A scene-adaptive switch control method for detonator
Through environmental monitoring and matrix analysis of the detonator, the influence vector and triggering moment are determined, and the switching mode is adjusted, which solves the problem of reduced sensitivity of the touch screen in harsh environments and improves the control reliability and work efficiency of the detonator.
Patent Information
- Application Number
- CN202410179088.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-18
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-02-18
AI Technical Summary
When there is rain in the mine or in the open air, the sensitivity of the touch screen is reduced, resulting in misoperation or inability to operate. When construction workers wear thick gloves in cold environments, the touch screen operation is inaccurate, seriously reducing work efficiency.
By monitoring the environment of the detonator's application space, constructing an environment matrix, analyzing the influence vector, matching the scene and determining the triggering moment, and adjusting the switching mode to achieve adaptive control, ensuring the reliability and efficiency of the detonator.
The control reliability and operating efficiency of the detonator are improved, and misoperation and efficiency reduction caused by environmental factors are avoided.
Smart Images

Figure CN118011822B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of adaptive control technology, and in particular to a scene adaptive switch control method for an initiator. Background Art
[0002] With the mandatory implementation of industrial electronic detonators in my country, the formulation of universal detonator standards has greatly improved the standardization of the civil explosives industry. According to the standards of universal detonators, many manufacturers in my country have joined the design and production of this standard equipment. Universal detonators support touch screens by default, which is convenient for users to operate. Touch screen operation is convenient and well known on consumer products. However, in special scenarios where detonators are used, for example, when it rains in mines or in the open air, water will drip onto the touch screen, which will reduce the sensitivity of the touch screen. At the same time, water dripping down is prone to misoperation or the touch screen cannot be operated. Or when it is cold and construction workers wear thick gloves, the sensitivity of the touch screen is not accurate, and even the touch screen cannot be operated, which greatly reduces work efficiency.
[0003] Therefore, the present invention proposes a scene-adaptive switch control method for an initiator. Summary of the invention
[0004] The present invention provides a scene-adaptive switch control method for a detonator, which is used to construct an environmental matrix by performing environmental monitoring on the current application space of the detonator, so as to obtain basic parameters for analyzing the scene and improve the reliability of the control of the detonator. Moreover, by analyzing the matrix, matching and analyzing the vectors and determining the triggering moment, it is convenient to effectively ensure that the detonator is switched to the corresponding mode in advance, thereby facilitating the detonator to effectively capture the execution of the operator and improve work efficiency.
[0005] The present invention provides a scene-adaptive switch control method for an initiator, comprising:
[0006] Step 1: determine the usage of the detonator, and perform scenario analysis on the usage to obtain a scenario control set;
[0007] Step 2: Perform environmental monitoring on the current application space of the detonator, construct an environmental matrix, and analyze the environmental matrix to determine the impact vector on the detonator at different prediction times;
[0008] Step 3: Perform matching analysis on the influence vector and the scene control set, and determine the best matching scene and the second matching scene according to the matching analysis result;
[0009] Step 4: respectively determining the first effective time of the most matching scene and the second effective time of the second matching scene to obtain the triggering time for the detonator;
[0010] Step 5: When the triggering moment is reached, the detonator is controlled to adjust the switch mode according to the final control output under the best matching scenario and the second matching scenario, and then the capture device corresponding to the adjusted switch mode is controlled to capture the input instruction of the operator, so as to realize adaptive control of the detonator.
[0011] Preferably, performing scene analysis on the usage to obtain a scene control set includes:
[0012] Obtaining an initial scene queue associated with each usage purpose according to the usage-scene mapping table;
[0013] Assigning the control parameters of the predefined environmental scene to the initial scene queue;
[0014] Combine all the queues assigned to the scene to get the scene control set.
[0015] Preferably, the current application space of the detonator is subjected to environmental monitoring to construct an environmental matrix, including:
[0016] Acquire several types of monitoring sensors for performing environmental monitoring on the current application space;
[0017] The error range of each type of monitoring sensor is obtained from the sensor experiment database, and a matching variable array is constructed according to the error range and the monitoring attribute of each type of monitoring sensor based on the current application space of the corresponding detonator;
[0018] Inputting the matching variable array into the primary and secondary analysis model to generate the primary monitoring class and the secondary monitoring class of the current application space;
[0019] respectively obtaining the probe geometry of the monitoring probe of each type of monitoring sensor;
[0020] Dividing the probe geometry into units according to the predefined monitoring accuracy of the corresponding monitoring sensor and in combination with the generated primary and secondary results of the monitoring class;
[0021]
[0022] Where H1 is the final number of divisions of the probe geometry; N(J) is the standard number of divisions determined according to the predefined monitoring accuracy; wc max is the maximum value in the error range corresponding to the corresponding monitoring sensor; wc minis the minimum value in the error range corresponding to the corresponding monitoring sensor; D0 is whether the corresponding monitoring sensor has split value, if yes, the value is 1, if not, the value is 0; [] is the integer symbol; a1 is when the corresponding monitoring sensor is the main monitoring type, for N(J)×(1+wc max ) adjustment variables;
[0023] Determine the acquisition frequency of each division unit and construct a frequency array;
[0024] According to the probe length and probe material properties of the corresponding monitoring probe, the monitoring attenuation coefficient of each divided unit is obtained by matching from the length-property-attenuation data table;
[0025] According to the actual collected value and frequency array of each monitoring sensor and combined with the monitoring attenuation coefficient, the effective collected value of the corresponding monitoring sensor is determined;
[0026]
[0027] Wherein, Yx represents the effective collected value of the corresponding monitoring sensor; rand(1, *) represents a random function that randomly selects a calculation result from *; Sc represents the corresponding actual collected value; represents the variance of the standard acquisition combination C(p) corresponding to the frequency combination p; represents the coefficient variance of all monitoring attenuation coefficients involved in the corresponding monitoring sensor; Δwc represents the unit error of the corresponding type of monitoring sensor; b1 represents the variance constant;
[0028] According to all valid acquisition values of each monitoring sensor, an acquisition vector is constructed;
[0029] Arrange the acquisition vectors of all monitoring sensors in rows to obtain the environment matrix.
[0030] Preferably, analyzing the environment matrix to determine the impact vector on the detonator at different prediction times includes:
[0031] Respectively determining the monitoring sensitivity values of adjacent column vectors in the environment matrix, and drawing a monitoring curve;
[0032] Taking the monitoring sensitivity value of each convex point in the monitoring curve as the first deletion point, obtaining a first fitting value corresponding to the first deletion curve;
[0033] Taking the monitoring sensitivity value of each concave point in the monitoring curve as the second deletion point, obtaining a second fitting value corresponding to the second deletion curve;
[0034] Based on all the first fitting values and the second fitting values, the corresponding initiator double influence coefficient is obtained;
[0035] According to the dual influence coefficients, each row vector in the environment matrix is subjected to influence analysis, and a final influence factor of the corresponding row vector is determined in combination with the monitoring purpose of the monitoring sensor of the corresponding row vector;
[0036] Based on all the final influencing factors and combined with the monitoring column vector of the previous time before the prediction time, the influence vector at the corresponding prediction time is obtained.
[0037] Preferably, matching analysis is performed on the influence vector and the scene control set, and the best matching scene and the second matching scene are determined according to the matching analysis result, including:
[0038] Inputting the influence vector into a vector analysis model to obtain a scene to be determined;
[0039] The to-be-determined scene is matched with the scene control set, and a best matching scene and a second matching scene are obtained according to a similarity calculation function.
[0040] Preferably, obtaining the triggering moment for the detonator includes:
[0041] Obtain the differences between multiple sets of set execution times and actual execution times determined in the historical process for the best matching scenario and the second matching scenario, and construct a first difference array corresponding to the matching scenario; at the same time, capture multiple sets of first control times and first success times of the operator based on the corresponding matching scenarios, and construct a second difference array corresponding to the matching scenario;
[0042] Determine the execution uncertainty of the corresponding matching scenario according to the first difference array, and at the same time, determine the trigger sensitivity of the corresponding matching scenario according to the second difference array;
[0043] Obtaining a first frequency curve of the detonator based on random T1 historical cycles and a second frequency curve of T2 historical cycles during the actual historical continuous execution process based on the corresponding matching scenario;
[0044] Obtain a frequency deviation array according to the first frequency curve and the second frequency curve, and determine a first time compensation coefficient for the most matching scene and a second time compensation coefficient for the second matching scene;
[0045] Respectively obtaining a first probability difference value and a second probability difference value of the first difference value array and the second difference value array under corresponding set centralized distribution;
[0046] According to the execution uncertainty, the time compensation coefficient, the probability difference and the trigger sensitivity, a control stability coefficient corresponding to the matching scenario is obtained;
[0047] At the same time, according to the setting working time St of the detonator by the operator and the current time Dt, a first time difference ΔT1 is determined;
[0048] If the first time difference ΔT1 is greater than the preset difference Yt, As the first effective moment St1 and As the second effective time St2, where kw1 is the control stability coefficient corresponding to the best matching scene, and kw2 is the control stability coefficient corresponding to the second matching scene;
[0049] If the first time difference ΔT1 is less than the preset difference Yt, As the first effective moment St1 and As the second effective time St2,
[0050] The smaller time between the first effective time and the second effective time finally obtained is selected as the triggering time for the detonator.
[0051] Preferably, controlling the detonator to adjust the switch mode according to the final control output in the best matching scenario and the second matching scenario includes:
[0052] Acquire first matching information between the influence vector and the most matching scene, and at the same time, acquire second matching information between the influence vector and the second matching scene;
[0053] Searching for a matching result consistent with the parameter information description of the non-matching information in the best matching scene from the second matching information and replacing the result to obtain a new matching scene;
[0054] The final control output is obtained according to the set control parameters in the new matching scene, and then the detonator is controlled to be adjusted to a switching mode consistent with the final control output.
[0055] Preferably, the capture device is communicatively connected to the detonator.
[0056] Compared with the prior art, the present invention has the following beneficial effects:
[0057] By conducting environmental monitoring on the current application space of the detonator and constructing an environmental matrix, it is convenient to obtain the basic parameters for analyzing the scene and improve the reliability of the detonator control. By analyzing the matrix, matching the vectors and determining the triggering moment, it is convenient to effectively ensure that the detonator is switched to the corresponding mode in advance, thereby facilitating the detonator to effectively capture the operator's execution and improve work efficiency.
[0058] Other features and advantages of the present invention will be described in the following description, and partly become apparent from the description, or understood by practicing the present invention. The purpose and other advantages of the present invention can be realized and obtained by the structures particularly pointed out in the written description and the accompanying drawings.
[0059] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0060] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0061] Figure 1 The present invention is a flowchart of a scene-adaptive switch control method for an initiator according to an embodiment of the present invention. DETAILED DESCRIPTION
[0062] The preferred embodiments of the present invention are described below in conjunction with the accompanying drawings. It should be understood that the preferred embodiments described herein are only used to illustrate and explain the present invention, and are not used to limit the present invention.
[0063] The present invention provides a scene-adaptive switch control method for an initiator, such as Figure 1 As shown, including:
[0064] Step 1: determine the usage of the detonator, and perform scenario analysis on the usage to obtain a scenario control set;
[0065] Step 2: Perform environmental monitoring on the current application space of the detonator, construct an environmental matrix, and analyze the environmental matrix to determine the impact vector on the detonator at different prediction times;
[0066] Step 3: Perform matching analysis on the influence vector and the scene control set, and determine the best matching scene and the second matching scene according to the matching analysis result;
[0067] Step 4: respectively determining the first effective time of the most matching scene and the second effective time of the second matching scene to obtain the triggering time for the detonator;
[0068] Step 5: When the triggering moment is reached, the detonator is controlled to adjust the switch mode according to the final control output under the best matching scenario and the second matching scenario, and then the capture device corresponding to the adjusted switch mode is controlled to capture the input instruction of the operator, so as to realize adaptive control of the detonator.
[0069] Preferably, the capture device is communicatively connected to the detonator.
[0070] In this embodiment, the uses include: detonation for demolishing buildings, detonation for demolishing bridges, detonation for mining ore, detonation for digging tunnels, etc.
[0071] In this embodiment, the scene analysis is to determine the historical detonation environment corresponding to different detonation purposes and the control parameters used for the detonator under the corresponding historical detonation environment (mainly to determine the control mode), so as to facilitate the construction of a scene control set, that is, each use purpose under the scene control set contains scene parameters of several historical detonation scenes and control parameters under the corresponding scenes, and the control parameters are set by experts according to the corresponding scenes, mainly to facilitate the control of the detonator.
[0072] In this embodiment, when the detonator is in different required control modes, the corresponding capture devices may be different. For example, the capture device 1 (touch screen mode) corresponding to the switch mode 1 is turned on, the capture device 2 (keyboard mode) corresponding to the switch mode 2 is turned on, and the shooting device 3 (camera) corresponding to the switch mode 3 is turned on. The main purpose is to adapt to local conditions and achieve the most reasonable control of the detonator, that is, to ensure that the detonator works in a timely manner.
[0073] In this embodiment, the purpose of environmental monitoring is to determine the environmental conditions of the current application space to facilitate subsequent determination of which switching mode is more appropriate.
[0074] In this embodiment, each row in the environment matrix is obtained after the corresponding monitoring sensor performs environmental monitoring on the current application space. For example, the sensor is a dust sensor, an ultrasonic sensor, a photosensitive sensor, a rainfall monitoring sensor, etc. It should be noted that the detonator may be in the same position as the operator, or may not be in the same position as the operator. For example, when the dust concentration is too high or the space for the detonator to detonate is too narrow, the detonator may be in a different position from the operator, mainly to protect the safety of the operator. At this time, the shooting device 3 can be used to capture the input, and then analyze the input command to achieve detonation control.
[0075] In this embodiment, the predicted time refers to the next time based on the actual acquisition time, which can be a moment. The purpose of the influence vector is to match the scene control set and obtain the best matching scene and the second matching scene according to the similarity calculation method.
[0076] In this embodiment, the first effective time and the second effective time are used to determine the triggering time of the corresponding detonator, and the effective time is determined so that the detonator has switched to the corresponding switch mode before the actual execution time, that is, enters the corresponding switch mode in advance to avoid the failure of the early control of the detonator due to the switching time being too late.
[0077] In this embodiment, the switch mode is adjusted. For example, the most matching scenario is the switch mode 3, and the second matching scenario is the switch mode 2. After the switch mode is adjusted, it is a combination of mode 2 and mode 3. At this time, only when the input instructions captured in the two modes are consistent, will the detonation be successful.
[0078] In this embodiment, the switch mode of the detonator can also be manually selected by the operator. Generally, the switch mode is automatically selected according to the environment. In the manual selection process, the mode switching can be achieved by pressing the physical switch key designed on the detonator back and forth. For example, pressing button 1 switches to switch mode 1, pressing button 2 switches to switch mode 2, and pressing button 3 switches to switch mode 3.
[0079] The beneficial effects of the above technical solution are: by constructing an environmental matrix through environmental monitoring of the current application space of the detonator, it is convenient to obtain the basic parameters for analyzing the scene, improve the reliability of the control of the detonator, and through matrix analysis, vector matching analysis and determination of the triggering moment, it is convenient to effectively ensure that the detonator is switched to the corresponding mode in advance, thereby facilitating the detonator to effectively capture the execution of the operator and improve work efficiency.
[0080] The present invention provides a scene-adaptive switch control method for an initiator, which performs scene analysis on the usage purpose to obtain a scene control set, including:
[0081] Obtaining an initial scene queue associated with each usage purpose according to the usage-scene mapping table;
[0082] Assigning the control parameters of the predefined environmental scene to the initial scene queue;
[0083] Combine all the queues assigned to the scene to get the scene control set.
[0084] In this embodiment, the purpose-scene mapping table is based on different uses and the scenes that may be involved in the corresponding uses, and then all the scenes under the required purposes are extracted, and the scenes (dust concentration, rainfall, spatial narrowness, etc. may vary) are arranged in sequence to obtain the initial scene queue.
[0085] In this embodiment, the control parameters are pre-set by an expert, mainly to determine the subsequent switching mode, and all the assigned scene queues are scene control sets.
[0086] The beneficial effect of the above technical solution is: by obtaining the initial scene queue from the mapping table and assigning parameters to each queue, it is convenient to obtain the control set, which facilitates the subsequent matching analysis.
[0087] The present invention provides a scene-adaptive switch control method for an initiator, which performs environmental monitoring on a current application space of the initiator to construct an environmental matrix, including:
[0088] Acquire several types of monitoring sensors for performing environmental monitoring on the current application space;
[0089] Obtain the error range of each type of monitoring sensor from the sensor experiment database, and construct a matching variable array of each type according to the error range and the monitoring attribute of each monitoring sensor based on the current application space of the corresponding detonator;
[0090] Input all matching variable arrays into the primary and secondary analysis models in sequence to generate the primary monitoring class and the secondary monitoring class of the current application space;
[0091] respectively obtaining the probe geometry of the monitoring probe of each type of monitoring sensor;
[0092] Dividing the probe geometry into units according to the predefined monitoring accuracy of the corresponding monitoring sensor and in combination with the generated primary and secondary results of the monitoring class;
[0093]
[0094] Where H1 is the final number of divisions of the probe geometry; N(J) is the standard number of divisions determined according to the predefined monitoring accuracy; Wc max is the maximum value in the error range corresponding to the corresponding monitoring sensor; wc min is the minimum value in the error range corresponding to the corresponding monitoring sensor; D0 is whether the corresponding monitoring sensor has split value, if yes, the value is 1, if not, the value is 0; [] is the integer symbol; a1 is when the corresponding monitoring sensor is the main monitoring type, for N(J)×(1+wc max ) adjustment variables;
[0095] Determine the acquisition frequency of each division unit and construct a frequency array;
[0096] According to the probe length and probe material properties of the corresponding monitoring probe, the monitoring attenuation coefficient of each divided unit is obtained by matching from the length-property-attenuation data table;
[0097] According to the actual collected value and frequency array of each monitoring sensor and combined with the monitoring attenuation coefficient, the effective collected value of the corresponding monitoring sensor is determined;
[0098]
[0099] Wherein, Yx represents the effective collected value of the corresponding monitoring sensor; rand(1, *) represents a random function that randomly selects a calculation result from *; Sc represents the corresponding actual collected value; represents the variance of the standard acquisition combination C(p) corresponding to the frequency combination p; represents the coefficient variance of all monitoring attenuation coefficients involved in the corresponding monitoring sensor; Δwc represents the unit error of the corresponding type of monitoring sensor; b1 represents the variance constant;
[0100] According to all valid acquisition values of each monitoring sensor, an acquisition vector is constructed;
[0101] Arrange the acquisition vectors of all monitoring sensors in rows to obtain the environment matrix.
[0102] In this embodiment, the monitoring sensors are classified according to their working principles, and the subsequent analysis methods used for sensors classified according to similar working principles are consistent.
[0103] In this embodiment, the sensor experiment database includes experimental data obtained by experimentally testing several sensors after they are built to determine the measurement accuracy of the sensor, thereby obtaining the error range of the corresponding type of sensor.
[0104] In this embodiment, the monitoring attribute refers to the monitoring type of the corresponding sensor, such as temperature, humidity, light sensitivity, etc.
[0105] In this example, the matching variable array is:
[0106] in,
[0107] The margin of error is the same for each category.
[0108] In this embodiment, the primary and secondary analysis models are pre-trained and are obtained by training the neural network model based on different matching variable arrays and the main and secondary situations of the arrays after experts analyze the data in the relevant arrays as samples. Therefore, it can be obtained whether the corresponding class is the main monitoring class or the secondary monitoring class, that is, whether the corresponding working principle is critical or non-critical for environmental parameter collection, because the corresponding class sensor needs to be subjected to probe analysis later.
[0109] In this embodiment, the probe geometry refers to the geometric shape of the probe.
[0110] In this embodiment, the monitoring accuracy is pre-set, and the accuracy requirements of different types of monitoring sensors are different.
[0111] In this embodiment, the value of H1 is an integer, that is, when it is a secondary monitoring class, the corresponding probe geometry is not divided, and the consistent setting of the above-mentioned standard division times is to facilitate the consistency of the number in the subsequent frequency array and to facilitate the comparison of numerical calculations.
[0112] In this embodiment, the frequency array = {the acquisition frequency of the division unit 1, the acquisition frequency of the division unit 2, ...}, and the acquisition frequency is obtained based on the standard test of the corresponding sensor. When no division is performed, the variance of the corresponding frequency combination is 0.
[0113] In this embodiment, the length-property-attenuation data table includes different probe lengths, probe material properties and matched attenuation coefficients, thereby facilitating the monitoring attenuation coefficient, mainly to determine the attenuation of the information collected by the probe, and to facilitate the subsequent calculation of the effective collection value.
[0114] In this embodiment, the number of valid collected values under each monitoring sensor is consistent.
[0115] In this embodiment,
[0116] The beneficial effects of the above technical solution are: by obtaining the error range and monitoring attributes of the sensor to obtain an array, and then based on the model analysis of the corresponding class of primary and secondary to facilitate the subsequent division of the probe, that is, to further ensure the accurate measurement value obtained by the probe after measuring the environment, and by calculating the number of divisions to achieve accurate calculation of the measurement results, by determining the attenuation coefficient, etc. to calculate the effective acquisition value to effectively ensure the accuracy of the acquisition results, all acquisition vectors are arranged in rows to construct a matrix, effectively ensuring the reliability of environmental information monitoring, providing an accurate basis for the subsequent determination of the switching mode, and indirectly improving work efficiency.
[0117] The present invention provides a scene-adaptive switch control method for an initiator, which analyzes the environment matrix to determine the influence vector on the initiator at different prediction times, including:
[0118] Respectively determining the monitoring sensitivity values of adjacent column vectors in the environment matrix, and drawing a monitoring curve;
[0119] Taking the monitoring sensitivity value of each convex point in the monitoring curve as the first deletion point, obtaining a first fitting value corresponding to the first deletion curve;
[0120] Taking the monitoring sensitivity value of each concave point in the monitoring curve as the second deletion point, obtaining a second fitting value corresponding to the second deletion curve;
[0121] Based on all the first fitting values and the second fitting values, the corresponding initiator double influence coefficient is obtained;
[0122] According to the dual influence coefficients, each row vector in the environment matrix is subjected to influence analysis, and a final influence factor of the corresponding row vector is determined in combination with the monitoring purpose of the monitoring sensor of the corresponding row vector;
[0123] Based on all the final influencing factors and combined with the monitoring column vector of the previous time before the prediction time, the influence vector at the corresponding prediction time is obtained.
[0124] In this embodiment, the environment type measured in each column vector is the same, and the monitoring sensitivity is determined based on whether the two element values under the same environment type change too much. The larger the change, the more unreasonable the corresponding sensitivity value, and the smaller the change, the more reasonable the corresponding sensitivity value, that is:
[0125] Monitoring sensitivity = 1-the average value of the cumulative sum of the coefficient converted from the element difference standard under the same environment type and the corresponding weight multiplied by the corresponding weight, and the corresponding weight is pre-set, and the sum of the weights under all environment types is 1.
[0126] In this embodiment, the monitoring curve is obtained by plotting a curve based on all acquired monitoring sensitivity values.
[0127] In this embodiment, the convex point refers to the peak point in the curve, and the concave point refers to the valley point in the curve.
[0128] In this embodiment, the monitoring curve is redrawn after deletion to obtain the fitting value of the curve.
[0129] In this embodiment, the dual influence coefficient refers to the first variance of all first fitting values and the second variance of all second fitting values.
[0130] In this embodiment, the impact analysis is to input the dual impact coefficients, monitoring purposes and corresponding row vector combinations into the analysis model to obtain the final impact factor. The analysis model is based on different impact coefficients, monitoring purposes and vectors, and then combined with the expert's evaluation results of the above combinations as samples to train the neural network model, so as to directly obtain the impact factor, that is, the impact factor will adjust the results in the row vector to a certain extent, further ensuring the accuracy of each value in the vector.
[0131] In this embodiment, for example, the prediction time is t1, and the time before the prediction time is t2, that is, the column vector at time t2 is obtained to obtain the influence vector at t1, that is, the column vector at t2 will adjust the originally obtained influence factor again to obtain the influence vector = {influence factor 1 influence factor 2....}, for example, the original influence factor of row vector 1 is d1, and after adjusting according to the corresponding column vector, the influence factor d2 is obtained.
[0132] In this embodiment, the column vector is the vector matching t2 in the corresponding environment matrix.
[0133] The beneficial effect of the above technical solution is: by calculating the monitoring sensitivity value to draw a curve and then deleting the convex points and concave points to obtain the fitting value, the double influence coefficient is calculated, and the influence vector is obtained by combining the monitoring purpose and the column vector of the signing time, which provides a basis for subsequent matching analysis and ensures the reliability of the matching results.
[0134] The present invention provides a scene adaptive switch control method for an initiator, which performs matching analysis on the influence vector and the scene control set, and determines the best matching scene and the second matching scene according to the matching analysis result, including:
[0135] Inputting the influence vector into a vector analysis model to obtain a scene to be determined;
[0136] The scene to be determined is matched with the scene control set, and a best matching scene and a second matching scene are obtained according to a similarity calculation function.
[0137] In this embodiment, the vector analysis model is obtained by training the neural network model based on samples of different influence vectors, environmental matrices and expert analysis results of the influence vectors and environmental matrices, thereby facilitating direct acquisition of the scene to be determined.
[0138] In this embodiment, the matching process is based on matching the scene parameters involved in the to-be-determined scene with the scene parameters in the scene control set, thereby acquiring the corresponding control parameters.
[0139] The beneficial effect of the above technical solution is: determining the scene to be determined through vector analysis, and further obtaining the matching scene through scene matching, providing a basis for determining the triggering moment.
[0140] The present invention provides a scene-adaptive switch control method for an initiator, which obtains a triggering moment for the initiator, comprising:
[0141] Obtain the differences between multiple sets of set execution times and actual execution times determined in the historical process for the best matching scenario and the second matching scenario, and construct a first difference array corresponding to the matching scenario; at the same time, capture multiple sets of first control times and first success times of the operator based on the corresponding matching scenarios, and construct a second difference array corresponding to the matching scenario;
[0142] Determine the execution uncertainty of the corresponding matching scenario according to the first difference array, and at the same time, determine the trigger sensitivity of the corresponding matching scenario according to the second difference array;
[0143] Obtaining a first frequency curve of the detonator based on random T1 historical cycles and a second frequency curve of T2 historical cycles during the actual historical continuous execution process based on the corresponding matching scenario;
[0144] Obtain a frequency deviation array according to the first frequency curve and the second frequency curve, and determine a first time compensation coefficient for the most matching scene and a second time compensation coefficient for the second matching scene;
[0145] Respectively obtaining a first probability difference value and a second probability difference value of the first difference value array and the second difference value array under corresponding set centralized distribution;
[0146] According to the execution uncertainty, the time compensation coefficient, the probability difference and the trigger sensitivity, a control stability coefficient corresponding to the matching scenario is obtained;
[0147] At the same time, according to the setting working time St of the detonator by the operator and the current time Dt, a first time difference ΔT1 is determined;
[0148] If the first time difference ΔT1 is greater than the preset difference Yt, As the first effective moment St1 and As the second effective time St2, where kw1 is the control stability coefficient corresponding to the best matching scene, and kw2 is the control stability coefficient corresponding to the second matching scene;
[0149] If the first time difference ΔT1 is less than the preset difference Yt, As the first effective moment St1 and As the second effective time St2,
[0150] The smaller time between the first effective time and the second effective time finally obtained is selected as the triggering time for the detonator.
[0151] In this embodiment, the execution time is set in advance. For example, the execution time is set to t01, but it is actually executed at t02. At this time, the difference under this group is t01-t02, and the first difference array and the second difference array are constructed by many corresponding first differences and second differences respectively.
[0152] In this embodiment, the uncertainty is performed by determining the number of difference values in the first difference value array that are less than 0 / the number of all difference values in the first difference value array.
[0153] The trigger sensitivity is determined by the absolute value of the second difference in the second difference array being greater than the number of preset difference values / the number of all difference values in the second difference array.
[0154] In this embodiment, the first frequency curve and the second frequency curve are obtained to determine the working conditions of the corresponding detonators, and the period lengths of the historical periods are equal.
[0155] In this embodiment, the probability difference refers to the average value of all differences that satisfy the normal distribution, such as the 80% home distribution.
[0156] In this embodiment, the time compensation coefficient is based on the variance of the corresponding deviation array and is obtained by matching according to a variance-compensation mapping table, which includes several variances and compensation coefficients under different variances.
[0157] In this embodiment, the control stability coefficient=trigger sensitivity×(uncertainty conversion standard×(1-execution uncertainty)+compensation conversion standard time×compensation coefficient+difference conversion standard×probability difference).
[0158] In this embodiment, ΔT1=St-Dt.
[0159] In this embodiment, the smaller time refers to the effective time that is far away from the set working time.
[0160] The beneficial effect of the above technical solution is: by determining multiple arrays to comprehensively determine the control stability coefficient, and combining the comparison result of the first time difference with the preset difference, respectively adjust Dt in different situations to select a smaller moment as the trigger moment, to ensure that the detonator reaches the relevant mode in advance to the greatest extent, to avoid the situation where the control is invalid due to the trigger moment being too late, and thus improve work efficiency.
[0161] The present invention provides a scene-adaptive switch control method for an initiator, which controls the initiator to adjust the switch mode according to the final control output under the best matching scene and the second matching scene, comprising:
[0162] Acquire first matching information between the influence vector and the most matching scene, and at the same time, acquire second matching information between the influence vector and the second matching scene;
[0163] Searching for a matching result consistent with the parameter information description of the non-matching information in the best matching scene from the second matching information and replacing the result to obtain a new matching scene;
[0164] The final control output is obtained according to the set control parameters in the new matching scene, and then the detonator is controlled to be adjusted to a switching mode consistent with the final control output.
[0165] In this embodiment, the matching information refers to the scene parameters matched with the corresponding scene.
[0166] For example, the first matching information is: parameter 01, parameter 02, parameter 03, parameter 94 and parameter 05, and the unmatched information is parameter 12 (value is a01), the second matching information is: parameter 11, parameter 12 (value is a02), and then the parameter 12 in the second matching information replaces the unmatched information parameter 12 in the first matching information, and a new scenario is obtained: parameter 01, parameter 02, parameter 03, parameter 94 and parameter 05, parameter 12 (value is a02).
[0167] In this embodiment, relevant control parameters can be directly obtained in the new scene to control the output, that is, to determine which mode the final mode is, which can be a single mode or a combination of modes, thereby achieving effective control.
[0168] The beneficial effect of the above technical solution is: by performing information matching and result replacement, a new matching scene is obtained, and then relevant control parameters are obtained, so as to achieve effective control triggering of the detonator.
[0169] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.
Claims
1. A scene-adaptive switch control method for an initiator, characterized in that: include: Step 1: determine the usage of the detonator, and perform scenario analysis on the usage to obtain a scenario control set; Step 2: Perform environmental monitoring on the current application space of the detonator, construct an environmental matrix, and analyze the environmental matrix to determine the impact vector on the detonator at different prediction times; Step 3: Perform matching analysis on the influence vector and the scene control set, and determine the best matching scene and the second matching scene according to the matching analysis result; Step 4: respectively determining the first effective time of the most matching scene and the second effective time of the second matching scene to obtain the triggering time for the detonator; Step 5: When the triggering moment is reached, the detonator is controlled to adjust the switch mode according to the final control output under the best matching scenario and the second matching scenario, and then the capture device corresponding to the adjusted switch mode is controlled to capture the input instruction of the operator to realize adaptive control of the detonator; wherein, obtaining the triggering moment for the detonator includes: Obtain the differences between multiple sets of set execution times and actual execution times determined in the historical process for the best matching scenario and the second matching scenario, and construct a first difference array corresponding to the matching scenario; at the same time, capture multiple sets of first control times and first success times of the operator based on the corresponding matching scenarios, and construct a second difference array corresponding to the matching scenario; Determine the execution uncertainty of the corresponding matching scenario according to the first difference array, and at the same time, determine the trigger sensitivity of the corresponding matching scenario according to the second difference array; Obtaining a first frequency curve of the detonator based on random T1 historical cycles and a second frequency curve of T2 historical cycles during the actual historical continuous execution process based on the corresponding matching scenario; Obtain a frequency deviation array according to the first frequency curve and the second frequency curve, and determine a first time compensation coefficient for the most matching scene and a second time compensation coefficient for the second matching scene; Respectively obtaining a first probability difference value and a second probability difference value of the first difference value array and the second difference value array under corresponding set centralized distribution; According to the execution uncertainty, the time compensation coefficient, the probability difference and the trigger sensitivity, a control stability coefficient corresponding to the matching scenario is obtained; At the same time, the first time difference is determined according to the operator's setting working time St of the detonator and the current time Dt. ; If the first time difference If it is greater than the preset difference Yt, As the first effective moment St1 and As the second effective time St2, is the control stability coefficient corresponding to the best matching scenario, is the control stability coefficient corresponding to the second matching scenario; if the first time difference is less than the preset difference Yt, then As the first effective moment St1 and As the second effective time St2, ; Filter the smaller time between the first effective time and the second effective time finally obtained as the triggering time for the detonator.
2. The scene-adaptive switch control method for an initiator according to claim 1, characterized in that: Performing scenario analysis on the usage to obtain a scenario control set includes: Obtaining an initial scene queue associated with each usage purpose according to the usage-scene mapping table; Assigning the control parameters of the predefined environmental scene to the initial scene queue; Combine all the queues assigned to the scene to get the scene control set.
3. The scene-adaptive switch control method for an initiator according to claim 1, characterized in that: Perform environmental monitoring on the current application space of the detonator to construct an environmental matrix, including: Acquire several types of monitoring sensors for performing environmental monitoring on the current application space; The error range of each type of monitoring sensor is obtained from the sensor experiment database, and a matching variable array is constructed according to the error range and the monitoring attribute of each type of monitoring sensor based on the current application space of the corresponding detonator; Inputting the matching variable array into the primary and secondary analysis model to generate the primary monitoring class and the secondary monitoring class of the current application space; respectively obtaining the probe geometry of the monitoring probe of each type of monitoring sensor; Dividing the probe geometry into units according to the predefined monitoring accuracy of the corresponding monitoring sensor and in combination with the generated primary and secondary results of the monitoring class; ; Where H1 is the final number of divisions of the probe geometry; The number of divisions is determined according to the standard of predefined monitoring accuracy; It is the maximum value in the error range corresponding to the corresponding monitoring sensor; It is the minimum value in the error range corresponding to the corresponding type of monitoring sensor; Indicates whether the corresponding monitoring sensor has splitting value. If yes, the value is 1; if no, the value is 0. is the rounding symbol; When the corresponding monitoring sensor is the main monitoring type, The adjustment variables; Determine the acquisition frequency of each division unit and construct a frequency array; According to the probe length and probe material properties of the corresponding monitoring probe, the monitoring attenuation coefficient of each divided unit is obtained by matching from the length-property-attenuation data table; According to the actual collected value and frequency array of each monitoring sensor and combined with the monitoring attenuation coefficient, the effective collected value of the corresponding monitoring sensor is determined; ; Wherein, Yx represents the effective collection value of the corresponding monitoring sensor; Indicates from A random function that randomly selects a calculation result; Indicates the corresponding actual collected value; Indicates the standard acquisition combination corresponding to the corresponding frequency combination p The variance of Represents the coefficient variance of all monitoring attenuation coefficients involved in the corresponding monitoring sensor; Indicates the unit error of the corresponding type of monitoring sensor; represents the variance constant; According to all valid acquisition values of each monitoring sensor, an acquisition vector is constructed; Arrange the acquisition vectors of all monitoring sensors in rows to obtain the environment matrix.
4. The scene-adaptive switch control method for an initiator according to claim 1, characterized in that: The environmental matrix is analyzed to determine the impact vector on the detonator at different prediction times, including: Respectively determining the monitoring sensitivity values of adjacent column vectors in the environment matrix, and drawing a monitoring curve; Taking the monitoring sensitivity value of each convex point in the monitoring curve as the first deletion point, obtaining a first fitting value corresponding to the first deletion curve; Taking the monitoring sensitivity value of each concave point in the monitoring curve as the second deletion point, obtaining a second fitting value corresponding to the second deletion curve; Based on all the first fitting values and the second fitting values, the corresponding initiator double influence coefficient is obtained; According to the dual influence coefficients, each row vector in the environment matrix is subjected to influence analysis, and a final influence factor of the corresponding row vector is determined in combination with the monitoring purpose of the monitoring sensor of the corresponding row vector; Based on all the final influencing factors and combined with the monitoring column vector of the previous time before the prediction time, the influence vector at the corresponding prediction time is obtained.
5. The scene-adaptive switch control method for an initiator according to claim 1, characterized in that: Performing matching analysis on the influence vector and the scene control set, and determining the best matching scene and the second matching scene according to the matching analysis result, including: Inputting the influence vector into a vector analysis model to obtain a scene to be determined; The to-be-determined scene is matched with the scene control set, and a best matching scene and a second matching scene are obtained according to a similarity calculation function.
6. The scene-adaptive switch control method for an initiator according to claim 1, characterized in that: Controlling the detonator to adjust the switch mode according to the final control output under the best matching scenario and the second matching scenario, comprising: Acquire first matching information between the influence vector and the most matching scene, and at the same time, acquire second matching information between the influence vector and the second matching scene; Searching for a matching result consistent with the parameter information description of the non-matching information in the best matching scene from the second matching information and replacing the result to obtain a new matching scene; The final control output is obtained according to the set control parameters in the new matching scene, and then the detonator is controlled to be adjusted to a switching mode consistent with the final control output.
7. The scene-adaptive switch control method for an initiator according to claim 6, characterized in that: The capture device is in communication with the detonator.