Method, device and electronic equipment for determining power parameters

By integrating a comprehensive power allocation model and combining multiple power trading modes, the method for determining power parameters was optimized, which solved the problem of poor returns for power providers under different modes and achieved higher overall economic benefits.

CN118154000BActive Publication Date: 2024-11-08中能智新科技产业发展有限公司 +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410565100.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-09
Publication Date
2024-11-08
Estimated Expiration
2044-05-09

AI Technical Summary

Technical Problem

In existing technologies, the process of determining power parameters by power providers under different power trading models is independent and economically inefficient, resulting in poor overall returns.

Method used

A comprehensive power allocation model is adopted, including a first clearing model, a second clearing model, a third clearing model, and a financial transmission rights allocation model. By inputting multiple sets of power parameters, the profit value of the target power provider under different models is calculated, the optimal power parameters are determined, and the close relationship between different power trading models is considered.

Benefits of technology

This improves the overall economic benefits for the target power provider in the electricity market by comprehensively considering the relationship between various trading models and optimizing the process of determining power parameters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118154000B_ABST
    Figure CN118154000B_ABST
Patent Text Reader

Abstract

The present application provides a method, device and electronic device for determining power parameters, which are applied to the field of power technology. The method includes inputting multiple groups of power parameters into a preset power configuration model to obtain multiple groups of power configuration results; obtaining multiple groups of target power configuration results corresponding to the target power provider from the multiple groups of power configuration results; calculating multiple profit values ​​corresponding to the target power provider under the multiple groups of target power configuration results; and determining the target power parameters of the target power provider based on the multiple profit values. The method comprehensively considers the relationship between different power trading modes in the power market, thereby improving the overall economic benefits obtained by the target power provider.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of electric power technology, and in particular to a method, device and electronic equipment for determining electric power parameters. Background Art

[0002] In the power system, power providers refer to companies or entities that produce electricity. They can choose to sell the electricity they produce based on different power parameters under various power trading modes. Power parameters usually include electricity price (cost per unit of electricity) and quantity (amount of electricity to be sold). Each power provider needs to determine appropriate power parameters to make an ideal profit. There is a close relationship between the various power trading modes in the power system. However, in the prior art, the power provider's power parameter determination process under different modes is independent, and the overall economic efficiency of this power parameter determination method is poor. Summary of the invention

[0003] The embodiments of the present application provide a method, device and electronic device for determining power parameters to solve the problem.

[0004] In order to solve the above technical problems, this application is implemented as follows:

[0005] In a first aspect, an embodiment of the present application provides a method for determining a power parameter, the method for determining a power parameter comprising:

[0006] Inputting multiple sets of power parameters into a preset power configuration model respectively to obtain multiple sets of power configuration results;

[0007] Acquire multiple groups of target power configuration results corresponding to target power providers from the multiple groups of power configuration results;

[0008] Calculating a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results;

[0009] determining a target power parameter of the target power provider according to the multiple profit values;

[0010] Wherein, each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission rights configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power configuration results include at least two of multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, multiple groups of third power configuration results output by the third clearing model and multiple groups of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result;

[0011] The first power parameter includes the declared power quantity and declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode;

[0012] The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode;

[0013] The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode;

[0014] The fourth power configuration result includes whether to purchase financial transmission rights.

[0015] Optionally, the first clearing model includes a first objective function with the goal of minimizing the clearing electricity price under the first mode, a first constraint condition and a safe operation constraint condition;

[0016] The first objective function is:

[0017] ;

[0018] The first constraint condition includes:

[0019] ;

[0020] in, Pzhong represents the clearing electricity price finally output by the first clearing model, P’ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l / P i,l Indicates the power provider i The winning bid is Q i,l The corresponding declared electricity price is P i,l , Q b i,l Indicates the power provider i The declared power in the first mode is: Q lD surface indicating the power demand in the first mode;

[0021] The safety operation constraints include:

[0022] ;

[0023] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0024] Optionally, the second clearing model includes a second objective function and a second constraint condition with the goal of minimizing the clearing electricity price under the second mode;

[0025] The second objective function is:

[0026] ;

[0027] The second constraint is:

[0028] ;

[0029] in, P f1 represents the clearing electricity price finally output by the second clearing model, P’ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme under the second mode, B i / Q i,f Indicates the power provider i The winning bid capacity is Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β 1 Indicates the lower limit requirement of capacity, β 2 Indicates the upper limit requirement of capacity. Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity under the second mode.

[0030] Optionally, the third clearing model includes a third objective function with the goal of minimizing the power generation cost under the third mode, a third constraint condition and a safe operation constraint condition;

[0031] The third objective function is:

[0032] ;

[0033] The third constraint condition is:

[0034] ;

[0035] in, B i,s Indicates the power provider i The power generation cost function under the third mode is: C i,0 Indicates the power provider i fixed costs, k i Indicates the power provider i The declared electricity price factor, Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity in the second mode is N express N Electricity providers, T express T time point;

[0036] The safety operation constraints are:

[0037] ;

[0038] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformersj , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0039] Optionally, the fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

[0040] Optionally, the multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results;

[0041] The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode;

[0042] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0043] Optionally, the first profit value is calculated according to the following calculation formula:

[0044] ;

[0045] in, J 1 represents the first profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the target electricity provider i At the time point in the first mode j The clearing price of electricity, Indicates the target power provider i At the point in time j The unified settlement point electricity price, M represents the penalty factor, Q' represents the target power provider i The expected power generation, n 1 Indicates the number of time points, n 2 Indicates the number of contract days. Indicates the target power provider i Existing contracted electricity, N k Indicates the selection of k The number of standard curves, U k,j express k The standard curve j The amount of electricity at a point in time, Indicates the maximum output of the unit.

[0046] Optionally, the multiple groups of second power configuration results include multiple groups of target second power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple second profit values ​​corresponding to the multiple groups of target second power configuration results;

[0047] The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0048] Optionally, the second profit value is obtained according to the following calculation formula:

[0049] ;

[0050] in, J 2 represents the second profit value, T represents the preset number of cycles, D t Indicates that the target power supplier is t The frequency modulation mileage in response to the AGC control command in a preset cycle, Indicates that the target power provider is t The mileage settlement price for a preset period, K i,t Indicates the target power provider i In the t The average value of the comprehensive frequency modulation performance index in the preset period, Q i,f Indicates the target power provider i In the t The winning capacity in the preset period, represents the historical average node electricity price, C i Indicates the target power provider i The approved cost.

[0051] Optionally, the multiple groups of third power configuration results include multiple groups of target third power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple third profit values ​​corresponding to the multiple groups of target third power configuration results;

[0052] The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price;

[0053] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0054] Optionally, the third profit value is obtained according to the following calculation formula:

[0055] ;

[0056] in, J 3 represents the third profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the time point in the first mode j The clearing price of electricity, Indicates at a point in time j The unified settlement point electricity price, Indicates the target power provider i At the time point in the third mode j The winning bid quantity, Indicates the time point in the third mode j The clearing price.

[0057] In a second aspect, an embodiment of the present application further provides a device for determining a power parameter, the device for determining a power parameter comprising:

[0058] A first processing module, used to input multiple groups of power parameters into a preset power configuration model respectively to obtain multiple groups of power configuration results;

[0059] A first acquisition module, configured to acquire, from the plurality of groups of power configuration results, a plurality of groups of target power configuration results corresponding to the target power provider;

[0060] A first calculation module, used for calculating a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results;

[0061] A first determining module, configured to determine a target power parameter of the target power provider according to the multiple profit values;

[0062] Wherein, each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission rights configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power configuration results include at least two of multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, multiple groups of third power configuration results output by the third clearing model and multiple groups of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result;

[0063] The first power parameter includes the declared power quantity and declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode;

[0064] The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode;

[0065] The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode;

[0066] The fourth power configuration result includes whether to purchase financial transmission rights.

[0067] Optionally, the first clearing model includes a first objective function with the goal of minimizing the clearing electricity price under the first mode, a first constraint condition and a safe operation constraint condition;

[0068] The first objective function is:

[0069] ;

[0070] The first constraint condition includes:

[0071] ;

[0072] in, P zhong represents the clearing electricity price finally output by the first clearing model, P’ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l / P i,l Indicates the power provider i The winning bid is Q i,l The corresponding declared electricity price is P i,l , Q b i,l Indicates the power provider i The declared power in the first mode is: Q lD surface indicating the power demand in the first mode;

[0073] The safety operation constraints include:

[0074] ;

[0075] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ijActive power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0076] Optionally, the second clearing model includes a second objective function and a second constraint condition with the goal of minimizing the clearing electricity price under the second mode;

[0077] The second objective function is:

[0078] ;

[0079] The second constraint is:

[0080] ;

[0081] in, P f1 represents the clearing electricity price finally output by the second clearing model, P’ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme under the second mode, B i / Q i,f Indicates the power provider i The winning bid capacity is Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β 1 Indicates the lower limit requirement of capacity, β 2 Indicates the upper limit requirement of capacity. Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity under the second mode.

[0082] Optionally, the third clearing model includes a third objective function with the goal of minimizing the power generation cost under the third mode, a third constraint condition and a safe operation constraint condition;

[0083] The third objective function is:

[0084] ;

[0085] The third constraint condition is:

[0086] ;

[0087] in, B i,s Indicates the power provider i The power generation cost function under the third mode is: C i,0 Indicates the power provider i fixed costs, k i Indicates the power provider i The declared electricity price factor, Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity in the second mode is N express N Electricity providers, T express T time point;

[0088] The safety operation constraints are:

[0089] ;

[0090] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, yrepresents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0091] Optionally, the fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

[0092] Optionally, the multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results;

[0093] The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode;

[0094] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0095] Optionally, the first profit value is calculated according to the following calculation formula:

[0096] ;

[0097] in, J 1 represents the first profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the target power provider i At the time point in the first mode j The clearing price of electricity, Indicates the target power provider i At the point in time j The unified settlement point electricity price, M represents the penalty factor, Q' represents the target power provider i The expected power generation, n1 Indicates the number of time points, n 2 Indicates the number of contract days. Indicates the target power provider i Existing contracted electricity, N k Indicates the selection of k The number of standard curves, U k,j express k The standard curve j The amount of electricity at a point in time, Indicates the maximum output of the unit.

[0098] Optionally, the multiple groups of second power configuration results include multiple groups of target second power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple second profit values ​​corresponding to the multiple groups of target second power configuration results;

[0099] The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0100] Optionally, the second profit value is obtained according to the following calculation formula:

[0101] ;

[0102] in, J 2 represents the second profit value, T represents the preset number of cycles, D t Indicates that the target power supplier is t The frequency modulation mileage in response to the AGC control command in a preset cycle, Indicates that the target power provider is t The mileage settlement price for a preset period, K i,t Indicates the target power provider i In the t The average value of the comprehensive frequency modulation performance index in the preset period, Q i,f Indicates the target power provider i In the t The winning capacity in the preset period, represents the historical average node electricity price,C i Indicates the target power provider i The approved cost.

[0103] Optionally, the multiple groups of third power configuration results include multiple groups of target third power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple third profit values ​​corresponding to the multiple groups of target third power configuration results;

[0104] The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price;

[0105] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0106] Optionally, the third profit value is obtained according to the following calculation formula:

[0107] ;

[0108] in, J 3 represents the third profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the time point in the first mode j The clearing price of electricity, Indicates at a point in time j The unified settlement point electricity price, Indicates the target power provider i At the time point in the third mode j The winning bid quantity, Indicates the time point in the third mode j The clearing price.

[0109] In a third aspect, an embodiment of the present application further provides an electronic device, comprising a processor, a memory, and a computer program stored in the memory and executable on the processor, wherein the computer program implements the steps of the above-mentioned power parameter determination method when executed by the processor.

[0110] In a fourth aspect, an embodiment of the present application further provides a computer-readable storage medium, on which a computer program is stored, and when the computer program is executed by a processor, the steps of the above-mentioned method for determining power parameters are implemented.

[0111] In a fifth aspect, a computer program product is provided, comprising computer instructions, which, when executed by a processor, implement the steps of the method for determining power parameters as described in the first aspect.

[0112] The method for determining power parameters of an embodiment of the present application includes inputting multiple groups of power parameters into a preset power configuration model respectively to obtain multiple groups of power configuration results; obtaining multiple groups of target power configuration results corresponding to target power providers from the multiple groups of power configuration results; calculating multiple profit values ​​corresponding to the target power providers under the multiple groups of target power configuration results; and determining the target power parameters of the target power providers based on the multiple profit values; wherein each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission right configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, and the multiple groups of power configuration results include multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, and multiple groups of third power configuration results output by the third clearing model. and at least two of the multiple groups of fourth power configuration results output by the financial transmission rights configuration model, the input of the financial transmission rights configuration model is the third power configuration result; the first power parameter includes the declared power quantity and declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning power quantity of each of the multiple power providers in the first mode; the second power parameter includes the declared capacity and declared power price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing power price in the second mode and the winning power quantity of each of the multiple power providers in the second mode; the third power parameter includes the declared power price factor of each of the multiple power providers in the third mode, and the third power configuration result includes the clearing power price in the third mode and the winning power quantity of each of the multiple power providers in the third mode; the fourth power configuration result includes whether to purchase financial transmission rights. The method takes into account the close relationship between different power trading modes in the power market. The preset power configuration model is obtained by integrating at least two of the first clearing model, the second clearing model, the third clearing model and the financial transmission right model. The preset power configuration model is used to calculate the corresponding profit value of the target power provider under different power parameters, and then the calculated multiple profit values ​​are used to determine the optimal power parameters (i.e., target power parameters) of the target power provider. This power parameter determination method comprehensively considers the relationship between different power trading modes in the power market, thereby improving the overall economic benefits obtained by the target power provider. BRIEF DESCRIPTION OF THE DRAWINGS

[0113] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the description of the embodiments of the present application will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.

[0114] Figure 1 is a flow chart of a method for determining electric power parameters provided in an embodiment of the present application;

[0115] Figure 2 It is a schematic diagram of the relationship between various power trading modes provided in the embodiments of the present application;

[0116] Figure 3 is a schematic diagram of a method for determining power parameters provided in an embodiment of the present application;

[0117] Figure 4 is a structural diagram of a power parameter determination device provided in an embodiment of the present application;

[0118] Figure 5 It is a structural diagram of an electronic device provided in one embodiment of the present application. DETAILED DESCRIPTION

[0119] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0120] The present application embodiment provides a method for determining power parameters. Figure 1 , Figure 1 is a flow chart of a method for determining power parameters provided in an embodiment of the present application. Figure 1 As shown, the following steps are included:

[0121] Step 101: Input multiple groups of power parameters into a preset power configuration model to obtain multiple groups of power configuration results;

[0122] In this step, each set of power parameters includes power parameters of multiple power providers, and the power parameters here can be understood as the bidding strategy of the power provider. The preset power configuration model includes at least two of the first clearing model, the second clearing model, the third clearing model and the financial transmission rights configuration model. The multiple sets of power parameters include at least one of the multiple sets of first power parameters input into the first clearing model, the multiple sets of second power parameters input into the second clearing model and the multiple sets of third power parameters input into the third clearing model. The multiple sets of power configuration results include at least two of the multiple sets of first power configuration results output by the first clearing model, the multiple sets of second power configuration results output by the second clearing model, the multiple sets of third power configuration results output by the third clearing model and the multiple sets of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result.

[0123] The first clearing model can be understood as a medium- and long-term market clearing model. The first power parameter includes the declared power and declared power price of each power provider in the first mode. The first power configuration result includes the clearing power price in the first mode and the winning power of each power provider in the first mode. The first mode can be understood as a trading mode of the medium- and long-term market. Therefore, the multiple first power parameters can be understood as the quotation strategies of multiple power providers in the medium- and long-term market. The multiple first power configuration results can be understood as the power configuration results of multiple power providers in the medium- and long-term market obtained by combining the medium- and long-term market clearing model with the quotation strategies of multiple power providers in the medium- and long-term market. The medium- and long-term market mainly refers to the electric energy trading market with a cycle of more than several days. It plays the role of ballast and stabilizer and can help market players avoid price risks. The clearing power price in the medium- and long-term market refers to the price level that can achieve a balance between supply and demand in the medium- and long-term market.

[0124] The second clearing model can be understood as the frequency regulation auxiliary service market clearing model, the second power parameter includes the declared capacity and declared electricity price of each power provider in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid electricity of each power provider in the second mode. The second mode can be understood as the transaction mode of the frequency regulation auxiliary service market, so the multiple second power parameters can be understood as the quotation strategies of multiple power providers in the frequency regulation auxiliary service market, and the multiple second power configuration results can be understood as the power configuration results of multiple power providers in the frequency regulation auxiliary service market obtained by combining the frequency regulation auxiliary service market clearing model with the quotation strategies of multiple power providers in the frequency regulation auxiliary service market. The frequency regulation auxiliary service market aims to maintain the safe and stable operation of the power system. The frequency regulation auxiliary service refers to the service provided by the grid-connected entity to adjust the active output and reduce the frequency deviation through the speed regulation system, automatic power control and other means when the power system deviates from the target frequency. The clearing electricity price in the frequency regulation auxiliary service market refers to the price level that can achieve the balance between supply and demand in the frequency regulation auxiliary service market.

[0125] The third clearing model can be understood as a spot market clearing model, the third power parameter includes the declared electricity price factor of each of the multiple power providers in the third mode, and the third power configuration result includes the clearing electricity price in the third mode and the winning bid electricity of each of the multiple power providers in the third mode. The third mode can be understood as a trading mode of the spot market, so the multiple third power parameters can be understood as the quotation strategies of multiple power providers in the spot market, and the multiple third power configuration results can be understood as the power configuration results of multiple power providers in the spot market obtained by combining the spot market clearing model with the quotation strategies of multiple power providers in the spot market. The spot market refers to the day-ahead and real-time electric energy trading market, which can form a price signal with time and space characteristics that reflects market supply and demand, and guide the effective allocation of resources. The clearing electricity price in the spot market refers to the price level that can achieve a balance between supply and demand in the spot market.

[0126] Under the current electricity market system, users use a unified settlement point electricity price for settlement, and users who sign medium- and long-term contracts can completely avoid risks; while power providers (which can be understood as power generators) use node electricity prices for settlement, and their spot settlement prices are different from medium- and long-term settlement prices. Power generators that sign medium- and long-term contracts cannot completely avoid risks. In order to avoid the risk of node electricity price divergence caused by line congestion, financial transmission rights are introduced as a hedging tool in existing technologies. However, the introduction of financial transmission rights makes the electricity market faced by power providers more complicated, so whether to purchase financial transmission rights is an important consideration for power providers when making decisions in the electricity market.

[0127] Considering the impact of node electricity prices and unified settlement point electricity prices in the spot market on the benefits of financial transmission rights, and considering the role of financial transmission rights in avoiding blocking price risks, the impact of the electricity supplier's winning bid in the spot market on the demand for financial transmission rights. This step constructs a financial transmission rights model, inputs the third power allocation result corresponding to the third clearing model (i.e., the spot market clearing model) into the financial transmission rights model, and obtains the fourth power allocation result (i.e., determining whether to purchase financial transmission rights).

[0128] Step 102: Acquire multiple groups of target power configuration results corresponding to target power providers from the multiple groups of power configuration results;

[0129] In this step, specifically, multiple groups of target first power configuration results corresponding to the target power provider are obtained from the multiple groups of first power configuration results; multiple groups of target second power configuration results corresponding to the target power provider are obtained from the multiple groups of second power configuration results; multiple groups of target third power configuration results corresponding to the target power provider are obtained from the multiple groups of third power configuration results; and multiple groups of target fourth power configuration results corresponding to the target power provider are obtained from the multiple groups of fourth power configuration results.

[0130] Step 103, calculating a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results;

[0131] In this step, specifically, based on multiple sets of target first power configuration results, multiple first profit values ​​corresponding to the target power provider in the first mode (i.e., the medium- and long-term market) are calculated; based on multiple sets of target second power configuration results, multiple second profit values ​​corresponding to the target power provider in the second mode (i.e., the frequency regulation auxiliary service market) are calculated; based on multiple sets of target third power configuration results, multiple third profit values ​​corresponding to the target power provider in the third mode (i.e., the spot market) are calculated.

[0132] Step 104: determining the target power parameter of the target power provider according to the multiple profit values;

[0133] In this step, the target power provider can reversely infer its optimal power parameters (i.e., target power parameters) based on the possible power parameters of other power providers. Exemplarily, in the medium- and long-term market, the first power parameters corresponding to the target power provider may be A1 and A2, and the target power provider speculates that the first power parameters corresponding to other power providers may be B1 and B2. Then, the first power parameter combinations that exist include A1 and B1, A1 and B2, A2 and B1, and A2 and B2. These four first power parameter combinations are respectively input into the first clearing model (i.e., the medium- and long-term market clearing model), and four groups of first power configuration results can be obtained accordingly. The target power provider calculates its own profit value based on the medium- and long-term market clearing electricity price under each group of power configuration results and the winning bid electricity volume obtained by itself. Assume that when the first power parameter combination is A1 and B1, the profit value of the target power provider is 4; when the first power parameter combination is A1 and B2, the profit value of the target power provider is 6; when the first power parameter combination is A2 and B1, the profit value of the target power provider is 3; when the first power parameter combination is A2 and B2, the profit value of the target power provider is 9. Then when the first power parameter is A1, the target power provider obtains a profit mean of (4+6) / 2=5, and when the first power parameter is A2, the target power provider obtains a profit mean of (3+9) / 2=6. Then, in the medium and long-term market, the target first power parameter (i.e., target quotation strategy) of the target power provider is determined to be A2. The target power parameters of other markets are determined in the same way, which will not be repeated here. It should be noted that in addition to determining the target power parameters by the profit mean, according to practical needs, the target power parameters can also be determined by the maximum profit and other methods, which will not be repeated here.

[0134] In one embodiment, taking into account the close relationship between different power trading modes in the power market, a preset power configuration model is obtained by integrating at least two of the first clearing model, the second clearing model, the third clearing model and the financial transmission rights model. The preset power configuration model is used to calculate the corresponding profit value of the target power provider under different power parameters, and then the calculated multiple profit values ​​are used to determine the optimal power parameters (i.e., target power parameters) of the target power provider. This power parameter determination method comprehensively considers the relationship between different power trading modes in the power market, thereby improving the overall economic benefits obtained by the target power provider.

[0135] See also Figure 2, the power demand, bids and winning bids in different power markets will affect each other. Specifically, the impact of the medium- and long-term market on the spot market includes two aspects: (1) The winning bids in the medium- and long-term market will affect the supply in the spot market, because the total output of the power generator (i.e. the aforementioned power provider) at the same time is limited by its own power generation output. (2) The power demand in the medium- and long-term market should be lower than the total power demand in the spot market. The impact of the frequency regulation ancillary service market on the spot market is mainly in terms of the capacity of the spot market. The frequency regulation capacity won in the frequency regulation ancillary service market can no longer participate in the power trading in the spot market. The impact of the spot market clearing results on the decision-making of financial transmission rights mainly includes two aspects: (1) The node electricity price and the unified settlement point electricity price in the spot market affect the income of financial transmission rights. (2) Considering the role of financial transmission rights in avoiding blocking price risks, the winning bids in the spot market determine the demand for financial transmission rights of power generators.

[0136] Based on the relationship between the above-mentioned power markets, it is necessary to set relevant constraints for each clearing model so that the power allocation results obtained by each clearing model are more reasonable. For details, please refer to the following embodiments:

[0137] Optionally, the first clearing model includes a first objective function with the goal of minimizing the clearing electricity price under the first mode, a first constraint condition and a safe operation constraint condition;

[0138] The first objective function is:

[0139] ;

[0140] The first constraint condition includes:

[0141] ;

[0142] in, P zhong represents the clearing electricity price finally output by the first clearing model, P’ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l / P i,l Indicates the power provider i The winning bid is Q i,l The corresponding declared electricity price is P i,l , Q b i,l Indicates the power provider i The declared power in the first mode is: QlD surface indicating the power demand in the first mode;

[0143] The safety operation constraints include:

[0144] ;

[0145] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0146] In one implementation, the first mode can be understood as a medium- and long-term market trading mode. The medium- and long-term market adopts a centralized bidding transaction and marginal clearing mode, that is, the price of the last winning unit in the transaction is used as the medium- and long-term market clearing price. Each power provider declares the transaction volume and transaction price through the trading platform according to the standard transaction curve and transaction execution start and end time given in the transaction announcement.

[0147] According to the principle of maximizing social welfare, under the constraint of electricity demand, the first clearing model aims to minimize the clearing price. The specific clearing price can be determined as follows. For example, there are power providers A, B and C. A declares 3 kWh of electricity at a price of 0.1 yuan / kWh; B declares 5 kWh of electricity at a price of 0.2 yuan / kWh; C declares 5 kWh of electricity at a price of 0.3 yuan / kWh. The electricity demand in the medium and long term market is 5 kWh.

[0148] Then there are several power configuration schemes that can meet the power demand of the medium- and long-term market: Scheme 1: A is configured with 1 kWh, B is configured with 1 kWh, and C is configured with 3 kWh. At this time, the clearing price should be 0.3 yuan / kWh (i.e., the largest declared price in Scheme 1); Scheme 2: A is configured with 3 kWh, B is configured with 2 kWh, and C is configured with 0 kWh. At this time, the price should be 0.2 yuan / kWh (i.e., the largest declared price in Scheme 2). The medium- and long-term market clearing should choose the lowest price scheme, i.e., Scheme 2. Then the final power configuration result should be that A's winning bid is 3 kWh, B's winning bid is 2 kWh, and C's winning bid is 0 kWh. The final clearing price of the first clearing model should be 0.2 yuan / kWh.

[0149] In addition, it should be noted that medium- and long-term market clearing must also undergo safety verification by the dispatching department, and therefore must also meet the constraints on safe operation of the power grid.

[0150] This implementation method, through the setting of the first objective function, the first constraint condition and the safety constraint condition, is conducive to obtaining the first power configuration result that meets the medium- and long-term market demand and safe operation conditions through the first clearing model.

[0151] Optionally, the second clearing model includes a second objective function and a second constraint condition with the goal of minimizing the clearing electricity price under the second mode;

[0152] The second objective function is:

[0153] ;

[0154] The second constraint is:

[0155] ;

[0156] in, P f1 represents the clearing electricity price finally output by the second clearing model, P’ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme under the second mode, B i / Q i,f Indicates the power provider i The winning bid capacity is Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β 1 Indicates the lower limit requirement of capacity, β 2 Indicates the upper limit requirement of capacity. Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity under the second mode.

[0157] In one implementation, the second mode can be understood as a trading mode of the frequency regulation auxiliary service market. The frequency regulation auxiliary service market also adopts a centralized bidding transaction and marginal clearing mode, that is, the price of the last winning unit is used as the clearing price of the frequency regulation auxiliary service market. According to the principle of maximizing social welfare, under the constraint of frequency regulation demand, the second clearing model aims to minimize the clearing price.

[0158] With reference to the explanation of the above embodiment, P f1 It represents the clearing electricity price finally output by the frequency regulation ancillary service market clearing model, which is the smallest clearing electricity price among the clearing electricity prices corresponding to different winning bid electricity allocation schemes in the frequency regulation ancillary service market. P’ f1 It represents the clearing electricity price corresponding to each winning electricity allocation scheme in the frequency regulation auxiliary service market, which is the maximum declared electricity price in each winning electricity allocation scheme in the frequency regulation auxiliary service market.

[0159] This implementation method, through the setting of the second objective function and the second constraint condition, is conducive to obtaining the second power configuration result that meets the frequency regulation demand and satisfies the principle of maximizing social welfare through the second clearing model.

[0160] Optionally, the third clearing model includes a third objective function with the goal of minimizing the power generation cost under the third mode, a third constraint condition and a safe operation constraint condition;

[0161] The third objective function is:

[0162] ;

[0163] The third constraint condition is:

[0164] ;

[0165] in, B i,s Indicates the power provider i The power generation cost function under the third mode is: C i,0 Indicates the power provider i fixed costs, k i Indicates the power provider i The declared electricity price factor, Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity in the second mode is N express N Electricity providers, T express T time point;

[0166] The safety operation constraints are:

[0167] ;

[0168] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θrepresents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0169] In one implementation, the third mode can be understood as a spot market. The spot market will be cleared according to the minimization of the total power generation cost. At this time, the marginal cost quotation of the power provider is reduced to a quadratic cost function , a and b represent the coefficients of the quadratic function. The power generation cost function of the power provider reflects the relationship between the power provider's declared electricity price and the winning bid electricity quantity. For the power provider, different winning bid electricity quantities correspond to different declared electricity prices. To solve the minimization of the power generation cost, the variable to be optimized is the winning bid electricity quantity of the power provider. The output of the third clearing model is the winning bid electricity quantity and the clearing electricity price of the power provider in the spot market. The clearing electricity price is the increment of the power generation cost function when the node load of the power provider increases by one unit.

[0170] This implementation method is conducive to obtaining the second power configuration result that meets the unit output limitation and safe operation conditions through the third clearing model by setting the third objective function, the third constraint condition and the safety constraint condition.

[0171] Optionally, the fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

[0172] In one implementation, a financial transmission right market decision is made based on the clearing price of the spot market. Specifically, the difference between the unified settlement point electricity price and the clearing price of the spot market is calculated. If the difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased, and if the difference is less than the financial transmission right price, the financial transmission right is not purchased.

[0173] In this implementation, the impact of node electricity prices and unified settlement point electricity prices in the spot market on the revenue of financial transmission rights is taken into account, as well as the role of financial transmission rights in avoiding blocking price risks, and the impact of the power supplier's winning bid volume in the spot market on the demand for financial transmission rights. In the multi-market joint bidding decision, the financial transmission rights market is placed at the last decision, which is conducive to improving the accuracy of determining the financial transmission rights market decision.

[0174] Optionally, the multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results;

[0175] The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode;

[0176] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0177] In one implementation, the first profit value can be determined based on parameters such as the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider in the medium and long-term market. The present application adopts the method of sequential equilibrium to perform strategy optimization in each market, and uses the optimization results of the previous market as the initial conditions for the next market, and finally obtains the strategy optimization results for all markets. When the strategy optimization enters the medium and long-term market part, the price data of the historical spot market, the financial transmission rights market, and the frequency regulation auxiliary service market are known. Therefore, in this implementation, the unified settlement point electricity price to be used in calculating the first profit value of the target power provider in the medium and long-term market can be determined based on the electricity data in the historical spot market.

[0178] This implementation method calculates multiple first profit values ​​corresponding to multiple groups of target first power configuration results of the target power provider, which is conducive to the subsequent selection of optimal power parameters based on the multiple first profit values.

[0179] Optionally, the first profit value is calculated according to the following calculation formula:

[0180] ;

[0181] in, J 1 represents the first profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the target power provideri At the time point in the first mode j The clearing price of electricity, Indicates the target power provider i At the point in time j The unified settlement point electricity price, M represents the penalty factor, Q' represents the target power provider i The expected power generation, n 1 Indicates the number of time points, n 2 Indicates the number of contract days. Indicates the target power provider i Existing contracted electricity, N k Indicates the selection of k The number of standard curves, U k,j express k The standard curve j The amount of electricity at a point in time, Indicates the maximum output of the unit.

[0182] In one implementation, market entities declare transaction volume and transaction price through the trading platform according to the standard transaction curve and transaction execution start and end time given in the transaction announcement. The trading institution clears according to high-low matching or unified margin. The specific clearing method is subject to the transaction announcement, and the transaction result is formed after transaction verification. The centralized bidding transaction method adopts standardized curves (D1 / D2 / D3). Under the condition of ensuring that the maximum load is not exceeded, three standard curves of different numbers are selected to make the average price per kilowatt-hour the highest. This implementation method introduces medium- and long-term target curves for settlement in the benefit-first mode to maximize the profit of the target power provider.

[0183] This implementation method calculates the first profit value through the above calculation formula, which is conducive to improving the accuracy of the calculated first profit value.

[0184] Optionally, the multiple groups of second power configuration results include multiple groups of target second power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple second profit values ​​corresponding to the multiple groups of target second power configuration results;

[0185] The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0186] In one embodiment, the second profit value can be determined based on parameters such as the frequency regulation mileage of the target power provider in response to the Automatic Generation Control (AGC) instruction in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance index of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0187] This implementation method calculates multiple second profit values ​​corresponding to multiple groups of target second power configuration results of the target power provider, which is conducive to the subsequent selection of optimal power parameters based on the multiple second profit values.

[0188] Optionally, the second profit value is obtained according to the following calculation formula:

[0189] ;

[0190] in, J 2 represents the second profit value, T represents the preset number of cycles, D t Indicates that the target power supplier is t The frequency modulation mileage in response to the AGC control command in a preset cycle, Indicates that the target power provider is t The mileage settlement price for a preset period, K i,t Indicates the target power provider i In the t The average value of the comprehensive frequency modulation performance index in the preset period, Q i,f Indicates the target power provider i In the t The winning capacity in the preset period, represents the historical average node electricity price, C i Indicates the target power provider i The approved cost.

[0191] This implementation method calculates the second profit value through the above calculation formula, which is conducive to improving the accuracy of the calculated second profit value.

[0192] Optionally, the multiple groups of third power configuration results include multiple groups of target third power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple third profit values ​​corresponding to the multiple groups of target third power configuration results;

[0193] The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price;

[0194] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0195] In one implementation, the third profit value can be determined based on parameters such as the target power provider's winning bid volume in the medium- and long-term market, the clearing price in the medium- and long-term market, the target power provider's winning bid volume in the spot market, the clearing price in the spot market, and the unified settlement point electricity price.

[0196] This implementation method calculates multiple third profit values ​​corresponding to multiple groups of target third power configuration results of the target power provider, which is conducive to the subsequent selection of optimal power parameters based on the multiple third profit values.

[0197] Optionally, the third profit value is obtained according to the following calculation formula:

[0198] ;

[0199] in, J 3 represents the third profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the time point in the first mode j The clearing price of electricity, Indicates at a point in time j The unified settlement point electricity price, Indicates the target power provider i At the time point in the third mode j The winning bid quantity, Indicates the time point in the third mode j The clearing price.

[0200] In one implementation, the following constraints need to be considered when calculating the third profit value:

[0201] (1) Minimum and maximum technical output constraints of the unit:

[0202] ;

[0203] (2) Constraints on the output interval between the front and rear sections:

[0204] ;

[0205] The spot market linearizes the curve reported by the power provider, y represents the number of segments into which the power price reported by the power provider is divided, and α represents the output interval constraint parameter of the front and rear segments.

[0206] (3) The lower limit of the price of the first segment = 0, and the upper limit of the price of the nth segment is not greater than P max :

[0207] ;

[0208] (4) Unit cost constraints:

[0209] ;

[0210] in, f(Q) is the marginal cost function of the unit, which is a concave quadratic function about the unit output Q; a, b, c represent the coefficients of the quadratic function.

[0211] (5) Unit output climbing constraints

[0212] ;

[0213] This implementation method calculates the third profit value through the above calculation formula, which is conducive to improving the accuracy of the calculated third profit value.

[0214] In one embodiment, see Figure 3 , Figure 3 The figure is a schematic diagram of the method for determining power parameters. A medium- and long-term market clearing model is constructed based on multiple boundary parameters in the medium- and long-term market. The power parameters of each power provider (including the declared power quantity and the declared power price) are input into the medium- and long-term market clearing model to obtain the clearing price in the medium- and long-term market and the winning power quantity of each power provider. The target power provider calculates its profit value based on the clearing price in the medium- and long-term market and the winning power quantity it obtains, thereby continuously optimizing its power parameters in the medium- and long-term market.

[0215] Based on multiple boundary parameters and historical electricity price data of the frequency regulation ancillary service market, a frequency regulation ancillary service market clearing model is constructed. The power parameters of each power provider (including declared capacity and declared electricity price) are input into the frequency regulation ancillary service market clearing model to obtain the clearing price in the frequency regulation ancillary service market and the winning capacity of each power provider. The target power provider calculates its profit value based on the clearing price in the frequency regulation ancillary service market and the winning capacity it obtains, and then continuously optimizes its power parameters in the frequency regulation ancillary service market.

[0216] A spot market clearing model is constructed based on multiple boundary parameters of the spot market. The power parameters of each power provider (including declared electricity volume and declared electricity price) are input into the spot market clearing model to obtain the clearing price in the spot market and the winning electricity volume of each power provider. The target power provider calculates its profit value based on the clearing price in the spot market and the winning electricity volume it obtains, and then continuously optimizes its power parameters in the spot market.

[0217] A financial transmission rights allocation model is constructed based on multiple boundary parameters of the financial transmission rights market. The clearing price in the spot market output by the spot market clearing model and the winning bid volume of the target power provider are input into the financial transmission rights allocation model, so that the target power provider can determine whether to purchase the financial transmission rights.

[0218] After the target power provider determines the target power parameters, the actual profit value can be calculated based on the following calculation formula:

[0219] (1) The profit in the medium and long term market is:

[0220] ;

[0221] in: π i,l Indicates the actual profit value of the target power provider in the medium and long term market, P zhong,i represents the clearing price of the medium and long term market, represents the unified settlement point electricity price, Q zhong,i The amount of electricity won by the target electricity provider in the medium and long-term market.

[0222] (2) In the frequency regulation ancillary service market, the target power provider can obtain two parts of income, one is the frequency regulation capacity income; the other is the frequency regulation mileage income. Frequency regulation capacity refers to the unit capacity declared by the target power provider to provide frequency regulation. The total frequency regulation mileage in a certain period of time is the sum of the adjustment mileage of the power generation units in response to the AGC control command during that period. Specifically, the actual profit value of the target power provider in the frequency regulation ancillary service market is:

[0223] ;

[0224] in, π i,f1 represents the frequency regulation mileage income of the target power provider, T represents the number of transaction cycles, D t Indicates that the target power supplier is t Frequency modulation mileage responding to AGC control instructions in a transaction cycle, Indicates t Mileage settlement price for a transaction cycle, K i,t Indicates that the target power supplier is t The average value of comprehensive frequency modulation performance indicators in a trading cycle.

[0225] ;

[0226] in, π i,f2 Indicates the frequency regulation capacity compensation obtained by the target power supplier, Q i,f Indicates that the target power supplier is t The frequency modulation capacity won in the trading cycle, represents the historical average node electricity price, C i Represents the approved cost of the target electricity provider.

[0227] (3) The path of the financial transmission rights purchased by the target power provider is the node where the target power provider is located. i At the unified settlement point, the actual profit value in the spot market and the financial transmission rights market is:

[0228] ;

[0229] ;

[0230] in, π i,s Indicates the actual profit value of the spot market obtained by the target power supplier. Q riqian,i Indicates the target power supplier's winning bid in the spot market. P riqian,i represents the clearing price of electricity in the spot market, π i,FIR It represents the actual profit value of the target power supplier for purchasing the financial transmission right. Q i,FIR represents the amount of financial transmission rights purchased by the target power supplier, P FIR represents the price of financial transmission rights, Indicates the unified settlement point electricity price.

[0231] The overall profit value of the target electricity provider is:

[0232] π i = π i,l + π i,f1 + π i,f2 + π i,s + π i,FIR ;

[0233] In the present application, taking into account the close relationship between different power trading modes in the power market, the preset power configuration model is obtained by integrating at least two of the first clearing model, the second clearing model, the third clearing model and the financial transmission rights model. The preset power configuration model is used to calculate the corresponding profit value of the target power provider under different power parameters, and then the multiple profit values ​​calculated are used to determine the optimal power parameters (i.e., target power parameters) of the target power provider. This power parameter determination method comprehensively considers the relationship between different power trading modes in the power market, thereby improving the overall economic benefits obtained by the target power provider.

[0234] See also Figure 4 , Figure 4 is a structural diagram of a power parameter determination device provided in an embodiment of the present application. Figure 4 As shown, the power parameter determination device 400 includes:

[0235] The first processing module 401 is used to input multiple groups of power parameters into a preset power configuration model to obtain multiple groups of power configuration results;

[0236] A first acquisition module 402, configured to acquire, from the plurality of groups of power configuration results, a plurality of groups of target power configuration results corresponding to a target power provider;

[0237] A first calculation module 403 is used to calculate a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results;

[0238] A first determining module 404, configured to determine a target power parameter of the target power provider according to the multiple profit values;

[0239] Wherein, each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission rights configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power configuration results include at least two of multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, multiple groups of third power configuration results output by the third clearing model and multiple groups of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result;

[0240] The first power parameter includes the declared power quantity and declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode;

[0241] The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode;

[0242] The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode;

[0243] The fourth power configuration result includes whether to purchase financial transmission rights.

[0244] Optionally, the first clearing model includes a first objective function with the goal of minimizing the clearing electricity price under the first mode, a first constraint condition and a safe operation constraint condition;

[0245] The first objective function is:

[0246] ;

[0247] The first constraint condition includes:

[0248] ;

[0249] in, Pzhong represents the clearing electricity price finally output by the first clearing model, P’ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l / P i,l Indicates the power provider i The winning bid is Q i,l The corresponding declared electricity price is P i,l , Q b i,l Indicates the power provider i The declared power in the first mode is: Q lD surface indicating the power demand in the first mode;

[0250] The safety operation constraints include:

[0251] ;

[0252] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0253] Optionally, the second clearing model includes a second objective function and a second constraint condition with the goal of minimizing the clearing electricity price under the second mode;

[0254] The second objective function is:

[0255] ;

[0256] The second constraint is:

[0257] ;

[0258] in, P f1 represents the clearing electricity price finally output by the second clearing model, P’ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme under the second mode, B i / Q i,f Indicates the power provider i The winning bid capacity is Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β 1 Indicates the lower limit requirement of capacity, β 2 Indicates the upper limit requirement of capacity. Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity under the second mode.

[0259] Optionally, the third clearing model includes a third objective function with the goal of minimizing the power generation cost under the third mode, a third constraint condition and a safe operation constraint condition;

[0260] The third objective function is:

[0261] ;

[0262] The third constraint condition is:

[0263] ;

[0264] in, B i,s Indicates the power provider i The power generation cost function under the third mode is: C i,0 Indicates the power provider i fixed costs, k i Indicates the power provider i The declared electricity price factor, Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity in the second mode is N express N Electricity providers, T express T time point;

[0265] The safety operation constraints are:

[0266] ;

[0267] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformersj , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0268] Optionally, the fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

[0269] Optionally, the multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results;

[0270] The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode;

[0271] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0272] Optionally, the first profit value is calculated according to the following calculation formula:

[0273] ;

[0274] in, J 1 represents the first profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the target power provider i At the time point in the first mode j The clearing price of electricity, Indicates the target power provider i At the point in time j The unified settlement point electricity price, M represents the penalty factor, Q' represents the target power provider i The expected power generation, n 1 Indicates the number of time points, n 2 Indicates the number of contract days. Indicates the target power provider i Existing contracted electricity, N k Indicates the selection of k The number of standard curves, U k,j express k The standard curve j The amount of electricity at a point in time, Indicates the maximum output of the unit.

[0275] Optionally, the multiple groups of second power configuration results include multiple groups of target second power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple second profit values ​​corresponding to the multiple groups of target second power configuration results;

[0276] The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0277] Optionally, the second profit value is obtained according to the following calculation formula:

[0278] ;

[0279] in, J 2 represents the second profit value, T represents the preset number of cycles, D t Indicates that the target power supplier is t The frequency modulation mileage in response to the AGC control command in a preset cycle, Indicates that the target power provider is t The mileage settlement price for a preset period, K i,t Indicates the target power provider i In the t The average value of the comprehensive frequency modulation performance index in the preset period, Q i,f Indicates the target power provider i In the t The winning capacity in the preset period, represents the historical average node electricity price, C i Indicates the target power provider i The approved cost.

[0280] Optionally, the multiple groups of third power configuration results include multiple groups of target third power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple third profit values ​​corresponding to the multiple groups of target third power configuration results;

[0281] The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price;

[0282] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0283] Optionally, the third profit value is obtained according to the following calculation formula:

[0284] ;

[0285] in, J 3 represents the third profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the time point in the first mode j The clearing price of electricity, Indicates at a point in time j The unified settlement point electricity price, Indicates the target power provider i At the time point in the third mode j The winning bid quantity, Indicates the time point in the third mode j The clearing price.

[0286] See also Figure 5 , Figure 5 is a structural diagram of an electronic device provided by an embodiment of the present application, such as Figure 5 As shown, the electronic device includes: a processor 501 , a communication interface 502 , a communication bus 504 and a memory 503 , wherein the processor 501 , the communication interface 502 and the memory 503 interact with each other via the communication bus 504 .

[0287] Among them, the memory 503 is used to store computer programs; the processor 501 is used to execute the programs stored in the memory 503, and when the calculator program is executed by the processor 501: the processor 501 is used to input multiple groups of power parameters into the preset power configuration model respectively to obtain multiple groups of power configuration results; obtain multiple groups of target power configuration results corresponding to the target power provider from the multiple groups of power configuration results; calculate the multiple profit values ​​corresponding to the target power provider under the multiple groups of target power configuration results; determine the target power parameters of the target power provider based on the multiple profit values; wherein each group of power parameters includes power parameters of multiple power providers, and the preset power configuration model includes a first clearing model, at least two of a second clearing model, a third clearing model and a financial transmission rights allocation model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power allocation results include at least two of multiple groups of first power allocation results output by the first clearing model, multiple groups of second power allocation results output by the second clearing model, multiple groups of third power allocation results output by the third clearing model and multiple groups of fourth power allocation results output by the financial transmission rights allocation model, and the input of the financial transmission rights allocation model is the third power allocation result;

[0288] The first power parameter includes the declared power quantity and declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode;

[0289] The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode;

[0290] The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode;

[0291] The fourth power configuration result includes whether to purchase financial transmission rights.

[0292] Optionally, the first clearing model includes a first objective function with the goal of minimizing the clearing electricity price under the first mode, a first constraint condition and a safe operation constraint condition;

[0293] The first objective function is:

[0294] ;

[0295] The first constraint condition includes:

[0296] ;

[0297] in, P zhong represents the clearing electricity price finally output by the first clearing model, P’ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l / P i,l Indicates the power provider i The winning bid is Q i,l The corresponding declared electricity price is P i,l , Q b i,l Indicates the power provider i The declared power in the first mode is: Q lD surface indicating the power demand in the first mode;

[0298] The safety operation constraints include:

[0299] ;

[0300] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider i The reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θrepresents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0301] Optionally, the second clearing model includes a second objective function and a second constraint condition with the goal of minimizing the clearing electricity price under the second mode;

[0302] The second objective function is:

[0303] ;

[0304] The second constraint is:

[0305] ;

[0306] in, P f1 represents the clearing electricity price finally output by the second clearing model, P’ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme under the second mode, B i / Q i,f Indicates the power provider i The winning bid capacity is Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β 1 Indicates the lower limit requirement of capacity, β 2 Indicates the upper limit requirement of capacity. Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity under the second mode.

[0307] Optionally, the third clearing model includes a third objective function with the goal of minimizing the power generation cost under the third mode, a third constraint condition and a safe operation constraint condition;

[0308] The third objective function is:

[0309] ;

[0310] The third constraint condition is:

[0311] ;

[0312] in, B i,s Indicates the power provider i The power generation cost function under the third mode is: C i,0 Indicates the power provider i fixed costs, k i Indicates the power provider i The declared electricity price factor, Indicates the maximum output of the unit. Indicates the minimum output of the unit. Q i Indicates the power provider i The sum of the winning bid electricity in the first mode and the winning bid electricity in the third mode, Q i,f Indicates the power provider i The winning bid capacity in the second mode is N express N Electricity providers, T express T time point;

[0313] The safety operation constraints are:

[0314] ;

[0315] in, P Gi Indicates the power provider i The active power output at the node, P Di Indicates the power provider i The active load at the node, Q Gi Indicates the power provider i The reactive power output at the node, Q Di Indicates the power provider iThe reactive load at the node, V i Indicates the power provider i The voltage amplitude at the node, V Represents the voltage amplitude set of all nodes in the power system ,θ represents the phase angle set of voltages at all nodes in the power system, y represents the set of grid branch parameters, j∈i Represents all and nodes i Nodes connected by transmission lines or transformers j , P ij Indicates line ij Active power transmitted ,Q ij Indicates line ij The reactive power transmitted.

[0316] Optionally, the fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

[0317] Optionally, the multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results;

[0318] The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode;

[0319] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0320] Optionally, the first profit value is calculated according to the following calculation formula:

[0321] ;

[0322] in, J 1 represents the first profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the target power provider i At the time point in the first modej The clearing price of electricity, Indicates the target power provider i At the point in time j The unified settlement point electricity price, M represents the penalty factor, Q' represents the target power provider i The expected power generation, n 1 Indicates the number of time points, n 2 Indicates the number of contract days. Indicates the target power provider i Existing contracted electricity, N k Indicates the selection of k The number of standard curves, U k,j express k The standard curve j The amount of electricity at a point in time, Indicates the maximum output of the unit.

[0323] Optionally, the multiple groups of second power configuration results include multiple groups of target second power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple second profit values ​​corresponding to the multiple groups of target second power configuration results;

[0324] The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

[0325] Optionally, the second profit value is obtained according to the following calculation formula:

[0326] ;

[0327] in, J 2 represents the second profit value, T represents the preset number of cycles, D t Indicates that the target power supplier is t The frequency modulation mileage in response to the AGC control command in a preset cycle, Indicates that the target power provider is t The mileage settlement price for a preset period, K i,t Indicates the target power provideri In the t The average value of the comprehensive frequency modulation performance index in the preset period, Q i,f Indicates the target power provider i In the t The winning capacity in the preset period, represents the historical average node electricity price, C i Indicates the target power provider i The approved cost.

[0328] Optionally, the multiple groups of third power configuration results include multiple groups of target third power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple third profit values ​​corresponding to the multiple groups of target third power configuration results;

[0329] The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price;

[0330] The unified settlement point electricity price is determined based on historical electricity data under the third mode.

[0331] Optionally, the third profit value is obtained according to the following calculation formula:

[0332] ;

[0333] in, J 3 represents the third profit value, Indicates the target power provider i At the time point in the first mode j The winning bid quantity, Indicates the time point in the first mode j The clearing price of electricity, Indicates at a point in time j The unified settlement point electricity price, Indicates the target power provider i At the time point in the third mode j The winning bid quantity, Indicates the time point in the third mode j The clearing price.

[0334] The embodiment of the present application also provides a computer-readable storage medium, on which a computer program is stored, and when the computer program is executed by a processor, each process of the above-mentioned power parameter determination method embodiment is implemented, and the same technical effect can be achieved. To avoid repetition, it is not repeated here. The computer-readable storage medium is, for example, a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.

[0335] The present application also provides a computer program product, including computer instructions, which, when executed by a processor, implement the above Figure 1 The various processes of the method embodiment shown can achieve the same technical effect, and will not be described again here to avoid repetition.

[0336] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, article or device including the element.

[0337] Through the description of the above implementation methods, those skilled in the art can clearly understand that the above-mentioned embodiment methods can be implemented by means of software plus a necessary general hardware platform, and of course by hardware, but in many cases the former is a better implementation method. Based on such an understanding, the technical solution of the present application, or the part that contributes to the prior art, can be embodied in the form of a software product, which is stored in a storage medium (such as ROM / RAM, a magnetic disk, or an optical disk), and includes a number of instructions for a terminal (which can be a mobile phone, a computer, a server, an air conditioner, or a network device, etc.) to execute the methods described in each embodiment of the present application.

[0338] The embodiments of the present application are described above in conjunction with the accompanying drawings, but the present application is not limited to the above-mentioned specific implementation methods. The above-mentioned specific implementation methods are merely illustrative and not restrictive. Under the guidance of the present application, ordinary technicians in this field can also make many forms without departing from the purpose of the present application and the scope of protection of the claims, all of which are within the protection of the present application.

Claims

1. A method for determining power parameters, characterized in that: The method comprises: Inputting multiple sets of power parameters into a preset power configuration model respectively to obtain multiple sets of power configuration results; Acquire multiple groups of target power configuration results corresponding to target power providers from the multiple groups of power configuration results; Calculating a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results; Determining a target power parameter of the target power provider according to the multiple profit values, wherein the target power parameter is used to input the preset power configuration model to obtain a target power configuration result corresponding to the target power provider; Wherein, each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission rights configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power configuration results include at least two of multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, multiple groups of third power configuration results output by the third clearing model and multiple groups of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result; The first power parameter includes the declared power quantity and the declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode; The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode; The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode; The fourth power allocation result includes whether to purchase financial transmission rights; The first clearing model includes a first constraint condition and a safe operation constraint condition, and the first constraint condition includes: P′ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l P i,l It means that the power supplier i has a winning bid of Q i,l The corresponding declared electricity price is P i,l , represents the reported power quantity of power provider i in the first mode, Q lD Indicates the power demand in the first mode; The safety operation constraints include: Among them, P Gi represents the active power output at the node where the power provider i is located, P Di represents the active load at the node where the power provider i is located, Q Gi represents the reactive power output at the node where the power provider i is located, Q Di represents the reactive load at the node where the power provider i is located, V i represents the voltage amplitude at the node where the power provider i is located, V represents the voltage amplitude set of all nodes in the power system, θ represents the voltage phase angle set of all nodes in the power system, y represents the grid branch parameter set, j∈i represents all nodes j connected to node i through transmission lines or transformers, P ij represents the active power transmitted by line ij, Q ij Represents the reactive power transmitted by line ij; The second clearing model includes a second constraint condition, and the second constraint condition includes: Among them, P f1 represents the final clearing price of the second clearing model, P′ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme in the second mode, B i Q i,f It means that the power supplier i has a winning bid capacity of Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β1 represents the lower limit requirement of capacity, β2 represents the upper limit requirement of capacity, Indicates the maximum output of the unit. Indicates the minimum output of the unit, Q i represents the sum of the winning bid quantity of power provider i in the first mode and the winning bid quantity in the third mode, Q i,f represents the winning bid capacity of power provider i in the second mode; The third clearing model includes a third constraint condition and the safe operation constraint condition, and the third constraint condition includes: The third constraint condition is: Among them, B i,s represents the power generation cost function of the power provider i in the third mode, C i,0 represents the fixed cost of electricity provider i, k i represents the declared electricity price factor of power supplier i, Indicates the maximum output of the unit. Indicates the minimum output of the unit, Q i represents the sum of the winning bid quantity of power provider i in the first mode and the winning bid quantity in the third mode, Q i,f represents the winning bid capacity of power provider i in the second mode, N represents N power providers, and T represents T time points; The fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

2. The method for determining electric power parameters according to claim 1, characterized in that: The first clearing model includes a first objective function and a first constraint condition with the goal of minimizing the clearing electricity price under the first mode; The first objective function is: P zhong =min P′ zhong (Q 1,l |P 1,l ,…,Q i,l |P i,l ,…,Q N,l |P 1N,l ); Among them, P zhong represents the final clearing price output by the first clearing model, Q i,l |P i,l It means that the power supplier i has a winning bid of Q i,l The corresponding declared electricity price is P i,l .

3. The method for determining electric power parameters according to claim 1, characterized in that: The second clearing model includes a second objective function with the goal of minimizing the clearing electricity price under the second mode; The second objective function is: P f1 =min P′ f1 (B1,…,B i ,…,B N ); Among them, P f1 represents the final clearing price output by the second clearing model, B i |Q i,f It means that the power supplier i has a winning bid capacity of Q i,f The corresponding declared electricity price is B i .

4. The method for determining electric power parameters according to claim 1, characterized in that: The third clearing model includes a third objective function and a third constraint condition with the goal of minimizing the power generation cost under the third mode; The third objective function is: Among them, B i,s represents the power generation cost function of the power provider i in the third mode, Q i represents the sum of the successful bid electricity of power provider i in the first mode and the successful bid electricity in the third mode, N represents N power providers, and T represents T time points.

5. The method for determining electric power parameters according to claim 2, characterized in that: The multiple groups of first power configuration results include multiple groups of target first power configuration results corresponding to the target power providers, and the multiple profit values ​​include multiple first profit values ​​corresponding to the multiple groups of target first power configuration results; The first profit value is determined based on the following parameters: the target first power configuration result, the unified settlement point electricity price, the penalty factor, and the expected power generation of the target power provider under the first mode; The unified settlement point electricity price is determined based on historical electricity data under the third mode.

6. The method for determining electric power parameters according to claim 5, characterized in that: The first profit value is calculated according to the following calculation formula: Among them, J1 represents the first profit value, represents the winning bid quantity of target power provider i at time point j in the first mode, represents the clearing electricity price of the target power supplier i at time point j in the first mode, represents the unified settlement point electricity price of the target power provider i at time point j, M represents the penalty factor, Q' represents the expected power generation of the target power provider i, n1 represents the number of time points, n2 represents the number of contract days, and P' d,j represents the contracted electricity quantity of the target power supplier i, N k Indicates the number of selected k-th standard curves, U k,j represents the charge at the jth time point of the k-type standard curve, P i max Indicates the maximum output of the unit.

7. The method for determining electric power parameters according to claim 3, characterized in that: The plurality of groups of second power configuration results include a plurality of groups of target second power configuration results corresponding to the target power providers, and the plurality of profit values ​​include a plurality of second profit values ​​corresponding to the plurality of groups of target second power configuration results; The second profit value is determined based on the following parameters respectively: the frequency regulation mileage of the target power provider in response to the automatic power generation control AGC instructions in multiple preset periods, the mileage settlement price of the target power provider in the multiple preset periods, the average value of the comprehensive frequency regulation performance indicators of the target power provider in the multiple preset periods, the winning capacity of the target power provider in the multiple preset periods, the historical average node electricity price and the approved cost of the target power provider.

8. The method for determining electric power parameters according to claim 7, characterized in that: The second profit value is obtained according to the following calculation formula: Among them, J2 represents the second profit value, T represents the preset cycle number, and D t represents the frequency modulation mileage of the target power provider in response to the AGC control command in the tth preset cycle, P t f1 represents the mileage settlement price of the target power provider in the tth preset period, K i,t represents the average value of the comprehensive frequency regulation performance index of the target power provider i in the tth preset period, Q i,f represents the winning bid capacity of the target power provider i in the tth preset period, represents the historical average node electricity price, C i represents the approved cost of the target electricity provider i.

9. The method for determining electric power parameters according to claim 4, characterized in that: The plurality of sets of third power configuration results include a plurality of sets of target third power configuration results corresponding to the target power providers, and the plurality of profit values ​​include a plurality of third profit values ​​corresponding to the plurality of sets of target third power configuration results; The third profit value is determined based on the following parameters: the winning bid quantity of the target power supplier in the first mode, the clearing price in the first mode, the winning bid quantity of the target power supplier in the third mode, the clearing price in the third mode, and the unified settlement point electricity price; The unified settlement point electricity price is determined based on historical electricity data under the third mode.

10. The method for determining electric power parameters according to claim 9, characterized in that: The third profit value is obtained according to the following calculation formula: Among them, J3 represents the third profit value, represents the winning bid quantity of target power provider i at time point j in the first mode, represents the clearing electricity price at time point j in the first mode, represents the unified settlement point electricity price at time point j, represents the winning bid power of the target power provider i at time point j in the third mode, Represents the clearing price at time point j in the third mode.

11. A device for determining electric power parameters, characterized in that: The device comprises: A first processing module, used to input multiple groups of power parameters into a preset power configuration model respectively to obtain multiple groups of power configuration results; A first acquisition module, configured to acquire, from the plurality of groups of power configuration results, a plurality of groups of target power configuration results corresponding to the target power provider; A first calculation module, used for calculating a plurality of profit values ​​corresponding to the target power provider under the plurality of sets of target power configuration results; A first determining module, configured to determine a target power parameter of the target power provider according to the multiple profit values; Wherein, each group of power parameters includes power parameters of multiple power providers, the preset power configuration model includes at least two of a first clearing model, a second clearing model, a third clearing model and a financial transmission rights configuration model, the multiple groups of power parameters include at least one of multiple groups of first power parameters input into the first clearing model, multiple groups of second power parameters input into the second clearing model and multiple groups of third power parameters input into the third clearing model, the multiple groups of power configuration results include at least two of multiple groups of first power configuration results output by the first clearing model, multiple groups of second power configuration results output by the second clearing model, multiple groups of third power configuration results output by the third clearing model and multiple groups of fourth power configuration results output by the financial transmission rights configuration model, and the input of the financial transmission rights configuration model is the third power configuration result; The first power parameter includes the declared power quantity and the declared power price of each of the multiple power providers in the first mode, and the first power configuration result includes the clearing power price in the first mode and the winning bid power quantity of each of the multiple power providers in the first mode; The second power parameters include the declared capacity and declared electricity price of each of the multiple power providers in the second mode, and the second power configuration result includes the clearing electricity price in the second mode and the winning bid power of each of the multiple power providers in the second mode; The third power parameter includes a declared power price factor of each power provider among the multiple power providers in the third mode, and the third power configuration result includes a clearing power price in the third mode and a winning bid power of each power provider among the multiple power providers in the third mode; The fourth power allocation result includes whether to purchase financial transmission rights; The first clearing model includes a first constraint condition and a safe operation constraint condition, and the first constraint condition includes: P′ zhong represents the clearing electricity price corresponding to each winning electricity allocation scheme under the first mode, Q i,l P i,l It means that the power supplier i has a winning bid of Q i,l The corresponding declared electricity price is P i,l , represents the reported power quantity of power provider i in the first mode, Q lD Indicates the power demand in the first mode; The safety operation constraints include: Among them, P Gi represents the active power output at the node where the power provider i is located, P Di represents the active load at the node where the power provider i is located, Q Gi represents the reactive power output at the node where the power provider i is located, Q Di represents the reactive load at the node where the power provider i is located, V i represents the voltage amplitude at the node where the power provider i is located, V represents the voltage amplitude set of all nodes in the power system, θ represents the voltage phase angle set of all nodes in the power system, y represents the grid branch parameter set, j∈i represents all nodes j connected to node i through transmission lines or transformers, P ij represents the active power transmitted by line ij, Q ij Represents the reactive power transmitted by line ij; The second clearing model includes a second constraint condition, and the second constraint condition includes: Among them, P f1 represents the final clearing price of the second clearing model, P′ f1 represents the clearing electricity price corresponding to each winning electricity allocation scheme in the second mode, B i |Q i,f It means that the power supplier i has a winning bid capacity of Q i,f The corresponding declared electricity price is B i , F D represents the power demand in the second mode, β1 represents the lower limit requirement of capacity, β2 represents the upper limit requirement of capacity, Indicates the maximum output of the unit. Indicates the minimum output of the unit, Q i represents the sum of the winning bid quantity of power provider i in the first mode and the winning bid quantity in the third mode, Q i,f represents the winning bid capacity of power provider i in the second mode; The third clearing model includes a third constraint condition and the safe operation constraint condition, and the third constraint condition includes: The third constraint condition is: Among them, B i,s represents the power generation cost function of the power provider i in the third mode, C i,0 represents the fixed cost of electricity provider i, k i represents the declared electricity price factor of power supplier i, Indicates the maximum output of the unit. Indicates the minimum output of the unit, Q i represents the sum of the winning bid quantity of power provider i in the first mode and the winning bid quantity in the third mode, Q i,f represents the winning bid capacity of power provider i in the second mode, N represents N power providers, and T represents T time points; The fourth power configuration result is determined based on the target difference and the financial transmission right price. When the target difference is greater than or equal to the financial transmission right price, the financial transmission right is purchased. When the target difference is less than the financial transmission right price, the financial transmission right is not purchased. The target difference is the difference between the unified settlement point electricity price and the clearing electricity price under the third mode.

12. An electronic device, characterized in that: The method comprises a processor, a memory and a computer program stored in the memory and executable on the processor, wherein the computer program implements the steps of the method for determining electric power parameters as claimed in any one of claims 1 to 10 when executed by the processor.

13. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the method for determining a power parameter according to any one of claims 1 to 10 are implemented.

14. A computer program product, characterized in that The method comprises computer instructions, which, when executed by a processor, implement the steps of the method for determining a power parameter according to any one of claims 1 to 10.