A method and computer device for calculating the water inflow of large-flow water in foundation pit
Using drone oblique photography technology and a three-dimensional soil point cloud model, the amount of water inflow in the foundation pit is accurately calculated, which solves the problem of large flow of water in the foundation pit and untimely drainage, enables rapid decision-making and resource optimization, and reduces economic losses.
Patent Information
- Application Number
- CN202410867914.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2044-07-01
AI Technical Summary
During the excavation process of the foundation pit, untimely drainage of large-flow permeable water in the foundation pit will cause water flooding in the equipment. It is difficult to accurately calculate the amount of water inflow with existing technology, resulting in waste of resources or insufficient drainage capacity, affecting project progress and economic losses.
UAV oblique photography technology is used to measure the irregular excavation surface in the foundation pit, and the three-dimensional soil point cloud model is used to divide the grid units to calculate the earth volume and water volume changes in the foundation pit, and then accurately calculate the water inflow flow rate and determine the water pump selection. type and quantity.
Quickly and accurately calculate the large flow of water in the foundation pit, reduce workload, shorten drainage time, reduce economic losses, and improve resource utilization efficiency.
Smart Images

Figure CN118397013B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of foundation pit water inflow calculation, and in particular to a method for calculating large-flow permeable water inflow in a foundation pit and a computer device. Background Art
[0002] If a large amount of water seepage and gushing occurs in the foundation pit, it is easy to cause the equipment to be soaked in water if the drainage is not timely. If a large amount of water seepage and gushing occurs in the foundation pit, the project requires that the excavation and support operations be stopped immediately, the workers in the pit be evacuated, and a large-flow water pump be added to drain the water in the pit. However, the type of water pump with drainage capacity and the number of water pumps to be called must be evaluated and calculated to determine the amount of water inflow. The determination of the amount of water inflow can also predict the scope and size of the impact on the surrounding environment.
[0003] Due to the uneven excavation surface of the foundation pit, in most cases, there is unexcavated earth exposed to the water level, and the water flow cannot be simply determined by the water level change value in the foundation pit. In actual projects, the empirical method is usually used to determine the water flow by gradually increasing the drainage pumps and observing the water level change value in the foundation pit. However, due to the large area of the foundation pit, the effect of increasing or reducing the water pumps for drainage on the water level change value of the foundation pit is not obvious, which makes this empirical method inaccurate in judging the water flow rate, and may also invest too much resources, resulting in waste of resources, or call an insufficient number of water pumps, resulting in insufficient drainage capacity. The present invention innovatively proposes a method for calculating the large-flow permeable water flow of a foundation pit, which accurately calculates the amount of earthwork in the foundation pit and the water flow of the foundation pit, so as to quickly make decisions, select the type and number of water pumps, reduce the workload for foundation pit water blocking, shorten the foundation pit drainage time, and reduce economic losses. Summary of the invention
[0004] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a method and a computer device for calculating the large-flow permeable water inflow of a foundation pit, which can quickly and accurately calculate the large-flow permeable water inflow of a foundation pit.
[0005] The present invention adopts the following technical solutions to achieve the above-mentioned purpose. In the first aspect, the present invention provides a method for calculating the water inflow of a large flow rate of a foundation pit, comprising:
[0006] S1: Use drone oblique photography technology to measure the irregular excavation surface in the foundation pit and determine the t i The amount of earthwork exposed to the water level in the foundation pit v i ;
[0007] S2: According to the time t i The elevation of the water level in the foundation pit and the design elevation of the pit bottom determine the depth from the water level to the pit bottom h i ;
[0008] S3: Measure the surface area of the foundation pit S ;
[0009] S4: Calculation time t i to t i+1 Changes in water volume in foundation pit:
[0010] First, according to the earthwork volume exposed on the water level v i , Depth from water level to pit bottom h i and foundation pit area S , the moment t i The volume of water in the foundation pit is expressed as , where The remaining excavation volume in the foundation pit;
[0011] Then, by the time t i , t i+1 The difference in the volume of water accumulated in the foundation pit is used to calculate the change in the volume of water accumulated in the foundation pit:
[0012] , Indicates time t i+1 The volume of water in the foundation pit, Indicates time t i+1 Depth from water level to pit bottom, Indicates time t i+1 Earthwork volume exposed to water level, Indicates time t i , t i+1 Changes in the volume of water in the foundation pit;
[0013] S5: Calculation time t i to t i+1 Water seepage flow in foundation pit:
[0014] According to the change of water volume in the foundation pit per unit time and the total drainage flow of the water pump q i , calculate the water inflow flow rate of foundation pit , calculated as:
[0015] ;
[0016] Calculate the time by taking the average value of the adjacent time periodst i Foundation pit water inflow , then:
[0017] .
[0018] Furthermore, at any time t i The amount of earthwork exposed to the water level in the foundation pit v i First, the grid units are divided according to the three-dimensional soil point cloud model of the UAV oblique photography, including:
[0019] The point cloud obtained by drone tilt photography is used as the grid unit node, divided into calculation grid units, and the grid units are j Numbered 1, ..., j, ..., n, the grid cells j The node number is ,node The coordinates of , where the coordinate values are obtained by oblique photography of UAV;
[0020] The node Project on the reference plane to obtain the node , by the grid unit node and projection nodes Composed of three-dimensional computing units, projection nodes The coordinates of , and have , , , is the elevation of the reference plane, when calculating the remaining earthwork volume V 0 When the reference plane is the bottom surface of the foundation pit, is the elevation of the bottom of the foundation pit; t j Soil that is always exposed to the water level v i When , the reference plane is t j The water level at time It is the elevation of the foundation pit water level.
[0021] Furthermore, at any time t i The amount of earthwork exposed to the water level in the foundation pit v i The remaining excavation volume in the foundation pit , calculated according to the divided grid units, specifically including:
[0022] The grid cell node elevations on the top surface of the prism are averaged. , m is the number of grid unit nodes; then the volume of the earthwork calculation unit is ;
[0023] If it is a triangular mesh unit, then ;
[0024] If it is a quadrilateral grid cell, then + ;
[0025] In the formula, For the j The horizontal projected area of a grid cell;
[0026] The total earthwork volume is the sum of the volumes of the prismatic units, which is , when the reference plane is the bottom plane of the foundation pit, then for V 0 ; When the reference plane is t j The water level at time for v i .
[0027] Furthermore, the following processing method is used for the boundary line unit of the foundation pit excavation surface:
[0028] The bottom edge line of the foundation pit excavation surface and the intersection line between the water level surface and the excavation surface are both curves. The boundary line unit is an irregular unit. Each unit intersecting with the curve is judged. If the unit area with one side as a curve is less than half of the unit area with a straight line side, the unit is deleted. If the unit area with one side as a curve is greater than half of the unit area with a straight line side, the unit is retained. The bottom boundary curve of the unexcavated earthwork grid unit is converted into a broken line.
[0029] Furthermore, the size of the grid unit division of the foundation pit excavation surface is such that the error between the unexcavated earthwork volume calculated according to the broken line boundary and the unexcavated earthwork volume calculated according to the curved line boundary is 3%~5%, so the unit division side length is set to 0.5m~1.0m.
[0030] Furthermore, the method also includes drawing a foundation pit water inflow curve according to t 1 to t i The amount of water inflow corresponding to the foundation pit at any time to , draw the water inflow curve of the foundation pit changing with time.
[0031] Furthermore, the mesh unit is a triangle or a quadrilateral; for a triangular mesh unitk =1, 2, 3 for quadrilateral mesh elements k =1, 2, 3, 4, the unit body is a triangular prism or a quadrangular prism.
[0032] In a second aspect, the present invention provides a computer device, including a memory, wherein the memory stores program instructions, and when the program instructions are run, the method for calculating the large-flow permeable water inflow of a foundation pit as described above is executed.
[0033] Compared with the prior art, the present invention has the following beneficial effects:
[0034] The present invention adopts the oblique photography technology of unmanned aerial vehicle to carry out photogrammetry of the topography of any plane shape of foundation pit and irregular undulating changes of excavation surface, and can generate a three-dimensional soil point cloud map, which can be converted into a three-dimensional model of the site and obtain the three-dimensional coordinates of any point on the earth excavation surface.
[0035] The present invention divides the foundation pit excavation surface into grid units, generates triangular prism or quadrangular prism units, and derives the three-dimensional coordinates of each grid unit node from the point cloud map, so as to accurately calculate the remaining earthwork volume in the foundation pit.
[0036] The present invention takes any time in the foundation pit t i , the depth from the water level in the pit to the bottom of the pit is h i ,calculate t i The change in volume of accumulated water caused by the change in water level in the foundation pit at any moment is taken into account, and the discharge of the water pump is taken into account to accurately calculate the amount of water gushing out of the foundation pit.
[0037] The present invention determines the total drainage volume required by the water pump according to the water gushing volume of the foundation pit, determines the arrangement of the on-site water pumps according to the drainage capacity of water pumps of different models, drains the accumulated water as quickly as possible, and completes the task of blocking and removing water. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 A plan view of foundation pit excavation provided by an embodiment of the present invention;
[0039] Figure 2 AA cross-sectional view of foundation pit excavation provided by an embodiment of the present invention;
[0040] Figure 3 The embodiment of the present invention provides t 1 Schematic diagram of water level in foundation pit at all times;
[0041] Figure 4 The embodiment of the present invention provides t 2 Schematic diagram of water level in foundation pit at all times;
[0042] Figure 5 The embodiment of the present invention provides t i Schematic diagram of water level in foundation pit at all times;
[0043] Figure 6 The oblique photography point cloud image of the UAV in the foundation pit provided by the embodiment of the present invention;
[0044] Figure 7 A schematic diagram of grid unit division provided in an embodiment of the present invention;
[0045] Figure 8 A schematic diagram of simplified processing of boundary grid units provided by an embodiment of the present invention;
[0046] Fig. 9 The grid provided by the embodiment of the present invention j Schematic diagram of prismatic unit soil calculation;
[0047] In the attached figure: 1- foundation pit, 101- supporting structure, 102- foundation pit bottom, 103- excavation slope, 104- excavation bottom edge; 105- soil exposed to the water level, 106- point cloud, 107- grid unit, 2- drainage pipe, 201- submersible pump, 202- valve; 3- water gushing point. DETAILED DESCRIPTION
[0048] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0049] The present invention provides a method for calculating the water inflow of a large-flow permeable foundation pit. During the pumping and drainage process of a large-flow permeable foundation pit, the unmanned aerial vehicle tilt photography technology is used to measure the undulating excavation surface in the foundation pit, calculate the earthwork volume exposed at any two moments, and then quickly determine the water inflow volume based on the difference in the earthwork volume exposed at these two moments, the water level change value, and the water pump drainage flow rate. The specific method is as follows:
[0050] S1, three-dimensional measurement of excavation topography and landform of foundation pit 1, calculation of remaining earthwork volume, use drone oblique photography technology to conduct photogrammetry of the undulating excavation slope 103 topography in the foundation pit, and generate a three-dimensional soil point cloud 106 model, such as Figure 6 shown.
[0051] S2, the excavation surface of the foundation pit 1 is divided into grid units 107, such as Figure 7 As shown in the figure, the three-dimensional coordinates of each unit grid point are derived from the point cloud image.
[0052] S3. Calculate the remaining earthwork volume of foundation pit 1 V 0and the earthwork volume above the water level v i .
[0053] S4. Water level measurement at different times in the foundation pit, changes in water accumulation, calculation of drainage volume, calculation of water inflow, such as Figure 3 , Figure 4 As shown, take two arbitrary moments when the foundation pit is completely covered by water t 1 , t 2 , the depths from the water level in the pit to the bottom of the pit are h 1 and h 2 , and any time t i The depths from the water level in the pit to the bottom of the pit are h i ,like Figure 5 As shown in the figure, the volume change of accumulated water caused by the water level change in the foundation pit at each moment is calculated respectively. .
[0054] S5. According to the change of water volume per unit time in the foundation pit plus the total water discharge of the pump in the same period, Obtain the water inflow of foundation pit 1 .
[0055] Specifically, the calculation of foundation pit water inflow includes:
[0056] like Figure 5 As shown, assuming the time t i The volume of water in the foundation pit is V i The foundation pit area is S , the depth from the water level to the bottom of the pit is h i , the remaining unexcavated earthwork in the foundation pit V 0 , the amount of earthwork exposed to the water level v i , then there is, .
[0057] time t i to t i+1 , the drainage flow rate of the water pump in the foundation pit is , the volume change of the water in the pit is:
[0058] , Indicates time t i+1 The volume of water in the foundation pit, Indicates time t i+1 Depth from water level to pit bottom, Indicates time t i+1 Earthwork volume exposed to water level, Indicates time t i , t i+1 Changes in the volume of water in the foundation pit;
[0059] time t i to t i+1 , the amount of water inflow from the foundation pit is:
[0060] , (Unit: m 3 / h)
[0061] Take the average value of the adjacent time periods, then the time t i The amount of water inflow from the foundation pit is .
[0062] Specifically, the earthwork volume of the foundation pit is calculated using the following steps:
[0063] S1. Use UAV oblique photography technology to generate a three-dimensional soil point cloud 106 model.
[0064] When the foundation pit is excavated to a certain depth or the bottom of the pit, water gushes at the bottom of the pit. The excavation surface in the foundation pit is scanned using drone oblique photography technology to generate a three-dimensional soil point cloud 106 model for calculating the remaining earthwork volume of the foundation pit excavation. V 0 .
[0065] When the foundation pit is pumped to t i , part of the soil in the foundation pit is exposed to the water level, such as Figure 5 As shown, the soil 105 exposed to the water level is scanned using the drone tilt photography technology, and a three-dimensional soil point cloud 106 model is generated to calculate the amount of earthwork exposed to the water level in the foundation pit. v i .
[0066] S2, dividing the grid unit 107 based on the three-dimensional soil point cloud 106 model, specifically dividing according to the following steps:
[0067] like Figure 8 As shown, the point cloud 106 obtained by the drone tilt photography is used as the grid unit 107 node, which is divided into calculation grid units, and the grid units are jNumbered 1, ..., j, ..., n, the grid cells j The node number is (Grid cells can be either triangular or quadrilateral; for triangular grid cells k =1, 2, 3, quadrilateral mesh element k =1, 2, 3,4), nodes The coordinates of , where the coordinate values are obtained by UAV oblique photography.
[0068] like Fig. 9 As shown, the node Project on the reference plane to obtain the node , by the grid unit node and projection nodes Composed of three-dimensional computing units, projection nodes The coordinates of , and have , , , is the elevation of the reference plane, when calculating the remaining earthwork volume V 0 When , the reference plane is the bottom surface of the foundation pit, then is the elevation of the bottom of the foundation pit; t j Soil that is always exposed to the water level v i When , the reference plane is t j The water level at time It is the elevation of the foundation pit water level.
[0069] S3. Calculation of earthwork volume.
[0070] Due to the uneven surface of the foundation pit ( Figures 1 to 5 ), the calculation unit is not a triangular prism or a quadrilateral prism with a flat top surface. In order to reduce the calculation error, the node elevations of the grid units on the top surface of the prism are averaged, that is, (m is the number of grid unit nodes).
[0071] Therefore, the volume of the earthwork calculation unit is .in,
[0072] Triangular mesh element
[0073] Quadrilateral mesh element +
[0074] In the formula, For the j The horizontal projection area of the grid.
[0075] Total earthwork volume is the volume of the prismatic unit The sum is When the reference plane is the bottom plane of the foundation pit, for V 0 ; When the reference plane is at this moment t j The water level is for v i .
[0076] The present invention also provides a method for drawing a foundation pit water inflow curve: according to t 1 , t 2 , …, t i-1 , t i The amount of water inflow corresponding to the foundation pit at any time , , …, , , draw the water inflow curve of the foundation pit changing with time.
[0077] The present invention also provides a method for calculating the drainage pumps in the foundation pit: Assume that a total of n submersible pumps 201 need to be installed in the foundation pit 1, and their rated drainage capacities are respectively q 1 , q 2 ,┉, q i ,┉, q n , open all submersible pumps 201 valves 202, the total discharge volume is , the total drainage capacity of the submersible pump should be greater than the water inflow of foundation pit 1, so that the accumulated water at the inflow point 3 in the foundation pit can be drained. ≥ .
[0078] Specifically, the processing of the excavation bottom line 104 unit of the foundation pit 1 adopts the following method. The excavation bottom line 104 of the excavation surface of the foundation pit 1 and the intersection line between the water level surface and the excavation surface are all curves, and the boundary line unit is an irregular unit such as Figure 7As shown, it is necessary to simplify the process approximately. For each unit intersecting with the curve, if the unit area with one side being the curve is less than half of the unit area with the straight side, delete this unit; if the unit area with one side being the curve is greater than half of the unit area with the straight side, retain this unit. The bottom boundary curve of the unexcavated earthwork grid unit is converted into a broken line, as shown in Figure 8 shown.
[0079] Specifically, the grid unit 107 may be a triangle or a quadrilateral. k =1, 2,3, quadrilateral mesh element k =1, 2, 3, 4, the unit soil is a triangular prism or a quadrangular prism, such as Fig. 9 shown.
[0080] Specifically, the size requirement of the grid unit 107 of the excavation surface of foundation pit 1 is that the error between the unexcavated earthwork volume calculated by simplifying the broken line boundary and the unexcavated earthwork volume calculated by the precise curve boundary is 3%~5%, and the unit division side length of 0.5m~1.0m can meet the accuracy requirement.
[0081] The present invention can quickly measure the water gushing amount of the foundation pit, determine the type and quantity of drainage pumps, and drain the accumulated water in the pit in the shortest time, so that the drainage work is targeted, the drainage fee is reduced, and the cost is controlled.
[0082] The above is only a preferred embodiment of the present invention. It should be understood that the present invention is not limited to the form disclosed herein, and should not be regarded as excluding other embodiments, but can be used in various other combinations, modifications and environments, and can be modified within the scope of the concept described herein through the above teachings or the technology or knowledge of the relevant field. The changes and modifications made by those skilled in the art shall not deviate from the spirit and scope of the present invention, and shall be within the scope of protection of the claims attached to the present invention.
Claims
1. A method for calculating the water inflow of a large foundation pit, characterized in that: include: S1: Use drone oblique photography technology to measure the irregular excavation surface in the foundation pit and determine the t i The amount of earthwork exposed to the water level in the foundation pit v i ; S2: According to the time t i The elevation of the water level in the foundation pit and the design elevation of the pit bottom determine the depth from the water level to the pit bottom h i ; S3: Measure the surface area of the foundation pit S ; S4: Calculation time t i to t i+1 Changes in water volume in foundation pit: First, according to the earthwork volume exposed on the water level v i , Depth from water level to pit bottom h i and foundation pit area S , the moment t i The volume of water in the foundation pit is expressed as , where The remaining excavation volume in the foundation pit; Then, by the time t i , t i+1 The difference in the volume of water accumulated in the foundation pit is used to calculate the change in the volume of water accumulated in the foundation pit: , Indicates time t i+1 The volume of water in the foundation pit, Indicates time t i+1 Depth from water level to pit bottom, Indicates time t i+1 Earthwork volume exposed to water level, Indicates time t i , t i+1 Changes in the volume of water in the foundation pit; S5: Calculation time t i to t i+1 Water seepage flow in foundation pit: According to the change of water volume in the foundation pit per unit time and the total drainage flow of the water pump q i , calculate the water inflow flow rate of foundation pit , calculated as: ; Calculate the time by taking the average value of the adjacent time periods t i Foundation pit water inflow , then: ; Any time t i The amount of earthwork exposed to the water level in the foundation pit v i First, the grid unit is divided according to the three-dimensional soil point cloud model obtained by UAV oblique photography, including: The point cloud obtained by drone tilt photography is used as the grid unit node, divided into calculation grid units, and the grid units are j Numbered 1, ..., j, ..., n, the grid cells j The node number is ,node The coordinates of , where the coordinate values are obtained by oblique photography of UAV; The node Project on the reference plane to obtain the node , by the grid unit node and projection nodes Composed of three-dimensional computing units, projection nodes The coordinates of , and have , , , is the elevation of the reference plane, when calculating the remaining earthwork volume V When 0, the reference plane is the bottom of the foundation pit, then is the elevation of the bottom of the foundation pit; t j Soil that is always exposed to the water level v i When , the reference plane is t j The water level at time is the elevation of the foundation pit water level; Any time t i The amount of earthwork exposed to the water level in the foundation pit v i The remaining excavation volume in the foundation pit , calculated according to the divided grid units, specifically including: The grid cell node elevations on the top surface of the prism are averaged. , m is the number of grid unit nodes; then the volume of the earthwork calculation unit is ; If it is a triangular mesh unit, then ; If it is a quadrilateral grid cell, then + ; In the formula, For the j The horizontal projected area of a grid cell; The total earthwork volume is the sum of the volumes of the prismatic units, which is , when the reference plane is the bottom plane of the foundation pit, then for V 0; when the reference plane is t j The water level at time for v i .
2. The method for calculating the water inflow of a large foundation pit according to claim 1 is characterized in that: The following processing methods are used for the boundary line units of the foundation pit excavation surface: The bottom edge line of the foundation pit excavation surface and the intersection line between the water level surface and the excavation surface are both curves. The boundary line unit is an irregular unit. Each unit intersecting with the curve is judged. If the unit area with one side as a curve is less than half of the unit area with a straight line side, the unit is deleted. If the unit area with one side as a curve is greater than half of the unit area with a straight line side, the unit is retained. The bottom boundary curve of the unexcavated earthwork grid unit is converted into a broken line.
3. The method for calculating the water inflow of a large foundation pit according to claim 1 is characterized in that: The size of the grid unit division of the foundation pit excavation surface is such that the error between the unexcavated earthwork volume calculated according to the broken line boundary and the unexcavated earthwork volume calculated according to the curved line boundary is 3%~5%, so the unit division side length is set to 0.5m~1.0m.
4. The method for calculating the water inflow of a large foundation pit according to claim 1 is characterized in that: The method also includes drawing a foundation pit water inflow curve. t 1 to t i The amount of water inflow corresponding to the foundation pit at any time to , draw the water inflow curve of the foundation pit changing with time.
5. The method for calculating the water inflow of a large foundation pit according to claim 1 is characterized in that: The mesh unit is a triangle or a quadrilateral. k =1, 2, 3 for quadrilateral mesh elements k =1, 2, 3, 4, the unit body is a triangular prism or a quadrangular prism.
6. A computer device comprising a memory, wherein the memory stores program instructions, characterized in that: When the program instructions are executed, the method for calculating the large-flow permeable water inflow of a foundation pit as described in any one of claims 1 to 5 is executed.