Water flooding simulation method, device and electronic equipment for power distribution room
By obtaining the distribution room description information to generate a three-dimensional model and performing flood simulation, the problems of poor manual inspection timeliness and high 3D modeling computing resources in the flood protection of the distribution room are solved, which improves the flood protection efficiency and reduces the Risk of damage to equipment due to flooding.
Patent Information
- Application Number
- CN202410814327.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-06-24
AI Technical Summary
The flood protection of existing distribution rooms relies on manual inspection and three-dimensional modeling and simulation, resulting in poor timeliness and high computing resource utilization, increasing the risk of equipment flood damage.
By obtaining the distribution room description information, generating a three-dimensional model, determining the water inlet point information, performing simulated flood simulation, generating flood disposal information, improving flood protection efficiency, and reducing the risk of equipment damage.
The flood simulation in complex situations is realized, the flood protection efficiency is improved, the risk of equipment being damaged by flooding is reduced, and the problems of poor manual inspection timeliness and high utilization of three-dimensional modeling and computing resources are avoided.
Smart Images

Figure CN118395744B_ABST
Abstract
Description
Technical Field
[0001] Embodiments of the present disclosure relate to the field of computer technology, and in particular to a flooding simulation method, device, and electronic equipment applied to a power distribution room. Background Art
[0002] As one of the important energy sources, electric power resources are of great significance to maintaining the operation of machinery. As an important facility for receiving, distributing and controlling electricity, it is particularly important to ensure the stability of the distribution room. In practice, since water is conductive, when the distribution room is flooded, it is very easy to cause a short circuit between equipment or even equipment damage. At present, when carrying out flood protection, the commonly used method is: mainly through manual inspection to carry out flood protection.
[0003] However, when the above method is adopted, the following technical problems often occur: 1. The timeliness of manual inspection is poor, which easily leads to untimely flood protection, thereby increasing the risk of equipment being damaged by flooding;
[0004] Continuing, when using the 3D modeling simulation method, there is further the following technical problem 2:
[0005] Conventional 3D modeling methods occupy more computing resources, which increases the computing resource occupancy rate of 3D modeling simulation.
[0006] The above information disclosed in this Background section is only for enhancement of understanding of the background of the inventive concept and therefore it may contain information that does not form the prior art that is already known to a person of ordinary skill in the art. Summary of the invention
[0007] The content of this disclosure is used to introduce concepts in a brief form, which will be described in detail in the detailed implementation section below. The content of this disclosure is not intended to identify the key features or essential features of the technical solution claimed for protection, nor is it intended to limit the scope of the technical solution claimed for protection.
[0008] Some embodiments of the present disclosure propose a flooding simulation method, device, and electronic device applied to a power distribution room to solve one or more of the technical problems mentioned in the above background technology section.
[0009] In a first aspect, some embodiments of the present disclosure provide a flooding simulation method applied to a distribution room, the method comprising: obtaining distribution room description information corresponding to a target distribution room, wherein the distribution room description information comprises: distribution room plane structure information and distribution room equipment information, wherein the distribution room plane structure information is used to describe the house plane structure of the target distribution room, and the distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the target distribution room; determining three-dimensional point cloud data for the target distribution room based on the distribution room description information; generating a three-dimensional model for the target distribution room based on the three-dimensional point cloud data; determining the three-dimensional model based on the three-dimensional model. The water inlet point information in the target distribution room is obtained to obtain a water inlet point information set; the water inlet point information in the above water inlet point information set is matched to generate simulated water inlet point information to obtain a simulated water inlet point information set; for each simulated water inlet point information in the above simulated water inlet point information set, the simulated water inlet point corresponding to the above simulated water inlet point information is used as the water inlet point, and the above target distribution room is subjected to a flooding simulation according to the above three-dimensional model to generate a flooding simulation result, wherein the above flooding simulation result characterizes the flooding situation of the distribution room equipment at each moment during the flooding simulation process; based on the obtained flooding simulation result set, the flooding disposal information for the above target distribution room is generated.
[0010] In a second aspect, some embodiments of the present disclosure provide a flooding simulation device applied to a distribution room, the device comprising: an acquisition unit, configured to acquire distribution room description information corresponding to a target distribution room, wherein the distribution room description information comprises: distribution room plane structure information and distribution room equipment information, wherein the distribution room plane structure information is used to describe the house plane structure of the target distribution room, and the distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the target distribution room; a first determination unit, configured to determine three-dimensional point cloud data for the target distribution room according to the distribution room description information; a first generation unit, configured to generate a three-dimensional model for the target distribution room according to the three-dimensional point cloud data; a second determination unit, configured to generate a three-dimensional model for the target distribution room according to the three-dimensional model, Determine the water inlet point information in the above-mentioned target distribution room and obtain a water inlet point information set; an information matching unit is configured to perform information matching on the water inlet point information in the above-mentioned water inlet point information set to generate simulated water inlet point information and obtain a simulated water inlet point information set; a flooding simulation unit is configured to, for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, use the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information as the water inlet point, and perform flooding simulation on the above-mentioned target distribution room according to the above-mentioned three-dimensional model to generate a flooding simulation result, wherein the above-mentioned flooding simulation result represents the flooding situation of the distribution room equipment at each moment during the flooding simulation process; a second generating unit is configured to generate flooding disposal information for the above-mentioned target distribution room according to the obtained flooding simulation result set.
[0011] In a third aspect, some embodiments of the present disclosure provide an electronic device comprising: one or more processors; a storage device on which one or more programs are stored, and when the one or more programs are executed by the one or more processors, the one or more processors implement the method described in any implementation manner of the above-mentioned first aspect.
[0012] In a fourth aspect, some embodiments of the present disclosure provide a computer-readable medium having a computer program stored thereon, wherein when the program is executed by a processor, the method described in any implementation manner of the above-mentioned first aspect is implemented.
[0013] The above-mentioned various embodiments of the present disclosure have the following beneficial effects: the flooding simulation method applied to the distribution room of some embodiments of the present disclosure reduces the risk of equipment being damaged by flooding. Specifically, the reason for the high risk of equipment being damaged by flooding is that the timeliness of manual inspection is poor, which easily leads to untimely flooding protection, thereby increasing the risk of equipment being damaged by flooding. In practice, when the flooding situation is more complicated, the timeliness of the method of using manual inspection and flooding protection according to the actual situation is poor, and because water is conductive, untimely flooding protection is very likely to increase the risk of equipment short circuit, thereby increasing the risk of equipment damage by flooding. Based on this, the flooding simulation method applied to the distribution room of some embodiments of the present disclosure, first, obtain the distribution room description information corresponding to the target distribution room, wherein the above-mentioned distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the above-mentioned distribution room plane structure information is used to describe the house plane structure of the above-mentioned target distribution room, and the above-mentioned distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the above-mentioned target distribution room. In this way, the house plane structure and equipment layout corresponding to the target distribution room are obtained. Secondly, according to the above-mentioned distribution room description information, the three-dimensional point cloud data for the above-mentioned target distribution room is determined. Then, according to the above-mentioned three-dimensional point cloud data, a three-dimensional model for the above-mentioned target distribution room is generated. In this way, a three-dimensional model for the target distribution room is obtained for subsequent flooding simulation. Further, according to the above-mentioned three-dimensional model, the water inlet point information in the above-mentioned target distribution room is determined to obtain a water inlet point information set. In practice, the non-enclosed area of the target distribution room often has multiple areas connected to the outside world, and when flooding occurs, the areas connected to the outside world can all be water inlet locations. In addition, the water inlet point information in the above-mentioned water inlet point information set is matched to generate simulated water inlet point information to obtain a simulated water inlet point information set. In practice, there may be a situation where multiple water inlet locations are flooded at the same time, so it is necessary to combine the water inlet points. In addition, for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information is used as the water inlet point, and the above-mentioned target distribution room is subjected to a flooding simulation according to the above-mentioned three-dimensional model to generate a flooding simulation result, wherein the above-mentioned flooding simulation result characterizes the flooding conditions of the distribution room equipment at each moment during the flooding simulation process. In this way, flooding simulation conditions under different circumstances and at different moments are obtained. Finally, based on the obtained flooding simulation result set, flooding disposal information for the above-mentioned target distribution room is generated. In this way, flooding simulation disposal plans for different circumstances are obtained. In this way, flooding simulation in complex situations is realized, the efficiency of flooding protection when flooding occurs is improved, and the risk of equipment being damaged by flooding is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The above and other features, advantages and aspects of the embodiments of the present disclosure will become more apparent with reference to the following detailed description in conjunction with the accompanying drawings. Throughout the accompanying drawings, the same or similar reference numerals represent the same or similar elements. It should be understood that the drawings are schematic and that components and elements are not necessarily drawn to scale.
[0015] Figure 1 is a flow chart of some embodiments of a flooding simulation method applied to a power distribution room according to the present disclosure;
[0016] Figure 2 is a schematic structural diagram of some embodiments of a flooding simulation device applied to a power distribution room according to the present disclosure;
[0017] Figure 3 It is a schematic diagram of the structure of an electronic device suitable for implementing some embodiments of the present disclosure. DETAILED DESCRIPTION
[0018] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments set forth herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.
[0019] It should also be noted that, for ease of description, only the parts related to the invention are shown in the drawings. In the absence of conflict, the embodiments and features in the embodiments of the present disclosure can be combined with each other.
[0020] It should be noted that the concepts such as "first" and "second" mentioned in the present disclosure are only used to distinguish different devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these devices, modules or units.
[0021] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".
[0022] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.
[0023] The present disclosure will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.
[0024] refer to Figure 1, shows a process 100 of some embodiments of a flooding simulation method applied to a power distribution room according to the present disclosure. The flooding simulation method applied to a power distribution room comprises the following steps:
[0025] Step 101, obtaining the distribution room description information corresponding to the target distribution room.
[0026] In some embodiments, the execution subject (for example, a computing device) of the flooding simulation method applied to the distribution room can obtain the distribution room description information corresponding to the above-mentioned target distribution room through a wired connection or a wireless connection. The target distribution room may be a distribution room to be subjected to flooding simulation. The distribution room description information includes: distribution room plane structure information and distribution room equipment information. The above-mentioned distribution room plane structure information is used to describe the house plane structure of the above-mentioned target distribution room. The above-mentioned distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the above-mentioned target distribution room. In practice, the distribution room plane structure information may include: distribution room size, distribution room ground slope, and distribution room line position. The distribution room size is used to describe the distribution room structure of the target distribution room. The distribution room ground slope is used to describe the ground slope of the target distribution room. The distribution room line position is used to describe the layout position of the line in the target distribution room. In practice, the target distribution room may include: transformers, circuit breakers, switchboards, electric energy metering equipment, and power monitoring and control equipment. For example, the power distribution room equipment information may include transformer specification parameters for the transformer and the layout position of the transformer in the target power distribution room.
[0027] It should be noted that the above-mentioned wireless connection methods may include but are not limited to 3G / 4G / 5G connection, WiFi connection, Bluetooth connection, WiMAX connection, Zigbee connection, UWB (ultra wideband) connection, and other wireless connection methods currently known or to be developed in the future.
[0028] It should be noted that the above-mentioned computing device can be hardware or software. When the computing device is hardware, it can be implemented as a distributed cluster consisting of multiple servers or terminal devices, or it can be implemented as a single server or a single terminal device. When the computing device is embodied as software, it can be installed in the hardware devices listed above. It can be implemented as multiple software or software modules for providing distributed services, for example, or it can be implemented as a single software or software module. No specific limitation is made here. It should be understood that the number of computing devices can be any number according to the implementation needs.
[0029] Step 102: Determine the three-dimensional point cloud data for the target distribution room according to the distribution room description information.
[0030] In some embodiments, the above-mentioned execution entity can determine the three-dimensional point cloud data for the target distribution room according to the distribution room description information. Among them, the three-dimensional point cloud data can correspond to a set of three-dimensional coordinate points. In practice, the three-dimensional coordinate points can also correspond to reflection intensity information. The reflection intensity information characterizes the laser intensity when the laser is irradiated at the three-dimensional coordinate point. In practice, according to the house plane structure and equipment layout corresponding to the target distribution room described in the distribution room description information, a suitable three-dimensional point cloud data acquisition device can be selected to scan the above-mentioned target distribution room to obtain the above-mentioned three-dimensional point cloud data. In practice, a point cloud scanner can be selected to scan the above-mentioned target distribution room to obtain the above-mentioned three-dimensional point cloud data.
[0031] In some optional implementations of some embodiments, the execution subject determines the three-dimensional point cloud data for the target power distribution room according to the power distribution room description information, which may include the following steps:
[0032] The first step is to generate a distribution room plan view for the target distribution room according to the distribution room plan structure information.
[0033] In practice, the above-mentioned execution entity can import the plan structure information of the distribution room into engineering drawing software, such as CAD (Computer Aided Design) software, to generate the above-mentioned distribution room plan.
[0034] The second step is to update the above distribution room floor plan based on the above distribution room equipment information to generate an updated distribution room floor plan.
[0035] In practice, the above-mentioned execution entity can update the above-mentioned distribution room plan according to the equipment parameters and equipment layout of the distribution room equipment described by the distribution room equipment information. Specifically, the legend corresponding to the distribution room equipment can be added to the distribution room plan to obtain the above-mentioned updated distribution room plan.
[0036] The third step is to take the distribution room entrance of the target distribution room as the starting point and generate the shortest traversal path for the target distribution room according to the updated distribution room plan.
[0037] In practice, the updated distribution room plan contains at least one path that can reach the distribution room entrance. Therefore, the execution subject can generate the shortest traversal path for the target distribution room by using the ant colony algorithm, taking the distribution room entrance of the target distribution room as the starting point.
[0038] The fourth step is to control the self-propelled point cloud data acquisition vehicle to collect point cloud data of the target distribution room using the shortest traversal path as the path to generate the three-dimensional point cloud data.
[0039] Among them, the self-propelled point cloud data collection vehicle includes: a crawler mobile chassis, a telescopic support rod and a 256-beam laser radar. The telescopic support rod is arranged between the crawler mobile chassis and the 256-beam laser radar to support the 256-beam laser radar. In practice, the telescopic support rod can be extended and retracted up and down to control the height of the supported 256-beam laser radar from the ground. The self-propelled point cloud data collection vehicle can be controlled by a microcomputer. Specifically, the path coordinates of the shortest path can be input into the microcomputer, and the vehicle movement of the point cloud data collection vehicle can be controlled by the microcomputer.
[0040] Step 103: Generate a three-dimensional model of the target power distribution room based on the three-dimensional point cloud data.
[0041] In some embodiments, the execution entity may generate a three-dimensional model for the target power distribution room using the three-dimensional point cloud data. In practice, the execution entity may input the three-dimensional point cloud data into PointCab software to generate a three-dimensional model for the target power distribution room.
[0042] In some optional implementations of some embodiments, the execution subject generates a three-dimensional model for a target power distribution room according to the three-dimensional point cloud data, which may include the following steps:
[0043] The first step is to segment the above three-dimensional point cloud data to obtain a three-dimensional point cloud sub-data sequence.
[0044] In practice, the execution subject may perform point cloud data segmentation on the three-dimensional point cloud data by a clustering algorithm to obtain a three-dimensional point cloud sub-data sequence. Specifically, the clustering algorithm may be a K-means clustering algorithm. In addition, the execution subject may also perform point cloud data segmentation on the three-dimensional point cloud data based on a segmentation method of geometric features (e.g., based on curvature, curvature change rate, etc.) to obtain a three-dimensional point cloud sub-data sequence.
[0045] In the second step, for each 3D point cloud sub-data in the above 3D point cloud sub-data sequence, the following processing steps are performed:
[0046] In the first sub-step, the three-dimensional point cloud sub-data is segmented into unit surfaces to generate three-dimensional point cloud data blocks, thereby obtaining a set of three-dimensional point cloud data blocks.
[0047] The unit face is an area of preset size. In practice, the execution subject can perform unit face segmentation along the plane formed by the three-dimensional point cloud sub-data to generate three-dimensional point cloud data blocks and obtain a set of three-dimensional point cloud data blocks. The three-dimensional point cloud data block is composed of at least one three-dimensional coordinate point in the area surrounded by the unit face.
[0048] In the second sub-step, outlier points are removed from each 3D point cloud data block in the above 3D point cloud data block set to generate a 3D point cloud data block after outlier points are removed, thereby obtaining a 3D point cloud data block set after outlier points are removed.
[0049] Among them, first, the above-mentioned execution entity can determine the midpoint coordinates of at least one three-dimensional coordinate point included in the three-dimensional point cloud data block. Then, determine the coordinate distance between at least one three-dimensional coordinate point included in the three-dimensional point cloud data block and the midpoint coordinates, and sort the at least one three-dimensional coordinate point included in the three-dimensional point cloud data block according to the coordinate distance. Then, the above-mentioned execution entity can remove the last K three-dimensional coordinate points of the at least one three-dimensional coordinate point after sorting as outliers. Among them, the value of K can be determined according to the number of three-dimensional coordinate points in the at least one three-dimensional coordinate point included in the three-dimensional point cloud data block. For example, K=10%×M. M is the number of three-dimensional coordinate points in the at least one three-dimensional coordinate point included in the three-dimensional point cloud data block. K≥0, when 10%×M contains a decimal, the value of 10%×M is rounded down.
[0050] The third sub-step is to determine the surface center of each unit surface corresponding to the three-dimensional point cloud data block after outlier removal in the above three-dimensional point cloud data block set after outlier removal, and obtain a surface center set.
[0051] In practice, the center of the surface may be a position point corresponding to the midpoint coordinates of at least one three-dimensional coordinate point included in the three-dimensional point cloud data block after outliers are removed.
[0052] The fourth sub-step is to construct a plane based on the obtained face center set to generate an initial plane corresponding to the above three-dimensional point cloud sub-data.
[0053] In practice, first, the execution subject may construct a triangular plane from three adjacent face centers in the face center set, and then splice the obtained triangular planes to obtain the initial plane.
[0054] The third step is to perform plane splicing on each initial plane in the obtained initial plane set to generate the above three-dimensional model.
[0055] In practice, the execution entity may splice adjacent initial planes in the initial plane set, and continuously iterate until the initial plane set is empty, so as to generate the three-dimensional model.
[0056] The content in the above "some optional implementations of some embodiments" is an inventive point of the present disclosure, which solves the second technical problem mentioned in the background technology, namely, "the conventional three-dimensional modeling method occupies more computing resources and increases the computing resource occupancy rate of the three-dimensional modeling simulation". Based on this, the present disclosure simplifies the construction method when constructing a three-dimensional model, that is, only considers the three-dimensional construction of the surface of the three-dimensional model. Specifically, first, the point cloud data is segmented, so that multiple three-dimensional point cloud sub-data can be synchronously processed in parallel. Then, since the present disclosure only involves the three-dimensional construction of the surface of the three-dimensional model, the above three-dimensional point cloud sub-data is segmented into unit faces to generate three-dimensional point cloud data blocks to obtain a set of three-dimensional point cloud data blocks. Compared with the voxelization method, the amount of data processing is reduced. Then, each three-dimensional point cloud data block in the above three-dimensional point cloud data block set is subjected to outlier removal to generate a three-dimensional point cloud data block after outlier removal, and obtain a set of three-dimensional point cloud data blocks after outlier removal. To reduce the influence of outliers on the final modeling longitude. Furthermore, the surface center of each unit surface corresponding to each three-dimensional point cloud data block after outlier removal in the above three-dimensional point cloud data block set after outlier removal is determined to obtain a surface center set. The three-dimensional point cloud data block after removal in the unit surface is represented by the surface center, and the volume of the point cloud data used for modeling is further reduced. Finally, a plane is constructed according to the obtained surface center set to generate an initial plane corresponding to the above three-dimensional point cloud sub-data. In this way, the amount of data processing for three-dimensional modeling is reduced and resource usage is reduced.
[0057] Step 104: Determine the water inlet point information in the target power distribution room according to the three-dimensional model, and obtain a water inlet point information set.
[0058] In some embodiments, the above-mentioned execution subject can determine the water inlet point information in the target distribution room according to the three-dimensional model to obtain the water inlet point information set. Among them, the water inlet point information represents the area in the three-dimensional model that is connected to the outside world. In other words, the water inlet point information can also represent the area in the target distribution room that is connected to the outside world. Optionally, the water inlet point information in the water inlet point information set may include: water inlet point position and water inlet point specification. Among them, the water inlet point position represents the coordinates of the water inlet point in the three-dimensional model, and can also represent the three-dimensional coordinates in the target distribution room. Among them, the coordinates of the water inlet point represented by the water inlet point position in the three-dimensional model and the three-dimensional coordinates represented in the target distribution room can be converted to each other. In practice, the above-mentioned execution subject can determine the area where the slope disappears, or the position where the surrounding slope values are greater than the slope value itself, as the water inlet point position by calculating the slope of the plane of the three-dimensional model. The water inlet point specification represents the regional size of the water inlet point.
[0059] In some optional implementations of some embodiments, the execution subject determines the water inlet point information in the target power distribution room according to the three-dimensional model to obtain the water inlet point information set, which may include the following steps:
[0060] The first step is to determine the plane boundary based on the above-mentioned plane structure information of the distribution room.
[0061] Among them, the above-mentioned plane boundary is the house plane boundary of the above-mentioned target distribution room. In practice, first, the above-mentioned execution subject can generate a distribution room plan for the above-mentioned target distribution room according to the above-mentioned distribution room plane construction information. Specifically, the above-mentioned execution subject can import the distribution room plane construction information into engineering drawing software, such as CAD (Computer Aided Design) software, to generate the above-mentioned distribution room plan. Then, the above-mentioned execution subject can determine the house plane boundary of the above-mentioned target distribution room in the distribution room plan as the above-mentioned plane boundary.
[0062] The second step is to determine a local three-dimensional model in the three-dimensional model that matches the plane boundary.
[0063] Among them, the boundary similarity between the orthographic projection boundary corresponding to the local three-dimensional model and the above-mentioned plane boundary meets the preset similarity condition. In practice, first, the above-mentioned execution entity can split the three-dimensional model into multiple candidate local three-dimensional models. Among them, the orthographic projection boundary of the candidate local three-dimensional model is a closed boundary. Then, the above-mentioned execution entity can respectively determine the boundary similarity between the orthographic projection boundary of each candidate local three-dimensional model in the multiple candidate local three-dimensional models and the above-mentioned plane boundary. Then, the above-mentioned execution entity can filter out the candidate local three-dimensional model whose corresponding boundary similarity is the maximum value from the candidate local three-dimensional models as the local three-dimensional model.
[0064] The third step is to determine the concave area corresponding to the above-mentioned local three-dimensional model and obtain a concave area set.
[0065] The curvature value of each point in the concave area is a positive value. In practice, the execution subject can determine the concave area corresponding to the local three-dimensional model by calculating the curvature of the surface, and obtain a concave area set.
[0066] The fourth step is to determine the regional position of each concave area in the concave area set in the three-dimensional model as the water inlet point position included in the water inlet point information corresponding to the concave area in the water inlet point information set.
[0067] The fifth step is to determine the area size of each concave area in the above-mentioned concave area set as the water inlet point specification included in the water inlet point information corresponding to the above-mentioned concave area in the above-mentioned water inlet point information set.
[0068] Step 105 , performing information matching on the water inlet point information in the water inlet point information set to generate simulated water inlet point information, thereby obtaining a simulated water inlet point information set.
[0069] In some embodiments, the execution subject may match the water inlet point information in the water inlet point information set to generate simulated water inlet point information and obtain a simulated water inlet point information set. The simulated water inlet point information in the simulated water inlet point information set includes: at least one water inlet point position information. When performing flooding simulation, the corresponding position of at least one water inlet point position information represented by the simulated water inlet point position information is used as the water inlet point.
[0070] In some optional implementations of some embodiments, the execution subject performs information matching on the water inlet point information in the water inlet point information set to generate simulated water inlet point information, and obtaining the simulated water inlet point information set may include the following steps:
[0071] The first step is to determine the number of water inlet point information in the above water inlet point information set as the first target value.
[0072] In practice, the execution subject may determine the first target value through the len() function.
[0073] In the second step, the first target value is used as the upper interval and the second target value is used as the lower interval to generate an interval range.
[0074] Among them, the above-mentioned second target value is 1.
[0075] In the third step, for each interval value within the above interval range, the above interval value is used as the quantity constraint value, and the water inlet point information in the above water inlet point information set is randomly and non-repetitively combined to obtain the simulated water inlet point information in the above simulated water inlet point information set.
[0076] The interval value is an integer value.
[0077] As an example, the interval range may be [1, 3]. The water inlet point information set may include: water inlet point information A, water inlet point information B, water inlet point information C, water inlet point information D, water inlet point information E and water inlet point information F. When the interval value is 1, the simulated water inlet point information set is the water inlet point information set. When the interval value is 2: water inlet point information A and water inlet point information B may be used as simulated water inlet point information. Water inlet point information A and water inlet point information C may be used as simulated water inlet point information. Water inlet point information A and water inlet point information D may be used as simulated water inlet point information. Water inlet point information A and water inlet point information E may be used as simulated water inlet point information. Water inlet point information A and water inlet point information F may be used as simulated water inlet point information. Water inlet point information B and water inlet point information C may be used as simulated water inlet point information. Water inlet point information B and water inlet point information D may be used as simulated water inlet point information. The water inlet point information B and the water inlet point information E can be used as simulated water inlet point information. The water inlet point information B and the water inlet point information F can be used as simulated water inlet point information. The water inlet point information C and the water inlet point information D can be used as simulated water inlet point information. The water inlet point information C and the water inlet point information E can be used as simulated water inlet point information. The water inlet point information C and the water inlet point information F can be used as simulated water inlet point information. The water inlet point information D and the water inlet point information E can be used as simulated water inlet point information. The water inlet point information D and the water inlet point information F can be used as simulated water inlet point information. The water inlet point information E and the water inlet point information F can be used as simulated water inlet point information.
[0078] Step 106, for each simulated water inlet point information in the simulated water inlet point information set, the simulated water inlet point corresponding to the simulated water inlet point information is used as the water inlet point, and a flooding simulation is performed on the target distribution room according to the three-dimensional model to generate a flooding simulation result.
[0079] In some embodiments, for each simulated water inlet point information in the simulated water inlet point information set, the execution subject may use the simulated water inlet point corresponding to the simulated water inlet point information as the water inlet point, and perform a flooding simulation on the target power distribution room according to the three-dimensional model to generate a flooding simulation result. The flooding simulation result represents the flooding situation of the power distribution room equipment at each time during the flooding simulation process.
[0080] In some optional implementations of some embodiments, the execution subject performs flooding simulation on the target distribution room according to the three-dimensional model for each simulated water inlet point information in the simulated water inlet point information set, taking the simulated water inlet point corresponding to the simulated water inlet point information as the water inlet point, to generate a flooding simulation result, which may include the following steps:
[0081] The first step is to construct a three-dimensional hydrodynamic model for the above three-dimensional model.
[0082] In practice, first, the above-mentioned execution subject can construct a hydrodynamic equation based on the Navier-Stokes equation and the continuity equation. Then, the parameters contained in the hydrodynamic equation are initialized. For example, the water viscosity parameter is initialized. Then, the hydrodynamic equation is solved. Specifically, the above-mentioned execution subject can solve the hydrodynamic equation by, for example, the finite element method, the finite volume method, etc. Then, the above-mentioned three-dimensional hydrodynamic equation is determined according to the hydrodynamic equation and the corresponding equation solution.
[0083] In the second step, the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information is used as the water inlet point, and according to the above-mentioned three-dimensional hydrodynamic model, a flooding simulation is performed on the above-mentioned target distribution room to generate the above-mentioned flooding simulation result.
[0084] In practice, the execution entity may simulate the three-dimensional hydrodynamic model and record the flooding conditions in the three-dimensional model at each moment during the simulation as a flooding simulation result.
[0085] Step 107: Generate flooding handling information for the target distribution room based on the obtained flooding simulation result set.
[0086] In some embodiments, the above-mentioned execution subject can generate flooding treatment information for the target distribution room according to the obtained flooding simulation result set. In practice, the flooding treatment information may include: power-off sequence information of the equipment, and flooding protection treatment information matching the flooding situation. Optionally, the flooding treatment information includes: a flooding treatment sub-information set. The flooding treatment sub-information corresponds to specific flooding protection strategies under different flooding situations.
[0087] In some optional implementations of some embodiments, the execution subject generates flooding disposal information for the target power distribution room according to the obtained flooding simulation result set, which may include the following steps:
[0088] In the first step, the flooding simulation results in the flooding simulation result set are clustered to generate a clustered flooding simulation result group set.
[0089] In practice, the execution subject may cluster the flooding simulation results in the flooding simulation result set by using a K clustering algorithm to generate a clustered flooding simulation result group set. Specifically, similar flooding situations may correspond to the same disposal strategy. In order to generate a universal disposal strategy, the flooding simulation results corresponding to the same disposal strategy are merged by clustering the results.
[0090] The second step is to search for flooding treatment sub-information matching the above-mentioned post-clustering flooding simulation result group from the flooding treatment information database for each post-clustering flooding simulation result group in the above-mentioned post-clustering flooding simulation result group set, and obtain the above-mentioned flooding treatment sub-information set.
[0091] In practice, the flood handling information base may be an information base storing pre-configured flood protection and handling strategies. Specifically, when the flood handling information base does not contain the corresponding flood protection and handling strategy, a supplementary reminder may be initiated to remind relevant personnel to update the strategy of the flood handling information base.
[0092] Optionally, the above method further includes:
[0093] The first step is to determine the sensor layout position of the water level sensor for the target distribution room according to the flooding simulation results.
[0094] In practice, the above-mentioned execution entity may determine the deepest water depth corresponding to the flooding simulation result as the sensor layout location.
[0095] In the second step, in response to the completion of the layout of the water level sensor to the above-mentioned sensor layout position, the real-time water level information collected by the above-mentioned water level sensor is synchronized to the digital twin corresponding to the above-mentioned target distribution room.
[0096] Among them, the digital twin is a data platform that matches the above-mentioned target distribution room and is used to display real-time operating parameters and real-time status.
[0097] The above-mentioned various embodiments of the present disclosure have the following beneficial effects: the flooding simulation method applied to the distribution room of some embodiments of the present disclosure reduces the risk of equipment being damaged by flooding. Specifically, the reason for the high risk of equipment being damaged by flooding is that the timeliness of manual inspection is poor, which easily leads to untimely flooding protection, thereby increasing the risk of equipment being damaged by flooding. In practice, when the flooding situation is more complicated, the timeliness of the method of using manual inspection and flooding protection according to the actual situation is poor, and because water is conductive, untimely flooding protection is very likely to increase the risk of equipment short circuit, thereby increasing the risk of equipment damage by flooding. Based on this, the flooding simulation method applied to the distribution room of some embodiments of the present disclosure, first, obtain the distribution room description information corresponding to the target distribution room, wherein the above-mentioned distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the above-mentioned distribution room plane structure information is used to describe the house plane structure of the above-mentioned target distribution room, and the above-mentioned distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the above-mentioned target distribution room. In this way, the house plane structure and equipment layout corresponding to the target distribution room are obtained. Secondly, according to the above-mentioned distribution room description information, the three-dimensional point cloud data for the above-mentioned target distribution room is determined. Then, according to the above-mentioned three-dimensional point cloud data, a three-dimensional model for the above-mentioned target distribution room is generated. In this way, a three-dimensional model for the target distribution room is obtained for subsequent flooding simulation. Further, according to the above-mentioned three-dimensional model, the water inlet point information in the above-mentioned target distribution room is determined to obtain a water inlet point information set. In practice, the non-enclosed area of the target distribution room often has multiple areas connected to the outside world, and when flooding occurs, the areas connected to the outside world can all be water inlet locations. In addition, the water inlet point information in the above-mentioned water inlet point information set is matched to generate simulated water inlet point information to obtain a simulated water inlet point information set. In practice, there may be a situation where multiple water inlet locations are flooded at the same time, so it is necessary to combine the water inlet points. In addition, for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information is used as the water inlet point, and the above-mentioned target distribution room is subjected to a flooding simulation according to the above-mentioned three-dimensional model to generate a flooding simulation result, wherein the above-mentioned flooding simulation result characterizes the flooding conditions of the distribution room equipment at each moment during the flooding simulation process. In this way, flooding simulation conditions under different circumstances and at different moments are obtained. Finally, based on the obtained flooding simulation result set, flooding disposal information for the above-mentioned target distribution room is generated. In this way, flooding simulation disposal plans for different circumstances are obtained. In this way, flooding simulation in complex situations is realized, the efficiency of flooding protection when flooding occurs is improved, and the risk of equipment being damaged by flooding is reduced.
[0098] Further references Figure 2As an implementation of the methods shown in the above figures, the present disclosure provides some embodiments of a flooding simulation device for a power distribution room. These device embodiments are similar to Figure 1 Corresponding to the method embodiments shown, the flooding simulation device applied to the power distribution room can be specifically applied to various electronic devices.
[0099] like Figure 2 As shown, some embodiments of the flooding simulation device 200 applied to the distribution room include: an acquisition unit 201, a first determination unit 202, a first generation unit 203, a second determination unit 204, an information matching unit 205, a flooding simulation unit 206, and a second generation unit 207. The acquisition unit 201 is configured to acquire the distribution room description information corresponding to the target distribution room, wherein the distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the distribution room plane structure information is used to describe the house plane structure of the target distribution room, and the distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the target distribution room; the first determination unit 202 is configured to determine the three-dimensional point cloud data for the target distribution room according to the distribution room description information; the first generation unit 203 is configured to generate a three-dimensional model for the target distribution room according to the three-dimensional point cloud data; the second determination unit 204 is configured to determine the water inlet point position information in the target distribution room according to the three-dimensional model. information to obtain a water inlet point information set; an information matching unit 205 is configured to perform information matching on the water inlet point information in the above-mentioned water inlet point information set to generate simulated water inlet point information and obtain a simulated water inlet point information set; a flooding simulation unit 206 is configured to, for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, take the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information as the water inlet point, perform a flooding simulation on the above-mentioned target distribution room according to the above-mentioned three-dimensional model to generate a flooding simulation result, wherein the above-mentioned flooding simulation result represents the flooding situation of the distribution room equipment at each moment during the flooding simulation process; a second generating unit 207 is configured to generate flooding disposal information for the above-mentioned target distribution room according to the obtained flooding simulation result set.
[0100] It can be understood that the units described in the flooding simulation device 200 for a power distribution room are similar to those described in the reference Figure 1 Therefore, the operations, features and beneficial effects described above for the method are also applicable to the flooding simulation device 200 for the power distribution room and the units contained therein, and will not be described in detail here.
[0101] Reference below Figure 3, which shows a structural schematic diagram of an electronic device (eg, a computing device) 300 suitable for implementing some embodiments of the present disclosure. Figure 3 The electronic device shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present disclosure.
[0102] like Figure 3 As shown, the electronic device 300 may include a processing device (e.g., a central processing unit, a graphics processing unit, etc.) 301, which can perform various appropriate actions and processes according to a program stored in a read-only memory 302 or a program loaded from a storage device 308 into a random access memory 303. Various programs and data required for the operation of the electronic device 300 are also stored in the random access memory 303. The processing device 301, the read-only memory 302, and the random access memory 303 are connected to each other via a bus 304. An input / output interface 305 is also connected to the bus 304.
[0103] Typically, the following devices may be connected to the I / O interface 305: an input device 306 including, for example, a touch screen, a touch pad, a keyboard, a mouse, a camera, a microphone, an accelerometer, a gyroscope, etc.; an output device 307 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; a storage device 308 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 309. The communication device 309 may allow the electronic device 300 to communicate with other devices wirelessly or by wire to exchange data. Figure 3 The electronic device 300 is shown with various devices, but it should be understood that it is not required to implement or possess all the devices shown. More or fewer devices may be implemented or possessed instead. Figure 3 Each block shown in the figure may represent one device, or may represent multiple devices as required.
[0104] In particular, according to some embodiments of the present disclosure, the process described above with reference to the flowchart can be implemented as a computer software program. For example, some embodiments of the present disclosure include a computer program product, which includes a computer program carried on a computer-readable medium, and the computer program contains program code for executing the method shown in the flowchart. In some such embodiments, the computer program can be downloaded and installed from the network through the communication device 309, or installed from the storage device 308, or installed from the read-only memory 302. When the computer program is executed by the processing device 301, the above-mentioned functions defined in the method of some embodiments of the present disclosure are executed.
[0105] It should be noted that the computer-readable medium recorded in some embodiments of the present disclosure may be a computer-readable signal medium or a computer-readable storage medium or any combination of the above two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In some embodiments of the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by or in combination with an instruction execution system, device or device. In some embodiments of the present disclosure, a computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer readable signal media may also be any computer readable medium other than computer readable storage media, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer readable medium may be transmitted using any appropriate medium, including but not limited to: wires, optical cables, RF (radio frequency), etc., or any suitable combination of the above.
[0106] In some embodiments, the client and the server may communicate using any currently known or future developed network protocol such as HTTP (Hyper Text Transfer Protocol), and may be interconnected with any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include a local area network ("LAN"), a wide area network ("WAN"), an internet (e.g., the Internet), and a peer-to-peer network (e.g., an ad hoc peer-to-peer network), as well as any currently known or future developed network.
[0107] The above-mentioned computer-readable medium may be included in the above-mentioned electronic device; or it may exist independently without being assembled into the electronic device. The above-mentioned computer-readable medium carries one or more programs. When the above-mentioned one or more programs are executed by the electronic device, the electronic device: obtains the distribution room description information corresponding to the target distribution room, wherein the above-mentioned distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the above-mentioned distribution room plane structure information is used to describe the building plane structure of the above-mentioned target distribution room, and the above-mentioned distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the above-mentioned target distribution room; according to the above-mentioned distribution room description information, determines the three-dimensional point cloud data for the above-mentioned target distribution room; according to the above-mentioned three-dimensional point cloud data, generates a three-dimensional model for the above-mentioned target distribution room; according to the above-mentioned three-dimensional model , determine the water inlet point information in the above-mentioned target distribution room to obtain a water inlet point information set; perform information matching on the water inlet point information in the above-mentioned water inlet point information set to generate simulated water inlet point information to obtain a simulated water inlet point information set; for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, take the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information as the water inlet point, and perform flooding simulation on the above-mentioned target distribution room according to the above-mentioned three-dimensional model to generate a flooding simulation result, wherein the above-mentioned flooding simulation result characterizes the flooding situation of the distribution room equipment at each moment during the flooding simulation process; based on the obtained flooding simulation result set, generate flooding disposal information for the above-mentioned target distribution room.
[0108] Computer program code for performing the operations of some embodiments of the present disclosure may be written in one or more programming languages or a combination thereof, including object-oriented programming languages such as Java, Smalltalk, C++, and conventional procedural programming languages such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., via the Internet using an Internet service provider).
[0109] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present disclosure. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some implementations as replacements, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.
[0110] The units described in some embodiments of the present disclosure may be implemented by software or by hardware. The units described may also be set in a processor, for example, may be described as: a processor including an acquisition unit, a first determination unit, a first generation unit, a second determination unit, an information matching unit, a flooding simulation unit, and a second generation unit. Among them, the names of these units do not constitute a limitation on the unit itself under certain circumstances. For example, the flooding simulation unit may also be described as "for each simulated water inlet point information in the above-mentioned simulated water inlet point information set, the simulated water inlet point corresponding to the above-mentioned simulated water inlet point information is used as the water inlet point, and the above-mentioned target distribution room is flooded according to the above-mentioned three-dimensional model. Simulation results are generated to generate flooding simulation results, wherein the above-mentioned flooding simulation results characterize the flooding conditions of the distribution room equipment at each moment during the flooding simulation process."
[0111] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.
[0112] The above descriptions are only some preferred embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the above inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the embodiments of the present disclosure.
Claims
1. A flooding simulation method applied to a power distribution room, comprising: Obtaining the distribution room description information corresponding to the target distribution room, wherein the distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the distribution room plane structure information is used to describe the house plane structure of the target distribution room, and the distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the target distribution room; Determine the three-dimensional point cloud data for the target power distribution room according to the power distribution room description information; Generating a three-dimensional model of the target power distribution room according to the three-dimensional point cloud data; According to the three-dimensional model, the water inlet point information in the target power distribution room is determined to obtain a water inlet point information set, wherein the water inlet point information in the water inlet point information set includes: water inlet point location and water inlet point specification, and the water inlet point information represents the area in the target power distribution room that is connected to the outside world; Performing information matching on the water inlet point information in the water inlet point information set to generate simulated water inlet point information, and obtaining a simulated water inlet point information set, wherein the simulated water inlet point information in the simulated water inlet point information set includes: at least one water inlet point position information, and when performing flooding simulation, taking the corresponding position of at least one water inlet point position information represented by the simulated water inlet point position information as the water inlet point; For each simulated water inlet point information in the simulated water inlet point information set, the simulated water inlet point corresponding to the simulated water inlet point information is used as the water inlet point, and the target power distribution room is subjected to a flooding simulation according to the three-dimensional model to generate a flooding simulation result, wherein the flooding simulation result represents the flooding condition of the power distribution room equipment at each moment during the flooding simulation process; According to the obtained flood simulation result set, flood handling information for the target power distribution room is generated, wherein the flood handling information includes: a flood handling sub-information set, wherein: Generating a three-dimensional model of the target power distribution room according to the three-dimensional point cloud data includes: Performing point cloud data segmentation on the three-dimensional point cloud data to obtain a three-dimensional point cloud sub-data sequence; For each 3D point cloud sub-data in the 3D point cloud sub-data sequence, the following processing steps are performed: Performing unit face segmentation on the three-dimensional point cloud sub-data to generate three-dimensional point cloud data blocks, thereby obtaining a three-dimensional point cloud data block set; Performing outlier elimination on each three-dimensional point cloud data block in the three-dimensional point cloud data block set to generate a three-dimensional point cloud data block after outlier elimination, thereby obtaining a three-dimensional point cloud data block set after outlier elimination; Determine the surface center of each unit surface corresponding to each outlier-eliminated three-dimensional point cloud data block in the outlier-eliminated three-dimensional point cloud data block set to obtain a surface center set; Constructing a plane according to the obtained face center set to generate an initial plane corresponding to the three-dimensional point cloud sub-data; Perform plane splicing on each initial plane in the obtained initial plane set to generate the three-dimensional model, wherein: Determining the water inlet point information in the target power distribution room according to the three-dimensional model to obtain a water inlet point information set includes: Determine a plane boundary according to the plane structure information of the power distribution room, wherein the plane boundary is a house plane boundary of the target power distribution room; Determine a local three-dimensional model in the three-dimensional model that matches the plane boundary, wherein a boundary similarity between an orthographic projection boundary corresponding to the local three-dimensional model and the plane boundary satisfies a preset similarity condition; Determine the concave area corresponding to the local three-dimensional model to obtain a concave area set; Determine the regional position of each concave area in the concave area set in the three-dimensional model as the water inlet point position position included in the water inlet point position information corresponding to the concave area in the water inlet point position information set; Determine the area size of each concave area in the concave area set as the water inlet point specification included in the water inlet point information set corresponding to the concave area, wherein: For each simulated water inlet point information in the simulated water inlet point information set, taking the simulated water inlet point corresponding to the simulated water inlet point information as the water inlet point, performing flooding simulation on the target power distribution room according to the three-dimensional model to generate a flooding simulation result, including: constructing a three-dimensional hydrodynamic model for the three-dimensional model; The simulated water inlet point corresponding to the simulated water inlet point information is used as the water inlet point, and according to the three-dimensional hydrodynamic model, a flooding simulation is performed on the target power distribution room to generate the flooding simulation result, wherein: The generating of flooding handling information for the target power distribution room according to the obtained flooding simulation result set includes: Clustering the flooding simulation results in the flooding simulation result set to generate a clustered flooding simulation result group set; For each post-clustering flooding simulation result group in the post-clustering flooding simulation result group set, the flooding treatment sub-information matching the post-clustering flooding simulation result group is searched from the flooding treatment information database to obtain the flooding treatment sub-information set.
2. The method according to claim 1, wherein: The method further comprises: Determining a sensor layout position of a water level sensor for the target power distribution room according to the flooding simulation result; In response to the completion of the layout of the water level sensor to the sensor layout position, the real-time water level information collected by the water level sensor is synchronized to the digital twin corresponding to the target power distribution room.
3. The method according to claim 2, wherein: The step of determining the three-dimensional point cloud data for the target power distribution room according to the power distribution room description information includes: Generate a power distribution room plan view for the target power distribution room according to the power distribution room plan structure information; According to the power distribution room equipment information, the power distribution room plan is updated to generate an updated power distribution room plan; Taking the distribution room entrance of the target distribution room as the starting point, generating the shortest traversal path for the target distribution room according to the updated distribution room plan; Taking the shortest traversal path as the path, control the self-propelled point cloud data acquisition vehicle to collect point cloud data of the target distribution room to generate the three-dimensional point cloud data, wherein the self-propelled point cloud data acquisition vehicle includes: a tracked mobile chassis, a telescopic support rod and a 256-beam laser radar, and the telescopic support rod is arranged between the tracked mobile chassis and the 256-beam laser radar to support the 256-beam laser radar.
4. The method according to claim 3, wherein: The information matching of the water inlet point information in the water inlet point information set to generate simulated water inlet point information to obtain the simulated water inlet point information set includes: Determine the number of water inlet point information in the water inlet point information set as a first target value; Using the first target value as the upper interval and the second target value as the lower interval to generate an interval range, wherein the second target value is 1; For each interval value within the interval range, the water inlet point information in the water inlet point information set is randomly and non-repetitively combined with the interval value as a quantity constraint value to obtain the simulated water inlet point information in the simulated water inlet point information set, wherein the interval value is an integer value.
5. A flooding simulation device for a power distribution room, comprising: An acquisition unit is configured to acquire distribution room description information corresponding to a target distribution room, wherein the distribution room description information includes: distribution room plane structure information and distribution room equipment information, wherein the distribution room plane structure information is used to describe the house plane structure of the target distribution room, and the distribution room equipment information is used to describe the equipment parameters and equipment layout of the distribution room equipment in the target distribution room; A first determining unit is configured to determine three-dimensional point cloud data for the target power distribution room according to the power distribution room description information; A first generating unit is configured to generate a three-dimensional model for the target power distribution room according to the three-dimensional point cloud data; The second determination unit is configured to determine the water inlet point information in the target power distribution room according to the three-dimensional model, and obtain a water inlet point information set, wherein the water inlet point information in the water inlet point information set includes: the water inlet point location and the water inlet point specification. The water inlet point information represents the area in the target power distribution room that is connected to the outside world; The information matching unit is configured to perform information matching on the water inlet point information in the water inlet point information set to generate simulated water inlet point information to obtain a simulated water inlet point information set, wherein the simulated water inlet point information in the simulated water inlet point information set includes: at least one water inlet point position information, when performing flooding simulation, the position corresponding to at least one water inlet point position information represented by the simulated water inlet point position information is used as the water inlet point; The flooding simulation unit is configured to perform flooding simulation on the target power distribution room according to the three-dimensional model for each simulated water inlet point information in the simulated water inlet point information set, taking the simulated water inlet point corresponding to the simulated water inlet point information as the water inlet point, so as to generate a flooding simulation result, wherein the flooding simulation result represents the flooding condition of the power distribution room equipment at each moment during the flooding simulation process; The second generating unit is configured to generate flooding treatment information for the target power distribution room according to the obtained flooding simulation result set, wherein the flooding treatment information includes: a flooding treatment sub-information set, wherein: Generating a three-dimensional model of the target power distribution room according to the three-dimensional point cloud data includes: Performing point cloud data segmentation on the three-dimensional point cloud data to obtain a three-dimensional point cloud sub-data sequence; For each 3D point cloud sub-data in the 3D point cloud sub-data sequence, the following processing steps are performed: Performing unit face segmentation on the three-dimensional point cloud sub-data to generate three-dimensional point cloud data blocks, thereby obtaining a three-dimensional point cloud data block set; Performing outlier elimination on each three-dimensional point cloud data block in the three-dimensional point cloud data block set to generate a three-dimensional point cloud data block after outlier elimination, thereby obtaining a three-dimensional point cloud data block set after outlier elimination; Determine the surface center of each unit surface corresponding to each outlier-eliminated three-dimensional point cloud data block in the outlier-eliminated three-dimensional point cloud data block set to obtain a surface center set; Constructing a plane according to the obtained face center set to generate an initial plane corresponding to the three-dimensional point cloud sub-data; Perform plane splicing on each initial plane in the obtained initial plane set to generate the three-dimensional model, wherein: Determining the water inlet point information in the target power distribution room according to the three-dimensional model to obtain a water inlet point information set includes: Determine a plane boundary according to the plane structure information of the power distribution room, wherein the plane boundary is a house plane boundary of the target power distribution room; Determine a local three-dimensional model in the three-dimensional model that matches the plane boundary, wherein a boundary similarity between an orthographic projection boundary corresponding to the local three-dimensional model and the plane boundary satisfies a preset similarity condition; Determine the concave area corresponding to the local three-dimensional model to obtain a concave area set; Determine the regional position of each concave area in the concave area set in the three-dimensional model as the water inlet point position position included in the water inlet point position information corresponding to the concave area in the water inlet point position information set; Determine the area size of each concave area in the concave area set as the water inlet point specification included in the water inlet point information set corresponding to the concave area, wherein: For each simulated water inlet point information in the simulated water inlet point information set, taking the simulated water inlet point corresponding to the simulated water inlet point information as the water inlet point, performing flooding simulation on the target power distribution room according to the three-dimensional model to generate a flooding simulation result, including: constructing a three-dimensional hydrodynamic model for the three-dimensional model; The simulated water inlet point corresponding to the simulated water inlet point information is used as the water inlet point, and according to the three-dimensional hydrodynamic model, a flooding simulation is performed on the target power distribution room to generate the flooding simulation result, wherein: The generating of flooding handling information for the target power distribution room according to the obtained flooding simulation result set includes: Clustering the flooding simulation results in the flooding simulation result set to generate a clustered flooding simulation result group set; For each post-clustering flooding simulation result group in the post-clustering flooding simulation result group set, the flooding treatment sub-information matching the post-clustering flooding simulation result group is searched from the flooding treatment information database to obtain the flooding treatment sub-information set.
6. An electronic device comprising: one or more processors; a storage device having one or more programs stored thereon; When the one or more programs are executed by the one or more processors, the one or more processors implement the method according to any one of claims 1 to 4.