A vertical shaft ultra-deep drilling water exploration high-pressure water drive grouting construction method
Through ultra-long drilling detection and high-pressure water transfer grouting technology, combined with geophysical detection and geological radar method, the problem of water surge in the rock mass of high inclination angle in deep vertical shafts is solved, achieving more efficient water blocking effect and construction safety , reduces construction period and investment.
Patent Information
- Application Number
- CN202410875041.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-07-02
AI Technical Summary
In the construction of deep vertical shafts of metal mines, the sudden flood disaster caused by high inclination angle micro-crack rock mass is severely threatened, and the existing technology is difficult to accurately predict and block, which affects construction safety and construction period.
The ultra-long-section drilling detection method combined with geophysical exploration and geological radar method is used to conduct advanced geological anomaly detection, and targeted grouting drilling is designed, and the deep wellbore pressure water is sealed by high-pressure water-driving grouting technology, and pass through bedrock rock Cap and cushion reinforcement to improve drilling stability and water blocking effect.
It improves the accuracy and safety of drilling construction, reduces the construction quantity and construction period, effectively seals the pressure-bearing water in the deep wellbore, avoids the phenomenon of water from the well wall, and saves investment in well construction.
Smart Images

Figure CN118423080B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water prevention and control in deep shaft construction of metal mines, and in particular to a high-pressure water drive grouting construction method for ultra-deep drilling water exploration in a shaft. Background Art
[0002] During the shaft excavation process, the engineering geological environment below the working face is hidden, complex and changeable, so the shaft faces unknown risks during construction. Among them, underground water inrush is a more serious type of geological disaster in mine construction. As the shaft excavation depth increases, the ground stress increases, resulting in an increase in the pressure water level and head pressure. Compared with shallow water hazards, deep groundwater storage mainly has the characteristics of "high pressure, strong water and delayed large-scale water inrush", and the threat of water inrush disasters caused by high pressure and strong water environment is becoming increasingly serious. The complex hydrogeological conditions lead to complex factors, variable mechanisms, diverse types, and more influencing factors in the shaft water inrush disaster, which has become a huge challenge to the safe construction of shaft engineering.
[0003] The existence of water-bearing fractured rock strata poses a challenge to the smooth excavation of shafts. Due to the complexity of fracture distribution, especially high-inclination micro-cracks, it has become a key problem in the management of deep water-bearing fractured rock strata in shaft excavation working faces. In order to understand the distribution characteristics of water-bearing fractures, corresponding measures need to be taken to conduct advance detection of the excavation working face. The current detection methods are mainly divided into geophysical exploration and drilling. Due to the heterogeneity of rock strata and the interference of underground mechanical equipment, geophysical exploration methods cannot be effectively used. Drilling, as the most intuitive and accurate detection method in the advanced geological prediction of shafts, can understand or determine complex geological structures in advance, thereby mastering the prediction of deep joint fracture changes and water content in the shaft excavation working face.
[0004] The exploration and grouting of deep shaft construction in metal mines follows the general requirement of "resolutely preventing water exposure and water control" and implements the water prevention and control policy of "exploration before excavation" and "combination of exploration and grouting". The current methods of "exposure and water control", grouting of stop pads and short-segment alternating grouting for water blocking in shafts are complex and difficult to accurately judge the distribution of deep geological anomalies at the working face, which can easily cause sudden water inrush during shaft excavation, affecting the safety of construction personnel and the construction period of the shaft. Summary of the invention
[0005] In view of the defects existing in the existing construction technology, the purpose of the present invention is to provide a vertical shaft water exploration and high-pressure water drive grouting construction method based on ultra-long section drilling detection, so as to overcome the difficulties such as the inability to effectively block the water gushing from micro-cracks with high inclination angles due to unclear geological information at the depth of the excavation working face. The technical scheme of the present invention can not only reduce the number of water exploration and grouting drilling construction and the construction period, but also improve the accuracy of advance detection of the excavation working face and the safety of shaft construction, and improve the construction working environment.
[0006] In order to achieve the above object, the present invention provides the following technical solution: a vertical shaft ultra-deep drilling water exploration high-pressure water drive grouting construction method, comprising the following steps:
[0007] Step 1: Conduct geological survey on the shaft construction working face;
[0008] Step 2: Conduct geophysical exploration on the advanced water exploration grouting working surface;
[0009] Step 2.1: Clean the advanced water exploration and grouting working surface, conduct on-site assessment of the surrounding rock conditions of the wellbore, and if the surrounding rock of the wellbore is broken, carry out anchor net support; if the surrounding rock is intact and has no cracks, carry out geophysical exploration;
[0010] Step 2.2: Use transient electromagnetic method and geological radar method to detect geological anomalies in deep strata at the advanced water exploration grouting working face;
[0011] Step 3: Carry out preparatory work before water exploration grouting on the advanced water exploration grouting working surface;
[0012] Step 3.1: Set up a water collection pit on the advanced water exploration grouting working surface;
[0013] Step 3.2: Leave a bedrock cap and lay a cushion layer on the bedrock cap;
[0014] Step 3.3: construct a pressure relief hole in the surrounding rock of the advanced water exploration grouting working face, and bury the orifice pipe at the pressure relief hole;
[0015] Driving step 4: drilling an extra-long section of the advanced water exploration and grouting working face and grouting and flooding the water after drilling, wherein the extra-long section height is ≥100m;
[0016] Step 4.1: Lower the well lining template and fix the drilling rig;
[0017] Step 4.2: Based on the results of Step 1 and Step 2, design the layout of the advance water exploration grouting drilling holes and construct the positioning holes;
[0018] Step 4.3: bury the orifice pipe, reinforce the bedrock cap by grouting, and conduct water pressure test;
[0019] Step 4.4: construct an extra-long section of water exploration and grouting drilling holes, where the extra-long section height is ≥100m. During the construction process, observe the water discharge in the water exploration and grouting drilling holes at any time and record the construction information in a timely manner;
[0020] Step 4.5: When the water inflow from the water exploration grouting borehole is ≥ 2m 3 / h, stop drilling and use segmented downward pressure grouting. If the water inflow of the water exploration grouting borehole is less than 2m 3 / h, directly drill to the designed depth and then carry out grouting;
[0021] Step 4.6: After reaching the grouting completion standard, each water exploration grouting borehole is swept to the designed depth. If the water inflow is ≥2m 3 / h, grout is injected until the single-hole grouting completion standard is met, then grouting is stopped and maintenance is carried out;
[0022] Step 4.7: After the curing is completed, the same water pressure test as in step 4.3 is carried out. When the water volume is less than 20L / min, no more grouting is required and the next water exploration grouting borehole is drilled. Otherwise, re-grouting is required.
[0023] Step 5: Inspection and refilling of pre-grouting of shaft working face.
[0024] Compared with the prior art, the present invention has the following beneficial effects:
[0025] The present invention can be directly applied to the water exploration and grouting construction of deep shaft working faces in metal mines, with super-long section (section height ≥ 100m) drill holes used as water exploration holes and grouting holes at the same time to improve construction efficiency. The vertical shaft geological survey is combined with the geophysical prospecting method to jointly determine the distribution orientation of deep fractured aquifers in the vertical shaft excavation working face, guide the layout of water exploration holes, assist in super-long section drilling and water exploration, and provide a basis for targeted grouting and water blocking. At the same time, the grouting rock mass in the previous construction stage is used as the bedrock cap in the next construction stage, which can effectively save construction materials. For micro-fracture rock masses with high inclination angles and high-pressure water conditions, the different water gushing volumes of the boreholes are used as the basis for division, the timing of using different grouting materials is determined, and high-pressure water drive grouting is carried out to improve the slurry injection rate. High-pressure water grouting in ultra-long-section drilling and water exploration can modify the broken rock mass, improve the integrity and strength of the broken rock mass, and is beneficial to the water blocking and stability control of the deep broken water-bearing section of the wellbore. It can effectively block the pressurized water in the deep wellbore, and the effect is better than the grouting water blocking condition under the dynamic water conditions of "exposing water to control water". It can effectively prevent and control the phenomenon of water dripping on the well wall in the later stage of grouting, reduce the amount of grouting behind the wall and grouting of lining concrete, realize "dry drilling", shorten the well construction period, and save well construction investment. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a construction flow chart of the present invention;
[0027] Figure 2 A vertical cross-sectional schematic diagram of an embodiment of the present invention;
[0028] Figure 3 A schematic diagram of the working surface arrangement of an embodiment of the present invention;
[0029] Among them: 1. Well wall; 2. Pressure relief hole; 3. Sump; 4. Cushion layer; 5. Blasting disturbance area; 6. Bedrock cap; 7. Water exploration and grouting drilling hole. DETAILED DESCRIPTION
[0030] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the technical solutions adopted by the present invention are further described in detail below in conjunction with the embodiments and the accompanying drawings of the specification. The schematic implementation modes of the present invention and their description are only used to explain the present invention and are not intended to limit the present invention.
[0031] The present invention adopts ultra-long section (section height ≥ 100m) drilling and bedrock cap for water exploration and grouting, supplemented by vertical shaft geological survey and geophysical exploration, and mainly uses drilling as an advanced detection method to obtain engineering geological information such as the distribution of geological anomalies and rock integrity below the shaft working face, improve detection accuracy, achieve targeted grouting, and save well construction costs.
[0032] In this embodiment, a gold mine is constructing a vertical shaft and pre-grouting is performed on the granite aquifer working face. The shaft has a net diameter of 10.5m and a lining thickness of 500mm. Through the results of the vertical shaft engineering survey and drilling exploration, it is found that there is a fracture zone aquifer at the shaft elevation of -960m~-1140m. The built vertical shaft is located in the footwall of the fault zone. The structural fracture surface in the area runs through the entire rock mass with uneven density. Most of the rock mass fractures are micro-cracks with high inclination angles (60°-89°). The fracture zone aquifer belongs to the water-bearing section where the original bedrock structural fracture aquifer is depressurized due to mining.
[0033] like Figure 1-3 As shown, the present invention provides a vertical shaft ultra-deep drilling water exploration high-pressure water drive grouting construction method, comprising the following steps:
[0034] Step 1: Conduct geological survey on the shaft construction working face;
[0035] When the shaft is excavated to the first five construction cycles of the advanced water exploration and grouting working face, a geological survey of the shaft is carried out, and a compass is used to measure the occurrence of joints and fissures in the surrounding rock of the shaft, find out the development law of joints and fissures, and record the occurrence of the surrounding rock fissures and the location of the water outlet point;
[0036] In this embodiment, according to the investigation, it was found that the occurrence of joints and fissures on the working face of each excavation cycle continued to change, but the orientation of the local water outlet points in the wellbore was mostly found in the northeast and southeast parts of the wellbore, and no water outlets were found in other directions. Moreover, the joints and fissures at the water outlet points of the wellbore were oriented in the northeast or southeast direction, and the inclination angle was mostly above 60°.
[0037] Step 2: Conduct geophysical exploration on the advanced water exploration grouting working surface, which is specifically described as follows:
[0038] Step 2.1: Clean the advanced water exploration and grouting working surface, conduct on-site assessment of the surrounding rock conditions of the wellbore, and if the surrounding rock of the wellbore is broken, carry out anchor net support; if the surrounding rock is intact and has no cracks, carry out geophysical exploration;
[0039] In this embodiment, when anchor net support is performed, Φ22×2250mm resin anchor rods or pipe seam anchor rods can be used, the spacing between anchor rods is 1000×1000mm, and the metal net is made of Φ6 round steel welded, with a mesh size of 100×100mm;
[0040] Step 2.2: Use transient electromagnetic method and geological radar method to detect geological anomalies in deep strata at the advanced water exploration grouting working face;
[0041] In this embodiment, the detection depths of the transient electromagnetic method and the geological radar method are 60m and 30m respectively.
[0042] Step 3: Carry out preparatory work before water exploration grouting on the advanced water exploration grouting working surface, which is specifically described as follows:
[0043] Step 3.1: Set up a water collection pit 3 at the center of the advanced water exploration grouting working surface;
[0044] In this embodiment, after the geophysical exploration of the advance water exploration grouting working face is completed, an excavator is used to clean and level the construction working face, and a sump 3 is set at the center line of the wellbore. The size of the sump 3 is 1m×1m. By setting up the sump 3, all the water from the well side and the bottom can be led to the pump pit to facilitate drainage during construction.
[0045] Step 3.2: leaving a bedrock cap 6, and laying a cushion layer 4 on the bedrock cap 6;
[0046] The calculation basis for the thickness of the bedrock cap 6 is: the sum of the maximum thickness of the bedrock cap 6 when shear or tensile failure occurs under the action of grouting pressure and the range of the previous blasting disturbance zone 5, as shown in the above formula (1):
[0047] (1);
[0048] In formula (1): The thickness of the bedrock cap 6 (m);
[0049] is the thickness of the bedrock cap 6 calculated according to the shear strength of the rock mass (m);
[0050] is the thickness of the bedrock cap 6 calculated according to the tensile strength of the rock mass (m);
[0051] is the range of the previous blasting disturbance zone 5 (m), in this embodiment, ;
[0052] Furthermore, according to the shear stress failure theory, the thickness of the bedrock cap 6 calculated according to the shear strength of the rock mass can be obtained: , as shown in formula (2):
[0053] {B}_{\tau}=\frac {{P}_{0}D} {4\left [ {\tau} \right ]} (2);
[0054] In formula (2): is the final grouting pressure (MPa);
[0055] is the net diameter of the wellbore (m). ;
[0056] \left [ {\tau} \right ] is the allowable shear strength of rock (MPa), according to the rock strength coefficient When \left [ {\tau} \right ]=2.4\sim 2.8MPa In this embodiment, \left [ {\tau} \right ] = 2.8MPa ;
[0057] Furthermore, the final grouting pressure , determined according to the sum of the measured hydrostatic pressure in the grouting hole and the residual pressure of grouting, as shown in formula (3):
[0058] (3);
[0059] In formula (3): is the hydrostatic pressure at the grouting port (MPa);
[0060] is the residual pressure of grouting (MPa);
[0061] In this embodiment, ;
[0062] Furthermore, according to the tensile stress failure theory, the thickness of the bedrock cap 6 calculated according to the tensile strength of the rock mass can be obtained. , as shown in formula (4):
[0063] {B}_{t}=\frac {D} {2}\sqrt {\frac {3+\gamma} {\sqrt[{3}] {\frac {16\left ( {2+\gamma} \right ){\sigma}^{2}} {2{P}_{0}}-1}}} (4);
[0064] In formula (4): is the rock Poisson's ratio. ;
[0065] is the rock tensile strength (MPa). ;
[0066] According to formulas (1)-(4), the thickness of the bedrock cap 6 can be obtained as In this embodiment ;
[0067] After the bedrock cap 6 is set, a certain thickness of concrete is poured on the top of the bedrock cap 6 to form a cushion layer 4. The concrete for forming the cushion layer 4 is prepared on the ground and poured by a bottom-unloading bucket. During the pouring, continuous construction and enhanced vibration are required. In this embodiment, the concrete strength grade of the cushion layer 4 is C40, and the pouring thickness of the cushion layer 4 is 1.5m.
[0068] Step 3.3: construct a pressure relief hole 2 at the exposed well wall 1 of the advanced water exploration grouting working face to prevent the upper well wall 1 from being damaged by high-pressure grouting, and bury an orifice pipe at the pressure relief hole 2;
[0069] In this embodiment, before water exploration and grouting, multiple pressure relief holes 2 are constructed on the bare wall of the working face well wall 1. The spacing between the multiple pressure relief holes 2 is 4m, the hole depth is 5m, and the holes are drilled using a YT-28 type air drill with a Φ42mm "I" drill bit. When burying the orifice pipe, the specifications of the orifice pipe are: length 2m, diameter 42mm, and the pressure relief hole 2 is not grouting.
[0070] Step 4: Drilling of an extra-long section and grouting and water discharging after drilling is performed on the advanced water exploration and grouting working face. The extra-long section height is ≥100m. The specific expression is:
[0071] Step 4.1: Lower the well lining template and fix the drilling rig;
[0072] The shaft lining formwork is lowered to the advance water exploration and grouting working surface and fully expanded. Six Φ108 seamless steel pipes are used to support the lower end of the shaft lining formwork, and four ZDY1900S hydraulic drilling rigs are evenly fixed on the formwork.
[0073] Step 4.2: According to the results of step 1 and step 2, the layout position of the advanced water exploration grouting drilling hole 7 is designed, and the positioning hole is constructed;
[0074] In this embodiment, according to step 1, the geological survey results of the vertical shaft are sorted out and it is found that the orientation of the local water outlet of the shaft is mostly in the northeast or southeast of the shaft, and no water outlet is found in other directions;
[0075] According to the geophysical exploration results of step 2, the advance water exploration grouting working face has low resistance areas from south to east to north along the shaft at a depth of 40m. It is inferred that the low resistance areas within this range are connected, and the water-bearing areas far outside the shaft may recharge near the shaft.
[0076] The conclusions obtained by these two methods are used as the design basis for the water exploration and grouting drilling holes 7, and the advanced water exploration and grouting drilling holes 7 are arranged and drilled by drilling rigs;
[0077] According to the occurrence of joints and fissures obtained from the geological survey of the vertical shaft, the water exploration and grouting boreholes 7 are made to penetrate the high-angle (>60°) bedrock fissures as much as possible. The radial outward inclination angle arrangement method is adopted, the radial inclination angle of the borehole is 3°26′1″, the advance water exploration and grouting boreholes 7 are 0.5m away from the edge of the wellbore, the hole mouth spacing is 1.24m, the hole bottom spacing is 2.81m, and 28 water exploration and grouting boreholes 7 (including 4 inspection holes) are arranged.
[0078] Step 4.3: burying the orifice pipe, grouting to reinforce the bedrock cap 6, and conducting a water pressure test;
[0079] In this embodiment, the buried orifice pipe has the specifications of: Φ108mm×6mm seamless steel pipe, made of A3 steel, the length of the buried orifice pipe on the working face of the wellbore is 16m, the middle and lower parts are processed into an inverted fish scale structure, and the top of the pipe is connected with a high-pressure valve of model Q47N-250 using a flange to prevent water from bursting in the hole and close the water in time. The orifice pipe serves as a guide for drilling. A high-pressure ball valve is installed on the orifice pipe, which can be closed in time when water comes out, and is used to connect the orifice device during grouting;
[0080] The drilling rig is equipped with a Φ150mm impact drill bit to drill a hole. After drilling to a sufficient depth, the rock powder in the hole is blown away with compressed air. The auxiliary first, auxiliary second, main lifting hook or template rope is used to suspend a Φ108mm×6mm orifice pipe and bury it in the water exploration grouting borehole 7. The orifice pipe is exposed to the rock layer for about 500mm. Hemp silk is wrapped around the middle and lower part of the steel pipe before burying it.
[0081] Grouting reinforcement of bedrock cap 6, using a grouting pump of model 2TGZ-60 / 210 to fill the hole with fast-curing high-strength micro-expansion grouting material of model HNT-T1, and then stop grouting. After the slurry in the orifice pipe solidifies, use a drilling rig to sweep away the slurry in the orifice pipe, install a high-pressure ball valve and conduct a joint pressure test;
[0082] The water pressure test, i.e., the pressure resistance and permeability test, is carried out at a pressure of 18MPa (i.e., 1.2 times the final grouting pressure) to flush the fillings in the rock fissures, improve the bonding strength and anti-permeability of the slurry stone body and the rock fissure surface, and measure the amount of grouting absorbed by the borehole according to the pump pressure and injection volume. The pressure in the water pressure process is increased from small to large. When the pressure rises to a constant level and the water pressure flow rate of the grouting section decreases from large to small, the pressure of the grouting section at this time reaches the final pressure. If the pressure is stabilized for 10min to 20min without leakage, it is qualified. The height, flow rate and pressure of the water pressure section are accurately measured and recorded. The water absorption per unit borehole measured according to the water pressure time is used to determine the initial concentration of the slurry during grouting, which is used as one of the bases for identifying the grouting effect. Water exploration can be carried out only after passing the test. If the pressure test fails, the grouting machine is connected to use double liquid slurry (cement-water glass slurry) to grout the orifice pipe and the grouting rock cap for grouting reinforcement until the pressure test passes.
[0083] Step 4.4: construct an extra-long section of water exploration and grouting drilling hole 7, wherein the extra-long section height is ≥100m. During the construction process, observe the water discharge in the water exploration and grouting drilling hole 7 at any time, and record the construction information such as water pressure, water inflow and water temperature in a timely manner;
[0084] According to the actual engineering conditions on site, considering the thickness and hardness of the rock formation, the vertical height of the first-stage water exploration grouting borehole 7 is 100m. Since the next stage of water exploration grouting work is carried out when the rock mass grouting is completed and the remaining thickness is 20m, the vertical height of the water exploration grouting borehole 7 is extended to 120m. If the subsequent stages are carried out in the same way, the vertical height of the water exploration grouting borehole 7 becomes 120m.
[0085] After the water pressure test is qualified, the water exploration and grouting drilling hole 7 is constructed. Four ZDY1900S full hydraulic drilling rigs are used for construction. The 1# hole is in the west direction and is numbered clockwise. The drilling rig is fixed on the template, and after adjusting the angle, drilling is carried out. Before drilling, a comprehensive inspection should be made to see whether the installation of all components is accurate, whether the screws, nuts and joints of each part have been tightened, and whether the clamps are firmly and reliably clamped. There should be no leakage at the pipe joints. Use a Φ90mm drill bit to drill in a Φ108mm seamless steel pipe. First, push the drill with a small force to facilitate the positioning of the drill bit, and give an appropriate amount of water to reduce dust; when the drill bit has drilled about 100mm, drill with the full amount, and increase the propulsion force appropriately to carry out normal drilling work. After drilling a drill rod, stop the drilling rig and stop supplying water, so that the joint is disconnected from the drill rod, and then connect the second drill rod, and work continuously in this cycle;
[0086] During the construction of water exploration and grouting drilling 7, the water outflow in the borehole is observed at any time. After the aquifer is uncovered, the water inflow of the borehole is measured. If the water volume increases or decreases during drilling, the water volume must be measured in time, and the information on water inflow, water pressure, water temperature, drilling times, hole sweeping footage, and drilling depth must be recorded in time. Specific statistics are shown in Table 1:
[0087]
[0088] Step 4.5: When the water inflow of the water exploration grouting borehole 7 is ≥ 2m 3 / h, stop drilling and use segmented downward pressure grouting. If the water inflow of the water exploration grouting borehole 7 is less than 2m 3 / h, directly drill to the designed depth and then carry out grouting;
[0089] The grouting slurry used includes 1250 mesh ultrafine cement slurry and modified urea-formaldehyde resin slurry. It should be noted that different slurries are used according to the amount of water inflow from the water exploration grouting borehole 7 during the grouting process. 3 / h, use 1250 mesh ultrafine cement, the water-cement ratio is 1.0~2.0; when the water inflow of the water exploration grouting drilling hole 7 is less than 3m 3 / h, use modified urea-formaldehyde resin, press the prepared slurry into the grouting hole through the slurry suction pipeline, mud pump, slurry discharge pipeline and grouting device, and maintain after the grouting is completed;
[0090] When grouting each borehole, use thick slurry for the initial injection, and gradually reduce the slurry concentration during re-injection. However, each time grouting is performed, it is generally diluted first and then concentrated. When the slurry is in the stage of fracture precipitation and filling, if the pressure does not rise and the slurry volume does not decrease, the concentration should be gradually increased. On the contrary, if the pressure rises quickly and the volume decreases quickly, in order to ensure sufficient injection volume, the slurry concentration should be reduced in turn, and the slurry concentration should be adjusted according to the specific changes in slurry absorption and grouting pressure. Each change of slurry concentration generally lasts for no less than 50 minutes. When the injection volume and grouting pressure reach the design requirements, the orifice valve should be closed and the pressure relief valve should be opened, and the grouting machine and slurry pipe should be flushed with clean water for no less than 30 minutes.
[0091] Step 4.6: After reaching the grouting completion standard, each water exploration grouting borehole 7 is swept to the designed depth. If the water inflow is ≥ 2m 3 / h, grout is injected until the single-hole grouting completion standard is met, then grouting is stopped and maintenance is carried out;
[0092] In this embodiment, when the grouting pressure of each water exploration grouting borehole 7 reaches the designed final pressure value, the injection volume is less than 40L / min, and it is stable for more than 20min, and the water inflow of a single hole is less than 2m 3 / h, the single hole grouting end standard is met and the grouting is stopped. After the grouting is completed, in principle, the hole can be swept as long as the drill hole can be supported at the grouting section. Generally, it takes 8 hours to sweep the hole until the single hole grouting end standard is met and maintenance is carried out.
[0093] Step 4.7: After the curing is completed, the same water pressure test as in step 4.3 is carried out. When the water volume is less than 20L / min, no more grouting is required and the next water exploration and grouting borehole 7 is drilled. Otherwise, re-grouting is required.
[0094] Step 5: Inspection and refilling of pre-grouting at the shaft working face;
[0095] Inspection holes are used to inspect and refill the pre-grouting effect of the working face, so that the pre-grouting of the working face meets the grouting effect;
[0096] In this embodiment, different inspection holes are used to detect the grouting effect of the entire working surface. If the water inflow of the first inspection hole is ≥2m 3 / h, grout is injected until the single hole grouting end standard is met, then grouting is stopped and the hole is sealed. If the water inflow of the first inspection hole does not exceed 2m 3 / h, then seal the hole directly, and follow the same steps for the other three inspection holes. After the inspection, the holes should be sealed, and the sealing material should be cement-water glass double liquid slurry.
Claims
1. A vertical shaft ultra-deep drilling water exploration high-pressure water drive grouting construction method, characterized in that: The following steps are involved: Step 1: Conduct geological survey on the shaft construction working face; Step 2: Conduct geophysical exploration on the advanced water exploration grouting working surface; Step 3: Carry out preparatory work before water exploration grouting on the advanced water exploration grouting working surface; include: Step 3.1: Set up a water collection pit on the advanced water exploration grouting working surface; Step 3.2: Leave a bedrock cap and lay a cushion layer on the bedrock cap; The calculation basis for the thickness of the bedrock cap to be left is: the sum of the maximum thickness of the bedrock cap when it is sheared or stretched under the action of grouting pressure and the range of the previous blasting disturbance zone; Step 3.3: construct a pressure relief hole at the exposed well wall of the advanced water exploration grouting working face, and bury the orifice pipe at the pressure relief hole; Step 4: Drilling of an ultra-long section of the advanced water exploration and grouting working face and grouting and water discharging after drilling, wherein the ultra-long section has a height of ≥100m; including: Step 4.1: Lower the well lining template and fix the drilling rig; Step 4.2: Based on the results of Step 1 and Step 2, design the layout of the advance water exploration grouting drilling holes and construct the positioning holes; Step 4.3: bury the borehole pipe, grout the bedrock cap, and conduct a water pressure test to measure the amount of grouting absorbed by the borehole, determine the initial concentration of the grouting slurry, and test the grouting effect; Step 4.4: construct an extra-long section of water exploration and grouting drilling holes, where the extra-long section height is ≥100m. During the construction process, observe the water discharge in the water exploration and grouting drilling holes at any time and record the construction information in a timely manner; Step 4.5: When the water inflow from the water exploration grouting borehole is ≥ 2m 3 / h, stop drilling and use segmented downward pressure grouting. If the water inflow of the water exploration grouting borehole is less than 2m 3 / h, directly drill to the designed depth and then carry out grouting; Step 4.6: After reaching the grouting completion standard, each water exploration grouting borehole is swept to the designed depth. If the water inflow is ≥2m 3 / h, grout is injected until the single-hole grouting completion standard is met, then grouting is stopped and maintenance is carried out; Step 4.7: After the curing is completed, the same water pressure test as in step 4.3 is carried out. When the water volume is less than 20L / min, no more grouting is required and the next water exploration grouting borehole is drilled. Otherwise, re-grouting is required. Step 5: Inspection and refilling of pre-grouting of shaft working face.
2. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 1 is characterized in that: The step 2 comprises: Step 2.1: Clean the advanced water exploration and grouting working surface, conduct on-site assessment of the surrounding rock conditions of the wellbore, and if the surrounding rock of the wellbore is broken, carry out anchor net support; if the surrounding rock is intact and has no cracks, carry out geophysical exploration; Step 2.2: Use transient electromagnetic method and geological radar method to detect geological anomalies in deep strata at the advance water exploration grouting working face.
3. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 2 is characterized in that: The thickness of the bedrock cap reserved in step 3.2 is given by the following formula (1): (1); In formula (1): The thickness of the bedrock cap, m; is the thickness of the bedrock cap calculated according to the shear strength of the rock mass, m; is the thickness of the bedrock cap calculated according to the tensile strength of the rock mass, m; is the range of the disturbance zone of the previous blasting, m; According to the shear stress failure theory, the thickness of the bedrock cap calculated according to the shear strength of the rock mass can be obtained. , as shown in formula (2): (2); In formula (2): is the final grouting pressure, MPa; is the net diameter of the wellbore, m; is the allowable shear strength of rock, MPa; The final grouting pressure , determined by the sum of the measured hydrostatic pressure in the grouting hole and the residual pressure of grouting, as shown in the following formula (3): (3); In formula (3): is the hydrostatic pressure in the grouting hole, MPa; Grouting residual pressure, MPa; According to the tensile stress failure theory, the thickness of the bedrock cap calculated according to the tensile strength of the rock mass can be obtained. , as shown in the following formula (4): (4); In formula (4): is the rock Poisson's ratio; is the tensile strength of rock, MPa; According to formulas (1)-(4), the thickness of the bedrock cap can be obtained: .
4. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 3 is characterized in that: The construction information recorded in step 4.4 includes: water inflow, water pressure, water temperature, drilling times, hole sweeping footage, and drilling depth.
5. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 4 is characterized in that: The grouting slurry in step 4.5 includes 1250 mesh ultrafine cement slurry and modified urea-formaldehyde resin slurry. Different slurries are used according to the amount of water inflow from the water exploration grouting borehole during the grouting process. When the water inflow from the water exploration grouting borehole is ≥3m 3 / h, use 1250 mesh ultrafine cement, water-cement ratio is 1.0~2.0, when the water inflow of water exploration grouting drilling is less than 3m 3 / h, use modified urea-formaldehyde resin.
6. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 5 is characterized in that: The method for testing and replenishing the pre-grouting of the shaft working face in step 5 is: use different inspection holes to test the grouting effect of the entire working face. If the water inflow of the first inspection hole is ≥2m 3 / h, grout is injected until the single hole grouting end standard is met, then grouting is stopped and the hole is sealed. If the water inflow of the first inspection hole does not exceed 2m 3 / h, seal the hole directly and follow this step for the remaining inspection holes.
7. The vertical shaft ultra-deep drilling water exploration high-pressure water grouting construction method according to claim 6 is characterized in that: The detection depths of transient electromagnetic method and geological radar method in step 2.2 are 60m and 30m respectively.
8. The vertical shaft ultra-deep drilling water exploration high-pressure water flooding grouting construction method according to claim 7 is characterized in that: The geological survey of the vertical shaft in step 1 should be carried out before excavation to the advanced water exploration and grouting working face. A compass should be used to measure the occurrence of joints and fissures in the surrounding rock of the shaft to find out the development pattern of joints and fissures.