embodiment include the following aspects:

[0069] 1. Basic work content of origin system improvement and innovation

[0070] 1) Summarize, analyze and evaluate the full-cycle human resources input of the main system, machinery, piping, electrical, and ventilation disciplines, determine new points for each discipline, and achieve balanced unification of each discipline.

[0071] 2) Analyze the weight, size, construction technology, structure and other characteristics of pressure vessels, steam generators, pressurizers and other equipment that exist in the main systems of each type of reactor, find out the common rules, formulate calculation rules, and achieve balance and unification of each type of reactor.

[0072] 3) Re-sort and refine the construction process steps for each equipment, add operation steps, i.e., point details, to achieve timely placement of "points" during equipment construction and reasonably present the progress of the nuclear island installation process.

[0073] 4) Determine unit values ​​for completely repetitive work without limiting the number of times to meet the needs of unconventional situations in nuclear island construction and adjustments to on-site construction content.

[0074] 5) Points will be awarded for participating in the pressure test and for the construction team's corresponding on-site work.

[0075] 6) Comprehensively evaluate each equipment construction operation item based on the current construction technology, tools, labor efficiency, etc., and re-divide the weight to achieve a balance between equipment and between operation steps.

[0076] 2. Mainstream Reactor Type Main System “Point System”

[0077] By summarizing and analyzing the actual manpower input throughout the entire cycle of the main systems, machinery, piping, electrical, ventilation and other professional aspects of completed nuclear power projects, the total number of installation points for the main system equipment of each reactor type is determined to ensure that they can be used in a homogeneous manner in the evaluation of the nuclear island installation progress.

[0078] Table 3 - Examples of several mainstream heap type points

[0079] Heap type Hualong One VVER AP Main system origin number 94511 327853 61541 Main system improved points 213353 336952 145026

[0080] 3. Main system similar to equipment "point system"

[0081] Unified rules are formulated for the same equipment in nuclear power plants with different reactor types. For example, in Hualong One, VVER, AP and other reactor types, there are pressure vessels, steam generators, pressurizers and other equipment. By analyzing the weight, size, construction technology, structure and other characteristics of the equipment, common rules are found, calculation rules are formulated, and unified rules are implemented to achieve balance and unification of various reactor types.

[0082] Table 4 - Hualong One Points Calculation Rules and Key Parameters

[0083]

[0084]

[0085]

[0086] 4. The main system is a complete "point system"

[0087] The construction process steps of each equipment were reorganized, the operation steps were refined, and the principle of unit measurement was added. The water pressure test step was added, and the proportion was determined based on the comprehensive evaluation of the current construction process, tools, labor efficiency, etc., and finally the improvement and optimization of the main system "point system" was completed. Taking Hualong One as an example, the point system formed is shown in the following table:

[0088] Table 5- Point system formed by taking Hualong One as an example

[0089]

[0090]

[0091]

[0092]

[0093]

[0094]

[0095]

[0096]

[0097]

[0098] 5. Key points of the measurement rules of the main system "point system"

[0099] 1) The equipment in the main system has few common points, and the construction technology and work content of each equipment vary greatly. Therefore, a detailed list should be listed in advance in the form of a checklist during the implementation of the project.

[0100] 2) For the main system equipment, only the surge pipe is subjected to a separate water pressure test during the installation process. Other equipment are tested together with the random group cold test after installation and are not tested separately.

[0101] 3) The total number of improved progress instructions is a pending value and will be adjusted according to the number of times the components in the pile enter and exit the pile and the number of drive mechanisms of the control unit.

[0102] VI. Reporting and statistics of the main system "point system"

[0103] 1) The point progress of the main system work package is calculated, counted and reported according to the different installation work items of each construction sub-item. When all the work contents of an installation work project are completed, the point progress of this installation work project can be calculated, counted and reported.

[0104] 2) The installation phases and corresponding point progress included in each construction sub-item of a unit have been determined in the list.

[0105] Taking the list of in-core components after the improvement of in-core component construction as an example, the work content included in the lower in-core component construction plan, the point items corresponding to the work content, and the relationship between the corresponding points to be released are shown in the following table:

[0106] Table 6 - Example of point release during the installation of internal components

[0107]

[0108]

[0109]

[0110] The embodiment of the present application provides an evaluation method for the construction progress of the main system equipment of the nuclear island of a nuclear power plant, which is used to measure the construction progress of the main system of the nuclear island installation project. Based on the original nuclear power plant nuclear island installation "point system" progress measurement method, the method improves and innovates the method of measuring the construction progress of the main system by investigating and analyzing the actual investment and consumption of the main system engineering of each nuclear power reactor type, and combining the actual problems of the original progress indicator system statistical method. Among them, the total number of points is raised to a reasonable state with reference to the common point efficiency of each profession; the proportion of each work package of the main system is optimized according to the changes in nuclear power construction over the years; the points of each operation item are re-evaluated and estimated according to the new construction process, investment and other conditions; the point list items are expanded and refined considering the construction period; the calculation method of the second and root is adjusted to complete the dynamic list; and the missing items of the water pressure test are supplemented. This method makes the new main system "point system" more comprehensive and fits the actual construction. The new "point system" is more accurately applied to daily progress management work, which is more conducive to the evaluation of the progress of the nuclear island installation project, and will have better effects on engineering management such as progress analysis, construction efficiency, manpower mobilization, and cost control.

[0111] In addition, the embodiment of the present invention also provides a system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, see Figure 3 The system comprises:

[0112] The list determination module 310 is used to determine the list of main system equipment of the nuclear island to be constructed based on historical nuclear power project data; the historical nuclear power project data includes the actual manpower input of the full cycle of the completed nuclear island main system equipment project; the list includes: the total points of the main system equipment installation of each reactor type, and the detailed points of each construction sub-item; wherein the main system equipment installation includes several construction sub-items; the point items contained in each construction sub-item correspond to the points to be released when the point items are completed;

[0113] The point release module 320 is used to complete each construction sub-item according to the installation steps of the main system equipment, and release the points corresponding to the completed point items in stages.

[0114] The evaluation system for the construction progress of the main system equipment of the nuclear island of a nuclear power plant provided in the embodiment of the present application can be specific hardware on the equipment or software or firmware installed on the equipment. The implementation principle and technical effect of the device provided in the embodiment of the present application are the same as those of the aforementioned method embodiment. For the sake of brief description, the parts not mentioned in the device embodiment can refer to the corresponding contents in the aforementioned method embodiment. Technical personnel in the relevant field can clearly understand that for the convenience and simplicity of description, the specific working processes of the systems, devices and units described above can all refer to the corresponding processes in the aforementioned method embodiment, and will not be repeated here. The evaluation system for the construction progress of the main system equipment of the nuclear island of a nuclear power plant provided in the embodiment of the present application has the same technical features as the evaluation method for the construction progress of the main system equipment of the nuclear island of a nuclear power plant provided in the above embodiment, so it can also solve the same technical problems and achieve the same technical effects.

[0115] An embodiment of the present application further provides an electronic device. Specifically, the electronic device includes a processor and a storage device. The storage device stores a computer program, and when the computer program is executed by the processor, it executes the method described in any one of the above-mentioned embodiments.

[0116] Figure 4 A structural schematic diagram of an electronic device provided in an embodiment of the present application, the electronic device 400 includes: a processor 40, a memory 41, a bus 42 and a communication interface 43, wherein the processor 40, the communication interface 43 and the memory 41 are connected via the bus 42; the processor 40 is used to execute an executable module stored in the memory 41, such as a computer program.

[0117] The memory 41 may include a high-speed random access memory (RAM), and may also include a non-volatile memory, such as at least one disk memory. The communication connection between the system network element and at least one other network element is realized through at least one communication interface 43 (which may be wired or wireless), and the Internet, wide area network, local area network, metropolitan area network, etc. may be used.

[0118] The bus 42 may be an ISA bus, a PCI bus, or an EISA bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, Figure 4 Only one bidirectional arrow is used in the diagram, but this does not mean that there is only one bus or only one type of bus.

[0119] Among them, the memory 41 is used to store programs, and the processor 40 executes the program after receiving the execution instruction. The method executed by the device for flow process definition disclosed in any embodiment of the above-mentioned embodiments of the present invention can be applied to the processor 40 or implemented by the processor 40.

[0120] The processor 40 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by the hardware integrated logic circuit or software instructions in the processor 40. The above processor 40 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA), or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present invention can be implemented or executed. The general-purpose processor can be a microprocessor or the processor can also be any conventional processor. The steps of the method disclosed in the embodiments of the present invention can be directly embodied as a hardware decoding processor to execute, or can be executed by a combination of hardware and software modules in the decoding processor. The software module can be located in a mature storage medium in the field such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory 41, and the processor 40 reads the information in the memory 41 and completes the steps of the above method in combination with its hardware.

[0121] Corresponding to the above method, an embodiment of the present application also provides a computer-readable storage medium, which stores machine-executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to execute the steps of the above method.

[0122] In the embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The device embodiments described above are merely schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some communication interfaces, and the indirect coupling or communication connection of the devices or units can be electrical, mechanical or other forms.

[0123] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0124] In addition, each functional unit in the embodiments provided in the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0125] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or the part of the technical solution, can be embodied in the form of a software product, which is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, electronic device, or network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: various media that can store program codes, such as a USB flash drive, a mobile hard disk, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk.

[0126] It should be noted that similar numbers and letters represent similar items in the accompanying drawings. Therefore, once an item is defined in one drawing, it does not need to be further defined and explained in subsequent drawings. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.

[0127] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, characterized in that: include: Based on historical nuclear power project data, determine the list of main system equipment of the nuclear island to be constructed; The historical nuclear power project data includes the equipment information of the completed nuclear island main system and the corresponding equipment installation points; the list includes: the total points of the main system equipment installation of various reactor types and the detailed points of each construction sub-item; wherein the main system equipment installation includes a number of the construction sub-items; the point items contained in each construction sub-item correspond to the points to be released when the point items are completed; the total points are adjusted based on the number of times the internal components enter and exit the pile and the number of drive mechanisms of the control unit; Complete each of the construction sub-items according to the installation steps of the main system equipment, and release the points corresponding to the completed point items in stages; The main system equipment includes a plurality of subsystem equipment; the subsystem equipment includes: main loop equipment, reactor equipment and fuel processing system; each of the subsystem equipment includes a plurality of basic equipment, and each of the basic equipment includes at least one construction sub-item; Each of the basic equipment corresponds to a point in the quality plan; the points in the quality plan are used to evaluate the acceptance quality of the basic equipment; The steps of completing each of the construction sub-items according to the installation steps of the main system equipment and releasing the points corresponding to the completed point items in stages include: Carry out the construction of each of the construction sub-items according to the installation steps of each of the basic equipment; After each of the installation steps is checked and confirmed, the points corresponding to the point entry are released; After the basic equipment is completed, the quality plan corresponding to the current basic equipment is closed, and some points of the quality plan are released; After the completion of the basic equipment, if it participates in the unit cold test and succeeds, the remaining points will be released.

2. The method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant according to claim 1, characterized in that: The method further comprises: formulating a unified equipment installation point number rule for the same equipment in nuclear power plants of different reactor types.

3. The method for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant according to claim 2, characterized in that: The unified equipment installation point rule includes: the point items included in the construction sub-items are the same, the points to be released when the point items are completed are the same, and the basic equipment has the same points corresponding to the quality plan.

4. A system for evaluating the construction progress of the main system equipment of the nuclear island of a nuclear power plant, characterized in that: The system comprises: The main system equipment list determination module is used to determine the main system equipment list of the nuclear island to be constructed based on historical nuclear power project data; the historical nuclear power project data includes the actual manpower input of the full cycle of the completed nuclear island main system equipment project; the list includes: the total points of the installation of various reactor types of main system equipment and the detailed points of each construction sub-item; wherein the main system equipment installation includes a number of the construction sub-items; the point items contained in each of the construction sub-items correspond to the points to be released when the point items are completed; the total points are adjusted based on the number of times the internal components enter and exit the pile and the number of drive mechanisms of the control unit; A point release module is used to complete each of the construction sub-items according to the installation steps of the main system equipment, and release the points corresponding to the completed point items in stages; the main system equipment includes a plurality of sub-system equipment; the sub-system equipment includes: main loop equipment, reactor equipment and fuel processing system; each of the sub-system equipment includes a plurality of basic equipment, and each of the basic equipment includes at least one construction sub-item; each of the basic equipment corresponds to the points of the quality plan; the points of the quality plan are used to evaluate the acceptance quality of the basic equipment; The point release module is also used to: carry out the construction of each construction sub-item according to the installation steps of each basic equipment; after each installation step is checked and confirmed, the points corresponding to the point item are released; after the basic equipment is completed, the quality plan corresponding to the current basic equipment is closed, and the points of part of the quality plan are released; after the completed basic equipment participates in the unit cold test and succeeds, the remaining points are released.

5. An electronic device comprising a memory and a processor, wherein the memory stores a computer program that can be run on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 3 are implemented.

6. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores machine executable instructions. When the computer-executable instructions are called and executed by a processor, the computer-executable instructions prompt the processor to execute the method according to any one of claims 1 to 3.