T-shaped laminated shear wall, building and construction method of T-shaped laminated shear wall
By adopting the T-shaped overlapping shear wall design and using detachable modules and connection systems, the problem that existing shear walls cannot be disassembled and applied to multiple room modules is solved, achieving higher building flexibility and installation efficiency.
Patent Information
- Application Number
- CN202510339786.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2025-03-21
- Publication Date
- 2025-05-13
AI Technical Summary
The existing double-sided overlapping shear wall and assembled integral shear wall cannot be split into two parts and cannot be applied to the partition wall shared by two adjacent room modules.
The T-shaped overlapping shear wall design is designed, which includes two detachable modules. By pouring concrete in the factory, the modules are spliced into one, and the modules are connected by connecting stirrups and steel bar connection rings, and longitudinal steel bars and poured concrete are set up at the construction site to form a complete T-edge member.
The T-shaped overlapping shear wall is split and can be applied to the partition walls of two adjacent room modules, improving the flexibility and installation efficiency of the building without affecting the stress performance.
Smart Images

Figure CN119981314A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of construction, and in particular relates to a T-shaped composite shear wall, a building and a construction method thereof. Background Art
[0002] Prefabricated shear walls can be divided into double-sided composite wall panels and assembled integral shear walls. Double-sided composite shear walls are made of two prefabricated reinforced concrete panels, which are connected to form a wall panel component with a middle cavity through trusses or connectors in the factory. After on-site installation, concrete is poured to fill the middle cavity to form a concrete wall. Double-sided composite wall panels are produced through fully automatic imported assembly lines with a high degree of automation, very high production efficiency and processing accuracy, as well as good integrity and excellent waterproof performance. The assembled integral shear wall is a solid structure. The wall reinforcement binding and concrete pouring are completed in the factory and then transported to the construction site for installation.
[0003] The existing double-sided composite shear wall and assembled integral shear wall have many limitations when applied to the partition wall shared by two prefabricated room modules, which are specifically manifested as follows:
[0004] The inner and outer blades of the double-sided composite shear wall are connected by truss steel bars or connectors to form a wall panel component with a cavity in the middle. The inner and outer blades are integrated, which means that it can only be used on the facade of a modular building. The inner and outer blades cannot be detached and distributed to two adjacent room modules, that is, it cannot be used in the partition wall shared by two room modules.
[0005] The fabricated integral shear wall is a solid component, and its integrity makes it impossible to split it into two parts and distribute it to the partition wall between two adjacent room modules. Summary of the invention
[0006] The object of the present invention is to provide a T-shaped composite shear wall, a building and a construction method thereof, which solves the problem that the inner and outer blades of the existing double-sided composite shear wall cannot be split into two parts and cannot be used in the partition walls of adjacent room modules.
[0007] The present invention is implemented as follows: a T-shaped composite shear wall comprises a first module and a second module arranged opposite to each other, wherein the first module comprises a first module edge member and a first module shell mold, the first module edge member is located at a side edge position of the top of the first module shell mold, and the two are spliced into one by pouring concrete in a factory; the second module comprises a second module edge member and a second module shell mold, the second module edge member is located at a side edge position of the top of the second module shell mold, and the two are spliced into one by pouring concrete in a factory;
[0008] One side of the first module edge member protrudes out the first module horizontal stirrup, and one side of the first module shell formwork protrudes out the first wall body steel bar connecting ring in the horizontal direction; one side of the second module edge member protrudes out the second module horizontal stirrup, and one side of the second module shell formwork protrudes out the second wall body steel bar connecting ring in the horizontal direction; wherein the first module horizontal stirrup is connected to the second module horizontal stirrup by connecting stirrups provided at the construction site, and the first wall body steel bar connecting ring in the horizontal direction is anchored to the second wall body steel bar connecting ring in the horizontal direction;
[0009] After the first module and the second module are combined, a cavity is formed between the two. Longitudinal steel bars are arranged in the cavity and concrete is poured at the construction site.
[0010] Furthermore, the first module edge component includes a first module precast beam body, in which the first module precast beam longitudinal reinforcement, the first module precast beam stirrups and the first module horizontal stirrups are embedded; two upper and lower adjacent first module precast beam longitudinal reinforcements are tied into a steel cage by the first module precast beam stirrups, and a first module edge component notch is reserved at one end of the first module precast beam body near the splicing point as a part of the cavity, and one end of the first module precast beam longitudinal reinforcement and the first module horizontal stirrups extend into the first module edge component notch.
[0011] Further, the first module shell formwork includes a first module edge member shell formwork, a first module wall shell formwork, a first module beam shell formwork and a first module structural column, and the first module edge member shell formwork, the first module wall shell formwork and the first module beam shell formwork are all embedded with first module prefabricated wall horizontal reinforcement and first module prefabricated wall longitudinal reinforcement in concrete; wherein the first module wall shell formwork is also embedded with the first horizontal wall steel bar connecting ring, and one end of the first horizontal wall steel bar connecting ring extends into the cavity; the first module structural column is located at the junction of the first module wall shell formwork and the first module beam shell formwork, so as to serve as a template to close the cavity.
[0012] Furthermore, the second module edge component includes a second module precast beam body, in which the second module precast beam longitudinal reinforcement, the second module precast beam stirrups and the second module horizontal stirrups are embedded; two adjacent second module precast beam longitudinal reinforcements are tied into a steel cage by the second module precast beam stirrups, and a second module edge component notch is reserved at one end of the second module precast beam body near the splicing point as a part of the cavity, and one end of the second module precast beam longitudinal reinforcement and the second module horizontal stirrups extend into the second module edge component notch.
[0013] Furthermore, the second module shell formwork includes a second module edge component shell formwork, a second module wall shell formwork, a second module beam shell formwork and a second module structural column, and the second module edge component shell formwork, the second module wall shell formwork and the second module beam shell formwork are all embedded with second module prefabricated wall horizontal reinforcement and second module prefabricated wall longitudinal reinforcement in concrete; wherein, the second module wall shell formwork is also embedded with a second wall body steel bar connecting ring, and one end of the second wall body steel bar connecting ring extends into the cavity; the second module beam shell formwork is also provided with two rows of second module beam longitudinal reinforcement, and the two rows of second module beam longitudinal reinforcement are tied into a steel cage through the second module beam stirrups, and one row of the second module beam longitudinal reinforcement is embedded in the concrete of the second module beam shell formwork; the second module structural column is located at the intersection of the second module wall body shell formwork and the second module beam shell formwork.
[0014] Furthermore, first bolt sleeves are pre-embedded in the first module shell mold at a certain distance in the longitudinal and transverse directions, and second bolt sleeves are pre-embedded in the second module shell mold at a certain distance in the longitudinal and transverse directions.
[0015] In order to achieve the above-mentioned object of the invention, the present invention further provides a building, wherein the inner partition wall of the building is provided with any of the above-mentioned T-shaped composite shear walls.
[0016] Furthermore, the building comprises at least two room modules, and the inner partition wall between two adjacent room modules is provided with the T-shaped composite shear wall.
[0017] Furthermore, the building comprises at least two floors, wherein the top of the T-shaped composite shear wall of the lower floor is provided with dowel bars, and the bottom of the T-shaped composite shear wall of the upper floor is provided with grooves extending along the length direction of the wall body, and the dowel bars are inserted into the grooves; the T-shaped composite shear walls of the upper and lower floors are combined together by pouring concrete in the cavity.
[0018] To achieve the above object of the invention, the present invention also provides a method for constructing a building, comprising the following steps:
[0019] During the prefabrication of the first module, the first module and its surrounding walls form a first room module by pouring concrete in the factory; during the prefabrication of the second module, the second module and its surrounding walls form a second room module by pouring concrete in the factory;
[0020] A first back rib is installed on the inner side of the first module of the first room module, and the first back rib is connected to the first embedded bolt sleeve on the first module through a first connecting bolt; a second back rib is installed on the inner side of the second module of the second room module, and the second back rib is connected to the second embedded bolt sleeve on the second module through a second connecting bolt;
[0021] Transport the required room modules to the construction site;
[0022] First, hoist the first room module, and during the hoisting process, drop it from top to bottom until it is installed in place; then hoist the second room module, and during the hoisting process, drop it from top to bottom until it is installed in place;
[0023] At the construction site, the horizontal stirrups of the first module and the horizontal stirrups of the second module are connected by connecting stirrups, and the first wall reinforcement connecting ring in the horizontal direction and the second wall reinforcement connecting ring in the horizontal direction are anchored to each other; and longitudinal reinforcement is arranged in the cavity;
[0024] A template is provided on the outer sides of the edge member of the first module and the edge member of the second module to seal the open part of the cavity;
[0025] At the construction site, concrete is poured into the cavity;
[0026] After the concrete is solid, remove the first back rib, the second back rib and the formwork.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The T-shaped composite shear wall of the present invention has a first module and a second module which can be split into two adjacent room modules. After the two modules are poured with concrete at the construction site, a complete T-shaped edge member is formed. This method does not increase the thickness of the wall edge member, and it is convenient to place steel bars on site. The prefabricated and cast-in-place parts are effectively connected through the reserved horizontal stirrups of the prefabricated part and the stirrups installed in the cast-in-place, so that the T-shaped composite shear wall forms a complete whole, and its stress-bearing performance is not affected compared with the cast-in-place member.
[0029] The present invention proposes a prefabricated shear wall body combination form, in which the wall body component is split into two shell membrane form components, both of which are provided with horizontal stirrups, horizontal steel bars and longitudinal steel bars of the shear wall, and the truss bars or connectors of the double-sided superimposed shear wall are replaced by horizontal stirrups. The horizontal stirrups carried by the two components are arranged at intervals, and a cavity for post-cast concrete is formed in the middle after the two components are combined. After concrete is poured in the cavity, the horizontal stirrups of the two components form an effective tensile force after the concrete solidifies, so that the two components can be effectively combined into a complete shear wall body.
[0030] The top of the lower prefabricated shear wall can be reserved with dowel bars, and the bottom of the upper shear wall is provided with grooves extending along the length of the wall. After the steel bars are inserted into the grooves, the two floors can be combined by pouring concrete in the wall cavity. The thickness of the shear wall does not need to be increased, and there is no need to install longitudinal connecting bars and formwork on the construction site. The wall installation efficiency is high, the quality is reliable, and the on-site assembly efficiency can be improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic plan view of a T-shaped portion of a T-shaped composite shear wall formed by assembling a first module and a second module provided in an embodiment of the present invention;
[0032] Figure 2 yes Figure 1 A schematic cross-sectional view along line 1-1;
[0033] Figure 3 yes Figure 1 A schematic cross-sectional view along line 2-2;
[0034] Figure 4 yes Figure 1 A schematic cross-sectional view along line 3-3;
[0035] Figure 5 yes Figure 1 A schematic cross-sectional view along line 4-4;
[0036] Figure 6 is a structural diagram of a first module provided by an embodiment of the present invention;
[0037] Figure 7 is a structural schematic diagram of a first module edge component of a first module provided in an embodiment of the present invention;
[0038] Figure 8 is a structural schematic diagram of a first module shell mold of a first module provided in an embodiment of the present invention;
[0039] Fig. 9 is a structural diagram of a second module provided by an embodiment of the present invention;
[0040] Fig.10 is a schematic structural diagram of a second module edge component of a second module provided by an embodiment of the present invention;
[0041] Fig.11 is a structural schematic diagram of a second module shell mold of a second module provided in an embodiment of the present invention;
[0042] Fig.12 is a schematic diagram of the structure of two room modules in a building provided by an embodiment of the present invention;
[0043] Fig.13 It is a construction flow chart of a building provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.
[0045] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "front", "rear", "vertical", "horizontal", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention; the terms "first", "second", and "third" are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance; in addition, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be a connection between the two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0046] See also Figures 1 to 5 , shows a T-shaped composite shear wall provided in this embodiment, wherein: Figure 1 A schematic plan view of a T-shaped portion of a T-shaped composite shear wall formed by assembling a first module and a second module provided in an embodiment of the present invention; Figure 2 yes Figure 1 A schematic cross-sectional view along line 1-1; Figure 3 yes Figure 1 A schematic cross-sectional view along line 2-2; Figure 4 yes Figure 1 A schematic cross-sectional view along line 3-3; Figure 5 yes Figure 1 Schematic cross-sectional view along line 4-4. As shown in the figure, the T-shaped composite shear wall includes a first module and a second module arranged opposite to each other. Figure 6 As shown, the first module includes a first module edge member 110 and a first module shell mold 120. The first module edge member 110 is located at one side of the top of the first module shell mold 120. The two are spliced into one by pouring concrete in the factory. Fig. 9 As shown, the second module includes a second module edge member 210 and a second module shell mold 220. The second module edge member 210 is located at one side of the top of the second module shell mold 220. The two are joined together by pouring concrete in the factory. The first module and its surrounding walls constitute a first room module, and the second module and its surrounding walls constitute a second room module.
[0047] The first module horizontal stirrup 111 protrudes from one side of the first module edge member 110, and the first module shell formwork 120 protrudes from one side of the horizontal wall body steel bar connection ring 121; the second module horizontal stirrup 211 protrudes from one side of the second module edge member 210, and the second module shell formwork 220 protrudes from one side of the horizontal wall body steel bar connection ring 221. The first module horizontal stirrup 111 and the second module horizontal stirrup 211 are connected by connecting stirrups 300 provided at the construction site, and the first wall body steel bar connection ring 121 and the second wall body steel bar connection ring 221 are anchored to each other;
[0048] After the first module and the second module are combined, a cavity is formed between the two. At the construction site, longitudinal steel bars 400 are arranged in the cavity and concrete is poured.
[0049] Specifically, see Figure 6 and Figure 7 The first module edge member 110 includes a first module precast beam body, in which the first module precast beam longitudinal reinforcement 112, the first module precast beam stirrups 113 and the above-mentioned first module horizontal stirrups 111 are embedded; two upper and lower adjacent first module precast beam longitudinal reinforcements 112 are tied into a steel cage through the first module precast beam stirrups 113, and a first module edge member notch 114 as a part of the cavity is reserved at one end of the first module precast beam body near the splicing part, and one end of the first module precast beam longitudinal reinforcement 112 and the first module horizontal stirrups 111 extend into the first module edge member notch 114.
[0050] Specifically, see Figure 8 The first module shell form 120 includes a first module edge member shell form 122, a first module wall shell form 123, a first module beam shell form 124 and a first module structural column 125. The first module precast wall horizontal reinforcement 126 and the first module precast wall longitudinal reinforcement 127 are embedded in the concrete of the first module edge member shell form 122, the first module wall shell form 123 and the first module beam shell form 124; wherein the first module wall shell form 123 is also embedded with the above-mentioned first wall steel bar connecting ring 121 in the horizontal direction, and one end of the first wall steel bar connecting ring 121 in the horizontal direction extends into the cavity; the first module structural column 125 is located at the intersection of the first module wall shell form 123 and the first module beam shell form 124, so as to be used as a template to close the cavity.
[0051] Specifically, see Fig. 9 and Fig.10The second module edge member 210 includes a second module precast beam body, in which the second module precast beam longitudinal reinforcement 212, the second module precast beam stirrups 213 and the above-mentioned second module horizontal stirrups 211 are embedded; two adjacent second module precast beam longitudinal reinforcements 212 are tied into a steel cage through the second module precast beam stirrups 213, and a second module edge member notch 214 as a part of the cavity is reserved at one end of the second module precast beam body near the splicing part, and one end of the second module precast beam longitudinal reinforcement 212 and the second module horizontal stirrups 211 extend into the second module edge member notch 214.
[0052] Specifically, see Fig.11 The second module shell form 220 includes a second module edge member shell form 222, a second module wall shell form 223, a second module beam shell form 224, and a second module structural column 225. The second module edge member shell form 222, the second module wall shell form 223, and the second module beam shell form 224 are embedded with second module precast wall horizontal reinforcement 226 and second module precast wall longitudinal reinforcement 227 in concrete; wherein the second module wall shell form 223 is also embedded with the second wall steel bar in the horizontal direction. The second module beam shell formwork 224 is also provided with two rows of second module beam longitudinal bars 228, and the two rows of second module beam longitudinal bars 228 are tied into a steel cage through the second module beam stirrups 229, and one row of the second module beam longitudinal bars 228 is embedded in the concrete of the second module beam shell formwork 224; the second module structural column 225 is located at the intersection of the second module wall shell formwork 223 and the second module beam shell formwork 224.
[0053] Furthermore, if Figure 6 As shown, first bolt sleeves 12a are pre-buried at certain intervals in the longitudinal and transverse directions in the first module shell mold 120, and first back ribs 12c are installed on the inner side of the first module through first connecting bolts 12b; second bolt sleeves 22a are pre-buried at certain intervals in the longitudinal and transverse directions in the second module shell mold 220, and second back ribs 22c are installed on the inner side of the second module through second connecting bolts 22b. By installing back ribs on the inner side of the module, the rigidity of the shell membrane can be increased, ensuring that the shell membrane will not crack or deform during the transportation of the module. At the same time, when pouring concrete at the construction site, the shell membrane can also be prevented from bursting. The back ribs can be removed and recycled after the concrete is poured and solidified.
[0054] See also Fig.12 This embodiment also provides a building, including at least two room modules, and the inner partition wall between the left and right adjacent first room modules and second room modules is provided with a T-shaped composite shear wall in any of the above-mentioned embodiments.
[0055] The building comprises at least two floors, the top of the T-shaped composite shear wall of the lower floor is provided with dowel bars, the bottom of the T-shaped composite shear wall of the upper floor is provided with grooves extending along the length direction of the wall body, and the dowel bars are inserted into the grooves; the T-shaped composite shear walls of the upper and lower floors are combined together by pouring concrete in the cavity.
[0056] See also Fig.13 The present embodiment provides a method for constructing a building, comprising the following steps:
[0057] During the prefabrication of the first module, the first module and its surrounding walls form a first room module by pouring concrete in the factory; during the prefabrication of the second module, the second module and its surrounding walls form a second room module by pouring concrete in the factory;
[0058] A first back rib 12c is installed on the inner side of the first module of the first room module, and the first back rib 12c is connected to the first embedded bolt sleeve 12a on the first module through a first connecting bolt 12b; a second back rib 22c is installed on the inner side of the second module of the second room module, and the second back rib 22c is connected to the second embedded bolt sleeve 22a on the second module through a second connecting bolt 22b;
[0059] Transport the required room modules to the construction site;
[0060] First, hoist the first room module, and during the hoisting process, drop it from top to bottom until it is installed in place; then hoist the second room module, and during the hoisting process, drop it from top to bottom until it is installed in place;
[0061] At the construction site, the first module horizontal stirrup 111 and the second module horizontal stirrup 211 are connected by connecting stirrups 300, and the first wall body steel bar connecting ring 121 and the second wall body steel bar connecting ring 221 in the horizontal direction are anchored to each other; and longitudinal steel bars 400 are arranged in the cavity;
[0062] A template is provided on the outer sides of the first module edge member 110 and the second module edge member 210 to seal the open part of the cavity;
[0063] At the construction site, concrete is poured into the cavity;
[0064] After the concrete is solid, remove all back ribs and formwork.
[0065] In summary, the first module and the second module of the T-shaped composite shear wall of this embodiment can be split into two adjacent room modules, and the two modules form a complete T-shaped edge member after pouring concrete at the construction site. This method does not increase the thickness of the wall edge member, and it is convenient to place steel bars on site. The prefabricated and cast-in-place parts are effectively connected through the reserved horizontal stirrups of the prefabricated part and the stirrups installed in the cast-in-place, so that the T-shaped composite shear wall forms a complete whole, and its stress performance is not affected compared with the cast-in-place member.
[0066] This embodiment proposes a prefabricated shear wall body combination form, which splits the wall body component into two shell membrane form components, both of which are equipped with horizontal stirrups, horizontal steel bars and longitudinal steel bars of the shear wall. The truss bars or connectors of the double-sided composite shear wall are replaced by horizontal stirrups. The horizontal stirrups carried by the two components are arranged at intervals. After the two components are combined, a cavity for post-cast concrete is formed in the middle. After concrete is poured in the cavity, the horizontal stirrups of the two components form an effective tensile force after the concrete solidifies, so that the two components can be effectively combined into a complete shear wall body.
[0067] The top of the lower prefabricated shear wall can be reserved with dowel bars, and the bottom of the upper shear wall is provided with grooves extending along the length of the wall. After the steel bars are inserted into the grooves, the two floors can be combined by pouring concrete in the wall cavity. The thickness of the shear wall does not need to be increased, and there is no need to install longitudinal connecting bars and formwork on the construction site. The wall installation efficiency is high, the quality is reliable, and the on-site assembly efficiency can be improved.
[0068] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A T-shaped composite shear wall, characterized in that: The first module comprises a first module edge member and a first module shell mold, the first module edge member is located at one side of the top of the first module shell mold, and the two are spliced into one by pouring concrete in the factory; the second module comprises a second module edge member and a second module shell mold, the second module edge member is located at one side of the top of the second module shell mold, and the two are spliced into one by pouring concrete in the factory; the first module and the surrounding walls constitute a first room module, and the second module and the surrounding walls constitute a second room module; One side of the first module edge member protrudes out the first module horizontal stirrup, and one side of the first module shell formwork protrudes out the first wall body steel bar connecting ring in the horizontal direction; one side of the second module edge member protrudes out the second module horizontal stirrup, and one side of the second module shell formwork protrudes out the second wall body steel bar connecting ring in the horizontal direction; wherein the first module horizontal stirrup is connected to the second module horizontal stirrup by connecting stirrups provided at the construction site, and the first wall body steel bar connecting ring in the horizontal direction is anchored to the second wall body steel bar connecting ring in the horizontal direction; After the first module and the second module are combined, a cavity is formed between the two. Longitudinal steel bars are arranged in the cavity and concrete is poured at the construction site.
2. The T-shaped composite shear wall according to claim 1, characterized in that: The first module edge component comprises a first module precast beam body, in which the first module precast beam longitudinal reinforcement, the first module precast beam stirrups and the first module horizontal stirrups are embedded; two upper and lower adjacent first module precast beam longitudinal reinforcements are bound into a steel cage by the first module precast beam stirrups, and a first module edge component notch as a part of the cavity is reserved at one end of the first module precast beam body near the splicing part, and one end of the first module precast beam longitudinal reinforcement and the first module horizontal stirrups extend into the first module edge component notch.
3. The T-shaped composite shear wall according to claim 1, characterized in that: The first module shell formwork includes a first module edge component shell formwork, a first module wall shell formwork, a first module beam shell formwork and a first module structural column. The first module prefabricated wall horizontal reinforcement and the first module prefabricated wall longitudinal reinforcement are embedded in the concrete of the first module edge component shell formwork, the first module wall shell formwork and the first module beam shell formwork; wherein the first module wall shell formwork is also embedded with the first horizontal wall steel bar connecting ring, and one end of the first horizontal wall steel bar connecting ring extends into the cavity; the first module structural column is located at the intersection of the first module wall shell formwork and the first module beam shell formwork, so as to serve as a template to close the cavity.
4. The T-shaped composite shear wall according to claim 1, characterized in that: The second module edge component includes a second module prefabricated beam body, in which the second module prefabricated beam longitudinal reinforcement, the second module prefabricated beam stirrups and the second module horizontal stirrups are embedded; two adjacent second module prefabricated beam longitudinal reinforcements are tied into a steel cage by the second module prefabricated beam stirrups, and a second module edge component notch is reserved at one end of the second module prefabricated beam body near the splicing point as a part of the cavity, and one end of the second module prefabricated beam longitudinal reinforcement and the second module horizontal stirrups extend into the second module edge component notch.
5. The T-shaped composite shear wall according to claim 1, characterized in that: The second module shell formwork comprises a second module edge member shell formwork, a second module wall shell formwork, a second module beam shell formwork and a second module structural column, and the second module edge member shell formwork, the second module wall shell formwork and the second module beam shell formwork are all embedded with second module prefabricated wall horizontal reinforcement and second module prefabricated wall longitudinal reinforcement in concrete; wherein, the second module wall shell formwork is also embedded with the second wall body steel bar connecting ring in the horizontal direction, and one end of the second wall body steel bar connecting ring in the horizontal direction extends into the cavity; the second module beam shell formwork is also provided with two rows of second module beam longitudinal reinforcement, and the two rows of second module beam longitudinal reinforcement are tied into a steel cage through the second module beam stirrups, and one row of the second module beam longitudinal reinforcement is embedded in the concrete of the second module beam shell formwork; the second module structural column is located at the intersection of the second module wall body shell formwork and the second module beam shell formwork.
6. The T-shaped composite shear wall according to claim 1, characterized in that: First bolt sleeves are pre-buried in the first module shell mold at a certain distance in the longitudinal and transverse directions, and second bolt sleeves are pre-buried in the second module shell mold at a certain distance in the longitudinal and transverse directions.
7. A building, characterized in that: The inner partition wall in the building is provided with a T-shaped composite shear wall as claimed in any one of claims 1 to 6.
8. The building according to claim 7, characterized in that It comprises at least two room modules, and the inner partition wall between two adjacent room modules is provided with the T-shaped composite shear wall.
9. The building according to claim 7 or 8, characterized in that: The invention comprises at least two floors, wherein the top of the T-shaped composite shear wall of the lower floor is provided with dowel bars, and the bottom of the T-shaped composite shear wall of the upper floor is provided with grooves extending along the length direction of the wall body, and the dowel bars are inserted into the grooves; the T-shaped composite shear walls of the upper and lower floors are combined together by pouring concrete in the cavity.
10. A method for constructing a building according to claim 7, characterized in that: The following steps are involved: During the prefabrication of the first module, the first module and its surrounding walls form a first room module by pouring concrete in the factory; during the prefabrication of the second module, the second module and its surrounding walls form a second room module by pouring concrete in the factory; A first back rib is installed on the inner side of the first module of the first room module, and the first back rib is connected to the first embedded bolt sleeve on the first module through a first connecting bolt; a second back rib is installed on the inner side of the second module of the second room module, and the second back rib is connected to the second embedded bolt sleeve on the second module through a second connecting bolt; Transport the required room modules to the construction site; First, hoist the first room module, and during the hoisting process, drop it from top to bottom until it is installed in place; then hoist the second room module, and during the hoisting process, drop it from top to bottom until it is installed in place; At the construction site, the horizontal stirrups of the first module and the horizontal stirrups of the second module are connected by connecting stirrups, and the first wall reinforcement connecting ring in the horizontal direction and the second wall reinforcement connecting ring in the horizontal direction are anchored to each other; and longitudinal reinforcement is arranged in the cavity; A template is provided on the outer sides of the edge member of the first module and the edge member of the second module to seal the open part of the cavity; At the construction site, concrete is poured into the cavity; After the concrete is solid, remove the first back rib, the second back rib and the formwork.
Citation Information
Cited By
Superimposed shear wall module structure system with mutually lapped single truss steel bars and construction method
CN120946032A
Monolithic truss steel bar overlapping composite shear wall module structural system and construction method
CN120946032B
Vertical superposed beam for modular superposed shear wall and construction method of vertical superposed beam
CN122383083A
A vertical laminated beam for a modular laminated shear wall and a construction method thereof
CN122383083B