An intelligent drainage method based on big data model
Through the intelligent hydrophobic method based on the big data model, the problem of data redundancy and clutter in the steam pipe network is solved, the hydrophobic status is accurately monitored and dynamically updated, and the efficiency and safety of the hydrophobic treatment are improved.
Patent Information
- Application Number
- CN202410797681.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-20
- Publication Date
- 2024-10-18
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Existing intelligent hydrophobic methods have problems with data redundancy and clutter in steam pipe networks, which increases the difficulty of data analysis and increases errors, affecting the accuracy of hydrophobic state prediction.
An intelligent hydrophobic method based on a big data model is used to collect and preprocess the structural and environmental parameters of the steam pipe network, classify and process abnormal characteristic parameters, build a monitoring model, monitor the hydrophobic status in real time, and match the repair plan based on the real-time recovery offset.
It achieves accurate monitoring and dynamic updating of the hydrophobic status of the steam pipe network, improves the efficiency and safety of hydrophobic treatment, avoids irreparable faults, and ensures the operational safety of the steam pipe network.
Smart Images

Figure CN118361650B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of intelligent drainage of steam pipe networks, and in particular relates to an intelligent drainage method based on a big data model. Background Art
[0002] With the advancement of science and technology and the development of industry, steam pipeline network, as an important energy transmission system, plays a vital role in industrial production, urban heating and other fields. However, during the operation of steam pipeline network, due to pipeline aging, valve damage and other reasons, the problem of poor drainage often occurs, which not only affects the normal operation of steam pipeline network, but also may cause energy waste and safety hazards. Therefore, how to realize intelligent drainage of steam pipeline network, improve drainage efficiency and reduce energy consumption is a problem that needs to be solved urgently.
[0003] Traditional steam pipe network drainage methods mostly rely on manual inspections and empirical judgments, and have problems such as strong subjectivity, low accuracy, and slow response speed. In recent years, with the rapid development of big data technology, new solutions have been provided for the intelligent drainage of steam pipe networks. However, the existing intelligent drainage methods still have some shortcomings. For example, they will collect the overall operating parameters in the steam pipe network. Due to the long time span, the collected data will be too much, and data redundancy and clutter will inevitably occur, which will lead to increased difficulty in data analysis. At the same time, too much data parameter analysis lacks corresponding responses, which will undoubtedly lead to increased errors in data analysis results, which is not conducive to drainage status prediction. Based on this, this scheme provides an intelligent drainage method based on a big data model to solve the above problems. Summary of the invention
[0004] The purpose of the present invention is to provide an intelligent drainage method based on a big data model, which can realize intelligent monitoring and prediction of the drainage status of a steam network, thereby improving the efficiency and safety of drainage treatment.
[0005] The technical solution adopted by the present invention is as follows:
[0006] An intelligent drainage method based on a big data model, comprising:
[0007] Collecting structural parameters and environmental parameters of the steam network, performing preprocessing, and summarizing the preprocessed structural parameters and environmental parameters as reference parameters, wherein the structural parameters include the length of the delivery pipeline, the pipe diameter, the position of the steam trap, the size of the steam trap, and the flow rate of the steam trap, and the environmental parameters include temperature, humidity, and air pressure;
[0008] Acquire a pre-classification condition, and classify the reference parameter according to the pre-classification condition to obtain a normal characteristic parameter and an abnormal characteristic parameter;
[0009] Collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain a first sample collection period and a second sample collection period;
[0010] Building a monitoring model according to the normal characteristic parameters in the first sample collection period, verifying the benchmark parameters collected in real time according to the monitoring model, and outputting a hydrophobic state according to the verification result, wherein the hydrophobic state includes a risk state and a normal state;
[0011] The second sample collection period is arranged according to the occurrence sequence, and the normal characteristic parameters under the second sample collection period are combined and calculated according to the arrangement result, and the calculation result is recorded as a real-time recovery bias, and then the repair plan is matched according to the real-time recovery bias.
[0012] In a preferred embodiment, the step of collecting the structural parameters and environmental parameters of the steam network, preprocessing them, and then aggregating the preprocessed structural parameters and environmental parameters into reference parameters includes:
[0013] Acquire original structural parameters and original environmental parameters of the steam pipe network, and perform denoising on the original structural parameters and original environmental parameters to obtain denoised structural parameters and denoised environmental parameters;
[0014] Normalizing the denoised structural parameters and the denoised environmental parameters to obtain normalized structural parameters and normalized environmental parameters;
[0015] The normalized structural parameters and the normalized environmental parameters are aggregated, and the aggregated results are output as reference parameters.
[0016] In a preferred embodiment, the step of obtaining the pre-classification conditions, and classifying the reference parameters according to the pre-classification conditions to obtain normal characteristic parameters and abnormal characteristic parameters includes:
[0017] Acquire all historical fault data, extract fault features in the historical fault data, and set the fault features as pre-classification conditions;
[0018] Compare the reference parameters with the pre-classification conditions one by one, and classify the reference parameters according to the comparison results to obtain normal characteristic parameters and characteristic parameters to be verified;
[0019] Obtaining the normal parameter interval corresponding to each of the characteristic parameters to be verified;
[0020] If the characteristic parameter to be checked belongs to the normal parameter range, the characteristic parameter to be checked is marked as an accidental abnormality;
[0021] If the characteristic parameter to be checked does not belong to the normal parameter range, the characteristic parameter to be checked is directly calibrated as an abnormal characteristic parameter.
[0022] In a preferred embodiment, the step of collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain the first sample collection period and the second sample collection period includes:
[0023] Obtaining the occurrence node and recovery node of the abnormal characteristic parameter in the steam pipe network;
[0024] Performing backtracking offset processing with the occurrence node as the end point to obtain a backtracking period, and arranging normal characteristic parameters within the backtracking period according to the occurrence time sequence;
[0025] Performing difference processing on adjacent normal characteristic parameters within the backtracking period, recording the difference result as a sample fluctuation parameter, and outputting a first sample collection period according to the sample fluctuation parameter;
[0026] A fixed offset duration is obtained, and based on the fixed offset duration, an offset is performed with the recovery node as a starting point, and the offset result is recorded as a second sample collection period.
[0027] In a preferred embodiment, the step of outputting the first sample collection period according to the sample fluctuation parameter includes:
[0028] Obtaining a normal fluctuation interval, and comparing the normal fluctuation interval with a sample fluctuation parameter;
[0029] If the sample fluctuation parameter belongs to the normal fluctuation range, the corresponding backtracking period is marked as the first offset period;
[0030] If the sample fluctuation parameter does not belong to the normal fluctuation range, the abnormal fluctuation duration is calculated according to the sample fluctuation parameter, and the abnormal fluctuation duration is calibrated as the time period offset, and the occurrence node is backtracked according to the time period offset, and the backtracking result is recorded as the offset time period;
[0031] All offset periods are sorted according to their time lengths, and the offset period with the largest time length is marked as the first sample collection period.
[0032] In a preferred embodiment, the step of constructing a monitoring model according to normal characteristic parameters during the first sample collection period includes:
[0033] Selecting normal characteristic parameters within the first sample collection period as training samples;
[0034] Acquire an initial neural network model, and train the initial neural network model according to the training sample to obtain a trained neural network model;
[0035] Performing cross validation on the trained neural network model;
[0036] If the verification is passed, the trained neural network model is calibrated as a monitoring model;
[0037] If the verification fails, reselect the training samples and perform training again until the verification passes.
[0038] In a preferred embodiment, the step of verifying the benchmark parameters collected in real time according to the monitoring model and outputting the hydrophobic state according to the verification result includes:
[0039] Obtain the benchmark parameters of the current node and input them into the monitoring model for verification;
[0040] If the benchmark parameters at the current node pass the verification, it indicates that the steam network drainage tends to be abnormal, and the drainage state is output as a risk state, and;
[0041] If the reference parameter at the current node fails to pass the verification, it indicates that the steam network drain is output normally, and the drain state is output as a normal state;
[0042] In the normal state, the steam pipe network continues to be monitored in real time, and the drainage state of the steam pipe network is dynamically updated according to the benchmark parameters collected in real time;
[0043] Under the risk state, an alarm signal is synchronously issued, and the steam pipe network is subjected to emergency drainage treatment until the drainage state is restored to a normal state.
[0044] In a preferred solution, the step of matching the repair solution according to the real-time recovery offset includes:
[0045] Obtaining normal characteristic parameters in each of the second sample collection periods, and recording them as conditional parameters;
[0046] Obtaining a calculation function, inputting the conditional parameters into the calculation function, and calibrating an output result of the calculation function as a real-time recovery bias;
[0047] Obtaining an evaluation threshold, and comparing the evaluation threshold with a real-time recovery bias;
[0048] If the real-time recovery deviation is greater than the evaluation threshold, it indicates that the subsequent recovery of the steam network is effective, and the drainage state of the steam network continues to be monitored;
[0049] If the real-time recovery deviation is less than or equal to the evaluation threshold, it indicates that the subsequent recovery of the steam network is invalid, and a repair plan is matched from a preset repair plan database.
[0050] The present invention also provides an intelligent drainage system based on a big data model, using the above-mentioned intelligent drainage method based on a big data model, comprising:
[0051] A parameter collection module, which is used to collect structural parameters and environmental parameters of the steam network, perform preprocessing, and then summarize the preprocessed structural parameters and environmental parameters as reference parameters, wherein the structural parameters include the length of the delivery pipeline, the diameter of the pipe, the position of the steam trap, the size of the steam trap and the flow rate of the steam trap, and the environmental parameters include temperature, humidity and air pressure;
[0052] A parameter classification module, the parameter classification module is used to obtain a pre-classification condition, and classify the reference parameters according to the pre-classification condition to obtain normal characteristic parameters and abnormal characteristic parameters;
[0053] A time period construction module, the time period construction module is used to collect the occurrence node and the recovery node of the abnormal characteristic parameter, and perform offset processing on the occurrence node and the recovery node to obtain a first sample collection time period and a second sample collection time period;
[0054] A real-time monitoring module, the real-time monitoring module is used to build a monitoring model according to the normal characteristic parameters in the first sample collection period, and verify the benchmark parameters collected in real time according to the monitoring model, and output a hydrophobic state according to the verification result, wherein the hydrophobic state includes a risk state and a normal state;
[0055] A recovery evaluation module is used to arrange the second sample collection period according to the occurrence sequence, and perform a combined operation on the normal characteristic parameters under the second sample collection period according to the arrangement result, and record the operation result as a real-time recovery bias, and then match the repair plan according to the real-time recovery bias.
[0056] And, an electronic device, the electronic device comprising:
[0057] at least one processor;
[0058] and a memory communicatively coupled to the at least one processor;
[0059] Wherein, the memory stores a computer program that can be executed by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the above-mentioned intelligent hydrophobic method based on the big data model.
[0060] The technical effects achieved by the present invention are:
[0061] The present invention collects and preprocesses the baseline parameters of the steam pipeline network, classifies them using pre-classification conditions, effectively distinguishes normal characteristic parameters from abnormal characteristic parameters, and constructs a first sample collection period and a second sample collection period by offsetting the occurrence nodes and recovery nodes of the abnormal characteristic parameters. When constructing a monitoring model, normal characteristic parameters within the first sample collection period are selected as training samples, and a neural network model for the normal characteristic parameters before the abnormality occurs is output. The monitoring model can be used to more accurately output the drainage state of the pipeline network, thereby realizing real-time monitoring and dynamic updating of the drainage state of the steam pipeline network. In addition, a repair plan is matched according to the real-time recovery offset to avoid irreparable failures in the pipeline network and ensure the operational safety of the steam pipeline network. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] Figure 1 is a flow chart of the method of the present invention;
[0063] Figure 2 It is a system module diagram of the present invention;
[0064] Figure 3 It is a structural diagram of an electronic device of the present invention. DETAILED DESCRIPTION
[0065] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.
[0066] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.
[0067] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. The phrase "in a preferred embodiment" that appears in different places in this specification does not refer to the same embodiment, nor is it a separate or selective embodiment that is mutually exclusive with other embodiments.
[0068] See also Figure 1 As shown, the present invention provides an intelligent drainage method based on a big data model, comprising:
[0069] S1. Collecting structural parameters and environmental parameters of the steam network, preprocessing them, and summarizing the preprocessed structural parameters and environmental parameters as benchmark parameters, wherein the structural parameters include the length of the transmission pipeline, the pipe diameter, the position of the steam trap, the size of the steam trap, and the flow rate of the steam trap, and the environmental parameters include temperature, humidity, and air pressure;
[0070] S2. Obtaining pre-classification conditions, and classifying the reference parameters according to the pre-classification conditions to obtain normal feature parameters and abnormal feature parameters;
[0071] S3, collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain a first sample collection period and a second sample collection period;
[0072] S4, constructing a monitoring model according to the normal characteristic parameters in the first sample collection period, verifying the benchmark parameters collected in real time according to the monitoring model, and outputting a hydrophobic state according to the verification result, wherein the hydrophobic state includes a risk state and a normal state;
[0073] S5. Arrange the second sample collection period according to the occurrence sequence, and perform a combined operation on the normal characteristic parameters in the second sample collection period according to the arrangement result, and record the operation result as a real-time recovery bias, and then match the repair plan according to the real-time recovery bias.
[0074] As described in the above steps S1-S5, the steam network, as an important energy transmission system, plays a vital role in industrial production, urban heating and other fields. In this embodiment, the structural parameters and environmental parameters of the steam network are first collected. The structural parameters include the length of the transmission pipeline, the diameter of the pipe, the position of the steam trap, the size of the steam trap and the flow rate of the steam trap. These parameters affect the operation status and efficiency of the steam network. The environmental parameters mainly include temperature, humidity and air pressure. Environmental changes will affect the operation of the steam network. After collecting these data, it is necessary to pre-process the data. The pre-processed structural parameters and environmental parameters need to be summarized as benchmark parameters. These benchmark parameters will serve as the basis for subsequent analysis. Then, the preset pre-classification conditions are obtained, and the benchmark parameters are classified. The purpose of the classification is to divide the data into normal characteristic parameters and abnormal characteristic parameters, which is conducive to targeted processing of abnormal situations. After obtaining the normal characteristic parameters and abnormal characteristic parameters, it is necessary The occurrence nodes and recovery nodes of abnormal characteristic parameters are collected. The occurrence nodes and recovery nodes are the moments when the abnormal situation occurs and recovers. At the same time, the occurrence nodes and recovery nodes are offset to obtain the first sample collection period and the second sample collection period, and a monitoring model is constructed based on the normal characteristic parameters under the first sample collection period. Based on the real-time benchmark parameters, the monitoring model is used to predict the drainage state. The drainage state includes the risk state and the normal state. After the second sample collection period is constructed, the second sample collection period needs to be arranged according to the occurrence sequence. The normal characteristic parameters under the arranged second sample collection period need to be combined and calculated, and the calculation results are recorded as real-time recovery deviations. Based on this real-time recovery deviation, it can be used to determine whether the steam pipeline network can be repaired normally. When the repair cannot be completed normally, the corresponding repair plan is matched, such as replacement of the steam trap and maintenance of the transmission pipeline, etc., to effectively avoid freezing and blockage of the transmission pipeline.
[0075] In a preferred embodiment, the steps of collecting the structural parameters and environmental parameters of the steam network, preprocessing them, and then aggregating the preprocessed structural parameters and environmental parameters into reference parameters include:
[0076] S101, obtaining original structural parameters and original environmental parameters of the steam pipe network, and performing denoising on the original structural parameters and original environmental parameters to obtain denoised structural parameters and denoised environmental parameters;
[0077] S102, normalizing the denoised structural parameters and the denoised environmental parameters to obtain normalized structural parameters and normalized environmental parameters;
[0078] S103: Summarize the normalized structural parameters and the normalized environmental parameters, and output the summary results as reference parameters.
[0079] As described in the above steps S101-S103, when collecting the structural parameters and environmental parameters of the steam pipe network, the first thing to do is to collect the original parameters, which include the structural parameters and environmental parameters of the steam pipe network. The structural parameters mainly include the layout of the pipe network, pipe materials, pipe diameter, etc., and the environmental parameters include temperature, pressure, humidity, etc. After collecting the original parameters, they need to be preprocessed. The main purpose of the preprocessing is to remove noise and obtain clean structural parameters and environmental parameters. Noise may be caused by various factors, such as measurement errors, environmental interference, etc. De-noising can be performed by filtering algorithms, interpolation algorithms, etc. After obtaining the denoised structural parameters and environmental parameters, they need to be normalized to unify the various parameters to the same scale for subsequent analysis. Finally, the normalized structural parameters and environmental parameters are summarized and processed to obtain a benchmark parameter that can reflect the overall operation of the steam pipe network.
[0080] In a preferred embodiment, the steps of obtaining the pre-classification conditions, and classifying the reference parameters according to the pre-classification conditions to obtain the normal characteristic parameters and the abnormal characteristic parameters include:
[0081] S201, acquiring all historical fault data, extracting fault features in the historical fault data, and setting the fault features as pre-classification conditions;
[0082] S202, comparing the reference parameters with the pre-classification conditions one by one, and classifying the reference parameters according to the comparison results to obtain normal characteristic parameters and characteristic parameters to be verified;
[0083] S203, obtaining a normal parameter range corresponding to each characteristic parameter to be verified;
[0084] If the characteristic parameter to be checked belongs to the normal parameter range, the characteristic parameter to be checked is marked as an accidental abnormality;
[0085] If the characteristic parameter to be checked does not belong to the normal parameter range, the characteristic parameter to be checked is directly calibrated as an abnormal characteristic parameter.
[0086] As described in the above steps S201-S203, before the benchmark parameters are determined, all historical fault data need to be collected. These historical fault data contain the performance and characteristics of the equipment under different fault conditions, and the fault characteristics are extracted from these historical fault data as the pre-classification conditions. The fault characteristics can be abnormal values of parameters such as temperature, speed, pressure, etc. After the fault characteristics are extracted, these characteristics will be compared with the benchmark parameters one by one. According to the comparison results, the benchmark parameters can be divided into two categories: normal characteristic parameters and characteristic parameters to be verified. Then, it is necessary to determine the normal parameter interval corresponding to each characteristic parameter to be verified. This normal parameter interval can be determined based on the statistical analysis of historical data, so as to clarify the range of the pipeline network under normal operation, and on this basis, it is judged whether the characteristic parameter to be verified belongs to the normal range. If the characteristic parameter to be verified belongs to the normal parameter interval, it is considered that this is an accidental abnormality, which may be caused by temporary external factors. Specifically, the normal operation of the pipeline network can be ensured by strengthening monitoring, adjusting equipment parameters, etc. However, if the characteristic parameter to be verified does not belong to the normal parameter interval, then this means that there is a fault in the pipeline network, and the characteristic parameter to be verified is calibrated as an abnormal characteristic parameter.
[0087] In a preferred embodiment, the step of collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain the first sample collection period and the second sample collection period includes:
[0088] S301, obtaining occurrence nodes and recovery nodes of abnormal characteristic parameters in the steam network;
[0089] S302, performing backtracking offset processing with the occurrence node as the end point to obtain a backtracking period, and arranging normal characteristic parameters within the backtracking period according to the occurrence time sequence;
[0090] S303, performing difference processing on adjacent normal characteristic parameters within the backtracking period, recording the difference result as a sample fluctuation parameter, and outputting the first sample collection period according to the sample fluctuation parameter;
[0091] S304: Obtain a fixed offset duration, and perform an offset based on the fixed offset duration with the recovery node as the starting point, and record the offset result as a second sample collection period.
[0092] As described in the above steps S301-S304, after the abnormal characteristic parameters are classified, the occurrence node and the recovery node of the abnormal characteristic parameters are synchronously obtained, and the occurrence node and the recovery node are offset, and the first sample collection period and the second sample collection period are obtained. The occurrence node refers to the time node when the abnormal characteristic parameters occur, and the recovery node is the time node when the abnormal characteristic parameters are recovered. After determining the occurrence node and the recovery node, offset processing is required. First, backtracking offset processing is performed with the occurrence node as the end point, that is, backtracking to a period of time before the abnormal characteristic parameters occur. The time length of the first backtracking offset is a fixed length, which can be set according to the duration of the pipeline network maintenance requirement. The normal time period within the backtracking period is The normal characteristic parameters are arranged in chronological order, and then the adjacent normal characteristic parameters in the retrospective period are differenced, and the difference results are recorded as sample fluctuation parameters. The sample fluctuation parameters reflect the changes in the normal characteristic parameters of the pipeline network before the abnormality occurs. Then, the first sample collection period can be output based on the sample fluctuation parameters. At the same time, a fixed offset duration needs to be set, and a forward offset is performed with the recovery node as the starting point. The offset result is recorded as the second sample collection period. The second sample collection period covers the pipeline network operation parameters after the abnormal characteristic parameters are restored. Through such offset processing, the pipeline network characteristic parameters before and after the occurrence of the abnormal characteristic parameters can be obtained respectively, providing corresponding data support for subsequent analysis and repair.
[0093] In a preferred embodiment, the step of outputting the first sample collection period according to the sample fluctuation parameter includes:
[0094] Obtain the normal fluctuation range and compare the normal fluctuation range with the sample fluctuation parameter;
[0095] If the sample volatility parameter belongs to the normal volatility range, the corresponding lookback period is marked as the first offset period;
[0096] If the sample fluctuation parameter does not belong to the normal fluctuation range, the abnormal fluctuation duration is calculated based on the sample fluctuation parameter, and the abnormal fluctuation duration is calibrated as the time period offset. The occurrence node is backtracked based on the time period offset, and the backtracking result is recorded as the offset period;
[0097] All offset periods are sorted according to their time lengths, and the offset period with the largest time length is marked as the first sample collection period.
[0098] In this embodiment, when determining the first sample collection period, it is necessary to analyze based on the sample fluctuation parameter. First, it is necessary to obtain the normal fluctuation range, the normal range of allowable data fluctuation, which can be determined based on historical data or professional experience. Then, it is necessary to compare the sample fluctuation parameter with the normal fluctuation range to determine whether the sample fluctuation parameter is within the normal range. If the sample fluctuation parameter is within the normal fluctuation range, then the corresponding backtracking period will be directly calibrated as the first offset period. If the sample fluctuation parameter is not within the normal fluctuation range, it is necessary to calculate the abnormal fluctuation duration, and the calculation formula is: , where Indicates the duration of abnormal fluctuations. Represents abnormal characteristic parameters, Indicates the lower limit of the normal fluctuation range. represents the number of sample fluctuation parameters, and Represents adjacent sample fluctuation parameters. According to the calculated abnormal fluctuation duration, it is calibrated as a time period offset. Based on the time period offset, the node where the abnormal fluctuation occurs is traced back to the time when the abnormal fluctuation occurs, so as to obtain the offset time period. After obtaining all the offset time periods, they need to be sorted according to the time length, and the offset time period with the largest time length is found as the first sample collection time period. Here, it should be made clear that the time length of the first sample time period is not less than the backtracking period, otherwise the backtracking period will be used as the first sample collection period.
[0099] In a preferred embodiment, the step of constructing a monitoring model according to normal characteristic parameters during the first sample collection period includes:
[0100] S401, selecting normal feature parameters within the first sample collection period as training samples;
[0101] S402, obtaining an initial neural network model, and training the initial neural network model according to the training sample to obtain a trained neural network model;
[0102] S403, cross-validating the trained neural network model;
[0103] If the verification is successful, the trained neural network model is calibrated as the monitoring model;
[0104] If the verification fails, reselect the training samples and perform training again until the verification passes.
[0105] As described in the above steps S401-S403, when constructing a monitoring model to deal with normal feature parameters in the first sample collection period, it is first necessary to call the normal feature parameters from the first sample collection period and use the normal feature parameters as training samples. Then, an initial neural network model is obtained, and the initial neural network model is trained using the training samples. During the training process, the neural network model will be cross-validated, and the training data will be divided into multiple subsets, one of which is used as a validation set each time, and the remaining subsets are used as training sets. By comparing the prediction performance of the model on the training set and the validation set, the generalization ability of the model can be judged. If the validation passes, that is, the performance of the model on the validation set meets expectations, the trained neural network model can be calibrated as a monitoring model. If the validation fails, it means that the model performs poorly on unknown data and the training strategy needs to be readjusted. At this time, it is necessary to re-select training samples and train the neural network model again. Repeat the cross-validation until the model passes the validation and stops until the expected effect is achieved.
[0106] In a preferred embodiment, the step of verifying the benchmark parameters collected in real time according to the monitoring model and outputting the hydrophobic state according to the verification result includes:
[0107] S404, obtaining the benchmark parameters of the current node and inputting them into the monitoring model for verification;
[0108] S405. If the benchmark parameters at the current node pass the verification, it indicates that the steam network drainage tends to be abnormal, and the drainage state is output as a risk state, and;
[0109] S406. If the reference parameter at the current node fails to pass the verification, it indicates that the steam network drain is output normally, and the drain state is output as a normal state;
[0110] S407, under normal conditions, continue to monitor the steam pipe network in real time, and dynamically update the drainage status of the steam pipe network according to the benchmark parameters collected in real time;
[0111] S408. Under risk conditions, an alarm signal is issued synchronously, and the steam network is emergency drained until the drain state returns to normal.
[0112] As described in the above steps S404-S408, after the monitoring model is built, the benchmark parameters at the current node are obtained in real time and input into the monitoring model for verification. If the benchmark parameters at the current node pass the verification, that is, these normal characteristic parameters are within the normal range of the first sample sampling period, it indicates that the drainage state of the steam pipe network tends to be abnormal. At this time, it is necessary to output the drainage state as a risk state, and simultaneously send out an alarm signal to remind relevant personnel to take timely measures to avoid freezing and blockage of the pipe network. Specifically, emergency drainage treatment can be performed until the drainage state is restored to a normal state to ensure the safe and stable operation of the steam pipe network. On the contrary, if the benchmark parameters at the current node fail to pass the verification, indicating that they are not within the normal range, then this indicates that the drainage state of the steam pipe network is normal. Of course, it also needs to be compared with the normal operating parameters of the pipe network to avoid the occurrence of accidental abnormalities. After eliminating accidental abnormalities, the drainage state is output as a normal state, and the steam pipe network continues to be monitored in real time to ensure its normal operation. The drainage state of the steam pipe network is dynamically updated according to the benchmark parameters collected in real time, so as to respond to changes in the steam pipe network in a timely manner.
[0113] In a preferred embodiment, the steps of the real-time recovery offset matching repair solution include:
[0114] S501, obtaining normal characteristic parameters in each second sample collection period, and recording them as conditional parameters;
[0115] S502, obtaining a calculation function, inputting conditional parameters into the calculation function, and calibrating an output result of the calculation function as a real-time recovery bias;
[0116] S503, obtaining an evaluation threshold, and comparing the evaluation threshold with the real-time recovery bias;
[0117] If the real-time recovery deviation is greater than the evaluation threshold, it indicates that the subsequent recovery of the steam network is effective, and the drainage status of the steam network continues to be monitored;
[0118] If the real-time recovery deviation is less than or equal to the evaluation threshold, it indicates that the subsequent recovery of the steam network is invalid, and a repair plan is matched from the preset repair plan database.
[0119] As described in the above steps S501-S503, after the second sample collection period is output, it is necessary to obtain normal characteristic parameters in each second sample collection period, and use these normal characteristic parameters as conditional parameters. Specifically, it is necessary to obtain a measurement function, and input the conditional parameters into the measurement function for calculation, wherein the expression of the measurement function is: , where Indicates real-time recovery bias. Indicates the recovery deviation after the last pipe network abnormality occurred. Indicates the amount of deviation recovered after historical anomaly recovery. and Both represent the recovery deviation after the recovery of historical anomalies. After the real-time recovery deviation is output, we need to set an evaluation threshold and compare the calculated real-time recovery deviation with the evaluation threshold to determine whether the recovery of the steam network has achieved the expected effect. If the real-time recovery deviation is greater than the evaluation threshold, it means that the subsequent recovery effect of the steam network is good, and the drainage status of the steam network can continue to be monitored. At this stage, it is necessary to continue to maintain real-time monitoring of the drainage status of the steam network. On the contrary, if the real-time recovery deviation is less than or equal to the evaluation threshold, it means that the recovery effect of the steam network is not good, and corresponding repair measures need to be taken, such as replacing the steam trap, cleaning the pipeline, etc. Specifically, it is necessary to match the appropriate repair plan from the preset repair plan database to improve the operation efficiency of the steam network.
[0120] See also Figure 2 , an intelligent drainage system based on a big data model, using the above-mentioned intelligent drainage method based on a big data model, comprising:
[0121] Parameter collection module, which is used to collect structural parameters and environmental parameters of the steam network, perform preprocessing, and then summarize the preprocessed structural parameters and environmental parameters as reference parameters, wherein the structural parameters include the length of the transmission pipeline, the diameter, the position of the steam trap, the size of the steam trap and the flow rate of the steam trap, and the environmental parameters include temperature, humidity and air pressure;
[0122] The parameter classification module is used to obtain the pre-classification conditions and classify the reference parameters according to the pre-classification conditions to obtain normal characteristic parameters and abnormal characteristic parameters;
[0123] A time period construction module, which is used to collect occurrence nodes and recovery nodes of abnormal characteristic parameters, and perform offset processing on the occurrence nodes and the recovery nodes to obtain a first sample collection time period and a second sample collection time period;
[0124] A real-time monitoring module, which is used to build a monitoring model based on the normal characteristic parameters in the first sample collection period, verify the benchmark parameters collected in real time based on the monitoring model, and output a hydrophobic state based on the verification result, wherein the hydrophobic state includes a risk state and a normal state;
[0125] The recovery evaluation module is used to arrange the second sample collection period according to the occurrence sequence, and perform combined operation on the normal characteristic parameters under the second sample collection period according to the arrangement result, and record the operation result as the real-time recovery bias, and then match the repair plan according to the real-time recovery bias.
[0126] As mentioned above, the steam trap system includes a parameter acquisition module, a parameter classification module, a time period construction module, a real-time monitoring module and a recovery evaluation module. The parameter acquisition module is responsible for collecting the structural parameters and environmental parameters of the steam network, such as the length of the transmission pipeline, the diameter, the position of the steam trap, the size of the steam trap and the flow rate of the steam trap, and preprocessing these data. The preprocessed structural parameters and environmental parameters will be summarized as benchmark parameters to provide basic data for subsequent analysis. The parameter classification module is responsible for obtaining the pre-classification conditions, classifying the benchmark parameters according to these conditions, and obtaining normal characteristic parameters and abnormal characteristic parameters, which provide a basis for subsequent fault diagnosis and early warning. The time period construction module is responsible for collecting the occurrence nodes and recovery nodes of abnormal characteristic parameters. These nodes are offset to obtain the first sample collection period and the second sample collection period. The real-time monitoring module constructs a monitoring model based on the normal characteristic parameters under the first sample collection period, and uses the monitoring model to verify the benchmark parameters collected in real time. The verification results will be used to judge the drainage state, including the risk state and the normal state, which will help to monitor the operation status of the steam pipeline network in real time and ensure the safe and stable operation of the system. The recovery evaluation module is responsible for arranging the second sample collection period according to the occurrence sequence, and combining the normal characteristic parameters according to the arrangement results. The calculation results are recorded as real-time recovery deviations. According to the real-time recovery deviations, the system can match the best repair plan, thereby realizing the rapid recovery of the steam pipeline network.
[0127] See also Figure 3 , an electronic device, the electronic device comprising:
[0128] at least one processor;
[0129] and a memory communicatively coupled to the at least one processor;
[0130] The memory stores a computer program that can be executed by at least one processor, and the computer program is executed by at least one processor so that the at least one processor can execute the above-mentioned intelligent hydrophobic method based on the big data model.
[0131] The electronic device includes at least one processor and a memory connected to the processor in communication. The memory stores computer programs, and when these programs are executed by the processor, the aforementioned intelligent drainage method based on the big data model can be executed. This electronic device can be a device specifically used to perform intelligent drainage functions, or it can be a general-purpose device with multiple functions, such as a server, a workstation, a personal computer or an intelligent mobile device. By running the computer program stored in the memory, the electronic device can collect the operating data of the steam network in real time, and process, analyze and judge it, so as to realize intelligent monitoring and recovery evaluation of the drainage status of the steam network. In addition, the electronic device can also be equipped with a network interface to communicate with other devices or systems to realize data sharing and collaborative work. At the same time, in order to ensure the security and integrity of the data, the electronic device can also adopt encryption technology, permission control and other security measures to ensure that the data is not illegally accessed or tampered with during transmission and storage.
[0132] The electronic device also includes an input device and an output device. The input device is used to receive instructions and data input by the user so that the user can interact with the system. The output device is used to display processing results and related information so that the user can intuitively understand the drainage status of the steam network and the operation of the system. Through these input and output devices, the user can conveniently operate the electronic device to realize various functions of the intelligent drainage system;
[0133] And, an operator for performing various arithmetic and logical operations to support the processor's processing and analysis of data, which can be an arithmetic logic unit (ALU) in a central processing unit (CPU), responsible for performing various arithmetic operations (such as addition, subtraction, multiplication, and division) and logical operations (such as AND, OR, and NOT), thereby supporting the processor's processing and analysis of steam network operation data. These operations include but are not limited to preprocessing, classification processing, and combined operations of structural parameters and environmental parameters to generate key data such as baseline parameters, normal characteristic parameters, abnormal characteristic parameters, and real-time recovery deviations.
[0134] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, device, article or method including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, device, article or method. In the absence of further restrictions, an element defined by the sentence "includes a ..." does not exclude the presence of other identical elements in the process, device, article or method including the element.
[0135] The above is only a preferred embodiment of the present invention. It should be noted that, for those skilled in the art, several improvements and modifications can be made without departing from the principles of the present invention, and these improvements and modifications should also be considered as the protection scope of the present invention. The structures, devices and operating methods not specifically described and explained in the present invention shall be implemented according to the conventional means in the art unless otherwise specified and limited.
Claims
1. An intelligent drainage method based on a big data model, characterized in that: include: Collecting structural parameters and environmental parameters of the steam network, performing preprocessing, and summarizing the preprocessed structural parameters and environmental parameters as reference parameters, wherein the structural parameters include the length of the delivery pipeline, the pipe diameter, the position of the steam trap, the size of the steam trap, and the flow rate of the steam trap, and the environmental parameters include temperature, humidity, and air pressure; Acquire a pre-classification condition, and classify the reference parameter according to the pre-classification condition to obtain a normal characteristic parameter and an abnormal characteristic parameter; Collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain a first sample collection period and a second sample collection period; Building a monitoring model according to the normal characteristic parameters in the first sample collection period, verifying the benchmark parameters collected in real time according to the monitoring model, and outputting a hydrophobic state according to the verification result, wherein the hydrophobic state includes a risk state and a normal state; Arrange the second sample collection period according to the occurrence time sequence, and perform a combined operation on the normal characteristic parameters in the second sample collection period according to the arrangement result, and record the operation result as a real-time recovery offset, and then match the repair solution according to the real-time recovery offset; The step of collecting the structural parameters and environmental parameters of the steam network, preprocessing them, and then aggregating the preprocessed structural parameters and environmental parameters into reference parameters includes: Acquire original structural parameters and original environmental parameters of the steam pipe network, and perform denoising on the original structural parameters and original environmental parameters to obtain denoised structural parameters and denoised environmental parameters; Normalizing the denoised structural parameters and the denoised environmental parameters to obtain normalized structural parameters and normalized environmental parameters; Summarizing the normalized structural parameters and the normalized environmental parameters, and outputting the summary results as reference parameters; The step of obtaining the pre-classification conditions, and classifying the reference parameters according to the pre-classification conditions to obtain normal characteristic parameters and abnormal characteristic parameters includes: Acquire all historical fault data, extract fault features in the historical fault data, and set the fault features as pre-classification conditions; Compare the reference parameters with the pre-classification conditions one by one, and classify the reference parameters according to the comparison results to obtain normal characteristic parameters and characteristic parameters to be verified; Obtaining the normal parameter interval corresponding to each of the characteristic parameters to be verified; If the characteristic parameter to be checked belongs to the normal parameter range, the characteristic parameter to be checked is marked as an accidental abnormality; If the characteristic parameter to be checked does not belong to the normal parameter range, the characteristic parameter to be checked is directly marked as an abnormal characteristic parameter; The step of collecting the occurrence node and the recovery node of the abnormal characteristic parameter, and performing offset processing on the occurrence node and the recovery node to obtain the first sample collection period and the second sample collection period includes: Obtaining the occurrence node and recovery node of the abnormal characteristic parameter in the steam pipe network; Performing backtracking offset processing with the occurrence node as the end point to obtain a backtracking period, and arranging normal characteristic parameters within the backtracking period according to the occurrence time sequence; Performing difference processing on adjacent normal characteristic parameters within the backtracking period, recording the difference result as a sample fluctuation parameter, and outputting a first sample collection period according to the sample fluctuation parameter; Obtaining a fixed offset duration, and performing an offset based on the fixed offset duration with the recovery node as a starting point, and recording the offset result as a second sample collection period; The step of outputting the first sample collection period according to the sample fluctuation parameter comprises: Obtaining a normal fluctuation interval, and comparing the normal fluctuation interval with a sample fluctuation parameter; If the sample fluctuation parameter belongs to the normal fluctuation range, the corresponding backtracking period is marked as the first offset period; If the sample fluctuation parameter does not belong to the normal fluctuation range, the abnormal fluctuation duration is calculated according to the sample fluctuation parameter, and the abnormal fluctuation duration is calibrated as the time period offset, and the occurrence node is backtracked according to the time period offset, and the backtracking result is recorded as the offset time period; All offset periods are sorted according to their time lengths, and the offset period with the largest time length is marked as the first sample collection period.
2. The intelligent drainage method based on big data model according to claim 1, characterized in that: The step of constructing a monitoring model according to the normal characteristic parameters in the first sample collection period includes: Selecting normal characteristic parameters within the first sample collection period as training samples; Acquire an initial neural network model, and train the initial neural network model according to the training sample to obtain a trained neural network model; Performing cross validation on the trained neural network model; If the verification is passed, the trained neural network model is calibrated as a monitoring model; If the verification fails, reselect the training samples and perform training again until the verification passes.
3. The intelligent drainage method based on big data model according to claim 1, characterized in that: The step of verifying the benchmark parameters collected in real time according to the monitoring model and outputting the hydrophobic state according to the verification result includes: Obtain the benchmark parameters of the current node and input them into the monitoring model for verification; If the benchmark parameters at the current node pass the verification, it indicates that the steam network drainage tends to be abnormal, and the drainage state is output as a risk state, and; If the reference parameter at the current node fails to pass the verification, it indicates that the steam network drain is output normally, and the drain state is output as a normal state; In the normal state, the steam pipe network continues to be monitored in real time, and the drainage state of the steam pipe network is dynamically updated according to the benchmark parameters collected in real time; Under the risk state, an alarm signal is synchronously issued, and the steam pipe network is subjected to emergency drainage treatment until the drainage state is restored to a normal state.
4. The intelligent drainage method based on big data model according to claim 1, characterized in that: The step of matching the repair solution according to the real-time recovery offset includes: Obtaining normal characteristic parameters in each of the second sample collection periods, and recording them as conditional parameters; Obtaining a calculation function, inputting the conditional parameters into the calculation function, and calibrating an output result of the calculation function as a real-time recovery bias; Obtaining an evaluation threshold, and comparing the evaluation threshold with a real-time recovery bias; If the real-time recovery deviation is greater than the evaluation threshold, it indicates that the subsequent recovery of the steam network is effective, and the drainage state of the steam network continues to be monitored; If the real-time recovery deviation is less than or equal to the evaluation threshold, it indicates that the subsequent recovery of the steam network is invalid, and a repair plan is matched from a preset repair plan database.
5. An intelligent drainage system based on a big data model, using the intelligent drainage method based on a big data model according to any one of claims 1 to 4, characterized in that: include: A parameter collection module, which is used to collect structural parameters and environmental parameters of the steam network, perform preprocessing, and then summarize the preprocessed structural parameters and environmental parameters as reference parameters, wherein the structural parameters include the length of the delivery pipeline, the diameter of the pipe, the position of the steam trap, the size of the steam trap and the flow rate of the steam trap, and the environmental parameters include temperature, humidity and air pressure; A parameter classification module, the parameter classification module is used to obtain a pre-classification condition, and classify the reference parameters according to the pre-classification condition to obtain normal characteristic parameters and abnormal characteristic parameters; A time period construction module, the time period construction module is used to collect the occurrence node and the recovery node of the abnormal characteristic parameter, and perform offset processing on the occurrence node and the recovery node to obtain a first sample collection time period and a second sample collection time period; A real-time monitoring module, the real-time monitoring module is used to build a monitoring model according to the normal characteristic parameters in the first sample collection period, and verify the benchmark parameters collected in real time according to the monitoring model, and output a hydrophobic state according to the verification result, wherein the hydrophobic state includes a risk state and a normal state; A recovery evaluation module is used to arrange the second sample collection period according to the occurrence sequence, and perform a combined operation on the normal characteristic parameters under the second sample collection period according to the arrangement result, and record the operation result as a real-time recovery bias, and then match the repair plan according to the real-time recovery bias.
6. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively coupled to the at least one processor; Wherein, the memory stores a computer program that can be executed by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the intelligent hydrophobic method based on the big data model as described in any one of claims 1 to 4.
Citation Information
Patent Citations
Monitor method and system for steam pipe system
CN106338006A
Steam pipe hydrophobic recovery system suitable for severe cold regions
CN107035959A
Steam pipe network water attach risk monitoring and early warning system and method
CN109307157A
Steam heat supply pipe network infrastructure working state judgment system and judgment method thereof
CN111059457A
Steam pipeline drainage system and method based on machine vision
CN113483249A