Work task scheduling method, device, computer equipment and storage medium

By decomposing and evaluating complex work tasks through correlation algorithms and analytic hierarchy process, the problem of low efficiency in traditional technology is solved, the systematization and coherence of tasks are achieved, and the efficiency of production operation and maintenance is improved.

CN118171891BActive Publication Date: 2024-10-08SOUTHERN POWER GRID PEAK LOAD & FREQUENCY REGULATION GENERATING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410581723.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-11
Publication Date
2024-10-08
Estimated Expiration
2044-05-11

AI Technical Summary

Technical Problem

The decomposition and allocation of complex work tasks in traditional technology is inefficient and prone to errors and omissions, which affects the execution of work tasks.

Method used

Use the correlation algorithm to decompose work tasks into subtasks, and use the analytic hierarchy process to calculate the importance score of each subtask, determine the allocation plan, and ensure the systematicness and coherence of tasks.

Benefits of technology

It realizes the effective decomposition and distribution of complex work tasks, and improves the efficiency of production operation and maintenance tasks and equipment reliability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118171891B_ABST
    Figure CN118171891B_ABST
Patent Text Reader

Abstract

The present application relates to a method, device, computer equipment and storage medium for scheduling work tasks. The method comprises: obtaining the work tasks to be decomposed; decomposing the work tasks into multiple subtasks using a correlation algorithm to obtain a subtask set corresponding to the work tasks; calculating the importance score of each subtask using a hierarchical analysis method, and determining the allocation scheme of the work tasks according to the importance score. The method can achieve effective decomposition and allocation of complex work tasks, ensure the systematicness and coherence of production and operation work tasks, and improve production operation efficiency and equipment reliability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of computer technology, and in particular to a work task scheduling method, device, computer equipment and storage medium. Background Art

[0002] As enterprises develop, work plans such as department division and task allocation are becoming more and more detailed. However, for complex work tasks, traditional technologies mainly rely on manual processing and decomposition, and subsequent tracking and implementation, which is inefficient and prone to errors and omissions, affecting the allocation and execution of work tasks. Summary of the invention

[0003] Based on this, it is necessary to provide a work task scheduling method, device, computer equipment and storage medium that can achieve effective decomposition of complex work tasks in response to the above technical problems.

[0004] In a first aspect, the present application provides a work task scheduling method, comprising: obtaining the work task to be decomposed; using a correlation algorithm to decompose the work task into multiple subtasks to obtain a subtask set corresponding to the work task; using a hierarchical analysis method to calculate the importance score of each subtask, and determining the distribution plan of the work task based on the importance score.

[0005] In one of the embodiments, a relevance algorithm is used to decompose a work task into multiple subtasks to obtain a subtask set corresponding to the work task, including: using a hierarchical tree structure representation to decompose the work task into multiple subtasks to obtain an initial subtask set; using a relevance algorithm to evaluate the correlation between subtasks based on frequent item sets and association rules in the initial subtask set to achieve optimal decomposition of subtasks and obtain a subtask set.

[0006] In one embodiment, evaluating the association between subtasks includes: for an initial set of subtasks, using a Subtask relationship matrix Represents the relationship between n subtasks; any row and any column in the matrix T represents a subtask; the i-th row in the matrix T is the strength of the effect of other subtasks on subtask i, and the j-th column is the strength of the effect of other subtasks on subtask j; based on the following formula, using the Jaccard similarity coefficient, the similarity between rows and columns in the matrix is ​​obtained: ,in, is the similarity between rows, is the similarity between columns; use the following formula to get the similarity between any two subtasks As the correlation between subtasks: ,in, is the similarity between subtask i and subtask j.

[0007] In one embodiment, a relevance algorithm is used to evaluate the relevance between subtasks according to the frequent item sets and association rules in the initial subtask set to achieve the optimal decomposition of the subtasks and obtain the subtask set, including: using the following formula to determine the support of the frequent item set , and filter the frequent itemsets that meet the minimum support according to the standard of support ≥minsup threshold: ,in, Represents the probability of the union of task sets Bi and Bj; Use the following formula to calculate the confidence of the association rule, and filter the strong rules that meet the minimum confidence according to the standard of confidence ≥ minconf threshold: , where Bi and Bj are disjoint item sets, that is ; Based on the association rules that meet the minimum support and minimum confidence, determine the final association rules to be mined; Based on the similarity between the final association rules and subtasks, determine the association similarity between subtasks as ; According to the size of the correlation similarity values ​​between different subtasks, the subtasks with high correlation similarity are combined to form a new subtask ; Regroup the new subtasks to obtain the subtask set B={C1,C2,C3,...,Cn}.

[0008] In one of the embodiments, the importance score of each subtask is calculated using the analytic hierarchy process, including: obtaining various indicators that affect the importance of the subtask to form three levels: the target level, the criterion level, and the solution level; wherein the criterion level includes five indicators: work initiatives, initiating departments, undertaking departments, task types, and task complexity; forming an importance comparison matrix based on the target level, the criterion level, and the solution level; performing hierarchical single sorting and hierarchical total sorting on the indicators to obtain the final importance evaluation result as the importance score of the subtask.

[0009] In one of the embodiments, the method further includes: distributing the subtasks to corresponding undertaking terminals according to the allocation plan, and generating corresponding task undertaking information; the task undertaking information includes time records, status records and undertaking content descriptions.

[0010] In the second aspect, the present application also provides a work task scheduling device, including: a task acquisition module, used to obtain the work tasks to be decomposed; a task decomposition module, used to decompose the work tasks into multiple subtasks using a correlation algorithm, and obtain a subtask set corresponding to the work tasks; an allocation module, used to calculate the importance score of each subtask using a hierarchical analysis method, and determine the allocation plan of the work tasks based on the importance score.

[0011] In a third aspect, the present application further provides a computer device, including a memory and a processor, wherein the memory stores a computer program, and the processor implements the steps of the above method when executing the computer program.

[0012] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, wherein the computer program implements the steps of the above method when executed by a processor.

[0013] In a fifth aspect, the present application also provides a computer program product, including a computer program, which implements the steps of the above method when executed by a processor.

[0014] The above-mentioned work task scheduling method, device, computer equipment and storage medium obtain the work task to be decomposed; use the correlation algorithm to decompose the work task into multiple subtasks to obtain the subtask set corresponding to the work task; use the hierarchical analysis method to calculate the importance score of each subtask, and determine the allocation plan of the work task according to the importance score. It can achieve effective decomposition and allocation of complex work tasks, ensure the systematicness and consistency of production and operation work tasks, and improve production operation efficiency and equipment reliability. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] In order to more clearly illustrate the technical solutions in the embodiments of the present application or the related technologies, the drawings required for use in the embodiments or the related technical descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0016] FIG1 is a schematic flow chart of a method for scheduling work tasks in one embodiment.

[0017] FIG. 2 is a flow chart of using a correlation algorithm to decompose a work task into multiple subtasks to obtain a subtask set corresponding to the work task in one embodiment.

[0018] FIG. 3 is a schematic diagram of a process of calculating the importance score of each subtask using the hierarchical analysis method in one embodiment.

[0019] FIG. 4 is a structural block diagram of a work task scheduling device in one embodiment.

[0020] FIG. 5 is a diagram showing the internal structure of a computer device in one embodiment. DETAILED DESCRIPTION

[0021] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0022] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are only for the purpose of describing the embodiments of this application and are not intended to limit this application.

[0023] It is to be understood that terms such as “first”, “second”, etc. in the present application are only used to distinguish similar objects, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features.

[0024] It will be understood that “at least one” means one or more, and “plurality” means two or more.

[0025] When used herein, the singular forms "a", "an", and "said / the" may also include plural forms, unless the context clearly indicates otherwise. It should also be understood that the terms "include / comprise" or "have" and the like specify the presence of stated features, wholes, steps, operations, components, parts, or combinations thereof, but do not exclude the possibility of the presence or addition of one or more other features, wholes, steps, operations, components, parts, or combinations thereof. At the same time, the term "and / or" used in this specification includes any and all combinations of the relevant listed items.

[0026] In one embodiment, as shown in FIG1 , a method for scheduling work tasks is provided. This embodiment uses the method applied to a terminal as an example for illustration. It is understandable that the method can also be applied to a server, and can also be applied to a system including a terminal and a server, and is implemented through the interaction between the terminal and the server. In this embodiment, the method includes the following steps.

[0027] Step 102, obtaining the work tasks to be decomposed.

[0028] Among them, in a specific application scenario, the work task may be a work task involving the operation and maintenance of production equipment. Exemplarily, the work task includes key work task Y1, professional work task Y2, and technical supervision task Y3. Optionally, the work task information B of the work task can be encoded and classified and stored by establishing a task library. Among them, the task information may include task content, executor, completion time, centralized unit (the unit responsible for supervising and accepting the task), etc., which can be filled in by the task management personnel.

[0029] In a specific application scenario, a task library A can be established to store work task information B of business type Y from different sources; wherein the business type Y includes at least key work tasks Y1, professional work tasks Y2, technical supervision tasks Y3, maintenance and testing tasks Y4, anti-accident technical measures tasks Y5, personal accident prevention measures tasks Y6, supervision and inspection tasks Y7, and meeting minutes Y8.

[0030] Exemplarily, the server can obtain the work tasks to be decomposed by reading the work information in the task library.

[0031] Step 104: Use a correlation algorithm to decompose the work task into multiple subtasks to obtain a subtask set corresponding to the work task.

[0032] Specifically, by constructing a task decomposition module, the task information B can be decomposed into multiple subtasks to form a set of subtasks, that is, B={B1,B2,B3,...,Bn}, and the association algorithm can be used to achieve the optimal decomposition of subtasks to form a new subtask set B={C1,C2,C3,...,Cn}.

[0033] Step 106, using the hierarchical analysis method to calculate the importance score of each subtask, and determine the distribution plan of the work tasks according to the importance score.

[0034] Specifically, by building a task scheduling module, we can group the subtasks B and use the AHP (Analytic Hierarchy Process) method to evaluate the importance of each subtask based on multiple dimensions such as the work initiatives, initiating department, undertaking department, task type, and task complexity of each subtask, and formulate a task allocation plan based on its importance.

[0035] In the work task scheduling method provided in the embodiment of the present application, by obtaining the work task to be decomposed; using the correlation algorithm to decompose the work task into multiple subtasks, obtaining the subtask set corresponding to the work task; using the hierarchical analysis method to calculate the importance score of each subtask, and determining the allocation plan of the work task according to the importance score, it is possible to achieve effective decomposition and allocation of complex work tasks, ensure the systematicness and consistency of production and operation work tasks, and improve production operation efficiency and equipment reliability.

[0036] In one embodiment, as shown in FIG. 2 , decomposing a work task into multiple subtasks using a correlation algorithm to obtain a subtask set corresponding to the work task may include the following steps.

[0037] Step 202: Use a hierarchical tree structure to decompose the work task into multiple subtasks to obtain an initial subtask set.

[0038] Specifically, the task information B of the work task can be decomposed into multiple subtasks to form a set of subtasks, that is, B={B1, B2, B3, ..., Bn}.

[0039] The task decomposition process can be represented by a hierarchical tree structure. Each node in the task tree can be represented as a finite set, such as B1={B11,B12,B13,...,B1m}. The root node is the total task, and all nodes except the root node can be decomposed and summarized.

[0040] Step 204 , using a relevance algorithm, based on frequent item sets and association rules in the initial subtask set, evaluates the relevance between subtasks to achieve optimal decomposition of subtasks and obtain a subtask set.

[0041] Among them, the association algorithm is a type of algorithm in data mining, which is used to discover the association relationship between different items in the data set. By analyzing the association rules between data items in large-scale data sets, the potential association between them can be revealed, thus providing valuable information for prediction and decision-making.

[0042] Specifically, the association algorithm can be used to evaluate the association between subtasks based on frequent subtask item sets and association rules, so as to achieve the optimal decomposition of subtasks and form a new subtask set B={C1,C2,C3,...,Cn}.

[0043] In one embodiment, evaluating the relevance between subtasks may include the following steps: Step 302: for an initial set of subtasks, use a Subtask relationship matrix Represents the relationship between n subtasks; any row and any column in the matrix T represents a subtask; the i-th row in the matrix T is the intensity of the effect of other subtasks on subtask i, and the j-th column is the intensity of the effect of other subtasks on subtask j.

[0044] Specifically, for an existing set of subtasks, the relationship between the n subtasks can be represented by a The subtask relationship matrix is ​​used to represent it. Any row and any column in the matrix T represents a subtask. Then the matrix T can be expressed as Among them, the similarity coefficient can be used to describe the similarity between subtasks. The i-th row in the T matrix is ​​the effect strength of other subtasks on subtask i, and the j-th column is the effect strength of other subtasks on subtask j.

[0045] Step 304, based on the following formula, using the Jaccard similarity coefficient, obtain the similarity between rows and columns in the matrix: ,in, is the similarity between rows, is the similarity between columns.

[0046] Step 306: Use the following formula to obtain the similarity between any two subtasks: As the correlation between subtasks: ,in, is the similarity between subtask i and subtask j.

[0047] Based on the above-mentioned correlation evaluation, we can use correlation algorithms to mine the correlation between subtasks, use frequent item sets to mine the collinear relationship between subtasks, use association rules to mine the causal relationship between subtasks, and then achieve the optimal decomposition of subtasks based on their collinearity and causal relationship.

[0048] In one embodiment, using a relevance algorithm, based on frequent item sets and association rules in an initial subtask set, evaluating the relevance between subtasks to achieve optimal decomposition of subtasks and obtain a subtask set may include the following steps.

[0049] Step 402: Use the following formula to determine the support of frequent itemsets: , and filter the frequent itemsets that meet the minimum support according to the standard of support≥minsup threshold: ,in, Represents the probability of the union of task sets Bi and Bj.

[0050] Specifically, support can be used to quantitatively evaluate the frequent co-occurrence (i.e., coverage) of frequent item sets. The support of association rules is defined as follows: ,in It represents the probability of the union of task sets Bi and Bj. The support here can also be understood as the collinear probability of task sets Bi and Bj.

[0051] Step 404, using the following formula, calculate the confidence of the association rule, and select strong rules that meet the minimum confidence according to the standard of confidence ≥ minconfthreshold: , where Bi and Bj are disjoint item sets, that is .

[0052] Specifically, the confidence (i.e., accuracy) of a frequent item set can be quantitatively evaluated using confidence. The association rule is an implication expression of the form Bi→Bj, where Bi and Bj are disjoint item sets, i.e. The confidence of an association rule is defined as follows: .

[0053] Step 406: Determine the final association rules to be mined based on the association rules that satisfy the minimum support and the minimum confidence.

[0054] Specifically, in the frequent item set discovery phase, frequent item sets that meet the minimum support are screened according to the standard of "support ≥ minsup threshold"; in the association rule discovery phase, strong rules that meet the minimum confidence are screened according to the standard of "confidence ≥ minconfthreshold"; association rules that meet the minimum support and minimum confidence are the final association rules to be mined.

[0055] Step 408: Based on the final association rule and the similarity between subtasks, the association similarity between subtasks is determined as .

[0056] Specifically, we can use the association rule results between subtask sets and combine them with the similarity between subtasks to obtain the association similarity between subtasks: .

[0057] Step 410: According to the magnitude of the correlation similarity values ​​between different subtasks, subtasks with high correlation similarity are combined to form a new subtask. .

[0058] Step 412, regroup the new subtasks to obtain a subtask set B = {C1, C2, C3, ..., Cn}.

[0059] Among them, using support and credibility to measure the correlation between things can be abstracted based on statistical laws and Bayesian conditional probability theory to obtain a numerical measurement description.

[0060] In one embodiment, as shown in FIG3 , calculating the importance score of each subtask using the hierarchical analysis method may include the following steps.

[0061] Step 502, obtain various indicators that affect the importance of the subtask, and form three levels: target level, criterion level and plan level; among them, the criterion level includes five indicators: work measures, initiating department, undertaking department, task type and task complexity.

[0062] Specifically, we can establish a hierarchical model to conduct an in-depth analysis of the problem. First, we can explore and clarify the various indicators that affect the importance of the subtask, summarize and decompose the different indicators, and finally form three levels: goal layer, criterion layer and solution layer.

[0063] For example, in the model of sub-task item importance assessment, the sub-task item importance index is the final goal, serving as the target layer; the five dimensions of work initiatives, initiating department, undertaking department, task type, and task complexity are the small goals after the final goal is decomposed, serving as the criterion layer; and the above five dimensions have more detailed and summarized indicators, which serve as the plan layer under each criterion layer.

[0064] Step 504, forming an importance comparison matrix based on the target layer, the criterion layer and the solution layer.

[0065] Relatively speaking, the more levels there are, the more complex the judgment matrix is. After forming a fixed hierarchical structure, it is necessary to compare the indicators at the same level one by one. Each indicator has its own importance level. According to its importance level, its importance level is divided and copied. Finally, after each indicator is assigned a value, the judgment matrix is ​​obtained: ; The judgment matrix mainly compares the importance of all relevant indicators under a certain dimension for the current level and the previous level. In this comparison process, it is necessary to quantify the importance of a certain indicator to make the judgment more intuitive. Generally speaking, the model is divided into three levels: target layer, criterion layer, and solution layer. Usually starting from the criterion layer, the relevant solution layers under the criterion layer are compared pairwise, and the criterion layers under the target layer are compared pairwise to construct a comparison matrix. To form an importance comparison matrix, the judgment matrix mainly compares the importance of all relevant indicators under a certain dimension for the current level and the previous level.

[0066] According to the results of pairwise comparison of each criterion layer, the judgment matrix of the overall evaluation of the criterion layer can be obtained as follows: .

[0067] in, , , ,so , n is the number of elements in the same layer, and n is 5 in the criterion layer summary. ij is the comparison scale between the i-th criterion layer and the j-th criterion layer, Z is the comparison matrix formed by the comparison scales between the five criterion layers, n is the total number of criterion layer evaluations 5, w is the unit root of the comparison matrix, a is the weight of each criterion layer, i is the row label in the judgment matrix, and j is the column label in the judgment matrix.

[0068] Step 506 , perform hierarchical single sorting and hierarchical total sorting on the indicators to obtain a final importance evaluation result as the importance score of the subtask.

[0069] Among them, hierarchical single sorting is mainly for a certain layer in the model. For a certain layer, an order of arrangement is obtained according to its importance. This step is to calculate the judgment matrix and obtain its maximum eigenvector: The total ranking of the AHP needs to be based on the hierarchical single ranking, and the importance of each single ranking is ranked. The same as the hierarchical single ranking, the sum-product method is used to calculate after the calculation to get the final importance evaluation result. Then, the final importance evaluation result is used as the importance score of the subtask.

[0070] The work scheduling method provided in the embodiment of the present application uses the AHP hierarchical analysis method to evaluate the importance of each subtask, and based on the importance evaluation results of the subtasks, it can achieve reasonable decomposition and allocation of complex work tasks.

[0071] In one of the embodiments, the method may further include the following steps.

[0072] According to the allocation plan, the subtasks are distributed to the corresponding undertaking terminals, and the corresponding task undertaking information is generated; the task undertaking information includes time records, status records and undertaking content descriptions.

[0073] The receiving terminal can be a terminal corresponding to the receiving department or person in charge of the subtask, such as a smart device. Optionally, the receiving terminal can be a smart phone or tablet computer to achieve instant update of task information and instant communication with the person in charge, thereby improving the flexibility and response rate of the production equipment operation and maintenance method.

[0074] Specifically, the task library A can be used to distribute the work task information B to the undertaking department D according to the attribute field C of the work task information B, and generate task undertaking information.

[0075] Among them, the attribute field C of the work task information B at least includes: work initiative C1, initiating department C2, undertaking department C3, planned completion time C4, and task priority C5.

[0076] Among them, the undertaking department D at least includes the department name D1, department code D2, department head D3, workload D4, and professional skill scope D5.

[0077] Among them, the task acceptance information includes at least three contents, namely the time record, status record and acceptance content description of the task acceptance; the status record at least includes a status record representing a status of "1" and a status record representing a status of "0".

[0078] Optionally, in an actual work scenario, the following steps may also be included: the undertaking department D decomposes the task by stage or step according to the task allocation plan and allocates it to different responsible persons E; after obtaining the task information, the responsible person E formulates and executes the annual work plan F1, the monthly work plan F2, and the weekly work plan F3, and the execution status is associated with the operation and maintenance work order information T; the execution status of the annual work plan F1, the monthly work plan F2, and the weekly work plan F3 is recursively collected layer by layer into the work task information B. Specifically, the collected work task information can also be stored in the task library, and the server obtains the work information through the task library and performs subsequent processing.

[0079] Furthermore, in actual work, the execution status of the annual work plan F1, the monthly work plan F2, and the weekly work plan F3 can also be recursively collected layer by layer to the work task information B, so as to comprehensively track and manage the task execution; wherein, the collection of execution status further includes: setting up a regular reporting mechanism, and the responsible person E should report the work progress to the relevant management at the specified time point to facilitate the management to make decision adjustments and resource reallocation.

[0080] In the work task scheduling method provided in the embodiment of the present application, by sending the work task allocation plan to the undertaking department and obtaining feedback from the undertaking department, the distribution of work tasks and the collection of execution status are automatically processed, thereby improving the operational efficiency and data accuracy of the collection, decomposition and scheduling of planned tasks related to the operation and maintenance of production equipment.

[0081] In order to further explain the solution of the embodiment of the present application, a specific example is provided below. The embodiment of the present application provides a production equipment operation and maintenance method based on planned tasks (i.e., a work task scheduling method), which provides an effective method for task information transmission and tracking and implementation of key work tasks, professional work tasks, technical supervision tasks, etc. The specific steps are as follows: first, a task library is established to encode and classify the task information such as key tasks, professional tasks, technical supervision tasks, etc. related to the operation and maintenance of production equipment; then, a task decomposition module is constructed based on the attributes and other fields of the task information. In the task decomposition module, a task association matrix is ​​designed and a correlation algorithm is used. Then, the task association is calculated through the similarity between tasks and the correlation between information input and output, so as to minimize the task association and realize the decomposition of task goals; then, a task scheduling module is constructed for the decomposed goals. In the task scheduling module, the AHP hierarchical analysis method is used to evaluate the importance of the decomposed subtasks, determine their priorities according to their importance, and then determine the task resource allocation plan for each subtask; finally, annual, monthly, and weekly work plans are formulated and executed, and the execution status is associated with the operation and maintenance work order information, and the execution status of the annual, monthly, and weekly work plans is recursively collected to the task information layer by layer.

[0082] Exemplarily, the above method is implemented based on the following hardware and software modules: a database server, which is a dedicated storage medium for task library A; a database language, which is used to design a unique identifier to encode and store the work task; a task decomposition module, which is used to decompose the task objectives by minimizing the task correlation; a task scheduling module, which is used to implement the importance evaluation of sub-task objectives; a task management module, which is used to realize the distribution of work tasks and the automated processing of the collection and execution status of the execution status, so as to improve the operational efficiency and data accuracy of the collection, decomposition and scheduling of planned tasks related to the operation and maintenance of production equipment.

[0083] In a specific example, the following steps are included: (1.1) A task library A is established to encode and classify the work task information B including key work tasks Y1, professional work tasks Y2, technical supervision tasks Y3 and other work task information related to production equipment operation and maintenance.

[0084] (1.2) Construct a task decomposition module to decompose the task information B into multiple subtasks to form a subtask set, that is, B={B1,B2,B3,...,Bn}, and use the association algorithm to achieve the optimal decomposition of subtasks to form a new subtask set B={C1,C2,C3,...,Cn}.

[0085] (1.3) Construct a task scheduling module, and use the AHP hierarchical analysis method to evaluate the importance of each subtask based on multiple dimensions such as the work measures, initiating department, undertaking department, task type, and task complexity of each subtask, and formulate a task allocation plan based on its importance.

[0086] (1.4) The undertaking department D breaks down the tasks into stages or steps according to the task allocation plan and allocates them to different responsible persons E.

[0087] (1.5) After receiving the task information, the responsible person E formulates and executes the annual work plan F1, monthly work plan F2, and weekly work plan F3, and the execution status is associated with the operation and maintenance work order information T.

[0088] (1.6) The execution status of the annual work plan F1, the monthly work plan F2, and the weekly work plan F3 are recursively collected layer by layer into the work task information B.

[0089] Among them, a task library A is established to store work task information B of business type Y from different sources. The business type Y at least includes key work tasks Y1, professional work tasks Y2, technical supervision tasks Y3, maintenance and test tasks Y4, anti-accident technical measures tasks Y5, personal accident prevention measures tasks Y6, supervision and inspection tasks Y7, and meeting minutes Y8.

[0090] The task decomposition module is constructed to implement the following steps: decompose the task information B into multiple subtasks to form a subtask set, that is, B={B1,B2,B3,...,Bn}. The task decomposition process can be represented by a hierarchical tree structure. Each node in the task tree can be represented as a finite set, such as B1={B11,B12,B13,...,B1m}. The root node is the total task. Except for the root node, other nodes can be decomposed and summarized. Using the association algorithm, the association between subtasks is evaluated according to the frequent subtask item set and the association rules, so as to achieve the optimal decomposition of subtasks and form a new subtask set B={C1,C2,C3,...,Cn}.

[0091] Among them, exploring the association relationship of the subtask set based on the subtask matrix includes: for an existing subtask set, its n subtask relationships can be represented by an n×n subtask relationship matrix, and any row and any column in the matrix T represents a subtask, then the matrix T can be expressed as .

[0092] The similarity coefficient is used to describe the similarity between subtasks. The i-th row in the T matrix is ​​the effect of other subtasks on subtask i, and the j-th column is the effect of other subtasks on subtask j. By using the Jaccard similarity coefficient, the similarity between rows and columns in the matrix can be obtained: .

[0093] The similarity between subtasks is: .

[0094] The association algorithm is used to mine the association between subtasks, the frequent item sets are used to mine the collinear relationship between subtasks, and the association rules are used to mine the causal relationship between subtasks. Then, the optimal decomposition of subtasks is achieved based on their collinear and causal relationships.

[0095] Optionally, the optimal decomposition of subtasks using frequent item sets and association rules of the association algorithm includes: using support and credibility to measure the association relationship between things, which can be abstracted based on statistical laws and Bayesian conditional probability theory to obtain a numerical measurement description; using support to quantitatively evaluate the frequent co-occurrence (i.e., coverage) of frequent item sets, and the support of association rules is defined as follows ,in It represents the probability of the union of task sets Bi and Bj. The support here can also be understood as the collinear probability of task sets Bi and Bj.

[0096] The confidence (i.e., accuracy) of a frequent item set is quantitatively evaluated using confidence. The association rule is an implication expression of the form Bi→Bj, where Bi and Bj are disjoint item sets, i.e. The confidence of an association rule is defined as follows: .

[0097] Frequent item set discovery phase: filter frequent item sets that meet the minimum support according to the standard of "support ≥ minsup threshold"; association rule discovery phase: filter strong rules that meet the minimum confidence according to the standard of "confidence ≥ minconf threshold"; association rules that meet the minimum support and minimum confidence are the final association rules to be mined.

[0098] Using the association rule results between subtask sets and combining the similarity between subtasks, the association similarity between subtasks is obtained as According to the size of the correlation similarity values ​​between different subtasks, the subtasks with high correlation similarity are combined to form a new subtask . Regroup the new subtasks to form a new subtask set B={C1,C2,C3,...,Cn}.

[0099] Among them, the construction of the task scheduling module uses the AHP hierarchical analysis method to evaluate the importance of each subtask, including: establishing a hierarchical model, conducting an in-depth analysis of the problem, first exploring and clarifying the various indicators that affect the importance of the subtask, summarizing and decomposing different indicators, and finally forming three levels: target layer, criterion layer, and solution layer; forming an importance comparison matrix. The judgment matrix is ​​mainly for the current level and the previous level, and compares the importance of all relevant indicators under a certain dimension.

[0100] Specifically, the establishment of a hierarchical model in the AHP includes: in the model of sub-task item importance evaluation, the sub-task item importance index is the final goal, as the target layer; the five dimensions of work initiatives, initiating department, undertaking department, task type, and task complexity are the small goals after the final goal is decomposed, as the criterion layer; and the above five dimensions have more detailed descriptions and summary indicators, which serve as the solution layer under each criterion layer.

[0101] Relatively speaking, the more levels there are, the more complex the judgment matrix is. After forming a fixed hierarchical structure, it is necessary to compare the indicators at the same level one by one. Each indicator has its own importance level. According to its importance level, its importance level is divided and copied. Finally, after each indicator is assigned a value, the judgment matrix is ​​obtained: ; The importance comparison matrix formed in the AHP hierarchical analysis method includes: the judgment matrix mainly compares the importance of all relevant indicators under a certain dimension for the current level and the previous level. In this comparison process, it is necessary to quantify the importance of a certain indicator to make the judgment more intuitive. Generally speaking, the model is divided into three levels: the target layer, the criterion layer, and the solution layer. Usually starting from the criterion layer, the various related solution layers under the criterion layer are compared pairwise, and the various criterion layers under the target layer are compared pairwise to construct a comparison matrix.

[0102] According to the results of pairwise comparison of each criterion layer, the judgment matrix of the overall evaluation of the criterion layer can be obtained as follows: .

[0103] in, , , ,so , n is the number of elements in the same layer, and n is 5 in the criterion layer summary. ij is the comparison scale between the i-th criterion layer and the j-th criterion layer, Z is the comparison matrix formed by the comparison scales between the five criterion layers, n is the total number of criterion layer evaluations 5, w is the unit root of the comparison matrix, a is the weight of each criterion layer, i is the row label in the judgment matrix, and j is the column label in the judgment matrix.

[0104] The hierarchical analysis method single sorting is mainly for a certain layer in the model. For a certain layer, an order of arrangement is obtained according to its importance. This step is to calculate the judgment matrix and obtain its maximum eigenvector: ; The total ranking of the hierarchical analysis method needs to be based on the hierarchical single ranking, and the importance of each single ranking should be ranked. The same as the hierarchical single ranking, the sum-product method is used after calculation to get the final importance evaluation result.

[0105] Furthermore, the weight vector is calculated and a consistency test is performed, and the matrix consistency index CI is: .

[0106] The CI value is used to indicate the degree of deviation of the judgment matrix from consistency. The larger the CI value, the greater the deviation; conversely, the smaller the CI value, the smaller the deviation. The n in the formula indicates the order of the judgment matrix. The judgment matrix is ​​obtained by artificially constructed indicators and is affected by human factors. The CI value is also affected by the n value, that is, the CI value is also affected by human factors. Generally speaking, the size of n can be used to indicate the degree of deviation from consistency caused by human factors. The larger the n, the greater the CI value affected by human factors; conversely, the smaller the n, the smaller the CI value affected by human factors.

[0107] The random consistency ratio CR is used to determine whether to accept the consistency of the judgment matrix. The random consistency ratio CR is: ; When CR<0.10, it means that the consistency of the judgment matrix can be accepted; on the contrary, when CR≥0.10, it means that the consistency of the judgment matrix is ​​refuted. When the consistency is not accepted, it is necessary to make certain adjustments to the judgment matrix and verify the consistency of the adjusted judgment matrix, and repeat the process until the consistency of the judgment matrix is ​​accepted.

[0108] For the assigned subtasks and work information, the task library A is used to distribute the work task information B to the undertaking department D according to the attribute field C of the work task information B, and generate task undertaking information.

[0109] Among them, the attribute field C of the work task information B includes at least: work initiatives C1, initiating department C2, undertaking department C3, planned completion time C4, and task priority C5; the undertaking department D includes at least department name D1, department code D2, department head D3, work task load D4, and professional skill category D5; the task acceptance information includes at least three contents, namely the time record, status record and acceptance content description of the task acceptance; the status record includes at least a status record representing a status of "1" and a status record representing a status of "0".

[0110] Optionally, the execution status of the annual work plan F1, the monthly work plan F2, and the weekly work plan F3 are recursively collected layer by layer into the work task information B, so as to comprehensively track and manage the task execution.

[0111] Among them, the collection of execution status further includes: setting up a regular reporting mechanism, and the responsible person E should report the work progress to the relevant management at the specified time point to facilitate the management to make decision adjustments and resource reallocation.

[0112] Exemplarily, an early warning mechanism may be further included to monitor the deviation between the task execution status and the plan, mainly to detect the deviation between the execution time and the planned time, to clarify whether there is a stagnation in the task execution, and to trigger a status warning when it is detected that the execution time exceeds the planned time, to automatically notify the responsible person E and the management to make necessary adjustments. The early warning mechanism may include a notification function of SMS, email or mobile application to speed up the communication and response of abnormal status.

[0113] Among them, the above steps that need to be performed by the responsible person can be executed with the help of mobile computing devices, including smart phones or tablet computers, to achieve instant update of task information and instant communication with the responsible person E, thereby improving the flexibility and response rate of the production equipment operation and maintenance method.

[0114] The work scheduling method provided in the embodiment of the present application provides an effective method for decomposing and scheduling planned tasks related to production equipment operation and maintenance, which can realize effective decomposition, allocation and execution tracking of complex work tasks, ensure the systematicness and consistency of production operation and maintenance work tasks, and improve production operation efficiency and equipment reliability.

[0115] It should be understood that, although the various steps in the flowcharts involved in the above-mentioned embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above-mentioned embodiments can include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.

[0116] Based on the same inventive concept, the embodiment of the present application also provides a work task scheduling device for implementing the work task scheduling method involved above. The implementation scheme for solving the problem provided by the device is similar to the implementation scheme recorded in the above method, so the specific limitations in one or more work task scheduling device embodiments provided below can refer to the limitations of the work task scheduling method above, and will not be repeated here.

[0117] In an exemplary embodiment, as shown in FIG4 , a work task scheduling device 400 is provided, including: a task acquisition module 401, used to acquire the work task to be decomposed; a task decomposition module 402, used to decompose the work task into multiple subtasks using a correlation algorithm, and obtain a subtask set corresponding to the work task; an allocation module 403, used to calculate the importance score of each subtask using a hierarchical analysis method, and determine the allocation plan of the work task according to the importance score.

[0118] In one embodiment, the task decomposition module includes: an initial decomposition unit, which is used to decompose the work task into multiple subtasks using a hierarchical tree structure representation to obtain an initial subtask set; an association unit, which is used to use an association algorithm to evaluate the association between subtasks based on frequent item sets and association rules in the initial subtask set to achieve optimal decomposition of subtasks and obtain a subtask set.

[0119] In one embodiment, the association unit is further configured to: for the initial subtask set, use a Subtask relationship matrix Represents the relationship between n subtasks; any row and any column in the matrix T represents a subtask; the i-th row in the matrix T is the strength of the effect of other subtasks on subtask i, and the j-th column is the strength of the effect of other subtasks on subtask j; based on the following formula, using the Jaccard similarity coefficient, the similarity between rows and columns in the matrix is ​​obtained: ,in, is the similarity between rows, is the similarity between columns; use the following formula to get the similarity between any two subtasks As the correlation between subtasks: ,in, is the similarity between subtask i and subtask j.

[0120] In one embodiment, the association unit is further used to determine the support of the frequent item set using the following formula: , and filter the frequent itemsets that meet the minimum support according to the standard of support ≥ minsup threshold: ,in, Represents the probability of the union of task sets Bi and Bj; Use the following formula to calculate the confidence of the association rule, and filter the strong rules that meet the minimum confidence according to the standard of confidence ≥ minconf threshold: , where Bi and Bj are disjoint item sets, that is ; Based on the association rules that meet the minimum support and minimum confidence, determine the final association rules to be mined; Based on the similarity between the final association rules and subtasks, determine the association similarity between subtasks as ; According to the size of the correlation similarity values ​​between different subtasks, the subtasks with high correlation similarity are combined to form a new subtask ; Regroup the new subtasks to obtain the subtask set B={C1,C2,C3,...,Cn}.

[0121] In one embodiment, the allocation module includes: an indicator acquisition unit, which is used to acquire various indicators that affect the importance of subtasks, forming three levels: target layer, criterion layer and plan layer; wherein the criterion layer includes five indicators: work initiatives, initiating departments, undertaking departments, task types and task complexity; a matrix construction unit, which is used to form an importance comparison matrix based on the target layer, criterion layer and plan layer; an importance score evaluation unit, which is used to perform hierarchical single sorting and hierarchical total sorting on the indicators, and obtain the final importance evaluation result as the importance score of the subtask.

[0122] In one of the embodiments, it also includes: an acceptance module, which is used to distribute the subtasks to the corresponding acceptance terminals according to the allocation plan and generate corresponding task acceptance information; the task acceptance information includes time records, status records and acceptance content descriptions.

[0123] Each module in the above-mentioned work task scheduling device can be implemented in whole or in part by software, hardware or a combination thereof. Each module can be embedded in or independent of a processor in a computer device in the form of hardware, or can be stored in a memory in a computer device in the form of software, so that the processor can call and execute the operations corresponding to each module above.

[0124] In an exemplary embodiment, a computer device is provided, which may be a server, and its internal structure diagram may be shown in FIG5. The computer device includes a processor, a memory, an input / output interface (Input / Output, referred to as I / O) and a communication interface. The processor, the memory and the input / output interface are connected via a system bus, and the communication interface is connected to the system bus via the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store work task scheduling data. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal via a network connection. When the computer program is executed by the processor, a work task scheduling method is implemented.

[0125] Those skilled in the art will understand that the structure shown in FIG. 5 is merely a block diagram of a partial structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than shown in the figure, or combine certain components, or have a different arrangement of components.

[0126] In an exemplary embodiment, a computer device is provided, including a memory and a processor, wherein a computer program is stored in the memory, and the processor implements the steps of the above method when executing the computer program.

[0127] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of the above method are implemented.

[0128] In one embodiment, a computer program product is provided, comprising a computer program, which implements the steps of the above method when executed by a processor.

[0129] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided in this application can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetoresistive random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided in this application may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided in this application may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, etc., but are not limited to this.

[0130] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0131] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.

Claims

1. A work task scheduling method, characterized in that: The method comprises: Get the work tasks to be decomposed; Decomposing the work task into multiple subtasks using a correlation algorithm to obtain a subtask set corresponding to the work task, including: using a hierarchical tree structure representation to decompose the work task into multiple subtasks to obtain an initial subtask set; using a correlation algorithm to evaluate the correlation between the subtasks based on frequent item sets and association rules in the initial subtask set to achieve optimal decomposition of the subtasks to obtain the subtask set; the evaluating the correlation between the subtasks includes: for the initial subtask set, using a Subtask relationship matrix Represents the relationship between n subtasks; wherein any row and any column in the matrix T represents a subtask; the i-th row in the matrix T is the effect strength of other subtasks on subtask i, and the j-th column is the effect strength of other subtasks on subtask j; based on the following formula, using the Jaccard similarity coefficient, the similarity between rows and columns in the matrix is ​​obtained: ; in, is the similarity between rows, is the similarity between columns; use the following formula to get the similarity between any two subtasks As the degree of association between the subtasks: ; in, is the similarity between subtask i and subtask j; the use of the association algorithm to evaluate the association between the subtasks according to the frequent item sets and association rules in the initial subtask set to achieve the optimal decomposition of the subtasks and obtain the subtask set includes: using the following formula to determine the support of the frequent item sets , and filter the frequent itemsets that meet the minimum support according to the standard of support ≥ minsup threshold: ; in, represents the probability of the union of the task sets Bi and Bj; the confidence of the association rule is calculated using the following formula, and the strong rules that meet the minimum confidence are screened according to the standard of confidence ≥ minconf threshold: ; Among them, Bi and Bj are disjoint item sets, that is, ; Based on the association rules that satisfy the minimum support and the minimum confidence, determine the final association rules to be mined; based on the similarity between the final association rules and the subtasks, determine the association similarity between the subtasks as According to the magnitude of the association similarity values ​​between the different subtasks, the subtasks with high association similarity are combined to form a new subtask ; Regroup the new subtasks to obtain the subtask set B={C1,C2,C3,...,Cn}; use the hierarchical analysis method to calculate the importance score of each subtask, and determine the allocation plan of the work task according to the importance score; wherein, the use of the hierarchical analysis method to calculate the importance score of each subtask includes: obtaining various indicators that affect the importance of the subtask, forming three levels: the target layer, the criterion layer and the solution layer; wherein the criterion layer includes five indicators: work initiatives, initiating departments, undertaking departments, task types and task complexity; based on the target layer, the criterion layer and the solution layer, an importance comparison matrix is ​​formed; the indicators are hierarchically sorted and hierarchically sorted to obtain the final importance evaluation result as the importance score of the subtask.

2. The method according to claim 1, characterized in that The method further comprises: According to the allocation plan, the subtasks are distributed to the corresponding undertaking terminals, and corresponding task undertaking information is generated; the task undertaking information includes time records, status records and undertaking content descriptions.

3. A work task scheduling device, characterized in that: The device comprises: Task acquisition module, used to acquire work tasks to be decomposed; The task decomposition module is used to decompose the work task into multiple subtasks using a correlation algorithm to obtain a subtask set corresponding to the work task; it is also used to decompose the work task into multiple subtasks using a hierarchical tree structure representation to obtain an initial subtask set; using a correlation algorithm, according to frequent item sets and association rules in the initial subtask set, evaluate the correlation between the subtasks to achieve optimal decomposition of the subtasks and obtain the subtask set; the evaluation of the correlation between the subtasks includes: for the initial subtask set, using a Subtask relationship matrix Represents the relationship between n subtasks; wherein any row and any column in the matrix T represents a subtask; the i-th row in the matrix T is the effect strength of other subtasks on subtask i, and the j-th column is the effect strength of other subtasks on subtask j; based on the following formula, using the Jaccard similarity coefficient, the similarity between rows and columns in the matrix is ​​obtained: ; in, is the similarity between rows, is the similarity between columns; use the following formula to get the similarity between any two subtasks As the degree of association between the subtasks: ; in, is the similarity between subtask i and subtask j; the use of the association algorithm to evaluate the association between the subtasks according to the frequent item sets and association rules in the initial subtask set to achieve the optimal decomposition of the subtasks and obtain the subtask set includes: using the following formula to determine the support of the frequent item sets , and filter the frequent itemsets that meet the minimum support according to the standard of support ≥ minsup threshold: ; in, represents the probability of the union of the task sets Bi and Bj; the confidence of the association rule is calculated using the following formula, and the strong rules that meet the minimum confidence are screened according to the standard of confidence ≥ minconf threshold: ; Among them, Bi and Bj are disjoint item sets, that is, ; Based on the association rules that satisfy the minimum support and the minimum confidence, determine the final association rules to be mined; based on the similarity between the final association rules and the subtasks, determine the association similarity between the subtasks as According to the magnitude of the association similarity values ​​between the different subtasks, the subtasks with high association similarity are combined to form a new subtask ; Regroup the new subtasks to obtain the subtask set B={C1,C2,C3,...,Cn}; An allocation module is used to calculate the importance score of each subtask using the hierarchical analysis method, and determine the allocation plan of the work task according to the importance score; wherein, the use of the hierarchical analysis method to calculate the importance score of each subtask includes: obtaining various indicators that affect the importance of the subtask, forming three levels: the target layer, the criterion layer and the plan layer; wherein the criterion layer includes five indicators: work initiatives, initiating departments, undertaking departments, task types and task complexity; based on the target layer, the criterion layer and the plan layer, an importance comparison matrix is ​​formed; the indicators are hierarchically sorted and hierarchically sorted, and the final importance evaluation result is obtained as the importance score of the subtask.

4. A computer device comprising a memory and a processor, wherein the memory stores a computer program, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 2 are implemented.

5. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 2 are implemented.

6. A computer program product comprising a computer program, characterized in that When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 2 are implemented.