Power distribution cabinet simulation verification system, power distribution cabinet simulation verification method and device
The power distribution cabinet simulation verification system addresses the need for power outages in calibration by converting and amplifying secondary signals to identify faults, ensuring reliable and stable network operation without service disruptions.
Patent Information
- Application Number
- CN202410639035.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-22
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-05-22
AI Technical Summary
Existing distribution cabinet calibration processes require power outage for maintenance, leading to service disruptions and reliability issues due to maintenance risks and troubleshooting accuracy considerations.
A power distribution cabinet simulation verification system comprising a wiring module, signal conversion module, primary signal simulation module, and power supply module, which allows for simulating and identifying faults without power outage by converting secondary signals into target signals and amplifying them to generate visual signals for fault determination.
Enables fault identification in distribution cabinets without disrupting power supply, enhancing network reliability and stability by allowing maintenance under power, thus reducing service interruptions and improving troubleshooting accuracy.
Smart Images

Figure CN118376860B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of electrical detection technology, and in particular to a power distribution cabinet simulation calibration system, a power distribution cabinet simulation calibration method and a device. Background Art
[0002] With the acceleration of urbanization, urban distribution network automation equipment has been continuously developed from the original pole-mounted equipment to distribution cabinet equipment. Therefore, in the urban distribution network system, the stable operation of the distribution cabinet is particularly important for the normal operation of the urban distribution network system and the improvement of power supply reliability. During the actual operation on site, the remote control of the distribution cabinet may fail to operate. At present, the problem of distribution cabinet failure is generally detected by checking the primary side action and the secondary side control logic after a power outage.
[0003] However, in the existing distribution cabinet calibration process, due to the consideration of maintenance risk and troubleshooting accuracy, the calibration needs to be carried out in a power outage state. However, power outage maintenance will cause certain losses and also affect the quality of power supply service, which in turn leads to poor reliability of power supply in the distribution network. Summary of the invention
[0004] The purpose of this application is to solve at least one of the above technical defects, especially the technical defect that the prior art needs to perform verification in a power outage state due to maintenance risks and troubleshooting accuracy considerations. However, power outage maintenance will cause certain losses and will also affect the quality of power supply services, which in turn leads to the technical defect of poor reliability of power supply in the distribution network.
[0005] In a first aspect, the present application provides a power distribution cabinet simulation verification system, the system comprising a wiring module, a signal conversion module, a primary signal simulation module and a power supply module;
[0006] The power supply module is respectively connected to the wiring module, the signal conversion module and the primary signal simulation module, and is used to provide power for the power distribution cabinet simulation verification system;
[0007] The wiring module is connected to the signal conversion module, and the wiring module is used to connect the power distribution cabinet to be verified so as to connect the secondary signal of the power distribution cabinet to the simulation verification system of the power distribution cabinet;
[0008] The signal conversion module is connected to the primary signal simulation module, and the signal conversion module is used to convert the secondary signal connected to the wiring module into a target signal of a preset mode, and the primary signal simulation module is used to amplify the target signal to obtain a visual signal; wherein, the target signal is an action command signal sent from the master station to the secondary side of the distribution cabinet, and the visual signal is used to determine the electrical side of the distribution cabinet where a fault occurs.
[0009] In one of the embodiments, the wiring module includes a plurality of wiring ports, each wiring port corresponding to a type of power distribution cabinet interface.
[0010] In one embodiment, the process of the signal conversion module for converting the secondary signal connected to the wiring module into a target signal of a preset mode includes:
[0011] The signal conversion module identifies the secondary signal, and if the identification is successful, converts the secondary signal into a target signal of a preset mode; if the identification fails, issues an indication for checking the wiring condition, and re-identifies and converts the secondary signal connected to the wiring module; wherein the preset mode is a signal mode that matches the primary signal simulation module.
[0012] In one of the embodiments, the system further includes a display module; the display module is respectively connected to the primary signal simulation module and the power supply module, and is used for visually displaying the visual signal.
[0013] In one embodiment, the power module includes a lithium battery power source.
[0014] In one embodiment, the visual signal includes a first visual signal and a second visual signal; the primary signal simulation module includes a separation and closing circuit and a separation and storage circuit;
[0015] The opening and closing circuit is used to receive the target signal of the signal conversion module, and control the opening and closing operation of the opening and closing circuit according to the target signal to generate a first visual signal;
[0016] The energy storage circuit is used to receive the target signal of the signal conversion module and control the energy storage operation of the energy storage circuit according to the target signal to generate a second visible signal.
[0017] In one embodiment, the opening and closing circuit includes a first diode, a second diode, a first photoelectric isolator, a second photoelectric isolator, a first resistor, a second resistor and a first relay;
[0018] A first end of the first side coil of the first relay is connected to the cathode of the first diode, a second end is connected to the anode of the first diode, and the second end is grounded;
[0019] A first end of the second side coil of the first relay is connected to the cathode of the second diode, a second end is connected to the anode of the second diode, and the second end is grounded;
[0020] The first end of the second side coil of the first relay serves as the first input end of the opening and closing circuit;
[0021] A first contact of the switch element in the first relay is grounded, a second contact is connected to a first end of a first resistor, and a third contact is connected to a first end of the second photoelectric isolator;
[0022] The second end of the first resistor is used as an output end of the closing signal;
[0023] The first end and the second end of the second photoelectric isolator are respectively connected to the second end and the first end of the first photoelectric isolator, and the third end and the fourth end are respectively connected to the third end and the fourth end of the first photoelectric isolator;
[0024] The second end of the second photoelectric isolator is connected to the first end of the second resistor, and the second end of the second resistor serves as an output end of the opening signal;
[0025] The fourth terminal of the second photoelectric isolator serves as the second input terminal of the opening and closing circuit.
[0026] In one embodiment, the storage circuit includes a third diode, a fourth diode, a third photoelectric isolator, a fourth photoelectric isolator, a third resistor and a second relay;
[0027] The first end of the first side coil of the second relay is connected to the cathode of the third diode, the second end is connected to the anode of the third diode, and the second end is grounded;
[0028] A first end of the second side coil of the second relay is connected to the cathode of the fourth diode, a second end is connected to the anode of the fourth diode, and the second end is grounded;
[0029] A first contact of the switch element in the second relay is grounded, and a second contact is connected to a first end of the fourth photoelectric isolator;
[0030] The first end and the second end of the fourth photoelectric isolator are respectively connected to the first end and the second end of the third photoelectric isolator;
[0031] The third end and the fourth end of the fourth photoelectric isolator are respectively connected to the third end and the fourth end of the third photoelectric isolator;
[0032] The fourth end of the fourth photoelectric isolator serves as the input end of the storage circuit;
[0033] The second end of the fourth photoelectric isolator is connected to the first end of the third resistor, and the second end of the third resistor serves as an output end of the energy storage signal.
[0034] In a second aspect, the present application provides a power distribution cabinet simulation verification method, which is applied to a power distribution cabinet simulation verification system as described in any one of the above embodiments, and the method includes:
[0035] When it is detected that the target power distribution cabinet is connected to the wiring module, a secondary signal connected to the wiring module is obtained; wherein the secondary signal is an action command signal sent from the master station to the secondary side of the target power distribution cabinet;
[0036] Identifying the secondary signal, and if the identification is successful, converting the secondary signal into a target signal of a preset mode;
[0037] The target signal is amplified to obtain a visual signal, and the visual signal is visualized.
[0038] In a third aspect, the present application provides a power distribution cabinet simulation verification device, which is applied to a power distribution cabinet simulation verification system as described in any one of the above embodiments, and the device includes:
[0039] A signal acquisition module, used to acquire a secondary signal connected to the wiring module when it is detected that the target power distribution cabinet is connected to the wiring module; wherein the secondary signal is an action command signal sent from the master station to the secondary side of the target power distribution cabinet;
[0040] A signal conversion module, used to identify the secondary signal, and if the identification is successful, convert the secondary signal into a target signal of a preset mode;
[0041] The signal simulation module is used to amplify the target signal to obtain a visual signal, and to visualize the visual signal.
[0042] It can be seen from the above technical solutions that the embodiments of the present application have the following advantages:
[0043] The present application provides a distribution cabinet simulation verification system, a distribution cabinet simulation verification method and a device, the system includes a wiring module, a signal conversion module, a primary signal simulation module and a power supply module; the secondary signal of the distribution cabinet is connected through the wiring module, and then the secondary signal can be converted into a target signal of a preset mode through the signal conversion module to complete the adaptation conversion of the secondary signal to obtain the target signal, and finally the target signal is amplified and processed by the primary simulation module to obtain a visual signal to complete the simulation of the secondary signal. The visual signal obtained based on the simulation of the secondary signal can quickly identify the electrical side of the fault problem of the faulty distribution cabinet. And because the signal of the distribution cabinet is simulated, it can be repaired without affecting the operation of the distribution cabinet, that is, the faulty distribution cabinet can be verified under power. The defect identification of the distribution cabinet is realized without power outage. Thereby improving the reliability and stability of the distribution network. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0045] Figure 1 One of the structural schematic diagrams of a power distribution cabinet simulation verification system provided in an embodiment of the present application;
[0046] Figure 2 A second structural diagram of a power distribution cabinet simulation verification system provided in an embodiment of the present application;
[0047] Figure 3 A schematic diagram of the structure of a primary signal simulation module provided in an embodiment of the present application;
[0048] Figure 4 A circuit diagram of a switch-on and switch-off circuit provided in an embodiment of the present application;
[0049] Figure 5 A circuit schematic diagram of a storage circuit provided in an embodiment of the present application;
[0050] Figure 6 A schematic diagram of a flow chart of a power distribution cabinet simulation verification method provided in an embodiment of the present application;
[0051] Figure 7 A schematic diagram of the structure of a power distribution cabinet simulation calibration device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0052] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0053] like Figure 1 As shown, the present application provides a power distribution cabinet simulation verification system, the system comprising a wiring module 120, a signal conversion module 130, a primary signal simulation module 140 and a power supply module 110;
[0054] The power supply module 110 is respectively connected to the wiring module 120, the signal conversion module 130 and the primary signal simulation module 140, and is used to provide power for the power distribution cabinet simulation verification system;
[0055] The wiring module 120 is connected to the signal conversion module 130, and the wiring module 120 is used to connect the power distribution cabinet to be verified so as to connect the secondary signal of the power distribution cabinet to the power distribution cabinet simulation verification system;
[0056] The signal conversion module 130 is connected to the primary signal simulation module 140. The signal conversion module 130 is used to convert the secondary signal connected to the wiring module 120 into a target signal of a preset mode. The primary signal simulation module 140 is used to amplify the target signal to obtain a visual signal; wherein the target signal is an action command signal sent from the master station to the secondary side of the distribution cabinet, and the visual signal is used to determine the electrical side of the distribution cabinet where a fault occurs.
[0057] Among them, the distribution cabinet refers to a device used to distribute, control and protect electric energy in the power system, which is usually installed in the distribution room or electrical control room of the power system. Its main functions include power distribution, protection, monitoring and control. The distribution cabinet generally has a high-voltage side (primary side) and a low-voltage side (secondary side). The secondary signal is the signal sent from the master station to the secondary side of the distribution cabinet. The preset mode is the signal mode that matches the primary signal simulation module. Both the secondary signal and the target signal can refer to the command signal sent from the master station to the secondary side of the distribution cabinet, but the target signal is a secondary signal that has undergone mode conversion. The master station can refer to the central communication processing unit, which is used to monitor and manage the operation of the entire distribution network.
[0058] In this embodiment, the power distribution cabinet simulation verification system proposed in this application is equipped with a built-in power supply module 110, which can provide power support for the power distribution cabinet simulation verification system. Moreover, the built-in power supply can make the power distribution cabinet simulation verification system not need an external power supply to support the power distribution cabinet simulation verification system to work outdoors. Broaden the working scenario of the power distribution cabinet simulation verification system. The wiring module 120 in the power distribution cabinet simulation verification system can provide a port for connecting to the power distribution cabinet to be verified, and then connect the secondary signal of the power distribution cabinet to the power distribution cabinet simulation verification system by the wiring module. Then, the wiring module 120 transmits the connected secondary signal to the signal conversion module 130, and the signal conversion module 130 can convert the secondary signal into a target signal of a preset mode. It can be understood that since the interface types of power distribution cabinets produced by different manufacturers are not necessarily the same, the signal conversion module 130 can convert the signal modes of various secondary signals into signals of preset modes, so that the signal can be processed and simulated by the primary signal simulation module 140. In this way, the power distribution cabinet simulation verification system provided by this application can be used to simulate and verify different types of power distribution cabinets. To improve the compatibility of the power distribution cabinet simulation verification system. Finally, when the primary signal simulation module 140 receives the target signal transmitted by the signal conversion module 130, it amplifies the target signal to enhance the signal strength and obtain a visible signal.
[0059] Specifically, when a distribution cabinet fails, the secondary signal of the distribution cabinet can be connected to the distribution cabinet simulation verification system, and the resulting visual signal can be used to determine the electrical side of the distribution cabinet where the failure occurs, that is, the electrical side of the distribution cabinet where the failure occurs is determined based on the secondary signal sent by the master station and the manifestation of the visual signal in the distribution cabinet. The electrical side includes the primary side and the secondary side.
[0060] Furthermore, when the secondary signal sent by the master station does not match the visual signal in the distribution cabinet, the electrical side of the distribution cabinet where the fault occurs is determined to be the secondary side. When the secondary signal sent by the master station matches the visual signal in the distribution cabinet, the electrical side of the distribution cabinet where the fault occurs is determined to be the primary side.
[0061] For example, assuming that a fault occurs in distribution cabinet A, during the simulation verification of distribution cabinet A, when the signal sent from the master station to the secondary side of distribution cabinet A is a trip signal, if the visual signal in the distribution cabinet is consistent with the performance of the trip signal, it is determined that a fault occurs on the primary side of distribution cabinet A. If the visual signal in the distribution cabinet does not conform to the performance of the trip signal, it is determined that a fault occurs on the secondary side of distribution cabinet A.
[0062] The present application provides a distribution cabinet simulation verification system, a distribution cabinet simulation verification method and a device, the system includes a wiring module, a signal conversion module, a primary signal simulation module and a power supply module; the secondary signal of the distribution cabinet is connected through the wiring module, and then the secondary signal can be converted into a target signal of a preset mode through the signal conversion module to complete the adaptation conversion of the secondary signal to obtain the target signal, and finally the target signal is amplified and processed by the primary simulation module to obtain a visual signal to complete the simulation of the secondary signal. The visual signal obtained based on the simulation of the secondary signal can quickly identify the electrical side of the fault problem of the faulty distribution cabinet. And because the signal of the distribution cabinet is simulated, it can be repaired without affecting the operation of the distribution cabinet, that is, the faulty distribution cabinet can be verified under power. The defect identification of the distribution cabinet is realized without power outage. Thereby improving the reliability and stability of the distribution network.
[0063] In one embodiment, the wiring module includes a plurality of wiring ports, each wiring port corresponding to a type of power distribution cabinet interface.
[0064] In this embodiment, since the types of interfaces of distribution cabinets produced by different manufacturers are not necessarily the same, if different types of distribution cabinets need to be calibrated with the corresponding distribution cabinet simulation verification system, the cost of simulation verification will be greatly increased. Therefore, the wiring module in the distribution cabinet simulation verification system of the present application will be provided with multiple wiring ports, so that different types of distribution cabinets can insert wiring harnesses such as the opening and closing control lines and the grounding common terminal into the distribution cabinet simulation verification system. In this way, the compatibility of the distribution cabinet simulation verification system can be improved, and the cost of simulating and verifying the distribution cabinet can also be reduced.
[0065] In one embodiment, the process of the signal conversion module for converting the secondary signal connected to the wiring module into a target signal of a preset mode includes:
[0066] The signal conversion module identifies the secondary signal. If the identification is successful, the secondary signal is converted into a target signal of a preset mode. If the identification fails, an indication is issued to indicate the wiring check status, and the secondary signal connected to the wiring module is re-identified and converted.
[0067] The preset mode is a signal mode that matches the primary signal simulation module.
[0068] In this embodiment, the signal conversion module will identify the secondary signal to check the integrity and standardization of the secondary signal. When the identification is successful, the secondary signal is converted into a target signal of a preset mode, that is, the target signal is the secondary signal after the signal mode conversion. When the identification fails, the reason for the identification failure may be that the line access is incorrect or the contact is poor or not fully connected. At this time, an indication for characterizing the detection of the wiring condition is issued to prompt the user to check the wiring condition. The signal conversion module will re-identify and convert the secondary signal re-connected by the wiring module.
[0069] It is understandable that the signal conversion module can convert the signal modes of various secondary signals into signals of preset modes, so that the signals can be processed and simulated by the primary signal simulation module, thereby achieving the purpose of simulating and checking the power distribution cabinet.
[0070] like Figure 2 As shown, in one of the embodiments, the power distribution cabinet simulation verification system further includes a display module 150; the display module 150 is respectively connected to the primary signal simulation module 140 and the power supply module 110 for visually displaying the visual signal.
[0071] In this embodiment, the display module 150 is connected to the primary signal simulation module 140, and the visual signal output by the primary signal simulation module 140 can be transmitted to the display module 150. When receiving the visual signal, the display module 150 visualizes the visual signal. This allows the user to intuitively understand the response of the distribution cabinet simulation verification system to the connected secondary signal. This allows the user to quickly determine the electrical side of the distribution cabinet where the fault occurs. This improves the verification efficiency of the distribution cabinet simulation verification system.
[0072] In one example, the display module 150 can be a display screen or an indicator light, as long as the display module can display the visual signal in a visual manner. The specific visual display form can be selected according to actual conditions, and this application does not impose specific restrictions on this.
[0073] In one embodiment, the power module includes a lithium battery power source.
[0074] In this embodiment, a lithium battery power supply is used as a built-in power supply for the distribution cabinet simulation calibration system. Since the lithium battery power supply has the advantages of high energy density, long life, low self-discharge rate, etc., compared with other built-in battery power supplies, using a lithium battery power supply as a power module can reduce the weight and volume of the distribution cabinet simulation calibration system, thereby improving the portability of the distribution cabinet simulation calibration system.
[0075] like Figure 3As shown, in one embodiment, the visual signal includes a first visual signal and a second visual signal; the primary signal simulation module 140 includes a separation and closing circuit 141 and a separation and storage circuit 142;
[0076] The opening and closing circuit 141 is used to receive the target signal of the signal conversion module, and control the opening and closing operation of the opening and closing circuit according to the target signal to generate a first visible signal; the energy storage circuit 142 is used to receive the target signal of the signal conversion module, and control the energy storage operation of the energy storage circuit according to the target signal to generate a second visible signal.
[0077] The first visible signal refers to the opening signal and the closing signal, and the second visible signal refers to the energy storage signal.
[0078] In this embodiment, the primary signal simulation module 140 controls the opening and closing operation through the opening and closing circuit 141, thereby generating a corresponding opening and closing signal. The primary signal simulation module 140 controls the energy storage operation through the energy storage circuit 142, thereby generating an energy storage signal.
[0079] like Figure 4 As shown, in one embodiment, the opening and closing circuit includes a first diode D1, a second diode D2, a first photoelectric isolator U1, a second photoelectric isolator U2, a first resistor R1, a second resistor R2 and a first relay KA1;
[0080] The first end of the first side coil of the first relay KA1 is connected to the cathode of the first diode D1, the second end is connected to the anode of the first diode D1, and the second end is grounded; the first end of the second side coil of the first relay KA1 is connected to the cathode of the second diode D2, the second end is connected to the anode of the second diode D2, and the second end is grounded; the first end of the second side coil of the first relay KA1 serves as the first input end of the opening and closing circuit; the first contact of the switch element in the first relay KA1 is grounded, the second contact is connected to the first end of the first resistor R1, and the third contact is connected to the first end of the second photoelectric isolator U2; the second end of the first resistor R2 serves as the output end of the closing signal; the first end and the second end of the second photoelectric isolator U2 are respectively connected to the second end and the first end of the first photoelectric isolator U1, and the third end and the fourth end are respectively connected to the third end and the fourth end of the first photoelectric isolator U1; the second end of the second photoelectric isolator U2 is connected to the first end of the second resistor R2, and the second end of the second resistor R2 serves as the output end of the opening signal; the fourth end of the second photoelectric isolator U2 serves as the second input end of the opening and closing circuit.
[0081] Among them, the first opto-isolator U1 and the second opto-isolator U2 can be used to isolate the input and output circuits through photoelectric conversion. The opto-isolator is usually composed of a light-emitting diode (LED) and a photosensitive transistor (optocoupler). The first relay KA1 is an electrical control device used to control another circuit in one circuit by controlling the switch of one circuit. The relay is usually composed of an electromagnetic coil and a set of controllable switches (contacts). When current passes through the electromagnetic coil, it activates the electromagnetism, causing the contacts to open or close, thereby controlling the current flow of another circuit.
[0082] exist Figure 4 In the figure, the first contact of the switch element in the first relay KA1 refers to contact 4 in the figure, the second contact refers to contact 3 in the figure, and the third contact refers to contact 5 in the figure. FW-1 represents the output closing signal, and HW-1 represents the output opening signal. HZ_1 corresponds to the closing button of the system, HZ_2 corresponds to the opening button of the system, HZ refers to the input end of the closing signal in the target signal, and FZ refers to the input end of the opening signal in the target signal.
[0083] In this embodiment, the output signal type (opening signal and closing signal) is determined by the switching element in the first relay KA1. The opening circuit part and the closing circuit part in the opening and closing circuit are opposing circuits. When the closing button HZ_1 is pressed on the simulation verification system of the distribution cabinet, the closing circuit part in the opening and closing circuit works to output the closing signal FW-1. At this time, the opening circuit part in the opening and closing circuit does not work, and the output opening signal HW-1. Exemplarily, if the display form of the opening and closing signal is an indicator light, then when the closing button HZ_1 is pressed on the simulation verification system of the distribution cabinet, the closing circuit part in the opening and closing circuit works to output the closing signal FW-1, so that the closing indicator light is on. At this time, the opening circuit part in the opening and closing circuit does not work, and the output opening signal HW-1 makes the opening indicator light off.
[0084] It can be understood that the opening button HZ_2 and closing button HZ_1 on the distribution cabinet simulation verification system are mainly used to simulate signals on-site to verify whether the master station receives signals normally, thereby verifying the integrity of the communication channel.
[0085] In one example, the first relay KA1 can be a relay with a model number of HF3F-L-12-1ZL2T. The first photoelectric isolator U1 and the second photoelectric isolator U2 can be a photoelectric isolator with a model number of TLP627(F). The first resistor R1 and the second resistor R2 can be resistors with a parameter of "6.2kΩ ±1% 250mW". Among them, 6.2kΩ represents the resistance value of the resistor, and ±1% represents the allowable deviation range of the resistance value of the resistor. 50mW represents the power capacity of the resistor, indicating the maximum power that the resistor can dissipate continuously.
[0086] like Figure 5 As shown, in one embodiment, the storage circuit includes a third diode D3, a fourth diode D4, a third photoelectric isolator U3, a fourth photoelectric isolator U4, a third resistor R3 and a second relay KA2;
[0087] The first end of the first side coil of the second relay KA2 is connected to the cathode of the third diode D3, the second end is connected to the anode of the third diode D3, and the second end is grounded; the first end of the second side coil of the second relay KA2 is connected to the cathode of the fourth diode D4, the second end is connected to the anode of the fourth diode D4, and the second end is grounded; the first contact of the switch element in the second relay KA2 is grounded, and the second contact is connected to the first end of the fourth photoelectric isolator U4; the first end and the second end of the fourth photoelectric isolator U4 are respectively connected to the first end and the second end of the third photoelectric isolator U3; the third end and the fourth end of the fourth photoelectric isolator U4 are respectively connected to the third end and the fourth end of the third photoelectric isolator U3; the fourth end of the fourth photoelectric isolator U4 serves as the input end of the storage circuit; the second end of the fourth photoelectric isolator U4 is connected to the first end of the third resistor R3, and the second end of the third resistor R3 serves as the output end of the energy storage signal.
[0088] Among them, the third photoelectric isolator U3 and the fourth photoelectric isolator U4 can be used to isolate the input and output circuits through photoelectric conversion. The photoelectric isolator is usually composed of a light-emitting diode (LED) and a photosensitive transistor (photocoupler). The second relay KA2 is an electrical control device used to control another circuit in one circuit by controlling the switch of one circuit. The relay is usually composed of an electromagnetic coil and a set of controllable switches (contacts). When current passes through the electromagnetic coil, it activates the electromagnetism, causing the contacts to open or close, thereby controlling the current flow of another circuit.
[0089] exist Figure 5In the figure, the first contact of the switch element in the second relay KA2 refers to contact 4 in the figure, the second contact refers to contact 5 in the figure, and contact 3 in the figure can refer to the third contact, which is not connected to other circuit parts. CW-1 represents the output energy storage signal. HZ_1 corresponds to the closing button of the system, and HZ_2 corresponds to the opening button of the system. CN corresponds to the energy storage button of the system. HZ refers to the input end of the closing signal in the target signal, and FZ refers to the input end of the opening signal in the target signal.
[0090] In this embodiment, whether to output the energy storage signal is determined by the switch element in the second relay KA2. The opening circuit part and the energy storage circuit part in the sub-storage circuit are opposing circuits. When the closing button HZ_1 is pressed on the power distribution cabinet simulation verification system, the opening circuit part in the sub-storage circuit does not work. At this time, the energy storage circuit part in the sub-storage circuit automatically works and outputs the energy storage signal CNW-1. Exemplarily, if the energy storage signal is displayed in the form of an indicator light, then when the closing button HZ_1 is pressed on the power distribution cabinet simulation verification system, the opening circuit part in the sub-storage circuit does not work, and the energy storage circuit part in the sub-storage circuit automatically works and outputs the energy storage signal CNW-1, so that the energy storage indicator light is on.
[0091] It can be understood that the opening button HZ_2, closing button HZ_1 and energy storage button CN on the distribution cabinet simulation verification system are mainly used to simulate signals on-site to verify whether the master station receives signals normally, thereby verifying the integrity of the communication channel.
[0092] In one example, the second relay KA2 can be a relay with a model number of HF3F-L-12-1ZL2T. The third photoelectric isolator U3 and the fourth photoelectric isolator U4 can be a photoelectric isolator with a model number of TLP627 (F). The third resistor R3 can be a resistor with a parameter of "6.2kΩ ±1% 250mW". Among them, 6.2kΩ represents the resistance value of the resistor, and ±1% represents the allowable deviation range of the resistance value of the resistor. 50mW represents the power capacity of the resistor, indicating the maximum power that the resistor can dissipate continuously.
[0093] The power distribution cabinet simulation calibration method provided in an embodiment of the present application is described below. The power distribution cabinet simulation calibration method described below and the power distribution cabinet simulation calibration system described above can be referenced to each other.
[0094] like Figure 6 As shown, the present application provides a power distribution cabinet simulation verification method, which is applied to a power distribution cabinet simulation verification system as in any one of the above embodiments, and the method includes:
[0095] Step S601: when it is detected that the target power distribution cabinet is connected to the wiring module, a secondary signal connected to the wiring module is obtained.
[0096] Among them, the secondary signal is an action command signal sent from the master station to the secondary side of the target distribution cabinet.
[0097] Step S602: Identify the secondary signal, and if the identification is successful, convert the secondary signal into a target signal of a preset mode;
[0098] Step S603: amplify the target signal to obtain a visual signal, and visualize the visual signal.
[0099] It is understandable that the visual signal obtained based on the simulation of the secondary signal can quickly identify the electrical side of the fault problem of the faulty distribution cabinet. And because the signal of the distribution cabinet is simulated, it can be repaired without affecting the operation of the distribution cabinet, that is, the faulty distribution cabinet can be checked under power. The defect identification of the distribution cabinet is realized without power outage, thereby improving the reliability and stability of the distribution network.
[0100] It should be understood that, although the various steps in the flowcharts involved in the above-mentioned embodiments are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear explanation in this article, the execution of these steps does not have a strict order restriction, and these steps can be executed in other orders. Moreover, at least a part of the steps in the flowcharts involved in the above-mentioned embodiments can include multiple steps or multiple stages, and these steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a part of the steps or stages in other steps.
[0101] The power distribution cabinet simulation calibration device provided in the embodiment of the present application is described below. The power distribution cabinet simulation calibration device described below and the power distribution cabinet simulation calibration method described above can be referenced to each other.
[0102] like Figure 7 As shown, the present application provides a power distribution cabinet simulation verification device 700, which is applied to a power distribution cabinet simulation verification system as in any one of the above embodiments, and the device includes:
[0103] The signal acquisition module 701 is used to acquire the secondary signal connected to the wiring module when it is detected that the target distribution cabinet is connected to the wiring module; wherein the secondary signal is an action command signal sent from the master station to the secondary side of the target distribution cabinet;
[0104] The signal conversion module 702 is used to identify the secondary signal, and if the identification is successful, convert the secondary signal into a target signal of a preset mode;
[0105] The signal simulation module 703 is used to amplify the target signal to obtain a visual signal, and visualize the visual signal.
[0106] The division of each module in the above-mentioned power distribution cabinet simulation verification device is only for illustration. In other embodiments, the power distribution cabinet simulation verification device can be divided into different modules as needed to complete all or part of the functions of the above-mentioned power distribution cabinet simulation verification device. Each module in the above-mentioned power distribution cabinet simulation verification device can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0107] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish an entity or operation from another entity or operation, and do not necessarily require or imply that there is any such actual relationship or order between these entities or operations. Moreover, the term "include", "comprise" or any other variant thereof is intended to cover non-exclusive inclusion, so that the process, method, article or equipment including a series of elements not only include those elements, but also include other elements that are not clearly listed, or also include elements inherent to such process, method, article or equipment. In the absence of more restrictions, the elements limited by the sentence "comprise one..." do not exclude the existence of other identical elements in the process, method, article or equipment including the elements. Herein, the singular "one", "one" and "described / the" may also include plural forms, unless the context clearly indicates another way. It should also be understood that the terms "include / comprise" or "have" etc. specify the existence of stated features, wholes, steps, operations, components, parts or combinations thereof, but do not exclude the possibility of the existence or addition of one or more other features, wholes, steps, operations, components, parts or combinations thereof. At the same time, the term "and / or" used in this specification includes any and all combinations of the relevant listed items.
[0108] The "connection" involved in this article should be understood as "electrical connection", "communication connection", etc. if the connected circuits, blocks, units, etc. have the transmission of electrical signals or data between each other. When an element is considered to be "connected" to another element, it can be directly connected to the other element, or connected to the other element through an intermediate element.
[0109] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The various embodiments can be combined as needed, and the same or similar parts can refer to each other.
[0110] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A power distribution cabinet simulation verification system, characterized in that: The system includes a wiring module, a signal conversion module, a primary signal simulation module and a power supply module; The power supply module is respectively connected to the wiring module, the signal conversion module and the primary signal simulation module, and is used to provide power for the power distribution cabinet simulation verification system; The wiring module is connected to the signal conversion module, and the wiring module is used to connect the power distribution cabinet to be verified so as to connect the secondary signal of the power distribution cabinet to the simulation verification system of the power distribution cabinet; The signal conversion module is connected to the primary signal simulation module, and the signal conversion module is used to convert the secondary signal connected to the wiring module into a target signal of a preset mode, and the primary signal simulation module is used to amplify the target signal to obtain a visual signal; wherein the target signal is an action command signal sent from the master station to the secondary side of the power distribution cabinet, and the visual signal is used to determine the electrical side of the power distribution cabinet where a fault occurs; The process of using the visual signal to determine the electrical side of the power distribution cabinet where a fault occurs includes: When the secondary signal sent by the master station does not match the performance of the visual signal in the distribution cabinet, it is determined that the electrical side of the distribution cabinet failure is the secondary side. When the secondary signal sent by the master station matches the performance of the visual signal in the distribution cabinet, it is determined that the electrical side of the distribution cabinet failure is the primary side.
2. The power distribution cabinet simulation verification system according to claim 1 is characterized in that: The wiring module includes a plurality of wiring ports, each of which corresponds to a type of power distribution cabinet interface.
3. The power distribution cabinet simulation verification system according to claim 1 is characterized in that: The process in which the signal conversion module is used to convert the secondary signal connected to the wiring module into a target signal of a preset mode includes: The signal conversion module identifies the secondary signal, and if the identification is successful, converts the secondary signal into a target signal of a preset mode; if the identification fails, issues an indication for checking the wiring condition, and re-identifies and converts the secondary signal connected to the wiring module; wherein the preset mode is a signal mode that matches the primary signal simulation module.
4. The power distribution cabinet simulation verification system according to claim 1, characterized in that: The system further comprises a display module; the display module is respectively connected to the primary signal simulation module and the power supply module, and is used for visually displaying the visual signal.
5. The power distribution cabinet simulation verification system according to claim 1 is characterized in that: The power module includes a lithium battery power source.
6. A method for simulating and verifying a power distribution cabinet, characterized in that: Applied to the power distribution cabinet simulation verification system according to any one of claims 1 to 5, the method comprises: When it is detected that the target power distribution cabinet is connected to the wiring module, a secondary signal received by the wiring module is obtained; wherein the secondary signal received by the wiring module is an action command signal sent from the master station to the secondary side of the target power distribution cabinet; Identify the secondary signal connected to the wiring module, and if the identification is successful, convert the secondary signal connected to the wiring module into a target signal of a preset mode; The target signal is amplified to obtain a visual signal, and the visual signal is visualized.
7. A power distribution cabinet simulation verification device, characterized in that: Applicable to the power distribution cabinet simulation verification system according to any one of claims 1 to 5, the device comprises: A signal acquisition module, used to acquire a secondary signal received by the wiring module when it is detected that the target power distribution cabinet is connected to the wiring module; wherein the secondary signal received by the wiring module is an action command signal sent from the master station to the secondary side of the target power distribution cabinet; A signal conversion module, used for identifying the secondary signal connected to the wiring module, and if the identification is successful, converting the secondary signal connected to the wiring module into a target signal of a preset mode; The signal simulation module is used to amplify the target signal to obtain a visual signal, and to visualize the visual signal.