A chassis bracket automatic suspension point welding equipment
By designing automatic suspension point welding equipment, using motor-driven gears and air pressure to drive arc-shaped bends, automatic welding of chassis brackets is realized, which solves the problems of cumbersome operation and low efficiency of existing equipment, and improves welding efficiency and stability.
Patent Information
- Application Number
- CN202410939223.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-15
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2044-07-15
AI Technical Summary
The existing automatic suspension point welding equipment for chassis brackets is cumbersome to operate, has low efficiency, and requires a lot of manual operations, resulting in reduced welding efficiency and an increased risk of missed welds.
An automatic suspension point welding equipment including a frame, a support column, a placement plate, a shroud, a shaft feed barrel, an arc-shaped bend pipe and a power mechanism is designed. The gear mechanism is driven by a motor to achieve intermittent rotation, and the pistons are driven by air pressure. Cylinder and arc-shaped bent pipe, automatically complete the positioning and welding operation of the welding head, reducing manual intervention.
It improves the welding efficiency, reduces the tedious operation, realizes the automated welding process, reduces the risk of missed welding, and improves the production efficiency.
Smart Images

Figure CN118455826B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of welding equipment, and in particular to automatic suspension point welding equipment for a chassis bracket. Background Art
[0002] Automobile chassis parts often require hanging point welding. The usual operation is that the equipment is fixed and the parts are picked up manually. The hanging point welding in different positions is achieved by rotating or moving the parts. The operation is labor-intensive and inefficient. The position of the welding hanging point is affected by the individual's proficiency. There is also a risk of missing welds, which requires a 100% full inspection process to prevent it.
[0003] The prior art publication number CN212793706U is a tool for automatic suspension point welding of chassis brackets, comprising a base plate, a tool assembly is mounted on the base plate, the tool assembly comprises a middle positioning block, two side positioning blocks and a clamping block that cooperate with each other, the middle positioning block is fixedly mounted on the base plate through a middle positioning mounting support plate, the two side positioning blocks comprise a positioning block 1 and a positioning block 2, the positioning block 1 is fixedly mounted on the base plate through a positioning support block, a liftable positioning pin 1 is mounted on the end of the positioning block 1, the clamping block is an inverted L-shaped structure, which is evenly distributed around the cross-shaped clamping block mounting bracket, the clamping block mounting bracket is connected by a clamping block cylinder driving block on one side thereof, the clamping block cylinder driving block is driven by a clamping cylinder at its bottom end, and a positioning pin 2 is fixedly mounted on the end of the positioning block 2; it has simple operation, low manufacturing cost, high production efficiency, and does not require professional welder operation, and the suspension point position of the produced product is fixed without quality defects such as leaking welds.
[0004] The deficiency of the above-mentioned prior art is that, when in use, the external electrical controller is pressed to drive the switch to open the clamp, the parts are placed into the positioning pins for positioning, and the start key is pressed again to position the positioning pins. After welding is completed, the clamp is opened to remove the welded parts, and then the parts are placed again, etc. The operation is cumbersome and very inconvenient. Only when the parts are removed after welding can the next welding work be carried out, which reduces the welding efficiency. For this reason, the present application proposes an automatic suspension point welding device for chassis brackets. Summary of the invention
[0005] The purpose of the present invention is to solve the above technical problems and to propose an automatic suspension point welding device for a chassis bracket.
[0006] In order to achieve the above object, the present invention adopts the following technical solutions:
[0007] A chassis bracket automatic suspension point welding device comprises a frame, the inner bottom of the frame is rotatably connected to a support column that can rotate intermittently, the upper end of the support column is installed with a placement plate, the upper end of the placement plate is provided with a plurality of placement slots, the bottom of the placement plate is penetrated by a through slot connected to the placement slot, the inner top of the frame is installed with a guide cover, the guide cover is provided with an axis-type feeding barrel that passes through the upper end of the frame and is fixedly connected thereto, the outer side of the axis-type feeding barrel is provided with a first hollow ring that does not interfere with each other, the interior of the first hollow ring is rotatably connected to a connected second hollow ring, the outer wall of the second hollow ring is installed with a plurality of arc-shaped bent pipes, the bottom of the second hollow ring is installed with a welding head, and the inner top of the frame is installed with a power mechanism that drives the first hollow ring, the second hollow ring and the welding head to move.
[0008] Preferably, it includes a driving mechanism for driving the support column to rotate intermittently, the driving mechanism includes a motor mounted on a frame, the output end of the motor is fixedly connected to a short shaft, a first gear is fixed on the support column, a second gear is mounted on the short shaft, the first gear is meshed with the second gear, and the second gear is an incomplete gear.
[0009] Preferably, it also includes a power-on mechanism, which includes a first piston cylinder fixed at the bottom of the frame, a first movable piston slidably connected in the first piston cylinder, a first spring fixed between the first movable piston and the first piston cylinder, an insulating column fixed on the first movable piston, and a power connection block fixedly connected to the insulating column.
[0010] Preferably, it also includes a clamping mechanism, which includes a second piston cylinder installed on the frame, a second movable piston is slidably connected in the second piston cylinder, a second spring is fixed between the second movable piston and the second piston cylinder, a connecting rod is fixed on the second movable piston, and a clamping block is fixed on the connecting rod.
[0011] Preferably, the power mechanism includes a third piston cylinder installed on the top of the frame, a third movable piston is slidably connected in the third piston cylinder, an L-shaped tube is passed through the third movable piston and fixedly connected to it, the L-shaped tube is connected to the first hollow ring, and a pressure relief valve is installed on the L-shaped tube.
[0012] Preferably, it also includes an air supply mechanism for supplying air to the first piston cylinder, the second piston cylinder and the third piston cylinder, the air supply mechanism includes an air supply piston cylinder fixed on the frame, an air supply movable piston is slidably connected in the air supply piston cylinder, a connecting rod is hingedly connected to the air supply movable piston, a circular plate is fixed to the upper end of the short shaft, the connecting rod is eccentrically hinged to the upper end of the circular plate, an air intake pipe is installed on the air supply piston cylinder, an air intake check valve is installed on the air supply piston cylinder, the air supply piston cylinder is connected to the second piston cylinder through a delivery pipe, the second piston cylinder is connected to the first piston cylinder through a connecting pipe, and the delivery pipe is connected to the third piston cylinder through a branch pipe.
[0013] Preferably, the air intake check valve only allows air to enter the air supply piston cylinder through the air intake pipe.
[0014] Preferably, an annular groove is provided on the second hollow ring, and the annular groove divides the second hollow ring into an upper part and a lower part, the upper part is fixedly connected to the inner wall of the first hollow ring, and the lower part is rotatably connected to the inner wall of the first hollow ring, and a short tube is fixed on the first hollow ring, and the short tube passes through the annular groove.
[0015] Compared with the prior art, the present invention has the following beneficial effects:
[0016] 1. Air is delivered to the third piston cylinder through the delivery pipe and the branch pipe. The pressure in the third piston cylinder increases, thereby driving the third movable piston to move downward. The downward movement of the third movable piston drives the L-shaped tube, the first hollow ring, and the second hollow ring to move downward. The welding head abuts against the bottom of the shaft workpiece, completing the positioning of the welding head.
[0017] 2. When air is delivered to the first piston cylinder and the second piston, the second movable piston is driven to move first, and the second movable piston drives the connecting rod and the clamping block to move. Finally, the chassis bracket is abutted against the inner wall of the placement groove and cannot move, thereby realizing the positioning of the chassis bracket, making it difficult to move and requiring no manual operation. At this time, the shaft workpiece is abutted against the welding point of the chassis bracket.
[0018] 3. As the air continues to be transported through the delivery pipe, the air pressure in the first piston cylinder increases, thereby driving the first movable piston to move upward. The upward movement of the first movable piston drives the insulating column and the power block to move upward. The power block moves upward through the through groove, and finally the power block abuts against the chassis bracket, forming a circuit between the power block and the welding head to facilitate welding work.
[0019] 4. The air pressure in the third piston cylinder increases, and the air pressure is greater than the threshold of the pressure relief valve. The pressure relief valve opens, and the air is transported to the first hollow ring through the L-shaped tube, and then transported to the second hollow ring through the short tube. The air in the second hollow ring is ejected through the arc-shaped elbow. Since the ejected air receives air resistance, the arc-shaped elbow can be pushed to move. The movement of the arc-shaped elbow drives the lower part of the second hollow ring to rotate slowly. The rotation of the second hollow ring drives the welding head to rotate. At this time, the relay controls the welding head to be energized. The rotation of the welding head can weld the shaft workpiece to the chassis bracket.
[0020] 5. The air supply piston moves back, and the air in the first piston cylinder, the second piston cylinder and the third piston cylinder can be sucked into the air supply piston cylinder to reset the pressing block, the power block and the welding head, so as to rotate the placement plate without manual adjustment.
[0021] 6. The first gear and the second gear are meshed to drive the placement plate to rotate again, and this reciprocating process can be used to intermittently weld the chassis bracket and shaft workpieces, thereby improving the welding efficiency.
[0022] To sum up, the first gear and the second gear of the present invention are intermittently meshed, which can drive the placement plate to rotate intermittently, and so on, so that the chassis bracket and the shaft workpiece can be intermittently welded, thereby improving the welding efficiency and avoiding the disadvantage of low welding efficiency caused by the cumbersome and inconvenient operation of the prior art, in which the next welding work can only be carried out after the welding is removed. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 This is a schematic diagram of the structure of an automatic suspension point welding device for a chassis bracket proposed by the present invention;
[0024] Figure 2 This is a rear view of an automatic suspension point welding device for a chassis bracket proposed by the present invention;
[0025] Figure 3 A side view of an automatic suspension point welding device for a chassis bracket proposed by the present invention;
[0026] Figure 4 A schematic diagram of the structure of a chassis bracket automatic suspension point welding device proposed by the present invention with a deflector removed;
[0027] Figure 5 This is a schematic diagram of the structure of the third piston cylinder in the automatic suspension point welding equipment for chassis brackets proposed by the present invention;
[0028] Figure 6 This is a schematic structural diagram of a first piston cylinder in an automatic suspension point welding device for a chassis bracket proposed by the present invention;
[0029] Figure 7This is a schematic structural diagram of a second hollow ring in an automatic suspension point welding device for a chassis bracket proposed by the present invention.
[0030] In the figure: 1 frame, 2 shaft-type feeding cylinder, 3 conveying pipe, 4 branch pipe, 5 guide cover, 6 air supply piston cylinder, 7 support column, 8 first piston cylinder, 9 connecting pipe, 10 motor, 11 short shaft, 12 first gear, 13 second gear, 14 round plate, 15 connecting rod, 16 placement plate, 17 placement groove, 18 through groove, 19 insulating column, 20 power connection block, 21 air supply movable piston, 22 second piston cylinder, 23 tight block, 24 air intake pipe, 25 air intake check valve, 26 annular groove, 27 third piston cylinder, 28 L-shaped pipe, 29 first hollow ring, 30 arc elbow, 31 welding head, 32 first spring, 33 first movable piston, 34 second movable piston, 35 second spring, 36 connecting rod, 37 third movable piston, 38 pressure relief valve, 39 second hollow ring, 40 short pipe. DETAILED DESCRIPTION
[0031] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0032] Reference Figure 1-Figure 7 A chassis bracket automatic suspension point welding device includes a frame 1, the inner bottom of the frame 1 is rotatably connected to a support column 7 that can rotate intermittently, and includes a driving mechanism that drives the support column 7 to rotate intermittently, and the driving mechanism includes a motor 10 installed on the frame 1, and the output end of the motor 10 is fixedly connected to a short shaft 11, a first gear 12 is fixed on the support column 7, and a second gear 13 is installed on the short shaft 11. The first gear 12 is meshed with the second gear 13, and the second gear 13 is an incomplete gear. Since the second gear 13 is an incomplete gear, the second gear 13 is intermittently meshed with the first gear 12, thereby driving the first gear 12 and the support column 7 to rotate intermittently.
[0033] A clip connected to an electric wire is clamped on the welding object and connected to the welding rod on the welding gun, so as to short-circuit the metal object to be welded and form a loop through the secondary winding of the electric welder, so that the electric welder can weld the metal object; for this purpose, it is necessary to jog the accessories, and for this purpose, it also includes a jog mechanism, which includes a first piston cylinder 8 fixed at the bottom of the frame 1, a first movable piston 33 is slidably connected in the first piston cylinder 8, a first spring 32 is fixed between the first movable piston 33 and the first piston cylinder 8, an insulating column 19 is fixed on the first movable piston 33, and a power connection block 20 is fixedly connected to the insulating column 19, the chassis bracket is placed in the placement groove 17, and the power connection block 20 is abutted against the chassis bracket through the through groove 18.
[0034] A placement plate 16 is installed on the upper end of the support column 7. A plurality of placement grooves 17 are provided on the upper end of the placement plate 16. A through groove 18 connected to the placement groove 17 is penetrated through the bottom of the placement plate 16. After the chassis bracket is placed in the placement groove 17, in order to ensure the stability of welding, it also includes a clamping mechanism. The clamping mechanism includes a second piston cylinder 22 installed on the frame 1. A second movable piston 34 is slidably connected in the second piston cylinder 22. A second spring 35 is fixed between the second movable piston 34 and the second piston cylinder 22. The elastic force of the second spring 35 is less than the elastic force of the first spring 32. A connecting rod 36 is fixed on the second movable piston 34. A clamping block 23 is fixed on the connecting rod 36. The clamping block 23 moves to abut against the chassis bracket in the placement groove 17, so as to clamp and position it.
[0035] A flow guide cover 5 is installed on the inner top of the frame 1, and a shaft feeding barrel 2 is provided inside the flow guide cover 5, which passes through the upper end of the frame 1 and is fixedly connected thereto. A first hollow ring 29 that does not abut against each other is provided on the outside of the shaft feeding barrel 2. The inside of the first hollow ring 29 is rotatably connected to a connected second hollow ring 39. The shaft workpiece slides against the inner wall of the second hollow ring 39, and the second hollow ring 39 can be used to guide and limit the shaft workpiece so that it will not deviate.
[0036] The outer wall of the second hollow ring 39 is provided with a plurality of arc-shaped curved pipes 30, the bottom of the second hollow ring 39 is provided with a welding head 31, the second hollow ring 39 is provided with an annular groove 26, the annular groove 26 divides the second hollow ring 39 into an upper part and a lower part, the upper part is fixedly connected to the inner wall of the first hollow ring 29, and the lower part is rotatably connected to the inner wall of the first hollow ring 29, and a short pipe 40 is fixed to the first hollow ring 29, and the short pipe 40 passes through the annular groove 26. Figure 7 shown.
[0037] A power mechanism for driving the first hollow ring 29, the second hollow ring 39 and the welding head 31 to move is installed at the inner top of the frame 1. The power mechanism includes a third piston cylinder 27 installed at the inner top of the frame 1. A third movable piston 37 is slidably connected in the third piston cylinder 27. The third movable piston 37 is penetrated by an L-shaped tube 28 fixedly connected to it. The L-shaped tube 28 is connected to the first hollow ring 29, and a pressure relief valve 38 is installed on the L-shaped tube 28.
[0038] It also includes an air supply mechanism for supplying air to the first piston cylinder 8, the second piston cylinder 22, and the third piston cylinder 27. The air supply mechanism includes an air supply piston cylinder 6 fixed on the frame 1, and an air supply movable piston 21 is slidably connected in the air supply piston cylinder 6. A connecting rod 15 is hingedly connected to the air supply movable piston 21. A circular plate 14 is fixed to the upper end of the short shaft 11, and the connecting rod 15 is eccentrically hingedly connected to the upper end of the circular plate 14. An air intake pipe 24 is installed on the air supply piston cylinder 6, and an air intake check valve 25 is installed on the air intake pipe 24. The air intake check valve 25 only allows air to enter the air supply piston cylinder 6 through the air intake pipe 24. The air supply piston cylinder 6 is connected to the second piston cylinder 22 through the delivery pipe 3, the second piston cylinder 22 is connected to the first piston cylinder 8 through the connecting pipe 9, and the delivery pipe 3 is connected to the third piston cylinder 27 through the branch pipe 4.
[0039] When the present invention is used, the staff puts the chassis bracket in the placement groove 17, and then starts the motor 10. The motor 10 drives the short shaft 11 and the second gear 13 to rotate, and the second gear 13 rotates to drive the first gear 12 to rotate. Figure 2 As shown, there are four placement slots 17, and the second gear 13 drives the first gear 12 to rotate at an angle of 90°, and the second gear 13 is not engaged with the first gear 12, that is, the support column 7 and the placement plate 16 remain stationary at this time;
[0040] It should be noted that the placement groove 17 is set according to the shape of the chassis bracket and when the chassis bracket is placed in the placement groove 17, the upper end of the chassis bracket is flush with the upper end of the placement plate 16. When the staff places the shaft parts in the shaft feeding barrel 2, the shaft parts are against the upper end of the placement plate 16 due to gravity. Therefore, when the placement plate 16 drives the shaft parts to move, it will not cause the shaft parts to interfere with the chassis bracket and make it unable to rotate;
[0041] The rotation of the short shaft 11 drives the circular plate 14 to rotate, and the circular plate 14 drives the connecting rod 15 and the air supply movable piston 21 to move back and forth. At this time, the air supply movable piston 21 moves close to the motor 10, and the air in the first piston cylinder 8, the second piston 22 and the third piston cylinder 27 can be sucked into the air supply piston cylinder 6 through the delivery pipe 3 and the branch pipe 4, and part of the air enters the air supply piston cylinder 6 through the air intake pipe 24; when the air supply movable piston 21 moves away from the motor 10, the air in the air supply piston cylinder 6 can be delivered to the first piston cylinder 8, the second piston cylinder 22 and the third piston cylinder 27 through the delivery pipe 3 and the branch pipe 4;
[0042] Due to the setting of the first spring 32 and the second spring 35, the first movable piston 33 and the second movable piston 34 are not easy to move, and the air is transported to the third piston cylinder 27 through the delivery pipe 3 and the branch pipe 4. The pressure in the third piston cylinder 27 increases, thereby driving the third movable piston 37 to move downward, and the downward movement of the third movable piston 37 drives the L-shaped tube 28, the first hollow ring 29, and the second hollow ring 39 to move downward, and finally the welding head 31 is against the bottom of the shaft workpiece. It should be noted that a limit block can be fixed in the third piston cylinder 27. When the welding head 31 is against the bottom of the shaft workpiece, the third movable piston 37 is against the limit block at this time, that is to say, the third movable piston 37 cannot move downward at this time, and then the welding head 31 cannot move downward, which will not cause the welding head 31 to be squeezed and damaged;
[0043] Since the elastic force of the second spring 35 is smaller than the elastic force of the first spring 32, when the air is delivered to the first piston cylinder 8 and the second piston cylinder 22, the second movable piston 34 is first driven to move, and the second movable piston 34 drives the connecting rod 36 and the abutting block 23 to move. Finally, the chassis bracket abuts against the inner wall of the placement groove 17 and cannot move, so as to realize the positioning of the chassis bracket, making it difficult to move, and no manual operation is required. At this time, the welding part of the shaft workpiece and the chassis bracket abuts against each other;
[0044] As the air continues to be transported through the delivery pipe 3, the air pressure in the first piston cylinder 8 increases, thereby driving the first movable piston 33 to move upward, and the first movable piston 33 moves upward to drive the insulating column 19 and the power block 20 to move upward, and the power block 20 moves upward through the through groove 18, and finally the power block 20 abuts against the chassis bracket, and a circuit is formed between the power block 20 and the welding head 31. A relay can be installed between the circuit of the power block 20 and the welding head 31, that is, after the power block 20 forms a circuit with the welding head 31, it works after a period of time. The specific time control is as follows:
[0045] Since the power connection block 20 and the abutting block 23 cannot move, the air supply moving piston 21 continues to squeeze the air for delivery. Since the welding head 31 cannot move downward, as the air pressure in the third piston cylinder 27 increases, the air pressure is greater than the threshold of the pressure relief valve 38, and the pressure relief valve 38 opens. The air is delivered to the first hollow ring 29 through the L-shaped tube 28, and then delivered to the second hollow ring 39 through the short tube 40. The air in the second hollow ring 39 is ejected through the arc-shaped elbow 30. Since the ejected air receives the resistance of the air, the arc-shaped elbow 30 can be pushed to move. The movement of the arc-shaped elbow 30 drives the lower part of the second hollow ring 39 to rotate slowly. A metal spring can be installed on the upper cover of the first hollow ring 29. A rubber sheet is fixed on the metal spring. The rubber sheet abuts against the second hollow ring 39 to limit it and prevent it from rotating quickly.
[0046] The second hollow ring 39 rotates to drive the welding head 31 to rotate. At this time, the relay controls the welding head 31 to be energized. The welding head 31 rotates to weld the shaft workpiece on the chassis bracket. After one round of welding, the welding head 31 is de-energized.
[0047] At this time, the air supply moving piston 21 moves back, that is, moves closer to the motor 10, and the air in the first piston cylinder 8, the second piston 22 and the third piston cylinder 27 can be sucked into the air supply piston cylinder 6, so as to realize the reset of the abutting block 23, the power connection block 20 and the electric welding head 31. At this time, the upper end of the shaft workpiece is lower than the lower end of the second hollow ring 39, so that the shaft workpiece will not be hindered from following the movement of the chassis bracket after welding;
[0048] Then the first gear 12 and the second gear 13 are meshed, and the placing plate 16 is driven to rotate again, and this reciprocating process can be used to intermittently weld the chassis bracket and the shaft workpiece, thereby improving the welding efficiency;
[0049] When the welded chassis bracket moves in front of the staff, there will be a period of time when the first gear 12 and the second gear 13 are not engaged, and the placement plate 16 is stationary, so that the staff can remove the welded chassis bracket and then place the chassis bracket to be welded, which is more convenient.
[0050] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A chassis bracket automatic suspension point welding device, comprising a frame (1), characterized in that: The inner bottom of the frame (1) is rotatably connected to a support column (7) capable of intermittent rotation, the upper end of the support column (7) is mounted with a placement plate (16), the upper end of the placement plate (16) is provided with a plurality of placement grooves (17), the bottom of the placement plate (16) is penetrated by a through groove (18) connected to the placement grooves (17), the inner top of the frame (1) is mounted with a flow guide cover (5), the flow guide cover (5) is provided with a shaft-type material supply cylinder (2) penetrating the upper end of the frame (1) and fixedly connected thereto The shaft-type material supply cylinder (2) is provided with a non-aggressive first hollow ring (29) on the outside, the first hollow ring (29) is rotatably connected to a connected second hollow ring (39) on the inside, a plurality of arc-shaped curved pipes (30) are installed on the outer wall of the second hollow ring (39), a welding head (31) is installed on the bottom of the second hollow ring (39), and a power mechanism for driving the first hollow ring (29), the second hollow ring (39) and the welding head (31) to move is installed on the inner top of the frame (1); It also includes a power-on mechanism, the power-on mechanism comprising a first piston cylinder (8) fixed to the bottom of the frame (1), a first movable piston (33) slidably connected inside the first piston cylinder (8), a first spring (32) fixed between the first movable piston (33) and the first piston cylinder (8), an insulating column (19) fixed on the first movable piston (33), and a power connection block (20) fixedly connected to the insulating column (19); The device also comprises a clamping mechanism, the clamping mechanism comprising a second piston cylinder (22) mounted on the frame (1), a second movable piston (34) being slidably connected inside the second piston cylinder (22), a second spring (35) being fixed between the second movable piston (34) and the second piston cylinder (22), a connecting rod (36) being fixed on the second movable piston (34), and a clamping block (23) being fixed on the connecting rod (36); The power mechanism comprises a third piston cylinder (27) mounted on the top of the frame (1), a third movable piston (37) being slidably connected in the third piston cylinder (27), an L-shaped tube (28) being passed through the third movable piston (37) and fixedly connected thereto, the L-shaped tube (28) being connected to the first hollow ring (29), and a pressure relief valve (38) being mounted on the L-shaped tube (28); The invention also comprises an air supply mechanism for supplying air to the first piston cylinder (8), the second piston cylinder (22) and the third piston cylinder (27), the air supply mechanism comprising an air supply piston cylinder (6) fixed on the frame (1), an air supply movable piston (21) being slidably connected in the air supply piston cylinder (6), a connecting rod (15) being hingedly connected to the air supply movable piston (21), and a driving mechanism for driving the support column (7) to rotate intermittently, the driving mechanism comprising a motor (10) mounted on the frame (1), a short shaft (11) being fixedly connected to the output end of the motor (10), a first gear (12) being fixed on the support column (7), and a second gear (15) being mounted on the short shaft (11). 13), the first gear (12) is meshed with the second gear (13), and the second gear (13) is an incomplete gear, a circular plate (14) is fixed to the upper end of the short shaft (11), the connecting rod (15) is eccentrically hingedly connected to the upper end of the circular plate (14), an intake pipe (24) is installed on the air supply piston cylinder (6), an intake check valve (25) is installed on the intake pipe (24), the air supply piston cylinder (6) is connected to the second piston cylinder (22) through a delivery pipe (3), the second piston cylinder (22) is connected to the first piston cylinder (8) through a connecting pipe (9), and the delivery pipe (3) is connected to the third piston cylinder (27) through a branch pipe (4); The second hollow ring (39) is provided with an annular groove (26), the annular groove (26) dividing the second hollow ring (39) into an upper part and a lower part, the upper part is fixedly connected to the inner wall of the first hollow ring (29), and the lower part is rotatably connected to the inner wall of the first hollow ring (29), and a short tube (40) is fixed to the first hollow ring (29), and the short tube (40) is arranged to penetrate the annular groove (26).