Cable installation guide device and guide method

By designing the cable installation guide device and using aerial rolling supports and adjustable guide structures, the problems of damage and safety hazards during the cable installation process are solved, stable and efficient cable installation is achieved, and construction efficiency and safety are improved.

CN118399268BActive Publication Date: 2024-10-22CHINA RAILWAY CONSTR ENG GRP FOURTH CONSTR CO LTD +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410869394.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-01
Publication Date
2024-10-22
Estimated Expiration
2044-07-01

AI Technical Summary

Technical Problem

During the cable installation process, the cables are easily damaged due to friction, leading to safety hazards. It is difficult to effectively guide and protect the cables with existing technology, leading to construction delays and safety accidents.

Method used

A cable installation guide device is designed, which uses flying rolling supports and adjustable guide structures to form a semi-encircled guide and limit structure through rolling balls and I-shaped guide wheels to ensure that the cables do not sway during the installation process and reduce friction. , to avoid cable damage and safety accidents.

Benefits of technology

It effectively prevents cables from being swayed and damaged during installation, improves construction efficiency, reduces knotting and entanglement of cables, avoids electric shock accidents, and ensures safe and stable installation of cables.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118399268B_ABST
    Figure CN118399268B_ABST
Patent Text Reader

Abstract

The present invention discloses a cable installation guide device and a guide method, and relates to the field of cable installation technology. The device includes a base located at the position of a cable laying wellhead and a first guide member erected above the base, at least two support plates are located at the upper end of an annular support sleeve in a sliding manner, a support rod is fixed on the support plate, and a guide enclosure forms a semi-enclosed guide limit structure; the portion of the guide enclosure located between the two ends is an arc-shaped structure, and a plurality of rolling balls form a rolling support member for rolling and guiding the cable passing through the inner side of the arc-shaped structure in the air, and the rolling support member vacates and erects the cable at the cable laying wellhead to change the cable guiding direction. The present invention utilizes a rolling support member composed of a plurality of rolling balls to vacate and guide the cable, and after the cable is transmitted through the rolling support member, it bends downward and passes through the longitudinal through hole, and passes longitudinally downward along the cable laying well, and then is pulled horizontally along the cable laying well, so as to avoid the cable being scratched by friction with the inner wall of the wellhead due to the small opening.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cable installation, and in particular to a cable installation guiding device and a guiding method. Background Art

[0002] Cable installation guidance is a link that requires attention to details and technical requirements. The main purpose of cable installation guidance is to ensure that the cable can run stably and safely during the installation process, while avoiding cable damage and safety hazards.

[0003] In the installation process of the existing technology, the cable is generally laid out by manually placing a pulley or a simple pay-off rack outside the cable well. Since the cable needs to be laid over a long distance and has a large weight, the cable will rub against the ground of the cable well during transmission, and the opening size of the cable well is limited. Therefore, when the cable is laid out, the cable cannot be guided at a certain angle, causing the cable to be scratched by the cable well or the cable to damage the cable well, the edge of the well cover and the waterproof layer, causing the cable core to be exposed and leaking, causing a safety accident of electric shock. Therefore, a cable installation guide device and a guide method are designed here to solve the above problems. Summary of the invention

[0004] The object of the present invention is to provide a cable installation guide device and a guide method to solve the problems raised in the above background technology.

[0005] To achieve the above object, the present invention provides the following technical solution: a cable installation guide device is provided, comprising:

[0006] The base is arranged at the cable laying wellhead, the base is provided with a longitudinal through hole for the cable to pass through, and the upper end opening of the longitudinal through hole is provided with an annular support sleeve;

[0007] A first guide member is mounted above the base, and the first guide member comprises:

[0008] At least two support plates are slidably seated on the upper end of the annular support sleeve.

[0009] The guide enclosure forms a semi-enclosed guide limit structure as a whole, and the portion of the guide enclosure between the two ends is an arc-shaped structure;

[0010] A set of support rods, one end of which is arranged on the bottom walls of the two ends of the guide enclosure, and the other end is fixed on the support plate;

[0011] A plurality of rolling balls are rotatably sleeved on the arc-shaped structure, and the rolling balls form a rolling support member for guiding the cable passing through the inner side of the arc-shaped structure in the air, so as to change the guiding direction of the cable;

[0012] The base and one side wall of the annular support sleeve are both provided with openings for the cable to escape from the longitudinal through hole.

[0013] According to one aspect of the present application, two support plates are provided, and a semicircular connecting plate is fixed between the two support plates. One end of the support plate away from the center of the annular support sleeve is bent downward to form an inverted L-shaped clamping portion. An annular flange extends radially at the upper end of the annular support sleeve, and the inverted L-shaped clamping portion is slidably clamped on the radial side wall and bottom wall of the annular flange.

[0014] According to one aspect of the present application, a second guide member is also included, and the second guide member includes:

[0015] A flip rod, adjustably connected to one end of the guide enclosure;

[0016] One end of the I-shaped guide wheel is rotatably connected to the bottom end of the side wall of the flip rod through a pin.

[0017] After passing over the rolling support, the cable bends downward and extends. After passing through the side wall of the I-shaped guide wheel close to the rolling support, the transmission direction of the cable changes to a lateral guiding direction along the cable laying well.

[0018] In another embodiment of the present application, a cable installation guide device is also provided, including a base located at the cable laying wellhead position and a first guide member erected above the base, the base is provided with a longitudinal through hole for the cable to pass through, the upper end opening of the longitudinal through hole is provided with an annular support sleeve, the first guide member includes at least two support plates and a guide enclosure, at least two support plates are slidably located at the upper end of the annular support sleeve, the bottom walls of the two ends of the guide enclosure are provided with support rods, the support rods are fixed on the support plates, and the guide enclosure forms a semi-enclosed guide limit structure; the portion of the guide enclosure between the two ends is an arc-shaped structure, and the arc-shaped structure is rotatably sleeved with a plurality of rolling balls, the plurality of rolling balls constitute a rolling support member for rolling and guiding the cable passing through the inner side of the arc-shaped structure in the air, and the rolling support member vacates and erects the cable at the cable laying wellhead to change the cable guiding direction;

[0019] The base and one side wall of the annular support sleeve are both provided with openings for the cable to escape from the longitudinal through hole.

[0020] In a further embodiment, two support plates are provided, and a semicircular connecting plate is fixed between the two support plates, and one end of the support plate away from the center of the annular support sleeve is bent downward to form an inverted L-shaped clamping portion, and an annular flange is radially extended at the upper end of the annular support sleeve, and the inverted L-shaped clamping portion is slidably clamped on the radial side wall and bottom wall of the annular flange.

[0021] In a further embodiment, a guide member is also included, and the second guide member includes a flip rod and an I-shaped guide wheel. The flip rod is adjustably connected to one end of the guide enclosure, and one axial end of the I-shaped guide wheel is rotatably connected to the bottom end of the side wall of the flip rod through a pin shaft. After the cable passes over the rolling support member, it bends and extends downward. After passing through the side wall of the I-shaped guide wheel close to the rolling support member, the transmission direction of the cable changes to a lateral guiding direction along the cable laying well.

[0022] In a further embodiment, a guide plate is fixed to the bottom end of the side wall of the flip rod, and an inclined sliding opening is opened on the guide plate. An I-shaped pin is slidably clamped in the sliding opening, and a counterweight roller is rotatably provided at one end of the I-shaped pin, and a guiding channel for rolling and clamping the cable is formed between the counterweight roller and the radial side wall of the I-shaped guide wheel.

[0023] In a further embodiment, the sliding opening is arranged to extend obliquely downwardly toward a side away from the rolling support member.

[0024] In a further embodiment, a hinged seat is provided at one end of the guide enclosure, and a hinged notch is formed in the hinged seat. Pins are rotatably provided on the side walls on both sides of the hinged notch. Strip guide grooves are formed on both side walls of the flip rod. The pins are slidably engaged with the strip guide grooves. The flip rod slides along the pins through the strip guide grooves and flips with the pins as the rotation center to adjust the height and angle of the cable passing through the guide channel.

[0025] In a further embodiment, a limit member for limiting the position of the flip rod is further included, and the limit member includes two pull rods and two clamping columns, and the two clamping columns are rotatably arranged on the opposite side walls at both ends of the two pull rods, and a plurality of inverted J-shaped clamping blocks are fixed to the upper end of the guide enclosure. A plurality of notches are recessed on the side wall of the flip rod facing away from the guide enclosure, and one of the clamping columns is clamped on the inner side wall of an inverted J-shaped clamping block at a corresponding position, and the other clamping column is clamped in a notch at the corresponding position of the flip rod.

[0026] In a further embodiment, a positioning structure of multiple fixed bases is also included, and the positioning structure includes a gate-shaped seat fixed to the inner wall of the longitudinal through hole, a threaded sleeve hinged to the inner wall of the gate-shaped seat, and a threaded adjustment rod that rotates through the threaded sleeve, and the bottom end of the threaded adjustment rod is hinged with a fitting plate, and a torsion spring is provided at the hinge.

[0027] In a further embodiment, the upper end of the threaded adjustment rod is an enlarged portion, the outer wall of the threaded adjustment rod is slidably sleeved with a ring located between the threaded sleeve and the enlarged portion, and a connecting rod is hinged between the ring and the upper side wall of the gate-shaped seat.

[0028] A guiding method for cable installation comprises the following steps:

[0029] A1. The cable output end is inserted into the inner position of the guide enclosure from the gap between the two ends of the guide enclosure. The semi-enclosed structure of the guide enclosure is limited on both sides of the cable. The rolling support composed of multiple rolling balls on the guide enclosure suspended above the annular support sleeve is used to guide the cable passing through the inner side of the arc-shaped structure.

[0030] A2. Slide the flip rod along the bayonet through the strip guide groove and flip it with the bayonet as the rotation center to adjust the height and angle of the cable passing through the guide channel to adapt to the cable being guided and transmitted along the underground well at different heights and angles;

[0031] A3. After passing over the rolling support, the cable bends downward and extends. After passing through the side wall of the I-shaped guide wheel close to the rolling support, the transmission direction of the cable changes to the lateral guiding direction along the cable laying well.

[0032] Compared with the prior art, the present invention has the following beneficial effects:

[0033] The present invention first places the base at the mouth of the cable laying well, and uses a rolling support composed of multiple rolling balls on a guide enclosure suspended above the annular support sleeve to guide the cable passing through the inner side of the arc-shaped structure. The semi-enclosed structure formed by the guide enclosure is limited on both sides of the cable to prevent the cable from escaping from the sides of the guide enclosure. After the cable is transmitted through the rolling support, it is bent downward and passed through the longitudinal through hole, and passed longitudinally down along the cable laying well, and then pulled horizontally along the cable laying well. In this process, the cable can be prevented from shaking during the pulling process along the laying well, thereby reducing construction delays caused by cable shaking, and also helping to reduce cable knotting and entanglement, improving construction efficiency, while avoiding friction between the cable and the ground of the cable well when the cable is laid out, and avoiding friction between the cable and the inner wall of the wellhead with a small opening to be scratched, causing the cable core to be exposed and leaking, causing a safety accident of electric shock. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 This is a schematic diagram of the installation of the main structure of the present invention at the cable laying wellhead;

[0035] Figure 2 It is a schematic diagram of the main structure of the present invention;

[0036] Figure 3 It is a schematic diagram of the structure of the first guide member of the present invention;

[0037] Figure 4 For the present invention Figure 3 A magnified view of the structure at center;

[0038] Figure 5 It is a schematic diagram of the assembly structure of the first guide member and the second guide member of the present invention;

[0039] Figure 6 It is a schematic diagram of the structure of the turning rod, the guide plate and the counterweight roller of the present invention;

[0040] Figure 7 It is a schematic diagram of a limiting member of the present invention;

[0041] Figure 8 This is a schematic diagram of the I-shaped guide wheel and the counterweight roller rolling and clamping the cable structure of the present invention;

[0042] Fig. 9 It is a schematic diagram of the I-shaped guide wheel and the counterweight roller rolling and clamping the cable output of the present invention;

[0043] Fig.10 This is a schematic diagram of a further improved structure of the base of the present invention;

[0044] Fig.11 It is a schematic diagram of a single positioning structure of the present invention;

[0045] Fig.12 It is a partial cross-sectional view of a single positioning terminal of the present invention.

[0046] In the figure: 1. base; 2. annular support sleeve; 3. guide enclosure; 31. rolling ball; 32. support rod; 33. support plate; 34. inverted L-shaped clamping part; 35. semicircular connecting plate; 36. inverted J-shaped clamping block; 37. hinged seat; 4. pull rod; 41. clamping column; 5. flip rod; 51. I-shaped guide wheel; 52. guide plate; 53. counterweight roller; 6. door-type seat; 61. threaded sleeve; 62. threaded adjustment rod; 63. fitting plate; 64. connecting rod; 65. collar. DETAILED DESCRIPTION

[0047] The following will be described clearly and completely in conjunction with the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0048] Embodiment 1, this embodiment provides a cable installation guide device, such as Figure 1 , Figure 2 and Figure 3As shown, it includes a base 1 located at the cable laying wellhead position and a first guide member erected above the base 1, the base 1 is provided with a longitudinal through hole for the cable to pass through, the upper end opening of the longitudinal through hole is provided with an annular support sleeve 2, the first guide member includes at least two support plates 33 and a guide enclosure 3, at least two support plates 33 are slidably located on the upper end of the annular support sleeve 2, the bottom walls of both ends of the guide enclosure 3 are provided with support rods 32, the support rods 32 are fixed on the support plates 33, the entire first guide member is located on the upper end of the annular support sleeve 2 using at least two support plates 33, and there are preferably two support plates 33.

[0049] like Figure 2 As shown, two support plates 33 are arranged on the annular support sleeve 2 relative to each other, according to the direction of cable laying, as shown in FIG. Figure 1 As shown, the cable output end is inserted into the inner position of the guide enclosure 3 from the gap between the two ends of the guide enclosure 3. Here, the guide enclosure 3 forms a semi-enclosed guide limit structure. The semi-enclosed structure limits the cable on both sides to prevent the cable from escaping from the sides of the guide enclosure 3. This can prevent the cable from shaking during the traction process along the laying well, thereby reducing construction delays caused by cable shaking. At the same time, when laying cables, more than one cable is often laid, so when traction is used, setting the guide enclosure 3 as a guide limiter can help reduce the situation where multiple cables are entangled together and improve construction efficiency.

[0050] At the same time, the portion of the guide enclosure 3 between the two ends is set as an arc-shaped structure, and the arc-shaped structure is rotatably sleeved with multiple rolling balls 31, and the multiple rolling balls 31 form a rolling support member for rolling and guiding the cable passing through the inner side of the arc-shaped structure. The rolling support member vacates and sets up the cable at the cable laying wellhead to change the cable guiding direction. The rolling support member composed of multiple rolling balls 31 on the guide enclosure 3 vacated and set up above the annular support sleeve 2 is used to guide the cable passing through the inner side of the arc-shaped structure. After the starting end of the cable is subjected to traction, it rolls and contacts with the outer wall of the rolling ball 31, thereby reducing the resistance during traction.

[0051] Moreover, before entering the wellhead, the cable can be erected in a way that it is detached from the ground, so as to avoid friction between the cable and the ground of the cable well or the edge of the wellhead when the cable is laid. At the same time, after the cable passes through the rolling support, it bends downward and passes through the longitudinal through hole, and passes longitudinally down along the cable laying well, and then is pulled horizontally along the cable laying well. The cable does not contact the inner wall of the wellhead during transmission, which can avoid the cable being scratched by friction between the inner wall of the wellhead due to the small opening, causing the cable core to be exposed and leaking electricity, causing safety accidents such as electric shock. Or the cable well, the edge of the well cover and the waterproof layer are damaged during cable pulling, which increases the maintenance cost.

[0052] When the cable reaches the laying requirement along the length of the underground traction, the cable needs to be cut off, and a certain length of the cable needs to be reserved, extending out of the wellhead and connected to the external power distribution cabinet. In general, in order to ensure that the reserved length of the cable meets the external connection requirement, the height of the part of the reserved length of the cable extending out of the wellhead should be much higher than the base 1 and the annular support sleeve 2. If it is to be separated from the guide device, it is necessary to manually lift the entire guide device upwards, and the cable extending out of the wellhead reserved for laying is separated from the bottom of the longitudinal through hole, which is relatively laborious. In order to quickly separate, an opening for the cable to detach from the longitudinal through hole is provided on the side wall of the base 1 and the annular support sleeve 2. The width of the opening is greater than the diameter of the conventional cable to meet the requirement of the cable detaching from the longitudinal channel from the opening, and there is no need to manually lift the entire guide device. It should be particularly noted here that the width of the support plate 33 should be greater than the width of the opening, so as to ensure that the support plate 33 will not fall from the opening when sliding along the annular flange.

[0053] Adjust the position of the support plate 33 on the annular support sleeve 2, and then adjust the orientation of the two end portions of the guide enclosure 3. The end of the support plate 33 away from the center of the annular support sleeve 2 is bent downward to form an inverted L-shaped clamping portion 34. The upper end of the annular support sleeve 2 is radially extended with an annular flange. The inverted L-shaped clamping portion 34 is slidably clamped on the radial side wall and bottom wall of the annular flange. The clamping space formed by the inverted L-shaped clamping portion 34 and the bottom wall of the support plate 33 is slidably clamped on the upper and lower side walls of the annular flange. This can not only satisfy the need for the support plate 33 to slide along the distribution direction of the annular flange to adjust the orientation of the two end portions of the guide enclosure 3, but also prevent the support plate 33 from detaching from the annular flange. Moreover, a semicircular connecting plate 35 is fixed between the two support plates 33. The semicircular connecting plate 35 is used to connect the two support plates 33, so that the positions of the two support plates 33 are synchronously adjusted in the annular support sleeve 2, and the supporting strength of the entire first guide member is enhanced. Figure 4 As shown, a plurality of balls are rotatably embedded in the inner wall of the inverted L-shaped clamping portion 34 , and the resistance of the support plate 33 when rotating is reduced by adding balls and rolling fit with the annular flange.

[0054] In this embodiment, a second guide member is also included, such as Figure 5As shown, the second guide member includes a flip rod 5 and an I-shaped guide wheel 51. The flip rod 5 is adjustably connected to one end of the guide enclosure 3. The bottom end of the flip rod 5 extends below the annular support sleeve 2. One axial end of the I-shaped guide wheel 51 is rotatably connected to the bottom end of the side wall of the flip rod 5 through a pin. Since the intersection of the longitudinal direction and the transverse direction in the well is at different heights, the depth of the cable extension will also be different. Therefore, a hinge seat 37 is provided at one end of the guide enclosure 3. The hinge seat 37 is provided with a hinge notch. The side walls on both sides of the hinge notch are rotatably provided with a bayonet. The side walls of the flip rod 5 are provided with a strip guide groove. The bayonet is slidably engaged with the strip guide groove. The flip rod 5 is slid along the bayonet through the strip guide groove and flipped with the bayonet as the rotation center to adjust the height and angle of the cable passing through the guide channel to adapt to the transmission of the cable along the well guide at different heights and angles.

[0055] like Figure 5 As shown, after the cable is transmitted through the rolling support, it needs to be bent downward to pass through the longitudinal through hole and pass longitudinally down the cable laying well. Therefore, after the cable enters the well, it needs to be pulled horizontally along the well. Then the cable pulling direction needs to be changed again. At this time, the cable is changed from the longitudinal bending to the horizontal direction. At this time, the cable is bent downward and extended after passing through the rolling support. After passing the side wall of the I-shaped guide wheel 51 close to the rolling support, the transmission direction of the cable is changed to the horizontal guiding direction along the cable laying well, so as to avoid the cable touching the side wall at the intersection of the longitudinal direction and the horizontal direction in the well, causing the outer protective layer of the cable to be scratched.

[0056] Furthermore, a guide plate 52 is fixed to the bottom end of the side wall of the flip rod 5, and an inclined sliding opening is opened on the guide plate 52. An I-shaped pin is slidably connected in the sliding opening, and a counterweight roller 53 is rotatably arranged at one end of the I-shaped pin. Figure 6 and Figure 8 As shown, a guide channel for rolling and clamping the cable is formed between the counterweight roller 53 and the radial side wall of the I-shaped guide wheel 51, and the sliding opening is inclined and extended downward to the side away from the rolling support. When the cable needs to pass through the guide channel, the counterweight roller 53 is first slid upward along the sliding opening of the guide plate 52, and the counterweight roller 53 gradually moves away from the I-shaped guide wheel 51. The guide channel is in an open state. At this time, it is convenient to stick the cable on the radial side wall of the I-shaped guide wheel 51 from the open state, and then the counterweight roller 53 is released. The counterweight roller 53 slides down along the sliding opening using the I-shaped pin shaft, and finally rolls on the outer wall of the cable to prevent the cable from shaking and escaping from the guidance of the I-shaped guide wheel 51.

[0057] After the height and angle of the flip rod 5 are adjusted, its position needs to be limited, so a limiter for limiting the position of the flip rod 5 is also included. The limiter includes two pull rods 4 and two clamping columns 41. The two clamping columns 41 are rotatably arranged on the opposite side walls at both ends of the two pull rods 4. A plurality of inverted J-shaped clamping blocks 36 are fixed on the upper end of the guide enclosure 3. A plurality of notches are recessed on the side wall of the flip rod 5 facing away from the guide enclosure 3. After the height and angle of the flip rod 5 are adjusted, as shown in FIG. Figure 5 and Figure 7 As shown, two pull rods 4 and two clamping columns 41 form a rectangular hollow sleeve. First, the rectangular hollow sleeve is put on the outer wall of the flip rod 5, and then one of the clamping columns 41 is clamped on the inner wall of an inverted J-shaped clamping block 36 at the corresponding position, and the other clamping column 41 is clamped in a notch at the corresponding position of the flip rod 5 to limit the flip rod 5 that has been adjusted in position, thereby limiting the height and angle of the guide channel to remain unchanged.

[0058] It should be noted that when guiding the cable, the issue that needs attention is that the minimum bending radius of the cable must meet the relevant requirements. The multi-core cable cannot be less than 15D, and the single-core cable cannot be less than 20D (D is the outer diameter of the cable, 15 and 20 are multiples, and there is no unit). Excessive bending will cause the conductor to loosen and bulge, directly affecting the performance of the outer semi-conductive layer and insulation layer of the conductor. When the cable is bent at a certain bending radius, the insulation at the bend will be stretched and deformed. When the bend exceeds the minimum allowable bending radius, it may cause insulation damage. Medium-voltage cables are usually shielded with copper tape. When the cable is bent too much, it causes the metal tape to wrinkle or curl, which can easily cause insulation damage. When the cable is actually laid, it will pass through a laying well, be transmitted along the lateral guide of the well, and finally pass out from another laying wellhead, such as Fig. 9 As shown, when the cable passes through another laying well, the traction force is distributed along the axial direction of the cable when the cable is pulled. Since the cable is generally laid for at least tens of meters, hundreds of meters or even longer, during the traction process, it is limited by its own gravity and produces a large friction force with the lateral inner wall of the wellhead and the inner wall of the cable well. Therefore, when the cable passes through the laying well from the horizontal to the upward, the cable traction requires a large traction force. The greater the force, the straighter the cable is. When turning after passing the I-shaped guide wheel 51, the cable will fit tightly against the I-shaped guide wheel 51, resulting in a small turning angle, which can easily cause the corner radius to be smaller than the limit value, causing damage to the outer protective layer of the cable.

[0059] Therefore, a special design is made here that when the cable is bent and passed through the I-shaped guide wheel 51 and then transmitted horizontally, in order to prevent the bending radius from exceeding the bending limit, such as Figure 7As shown, the pull rod 4 here is an elastic rod bent upward, and because the cable itself is encapsulated by an outer protective layer, the cable has a certain bending strength when it is bent. During the lateral pulling process of the cable, when the cable changes its guide direction at the I-shaped guide wheel 51, as shown in FIG. Fig. 9 The traction in the middle A direction will push the flip rod 5 connected to the I-shaped guide wheel 51 to adaptively rotate around the rotation point of the hinge seat 37, and the pull rod 4 will be stretched and deformed to generate rebound potential energy, so that the flip rod 5 will rotate around the rotation point of the hinge seat 37. Then, the cable passing through the I-shaped guide wheel 51 will move along the Fig. 9 The cable rotates in the direction shown in B in the figure, thereby increasing the angle between the cable after passing through the outer wall of the I-shaped guide wheel 51 and the horizontal direction. Fig. 9 The cable turns in the direction shown in B, and the cable turns at a larger angle, and the deflection angles of the cable core and the outer wall protective layer are enlarged, to prevent the cable bending radius from being too small and exceeding the limit value, causing the outer protective layer to be damaged due to excessive bending and stretching deformation. The rebound potential energy generated by the tensile deformation of the pull rod 4 gives the flip rod 5 a real-time reverse rotation force around the hinge position, so as to push the portion of the cable located at the I-shaped guide wheel 51 in the opposite direction, to prevent the flip rod 5 from flipping randomly, which would affect the effective guiding operation of the cable.

[0060] Example 2 is further optimized on the basis of Example 1: Fig.10 , Fig.11 and Fig.12 As shown, it also includes a plurality of positioning structures for fixing the base 1, the positioning structures include a gate-shaped seat 6 fixed on the inner wall of the longitudinal through hole, a threaded sleeve 61 hinged on the inner wall of the gate-shaped seat 6, and a threaded adjustment rod 62 that rotates through the threaded sleeve 61, and a fitting plate 63 is hinged at the bottom end of the threaded adjustment rod 62, and a torsion spring is provided at the hinge. In order to enhance the guiding stability of the entire guiding device, after the base 1 is located at the cable laying wellhead position, the two relatively arranged positioning structures are adjusted, that is, the threaded adjustment rod 62 is rotated to adjust the threaded adjustment rod 62 downward along the axial direction of the threaded sleeve 61, so as to adjust the height of the fitting plate 63.

[0061] Here, it is necessary to symmetrically place the two relative bonding plates 63 against the inner wall of the wellhead at an inclined angle. For this purpose, the upper end of the threaded adjustment rod 62 is an expansion part. The outer wall of the threaded adjustment rod 62 is slidably sleeved with a collar 65 located between the threaded sleeve 61 and the expansion part. A connecting rod 64 is hinged between the collar 65 and the upper side wall of the gate-shaped seat 6. When the threaded adjustment rod 62 is rotated and adjusted, as the threaded adjustment rod 62 is continuously rotated and adjusted downward, the height is synchronously lowered by pressing the collar 65 downward by the expansion part. At this time, the connecting rod 64 rotates around the respective hinge positions, and the threaded adjustment rod 62 is turned over with the rotation point of the threaded sleeve 61 as the rotation center. As long as the two bonding plates 63 can be symmetrically pressed against the inner wall of the wellhead, the rotation of the threaded adjustment rod 62 is stopped immediately to prevent the base 1 from being lifted up. The bonding plate 63 is inserted into the wellhead, and after it is pressed against the inner wall of the wellhead, it forms a supporting relationship with the wellhead, and finally prevents the base 1 from shaking in the lateral direction and affecting the stability of the cable guide.

[0062] In another embodiment of the present application, the relationship between the rolling ball and the guide enclosure may also be:

[0063] A semicircular groove is formed on the inner wall of the guide enclosure, and the radius of the groove matches the radius of the ball. The ball is inserted into the groove so that its upper half is exposed. The ball is connected to the shaft seat at the bottom of the groove through a bearing to ensure that the ball can rotate flexibly. Blocks are set at both ends of the groove to prevent the ball from sliding out axially.

[0064] With this design, the ball can be stably embedded in the guide enclosure without falling off or getting stuck, and rolling friction can be reduced. When the cable passes through, it can be well guided and supported by the rotation of the ball, and the force is more evenly distributed. In addition, when making it, the guide enclosure can be divided into two parts, the upper and lower parts, and the middle surface coincides with the maximum diameter plane of the groove. In this way, the ball can be assembled into the groove of the lower part first, and then the upper part is covered, and the upper and lower parts are fixed with screws. This structure is convenient for the assembly and replacement of the ball.

[0065] In another embodiment of the present application, a worm parallel to the hinge axis of the flip rod can be fixed on the base, and the worm is driven to rotate by a hand wheel. A worm wheel is fixed on the flip rod, the axis of the worm wheel is coaxial with the hinge axis, and the worm wheel is meshed with the worm. When the hand wheel is turned, the worm rotates, driving the worm wheel to rotate, and then the flip rod rotates around the hinge axis to achieve angle adjustment. The worm gear transmission has the characteristics of large transmission ratio, high precision and good self-locking performance. It is more convenient and accurate to adjust, and the position can be reliably maintained after adjustment. At the same time, an angle dial is set on the flip rod, and a pointer is set on the base. The pointer indicates the angle value on the dial, which is convenient for the operator to accurately control the angle of the flip rod. Considering that different types of cables have different minimum bending radii, the maximum angle reference values ​​of several commonly used specifications of cables can also be marked on the dial to remind the operator not to exceed the safety range when adjusting.

[0066] In another embodiment of the present application, a torsion spring can be installed on the shaft of the I-shaped wheel, one end of the torsion spring is fixed on the shaft seat of the I-shaped wheel, and the other end is connected to the shaft of the counterweight roller. The counterweight roller is connected to the shaft through a bearing and can rotate freely around the shaft. When the cable is inserted between the two, the counterweight roller is always pressed on the cable under the combined action of gravity and torsion spring force, generating a downward compression force on the cable. When the cable deviates in the radial direction, the counterweight roller can also follow the deflection and continue to maintain the compression guide for the cable. The stiffness of the torsion spring can be calculated and selected according to parameters such as the weight of the cable and the maximum rated tension of the cable, so that it can provide a suitable compression force, which will neither damage the cable nor cause the cable to fall off due to too little pressure. Considering the different cable specifications, the gap between the counterweight roller and the I-shaped wheel needs to be adjusted. A waist groove can be opened on the shaft of the counterweight roller, and the axial position of the counterweight roller can be adjusted by adjusting the screw through the waist groove and locking it on the shaft seat of the I-shaped wheel to adapt to cables of different thicknesses.

[0067] In another embodiment of the present application, a force measuring roller is arranged in the middle position between the I-shaped wheel and the counterweight roller, and the force measuring roller is installed on a shaft equipped with a strain gauge through a bearing. When the cable passes around the force measuring roller, the tension of the cable causes the force measuring roller to produce radial displacement, thereby causing a slight deformation of the shaft. The strain gauge converts the deformation into a change in resistance value, which is converted into a voltage signal through a bridge and an operational amplifier, and then converted into a digital signal through AD and transmitted to the controller.

[0068] The controller calculates the cable traction tension in real time based on the received tension signal and compares it with the set safety tension threshold. If the actual tension exceeds the threshold, the controller immediately sends a command to the traction mechanism to reduce the traction speed or stop traction, and triggers an audible and visual alarm to remind the operator to take measures. When the tension is detected to be back to normal, the command can be sent again to resume normal traction. The controller can also record the tension change curve of the entire traction process for subsequent analysis. Considering that the tension signal may be subject to electromagnetic interference, resulting in unstable readings, filtering algorithms such as limiting filtering, median filtering, Kalman filtering, etc. can be added to the control program to eliminate spike noise and random disturbances in the signal and obtain a more reliable tension value. The tension threshold setting needs to take into account both traction efficiency and cable safety. You can refer to factors such as the cable model, material, and ambient temperature to establish an algorithm for threshold adaptive adjustment in the control program.

[0069] In the early stage of traction, the algorithm can set the threshold value to a lower level and observe the traction of the cable under low tension. If the traction process is stable and there is no abnormality such as jamming or slipping, you can try to increase the threshold value slightly and observe again. Repeat this process until an optimal balance is found, which can ensure cable safety and improve traction efficiency. After that, the temperature changes can be continuously tracked, because the ambient temperature will significantly affect the tension characteristics of the cable. Temperature compensation can be added to the algorithm so that the threshold value can be automatically adjusted with temperature changes.

[0070] In this embodiment, the data processing flow is as follows:

[0071] Step S1: The analog voltage signal output by the strain gauge bridge is amplified and filtered, and then sent to a 16-bit AD chip for sampling and conversion. The quantization accuracy can reach 0.1N, and the sampling frequency is 1KHz. The converted digital signal is transmitted to the controller.

[0072] Step S2: After receiving the digital signal, the controller first performs zero-point calibration, that is, multiple sampling is performed in a no-load state and the average value is calculated to obtain an initial zero-point reading. Subsequent readings are subtracted from the zero-point reading to eliminate the sensor installation deviation.

[0073] The controller performs limiting filtering on a set of continuously collected data, that is, sets an upper limit and a lower limit. Any data that exceeds the range is regarded as erroneous data and is eliminated. The filtered data is averaged to obtain an average tension value as the basis for subsequent control. In order to eliminate random errors as much as possible, the number of sampled data is not less than 10 each time. At the same time, the data collected each time is serially input into the Kalman filter for processing to estimate the true value of the lifting tension in real time. The Kalman filter predicts the optimal value of the current tension by establishing a mathematical model of the lifting tension and continuously iterating. The result after Kalman filtering is compared with the previous arithmetic mean. If the difference exceeds 5%, there may be a sensor failure or a sudden change in the lifting state, and the controller will send an alarm signal.

[0074] Step S3: The controller reads the data of the current ambient temperature sensor, and obtains the maximum allowable tension of the cable at the temperature according to the preset cable parameter table, and sets it as the upper limit threshold of the tension for this hoisting.

[0075] The average tension value is compared with the threshold value. If it exceeds the threshold value, a speed reduction or shutdown command is immediately issued to the actuator, and an alarm is issued at the same time. A PID control algorithm can be used to set a buffer interval to avoid frequent starts and stops.

[0076] If the average tension value exceeds the limit for multiple consecutive times and the temperature is normal, it means that the threshold setting may be unreasonable. The controller starts the adaptive algorithm, tries to slightly increase the threshold, and then re-evaluates the lifting situation.

[0077] Step S4: The controller saves the tension value, average tension value, threshold value, temperature value, lifting speed and other parameters at each sampling moment together with the timestamp into the internal memory, and uploads them to the construction monitoring platform through the wireless module for subsequent analysis by technical personnel.

[0078] If an abnormal alarm occurs during the lifting process, the data for the most recent period will be automatically intercepted and packaged, and the alarm message will be sent as an attachment to facilitate locating the fault as soon as possible.

[0079] In another embodiment of the present application, the specific workflow of the adaptive data processing algorithm is as follows:

[0080] Step 1: Build process:

[0081] Fuzzy matrix construction:

[0082] According to the cable model table, the maximum tension, minimum tension, nominal tension and other parameters of the cable at different temperatures are obtained, and the temperature-tension fuzzy matrix is ​​established.

[0083] According to the traction speed range, it is divided into three fuzzy subsets: low speed, medium speed and high speed, which correspond to different tension fuzzy subsets respectively, and the speed-tension fuzzy matrix is ​​established.

[0084] According to the geometric parameters such as cable length, bending radius, height difference, etc., the stress distribution of the cable is calculated, and the geometric parameter-tension fuzzy matrix is ​​established after normalization.

[0085] According to the ambient humidity, it is divided into three fuzzy subsets: dry, normal and wet, which correspond to different tension correction coefficients respectively, and the humidity-tension correction fuzzy matrix is ​​established.

[0086] Step 2, training process: build a three-layer BP neural network, the number of neurons in the input layer is the sum of the dimensions of each fuzzy matrix, the number of neurons in the hidden layer is 1.5 times that of the input layer, and the number of neurons in the output layer is 1, which is the optimal tension threshold under the current state.

[0087] Each fuzzy matrix is ​​taken as a training sample, and a batch of actual cases are selected from historical data as training sets. Each case contains the cable parameters, environmental parameters, traction parameters and the actual tension threshold used at that time.

[0088] The neural network is trained using the gradient descent algorithm, and the weight matrix and bias vector of each layer are continuously adjusted until the error between the network output and the actual threshold is less than the preset target.

[0089] Step 3. Usage process: In actual traction operations, the controller collects data fed back by various sensors in real time, including tension, speed, temperature, humidity, etc., and calculates the corresponding fuzzy matrix based on the current data.

[0090] The fuzzy matrix is ​​input into the trained neural network to obtain the calculated optimal threshold.

[0091] The threshold is compared with the actual threshold to form a new set of training samples. When a certain number of new samples are accumulated, an incremental training is started to update the parameters of the neural network.

[0092] When safety conditions are met, the controller attempts to increase the current threshold by 5% and continuously monitors the cable stress condition. If no abnormality is found within 1 minute, the threshold is used as the new baseline threshold, and the neural network is rerun based on this to obtain a better threshold.

[0093] If the tension exceeds the limit or anomalies such as slippage or vibration are found during the monitoring process, the threshold will be immediately restored to the safe baseline, and the abnormal data will be marked and used as a negative sample in subsequent incremental training.

[0094] In another embodiment of the present application, a pair of high-strength nylon brushes can be installed at both ends of the guide enclosure. The hardness of the bristles should be lower than that of the cable sheath, the friction coefficient should be small, and the wear resistance should be good. The two brushes are assembled opposite each other, leaving a gap in the middle for the cable to pass through. When the cable passes through, the soft bristles of the nylon brush can wipe off the dust on the surface of the cable, and at the same time play a buffering role to prevent the cable from directly scratching the metal enclosure. The brush can be installed in a frame, and the frame is fixed in the groove at the end of the enclosure by screws, which is convenient for disassembly and replacement. A lubricating oil groove can also be opened on the frame, and grease can be applied to the bristles regularly to further reduce the friction between the bristles and the cable surface. At the position where the base contacts the well wall, a circle of foam pads can be pasted at the bottom of the base. The foam pads are made of closed-cell foam material and covered with PU leather on the outside, which is waterproof and dustproof. In addition, there is inevitably a gap between the base and the well wall, and dust and water vapor may enter the well through the gap. Therefore, an expansion caulking glue can be filled between the base and the well wall. The initial state of this colloid is liquid. After being poured into the gap, it will automatically expand and become solid when it comes into contact with water, filling the gap and blocking the entry of external dirt. After the construction is completed, when the base is removed, the colloid will be exposed to the air and will automatically oxidize and degrade, returning to liquid state, making it easy to clean.

[0095] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A cable installation guide device, It is characterized in that include: A base (1) is arranged at the wellhead where the cable is laid, the base (1) is provided with a longitudinal through hole for the cable to pass through, and an annular support sleeve (2) is provided at the upper end opening of the longitudinal through hole; A first guide member is mounted above the base (1), and the first guide member comprises: At least two support plates (33) are slidably seated on the upper end of the annular support sleeve (2); one end of the support plate (33) away from the center of the annular support sleeve (2) is bent downward to form an inverted L-shaped clamping portion (34); an annular flange is radially extended from the upper end of the annular support sleeve (2); and the inverted L-shaped clamping portion (34) is slidably clamped on the radial side wall and bottom wall of the annular flange; The guide enclosure (3) forms a semi-enclosed guide limit structure as a whole, and the portion of the guide enclosure (3) between the two ends is an arc-shaped structure; A group of support rods (32), one end of which is arranged on the bottom walls of the two ends of the guide enclosure, and the other end is fixed on the support plate (33); A plurality of rolling balls (31) are rotatably sleeved on the arc-shaped structure, and the rolling balls (31) form rolling support members for guiding cables passing through the inner side of the arc-shaped structure in mid-air rolling manner, so as to change the guiding direction of the cables; The base (1) and the side wall of the annular support sleeve (2) are both provided with an opening for the cable to escape from the longitudinal through hole; The second guide member comprises: A flip rod (5) is adjustably connected to one end of the guide enclosure (3); One end of the I-shaped guide wheel (51) is rotatably connected to the bottom end of the side wall of the flip rod (5) through a pin. After the cable passes over the rolling support, it bends downward and extends, and after passing through the side wall of the I-shaped guide wheel (51) close to the rolling support, the transmission direction of the cable changes to a lateral transmission direction along the cable laying well; A guide plate (52) is fixed at the bottom end of the side wall of the flip rod (5), and an inclined sliding opening is opened on the guide plate (52). An I-shaped pin is slidably clamped in the sliding opening, and a counterweight roller (53) is rotatably provided at one end of the I-shaped pin. A guide channel for rolling and clamping the cable for guiding is formed between the counterweight roller (53) and the radial side wall of the I-shaped guide wheel (51); A positioning structure for a plurality of fixed bases (1), the positioning structure comprising a gate-shaped seat (6) fixed to the inner wall of a longitudinal through hole, a threaded sleeve (61) hinged to the inner wall of the gate-shaped seat (6), and a threaded adjustment rod (62) rotatably passing through the threaded sleeve (61), wherein a fitting plate (63) is hinged at the bottom end of the threaded adjustment rod (62), and a torsion spring is provided at the hinge.

2. The cable installation guide device according to claim 1, It is characterized in that Two support plates (33) are provided, and a semicircular connecting plate (35) is fixed between the two support plates (33).

3. The cable installation guide device according to claim 1, It is characterized in that The sliding opening is arranged to extend obliquely downwardly toward a side away from the rolling support member.

4. The cable installation guide device according to claim 3, It is characterized in that A hinge seat (37) is provided at one end of the guide enclosure (3), and a hinge notch is provided in the hinge seat (37). A latch pin is rotatably provided on both side walls in the hinge notch. A strip guide groove is provided on both side walls of the flip rod (5), and the latch pin is slidably engaged with the strip guide groove. The flip rod (5) slides along the latch pin through the strip guide groove and flips with the latch pin as the rotation center to adjust the height and angle of the cable passing through the guide channel.

5. The cable installation guide device according to claim 4, It is characterized in that It also includes a limiter for limiting the position of the flip rod (5), the limiter including two pull rods (4) and two clamping columns (41), the two clamping columns (41) are rotatably arranged on opposite side walls at both ends of the two pull rods (4), a plurality of inverted J-shaped clamping blocks (36) are fixed to the upper end of the guide enclosure (3), a plurality of notches are recessed on the side wall of the flip rod (5) facing away from the guide enclosure (3), one of the clamping columns (41) is clamped on the inner side wall of an inverted J-shaped clamping block (36) at a corresponding position, and the other clamping column (41) is clamped in a notch at a corresponding position of the flip rod (5).

6. The cable installation guide device according to claim 5, It is characterized in that The upper end of the threaded adjustment rod (62) is an enlarged portion, and a collar (65) located between the threaded sleeve (61) and the enlarged portion is slidably sleeved on the outer wall of the threaded adjustment rod (62), and a connecting rod (64) is hingedly connected between the collar (65) and the upper side wall of the gate-shaped seat (6).

7. A cable installation guiding method, using the cable installation guiding device according to any one of claims 1 to 6, It is characterized in that The steps include: A1. The output end of the cable is inserted into the inner side of the guide enclosure (3) through the gap between the two ends of the guide enclosure (3). The semi-enclosed structure of the guide enclosure (3) is limited on both sides of the cable. The cable passing through the inner side of the arc-shaped structure is guided by a rolling support member composed of a plurality of rolling balls (31) suspended above the annular support sleeve (2); A2. Slide the turning rod (5) along the latch pin through the strip guide groove and turn it around the latch pin to adjust the height and angle of the cable passing through the guide channel to adapt to the cable being guided and transmitted at different heights and angles downhole; A3. After the cable passes over the rolling support, it bends downward and extends. After passing the I-shaped guide wheel (51) close to the side wall of the rolling support, the transmission direction of the cable changes to the lateral transmission direction along the cable laying well.

Citation Information

Patent Citations

  • Cable guide device

    CN109217223A

  • Power cable construction guide frame

    CN112158669A

  • Wellhead guiding device of cable well for cable laying

    CN116946804A