A prefabricated exterior wall installation device and construction method for prefabricated buildings

By using automated control of the wall hoisting position adjustment device and the external support device, the problems of low efficiency, poor safety and large space occupation in the construction of prefabricated exterior walls of prefabricated buildings have been solved, and efficient and safe prefabricated exterior wall installation and same-floor grouting operation have been achieved.

CN118148382BActive Publication Date: 2026-11-10SHANGHAI CONSTR NO 5 GRP CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410371757.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2026-11-10
Estimated Expiration
2044-03-29

AI Technical Summary

Technical Problem

The existing construction of prefabricated exterior walls in prefabricated buildings suffers from problems such as low construction efficiency, poor safety, and large occupation of work space. In particular, a lot of effort is spent on the process of pre-embedded sleeves and steel bar alignment, and the use of diagonal supports leads to site clutter and safety hazards.

Method used

The system employs a wall hoisting position adjustment device, an external support device, and a disturbance state sensing device. It uses a monitor to detect the positional relationship between the sleeve and the reinforcing bar, and achieves precise alignment through a universal trolley and an adjusting arm. Combined with an adsorption joint and pressure/displacement sensing pads, it adjusts the verticality and support force of the wall in real time, thus realizing automated construction.

Benefits of technology

It improved construction efficiency, saved internal working space, enhanced construction safety and quality, reduced on-site clutter, and achieved efficient same-layer grouting conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118148382B_ABST
    Figure CN118148382B_ABST
Patent Text Reader

Abstract

This invention relates to an installation device and construction method for prefabricated exterior walls in prefabricated buildings. The device includes a wall hoisting position adjustment device, an external support device, and a disturbance sensing device. The wall hoisting position adjustment device includes a monitor and a universal trolley. The monitor is used for the alignment of the sleeve and the protruding reinforcing bars. An adjusting arm is installed on the universal trolley and clamps both sides of the upper wall. The external support device includes a supporting steel arm, which includes at least two rotating arm sections that are sequentially hinged. Adsorption joints are hinged to both ends of the supporting steel arm. Embedded steel plates corresponding to the adsorption joints are installed inside the wall, and the adsorption joints are respectively adsorbed onto the outer sides of the upper and lower walls. The disturbance sensing device uses pressure / displacement sensing pads installed on the adsorption joints. The external support device controls the force applied to the wall based on the detection results of the pressure / displacement sensing pads. This invention can reduce the occupation of internal construction space, improve construction safety, and ensure construction quality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of building construction, and in particular to a prefabricated exterior wall installation device and construction method for prefabricated buildings. Background Technology

[0002] In the construction industry, prefabricated exterior walls of assembled buildings often use sleeve grouting for vertical connection. During wall installation, the verticality of the wall is adjusted by diagonal supports, and a stable connection between the diagonal supports and the wall is ensured before grouting to support the wall.

[0003] The existing problems with vertical connection construction of precast exterior walls are as follows: 1. A lot of effort is required to align the embedded sleeves and reinforcing bars during the installation of precast walls; 2. The verticality of the wall is manually adjusted by using diagonal supports, which is inefficient. The diagonal supports cannot be removed before the grouting work is completed, occupying a large area of ​​work space, resulting in a messy site and safety issues such as haphazard bracing and welding of the diagonal supports; 3. Many projects use a construction method of concentrated grouting every three floors. The diagonal supports cannot be removed before grouting and curing, occupying a large number of diagonal supports.

[0004] Therefore, how to provide a prefabricated exterior wall installation device and construction method with higher work efficiency and safety is a technical problem that urgently needs to be solved by those skilled in the art. Summary of the Invention

[0005] This invention provides a prefabricated exterior wall installation device and construction method for prefabricated buildings to solve the above-mentioned technical problems.

[0006] To address the aforementioned technical problems, this invention provides a prefabricated exterior wall installation device for assembled buildings, comprising a wall hoisting position adjustment device, an external support device, and a disturbance state sensing device. The wall hoisting position adjustment device includes a monitor installed between the upper wall and the lower wall and a universal trolley placed at both ends of the wall. The monitor is used to detect the positional relationship between the sleeve and the protruding steel bar of the upper wall and the lower wall. The universal trolley is equipped with an adjusting arm, which is clamped on both sides of the upper wall. The external support device includes a support steel arm, which includes at least two rotating arms that are hinged in sequence; each end of the support steel arm is hinged with an adsorption connector; a pre-embedded steel plate corresponding to the adsorption connector is provided in the wall, and one end of the adsorption connector is adsorbed on the outside of the lower wall and the other end is adsorbed on the outside of the upper wall. The disturbance state sensing device uses a pressure / displacement sensing pad, which is installed on the adsorption connector. The external support device controls the force applied to the wall based on the detection results of the pressure / displacement sensing pad.

[0007] Preferably, a verticality monitoring ruler is also attached to the upper wall.

[0008] Preferably, the adjusting arm is connected to the connecting rod, and the connecting rod is mounted on the universal trolley via a hydraulic servo lifting device; the adjusting arm includes a fixed cover plate and two sets of clamping plates, one end of the clamping plates is installed inside the fixed cover plate, and can move along the fixed cover plate in directions toward and away from the wall.

[0009] Preferably, the omnidirectional vehicle is also equipped with a first vision sensor system.

[0010] Preferably, the adsorption connector includes an adsorption surface and a bearing support rod on the back of the adsorption surface, the bearing support rod is hinged to the end of the rotating arm, and a second visual sensing system is provided on the adsorption surface.

[0011] Preferably, the bearing support rod has a connecting gear in the middle, the end of the rotating arm is sleeved on the bearing support rod, and the end of the rotating arm has an adjusting gear that meshes with the connecting gear. The adjusting gear is driven to rotate by a first adjusting motor.

[0012] Preferably, the two rotating arms are engaged by a transmission gear and driven to rotate by a second regulating motor.

[0013] Preferably, it also includes an internal support device, which includes a top support steel arm, the two ends of which are respectively connected to the floor slab and the inner side of the upper wall through adsorption joints.

[0014] The present invention also provides a construction method for the prefabricated exterior wall installation device for prefabricated buildings as described above, comprising the following steps: Step 1: Before hoisting the prefabricated exterior wall, install one end of the external support device at the pre-embedded steel plate at the top of the lower wall, and adjust the other end to a position 20-30 cm away from the installation position of the upper wall; Step 2: Hoist the prefabricated exterior wall to a height of 1m above the floor slab at the installation location, and install the monitoring devices on both sides of the top of the lower wall. Step 3: Move the omnidirectional vehicle to both ends of the wall and control the adjusting arm to hold the wall. Adjust the wall installation position based on the detection result of the monitor. After the wall is aligned, lower it for installation. Remove the monitor after the extended steel bar enters the sleeve. Step 4: Adjust the external support device to attach the other end of the adsorption connector to the pre-embedded steel plate in the upper wall. Step 5: Install a verticality monitoring ruler on the wall to monitor the verticality of the wall surface, and transmit the verticality data to the external support device. Adjust the verticality of the wall through the first adjusting motor and the second adjusting motor. Step 6: During construction, the pressure / displacement sensing pad monitors the construction disturbance of the wall. Based on the construction disturbance, the first and second adjusting motors are controlled to rotate, so that the pressure value monitored by the pressure / displacement sensing pad returns to zero.

[0015] Preferably, in step 4, the position of the embedded steel plate is automatically detected by the second visual sensing system installed on the adsorption joint, and the position of the adsorption joint is adjusted by the first adjusting motor and the second adjusting motor.

[0016] Compared with the prior art, the prefabricated exterior wall installation device and construction method for prefabricated buildings provided by the present invention have the following advantages: 1. This invention can be fixed to the wall through the adsorption connector, and support the precast exterior wall from the outside of the wall. Combined with the verticality monitoring ruler, the verticality of the wall can be automatically adjusted in real time. It can replace the traditional internal support, save internal working space, and provide working conditions for the same-layer grouting. 2. This invention utilizes a disturbance state sensing device to monitor, provide feedback on, and make real-time adjustments to the disturbance state during wall construction, thereby further saving internal working space and improving construction efficiency. 3. This invention can effectively improve the construction efficiency of prefabricated wall hoisting and installation, enhance on-site safety and civilized construction, and ensure the construction quality of prefabricated buildings. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the structure of a prefabricated exterior wall installation device for prefabricated buildings according to a specific embodiment of the present invention; Figure 2 This is a schematic diagram illustrating the application of the wall hoisting position adjustment device in a specific embodiment of the present invention; Figure 3 This is a schematic diagram of the installation of the monitor in a specific embodiment of the present invention; Figure 4 This is a schematic diagram of the structure of the universal vehicle in a specific embodiment of the present invention; Figure 5 and Figure 6 These are schematic diagrams of the adjusting arm in a specific embodiment of the present invention; Figure 7 This is a schematic diagram of the calculation principle of the monitor in a specific embodiment of the present invention; Figure 8 This is a schematic diagram of the external support device in a specific embodiment of the present invention; Figure 9 This is a schematic diagram of the installation of the adsorption connector in a specific embodiment of the present invention; Figure 10 This is a schematic diagram of the structure of the adsorption connector in a specific embodiment of the present invention; Figure 11 This is a schematic diagram of the hinge of the rotating arm in a specific embodiment of the present invention; Figure 12 This is a schematic diagram of the installation of the transmission gear in a specific embodiment of the present invention; Figure 13 This is a schematic diagram of the installation of the second visual sensing system in a specific embodiment of the present invention; Figures 14a to 14c This is a schematic diagram of the construction process of the prefabricated exterior wall installation device for prefabricated buildings in Embodiment 1 of the present invention; Figure 15 This is a schematic diagram of the installation of the internal support device in Embodiment 2 of the present invention.

[0018] In the diagram: 010-Lower wall, 020-Upper wall, 030-Floor slab, 011-Extended reinforcing bar, 021-Sleeve, 040-Embedded steel plate; 100-Wall hoisting position adjustment device, 110-Monitor, 120-Universal trolley, 121-First vision sensor system, 130-Adjusting arm, 131-Fixed cover plate, 132-Clamping plate, 133-Rolling wheel, 134-Transmission belt, 135-Transmission motor, 140-Connecting rod, 150-Hydraulic servo lifting device. 200-External support device, 210-Support steel arm, 211-Rotating arm, 212-Adjusting gear, 213-First adjusting motor, 214-Transmission gear, 215-Second adjusting motor, 220-Adsorption connector, 221-Adsorption surface, 222-Bearing support rod, 223-Connecting gear, 224-Bearing ball, 225-Second vision sensing system, 310-Pressure / displacement sensing pad, 400-Verticality monitoring ruler, 500-Internal support device, 510-Top support steel arm. Detailed Implementation

[0019] To illustrate the technical solutions of the invention in more detail, specific embodiments are listed below to demonstrate the technical effects; it should be emphasized that these embodiments are used to illustrate the invention and not to limit the scope of the invention.

[0020] Example 1 The prefabricated exterior wall installation device and construction method for prefabricated buildings provided by this invention, such as... Figure 1 As shown, it includes a wall mounting position adjustment device 100, an external support device 200, and a disturbance state sensing device, wherein: The wall hoisting position adjustment device 100 includes a monitor 110 installed between the upper wall 020 and the lower wall 010, and a universal trolley 120 placed at both ends of the wall. The monitor 110 is used to detect the positional relationship between the sleeve 021 and the protruding reinforcing bar 011 of the upper wall 020 and the lower wall 010. The universal trolley 120 is equipped with an adjusting arm 130, which clamps on both sides of the upper wall 020. Based on the detection results of the monitor 110, the universal trolley 120 can control the adjusting arm 130 to move the wall to a designated position, completing the alignment and installation of the sleeve 021 and the protruding reinforcing bar 011.

[0021] The external support device 200 includes a support steel arm 210, which includes at least two rotating arms 211, which are hinged sequentially. Adsorption joints 220 are respectively hinged to both ends of the support steel arm 210. A pre-embedded steel plate 040 corresponding to the adsorption joint 220 is provided in the wall. One end of the adsorption joint 220 is adsorbed on the outside of the lower wall 010, and the other end is adsorbed on the outside of the upper wall 020. The prefabricated exterior wall is supported from the outside by the electromagnetic adsorption of the adsorption joint 220 and the pre-embedded steel plate 040.

[0022] The disturbance state sensing device uses a pressure / displacement sensing pad 310, which is installed on the adsorption joint 220 to collect the pressure / displacement of the wall under disturbance. The external support device 200 controls the force applied to the wall based on the detection results of the pressure / displacement sensing pad 310, thereby realizing the monitoring, feedback and real-time adjustment of the construction disturbance state of the wall.

[0023] This invention saves internal working space, provides working conditions for same-layer grouting, and has high construction efficiency and high safety.

[0024] In some embodiments, please refer to the following: Figures 2 to 4 The adjusting arm 130 is connected to the connecting rod 140. The connecting rod 140 is mounted on the universal carriage 120 via a hydraulic servo lifting device 150. The adjusting arm 130 moves in space by the movement of the universal carriage 120 on a plane and the extension and retraction of the hydraulic servo lifting device 150 in the vertical direction. The adjusting arm 130 includes a fixed cover plate 131 and two sets of clamping plates 132. One end of each clamping plate 132 is installed inside the fixed cover plate 131 and can move along the fixed cover plate 131 towards and away from the wall, thereby clamping and releasing the adjusting arm 130 onto the wall. In this embodiment, please refer to... Figure 5 and Figure 6A transmission belt 134 is installed inside the fixed cover plate 131. A transmission motor 135 can drive the transmission belt 134 to move cyclically. A rolling wheel 133 is provided at the end of the clamping plate 132. The rolling wheel 133 meshes with the transmission belt 134, thereby controlling the movement of the clamping plate 132. Of course, the structure of the adjusting arm 130 can also adopt other sliding methods, as long as the above functions can be achieved.

[0025] In some embodiments, please refer to Figure 2 The omnidirectional vehicle 120 is also equipped with a first vision sensor system 121, such as a binocular vision system, for detecting the position of the wall and controlling the movement distance of the drive motor 135 based on the relative position of the wall and the clamp 132.

[0026] In some embodiments, please refer to the following: Figure 7 The method by which the omnidirectional vehicle 120 controls the falling position of the wall based on the detection results of the monitor 110 is as follows: Figure 7 The dashed line represents the vertical shadow of sleeve 021, and the dotted line represents the center dividing line of monitor 110. Monitor 110 can automatically identify and measure the lateral distance *a* and longitudinal distance *a1* between the outer edge of the protruding rebar 011 and its own center dividing line, and the rebar radius *b*. Simultaneously, it automatically identifies and measures the lateral distance *c* between the center of the outermost sleeve 021 of the wall and its own center, and the longitudinal distance *c1*. Therefore, the lateral distance between the center of the protruding rebar 011 and the center of sleeve 021 is (a+b)-c or c-(a+b), and the longitudinal distance is (a1+b)-c1 or c1-(a1+b). Monitor 110 transmits the measured data to omnidirectional trolley 120, which uses adjusting arm 130 to control the movement of the wall for centering until the center of the protruding rebar 011 aligns with the corresponding center of sleeve 021. At this point, the hydraulic servo lifting device 150 can be controlled to descend, completing the hoisting and alignment of the wall.

[0027] In some embodiments, please refer to Figure 8 The upper wall 020 is also equipped with a verticality monitoring ruler 400 for detecting the verticality of the upper wall 020. The external support device 200 can control the support angle and support force of the support steel arm 210 based on the detection results of the verticality monitoring ruler 400 and the pressure / displacement sensing pad 310.

[0028] In some embodiments, please refer to the following: Figure 9 and Figure 13The adsorption connector 220 includes an adsorption surface 221 and a bearing support rod 222 on the back of the adsorption surface 221. The bearing support rod 222 is hinged to the end of the rotating arm 211. A second visual sensing system 225 is provided on the adsorption surface 221. The second visual sensing system 225 can be used to detect the position of the pre-embedded steel plate 040 in the wall in real time, so as to facilitate the alignment and connection of the adsorption connector 220 with the pre-embedded steel plate 040.

[0029] In some embodiments, please refer to the following: Figure 9 and Figure 10 The bearing support rod 222 has a connecting gear 223 in its middle. The end of the rotating arm 211 is sleeved on the bearing support rod 222, and the end of the rotating arm 211 has an adjusting gear 212 that meshes with the connecting gear 223. The adjusting gear 212 is driven to rotate by a first adjusting motor 213. That is, the connecting gear 223 and the adjusting gear 212 can rotate relative to each other by the first adjusting motor 213, thereby adjusting the angle between the rotating arm 211 and the adsorption connector 220. In some embodiments, please refer to... Figure 10 The rotating arm 211 and the bearing support rod 222 are provided with bearing balls 224 to ensure that the relative rotation between the support steel arm 210 and the adsorption connector 220 is smoother and more fluid.

[0030] In some embodiments, please refer to the following: Figure 11 and Figure 12 The two rotating arms 211 are engaged by a transmission gear 214 and driven to rotate by a second adjusting motor 215. That is, the second adjusting motor 215 is used as a power device to open the transmission gear 214, which drives the other rotating arm 211 to rotate, so as to realize the rotation adjustment of itself.

[0031] Example 2 like Figure 15 As shown, the difference between this embodiment and Embodiment 1 is that it also includes an internal support device 500. The internal support device 500 includes a top support steel arm 510. The two ends of the top support steel arm 510 are respectively connected to the floor slab 030 and the inner side of the upper wall 020 through adsorption joints 220. The external support device 200 and the internal support device 500 jointly provide support for the wall.

[0032] The present invention also provides a construction method for the prefabricated exterior wall installation device for prefabricated buildings as described above, comprising the following steps (taking Example 1 as an example): Step 1: Before hoisting the prefabricated exterior wall, install one end of the external support device 200 at the pre-embedded steel plate 040 at the top of the lower wall 010, and adjust the other end to a position 20-30 cm away from the installation position of the upper wall 020. Figure 14a As shown.

[0033] Step 2: Hoist the precast exterior wall (i.e., the upper wall 020) to a height of 1m above the floor slab at the installation location, and install the monitoring devices 110 on both sides of the top of the lower wall 010. Figure 14b As shown.

[0034] Step 3: Move the universal trolley 120 to both ends of the wall and control the adjusting arm 130 to clamp the wall. Adjust the wall installation position based on the detection result of the monitor 110. After the wall is aligned, lower it for installation. Remove the monitor 110 after the extended steel bar 011 extends into the sleeve 021.

[0035] Step 4: Adjust the external support device 200 to attach the other end of the adsorption connector 220 to the pre-embedded steel plate 040 of the upper wall 020, such as... Figure 14c As shown. In some embodiments, the position of the embedded steel plate 040 can be automatically detected based on the second vision sensing system 225 installed on the adsorption connector 220, and the position of the adsorption connector 220 can be adjusted by the first adjusting motor 213 and the second adjusting motor 215.

[0036] Step 5: Install a verticality monitoring ruler 400 on the wall to monitor the verticality of the wall surface, and transmit the verticality data to the external support device 200. Adjust the verticality of the wall through the first adjusting motor 213 and the second adjusting motor 215 until the verticality meets the requirements.

[0037] Step 6: During construction, the pressure / displacement sensing pad 310 monitors the construction disturbance of the wall. Based on the construction disturbance, the first adjusting motor 213 and the second adjusting motor 215 are controlled to rotate, so that the pressure value monitored by the pressure / displacement sensing pad 310 returns to zero. After the verticality of the external wall is adjusted, the external support device 200 provides support force to the wall. At this time, the pressure / displacement value monitored by the pressure / displacement sensing pad 310 is displayed (regardless of whether it is positive or negative). While keeping the position of the external support device 200 unchanged, the pressure / displacement value is adjusted to 0 as the initial value for disturbance monitoring. During construction, the change of pressure / displacement value is monitored in real time. A positive pressure / displacement value indicates that the external support device 200 is under pressure and the wall is deviated outward; a negative pressure / displacement value indicates that the external support device 200 is under tension and the wall is deviated inward. The external support device 200 automatically adjusts the verticality of the wall until the pressure / displacement value returns to zero, thereby eliminating construction disturbance.

[0038] In summary, the prefabricated exterior wall installation device and construction method for prefabricated buildings provided by this invention include a wall hoisting position adjustment device 100, an external support device 200, and a disturbance state sensing device. The wall hoisting position adjustment device 100 includes a monitor 110 installed between the upper wall 020 and the lower wall 010, and universal trolleys 120 placed at both ends of the wall. The monitor 110 is used to detect the positional relationship between the sleeve 021 and the protruding reinforcing bar 011 of the upper wall 020 and the lower wall 010. An adjusting arm 130 is installed on the universal trolley 120. The upper wall 020 is clamped on both sides; the external support device 200 includes a support steel arm 210, which includes at least two rotating arms 211, which are sequentially hinged; each end of the support steel arm 210 is hinged with an adsorption joint 220; a pre-embedded steel plate 040 corresponding to the adsorption joint 220 is provided in the wall, one end of the adsorption joint 220 is adsorbed on the outside of the lower wall 010, and the other end is adsorbed on the outside of the upper wall 020; the disturbance state sensing device uses a pressure / displacement sensing pad 310, which is installed on the adsorption joint 220. This invention saves internal working space, provides working conditions for same-layer grouting, and has high construction efficiency and high safety.

[0039] Obviously, those skilled in the art can make various modifications and variations to the invention without departing from the spirit and scope of the invention. Therefore, if these modifications and variations fall within the scope of the claims of the invention and their equivalents, the invention is also intended to include these modifications and variations.

Claims

1. A prefabricated exterior wall installation device for prefabricated buildings, characterized in that, It includes a wall mounting position adjustment device, an external support device, and a disturbance sensing device. The wall hoisting position adjustment device includes a monitor installed between the upper and lower walls and a universal trolley placed at both ends of the wall. The monitor is used to detect the positional relationship between the sleeves and protruding reinforcing bars of the upper and lower walls. The universal trolley is equipped with an adjusting arm, which is clamped on both sides of the upper wall. Based on the detection results of the monitor, the universal trolley controls the adjusting arm to move the wall to the designated position to complete the alignment and installation of the sleeves and protruding reinforcing bars. The external support device includes a support steel arm, which includes at least two rotating arms that are hinged sequentially. Adsorption joints are respectively hinged to both ends of the support steel arm. An embedded steel plate corresponding to the adsorption joint is provided inside the wall. One end of the adsorption joint is adsorbed on the outside of the lower wall and the other end is adsorbed on the outside of the upper wall. The prefabricated exterior wall is supported from the outside by the electromagnetic adsorption of the adsorption joint and the embedded steel plate. The disturbance state sensing device uses a pressure / displacement sensing pad, which is installed on the adsorption connector to collect the pressure / displacement of the wall under disturbance. The external support device controls the force applied to the wall based on the detection results of the pressure / displacement sensing pad.

2. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 1, characterized in that, A verticality monitoring ruler is also attached to the upper wall.

3. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 1, characterized in that, The adjusting arm is connected to the connecting rod, which is mounted on the omnidirectional vehicle via a hydraulic servo lifting device. The adjusting arm includes a fixed cover plate and two sets of clamping plates. One end of each clamping plate is installed inside the fixed cover plate and can move along the fixed cover plate towards and away from the wall.

4. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 3, characterized in that, The omnidirectional vehicle is also equipped with a first vision sensor system.

5. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 1, characterized in that, The adsorption connector includes an adsorption surface and a bearing support rod on the back of the adsorption surface. The bearing support rod is hinged to the end of the rotating arm. A second visual sensing system is provided on the adsorption surface.

6. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 5, characterized in that, The bearing support rod has a connecting gear in the middle, the end of the rotating arm is sleeved on the bearing support rod, and the end of the rotating arm has an adjusting gear that meshes with the connecting gear. The adjusting gear is driven to rotate by a first adjusting motor.

7. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 6, characterized in that, The two rotating arms are engaged by a transmission gear and driven to rotate by a second regulating motor.

8. The prefabricated exterior wall installation device for prefabricated buildings as described in claim 1, characterized in that, It also includes an internal support device, which includes a top support steel arm. The two ends of the top support steel arm are respectively connected to the floor slab and the inner side of the upper wall through adsorption joints.

9. A construction method for a prefabricated exterior wall installation device for prefabricated buildings as described in any one of claims 1 to 8, characterized in that, Includes the following steps: Step 1: Before hoisting the prefabricated exterior wall, install one end of the external support device at the pre-embedded steel plate at the top of the lower wall, and adjust the other end to a position 20-30 cm away from the installation position of the upper wall; Step 2: Hoist the prefabricated exterior wall to a height of 1m above the floor slab at the installation location, and install the monitoring devices on both sides of the top of the lower wall. Step 3: Move the omnidirectional vehicle to both ends of the wall and control the adjusting arm to hold the wall. Adjust the wall installation position based on the detection result of the monitor. After the wall is aligned, lower it for installation. Remove the monitor after the extended steel bar enters the sleeve. Step 4: Adjust the external support device to attach the other end of the adsorption connector to the pre-embedded steel plate in the upper wall. Step 5: Install a verticality monitoring ruler on the wall to monitor the verticality of the wall surface, and transmit the verticality data to the external support device. Adjust the verticality of the wall through the first adjusting motor and the second adjusting motor. Step 6: During construction, the pressure / displacement sensing pad monitors the construction disturbance of the wall. Based on the construction disturbance, the first and second adjusting motors are controlled to rotate, so that the pressure value monitored by the pressure / displacement sensing pad returns to zero.

10. The construction method as described in claim 9, characterized in that, In step 4, the position of the embedded steel plate is automatically detected by the second vision sensing system installed on the adsorption joint, and the position of the adsorption joint is adjusted by the first adjusting motor and the second adjusting motor.

Citation Information

Patent Citations

  • Automatically-adjusted oblique support and application method thereof

    CN108979169A

  • Accurate fabricating device and method for fabricated plate building wall

    CN112227734A

  • Alignment installation auxiliary device of fabricated wall bodies

    CN113356613A

  • Large-size thin-wall prefabricated bay window external wall panel hoisting, positioning and mounting method

    CN117627368A