A municipal construction project construction management system

By setting the duration analysis of environmental and construction impact parameters in the municipal construction project construction management system, calculating and evaluating indexes and triggering early warnings, the problem of insufficient construction safety management in the existing technology is solved, and real-time monitoring of the construction environment and impact is achieved and early warning improve the efficiency and accuracy of construction safety management.

CN118446530BActive Publication Date: 2024-12-17ZHEJIANG QIANZHOU CONSTRUCTION GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410873969.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-02
Publication Date
2024-12-17
Estimated Expiration
2044-07-02

AI Technical Summary

Technical Problem

The existing municipal construction project construction management system has shortcomings in construction safety management, which is difficult to ensure safety during construction, and it is impossible to effectively collect and analyze environmental parameters such as harmful gases in the tunnel construction environment, resulting in the inability to trigger early warnings in a timely manner.

Method used

A municipal construction engineering construction management system was designed, including construction planning module, environmental analysis module, construction evaluation module, environmental early warning module and construction management module. By setting the duration of the tunnel environmental parameters, the environment and the environment during the construction cycle are The construction impact parameters are analyzed, the environmental safety assessment index and construction impact assessment index are calculated, and the environmental and construction warning signals are triggered based on the preset threshold, and the corresponding early warning and management steps are performed.

Benefits of technology

It realizes effective safety assessment of the tunnel construction environment and real-time monitoring of construction impact, improves the efficiency and accuracy of construction safety management, promptly triggers early warnings, and avoids adverse effects on the environment and personnel around the construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118446530B_ABST
    Figure CN118446530B_ABST
Patent Text Reader

Abstract

The invention discloses a municipal construction engineering construction management system, which relates to the technical field of municipal engineering; it comprises a construction planning module, an environmental analysis module, a construction evaluation module, an environmental early warning module and a construction management module; the invention sets a continuous period for collecting tunnel environmental parameters, and analyzes the tunnel environmental parameters before the start time point of construction on each day in the construction period, thereby obtaining an environmental safety evaluation index before the start time point of construction on each day in the construction period; according to the obtained environmental safety evaluation index, potential safety risks can be effectively prevented, and environmental early warning signals can be triggered in time, thereby improving the efficiency and accuracy of construction safety management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of municipal engineering, and in particular to a municipal construction engineering construction management system. Background Art

[0002] With the acceleration of urbanization, the scale and complexity of municipal construction projects are growing, especially tunnel projects. Traditional construction management methods can no longer meet the high standards of modern project management.

[0003] However, the construction management system in the prior art still has the following deficiencies in practical application:

[0004] There are deficiencies in construction safety management, which makes it difficult to ensure safety during the construction process. Environmental parameters such as harmful gases in the tunnel construction environment cannot be effectively collected and analyzed before the start of construction, so as to accurately assess the construction tunnel environment and trigger early warning based on the assessment results.

[0005] For this purpose, a municipal construction project construction management system is introduced. Summary of the invention

[0006] In view of this, the present invention provides a municipal construction project construction management system to solve the problems raised by the above background technology.

[0007] The purpose of the present invention can be achieved through the following technical solutions: A municipal construction project construction management system, comprising:

[0008] Construction planning module: input the construction schedule of the current municipal tunnel project, obtain the construction period of the current municipal tunnel project, and set the duration of collecting tunnel environmental parameters and construction influencing parameters; tunnel environmental parameters include harmful gas concentration and dust concentration; construction influencing parameters include construction noise and abnormal vibration;

[0009] Environmental analysis module: Analyze the tunnel environmental parameters for the set duration before the start time of each day of the construction cycle, thereby obtaining the environmental safety assessment index for the set duration before the start time of each day of the construction cycle. ; where i represents the number of each day in the construction period, i=1,2...k, k is the total number of construction days; preset environmental safety assessment index for each day The reference threshold index is recorded as ; If the display result before the construction start time on a certain day during the construction period is > , then the environmental early warning signal is triggered;

[0010] Construction evaluation module: Analyze the construction impact parameters for the set duration after the construction start time of each day in the construction cycle, thereby obtaining the construction impact evaluation index for the set duration after the construction start time of each day in the construction cycle. ; Preset construction impact assessment index for each day The reference threshold index is recorded as ; If the display result after the construction start time on a certain day during the construction period is > , then the construction early warning signal is triggered;

[0011] Environmental warning module: receives triggered environmental warning signals and executes corresponding steps;

[0012] Construction management module: receives triggered construction warning signals and executes corresponding steps.

[0013] In some embodiments, tunnel environmental parameters for a set duration before the start time of construction on each day of the construction period are analyzed, specifically:

[0014] Acquire the harmful gas concentration parameters within the set duration before the construction start time of the day, and number each type of harmful gas concentration parameter. The number is represented by e, where e=1,2...v, and v represents the total number of types of harmful gas concentration parameters collected;

[0015] Based on the concentration values ​​of the corresponding types of harmful gases at each time point within the set duration, a line graph of the concentration changes of the corresponding types of harmful gases within the set duration is constructed, the numerical points corresponding to the concentration values ​​at each time point within the set duration are drawn in the line graph, adjacent numerical points are connected to obtain concentration change lines, and the slopes of the concentration change lines in the concentration change line graph and the angles between the lines and the horizontal line are calculated. If the angle is an acute angle, the slope of the concentration change line is marked as a descending slope, and if the angle is an obtuse angle, the slope of the concentration change line is marked as an ascending slope;

[0016] Sum all the descending slopes and ascending slopes respectively to obtain the total descending value and the total ascending value of the corresponding type of harmful gas within the set duration, calculate the ratio between the total ascending value and the total descending value, and obtain the trend ratio of the corresponding type of harmful gas, which is recorded as ;

[0017] Further, the maximum and average values ​​of the concentration values ​​of the corresponding type of harmful gas at each time point within the set duration are taken as the peak concentration value and average concentration value of the corresponding type of harmful gas, and are recorded as and ;

[0018] According to formula (1) and (2) , the abnormal estimation of the corresponding type of harmful gas in the set duration before the start time of construction on the day is obtained through formula (1): ;in and They represent the maximum allowable value of the trend ratio of the corresponding type of harmful gas and the maximum allowable value of the concentration; ae, be and ce represent the trend ratio of the corresponding type of harmful gas. , peak concentration And the mean concentration The influence weight factor of the construction is obtained by formula (2) to obtain the overall abnormal evaluation value within the set duration before the current construction start time point. ;in Indicates abnormal estimates of various types of harmful gases The reference threshold value, Indicates abnormal estimates of various types of harmful gases The weight factor of influence.

[0019] In some embodiments, the environmental safety assessment index for a set duration before the construction start time point on each day of the construction period is obtained. , specifically:

[0020] Based on the dust concentration at each time point in the set continuous period before the start time of construction on the day, take the average of the dust concentration at each time point, use the average as the dust estimation value for the set continuous period before the start time of construction on the day, preset the reference threshold of dust concentration, and calculate the ratio between the dust estimation value and the reference threshold, and use the calculated ratio as the dust assessment value for the set continuous period before the start time of construction on the day ;

[0021] Based on the overall evaluation value of abnormalities within the set duration before the start time of construction on the day and dust assessment value , build an abnormal assessment model of the tunnel environment before the construction start time of the day;

[0022] The abnormal overall evaluation value within the set duration before the construction start time of the day is respectively and dust assessment value Draw a rectangular model for the length and width of the rectangle, use the drawn rectangular model as the abnormal assessment model of the tunnel environment before the start of construction on that day, calculate the area value of the abnormal assessment model, and use the calculated area value as the environmental safety assessment index for the set duration before the start of construction on that day .

[0023] In some embodiments, the construction influencing parameters for a set duration after the construction start time point on each day of the construction period are analyzed, specifically:

[0024] Obtain the construction noise and abnormal vibration for a set duration after the construction start time of the day; construct a noise change curve based on the construction noise for a set duration after the construction start time of the day, and draw the threshold line corresponding to the maximum allowable noise in the current tunnel construction environment in the noise change curve; fill the area enclosed by the curve and the threshold line with a shadow, and calculate the area and duration of each filled shadow area, and add up each group of area values ​​and duration respectively to obtain the total area value and total duration, which are marked as and ;

[0025] Count the number of vibrations within a set duration after the construction start time of the day, obtain the vibration amplitude of each vibration number, preset the threshold of the vibration amplitude, and based on the comparison result of the vibration amplitude of each vibration number with the threshold, mark the vibration number higher than the threshold as abnormal vibration, count the number of abnormal vibrations, and mark it as .

[0026] In some embodiments, the construction impact assessment index for a set duration after the construction start time point on each day of the construction period is obtained. , specifically:

[0027] According to the formula Perform weighted calculation to obtain the construction impact assessment index for the set duration after the construction starts on the day. ;in , as well as Represents the total area Total duration And the number of abnormal vibrations The allowed value of g1, g2 and g3 are the preset influence weight factors.

[0028] In some embodiments, receiving a triggered environmental warning signal and executing corresponding steps are specifically:

[0029] Extract the environmental safety assessment index corresponding to the triggering environmental warning signal , and calculate the corresponding reference threshold index The calculated difference is used as the grade evaluation index, and three groups of index value ranges of the grade evaluation index are preset. Each group of index value ranges is set to correspond to a risk level. The risk levels include general risk, medium risk and serious risk.

[0030] Match the grade assessment index calculated by the current triggering environmental warning signal with the preset three groups of index value ranges to obtain the risk level at the current construction start time;

[0031] If the risk level is general risk, firstly, an environmental abnormality signal is sent to the mobile terminal of the construction personnel to remind them that the current tunnel environment is abnormal and they should wear protective equipment, but no emergency measures are needed. The sensors deployed in the tunnel environment continuously collect and monitor the tunnel environment parameters during the construction process, send an adjustment signal to the mobile terminal of the manager, and establish a communication connection between the ventilation equipment in the tunnel environment and the mobile terminal of the manager. The manager can remotely adjust the ventilation equipment parameters deployed in the tunnel environment through the mobile terminal.

[0032] If the risk level is medium, an environmental hazard signal is first sent to the mobile terminals of the construction personnel to remind them that the current tunnel environment is abnormal and construction should be suspended. An inspection signal is also sent to the mobile terminals of the management personnel to inform the inspectors that a detailed inspection of the tunnel construction area will be carried out.

[0033] If the risk level is severe, a construction suspension signal is first sent to the mobile terminals of the construction workers to remind them to suspend construction activities completely, adjust the collection time interval of the sensors deployed in the tunnel environment, and continue monitoring until the tunnel environment conditions are controlled and improved.

[0034] In some embodiments, a triggered construction warning signal is received and corresponding steps are performed, specifically:

[0035] Extract the construction impact assessment index corresponding to the construction warning signal that triggers And calculate the corresponding reference threshold index The calculated difference is used as the impact assessment index, and three groups of index value ranges of the impact assessment index are preset. Each group of index value ranges is set to correspond to an impact level, and the impact levels include slight impact, major impact and severe impact;

[0036] The impact assessment index calculated by the current triggering construction warning signal is matched with the preset three groups of index value ranges to obtain the impact level at the current construction start time point;

[0037] If the impact level is slight, record the current construction impact assessment index. The alarm installed in the tunnel environment is triggered and the sound frequency set for the minor impact level is played to remind the construction personnel to reduce the subsequent construction speed and reduce the impact on the environment and personnel. After the construction is completed on the same day, the construction method is reviewed and whether measures need to be taken to mitigate the impact of subsequent construction;

[0038] If the impact level is a major impact level, the construction impact parameters in the subsequent construction process are monitored and analyzed on the basis of the minor impact level. If the construction impact parameters in the subsequent construction process still trigger the construction early warning signal, the corresponding steps of the severe impact level are executed;

[0039] If the impact level obtained is a severe impact level, the alarm installed in the tunnel environment will be triggered, and the sound frequency set for the severe impact level will be played, the remaining construction progress for the day will be suspended, and a maintenance signal will be sent to the manager's mobile terminal. After receiving the maintenance signal, the manager can search for maintenance personnel around the current tunnel construction environment with one click. The manager selects a suitable maintenance personnel and sends a search signal to the personnel's mobile terminal. After arriving at the tunnel construction environment, the personnel will check the construction equipment and determine the cause of the abnormality.

[0040] In some embodiments, one-click retrieval of maintenance personnel around the current tunnel construction environment is as follows:

[0041] With the current tunnel construction location as the center and the set distance as the radius, draw a circle, screen the maintenance personnel within the circle, and obtain the distance between them and the tunnel construction location. The person with the shortest distance is taken as the fastest arriving person, and further obtain the working hours and number of inspections of each maintenance personnel within the circle. The person with the longest working hours is taken as the longest staff member, and the person with the highest number of inspections is taken as the most experienced person. The fastest arriving person, the longest staff member, and the most experienced person are pushed to the mobile terminal of the manager, and then selected through the mobile terminal.

[0042] Compared with the prior art, the present invention has the following beneficial effects:

[0043] The present invention sets a continuous period for collecting tunnel environmental parameters and analyzes the tunnel environmental parameters before the start time of each day of the construction period, thereby obtaining an environmental safety assessment index before the start time of each day of the construction period. According to the obtained environmental safety assessment index, potential safety risks can be effectively prevented, and environmental early warning signals can be triggered in time, thereby improving the efficiency and accuracy of construction safety management.

[0044] The present invention obtains a construction impact assessment index by analyzing the influencing parameters of construction noise and abnormal vibration, and triggers a construction early warning signal through a preset reference threshold index, thereby realizing real-time monitoring and timely response of the construction process, thereby avoiding adverse effects on the surrounding environment of the construction, and also ensuring the safety of construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] Further details, features and advantages of the present application are disclosed in the following description of exemplary embodiments in conjunction with the accompanying drawings, in which:

[0046] Figure 1 It is a principle block diagram of the present invention;

[0047] Figure 2 It is a schematic diagram of a concentration variation line graph in the present invention;

[0048] Figure 3 It is a schematic diagram of the noise change curve in the present invention. DETAILED DESCRIPTION

[0049] Several embodiments of the present application will be described in more detail below with reference to the accompanying drawings so that those skilled in the art can implement the present application. The present application can be embodied in many different forms and purposes and should not be limited to the embodiments described herein. These embodiments are provided to make the present application comprehensive and complete, and to fully convey the scope of the present application to those skilled in the art. The embodiments do not limit the present application.

[0050] Unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by those of ordinary skill in the art to which this application belongs. It will be further understood that terms such as those defined in commonly used dictionaries should be interpreted as having a meaning consistent with their meaning in the relevant art and / or the context of this specification, and will not be interpreted in an idealized or overly formal sense unless explicitly defined as such herein.

[0051] See also Figure 1-Figure 3 As shown, a municipal construction project construction management system includes a construction planning module, an environmental analysis module, a construction assessment module, an environmental early warning module and a construction management module;

[0052] The construction planning module is used to input the construction schedule of the current municipal tunnel project, obtain the construction period of the current municipal tunnel project, and set the duration of collecting tunnel environmental parameters and construction influencing parameters; tunnel environmental parameters include harmful gas concentration and dust concentration; construction influencing parameters include construction noise and abnormal vibration;

[0053] Based on the current construction schedule of the municipal tunnel project, the construction start time of each day within the construction period is determined, and the sensors deployed in the tunnel environment are automatically activated to collect tunnel environment parameters for a set duration before the construction start time;

[0054] The environmental analysis module is used to analyze the tunnel environmental parameters for a set duration before the start time of each day of the construction cycle, thereby obtaining the environmental safety assessment index for a set duration before the start time of each day of the construction cycle. ; where i represents the number of each day in the construction period, i=1,2...k, k is the total number of construction days; preset environmental safety assessment index for each day The reference threshold index is recorded as ; The technical staff shall set the dynamically changing reference threshold index according to the relevant data such as construction progress, geological conditions and construction methods, and adjust the reference threshold index when the corresponding date is reached; if the display result before the construction start time on a certain day during the construction period is > , then the environmental early warning signal is triggered;

[0055] Obtain the harmful gas concentration parameters within the set duration before the start time of construction on the day, and number each type of harmful gas concentration parameter. The number is represented by e, where e=1,2...v, and v represents the total number of types of harmful gas concentration parameters collected; harmful gas concentrations include but are not limited to gas concentrations, carbon monoxide concentrations, and carbon dioxide concentrations, etc. The specific number of types is set by the technical staff;

[0056] Based on the concentration values ​​of the corresponding types of harmful gases at each time point within the set duration, a line graph of the concentration changes of the corresponding types of harmful gases within the set duration is constructed, the numerical points corresponding to the concentration values ​​at each time point within the set duration are drawn in the line graph, adjacent numerical points are connected to obtain concentration change lines, and the slopes of the concentration change lines in the concentration change line graph and the angles between the lines and the horizontal line are calculated. If the angle is an acute angle, the slope of the concentration change line is marked as a descending slope, and if the angle is an obtuse angle, the slope of the concentration change line is marked as an ascending slope;

[0057] It should be noted that according to Figure 2 , draw the horizontal line corresponding to the concentration change line, and calculate the angle constructed by the horizontal line and the concentration change line.

[0058] Sum all the descending slopes and ascending slopes respectively to obtain the total descending value and the total ascending value of the corresponding type of harmful gas within the set duration, calculate the ratio between the total ascending value and the total descending value, and obtain the trend ratio of the corresponding type of harmful gas, which is recorded as ;

[0059] By calculating the trend ratio of the corresponding type of harmful gas, it can reflect whether the change trend of the corresponding type of harmful gas within the set duration is an upward trend or a downward trend, thus preventing potential risks;

[0060] Further, the maximum and average values ​​of the concentration values ​​of the corresponding type of harmful gas at each time point within the set duration are taken as the peak concentration value and average concentration value of the corresponding type of harmful gas, and are recorded as and ;

[0061] According to formulas (1) and (2) , the abnormal estimation value of the corresponding type of harmful gas in the set duration before the construction start time of the day is obtained through formula (1): ;in and They represent the maximum allowable value of the trend ratio of the corresponding type of harmful gas and the maximum allowable value of the concentration; ae, be and ce represent the trend ratio of the corresponding type of harmful gas. , peak concentration And the mean concentration The influence weight factor is set according to the type of harmful gas; the overall abnormal assessment value within the set duration before the current construction start time is obtained through formula (2): ;in Indicates abnormal estimates of various types of harmful gases The reference threshold value, Indicates abnormal estimates of various types of harmful gases The specific value is set according to the type of harmful gas;

[0062] Based on the dust concentration at each time point within the set continuous period before the start time of construction on the day, take the average of the dust concentration at each time point, and use the average as the dust estimate within the set continuous period before the start time of construction on the day;

[0063] Preset a reference threshold for dust concentration and calculate the ratio between the dust estimate and the reference threshold. Use the calculated ratio as the dust assessment value for the set duration before the start of construction on the day. ;

[0064] Based on the overall evaluation value of abnormalities within the set duration before the start time of construction on the day and dust assessment value , build an abnormal assessment model of the tunnel environment before the construction start time of the day;

[0065] The overall abnormal evaluation value within the set duration before the construction start time of the day is respectively and dust assessment value Draw a rectangular model for the length and width of the rectangle, and use the drawn rectangular model as an abnormal assessment model of the tunnel environment before the start time of construction on that day;

[0066] Calculate the area value of the abnormal assessment model and set the environmental safety assessment index for the duration before the construction start time on the day. ;

[0067] In summary, a comprehensive assessment of tunnel environmental safety is provided by taking into account a variety of harmful gases and dusts. The complex data is converted into intuitive images by drawing a rectangular model. A quantitative environmental safety assessment index is provided by calculating the area value of the abnormal assessment model, which provides a quantitative basis for construction safety management.

[0068] The construction assessment module is used to analyze the construction impact parameters of the set duration after the construction start time point on each day of the construction cycle, thereby obtaining the construction impact assessment index of the set duration after the construction start time point on each day of the construction cycle. ; Preset construction impact assessment index for each day The reference threshold index is recorded as ; Technical personnel set dynamically changing reference threshold indexes based on relevant data such as geological conditions, construction methods, regional standards, and sensitivity of the surrounding environment, and adjust the reference threshold indexes when the corresponding date is reached; if the display result after the construction start time on a certain day during the construction period is > , then the construction early warning signal is triggered;

[0069] Obtain the construction noise and abnormal vibration for a set duration after the construction start time of the day; construct a noise change curve based on the construction noise for the set duration after the construction start time of the day;

[0070] Draw the threshold line corresponding to the maximum allowable noise of the current tunnel construction environment in the noise change curve; set it based on the regional standards and surrounding environmental sensitivity of the tunnel construction area; fill the area surrounded by the curve and the threshold line with shadows, and calculate the area and duration of each filled shadow area, and add up each group of area values ​​and duration to obtain the total area value and total duration, which are marked as and ;

[0071] Count the number of vibrations within a set duration after the construction start time of the day, obtain the vibration amplitude of each vibration number, preset the threshold of the vibration amplitude, and based on the comparison result of the vibration amplitude of each vibration number with the threshold, mark the vibration number higher than the threshold as abnormal vibration, count the number of abnormal vibrations, and mark it as ;

[0072] According to the formula Perform weighted calculation to obtain the construction impact assessment index for the set duration after the construction starts on the day. ;in , as well as Represents the total area Total duration And the number of abnormal vibrations The allowed value of g1, g2 and g3 are the preset influence weight factors;

[0073] The environmental warning module is used to receive the triggered environmental warning signal and execute corresponding steps; specifically:

[0074] Extract the environmental safety assessment index corresponding to the triggering environmental warning signal , and calculate the corresponding reference threshold index The calculated difference is used as the grade evaluation index, and three groups of index value ranges of the grade evaluation index are preset. Each group of index value ranges is set to correspond to a risk level. The risk levels include general risk, medium risk and serious risk.

[0075] The grade evaluation index calculated by the current triggering environmental warning signal is matched with the preset three groups of index value ranges to obtain the risk level at the current construction start time; the larger the grade evaluation index, the higher the matched risk level;

[0076] If the risk level is general risk, firstly, an environmental abnormality signal is sent to the mobile terminal of the construction personnel to remind them that the current tunnel environment is abnormal and they should wear protective equipment, but no emergency measures are needed. The sensors deployed in the tunnel environment continuously collect and monitor the tunnel environment parameters during the construction process, send an adjustment signal to the mobile terminal of the manager, and establish a communication connection between the ventilation equipment in the tunnel environment and the mobile terminal of the manager. The manager can remotely adjust the ventilation equipment parameters deployed in the tunnel environment through the mobile terminal.

[0077] If the risk level is medium, an environmental hazard signal is first sent to the mobile terminals of the construction personnel to remind them that the current tunnel environment is abnormal and construction is suspended. An inspection signal is also sent to the mobile terminals of the management personnel to inform the inspectors that a detailed inspection of the tunnel construction area will be carried out and corresponding measures will be taken according to the inspection results.

[0078] If the inspection result shows that construction is possible, the corresponding steps for general risks will be carried out. If the inspection result shows that construction is suspended, the sensors deployed in the tunnel environment will continuously collect and monitor the tunnel environment parameters during the construction process.

[0079] If the risk level is severe, a construction suspension signal is first sent to the mobile terminals of the construction workers to remind them to suspend all construction activities, adjust the collection time interval of the sensors deployed in the tunnel environment, and continue monitoring until the tunnel environment conditions are controlled and improved;

[0080] The construction management module is used to receive the triggered construction warning signal and execute the corresponding steps; specifically:

[0081] Extract the construction impact assessment index corresponding to the construction warning signal that triggers And calculate the corresponding reference threshold index The calculated difference is used as the impact assessment index, and three groups of index value ranges of the impact assessment index are preset. Each group of index value ranges is set to correspond to an impact level, and the impact levels include slight impact, major impact and severe impact;

[0082] The impact assessment index calculated by the current triggering construction warning signal is matched with the preset three groups of index value ranges to obtain the impact level at the current construction start time point;

[0083] If the impact level is slight, record the current construction impact assessment index. The alarm installed in the tunnel environment is triggered and the sound frequency set for the minor impact level is played to remind the construction personnel to reduce the subsequent construction speed and reduce the impact on the environment and personnel. After the construction is completed on the same day, the construction method is reviewed and whether measures need to be taken to mitigate the impact of subsequent construction;

[0084] If the impact level is a major impact level, the construction impact parameters in the subsequent construction process are monitored and analyzed on the basis of the minor impact level. If the construction impact parameters in the subsequent construction process still trigger the construction early warning signal, the corresponding steps of the severe impact level are executed;

[0085] If the impact level is a severe impact level, the alarm installed in the tunnel environment is triggered and the sound frequency set for the severe impact level is played. The remaining construction progress for the day is suspended and a maintenance signal is sent to the mobile terminal of the manager. After receiving the maintenance signal, the manager searches for maintenance personnel around the current tunnel construction environment with one click. The manager selects a suitable maintenance personnel and sends a search signal to the mobile terminal of the personnel. After the personnel arrives at the tunnel construction environment, they check the construction equipment and determine the cause of the abnormality.

[0086] The specific process of one-key retrieval is as follows:

[0087] Draw a circle with the current tunnel construction location as the center and the distance as the radius, screen the maintenance personnel within the circle, and obtain the distance between them and the tunnel construction location. The person with the shortest distance is regarded as the fastest arriving person. Further obtain the working hours and number of inspections of each maintenance personnel within the circle, and regard the person with the longest working hours as the longest staff member, and the person with the highest number of inspections as the most experienced person. The fastest arriving person, the longest staff member, and the most experienced person are pushed to the mobile terminal of the manager, and then selected through the mobile terminal;

[0088] The construction management module is also provided with a dynamic adjustment unit, which is used to send a completion assessment signal to the mobile terminal of the manager one day before the construction period and execute corresponding steps;

[0089] Specifically:

[0090] After receiving the completion assessment signal, the manager will assess the progress of the current municipal tunnel project and provide feedback on the assessment results. If the feedback assessment result is a delay in completion, the estimated number of days for delayed completion will be pushed to fill in the interface. After the manager completes the filling, a construction analysis signal is sent to the manager's mobile terminal. After the manager confirms the construction analysis signal, the monitoring video of the surrounding environment of the current municipal tunnel project is extracted. The monitoring video is a driving video of the surrounding roads.

[0091] Fill in the results based on the estimated days of the managers, and match the filled-in estimated days from Monday to Sunday to obtain the construction dates for each future day;

[0092] If the first day of the estimated days is Tuesday, the driving video of Tuesday seven days in advance is divided into X sub-periods according to the preset division period, X>5, and the specific division period is set by the technical personnel; the traffic flow in the driving video of each sub-period is obtained, and the traffic flow of the corresponding sub-period in the past seven days is averaged to obtain the traffic flow estimation of the sub-period; based on the size of the traffic estimation, the divided sub-periods are sorted, the smaller the traffic estimation, the higher the ranking, and the top three sub-periods are selected as the preferred construction period for the first day of the estimated days, and pushed; similarly, the remaining dates of the estimated days are analyzed accordingly, and integrated into a delayed completion period optimization table and sent to the mobile terminal of the management personnel;

[0093] Through the analysis and sorting of traffic flow, it helps managers select the optimal construction period, improves construction efficiency, and reduces construction interruptions caused by traffic interference;

[0094] The above formulas are obtained by collecting a large amount of data and performing software simulation, and a formula close to the actual value is selected. The influencing weight factor and specific coefficient value in the formula are set by technical personnel in this field according to actual conditions, and can be adjusted and modified later.

[0095] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A municipal construction project construction management system, characterized in that: include: Construction planning module: input the construction schedule of the current municipal tunnel project, obtain the construction period of the current municipal tunnel project, and set the duration of collecting tunnel environmental parameters and construction influencing parameters; tunnel environmental parameters include harmful gas concentration and dust concentration; construction influencing parameters include construction noise and abnormal vibration; Environmental analysis module: Analyze the tunnel environmental parameters for the set duration before the start time of each day of the construction cycle, thereby obtaining the environmental safety assessment index for the set duration before the start time of each day of the construction cycle. ; where i represents the number of each day in the construction period, i=1,2...k, k is the total number of construction days; preset environmental safety assessment index for each day The reference threshold index is recorded as ; If the display result before the construction start time on a certain day during the construction period is > , then the environmental early warning signal is triggered; The tunnel environmental parameters for the set duration before the start time of construction on each day of the construction period are analyzed, specifically: Acquire the harmful gas concentration parameters within the set duration before the construction start time of the day, number each type of harmful gas concentration parameter, and the number is represented by e, where e=1,2...v, and v represents the total number of types of harmful gas concentration parameters collected; Based on the concentration values ​​of the corresponding types of harmful gases at each time point within the set duration, a line graph of the concentration changes of the corresponding types of harmful gases within the set duration is constructed, the numerical points corresponding to the concentration values ​​at each time point within the set duration are drawn in the line graph, adjacent numerical points are connected to obtain concentration change lines, and the slopes of the concentration change lines in the concentration change line graph and the angles between the lines and the horizontal line are calculated. If the angle is an acute angle, the slope of the concentration change line is marked as a descending slope, and if the angle is an obtuse angle, the slope of the concentration change line is marked as an ascending slope; Sum all the descending slopes and ascending slopes respectively to obtain the total descending value and the total ascending value of the corresponding type of harmful gas within the set duration, calculate the ratio between the total ascending value and the total descending value, and obtain the trend ratio of the corresponding type of harmful gas, which is recorded as ; Further, the maximum and average values ​​of the concentration values ​​of the corresponding type of harmful gas at each time point within the set duration are taken as the peak concentration value and average concentration value of the corresponding type of harmful gas, and are recorded as and ; According to formulas (1) and (2) , the abnormal estimation of the corresponding type of harmful gas in the set duration before the start time of construction on the day is obtained through formula (1): ;in and They represent the maximum allowable value of the trend ratio of the corresponding type of harmful gas and the maximum allowable value of the concentration; ae, be and ce represent the trend ratio of the corresponding type of harmful gas. , peak concentration And the mean concentration The influence weight factor of the construction is obtained by formula (2) to obtain the overall abnormal evaluation value within the set duration before the current construction start time point. ;in Indicates abnormal estimates of various types of harmful gases The reference threshold value, Indicates abnormal estimates of various types of harmful gases The impact weight factor of Get the environmental safety assessment index for the set duration before the construction start time of each day in the construction cycle , specifically: Based on the dust concentration at each time point in the set continuous period before the start time of construction on the day, take the average of the dust concentration at each time point, use the average as the dust estimation value for the set continuous period before the start time of construction on the day, preset the reference threshold of dust concentration, and calculate the ratio between the dust estimation value and the reference threshold, and use the calculated ratio as the dust assessment value for the set continuous period before the start time of construction on the day ; Based on the overall evaluation value of abnormalities within the set duration before the start time of construction on the day and dust assessment value , build an abnormal assessment model of the tunnel environment before the construction start time of the day; The abnormal overall evaluation value within the set duration before the construction start time of the day is respectively and dust assessment value Draw a rectangular model for the length and width of the rectangle, use the drawn rectangular model as the abnormal assessment model of the tunnel environment before the start of construction on that day, calculate the area value of the abnormal assessment model, and use the calculated area value as the environmental safety assessment index for the set duration before the start of construction on that day ; Construction evaluation module: Analyze the construction impact parameters for the set duration after the construction start time of each day in the construction cycle, thereby obtaining the construction impact evaluation index for the set duration after the construction start time of each day in the construction cycle. ; Preset construction impact assessment index for each day The reference threshold index is recorded as ; If the display result after the construction start time on a certain day during the construction period is > , then the construction early warning signal is triggered; Environmental warning module: receives triggered environmental warning signals and executes corresponding steps; Construction management module: receives triggered construction warning signals and executes corresponding steps.

2. A municipal construction project construction management system according to claim 1, characterized in that: The construction influencing parameters of the set duration after the construction start time of each day in the construction period are analyzed, specifically: Obtain the construction noise and abnormal vibration for a set duration after the construction start time of the day; construct a noise change curve based on the construction noise for a set duration after the construction start time of the day, and draw the threshold line corresponding to the maximum allowable noise in the current tunnel construction environment in the noise change curve; fill the area enclosed by the curve and the threshold line with a shadow, and calculate the area and duration of each filled shadow area, and add up each group of area values ​​and duration respectively to obtain the total area value and total duration, which are marked as and ; Count the number of vibrations within a set duration after the construction start time of the day, obtain the vibration amplitude of each vibration number, preset the threshold of the vibration amplitude, and based on the comparison result of the vibration amplitude of each vibration number with the threshold, mark the vibration number higher than the threshold as abnormal vibration, count the number of abnormal vibrations, and mark it as .

3. A municipal construction project construction management system according to claim 2, characterized in that: Get the construction impact assessment index for the set duration after the construction start time on each day of the construction period , specifically: According to the formula Perform weighted calculation to obtain the construction impact assessment index for the set duration after the construction starts on the day. ;in , as well as Represents the total area Total duration And the number of abnormal vibrations The allowed value of g1, g2 and g3 are the preset influence weight factors.

4. A municipal construction project construction management system according to claim 1, characterized in that: Receive the triggered environmental warning signal and execute corresponding steps, specifically: Extract the environmental safety assessment index corresponding to the triggering environmental warning signal , and calculate the corresponding reference threshold index The calculated difference is used as the grade evaluation index, and three groups of index value ranges of the grade evaluation index are preset. Each group of index value ranges is set to correspond to a risk level. The risk levels include general risk, medium risk and serious risk. Match the grade assessment index calculated by the current triggering environmental warning signal with the preset three groups of index value ranges to obtain the risk level at the current construction start time; If the risk level is general risk, firstly, an environmental abnormality signal is sent to the mobile terminal of the construction personnel to remind them that the current tunnel environment is abnormal and they should wear protective equipment, but no emergency measures are needed. The sensors deployed in the tunnel environment continuously collect and monitor the tunnel environment parameters during the construction process, send an adjustment signal to the mobile terminal of the manager, and establish a communication connection between the ventilation equipment in the tunnel environment and the mobile terminal of the manager. The manager can remotely adjust the ventilation equipment parameters deployed in the tunnel environment through the mobile terminal. If the risk level is medium, an environmental hazard signal is first sent to the mobile terminals of the construction personnel to remind them that the current tunnel environment is abnormal and construction should be suspended. An inspection signal is also sent to the mobile terminals of the management personnel to inform the inspectors that a detailed inspection of the tunnel construction area will be carried out. If the risk level is severe, a construction suspension signal is first sent to the construction workers' mobile terminals to remind them to suspend construction activities completely, adjust the collection time interval of the sensors deployed in the tunnel environment, and continue monitoring until the tunnel environment conditions are controlled and improved.

5. A municipal construction project construction management system according to claim 1, characterized in that: Receive the triggered construction warning signal and execute corresponding steps, specifically: Extract the construction impact assessment index corresponding to the construction warning signal that triggers And calculate the corresponding reference threshold index The calculated difference is used as the impact assessment index, and three groups of index value ranges of the impact assessment index are preset. Each group of index value ranges is set to correspond to an impact level, and the impact levels include slight impact, major impact and severe impact; The impact assessment index calculated by the current triggering construction warning signal is matched with the preset three groups of index value ranges to obtain the impact level at the current construction start time point; If the impact level is slight, record the current construction impact assessment index. The alarm installed in the tunnel environment is triggered and the sound frequency set for the minor impact level is played to remind the construction personnel to reduce the subsequent construction speed and reduce the impact on the environment and personnel. After the construction is completed on the same day, the construction method is reviewed and whether measures need to be taken to mitigate the impact of subsequent construction; If the impact level is a major impact level, the construction impact parameters in the subsequent construction process are monitored and analyzed on the basis of the minor impact level. If the construction impact parameters in the subsequent construction process still trigger the construction early warning signal, the corresponding steps of the severe impact level are executed; If the impact level obtained is a severe impact level, the alarm installed in the tunnel environment will be triggered, and the sound frequency set for the severe impact level will be played, the remaining construction progress for the day will be suspended, and a maintenance signal will be sent to the manager's mobile terminal. After receiving the maintenance signal, the manager can search for maintenance personnel around the current tunnel construction environment with one click. The manager selects a suitable maintenance personnel and sends a search signal to the personnel's mobile terminal. After arriving at the tunnel construction environment, the personnel will check the construction equipment and determine the cause of the abnormality.

6. A municipal construction project construction management system according to claim 5, characterized in that: One-click search for maintenance personnel around the current tunnel construction environment, specifically: With the current tunnel construction location as the center and the set distance as the radius, draw a circle, screen the maintenance personnel within the circle, and obtain the distance between them and the tunnel construction location. The person with the shortest distance is taken as the fastest arriving person, and further obtain the working hours and number of inspections of each maintenance personnel within the circle. The person with the longest working hours is taken as the longest staff member, and the person with the highest number of inspections is taken as the most experienced person. The fastest arriving person, the longest staff member, and the most experienced person are pushed to the mobile terminal of the manager, and then selected through the mobile terminal.