Material unloading device
By designing a guide rail structure and conveying table system with feeding, handling and cutting stations, the structure simplification of the material cutting device and the improvement of handling efficiency are achieved, and the problems of complex structure and low efficiency in the prior art are solved.
Patent Information
- Application Number
- CN202410728419.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-06
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-06-06
AI Technical Summary
The existing material cutting device has a complex structure and low handling efficiency. It is necessary to set up a transit mechanism or multiple pick-up and placement parts to temporarily store the material, which affects the material handling efficiency.
A material discharge device is designed, including a first conveying line and a second conveying line, adopting a first guide rail structure and a second guide rail structure, respectively, and is provided with feeding, handling and cutting stations, through the first conveying table and The second conveyor table moves back and forth between the guide rail structures, clamping or loosening the material tray to realize direct replacement and handling of the material tray, simplifying the structure and improving efficiency.
Without additional structure, the qualified and unqualified products in the material tray are directly replaced, which improves the efficiency and working efficiency of material handling and simplifies the device structure.
Smart Images

Figure CN118289428B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of automatic material unloading, and in particular to a material unloading device. Background Art
[0002] During the production process of semiconductor chips, it is necessary to inspect their outer surfaces to ensure that they are qualified before leaving the factory. The materials to be inspected are usually loaded into a tray. When the materials in the tray are inspected, the tray will be transferred to the unloading device for unloading.
[0003] In the prior art, the unloading device includes a first conveyor line, a second conveyor line and a handling mechanism. The first conveyor line and the second conveyor line are belt conveyor lines, both of which are used to receive and convey the inspected trays. When the trays are transported to the handling station, the handling mechanism can transport the qualified products in the trays on the first conveyor line to the trays on the second conveyor line, and transport the unqualified products in the trays on the second conveyor line to the trays on the first conveyor line. When the trays are full of unqualified products, the first conveyor line unloads the trays. When the trays are full of qualified products, the second conveyor line unloads the trays.
[0004] Since the material trays input into the first conveyor line and the second conveyor line are usually fully loaded, it is difficult for the conveying mechanism to directly transfer the materials, and a transfer mechanism needs to be set up, or multiple pick-and-place parts are set up on the conveying mechanism to temporarily store the materials. The above structure is complex, and the additional pick-and-place operation greatly affects the material handling efficiency.
[0005] Therefore, it is necessary to improve the prior art to overcome the above defects in the prior art. Summary of the invention
[0006] The object of the present invention is to provide a material unloading device which can simplify the structure and improve the handling efficiency.
[0007] The object of the present invention is achieved through the following technical solution: A material unloading device includes a first conveying line, wherein the first conveying line includes:
[0008] The first guide rail structure is used to carry and guide the movement of the material tray. The first guide rail structure is provided with a first loading station, a first transporting station, a first unloading station and a second loading station in sequence along its length direction. A material tray fully loaded with tested materials can be loaded to the first loading station, and an empty material tray can be loaded to the second loading station;
[0009] A first conveying platform, adapted to clamp or release the tray;
[0010] A first driving assembly, adapted to drive the first conveying platform to move back and forth between the first loading station, the first transporting station, the first unloading station and the second loading station;
[0011] There are two first conveying platforms, which are spaced apart along the length direction of the first guide rail structure.
[0012] Furthermore, the first loading station and the second loading station are respectively arranged at two ends of the first guide rail structure, and the first conveyor line includes a mounting seat, and the mounting seat can be slidably set on the first guide rail structure along the length direction of the first guide rail structure, and the two first conveying platforms are fixed on the mounting seat, and the first driving assembly is transmission-connected with the mounting seat to drive the mounting seat to slide, and when one of the first conveying platforms corresponds to a station, the other first conveying platform corresponds to a station adjacent to the station.
[0013] Furthermore, a guard assembly is provided on the first guide rail structure, and the guard assembly is suitable for opening to place an empty material tray at the second loading station, and the guard assembly is suitable for closing to enclose the second loading station. The guard assembly is open on one side in the length direction of the first guide rail structure to allow the first conveying platform to move into or out of the second loading station.
[0014] Furthermore, the first guide rail structure comprises:
[0015] Bracket;
[0016] A support rail is fixedly connected to the bracket, and the length direction is parallel to the movement direction of the first conveyor platform. There are two support rails, which are arranged opposite to each other along the width direction. The two support rails are suitable for supporting the material tray and limiting the material tray in the width direction of the support rails;
[0017] Wherein, a receiving area for receiving the first conveying platform is provided between the two supporting guide rails.
[0018] Furthermore, the first conveying platform is located below the bearing surface of the supporting guide rail, and the first conveying platform is provided with clamping components on both sides of the length direction of the first guide rail structure, and the clamping components have a loosened state and a clamping state. When the clamping component is in the loosened state, the clamping component is located below the bearing surface of the supporting guide rail, and when the clamping component is in the clamping state, the clamping component is at least partially located above the bearing surface of the supporting guide rail to clamp the material tray.
[0019] Furthermore, the material unloading device includes a second conveying line, and the second conveying line includes:
[0020] A second guide rail structure is used to carry and guide the movement of the material tray, and the second guide rail structure is provided with a third loading station, a second transporting station and a second unloading station in sequence along its length direction;
[0021] A second conveying platform, suitable for clamping or releasing the tray;
[0022] The second driving assembly is suitable for driving the second conveying platform to move back and forth between the third loading station, the second transporting station and the second unloading station.
[0023] Furthermore, the number of the second conveying platforms is two, and the projections of the first guide rail structure and / or the second guide rail structure in the length direction do not overlap, and the second driving assembly corresponds to the second conveying platform one by one.
[0024] Furthermore, the first guide rail structure and the second guide rail structure are arranged side by side and parallel in length direction, the third loading station and the second unloading station are located at both ends of the second guide rail structure, the third loading station and the first loading station are located on the same side, and the second unloading station and the second loading station are located on the same side.
[0025] Furthermore, the material unloading device comprises:
[0026] A transport mechanism, adapted to transport unqualified materials in the trays on the second conveyor line to the trays on the first conveyor line, and to transport qualified materials in the trays on the first conveyor line to the trays on the second conveyor line;
[0027] A first stacking mechanism, located at the first unloading station, to receive a tray full of defective products;
[0028] The second stacking mechanism is arranged at the second unloading station to receive a tray fully loaded with qualified products.
[0029] Furthermore, the transport mechanism comprises:
[0030] A transverse movement module, adapted to move along the width direction of the first guide rail structure and / or the second guide rail structure;
[0031] A lifting module is connected to the transverse module in a transmission manner and is suitable for moving in a vertical direction;
[0032] At least one pick-and-place member, drivingly connected to the lifting module, for picking up and placing materials;
[0033] Wherein, the pick-and-place member is suitable for moving to the first transport station or the second transport station under the drive of the transverse movement module and the lifting module.
[0034] Compared with the prior art, the present invention has the following beneficial effects: the present invention adopts the first conveyor line of the above-mentioned structure, the first conveyor line includes a first guide rail structure and a first conveying platform movable along the length direction of the first guide rail structure, a material tray fully loaded with materials can be loaded to the first loading station of the first guide rail structure, and an empty material tray can be loaded to the second loading station of the first guide rail structure, and there are two first conveying platforms to respectively clamp and transfer the material tray fully loaded with materials and the empty material tray to the first handling station, so that in the subsequent handling process, the handling structure can directly replace the qualified products and the unqualified products in the material tray, without the need to set up additional structures to temporarily store materials, thereby effectively improving the handling efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is a structural schematic diagram of the material unloading device of the present invention.
[0036] Figure 2 It is a structural schematic diagram of the first conveying line and the first stacking mechanism in the present invention.
[0037] Figure 3 It is a partial structural schematic diagram of the first conveyor line in the present invention.
[0038] Figure 4 It is a partial schematic diagram of the clamping assembly on the first conveying platform in the present invention in a loosened state.
[0039] Figure 5 It is a partial schematic diagram of the clamping assembly on the first conveying platform in the present invention in a clamping state.
[0040] Figure 6 yes Figure 4 Schematic diagram of the decomposition structure.
[0041] Figure 7 It is a structural schematic diagram of the shield assembly in the present invention.
[0042] Figure 8 yes Figure 7 Schematic diagram of the structure in another direction.
[0043] Fig. 9 It is a structural schematic diagram of the striking component in the present invention.
[0044] Fig.10 It is a structural schematic diagram of the second conveying line and the second stacking mechanism in the present invention.
[0045] Fig.11 It is a structural schematic diagram of the transport mechanism in the present invention.
[0046] Fig.12 yes Fig.11 Schematic diagram of the structure of the lifting module and the pick-and-place parts.
[0047] Fig.13 It is a structural schematic diagram of the first stacking mechanism in the present invention.
[0048] Description of reference numerals:
[0049] 100, first conveyor line; 100a, first loading station; 100b, second loading station; 100c, first handling station; 100d, first unloading station; 110, first guide rail structure; 111, bracket; 112, support rail; 120, first conveyor platform; 121, base; 122, platform body; 123, installation space; 1231, guide groove; 130, first drive assembly; 131, drive motor; 132, drive pulley group; 140, mounting seat; 150, clamping assembly; 151, first clamping cylinder; 152, transmission block; 153, first clamping member; 1531, first connecting portion; 1532, first clamping portion; 154, follower; 155, second clamping cylinder; 156, second clamping member; 1561, second connecting portion; 1562, second clamping Holding part; 160, shield assembly; 161, lower sealing plate; 162, first side sealing plate; 163, second side sealing plate; 164, upper cover plate; 165, handle; 170, knocking assembly; 171, knocking cylinder; 172, knocking block; 200, material tray; 300, second conveyor line; 300a, third loading station; 300b, second handling station; 300c, second unloading station; 310, second guide rail structure; 320, second conveyor platform; 330, second drive assembly; 400, handling mechanism; 410, transverse movement module; 420, lifting module; 430, pick-and-place component; 440, camera assembly; 500, first stacking mechanism; 510, stacking frame; 520, supporting member; 530, lifting assembly; 531, lifting module; 532, lifting member; 600, second stacking mechanism. DETAILED DESCRIPTION
[0050] In order to make the above-mentioned purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are described in detail below in conjunction with the accompanying drawings. It is to be understood that the specific embodiments described herein are only used to explain the present application, rather than to limit the present application. It should also be noted that, for ease of description, only some structures related to the present application are shown in the accompanying drawings, rather than all structures. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0051] The terms "including" and "having" and any variations thereof in this application are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device comprising a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units not listed, or may optionally include other steps or units inherent to these processes, methods, products or devices.
[0052] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present application. The appearance of the phrase in various locations in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0053] See also Figure 1 and Figure 2 As shown, a material unloading device corresponding to a preferred embodiment of the present invention includes a first conveyor line 100, and the first conveyor line 100 includes: a first guide rail structure 110, which is used to carry and guide the movement of a material tray 200, and the first guide rail structure 110 is provided with a first loading station 100a, a first handling station 100c, a first unloading station 100d and a second loading station 100b in sequence along its length direction, and the material tray 200 fully loaded with the inspected material can be loaded to the first loading station 100a, an empty material tray 200 can be loaded to the second loading station 100b; the first conveyor platform 120 is suitable for clamping or releasing the material tray 200; the first drive assembly 130 is suitable for driving the first conveyor platform 120 to and fro between the first loading station 100a, the first handling station 100c, the first unloading station 100d and the second loading station 100b; wherein, there are two first conveyor platforms 120, and they are spaced apart along the length direction of the first guide rail structure 110.
[0054] The present invention adopts the first conveyor line 100 of the above-mentioned structure, and the first conveyor line 100 includes a first guide rail structure 110 and a first conveying platform 120 that can move along the length direction of the first guide rail structure 110. The material tray 200 fully loaded with materials can be loaded to the first loading station 100a of the first guide rail structure 110, and the empty material tray 200 can be loaded to the second loading station 100b of the first guide rail structure 110. There are two first conveyor platforms 120 to respectively clamp and transfer the material tray 200 fully loaded with materials and the empty material tray 200 to the first handling station 100c, so that in the subsequent handling process, the handling structure can directly replace the qualified products and the unqualified products in the material tray 200, without setting up an additional structure to temporarily store the materials, thereby effectively improving the handling efficiency.
[0055] Furthermore, the first loading station 100a and the second loading station 100b are respectively arranged at the two ends of the first guide rail structure 110 to facilitate the loading operation. The first conveyor line 100 includes a mounting seat 140, which can be slidably arranged on the first guide rail structure 110 along the length direction of the first guide rail structure 110, and the two first conveyor platforms 120 are fixed on the mounting seat 140. The first drive assembly 130 is connected to the mounting seat 140 in a transmission manner to drive the mounting seat 140 to slide, thereby driving the two first conveyor platforms 120 to move synchronously, and when one of the first conveyor platforms 120 corresponds to a station, the other first conveyor platform 120 corresponds to a station adjacent to the station.
[0056] By adopting the above structure, a single first drive assembly 130 can realize the simultaneous movement of the two first conveyor platforms 120, simplify the structure and reduce the cost; and when one of the first conveyor platforms 120 corresponds to a workstation, the other first conveyor platform 120 corresponds to a workstation adjacent to the workstation, thereby effectively improving the work efficiency. For example, when one of the first conveyor platforms 120 drives the material tray 200 to move to the first handling station 100c for handling operations, the other first conveyor platform 120 is at the first loading station 100a or the first unloading station 100d, so as to continue to receive the material tray 200 or unload the material tray 200; when one of the first conveyor platforms 120 drives the material tray 200 to move to the first unloading station 100d for unloading operations, the other first conveyor platform 120 is at the first handling station 100c or the second loading station 100b, so as to carry out handling operations or receive empty material trays 200.
[0057] Further, refer to Figure 2 and Figure 3 As shown, the first guide rail structure 110 includes a bracket 111 and a support guide rail 112 fixedly connected to the bracket 111. The length direction of the support guide rail 112 is parallel to the movement direction of the first conveyor platform 120. There are two support guide rails 112, which are arranged relatively to each other along their width direction. The cross-section of the support guide rail 112 perpendicular to its length direction is an L-shaped structure to form a bearing surface and a limiting surface. The two support guide rails 112 are suitable for cooperating with the support material tray 200 and limiting the material tray 200 in the width direction of the support guide rail 112. There is a accommodating area for accommodating the first conveyor platform 120 between the two support guide rails 112.
[0058] Furthermore, the first drive assembly 130 includes a drive motor 131 and a transmission pulley group 132 arranged on the bracket 111. The drive motor 131 is transmission-connected to the transmission pulley group 132 to drive the transmission pulley group 132 to rotate. The mounting seat 140 is fixedly connected to the transmission belt of the transmission pulley group 132 to move under the drive of the drive motor 131.
[0059] The first conveyor platform 120 is located below the bearing surface of the support rail 112. The first conveyor platform 120 is provided with clamping assemblies 150 on both sides of the length direction of the first rail structure 110. The clamping assemblies 150 have a loose state and a clamping state. When the clamping assembly 150 is in the loose state, the clamping assembly 150 is located below the bearing surface of the support rail 112, so that the first conveyor platform 120 can flow through the material tray 200 on the support rail 112. When the clamping assembly 150 is in the clamping state, the clamping assembly 150 is at least partially located above the bearing surface of the support rail 112 to clamp the material tray 200, so that the material tray 200 can move synchronously with the first conveyor platform 120.
[0060] Further, refer to Figures 4 to 6 As shown, the first conveyor 120 includes a base 121 and a platform 122 located above the base 121, the base 121 is connected between the mounting base 140 and the platform 122, and the surface of the platform 122 is not higher than the bearing surface of the support rail 112, so as to prevent the material tray 200 on the support rail 112 from obstructing the first conveyor 120. In one embodiment, the surface of the platform 122 is flush with the bearing surface, so that the platform 122 and the support rail 112 can cooperate to bear the material tray 200, thereby improving the stability of the material tray 200 during movement. In another embodiment, the surface of the platform 122 is concave relative to the bearing surface, so that when the first conveyor 120 needs to flow through the material tray 200, the material tray 200 can be prevented from contacting the first conveyor 120, thereby improving the smoothness of movement.
[0061] Furthermore, an installation space 123 is formed between the base 121 and the platform 122. The installation space 123 is open on both sides in the length direction of the support rail 112. The two clamping assemblies 150 are both installed in the installation space 123, and part of them extend to the outside from different open sides. The clamping assembly 150 is partially installed in the installation space 123, so that the clamping assembly 150 can be effectively protected and safety hazards can be reduced.
[0062] The clamping assembly 150 includes a first clamping cylinder 151, a transmission block 152 and a first clamping member 153. The first clamping cylinder 151 is fixed in the installation space 123. The first clamping cylinder 151 is a linear cylinder, and its extension direction is parallel to the length direction of the first guide rail structure 110. The transmission block 152 is slidably connected in the installation space 123 and is fixed to the output end of the first clamping cylinder 151. The first clamping member 153 is hinged to the transmission block 152, and the hinge axis is parallel to the width direction of the first guide rail structure 110. The first clamping member 153 is partially located outside the installation space 123 to clamp the material tray 200 on the side of the length direction of the first guide rail structure 110. The first clamping member 153 is suitable for flipping toward the side of the table 122 in the length direction of the first guide rail structure 110 under the drive of the transmission block 152 to drive the clamping assembly 150 to switch to the clamping state, and the first clamping member 153 is suitable for flipping away from the side of the table 122 in the length direction of the first guide rail structure 110 under the drive of the transmission block 152 to drive the clamping assembly 150 to switch to the release state.
[0063] The first clamping member 153 includes a first connecting portion 1531 and a first clamping portion 1532 fixed to the first connecting portion 1531 . One end of the first connecting portion 1531 is hinged to the transmission block 152 through an open side, and the other end extends out of the installation space 123 and is fixedly connected to the first clamping portion 1532 .
[0064] Preferably, an arc-shaped guide groove 1231 is recessed on the inner wall of the installation space 123, and a follower 154 accommodated in the guide groove 1231 is provided on the first clamping member 153. The guide groove 1231 is adapted to the moving path of the first clamping member 153 to guide the rotation of the first clamping member 153, improve the position accuracy of the first clamping member 153, and enable it to flip only under the drive of the first clamping cylinder 151.
[0065] The guide groove 1231 has an upper end and a lower end located below the upper end. When the first clamping cylinder 151 pushes the transmission block 152, the transmission block 152 gradually moves toward the open side of the installation space 123, and the first clamping portion 1532 flips downward and gradually moves away from the open side of the installation space 123 until the follower 154 is at the lower end of the guide groove 1231. At this time, the clamping assembly 150 is in a loosened state, and the first clamping portion 1532 is located below the table 122; when the first clamping cylinder 151 pulls the transmission block 152, the first clamping portion 1532 flips upward and gradually approaches the open side of the installation space 123 until the follower 154 is at the upper end of the guide groove 1231. At this time, the clamping assembly 150 is in a clamping state, and the first clamping portion 1532 is against the side of the tray 200.
[0066] Preferably, when the clamping assembly 150 is in the clamping state, a side of the first clamping portion 1532 that abuts against the tray 200 is perpendicular to the length direction of the first guide rail structure 110 , thereby improving the reliability of clamping the tray 200 .
[0067] In addition, as a preferred embodiment, the clamping assembly 150 also includes a second clamping cylinder 155 and a second clamping member 156. The second clamping cylinder 155 is fixedly connected to the first clamping member 153 and is located outside the installation space 123. The second clamping member 156 is transmission-connected to the second clamping cylinder 155 and is used to limit the top surface of the material tray 200.
[0068] The second clamping member 156 includes a second connecting portion 1561 connected to the second clamping cylinder 155 and a second clamping portion 1562 connected to the second connecting portion 1561. When the clamping assembly 150 is switched to the clamping state, the second clamping portion 1562 is located above the table 122, and the driving direction of the second clamping cylinder 155 is parallel to the vertical direction. The second clamping portion 1562 can approach and contact the top surface of the material tray 200 under the drive of the second clamping cylinder 155 to limit the material tray 200 in the vertical direction. When the clamping assembly 150 is switched to the loose state, the second clamping portion 1562 does not protrude relative to the table surface of the table 122. By adopting the above structure, the reliability of the clamping of the material tray 200 and the stability during the movement can be further improved.
[0069] Furthermore, since the number of loading times of the empty tray 200 is relatively small, the second loading station 100b is usually manually loaded with the tray 200. However, when the first conveyor 120 moves to the second loading station 100b, the operator is likely to directly contact it, thereby causing a safety hazard. Figure 2 , Figure 7 and Figure 8 As shown, a shield assembly 160 is provided on the first guide rail structure 110, and the shield assembly 160 is suitable for opening to place an empty material tray 200 in the second loading station 100b, and the shield assembly 160 is suitable for closing to enclose the second loading station 100b, and the shield assembly 160 is an open side on one side of the length direction of the first guide rail structure 110 to allow the first conveying platform 120 to move into or out of the second loading station 100b.
[0070] With the above structure, after the operator places the material tray 200 on the second loading station 100 b , the shield assembly 160 is closed, thereby effectively isolating the operator from the second loading station 100 b , thereby preventing the operator from being injured during the movement of the first conveyor platform 120 .
[0071] Specifically, the shield assembly 160 includes a lower sealing plate 161 located below the first guide rail structure 110, a first side sealing plate 162 fixed to the top surface of the lower sealing plate 161, and a second side sealing plate 163. The first side sealing plates 162 are two in number and are located on both sides of the first guide rail structure 110 in the width direction, and the second side sealing plate 163 is located on one side of the first guide rail structure 110 in the length direction. The shield assembly 160 also includes an upper cover plate 164 located above the first guide rail structure 110, and the upper cover plate 164 is hingedly matched with one of the side sealing plates to open or close the shield assembly 160. Preferably, a handle 165 is provided on the upper cover plate 164 to improve the convenience of opening and closing.
[0072] Further, refer to Figure 1 and Fig.10 As shown, the material unloading device includes a second conveyor line 300 for receiving and conveying a material tray 200 fully loaded with materials. The first conveyor line 100 and the second conveyor line 300 are arranged side by side, and the conveying directions are parallel.
[0073] The second conveyor line 300 includes: a second guide rail structure 310, used for carrying and guiding the movement of the material tray 200, and the second guide rail structure 310 is provided with a third loading station 300a, a second handling station 300b and a second unloading station 300c in sequence along its length direction; a second conveyor platform 320, suitable for clamping or releasing the material tray 200; a second drive assembly 330, suitable for driving the second conveyor platform 320 to reciprocate between the third loading station 300a, the second handling station 300b and the second unloading station 300c.
[0074] The second guide rail structure 310 is the same as or similar to the first guide rail structure 110, the structure of the second conveyor platform 320 is the same as or similar to the structure of the first conveyor platform 120, and the structure of the second drive component 330 is the same as or similar to the structure of the first drive component 130, which will not be repeated herein.
[0075] The first guide rail structure 110 and the second guide rail structure 310 are arranged side by side and parallel in length direction. The third loading station 300a and the second unloading station 300c are located at both ends of the second guide rail structure 310. The third loading station 300a and the first loading station 100a are located on the same side, and the second unloading station 300c and the second loading station 100b are located on the same side, thereby facilitating the loading and unloading of the material tray 200.
[0076] Further, refer to Figure 1As shown, the material unloading device also includes: a conveying mechanism 400, suitable for conveying unqualified materials in the upper tray 200 of the second conveyor line 300 to the tray 200 of the first conveyor line 100, and conveying qualified materials in the upper tray 200 of the first conveyor line 100 to the tray 200 of the second conveyor line 300; a first stacking mechanism 500, located at the first unloading station 100d, to receive the tray 200 full of unqualified products; a second stacking mechanism 600, arranged at the second unloading station 300c, to receive the tray 200 full of qualified products.
[0077] Preferably, one end of the first guide rail structure 110 and the second guide rail structure 310 are flush in the conveying direction, and the first loading station 100a and the third loading station 300a are not staggered in the conveying direction of the first conveyor line 100 and / or the second conveyor line 300, so as to facilitate the loading operation of the loading structure on the material tray 200 fully loaded with materials; the first handling station 100c and the second handling station 300b are not staggered in the conveying direction of the first conveyor line 100 and / or the second conveyor line 300, so as to facilitate the handling mechanism 400 to transport materials back and forth between the first handling station 100c and the second handling station 300b, thereby improving the handling efficiency; the first unloading station 100d and the second unloading station 300c are not staggered in the conveying direction of the first conveyor line 100 and / or the second conveyor line 300, so as to facilitate the unloading operation.
[0078] Preferably, the length of the first guide rail structure 110 is longer than that of the second guide rail structure 310 , so that the other end of the first guide rail structure 110 protrudes relative to the second guide rail structure 310 in the conveying direction, so that there is enough space for operators to load the empty material tray 200 .
[0079] Furthermore, there are two second conveying platforms 320, and their projections in the length direction of the first guide rail structure 110 and / or the second guide rail structure 310 do not overlap, and the second driving assembly 330 corresponds to the second conveying platforms 320 one by one. With the above structure, the two second conveying platforms 320 can work independently and cooperatively without affecting each other, thereby improving the conveying efficiency of the second conveyor line 300.
[0080] Further, refer to Fig.11 and Fig.12As shown, the transport mechanism 400 includes a transverse movement module 410, a lifting module 420 and at least one pick-and-place member 430. The transverse movement module 410 is a linear module, which is suitable for moving along the width direction of the first guide rail structure 110 and / or the second guide rail structure 310. The lifting module 420 is a linear module, which is suitable for moving along the vertical direction. The lifting module 420 is transmission-connected with the transverse movement module 410 to move under the drive of the transverse movement module 410. The pick-and-place member 430 is specifically a suction nozzle structure, which is used to pick and place materials. The pick-and-place member 430 is transmission-connected with the lifting module 420. Of course, in other embodiments, the transport mechanism 400 may also be provided with other transverse movement structures so that the pick-and-place member 430 can also move along the length direction of the first guide rail structure 110 and / or the second guide rail structure 310.
[0081] Preferably, in order to improve the handling efficiency, multiple pick-and-place parts 430 are arranged at intervals along the length direction of the first guide rail structure 110 and / or the second guide rail structure 310, and there are multiple lifting modules 420, which correspond one-to-one to the pick-and-place parts 430, so that each pick-and-place part 430 can be independently lifted and lowered to pick up and place materials.
[0082] Since the material tray 200 has a plurality of placement slots arranged along the length and width directions of the first guide rail structure 110 and / or the second guide rail structure 310, the material may not be properly placed during the material transportation process, resulting in the material not being completely placed in the placement slots, resulting in poor placement reliability and affecting subsequent stacking.
[0083] Preferably, the transport mechanism 400 further includes a camera assembly 440 which is transmission-connected to the transverse movement module 410 , and the camera assembly 440 is suitable for photographing the material tray 200 to obtain the material status in the material tray 200 .
[0084] Reference Figure 2 , Fig. 9 and Fig.10 As shown, the first guide rail structure 110 is provided with a knocking assembly 170 at the first transport station 100c, and the second guide rail structure 310 is also provided with a knocking assembly 170 at the second transport station 300b. When the material tray 200 is fully loaded with qualified products or unqualified products, the camera assembly 440 is suitable for photographing the material tray 200 to determine whether the materials in the material tray 200 are placed in place, and when they are not placed in place, the knocking assembly 170 is suitable for knocking the material tray 200 to vibrate the materials so that they are completely placed in the placement slot.
[0085] The knocking assembly 170 includes a knocking cylinder 171 fixedly connected to the guide rail structure and a knocking block 172 drivingly connected to the knocking cylinder 171. The knocking cylinder 171 is a linear cylinder, which can drive the knocking block 172 to move along the width direction of the first guide rail structure 110 and / or the second guide rail structure 310, and knock the material tray 200. Preferably, in order to improve the vibration effect, at least two knocking assemblies 170 are provided on the first guide rail structure 110 and the second guide rail structure 310, and the two knocking assemblies 170 are arranged relatively in the width direction of the first guide rail structure 110 and / or the second guide rail structure 310 to cooperate in knocking the material tray 200.
[0086] Further, refer to Figure 1 , Figure 2 , Fig.10 and Fig.13 As shown, the first stacking mechanism 500 and the second stacking mechanism 600 have the same structure. Taking the first stacking mechanism 500 as an example, the first stacking mechanism 500 includes a stacking frame 510, a supporting member 520 and a lifting assembly 530. The top and bottom of the stacking frame 510 are both provided with openings, and the material tray 200 can be stacked and accommodated in the stacking frame 510 from the bottom of the stacking frame 510, or removed from the top of the stacking frame 510. There are multiple supporting members 520, and they are arranged on both sides of the stacking frame 510 in the width direction of the first guide rail structure 110. The supporting members 520 on both sides are suitable for carrying the material tray 200. The supporting member 520 is rotatably connected to the stacking frame 510, so as to flip upward and avoid the material tray 200 during the process of stacking the material tray 200 upward into the stacking frame 510, and when the stacking is completed, the supporting member 520 is suitable for flipping downward under the action of gravity and carrying the stacked material tray 200.
[0087] The lifting assembly 530 is located directly below the stacking frame 510. The lifting assembly 530 includes a lifting module 531 and a lifting member 532 that is transmission-connected to the lifting module 531. The lifting member 532 can lift the tray 200 upward into the stacking frame 510 under the drive of the lifting module 531. The lifting module 531 is a linear module, and the present invention will not be described in detail herein.
[0088] There are two lifting members 532 , which are arranged opposite to each other in the width direction of the first guide rail structure 110 . The two lifting members 532 cooperate to lift the material tray 200 , and the first conveyor platform 120 can move between the two lifting members 532 to be located directly below the material tray 200 .
[0089] The working process of the material unloading device of the present invention is as follows: for the convenience of description, the first conveying platform 120 close to the second loading station 100b is called the front first conveying platform 120, and the first conveying platform 120 close to the first loading station 100a is called the rear first conveying platform 120; initially, the operator loads the empty material tray 200 to the second loading station 100b, and the material tray 200 carrying the material after the inspection is automatically loaded to the first loading station 100a and the third loading station 300a through the loading structure;
[0090] The first conveyor 120 moves so that the front first conveyor 120 moves to the second loading station 100b and clamps the empty material tray 200, and then the first conveyor 120 continues to move so that the rear first conveyor 120 is at the first loading station 100a and clamps the material tray 200 fully loaded with materials, and the front first conveyor 120 is at the first handling station 100c; at the same time, one of the second conveyor 320 moves to the third loading station 300a to clamp the material tray 200 fully loaded with materials and drive it to move to the second handling station 300b;
[0091] Since most of the materials in the tray 200 fully loaded with the inspected materials are qualified products, usually, the conveying mechanism 400 conveys the unqualified materials in the tray 200 of the second conveying station 300b to the tray 200 of the first conveying station 100c. After the conveying is completed, the first conveying platform 120 at the rear end moves to the first conveying station 100c, and the conveying mechanism 400 conveys the qualified materials in the tray 200 of the first conveying station 100c to the tray 200 of the second conveying station 300b. When the tray 200 of the second conveying station 300b is fully loaded with qualified products, the second conveying platform 320 drives the tray 200 to move to the second unloading station 300c for unloading. During this process, the other second conveying platform 320 continues to move to the third loading station 300a to receive a new fully loaded tray 200. The material tray 200, when the material tray 200 fully loaded with qualified products moves to the second unloading station 300c, the new material tray 200 fully loaded with materials moves to the second handling station 300b, so that the handling mechanism 400 continues to perform the handling operation between the first handling station 100c and the second handling station 300b; when the material tray 200 at the first handling station 100c is fully loaded with unqualified products, the first conveyor platform 120 at the rear end moves to the first unloading station 100d to unload the material tray 200, and after the unloading is completed, the first conveyor platform 120 at the rear end moves to the first loading station 100a, and at the same time, the first conveyor platform 120 at the front end is in the first handling station 100c, so as to continue the handling operation; repeat the above steps, so that the material can be continuously transferred and the transfer efficiency is effectively improved.
[0092] The above description is only an implementation method of the present application, and does not limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the description and drawings of this application, or directly or indirectly used in other related technical fields, are also included in the patent protection scope of the present application.
Claims
1. A material unloading device, characterized in that: It comprises a first conveying line (100), wherein the first conveying line (100) comprises: A first guide rail structure (110) is used to carry and guide the material tray (200) to move; the first guide rail structure (110) is provided with a first loading station (100a), a first transporting station (100c), a first unloading station (100d) and a second loading station (100b) in sequence along its length direction; a material tray (200) fully loaded with inspected materials can be loaded to the first loading station (100a), and an empty material tray (200) can be loaded to the second loading station (100b); A first conveying platform (120) adapted to clamp or release a material tray (200); A first driving assembly (130) adapted to drive the first conveying platform (120) to move back and forth between the first loading station (100a), the first transporting station (100c), the first unloading station (100d) and the second loading station (100b); Wherein, the number of the first conveying platforms (120) is two, and they are spaced apart and distributed along the length direction of the first guide rail structure (110); The first loading station (100a) and the second loading station (100b) are respectively arranged at two ends of the first guide rail structure (110); the first conveyor line (100) comprises a mounting seat (140); the mounting seat (140) can be slidably arranged on the first guide rail structure (110) along the length direction of the first guide rail structure (110); the two first conveying platforms (120) are both fixed on the mounting seat (140); the first driving assembly (130) is transmission-connected to the mounting seat (140) to drive the mounting seat (140) to slide; when one of the first conveying platforms (120) corresponds to a station, the other of the first conveying platforms (120) corresponds to a station adjacent to the station; The first guide rail structure (110) comprises: Bracket (111); A support guide rail (112) is fixedly connected to the bracket (111), and its length direction is parallel to the movement direction of the first conveying platform (120); there are two support guide rails (112) and they are arranged opposite to each other along their width direction; the two support guide rails (112) are suitable for supporting the material tray (200) and limiting the material tray (200) in the width direction of the support guide rails (112); Wherein, a receiving area for receiving the first conveying platform (120) is provided between the two supporting guide rails (112); The material unloading device comprises a second conveying line (300) for receiving and conveying a material tray (200) fully loaded with materials, the first conveying line (100) and the second conveying line (300) being arranged side by side, and conveying directions being parallel; The second conveying line (300) comprises: A second guide rail structure (310) is used to carry and guide the material tray (200) to move, and the second guide rail structure (310) is provided with a third loading station (300a), a second transporting station (300b) and a second unloading station (300c) in sequence along its length direction; A second conveying platform (320) adapted to clamp or release the material tray (200); A second driving assembly (330) adapted to drive the second conveying platform (320) to and fro between the third loading station (300a), the second transporting station (300b) and the second unloading station (300c); The number of the second conveying platforms (320) is two, and the projections of the first guide rail structure (110) and / or the second guide rail structure (310) in the length direction do not overlap, and the second driving assembly (330) corresponds to the second conveying platforms (320) one by one; The first guide rail structure (110) and the second guide rail structure (310) are arranged side by side and are parallel in length direction; the third loading station (300a) and the second unloading station (300c) are located at two ends of the second guide rail structure (310); the third loading station (300a) and the first loading station (100a) are located on the same side; and the second unloading station (300c) and the second loading station (100b) are located on the same side; The material unloading device comprises: a transport mechanism (400) adapted to transport unqualified materials in the upper material tray (200) of the second conveyor line (300) to the material tray (200) of the first conveyor line (100), and to transport qualified materials in the upper material tray (200) of the first conveyor line (100) to the material tray (200) of the second conveyor line (300).
2. The material unloading device according to claim 1, characterized in that: A shield assembly (160) is provided on the first guide rail structure (110), and the shield assembly (160) is suitable for opening to place an empty material tray (200) at the second loading station (100b), and the shield assembly (160) is suitable for closing to enclose the second loading station (100b), and the shield assembly (160) is open on one side of the first guide rail structure (110) in the length direction to allow the first conveying platform (120) to move into or out of the second loading station (100b).
3. The material unloading device according to claim 1, characterized in that: The first conveying platform (120) is located below the bearing surface of the supporting guide rail (112). The first conveying platform (120) is provided with clamping assemblies (150) on both sides of the length direction of the first guide rail structure (110). The clamping assembly (150) has a loose state and a clamping state. When the clamping assembly (150) is in the loose state, the clamping assembly (150) is located below the bearing surface of the supporting guide rail (112). When the clamping assembly (150) is in the clamping state, the clamping assembly (150) is at least partially located above the bearing surface of the supporting guide rail (112) to clamp the material tray (200).
4. The material unloading device according to claim 1, characterized in that: The material unloading device also includes: A first stacking mechanism (500) is located at the first unloading station (100d) to receive a material tray (200) fully loaded with defective products; The second stacking mechanism (600) is arranged at the second unloading station (300c) to receive a material tray (200) fully loaded with qualified products.
5. The material unloading device according to claim 4, characterized in that: The transport mechanism (400) comprises: a transverse movement module (410), adapted to move along the width direction of the first guide rail structure (110) and / or the second guide rail structure (310); A lifting module (420) is drivingly connected to the transverse movement module (410) and is suitable for moving in a vertical direction; At least one picking and placing member (430) is transmission-connected to the lifting module (420) for picking and placing materials; The pick-and-place member (430) is suitable for being moved to the first transport station (100c) or the second transport station (300b) under the drive of the transverse movement module (410) and the lifting module (420).