A method and system for evaluating the power regulation capability of short-process steelmaking users

By establishing a short-process steelmaking user's electricity regulation capability evaluation method for process load classification, the problem of insufficient electricity regulation capability evaluation technology for short-process steelmaking users is solved, and the accurate evaluation of the electricity regulation capability of short-process steelmaking users is achieved. and improve the power grid regulation capability.

CN118396353BActive Publication Date: 2024-12-06STATE GRID ZHEJIANG ELECTRIC POWER CO MARKETING SERVICE CENT +2
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410860755.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2024-12-06
Estimated Expiration
2044-06-28

AI Technical Summary

Technical Problem

The power consumption adjustment capability evaluation technology of short-process steelmaking users has not yet been studied in-depth, and it is difficult to effectively participate in power grid regulation, resulting in unstable interaction between power grid supply and demand.

Method used

Establish a short-process steelmaking user's electricity regulation capability assessment method that considers process load classification. By establishing a production process equivalent model, process load classification and mixed integer linear optimization model, evaluate the electricity regulation capability of short-process steelmaking users to maximize Differences between power purchase and production plan.

Benefits of technology

It has achieved an accurate assessment of the power regulation capabilities of short-process steelmaking users, enhanced the flexibility of grid regulation and guaranteed production plans, and supported new energy access and demand-side response.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118396353B_ABST
    Figure CN118396353B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and system for evaluating the power regulation capability of a short-process steelmaking user. The power regulation capability evaluation method adopted by the present invention includes: establishing an equivalent model of the production process of a short-process steelmaking user; analyzing the energy consumption and operating characteristics of the process of the short-process steelmaking user, and classifying the process load; establishing a power regulation capability evaluation model for a short-process steelmaking user that takes into account the process load classification, the model takes the maximum power regulation capability of the short-process steelmaking user within a certain period of time as the objective function, and the regulation capability is characterized by the difference between the external power purchase of the short-process steelmaking user after the process is adjustable and the external power purchase of the short-process steelmaking user predicted when producing according to the production plan. Based on the energy consumption and operating characteristics of the production process, the present invention classifies the process load of the short-process steelmaking user considering the process technology, and establishes a power regulation capability evaluation model that takes into account the adjustable process energy consumption, so as to realize the evaluation of the power regulation capability of the short-process steelmaking user.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of electricity regulation capability assessment, and relates to a method and system for assessing the electricity regulation capability of short-process steelmaking users taking process load classification into consideration. Background Art

[0002] The steel industry accounts for a high proportion of electricity consumption and has great potential for regulating process energy consumption. It is one of the most flexible demand-side resources for the power grid. In particular, short-process steelmaking users use high-power arc furnace equipment in their steelmaking process, which has great potential for regulation. The energy-consuming equipment involved in the short-process steelmaking production process is large in power and variety, and has complex energy characteristics. For example, the arc furnace needs to be frequently started and stopped for charging, and the rolling mill generates a certain amount of impact power every time it rolls a billet. The energy characteristics of each process vary greatly, and the regulation characteristics are also different. For short-process steelmaking users, their regulation characteristics are closely related to the process flow. Based on the adjustable process energy consumption, by shifting or reducing the process load of short-process steelmaking users, the stability and flexibility of their participation in power grid regulation can be improved, providing support for the access of new energy and demand-side response technology for the power grid.

[0003] The construction of the supply and demand interaction system between short-process steelmaking users and the power grid is still in its initial stage, and in-depth research is urgently needed to provide a technical basis for the steel industry load to participate in the interactive regulation of the power grid. Summary of the invention

[0004] The purpose of the present invention is to provide a method and system for evaluating the electricity regulation capability of short-process steelmaking users taking into account the process load classification, which establishes an evaluation model for the electricity regulation capability of short-process steelmaking users taking into account the process load classification, and through this evaluation model, accurate evaluation of the electricity regulation capability of short-process steelmaking users can be achieved.

[0005] The present invention adopts the following technical solution: a method for evaluating the power regulation capability of a short-process steelmaking user, comprising:

[0006] Step 1, establishing an equivalent model of the production process of short-process steelmaking users;

[0007] Step 2: Analyze the energy consumption and operation characteristics of the short-process steelmaking user process and classify the process load;

[0008] Step 3, establish a short-process steelmaking user electricity regulation capacity evaluation model considering process load classification. The model takes the maximum electricity regulation capacity of short-process steelmaking users within a certain period of time as the objective function, and the regulation capacity is characterized by the difference between the external electricity purchase power of short-process steelmaking users after considering the adjustable process and the external electricity purchase power of short-process steelmaking users predicted when producing according to the production plan.

[0009] Based on the energy consumption and operation characteristics of the production process, the present invention classifies the process loads of short-process steelmaking users taking into account the process technology, and establishes an electricity regulation capability evaluation model taking into account the adjustable process energy consumption, thereby realizing the evaluation of the electricity regulation capability of short-process steelmaking users.

[0010] The evaluation model constructed in the present invention is a mixed integer linear optimization model, which can be solved by calling a commercial solver such as Gurobi.

[0011] Furthermore, the short-process steelmaking user production process equivalent model includes an electric arc furnace steelmaking process, a steel rolling process and a buffer zone located between the first two processes. The buffer zone is used to temporarily store molten steel, taking into account both electricity and heat energy sources. The electric arc furnace process and the steel rolling process both have recoverable waste heat, and the heat source of the steel rolling process is coal or natural gas. Considering that the consumption of coal and natural gas is not limited, there is no impact on the regulation capacity. The electric arc furnace steelmaking process, the steel rolling process and the buffer zone are powered by a power supply.

[0012] Furthermore, the equivalent model of the short-process steelmaking user production process is guided by the material flow, and the energy flow and material flow are integrated as follows:

[0013] (1)

[0014] in, Represents the integrated set of energy flow and material flow; The power purchased from outside; The output electric power of the waste heat power generation device; , , They are the electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process respectively; , They are the recoverable heat power of the electric arc furnace steelmaking process and the steel rolling process respectively; is the input thermal power of the waste heat power generation device, equal and sum; is the raw material input amount; The material output of the electric arc furnace steelmaking process; The material output of the buffer zone; is the material output of the steel rolling process, that is, the final output of finished products; T Represents matrix transpose.

[0015] Furthermore, the process loads are classified according to the impacts of energy-consuming equipment on the power grid on different time scales, and the process loads of short-process steelmaking users are divided into intermittent impact loads, continuous impact loads and stable loads; the intermittent impact loads are for the electric arc furnace steelmaking process, which has the characteristic of being adjustable at the hour level; the continuous impact loads are for the steel rolling process, which has the characteristic of being adjustable at the minute level; the stable loads are lighting equipment and transmission equipment, which have the characteristic of being adjustable at the day level.

[0016] Furthermore, the objective function is shown in the following formula:

[0017] (2)

[0018] in, For users who consider short-process steelmaking after process adjustment The power purchased from outside at any time; For users of short-process steelmaking predicted by production plan The power purchased from outside at any time; T 1 is the entire production cycle.

[0019] Furthermore, step 3 also includes: establishing constraints that take into account adjustable process energy consumption; the constraints include adjustable process operation constraints, process coupling constraints, buffer inventory constraints, production plan target constraints, and production process energy conservation constraints.

[0020] Furthermore, the operation constraints of the adjustable process are the operation constraints of the electric arc furnace steelmaking process and the operation constraints of the steel rolling process;

[0021] The operating constraints of the electric arc furnace steelmaking process are as follows:

[0022] (3)

[0023] (4)

[0024] in, It is the time scale number of the arc furnace steelmaking process in the operation cycle; is a 0-1 variable, subscript sub 1 indicates the electric arc furnace steelmaking process; When At this moment, the arc furnace steelmaking process is in a non-working state, and the energy consumption and material output are 0; when When The electric arc furnace steelmaking process is in normal working condition at all times; It is the working state matrix of the electric arc furnace steelmaking process; Integrate energy and material flows for short-process steelmaking users; It is an integrated set of energy flow and material flow for short-process steelmaking users after considering the changing working state of arc furnace operation;

[0025] The adjustment times of the electric arc furnace steelmaking process are constrained as follows:

[0026] (5)

[0027] in, The maximum allowable adjustment times of the electric arc furnace;

[0028] The operational constraints of the steel rolling process are as follows:

[0029] (6)

[0030] (7)

[0031] in, It is the time scale number of the steel rolling process in the operation cycle; is a 0-1 variable, subscript sub 3 represents the steel rolling process; when When The steel rolling process is in a non-working state at the moment, and the energy consumption and material output are 0; When The steel rolling process is in normal working condition at all times; is the working state matrix of the steel rolling process; It is an integrated set of energy flow and material flow of short-process steelmaking users after considering the change of working state of steel rolling process operation;

[0032] The adjustment times constraints of the steel rolling process are as follows:

[0033] (8)

[0034] in, The maximum number of adjustments allowed for the steel rolling process;

[0035] For the problem that the adjustment time scales of the arc furnace steelmaking process and the rolling process are different, the time scale coordination is achieved through the following constraints: the adjustment time scale of the rolling process close to the actual one is taken as the reference value, and the adjustment time scale of the arc furnace steelmaking process is taken to be close to the actual one and an integer multiple of the adjustment time scale of the rolling process, that is, the arc furnace is in the same working state within a certain integer multiple of the adjustment time scale of the rolling process. The constraints are as follows:

[0036] (9)

[0037] in, Is a positive integer.

[0038] Furthermore, the process coupling constraints are as follows:

[0039] The electric arc furnace steelmaking process involves two energy sources: electricity and heat. The process coupling constraints are established as follows:

[0040] (10)

[0041] In the formula, represents a zero matrix of dimension 4×2; , , They respectively represent the power consumption, waste heat recovery and raw material consumption corresponding to the unit material output of the electric arc furnace steelmaking process;

[0042] The coupling constraints of the steel rolling process are:

[0043] (11)

[0044] in, is the energy conversion coefficient matrix; , , They respectively represent the power consumption, waste heat recovery and material consumption corresponding to the unit material output of the steel rolling process; is the constant term in the linear relationship between energy consumption and production; , , Represents zero matrices of dimensions 4×4, 4×1, 4×3;

[0045] The buffer inventory constraints are as follows:

[0046] For the buffer, The inventory capacity at the time is equal to The capacity of the moment plus The material input at the time, minus The material output at the time, and because the capacity has upper and lower limits, its constraints are as follows:

[0047] (12)

[0048] (13)

[0049] in, for Material inventory in the time buffer; , Material inventory for buffer zones The upper and lower limits of for The material output of the electric arc furnace steelmaking process at that moment, that is, the material input of the buffer zone; for Material output in the time buffer;

[0050] The production planning objective constraints are as follows:

[0051] During the entire production cycle, the planned total output must be met, subject to the following constraints:

[0052] (14)

[0053] in, for The output of finished products from the steel rolling process at any given moment; It is the total planned production volume during the entire production cycle.

[0054] Furthermore, the energy conservation constraints of the production process are as follows:

[0055] The electrical power and thermal power of the entire system should be balanced at all times, and the balance constraints are as follows:

[0056] (15)

[0057] (16)

[0058] (17)

[0059] in, , They are The heat power can be recovered from the electric arc furnace steelmaking process and steel rolling process; for Total thermal power consumed by the waste heat power generation device at all times; The thermoelectric conversion efficiency of the waste heat power generation device; for Output electric power of the waste heat power generation device at any moment; for The power purchased from outside at any time; , , They are The electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process at all times.

[0060] Another technical solution adopted by the present invention is: a system for evaluating the power regulation capability of short-process steelmaking users, which comprises:

[0061] Equivalent model building unit: used to build an equivalent model of the production process of short-process steelmaking users;

[0062] Process load classification unit: Analyze the energy consumption and operation characteristics of the short-process steelmaking user process and classify the process load;

[0063] Evaluation model establishment unit: Establish an evaluation model for the electricity regulation capacity of short-process steelmaking users taking into account the process load classification. The model takes the maximum electricity regulation capacity of short-process steelmaking users within a certain period of time as the objective function, and the regulation capacity is characterized by the difference between the external electricity purchase power of short-process steelmaking users after considering the adjustable process and the external electricity purchase power of short-process steelmaking users predicted when producing according to the production plan.

[0064] The beneficial effects of the present invention are as follows: Based on the equivalent model of the production process of short-process steelmaking users, the present invention takes into account the adjustable energy consumption of the process, comprehensive process coupling, safe operation and process regulation constraints, etc., to accurately evaluate the power regulation capacity of short-process steelmaking users. The present invention aims to enhance the ability of short-process steelmaking users to participate in the response to grid demand, while increasing the flexible regulation capacity of the grid to ensure the production plan and production safety of short-process steelmaking users. In addition, the present invention is also applicable to the evaluation of the power regulation capacity of steelmaking and subsequent processes of long-process steelmaking users. BRIEF DESCRIPTION OF THE DRAWINGS

[0065] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0066] Figure 1 It is a flow chart of a method for evaluating the power regulation capability of a short-process steelmaking user according to the present invention;

[0067] Figure 2 This is a typical short-process steelmaking user production process equivalent model diagram of the present invention;

[0068] Figure 3 It is a structural diagram of the power regulation capability evaluation system for short-process steelmaking users of the present invention;

[0069] Figure 4 is a diagram showing the adjustment capability results of an application example of the present invention;

[0070] Figure 5 yes Figure 4 A partial enlarged schematic diagram of . DETAILED DESCRIPTION

[0071] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0072] Example 1

[0073] This embodiment is a method for evaluating the power regulation capability of short-process steelmaking users. Figure 1 As shown, the specific steps are as follows:

[0074] (1) Establishing an equivalent model for the production process of short-process steelmaking users

[0075] Short-process steelmaking users use scrap steel as raw materials, and their main processes include electric arc furnace steelmaking and steel rolling. Due to different types of products or requirements, different users will add different refining processes between steelmaking and steel rolling, but their production and operation characteristics are basically the same as those of electric arc furnaces. Here, only the production process equivalent model of a typical short-process steelmaking user containing the main processes is established, and the rest can refer to the present invention to establish a production process equivalent model that conforms to their actual situation.

[0076] The equivalent model of the short-process steelmaking user production process is established as follows Figure 2 As shown, it includes two processes: electric arc furnace steelmaking and steel rolling. Some equipment in the middle can temporarily store molten steel, which is simplified to a buffer zone. Considering both electricity and heat, the electric arc furnace and steel rolling processes have waste heat that can be recovered. The heat source of the steel rolling process is coal or natural gas. The consumption of coal and natural gas is not limited and can be regarded as having no effect on the regulation capacity, so it is not considered here. The equivalent model of the production process of short-process steelmaking users is guided by the material flow direction, and the energy flow and material flow are integrated as follows:

[0077] (1)

[0078] in, The power purchased from outside; The output electric power of the waste heat power generation device; They are the electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process respectively; are the recoverable heat power of the electric arc furnace steelmaking process and the steel rolling process respectively; is the total input thermal power of the waste heat power generation device; is the raw material input amount; The material output of the electric arc furnace steelmaking process; The material output of the buffer zone; is the material output of the steel rolling process, that is, the final output of finished products; T Represents matrix transpose.

[0079] (2) Process load classification

[0080] The arc furnace and rolling mill high-power energy-consuming equipment in the short-process steelmaking users will have impacts on the power grid at different time scales due to their frequent start-stop production and operation characteristics. The process loads of short-process steelmaking users are divided into intermittent impact loads, continuous impact loads and stable loads, as follows:

[0081] 1) Intermittent shock load

[0082] The electric arc furnace converts electrical energy into heat energy to melt the charge and complete the subsequent high-temperature metallurgical reaction through the arc generated between the end of the graphite electrode and the charge. That is, this process involves electrical energy and heat energy, among which the heat energy carried by the material can be used to improve energy utilization by waste heat recovery technology. The power fluctuation of the electric arc furnace is not large during the rated operation period, but it will start and stop once every 30min-60min for charging, the start and stop time is about 10s, and the charging time is about 5min; the change of the power from rated power to 0 at the moment of starting and stopping the electric arc furnace has a great impact on the power grid, and its energy consumption and material output are both zero during the charging period; therefore, it is classified as an intermittent impact load. Due to the buffer zone and thermal inertia, the electric arc furnace can be properly controlled to start and stop to participate in the grid regulation, but the interval in between should not be too short, and the electric arc furnace is generally adjustable at the hour level.

[0083] 2) Continuous impact load

[0084] For the steel rolling process, the steel billet needs to be heated before rolling, which is generally achieved through a gas boiler. That is, this process involves energy such as electricity and heat. As an auxiliary process of the steel rolling process, the operating characteristics of the gas boiler are consistent with the steel rolling process, so it will not be analyzed in detail here. In the steel rolling process, each time the steel billet passes through the rolling mill, a certain impact power will be generated. The interval between two adjacent rolling mills is about 3s-5s, and it takes about 5 minutes to complete the rolling of a whole steel billet; therefore, it is classified as a continuous impact load. The rolling mill can also participate in the grid regulation by starting and stopping. The start and stop of the rolling mill is completed within a few seconds, and a complete steel billet completes the steel rolling process within a few minutes, that is, the steel rolling process has minute-level adjustable characteristics.

[0085] 3) Stable load

[0086] Since steel enterprises are users who work continuously for 24 hours, other loads such as lighting equipment and conveyors remain stable or fluctuate slightly for a long time, and are classified as stable loads. Generally, they have daily adjustable characteristics according to the production plan.

[0087] (3) Based on the regulation characteristics of the above-mentioned classified loads, a model for evaluating the electricity regulation capacity of short-process steelmaking users is established

[0088] 31) Objective function: The objective function is to maximize the power regulation capacity of short-process steelmaking users within a certain period of time. The regulation capacity is represented by the difference between the power purchased by short-process steelmaking users after the process is adjustable and the power purchased by short-process steelmaking users predicted when producing according to the production plan, as shown in the following formula:

[0089] (2)

[0090] in, For users who consider short-process steelmaking after process adjustment The power purchased from outside at any time; For users of short-process steelmaking predicted by production plan The power purchased from outside at any time; T 1 is the entire production cycle.

[0091] 32) Constraints

[0092] 321) Operation constraints of adjustable processes

[0093] Due to thermal inertia and the buffer zone between the arc furnace and the rolling mill, both the arc furnace and the rolling mill can be interrupted. The rolling mill process is a continuous impact load with a short operating cycle, and can generally be started and stopped in a short time.

[0094] Establish hourly adjustable intermittent impact load, that is, the operation constraints of the electric arc furnace are as follows:

[0095] (3)

[0096] (4)

[0097] in, It is the time scale number of the arc furnace steelmaking process in the operation cycle; is a 0-1 variable, subscript sub 1 indicates the electric arc furnace steelmaking process; When At this moment, the arc furnace steelmaking process is in a non-working state, and the energy consumption and material output are 0; when When The electric arc furnace steelmaking process is in normal working condition at all times.

[0098] Since frequent start and stop have certain damage to the life and performance of the equipment, the adjustment frequency constraint of the arc furnace is established:

[0099] (5)

[0100] in, The maximum allowable adjustment times of the arc furnace.

[0101] Similarly, a continuous impact load adjustable at the minute level is established, that is, the operation constraints of the steel rolling process are as follows:

[0102] (6)

[0103] (7)

[0104] in, It is the time scale number of the steel rolling process in the operation cycle; is a 0-1 variable, subscript sub 3 represents the steel rolling process; when When The steel rolling process is in a non-working state at the moment, and the energy consumption and material output are 0; When The steel rolling process is in normal working condition at all times.

[0105] Similarly, set up the steel rolling process adjustment times constraint:

[0106] (8)

[0107] in, It is the maximum allowable adjustment times for the steel rolling process.

[0108] For the problem that the adjustment time scales of the arc furnace steelmaking process and the rolling process are different, the time scale coordination is achieved through the following constraints: the adjustment time scale of the rolling process close to the actual value is taken as the reference value, and the adjustment time scale of the arc furnace steelmaking process is close to the actual value and is an integer multiple of the adjustment time scale of the rolling process. That is, the arc furnace is in the same working state within a certain integer multiple of the adjustment time scale of the rolling process. The constraints are as follows:

[0109] (9)

[0110] in, Is a positive integer.

[0111] 322) Process coupling constraints

[0112] For the adjacent processes, the material output at each moment corresponds to a certain material input and energy consumption. The material input of the next process depends on the material output of the previous process. Therefore, the processes influence and restrict each other, and the energy consumption and type of each process are also different. The conversion relationship between process materials and energy is represented by the coupling matrix, and the coupling constraints of each process are established. For the buffer zone, it can be regarded as no material loss, only involving electrical energy consumption, and the electric power fluctuation is not large, which can be regarded as a constant. The coupling constraints of its input and output are included in the coupling constraints of the previous and next processes, so the coupling constraints of the buffer zone are no longer established separately. The electric arc furnace steelmaking process involves two energy sources, electric heat, and its process coupling constraints are established as follows:

[0113] (10)

[0114] In the formula, represents a zero matrix of dimension 4×2; , , They respectively represent the power consumption, waste heat recovery and raw material consumption corresponding to the unit material output of the electric arc furnace steelmaking process;

[0115] The coupling constraints of the steel rolling process are:

[0116] (11)

[0117] in, is the energy conversion coefficient matrix; , , They respectively represent the power consumption, waste heat recovery and material consumption corresponding to the unit material output of the steel rolling process; is the constant term in the linear relationship between energy consumption and production; , , Represents a zero matrix of dimensions 4×4, 4×1, 4×3.

[0118] 323) Buffer inventory constraints

[0119] For the buffer, The inventory capacity at the time is equal to The capacity of the moment plus The material input at the time, minus The material output at the time, and because the capacity has upper and lower limits, its constraints are as follows:

[0120] (12)

[0121] (13)

[0122] in, for Material inventory in the time buffer; , Material inventory for buffer zones The upper and lower limits of for The material output of the electric arc furnace steelmaking process at that moment, that is, the material input of the buffer zone; for Material output in the time buffer;

[0123] 324) Production planning target constraints

[0124] During the entire production cycle, the planned total output must be met, subject to the following constraints:

[0125] (14)

[0126] in, for The output of finished products from the steel rolling process at any given moment; It is the total planned production volume during the entire production cycle.

[0127] 6) Energy conservation constraints;

[0128] The electrical power and thermal power of the entire system should be balanced at all times, and the balance constraints are as follows:

[0129] (15)

[0130] (16)

[0131] (17)

[0132] in, , They are The heat power can be recovered from the electric arc furnace steelmaking process and steel rolling process; for Total thermal power consumed by the waste heat power generation device at all times; The thermoelectric conversion efficiency of the waste heat power generation device; for Output electric power of the waste heat power generation device at any moment; for The power purchased from outside at any time; , , They are The electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process at all times.

[0133] In summary, the objective function (2) and constraint conditions (3) to (17) are combined to form an evaluation model for the electricity regulation capacity of short-process steelmaking users.

[0134] (4) Solution of the evaluation model for the electricity regulation capability of short-process steelmaking users

[0135] The evaluation model constructed in the present invention is a mixed integer linear optimization model, which can be solved by calling a commercial solver such as Gurobi.

[0136] Example 2

[0137] This embodiment is a system for evaluating the power regulation capability of short-process steelmaking users. Figure 3 As shown, it consists of an equivalent model building unit, a process load classification unit and an evaluation model building unit.

[0138] 1. Equivalent model establishment unit: used to establish an equivalent model of the short-process steelmaking user production process.

[0139] The short-process steelmaking user production process equivalent model includes an electric arc furnace steelmaking process, a steel rolling process and a buffer zone located between the first two processes. The buffer zone is used to temporarily store molten steel, taking into account both electricity and heat energy. The electric arc furnace process and the steel rolling process both have waste heat that can be recovered. The heat source of the steel rolling process is coal or natural gas. Considering that the consumption of coal and natural gas is not limited, there is no impact on the regulation capacity. The electric arc furnace steelmaking process, the steel rolling process and the buffer zone are powered by a power supply.

[0140] The equivalent model of the short-process steelmaking user production process is guided by the material flow, and the energy flow and material flow are integrated as follows:

[0141] (1)

[0142] in, Represents the integrated set of energy flow and material flow; The power purchased from outside; The output electric power of the waste heat power generation device; , , They are the electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process respectively; , They are the recoverable heat power of the electric arc furnace steelmaking process and the steel rolling process respectively; is the input thermal power of the waste heat power generation device, equal and sum; is the raw material input amount; The material output of the electric arc furnace steelmaking process; The material output of the buffer zone; is the material output of the steel rolling process, that is, the final output of finished products; T Represents matrix transpose.

[0143] 2. Process load classification unit: Analyze the energy consumption and operating characteristics of the short-process steelmaking user process, and classify the process load.

[0144] The process loads are classified according to the impacts of energy-consuming equipment on the power grid on different time scales, and the process loads of short-process steelmaking users are divided into intermittent impact loads, continuous impact loads and stable loads; the intermittent impact loads are the loads of the electric arc furnace steelmaking process, which are adjustable at the hour level; the continuous impact loads are the loads of the steel rolling process, which are adjustable at the minute level; the stable loads are lighting equipment and transmission equipment, which are adjustable at the day level.

[0145] 3. Evaluation model establishment unit: Establish an evaluation model for the electricity regulation capacity of short-process steelmaking users taking into account the process load classification. The model takes the maximum electricity regulation capacity of short-process steelmaking users within a certain period of time as the objective function. The regulation capacity is characterized by the difference between the external electricity purchase power of short-process steelmaking users after considering the adjustable process and the external electricity purchase power of short-process steelmaking users predicted when producing according to the production plan; Establish constraint conditions that take into account the adjustable process energy consumption.

[0146] The short-process steelmaking user electricity regulation capability assessment model can be solved by calling the commercial solver Gurobi.

[0147] The objective function is shown as follows:

[0148] (2)

[0149] in, For users who consider short-process steelmaking after process adjustment The power purchased from outside at any time; For users of short-process steelmaking predicted by production plan The power purchased from outside at any time; T 1 is the entire production cycle.

[0150] The constraints include operation constraints of adjustable processes, process coupling constraints, buffer inventory constraints, production plan target constraints, and production process energy conservation constraints.

[0151] The operation constraints of the adjustable process are the operation constraints of the electric arc furnace steelmaking process and the operation constraints of the steel rolling process;

[0152] The operating constraints of the electric arc furnace steelmaking process are as follows:

[0153] (3)

[0154] (4)

[0155] in, It is the time scale number of the arc furnace steelmaking process in the operation cycle; is a 0-1 variable, subscript sub 1 indicates the electric arc furnace steelmaking process; When At this moment, the arc furnace steelmaking process is in a non-working state, and the energy consumption and material output are 0; when When The electric arc furnace steelmaking process is in normal working condition at all times. It is the working state matrix of the electric arc furnace steelmaking process; Integrate energy and material flows for short-process steelmaking users; It is an integrated set of energy flow and material flow for short-process steelmaking users after considering the changing working state of arc furnace operation;

[0156] The adjustment times of the electric arc furnace steelmaking process are constrained as follows:

[0157] (5)

[0158] in, The maximum allowable adjustment times of the electric arc furnace;

[0159] The operational constraints of the steel rolling process are as follows:

[0160] (6)

[0161] (7)

[0162] in, It is the time scale number of the steel rolling process in the operation cycle; is a 0-1 variable, subscript sub 3 represents the steel rolling process; when When The steel rolling process is in a non-working state at the moment, and the energy consumption and material output are 0; When The steel rolling process is in normal working condition at all times; is the working state matrix of the steel rolling process; It is an integrated set of energy and material flows for short-process steelmaking users after considering the changing working conditions of the steel rolling process;

[0163] The adjustment times constraints of the steel rolling process are as follows:

[0164] (8)

[0165] in, The maximum number of adjustments allowed for the steel rolling process;

[0166] For the problem that the adjustment time scales of the arc furnace steelmaking process and the rolling process are different, the time scale coordination is achieved through the following constraints: the adjustment time scale of the rolling process close to the actual one is taken as the reference value, and the adjustment time scale of the arc furnace steelmaking process is taken to be close to the actual one and an integer multiple of the adjustment time scale of the rolling process, that is, the arc furnace is in the same working state within a certain integer multiple of the adjustment time scale of the rolling process. The constraints are as follows:

[0167] (9)

[0168] in, Is a positive integer.

[0169] The process coupling constraints are as follows:

[0170] The electric arc furnace steelmaking process involves two energy sources: electricity and heat. The process coupling constraints are established as follows:

[0171] (10)

[0172] In the formula, represents a zero matrix of dimension 4×2; , , They respectively represent the power consumption, waste heat recovery and raw material consumption corresponding to the unit material output of the electric arc furnace steelmaking process;

[0173] The coupling constraints of the steel rolling process are:

[0174] (11)

[0175] in, is the energy conversion coefficient matrix; , , They respectively represent the power consumption, waste heat recovery and material consumption corresponding to the unit material output of the steel rolling process; is the constant term in the linear relationship between energy consumption and production; , , Represents a zero matrix of dimensions 4×4, 4×1, 4×3.

[0176] The buffer inventory constraints are as follows:

[0177] For the buffer, The inventory capacity at the time is equal to The capacity of the moment plus The material input at the time, minus The material output at the time, and because the capacity has upper and lower limits, its constraints are as follows:

[0178] (12)

[0179] (13)

[0180] in, for Material inventory in the time buffer; , Material inventory for buffer zones The upper and lower limits of for The material output of the electric arc furnace steelmaking process at that moment, that is, the material input of the buffer zone; for Material output in the time buffer;

[0181] The production planning objective constraints are as follows:

[0182] During the entire production cycle, the planned total output must be met, subject to the following constraints:

[0183] (14)

[0184] in, for The output of finished products from the steel rolling process at any given moment; It is the total planned production volume during the entire production cycle.

[0185] The energy conservation constraints of the production process are as follows:

[0186] The electrical power and thermal power of the entire system should be balanced at all times, and the balance constraints are as follows:

[0187] (15)

[0188] (16)

[0189] (17)

[0190] in, , They are The heat power can be recovered from the electric arc furnace steelmaking process and steel rolling process; for Total thermal power consumed by the waste heat power generation device at all times; The thermoelectric conversion efficiency of the waste heat power generation device; for Output electric power of the waste heat power generation device at any moment; for The power purchased from outside at any time; , , They are The electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process at all times.

[0191] Application Examples

[0192] The application of the method described in the above embodiment 1 is explained in conjunction with an actual short-process steelmaking user. The user is a typical production process user, that is, its production process can be simplified as follows: Figure 2 The equivalent model is shown in Figure 1. The equipment parameters involved by this user are shown in Table 1. The operating cycle is 24 hours a day, and the time scale is 5 minutes, that is, N is 288. It takes 5 minutes for a piece of steel billet to go through the entire steel rolling process. The arc furnace smelting cycle is 45 minutes, that is, 40 minutes of working time and 5 minutes of downtime for charging. The arc furnace and rolling mill can be started and stopped at most twice within 24 hours, and the steel rolling process can be stopped for a maximum of 1 hour. The maximum adjustment capacity at 12:00 noon is taken as the goal, that is, the maximum adjustment capacity between the 133rd moment and the 144th moment is taken as the objective function. The planned daily output is not less than 3000t. The results are as follows Figure 4 and Figure 5 shown.

[0193] Table 1 Energy consumption equipment parameters of a short process steelmaking user

[0194]

[0195] Depend on Figure 4 and Figure 5 It can be seen that within the time range of the objective function, both the arc furnace and the rolling mill are shut down, providing a certain adjustment space for the power grid. Since the adjustment time scale of the arc furnace is 45 minutes, the adjustment is carried out in advance when the arc furnace is shut down for charging at the 126th moment, and the rolling mill participates in the adjustment at the 133rd moment. The maximum adjustment capacity generated by the whole process is 46.767MW.

[0196] It is obvious that those skilled in the art can easily make various modifications to the above embodiments and apply the general principles described herein to other embodiments without creative work. Therefore, the present invention is not limited to the above embodiments, and improvements and modifications made by those skilled in the art to the present invention based on the disclosure of the present invention should be within the protection scope of the present invention.

Claims

1. A method for evaluating the power regulation capability of short-process steelmaking users, characterized in that: include: Step 1, establishing an equivalent model of the production process of short-process steelmaking users; Step 2: Analyze the energy consumption and operation characteristics of the short-process steelmaking user process and classify the process load; Step 3, establish a short-process steelmaking user electricity regulation capacity evaluation model considering process load classification, the model takes the maximum electricity regulation capacity of short-process steelmaking users within a certain period of time as the objective function, and the regulation capacity is characterized by the difference between the external power purchase of short-process steelmaking users after considering the adjustable process and the external power purchase of short-process steelmaking users predicted when producing according to the production plan; The short-process steelmaking user production process equivalent model includes an electric arc furnace steelmaking process, a steel rolling process and a buffer zone between the first two processes. The buffer zone is used to temporarily store molten steel, and two energy sources, electricity and heat, are considered. The electric arc furnace process and the steel rolling process both have waste heat that can be recovered. The heat source of the steel rolling process is coal or natural gas. Considering that the consumption of coal and natural gas is not limited, there is no impact on the regulation capacity. The electric arc furnace steelmaking process, the steel rolling process and the buffer zone are powered by a power supply; The equivalent model of the short-process steelmaking user production process is guided by the material flow, and the energy flow and material flow are integrated as follows: (1) in, Represents the integrated set of energy flow and material flow; The power purchased from outside; The output electric power of the waste heat power generation device; , , They are the electric power of the electric arc furnace steelmaking process, buffer zone and steel rolling process respectively; , They are the recoverable heat power of the electric arc furnace steelmaking process and the steel rolling process respectively; is the input thermal power of the waste heat power generation device, equal and sum; is the raw material input amount; The material output of the electric arc furnace steelmaking process; The material output of the buffer zone; is the material output of the steel rolling process, that is, the final output of finished products; T Represents matrix transpose; Step 3 also includes: establishing constraints that take into account adjustable process energy consumption; the constraints include adjustable process operation constraints, process coupling constraints, buffer inventory constraints, production plan target constraints, and production process energy conservation constraints; The operation constraints of the adjustable process are the operation constraints of the electric arc furnace steelmaking process and the operation constraints of the steel rolling process; The operating constraints of the electric arc furnace steelmaking process are as follows: (3) (4) in, It is the time scale number of the arc furnace steelmaking process in the operation cycle; is a 0-1 variable, subscript sub 1 indicates the electric arc furnace steelmaking process; When At this moment, the arc furnace steelmaking process is in a non-working state, and the energy consumption and material output are 0; when When The electric arc furnace steelmaking process is in normal working condition at all times; It is the working state matrix of the electric arc furnace steelmaking process; Integrate energy and material flows for short-process steelmaking users; It is an integrated set of energy flow and material flow of short-process steelmaking users after considering the change of working state of arc furnace steelmaking process operation; The adjustment times of the electric arc furnace steelmaking process are constrained as follows: (5) in, The maximum allowable adjustment times of the electric arc furnace; The operational constraints of the steel rolling process are as follows: (6) (7) in, It is the time scale number of the steel rolling process in the operation cycle; is a 0-1 variable, subscript sub 3 represents the steel rolling process; when When The steel rolling process is in a non-working state at the moment, and the energy consumption and material output are 0; When The steel rolling process is in normal working condition at all times; is the working state matrix of the steel rolling process; It is an integrated set of energy flow and material flow of short-process steelmaking users after considering the change of working state of steel rolling process operation; The adjustment times constraints of the steel rolling process are as follows: (8) in, The maximum number of adjustments allowed for the steel rolling process; For the problem that the adjustment time scales of the arc furnace steelmaking process and the rolling process are different, the time scale coordination is achieved through the following constraints: the adjustment time scale of the rolling process close to the actual one is taken as the reference value, and the adjustment time scale of the arc furnace steelmaking process is taken to be close to the actual one and an integer multiple of the adjustment time scale of the rolling process, that is, the arc furnace is in the same working state within a certain integer multiple of the adjustment time scale of the rolling process. The constraints are as follows: (9) in, is a positive integer; The process coupling constraints are as follows: The electric arc furnace steelmaking process involves two energy sources: electricity and heat. The process coupling constraints are established as follows: (10) In the formula, represents a zero matrix of dimension 4×2; , , They respectively represent the power consumption, waste heat recovery and raw material consumption corresponding to the unit material output of the electric arc furnace steelmaking process; The coupling constraints of the steel rolling process are: (11) in, is the energy conversion coefficient matrix; , , They respectively represent the power consumption, waste heat recovery and material consumption corresponding to the unit material output of the steel rolling process; is the constant term in the linear relationship between energy consumption and production; , , Represents zero matrices of dimensions 4×4, 4×1, 4×3; The buffer inventory constraints are as follows: For the buffer, The inventory capacity at the time is equal to The capacity of the moment plus The material input at the time, minus The material output at the time, and because the capacity has upper and lower limits, its constraints are as follows: (12) (13) in, for Material inventory in the time buffer; , Material inventory for buffer zones The upper and lower limits of for The material output of the electric arc furnace steelmaking process at that moment, that is, the material input of the buffer zone; for Material output in the time buffer; The production planning objective constraints are as follows: During the entire production cycle, the planned total output must be met, subject to the following constraints: (14) in, T 1 is the entire production cycle; for The output of finished products from the steel rolling process at any given moment; The total planned production volume during the entire production cycle; The energy conservation constraints of the production process are as follows: The electrical power and thermal power of the entire system should be balanced at all times, and the balance constraints are as follows: (15) (16) (17) in, , They are The heat power can be recovered from the electric arc furnace steelmaking process and steel rolling process; for Total thermal power consumed by the waste heat power generation device at all times; The thermoelectric conversion efficiency of the waste heat power generation device; for Output electric power of the waste heat power generation device at any moment; for The power purchased from outside at any time; , , They are The electrical power of the electric arc furnace steelmaking process, buffer zone and steel rolling process at all times.

2. The method for evaluating the power regulation capability of short-process steelmaking users according to claim 1, characterized in that: The process loads are classified according to the impacts of energy-consuming equipment on the power grid on different time scales, and the process loads of short-process steelmaking users are divided into intermittent impact loads, continuous impact loads and stable loads; the intermittent impact loads are the loads of the electric arc furnace steelmaking process, which are adjustable at the hour level; the continuous impact loads are the loads of the steel rolling process, which are adjustable at the minute level; the stable loads are lighting equipment and transmission equipment, which are adjustable at the day level.

3. The method for evaluating the power regulation capability of short-process steelmaking users according to claim 1, characterized in that: The objective function is shown as follows: (2) in, For users who consider short-process steelmaking after process adjustment The power purchased from outside at any time; For users of short-process steelmaking predicted by production plan The power purchased from outside at any time; T 1 is the entire production cycle.

4. A system for evaluating the power regulation capability of a short-process steelmaking user, used to implement the method for evaluating the power regulation capability of a short-process steelmaking user according to any one of claims 1 to 3, characterized in that: include: Equivalent model building unit: used to build an equivalent model of the production process of short-process steelmaking users; Process load classification unit: Analyze the energy consumption and operation characteristics of the short-process steelmaking user process and classify the process load; Evaluation model establishment unit: Establish an evaluation model for the electricity regulation capacity of short-process steelmaking users taking into account the process load classification. The model takes the maximum electricity regulation capacity of short-process steelmaking users within a certain period of time as the objective function, and the regulation capacity is characterized by the difference between the external electricity purchase power of short-process steelmaking users after considering the adjustable process and the external electricity purchase power of short-process steelmaking users predicted when producing according to the production plan.

Citation Information

Patent Citations

  • Multi-agent simulation-based evaluation method for electric power peak regulation response capability of electric smelting furnace for magnesia

    CN114385963A