Integrated construction and installation equipment for building embedded sleeves
By designing integrated construction and installation equipment for embedded sleeves in buildings, and using automation and precise alignment technology, we have solved the problems of low installation efficiency and safety hazards of embedded sleeves in hydropower, achieved fast and safe installation, and ensured construction quality and safety. Structural integrity.
Patent Information
- Application Number
- CN202410891329.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-04
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-04
AI Technical Summary
During construction, the installation efficiency of hydropower embedded sleeves is low, resulting in prolonged construction time, inaccurate positions, increased safety risks and labor intensity, and possible damage to the steel structure.
An integrated construction and installation equipment for building embedded sleeves is designed, including a load-bearing block, an electric push rod, a moving mechanism, a fixing mechanism and an alignment mechanism. Through automation and precise alignment, the sleeves can be installed quickly and safely, reducing manual labor. Operate to avoid injuries and structural damage caused by lifting steel bars.
It significantly improves the construction speed and quality consistency, reduces labor intensity and safety hazards, ensures uniform filling of concrete and structural integrity, avoids physical damage to steel bars, and improves construction efficiency and safety.
Smart Images

Figure CN118422894B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building engineering, in particular to an integrated construction and installation device for a building pre-buried sleeve. Background Art
[0002] Building water and electricity embedded sleeve (see Fig.10 ) is a hollow tubular component pre-installed during the construction of building structures. It is usually composed of ferrules at both ends and a pipe in the middle. It is mostly used for the future installation of water pipes, cables or other pipeline equipment. However, during concrete pouring operations, it is necessary to first fix the water and electricity pre-embedded sleeve in the steel cage so that the poured concrete can surround the water and electricity pre-embedded sleeve and completely fill it to ensure the uniformity and consistency of the concrete around the water and electricity pre-embedded sleeve.
[0003] At present, there are the following disadvantages in the construction of building embedded sleeves: 1. When the water and electricity embedded sleeves are fixedly installed in the steel cage, it is necessary to manually install the pre-assembled water and electricity embedded sleeves in the steel cage one by one, and the efficiency of one-by-one installation is relatively low, which greatly increases the construction time and affects the project progress. In addition, it is difficult to ensure that the position of each sleeve is accurate during manual installation, and the difference in position will affect the quality and safety of the final structure. In addition, manual operation in the complex environment of the steel cage increases the risk of injury to construction personnel; 2. When the water and electricity embedded sleeves are installed in the steel cage, workers are required to lift the steel bars on both sides of the steel cage before the water and electricity embedded sleeves can be inserted into the steel cage. Manually lifting the steel bars requires great physical strength, which will significantly increase the labor intensity of the workers. In addition, in the process of lifting the steel bars, the workers may suffer safety accidents such as cuts and pinching. In addition, if the steel bars suddenly slide or rebound, it will also cause impact injuries to the water and electricity embedded sleeves or workers, and frequent lifting and lowering of the steel bars may cause damage to the steel bars, such as bending or microcracks, which will affect the structural performance and durability of the steel bars.
[0004] Therefore, in order to ensure that the poured concrete can surround the water and electricity embedded sleeve and completely fill it, so as to ensure the uniformity and consistency of the concrete around the water and electricity embedded sleeve, the present invention provides an integrated construction and installation device for the building embedded sleeve. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides an integrated construction and installation device for a pre-embedded sleeve for a building, which is achieved by the following specific technical means: an integrated construction and installation device for a pre-embedded sleeve for a building, comprising a bearing block, on which a first electric push rod is fixedly mounted, a telescopic end of the first electric push rod is fixedly mounted with a pressure bin located below the bearing block, and a moving mechanism for moving on a steel cage is provided at the lower end of the bearing block; the moving mechanism comprises a distance adjusting portion arranged at the lower end of the bearing block, and a driving portion is provided on the distance adjusting portion for providing power to the distance adjusting portion and for implementing adaptive pressure on the steel bars.
[0006] The pressing bin is provided with a fixing mechanism for correcting and fixing the position of the embedded sleeve; the fixing mechanism comprises an expansion portion arranged in the pressing bin, the expansion portion is provided with a pressing portion for fixing the moving mechanism, and the pressing portion is provided with a correction portion for correcting the position of the moving mechanism.
[0007] The pressure bin is also provided with an alignment mechanism for automatically installing the ferrule and the pipe in the steel cage; the alignment mechanism includes a loading part arranged on the pressure bin for loading the ferrule and the pipe, the loading part is provided with an auxiliary part for assisting the docking of the ferrule and the pipe, the pressure bin and the loading part are jointly provided with an alignment part for aligning the ferrule and the pipe, and the alignment part is provided with an inner support part for coaxially supporting the ferrule and the pipe.
[0008] As a preferred technical solution of the present invention, the distance adjusting part includes an electric linear module, a loading slide, an auxiliary slide rail, a support frame, a roller and a limiting circular plate. The lower end of the loading block is slidably installed with a left-right symmetrical and oppositely moving loading slide through an electric linear module. The lower end of the loading block is fixedly installed with an auxiliary slide rail that is slidably connected to the left-right symmetrical loading slide at the same time. The loading slide is fixedly installed with a front-and-back symmetrical support frame, and rollers are installed in the support frame through bearings. The rollers are fixedly installed with left-and-right symmetrical limiting circular plates, and a number of grooves are provided on the limiting circular plate in a circular array.
[0009] As a preferred technical solution of the present invention, the driving part includes a first motor, a driving shaft, a spring rod and an arc-shaped support plate. The first motor is fixedly installed on the support frame on the front side, and the output end of the first motor is fixedly installed with a driving shaft that slides through the front roller at the same time. The side walls of the two limiting circular plates on the same roller that are close to each other are fixedly installed with spring rods in a circular array. The ends of the two spring rods opposite to the front and rear of the roller that are close to each other are fixedly installed with an arc-shaped support plate, and the side of the arc-shaped support plate away from the corresponding roller is set as an arc surface.
[0010] As a preferred technical solution of the present invention, the expansion part includes a first bidirectional screw, a first slide plate and a second motor. The first bidirectional screw is installed in the pressure chamber through a bearing, and the first bidirectional screw is threadedly connected with a first slide plate which is symmetrical front and back and slidingly connected to the pressure chamber. The second motor is fixedly installed in the pressure chamber, and the output end of the second motor is connected to the first bidirectional screw through a first gear set.
[0011] As a preferred technical solution of the present invention, the pressing part includes a pressing slide rod, a pressing block and an alignment groove. The side of the first slide plate away from each other is fixedly installed with a pressing slide rod which is symmetrical on the left and right and slides through the pressing bin. The end of the pressing slide rod away from the pressing bin is fixedly installed with a pressing block. The pressing bin is provided with an alignment groove which corresponds one to one with the pressing blocks.
[0012] As a preferred technical solution of the present invention, the correcting part includes a matching groove, a torsion spring rod, a C-shaped push rod and a rotation limiting block. A matching groove is provided on a side wall of the pressure block away from the pressure chamber. A torsion spring rod that is symmetrical on both sides and passes through the lower end surface of the pressure block is installed in the matching groove through a bearing. A C-shaped push rod is fixedly installed on the torsion spring rod. A rotation limiting block located between the symmetrical torsion spring rods is fixedly installed in the matching groove. The torsion spring rod is provided with a push block for cooperating with the rotation limiting block to limit the rotation angle of the torsion spring rod.
[0013] As a preferred technical solution of the present invention, the loading part includes a first supporting arm, a pipe-carrying tube, a first carrying sleeve, a second supporting arm, a second carrying sleeve and a flexible clamp. The first supporting arm is fixedly installed on the pressure chamber, and the right end of the first supporting arm is fixedly installed with a pipe-carrying tube for loading pipes, and the right end of the pipe-carrying tube is fixedly installed with a first carrying sleeve for loading a ferrule. The pressure chamber is fixedly installed with a second carrying sleeve located at a symmetrical position of the first carrying sleeve through the second supporting arm. The lower ends of the first carrying sleeve and the second carrying sleeve are both fixedly installed with flexible clamps that are symmetrical front and back and used to limit the ferrule. The lower end of the pipe-carrying tube is also fixedly installed with flexible clamps that are symmetrical front and back and used to limit the pipe, and the flexible clamp is a special L-shaped arrangement.
[0014] As a preferred technical solution of the present invention, the auxiliary part includes a supporting slide rail, a third motor, a sliding clamp, a screw and a fixed plate. The tube carrier tube and the first carrier sleeve are jointly fixedly installed with a supporting slide rail located behind the flexible clamping claw on this side, and a screw is installed in the supporting slide rail through a bearing. A sliding clamp threadedly connected to the screw is slidably installed on the side of the supporting slide rail close to the tube carrier tube. A third motor with an output end fixedly connected to the screw is fixedly installed on the supporting slide rail, and a fixed plate corresponding to the sliding clamp is fixedly installed on the right end of the supporting slide rail, and a through groove is provided on the fixed plate.
[0015] As a preferred technical solution of the present invention, the alignment part includes an alignment slide rail, a fourth motor, a supporting slider, an alignment slide plate, a second electric push rod and a tube-resisting pressure block. The pressure bin, the first carrier sleeve and the front end surface of the second carrier sleeve are commonly fixedly installed with the alignment slide rail, and the fourth motor is fixedly installed on the alignment slide rail. The second bidirectional screw rod fixedly connected to the output end of the fourth motor is installed in the alignment slide rail through a bearing, and a supporting slider that is symmetrical on both sides and threadedly connected to the second bidirectional screw is slidably installed in the alignment slide rail. The lower end of the support slider is slidably installed with the alignment slide plate through a set slide column, and the support slider is fixedly installed with a second electric push rod fixedly connected to the alignment slide plate at the telescopic end, and the tube-resisting pressure block corresponding to the through groove is fixedly installed on the upper end surface of the alignment slide plate.
[0016] As a preferred technical solution of the present invention, the inner support part includes a connecting cylinder, a circular slide, a third electric push rod, an inner support groove, a pressure rod and a limit column. A connecting cylinder is fixedly installed on one side wall of the tube-pushing block that is close to each other, a circular slide is slidably installed in the connecting cylinder, a third electric push rod whose telescopic end is fixedly connected to the circular slide is fixedly installed on the tube-pushing block, a plurality of inner support grooves are penetrated through the connecting cylinder in a circular array, a limit column is fixedly installed in the inner support groove, a pressure rod corresponding to the inner support groove one by one is hinged on the circular slide, and a limit sliding hole is penetrated through the pressure rod and slidably connected to the limit column.
[0017] Compared with the prior art, the present invention has the following beneficial effects: 1. The integrated construction and installation equipment for building embedded sleeves realizes a series of construction optimizations through the coordinated use of the moving mechanism, the fixing mechanism and the alignment mechanism, and enables the equipment to automatically move and align on the steel cage, automatically complete the precise installation of the embedded sleeves for drainage and electricity, significantly improves the construction speed, and ensures the consistency of installation quality. Secondly, the automated installation reduces the direct contact between workers and the steel cage, reduces the labor intensity and potential safety hazards during the construction process. Finally, through precise alignment and installation, unnecessary pressure on the pipeline is avoided, concrete damage and structural safety risks are reduced. At the same time, the operation steps are simplified, physical damage to the steel bars is avoided, and the integrity and stability of the structure are ensured. The use of this equipment not only improves construction efficiency and safety, but also ensures high standards of project quality and long-term stability of the structure.
[0018] 2. The integrated construction and installation equipment for the building embedded sleeve can automatically move on the steel cage through the coordinated use of the moving mechanism and the positioning mechanism, so that the equipment can automatically complete the installation of the same drainage embedded sleeve in the steel cage. Therefore, it can significantly improve the construction speed of the project, ensure that the quality of each installation is maintained at the same standard, reduce quality fluctuations caused by human errors, and reduce the number of times workers directly contact potential dangerous environments such as steel cages, thereby reducing labor intensity and improving construction safety.
[0019] 3. The integrated construction and installation equipment of the building embedded sleeve, through the coordinated use of the fixed mechanism and the alignment mechanism, can align and correct the installation position of the water and electricity embedded sleeve when installing it, to ensure the accuracy of the installation of the embedded sleeve. The precise installation position can avoid unnecessary pressure on the pipeline, thereby reducing the risk of concrete damaging the embedded sleeve structure, and then ensuring the safety of the building structure after the concrete is poured.
[0020] 4. The integrated construction and installation equipment of the building embedded sleeve, through the set alignment mechanism, automatically aligns the ferrules on both sides and the middle pipe in the steel cage, improves the installation accuracy of the embedded sleeve, ensures the correct position and direction of the water and electricity pipeline, and can complete the sleeve embedding without lifting the steel bars on both sides, thereby simplifying the operation steps and avoiding safety hazards in the construction process, speeding up the installation speed of the embedded sleeve, avoiding physical damage to the steel bars, maintaining their original structural integrity and strength, so as to ensure the bearing capacity and stability of the entire structure. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention when it is working.
[0022] Figure 2 It is a schematic diagram of the three-dimensional structure of the present invention.
[0023] Figure 3 It is a partially cutaway three-dimensional structural schematic diagram of the moving mechanism and the fixing mechanism of the present invention.
[0024] Figure 4 for Figure 3 Schematic diagram of the enlarged structure at point A in the middle.
[0025] Figure 5 It is a partial three-dimensional structural schematic diagram of the position correction part of the present invention.
[0026] Figure 6 It is a schematic diagram of the three-dimensional structure of the alignment part of the present invention.
[0027] Figure 7 It is a schematic diagram of a partially cutaway three-dimensional structure of the loading portion of the present invention.
[0028] Figure 8 It is a schematic diagram of the three-dimensional structure of the auxiliary part of the present invention.
[0029] Fig. 9 for Figure 7 Schematic diagram of the enlarged structure at point B in the middle.
[0030] Fig.10 It is a schematic diagram of the three-dimensional structure of the embedded sleeve.
[0031] In the figure: 1, bearing block; 2, first electric push rod; 3, pressing bin; 4, moving mechanism; 41, distance adjustment part; 411, electric linear module; 412, loading slide; 413, auxiliary slide rail; 414, support frame; 415, roller; 416, limiting circular plate; 42, driving part; 421, first motor; 422, driving shaft; 423, spring rod; 424, arc-shaped pressing plate; 5, fixing mechanism; 51, expansion part; 511, first bidirectional screw; 512, first slide; 513, second motor; 52, pressing part; 521, pressing slide rod; 522, pressing block; 523, alignment groove; 53, correction part; 531, matching groove; 532, torsion spring rod; 533, C-type pressing rod; 534, The limiting block; 6, the alignment mechanism; 61, the loading part; 611, the first supporting arm; 612, the tube-carrying tube; 613, the first carrying sleeve; 614, the second supporting arm; 615, the second carrying sleeve; 616, the flexible clamp; 62, the auxiliary part; 621, the supporting slide rail; 622, the third motor; 623, the sliding clamp; 624, the screw rod; 625, the fixed plate; 63, the alignment part; 631, the alignment slide rail; 632, the fourth motor; 633, the supporting slider; 634, the alignment slide plate; 635, the second electric push rod; 636, the tube-carrying pressure block; 64, the inner supporting part; 641, the connecting tube; 642, the circular slide plate; 643, the third electric push rod; 644, the inner supporting groove; 645, the pressure rod; 646, the limiting column. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] See also Figure 1 and Figure 2 A building embedded sleeve integrated construction and installation device comprises a bearing block 1, a first electric push rod 2 is fixedly mounted on the bearing block 1, a pressing bin 3 located below the bearing block 1 is fixedly mounted on the telescopic end of the first electric push rod 2, a moving mechanism 4 for moving on a steel cage is arranged at the lower end of the bearing block 1; the moving mechanism 4 comprises a distance adjusting part 41 arranged at the lower end of the bearing block 1, and a driving part 42 for providing power to the distance adjusting part 41 and implementing adaptive pressing on the steel bars is arranged on the distance adjusting part 41.
[0034] See also Figure 1 , Figure 2 and Figure 3A fixing mechanism 5 for correcting and fixing the position of the embedded sleeve is provided on the pressing bin 3; the fixing mechanism 5 includes an expansion portion 51 arranged in the pressing bin 3, a pressing portion 52 for fixing the moving mechanism 4 is provided on the expansion portion 51, and a correction portion 53 for correcting the position of the moving mechanism 4 is provided on the pressing portion 52.
[0035] See also Figure 1 and Figure 2 The pressing bin 3 is also provided with an alignment mechanism 6 for automatically installing the ferrule and the pipe in the steel cage; the alignment mechanism 6 includes a loading part 61 arranged on the pressing bin 3 for loading the ferrule and the pipe, and the loading part 61 is provided with an auxiliary part 62 for assisting the docking of the ferrule and the pipe. The pressing bin 3 and the loading part 61 are jointly provided with an alignment part 63 for aligning the ferrule and the pipe, and the alignment part 63 is provided with an inner support part 64 for coaxially supporting the ferrule and the pipe.
[0036] See also Figure 1 , Figure 2 and Figure 3 The distance adjustment part 41 includes an electric linear module 411, a loading slide 412, an auxiliary slide rail 413, a support frame 414, a roller 415 and a limiting circular plate 416. The lower end of the supporting block 1 is slidably installed with a loading slide 412 that is symmetrical and moves toward each other through the electric linear module 411. The lower end of the supporting block 1 is fixedly installed with an auxiliary slide rail 413 that is slidably connected to the symmetrical loading slide 412. A front-to-back symmetrical support frame 414 is fixedly installed on the loading slide 412. A roller 415 is installed in the support frame 414 through a bearing. A left-right symmetrical limiting circular plate 416 is fixedly installed on the roller 415. A plurality of grooves are provided on the limiting circular plate 416 in a circular array.
[0037] See also Figure 1 , Figure 3 and Figure 4 The driving part 42 includes a first motor 421, a driving shaft 422, a spring rod 423 and an arc-shaped abutment plate 424. The first motor 421 is fixedly installed on the front support frame 414. The output end of the first motor 421 is fixedly installed with a driving shaft 422 that slides through the front roller 415 at the same time. The spring rod 423 is fixedly installed in a circular array on one side wall of two limiting circular plates 416 on the same roller 415 that are close to each other. The arc-shaped abutment plate 424 is fixedly installed on one end of the two spring rods 423 facing each other at the front and rear of the roller 415 that are close to each other. The arc-shaped abutment plate 424 is set as an arc surface on the side away from the corresponding roller 415.
[0038] During specific work, when it is necessary to install the water and electricity embedded sleeve in the steel cage, the worker first places the bearing block 1 above the steel cage, and starts the electric linear module 411 to make it move synchronously with the loading slides 412 on both sides until the roller 415 moves to the vertical steel bars on the steel cage. At this time, the equipment can be placed above the steel cage. At this time, the limiting circular plates 416 on both sides of the roller 415 limit the steel bars from the side, thereby completing the loading of the equipment.
[0039] Then, the first motor 421 is started to rotate the driving shaft 422, and the driving shaft 422 will rotate the roller 415 symmetrical on the front side. During the rotation of the roller 415, the limiting circular plate 416 rotates synchronously, and the arc-shaped abutment plates 424 between the limiting circular plates 416 are in a state of being close to each other when not being pressed. When the limiting circular plate 416 rotates so that the arc surface of the arc-shaped abutment plates 424 contacts the steel bar, the steel bar will press the arc-shaped abutment plates 424 to the corresponding limiting circular plates 416, and the arc-shaped abutment plates 424 on both sides will press the steel bar under the action of the spring rod 423 to increase the friction force of the roller 415 on the steel bar, so that the roller 415 automatically moves with the equipment at the upper end of the steel cage, and then, with the cooperation of the alignment mechanism 6, the installation of the same drainage pre-embedded sleeve can be automatically completed in the steel cage, thereby significantly improving the construction speed of the project.
[0040] When the roller 415 moves the device forward, if the groove on the limiting circular plate 416 does not correspond to the horizontal steel bar, the limiting circular plate 416 on the front side will tilt up, but the spring rod 423 and the arc-shaped abutment plate 424 on the rear roller 415 will cooperate to limit the rear side of the device. At this time, the driving shaft 422 continues to rotate with the front roller 415, resulting in idling and eventually the groove is stuck in the horizontal steel bar, so that the device can continue to move.
[0041] See also Figure 1 and Figure 3 The expansion part 51 includes a first bidirectional screw 511, a first slide plate 512 and a second motor 513. The first bidirectional screw 511 is installed in the pressure chamber 3 through a bearing. The first bidirectional screw 511 is threadedly connected with a first slide plate 512 which is symmetrical front and back and slidingly connected to the pressure chamber 3. The second motor 513 is fixedly installed in the pressure chamber 3, and the output end of the second motor 513 is transmission-connected to the first bidirectional screw 511 through a first gear set.
[0042] See also Figure 1 , Figure 2 , Figure 3 and Figure 5The pressing part 52 includes a pressing slide bar 521, a pressing block 522 and an alignment groove 523. The side of the first slide plate 512 away from each other is fixedly installed with a pressing slide bar 521 that is symmetrical on both sides and slides through the pressing bin 3. The end of the pressing slide bar 521 away from the pressing bin 3 is fixedly installed with a pressing block 522. The pressing bin 3 is provided with an alignment groove 523 that corresponds to the pressing block 522 one by one.
[0043] See also Figure 2 , Figure 3 and Figure 5 The correcting part 53 includes a matching groove 531, a torsion spring rod 532, a C-shaped push rod 533 and a rotation limiting block 534. A matching groove 531 is provided on a side wall of the pressure block 522 away from the pressure bin 3. A torsion spring rod 532 which is symmetrical on both sides and passes through the lower end surface of the pressure block 522 is installed in the matching groove 531 through a bearing. A C-shaped push rod 533 is fixedly installed on the torsion spring rod 532. A rotation limiting block 534 located between the symmetrical torsion spring rods 532 is fixedly installed in the matching groove 531. The torsion spring rod 532 is provided with a push block for cooperating with the rotation limiting block 534 to limit the rotation angle of the torsion spring rod 532.
[0044] During specific operation, when the moving mechanism 4 moves the equipment to the location where the water and electricity embedded sleeve is required to be installed in the steel cage, the first motor 421 is stopped, and then the first electric push rod 2 is started to make it descend with the pressure bin 3 and fit the top of the steel cage, and then the second motor 513 can be started to rotate the first bidirectional screw 511 through the first gear set, and the first slide plate 512 is restricted by the sliding of the pressure bin 3, so that the first slide plates 512 on both sides move synchronously in opposite directions, and the first slide plate 512 will extend synchronously with the pressure slide bar 521, so that the pressure blocks 522 at the four corners support the transverse steel bars on the front and rear sides, thereby fixing the equipment and straightening its position.
[0045] When the pressure block 522 approaches the transverse steel bar, the rotation limit block 534 will limit the pressure block on the torsion spring rod 532, so that the C-shaped pressure rods 533 on both sides approach the transverse steel bar in an eight-shaped shape, and open to both sides when the C-shaped pressure rod 533 contacts the transverse steel bar. When the pressure block 522 contacts the transverse steel bar, the expanded C-shaped pressure rod 533 will use the vertical steel bar as a reference to correct the equipment again, so as to correct the installation position of the embedded sleeve when installing the water and electricity embedded sleeve, and ensure the accuracy of the installation of the embedded sleeve.
[0046] See also Figure 1 , Figure 2 , Figure 6 and Figure 7The loading part 61 includes a first supporting arm 611, a tube-carrying tube 612, a first carrying sleeve 613, a second supporting arm 614, a second carrying sleeve 615 and a flexible clamp 616. The first supporting arm 611 is fixedly installed on the pressure chamber 3. The right end of the first supporting arm 611 is fixedly installed with a tube-carrying tube 612 for loading pipes. The right end of the tube-carrying tube 612 is fixedly installed with a first carrying sleeve 613 for loading ferrules. The pressure chamber 3 is fixedly installed with a second carrying sleeve 615 located at a symmetrical position of the first carrying sleeve 613 through the second supporting arm 614. The lower ends of the first carrying sleeve 613 and the second carrying sleeve 615 are both fixedly installed with flexible clamps 616 that are symmetrical front and back and used to limit the ferrules. The lower end of the tube-carrying tube 612 is also fixedly installed with flexible clamps 616 that are symmetrical front and back and used to limit the pipe. The flexible clamps 616 are set in a special L shape.
[0047] See also Figure 1 , Figure 2 and Figure 8 The auxiliary part 62 includes a supporting rail 621, a third motor 622, a sliding clamp 623, a screw 624 and a fixed plate 625. The tube carrier tube 612 and the first carrier sleeve 613 are jointly fixedly installed with a supporting rail 621 located behind the flexible clamp 616 on this side. A screw 624 is installed in the supporting rail 621 through a bearing. A sliding clamp 623 threadedly connected to the screw 624 is slidably installed on the side of the supporting rail 621 close to the tube carrier tube 612. A third motor 622 fixedly connected to the screw 624 at its output end is fixedly installed on the supporting rail 621. A fixed plate 625 corresponding to the sliding clamp 623 is fixedly installed on the right end of the supporting rail 621, and a through groove is opened on the fixed plate 625.
[0048] During specific operation, after the fixing mechanism 5 completes the fixing of the equipment, the pipe loaded in the pipe carrier tube 612 will be between the flexible clamps 616 below it, and the first carrier sleeve 613 and the second carrier sleeve 615 will similarly make the ferrule between the corresponding flexible clamps 616. At this time, the right ferrule and the pipe are in a coaxial position. At this time, the third motor 622 can be started to rotate the screw rod 624, so that the pipe between the flexible clamps 616 is moved closer to the right ferrule through the sliding clamp plate 623, and the fixed plate 625 provides support for the right ferrule, so that the pipe can be inserted into the right ferrule, and the pipe in the pipe carrier tube 612 will not move down under the restriction of the sliding clamp plate 623. When the right ferrule and the pipe are docked, the third motor 622 can be started in reverse to reset the sliding clamp plate 623.
[0049] See also Figure 1 , Figure 2 , Figure 6 and Fig. 9The alignment part 63 includes an alignment rail 631, a fourth motor 632, a support slider 633, an alignment slide plate 634, a second electric push rod 635 and a tube-proof pressing block 636. The front end surfaces of the pressing chamber 3, the first carrier sleeve 613 and the second carrier sleeve 615 are fixedly installed with the alignment rail 631. The fourth motor 632 is fixedly installed on the alignment rail 631. A second bidirectional screw fixedly connected to the output end of the fourth motor 632 is installed in the alignment rail 631 through a bearing. A support slider 633 that is symmetrical on both sides and threadedly connected to the second bidirectional screw is slidably installed in the alignment rail 631. The lower end of the support slider 633 is slidably installed with the alignment slide plate 634 through a set slide column. A second electric push rod 635 fixedly connected to the alignment slide plate 634 at the telescopic end is fixedly installed on the support slider 633. A tube-proof pressing block 636 corresponding to the through groove is fixedly installed on the upper end surface of the alignment slide plate 634.
[0050] See also Figure 1 , Figure 2 and Fig. 9 The inner support part 64 includes a connecting cylinder 641, a circular slide 642, a third electric push rod 643, an inner support groove 644, a pressure rod 645 and a limiting column 646. A connecting cylinder 641 is fixedly installed on one side wall close to the tube pressure block 636. A circular slide 642 is slidably installed in the connecting cylinder 641. A third electric push rod 643 whose telescopic end is fixedly connected to the circular slide 642 is fixedly installed on the tube pressure block 636. A plurality of inner support grooves 644 are penetrated in a circular array on the connecting cylinder 641. A limiting column 646 is fixedly installed in the inner support groove 644. A pressure rod 645 corresponding to the inner support groove 644 is hinged on the circular slide 642. A limiting sliding hole slidably connected to the limiting column 646 is penetrated on the pressure rod 645.
[0051] During specific operation, after the loading part 61 and the auxiliary part 62 cooperate to complete the docking of the right-side ferrule and the pipe, the pipe pressing block 636 is in the through groove of the fixed plate 625. At this time, the third electric push rod 643 can be started to move it with the circular slide plate 642 to the other end of the connecting tube 641. During the movement, the pressure rod 645 will rotate with the limiting column 646 as the fulcrum, so that the pressure rod 645 will extend from the inner support groove 644 and open around. When the circular slide plate 642 moves a certain distance, the pressure rod 645 opened around will support and fix the right-side ferrule and the pipe from the inside. Similarly, the third electric push rod 643 on the left will support and fix the left-side ferrule through the inner support part 64. At this time, the right-side ferrule is in a coaxial position with the pipe and the left-side ferrule.
[0052] Then, the second electric push rods 635 on both sides are started to move down a certain position with the alignment slides 634 on both sides, so that the ferrule and the pipe are pulled out from under the flexible clamp 616 through the inner support part 64. When the ferrule and the pipe are separated from the corresponding flexible clamp 616, the latter group of ferrules and pipes will fall to this position. At this time, the fourth motor 632 is started to rotate the second bidirectional screw so that the support slides 633 on both sides are synchronously close. At this time, the alignment slide 634 will carry the descending ferrule and pipe for alignment combination in the steel cage, so that the left side of the pipe is inserted into the left ferrule in the steel cage, thereby completing the pre-embedded installation of the sleeve, so that the sleeve can be pre-embedded without lifting the steel bars on both sides, simplifying the operation steps and avoiding safety hazards during construction. Then all components are reset and the pre-embedded installation of the next group of ferrules and pipes can be continued with the moving mechanism 4.
[0053] Working principle: When it is necessary to install the water and electricity embedded sleeve in the steel cage, the worker first places the bearing block 1 above the steel cage, and starts the electric linear module 411 to move the rollers 415 to the corresponding steel bars on the steel cage through the distance adjusting part 41. At this time, the equipment can be placed above the steel cage to complete the loading of the equipment. Then start the first motor 421 to make the rollers 415 carry the equipment to move automatically on the upper end of the steel cage through the cooperation of the driving part 42 and the distance adjusting part 41.
[0054] When the moving mechanism 4 moves the equipment to the location where the water and electricity embedded sleeve is required to be installed on the steel cage, the first motor 421 is stopped, and then the first electric push rod 2 is started to lower the pressure bin 3 with it and fit the top of the steel cage, and then the second motor 513 is started to correct the equipment again through the fixing mechanism 5, so that the installation position of the water and electricity embedded sleeve is corrected when installing it, ensuring the accuracy of the installation of the embedded sleeve.
[0055] Then start the third motor 622 to insert the pipe into the right ferrule through the auxiliary part 62. After the right ferrule and the pipe are connected, start the third motor 622 in reverse to reset the sliding clamp 623. Then start the third electric push rod 643 to support and fix the right ferrule and the pipe from the inside through the inner support part 64. Similarly, the third electric push rod 643 on the left will support and fix the left ferrule through the inner support part 64.
[0056] Then, the second electric push rods 635 on both sides are started to move down a certain position with the alignment slides 634 on both sides, so that the ferrule and the pipe are pulled out from under the flexible clamp 616 through the inner support part 64. At this time, the fourth motor 632 is started to rotate the second bidirectional screw so that the support slides 633 on both sides are synchronously approached. At this time, the alignment slide 634 will carry the descending ferrule and the pipe for alignment combination in the steel cage, so that the left side of the pipe is inserted into the left ferrule in the steel cage, thereby completing the embedded installation of the sleeve. Then all components are reset and the embedded installation of the next group of ferrules and pipes can be continued with the moving mechanism 4.
[0057] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An integrated construction and installation device for a building pre-buried sleeve, comprising a bearing block (1), Features: A first electric push rod (2) is fixedly mounted on the bearing block (1); a pressure chamber (3) located below the bearing block (1) is fixedly mounted on the telescopic end of the first electric push rod (2); and a moving mechanism (4) for moving on the steel cage is arranged at the lower end of the bearing block (1); The moving mechanism (4) comprises a distance adjusting part (41) arranged at the lower end of the bearing block (1), and a driving part (42) is arranged on the distance adjusting part (41) for providing power to the distance adjusting part (41) and for implementing adaptive pressure on the steel bars; The pressing chamber (3) is provided with a fixing mechanism (5) for correcting and fixing the position of the embedded sleeve; The fixing mechanism (5) comprises an expansion portion (51) arranged in the pressing chamber (3), a pressing portion (52) for fixing the moving mechanism (4) is arranged on the expansion portion (51), and a position correction portion (53) for correcting the position of the moving mechanism (4) is arranged on the pressing portion (52); The pressing bin (3) is also provided with a positioning mechanism (6) for automatically installing the ferrule and the pipe in the steel cage; The alignment mechanism (6) comprises a loading part (61) arranged on the pressing chamber (3) for loading the ferrule and the pipe, the loading part (61) is provided with an auxiliary part (62) for assisting the ferrule and the pipe to dock, the pressing chamber (3) and the loading part (61) are jointly provided with an alignment part (63) for aligning the ferrule and the pipe, and the alignment part (63) is provided with an inner support part (64) for coaxially supporting the ferrule and the pipe; The distance adjustment part (41) comprises an electric linear module (411), a loading slide plate (412), an auxiliary slide rail (413), a support frame (414), a roller (415) and a limiting circular plate (416); the lower end of the carrying block (1) is slidably mounted with a loading slide plate (412) that is symmetrical and moves toward each other via the electric linear module (411); the lower end of the carrying block (1) is fixedly mounted with an auxiliary slide rail (413) that is slidably connected to the symmetrical loading slide plate (412); a front-to-back symmetrical supporting frame (414) is fixedly mounted on the loading slide plate (412); a roller (415) is mounted in the supporting frame (414) via a bearing; a left-right symmetrical limiting circular plate (416) is fixedly mounted on the roller (415); and a plurality of grooves are provided on the limiting circular plate (416) in a circular array; The driving part (42) comprises a first motor (421), a driving shaft (422), a spring rod (423) and an arc-shaped abutment plate (424); the first motor (421) is fixedly mounted on the support frame (414) on the front side; the driving shaft (422) which slides through the front roller (415) is fixedly mounted on the output end of the first motor (421); the spring rod (423) is fixedly mounted in a circular array on one side wall of two limiting circular plates (416) on the same roller (415) which are close to each other; the arc-shaped abutment plate (424) is fixedly mounted on one end of two spring rods (423) which are opposite to each other at the front and rear of the roller (415) which are close to each other; and the arc-shaped abutment plate (424) is arranged with an arc surface on the side away from the corresponding roller (415); The expansion part (51) comprises a first bidirectional screw (511), a first slide plate (512) and a second motor (513); the first bidirectional screw (511) is installed in the pressure chamber (3) via a bearing; a first slide plate (512) which is symmetrical in front and back and slidably connected to the pressure chamber (3) is threadedly connected to the first bidirectional screw (511); a second motor (513) is fixedly installed in the pressure chamber (3); an output end of the second motor (513) is transmission-connected to the first bidirectional screw (511) via a first gear set; The loading part (61) comprises a first support arm (611), a tube-carrying tube (612), a first carrier sleeve (613), a second support arm (614), a second carrier sleeve (615) and a flexible clamp (616); the first support arm (611) is fixedly mounted on the pressure chamber (3); the right end of the first support arm (611) is fixedly mounted with a tube-carrying tube (612) for loading a pipe; the right end of the tube-carrying tube (612) is fixedly mounted with a first carrier sleeve (613) for loading a ferrule 3), the pressure chamber (3) is fixedly installed with a second carrier sleeve (615) located at a symmetrical position of the first carrier sleeve (613) through a second support arm (614), and the lower ends of the first carrier sleeve (613) and the second carrier sleeve (615) are fixedly installed with flexible clamps (616) that are symmetrical in front and back and used for limiting the position of the ferrule, and the lower end of the carrier tube (612) is also fixedly installed with a flexible clamp (616) that is symmetrical in front and back and used for limiting the position of the pipe, and the flexible clamp (616) is a special L-shaped setting; The auxiliary part (62) comprises a supporting rail (621), a third motor (622), a sliding clamp (623), a screw (624) and a fixed plate (625); the tube carrier tube (612) and the first carrier sleeve (613) are fixedly mounted with a supporting rail (621) located behind the flexible clamp (616) on the side; a screw (624) is mounted in the supporting rail (621) via a bearing; a sliding clamp (623) threadedly connected to the screw (624) is slidably mounted on the side of the supporting rail (621) close to the tube carrier tube (612); a third motor (622) whose output end is fixedly connected to the screw (624) is fixedly mounted on the supporting rail (621); a fixed plate (625) corresponding to the sliding clamp (623) is fixedly mounted on the right end of the supporting rail (621); a through groove is provided on the fixed plate (625); The alignment part (63) comprises an alignment rail (631), a fourth motor (632), a support slider (633), an alignment slide plate (634), a second electric push rod (635) and a tube pressing block (636); the front end surfaces of the pressing chamber (3), the first carrier sleeve (613) and the second carrier sleeve (615) are fixedly mounted with the alignment rail (631); the fourth motor (632) is fixedly mounted on the alignment rail (631); the alignment rail (631) is fixedly mounted with the fourth motor (632) through a bearing. 32) a second bidirectional screw fixedly connected to the output end, a support slider (633) symmetrically disposed on both sides and threadedly connected to the second bidirectional screw is slidably installed in the alignment slide rail (631), an alignment slide plate (634) is slidably installed on the lower end of the support slider (633) through a set slide column, a second electric push rod (635) whose telescopic end is fixedly connected to the alignment slide plate (634) is fixedly installed on the support slider (633), and a pipe pressing block (636) corresponding to the through groove is fixedly installed on the upper end surface of the alignment slide plate (634); The inner support part (64) comprises a connecting tube (641), a circular slide (642), a third electric push rod (643), an inner support groove (644), a pressure rod (645) and a limiting column (646); a connecting tube (641) is fixedly installed on one side wall of the tube-pushing block (636) close to each other; a circular slide (642) is slidably installed in the connecting tube (641); a third electric push rod (643) whose telescopic end is fixedly connected to the circular slide (642) is fixedly installed on the tube-pushing block (636); a plurality of inner support grooves (644) are penetrated through the connecting tube (641) in a circular array; a limiting column (646) is fixedly installed in the inner support groove (644); a pressure rod (645) corresponding to the inner support groove (644) is hinged on the circular slide (642); a limiting sliding hole is penetrated through the pressure rod (645) and is slidably connected to the limiting column (646).
2. According to claim 1, a building embedded sleeve integrated construction and installation equipment, Features: The pressing portion (52) comprises a pressing slide bar (521), a pressing block (522) and an alignment groove (523); a pressing slide bar (521) which is symmetrical on both sides and slides through the pressing bin (3) is fixedly installed on the side of the first slide plate (512) away from each other; a pressing block (522) is fixedly installed on the end of the pressing slide bar (521) away from the pressing bin (3); and an alignment groove (523) corresponding to the pressing block (522) is opened on the pressing bin (3).
3. The integrated construction and installation equipment for building embedded sleeves according to claim 2, Features: The correcting portion (53) comprises a matching groove (531), a torsion spring rod (532), a C-shaped push rod (533) and a rotation limiting block (534); a matching groove (531) is provided on a side wall of the pressure block (522) away from the pressure chamber (3); a torsion spring rod (532) which is symmetrical on both sides and passes through the lower end surface of the pressure block (522) is installed in the matching groove (531) through a bearing; a C-shaped push rod (533) is fixedly installed on the torsion spring rod (532); a rotation limiting block (534) located between the symmetrical torsion spring rods (532) is fixedly installed in the matching groove (531); and a push block for cooperating with the rotation limiting block (534) to limit the rotation angle of the torsion spring rod (532) is provided on the torsion spring rod (532).
Citation Information
Patent Citations
Foundation pit foundation reinforcing structure under complex working conditions and construction method thereof
CN117822602A
Fabricated auxiliary reinforcing steel bar correcting device for constructional engineering
CN219188454U