Self-correction processing method based on photovoltaic optimizer

By analyzing the difference between the historical data of photovoltaic modules and the optimizer control signal, combined with the transmission distance and equipment temperature, the length of time for the optimizer control signal to be sent in advance is calculated, which solves the problem of late pursuit of the maximum power point in the photovoltaic optimizer and achieves Fast response and efficient tracking of photovoltaic modules.

CN118484059BActive Publication Date: 2024-10-08JIANG SU MAI KE ZHI HUI NENG YUAN YOU XIAN GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410555214.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-07
Publication Date
2024-10-08
Estimated Expiration
2044-05-07

AI Technical Summary

Technical Problem

The difference in the time when the photovoltaic optimizer control signal is sent causes the photovoltaic module operating point to change at different times, resulting in a delay in tracking the maximum power point, a time delay, and difficulty in achieving fast tracking.

Method used

By analyzing the difference between the historical operating point change time of photovoltaic modules and the optimizer control signal adjustment time, the standard delay time of each component is calculated, and combined with the transmission distance and equipment temperature, the optimizer control signal is sent in advance to calculate the time for self-correction Control signal sending time.

Benefits of technology

The delay time of the optimizer control signal transmission is reduced, the maximum power point of the photovoltaic module is quickly tracked, and the tracking efficiency and response speed are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118484059B_ABST
    Figure CN118484059B_ABST
Patent Text Reader

Abstract

The invention discloses a self-correction processing method based on a photovoltaic optimizer, and relates to the technical field of photovoltaic optimizers. The method comprises the following steps: step one: obtaining the historical working point change moment of each photovoltaic module and the corresponding optimizer control signal adjustment moment; step two: analyzing the difference between the historical working point change moment of each photovoltaic module and the corresponding optimizer control signal adjustment moment, and obtaining the standard delay time corresponding to each photovoltaic module, thereby solving the technical problem that the control signal cannot chase the maximum power point in time due to the different change moments of the working points of different photovoltaic modules, and it is difficult to realize the rapid tracking of the maximum power point of the photovoltaic module; and performing self-correction processing on the sending time of the photovoltaic optimizer control signal according to the advance sending time of the optimizer control signal, so as to reduce the delay time of the sending of the optimizer control signal, and realize the adaptive correction of the control signal.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of photovoltaic optimizers, and in particular to a self-correction processing method based on a photovoltaic optimizer. Background Art

[0002] In a photovoltaic system, a photovoltaic array is usually formed by connecting multiple components in series and parallel. Due to the inconsistency of the electrical parameters of the components in series and parallel, partial shading or damage of the strings, the system output power is reduced, which is professionally called "mismatch loss". It will affect the power generation of the power station to varying degrees;

[0003] The photovoltaic optimizer monitors the connected photovoltaic modules in real time to determine the optimal working point of the current module, that is, the maximum power point (MPP). The optimizer adjusts the working voltage and current of the module through the internal DC / DC converter to make the module work at the maximum power point. Since the series modules need to maintain the same current, when the working point of a module changes due to mismatch, the optimizer can independently adjust the output of the module to reduce the power loss of the entire string.

[0004] The patent publication number CN115933805A discloses a self-correcting photovoltaic optimizer, including: a converter module, a regulating module, a driving module and a sampling module; wherein the first end of the converter module is connected to an input voltage end, the second end of the converter module is connected to the input end of the sampling module, the output end of the sampling module is connected to the first end of the regulating module, the second end of the regulating module is connected to the input voltage end, the third end of the regulating module is connected to the input end of the driving module, the first output end of the driving module is connected to the fourth end of the regulating module, the second output end of the driving module is connected to the third end of the converter module, and the second end of the converter module is also connected to an output voltage end; the regulating module is configured to: determine the maximum output power according to the current output power, and output a first reference voltage; the first reference voltage is characterized as the input voltage corresponding to the maximum output power,

[0005] However, the photovoltaic optimizer tracks the maximum power point of the photovoltaic module according to the MPPT voltage range of the photovoltaic optimizer. Due to the different times when the photovoltaic optimizer control signals are sent, the working points of different photovoltaic modules change at different times, resulting in untimely tracking of the maximum power point by the control signal. There is a time delay, and it is difficult to achieve rapid tracking of the maximum power point of the photovoltaic module. Based on this, a self-correction processing method based on the photovoltaic optimizer is proposed. Summary of the invention

[0006] The purpose of the present invention is to provide a self-correction processing method based on a photovoltaic optimizer, which solves the technical problem that due to the different times of sending control signals of the photovoltaic optimizer, the changing times of the working points of different photovoltaic modules are different, resulting in the control signal not being able to chase the maximum power point in time, there is a time delay, and it is difficult to quickly track the maximum power point of the photovoltaic module.

[0007] The purpose of the present invention can be achieved by the following technical solutions:

[0008] The self-correction processing method based on the photovoltaic optimizer includes the following steps:

[0009] Step 1: Obtain the historical operating point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time;

[0010] Step 2: Analyze the difference between the historical working point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time to obtain the standard delay time corresponding to each photovoltaic module:

[0011] Step 3: Analyze the transmission distance between each PV module and the optimizer in combination with the standard delay time corresponding to each PV module to obtain the distance correlation coefficient between the optimizer and the PV module;

[0012] Step 4: Perform correlation analysis on the device temperature corresponding to each control signal adjustment moment of the optimizer and the standard delay time corresponding to each photovoltaic module to obtain the temperature correlation coefficient between the optimizer and the device temperature;

[0013] Step 5: According to the transmission distance between the PV module and the optimizer with the change of the working point and the corresponding distance correlation coefficient and the corresponding real-time device temperature of the optimizer, the advance sending time of the optimizer control signal is obtained.

[0014] As a further solution of the present invention, a specific method for obtaining the standard delay time corresponding to each photovoltaic module between the optimizer and each photovoltaic module is as follows:

[0015] S1: designate an analysis component from each photovoltaic component, obtain the difference Yn between the working point change moment of the analysis component for a preset number of times n and the corresponding optimizer control signal adjustment moment, and use the mode in Yn as the standard delay time B1 corresponding to the analysis component, where n is greater than or equal to 1;

[0016] S2: Repeat step S1 to obtain the standard delay time Bn corresponding to each photovoltaic module.

[0017] As a further solution of the present invention: a specific method for obtaining the distance correlation coefficient between the optimizer and the photovoltaic module is:

[0018] S01: Obtain the transmission distance between each photovoltaic module and the optimizer, and mark it as Ln;

[0019] S02: Take the transmission distance Ln between each PV module and the optimizer as the horizontal coordinate, and take the standard delay time Bn corresponding to each PV module as the vertical coordinate, draw the scatter plot corresponding to the PV module, and obtain the correlation value G between the PV module delay time and the corresponding distance between the optimizer through the correlation formula, and compare and analyze it with 0.58 or -0.58 to obtain the distance correlation coefficient H1 between the optimizer and the PV module.

[0020] As a further solution of the present invention: when the correlation value G is greater than 0.58 or less than -0.58, the standard delay times D1 and D2 corresponding to the maximum and minimum values ​​of the transmission distances Ln between each photovoltaic module and the optimizer are obtained, and then according to the formula: H1=(D1-D2) / (Lmax-Lmin), the distance correlation coefficient H1 corresponding to the optimizer and the photovoltaic module is calculated, wherein Lmax is the maximum value in Ln and Lmin is the minimum value in Ln; when the correlation value G is less than or equal to -0.58 and greater than or equal to 0.58, no processing is performed.

[0021] As a further solution of the present invention: obtaining the temperature correlation coefficient corresponding to the optimizer temperature and the device temperature, the specific method is:

[0022] The same analysis method as that used in steps S01-S02 to obtain the distance correlation coefficient between the optimizer and the photovoltaic module is adopted to perform correlation analysis on the delay duration Wb corresponding to the optimizer at each analysis temperature value and each analysis temperature value Fb, and based on the analysis results, obtain the temperature correlation coefficient M1 corresponding to the optimizer and the equipment temperature.

[0023] As a further solution of the present invention: the method of obtaining each analysis temperature of the optimizer is:

[0024] The temperature state values ​​corresponding to the control signal adjustment moments of the optimizer at the preset number of j times are obtained, and the temperature values ​​that meet the preset condition Q1 are obtained as the analysis temperature value Fb, where b is the number corresponding to the analysis temperature value, b≥1.

[0025] As a further solution of the present invention: the specific method of obtaining the delay time corresponding to each analysis temperature value of the optimizer is:

[0026] Obtain a preset number of optimizer control signal adjustments of the optimizer at each analysis temperature value, which correspond to the optimizer control signal adjustment moment and the corresponding working point change moment, and obtain the difference between the two. At the same time, take the average of the differences in a optimizer control signal adjustments at each analysis temperature value as the delay time Wb corresponding to the optimizer at each analysis temperature value, a≥1.

[0027] As a further solution of the present invention: the preset condition Q1 is specifically: the temperature state value corresponding to the temperature state value having a maintenance time longer than the preset value T1 is used as the analysis temperature value.

[0028] As a further solution of the present invention: the specific method of obtaining the advance sending duration of the optimizer control signal is:

[0029] According to the formula K-[K×(H1×V)+(M1×U)]=R3, the corresponding optimizer compensation duration R3 is calculated. When R3 is a positive value, the value corresponding to R3 is used as the advance sending duration Q3 of the optimizer control signal. When R3 is less than or equal to 0, no processing is performed. V is the transmission distance between the PV module with the change of the working point and the optimizer, U is the real-time device temperature corresponding to the optimizer, and K is the calculation duration.

[0030] As a further solution of the present invention: the specific method of obtaining the calculation duration is:

[0031] The average of the standard delay time lengths Bn corresponding to each photovoltaic module is used as the calculation time length K.

[0032] Beneficial effects of the present invention:

[0033] The present invention performs self-correction processing on the sending time of the photovoltaic optimizer control signal according to the advance sending time of the optimizer control signal when the working points of different photovoltaic modules change, so as to reduce the delay time of the optimizer control signal sending, realize adaptive correction of the control signal, and quickly track the maximum power point of each photovoltaic module. The optimizer adjusts the sending time of the control signal according to the transmission distance between the optimizer and the photovoltaic module and the device temperature of the optimizer, thereby reducing the time delay of the optimizer control signal sending, realizing a quick response to the change of the working point of the photovoltaic module, and improving the efficiency of tracking the maximum power point. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] The present invention will be further described below in conjunction with the accompanying drawings.

[0035] Figure 1 It is a schematic diagram of the framework structure of the self-correction processing method based on the photovoltaic optimizer of the present invention. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] See also Figure 1 As shown, the present invention is a self-correction processing method based on a photovoltaic optimizer, comprising the following steps:

[0038] Step 1: obtaining the historical operating point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time from the data storage terminal;

[0039] The data storage end is used to use the sensors and monitoring systems built into the PV modules and optimizers to record and store the change time of the working point of each PV module and the adjustment time of the optimizer control signal to ensure the accuracy of the data timestamp for subsequent time alignment and analysis;

[0040] Step 2: Analyze and calculate the difference between the historical working point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time, and obtain the standard delay time corresponding to the optimizer and each photovoltaic module. The specific method is:

[0041] S1: designate any one of the photovoltaic modules as an analysis module;

[0042] S2: Obtain the working point change time of the analysis component for a preset number of times n and the corresponding optimizer control signal adjustment time, and obtain the corresponding difference between the two, which is used as the delay time corresponding to each of the analysis component in the preset number of times, and marked as Yn, where n refers to the historical number of times from the moment of obtaining data, and n is greater than or equal to 1, where n=160;

[0043] S3: taking the mode of the delay duration Yn corresponding to each of the preset times of the analysis component as the standard delay duration B1 corresponding to the optimizer and the analysis component;

[0044] S4: Repeat steps S1-S3 to obtain the standard delay time Bn corresponding to each PV module between the optimizer and each PV module;

[0045] Step 3: Obtain the transmission distance between each PV module and the optimizer, and perform correlation analysis based on the standard delay time corresponding to each PV module. According to the analysis results, obtain the distance correlation coefficient between the optimizer and the PV module. The specific method is as follows:

[0046] S01: Obtain the transmission distance between each photovoltaic module and the optimizer, and mark it as Ln;

[0047] S02: Take the transmission distance between each photovoltaic module and the optimizer as the horizontal coordinate Ln, take the standard delay time Bn corresponding to each photovoltaic module as the vertical coordinate, draw a scatter plot corresponding to the photovoltaic module, and mark the coordinates of each data point on the scatter plot as (Ln, Bn);

[0048] Through the correlation formula, the correlation value G between the delay time of the photovoltaic module and the corresponding distance between the optimizer is obtained. When the correlation value satisfies G>0.58, it means that there is a positive correlation between the transmission distance between the photovoltaic module and the optimizer and the standard delay time corresponding to each photovoltaic module, that is, the delay time of the photovoltaic module increases with the increase of the transmission distance between the photovoltaic module and the optimizer.

[0049] The correlation formula is: ; Wherein, Lp and Bp are the average values ​​of the transmission distance and the standard delay time Bn, respectively, n≥e≥1;

[0050] Then, the coordinates (Lmax, D1) and (Lmin, D2) of the data points corresponding to the maximum and minimum values ​​of the transmission distance Ln between each photovoltaic component and the optimizer are obtained from the scatter plot corresponding to the photovoltaic components, where D1 and D2 are the standard delay times corresponding to the photovoltaic components with the maximum and minimum transmission distances, respectively, Lmax is the maximum value in Ln, and Lmin is the minimum value in Ln. Then, according to the formula: H1=(D1-D2) / (Lmax-Lmin), the distance correlation coefficient H1 between the optimizer and the photovoltaic component is calculated;

[0051] When the correlation value satisfies, G<-0.58, it means that there is a negative correlation between the transmission distance between the PV module and the optimizer and the standard delay time corresponding to each PV module, that is, the delay time of the PV module decreases as the transmission distance between the PV module and the optimizer increases;

[0052] Similarly, the coordinates (Lmax, D1) and (Lmin, D2) of the data points corresponding to the maximum and minimum values ​​of the transmission distance Ln between each photovoltaic component and the optimizer are obtained from the scatter plot corresponding to the photovoltaic component. According to the formula: H1=(D1-D2) / (Lmax-Lmin), the distance correlation coefficient H1 between the optimizer and the photovoltaic component is calculated and obtained;

[0053] When -0.58≤G≤-0.58, it means that there is no relationship between the transmission distance between the PV module and the optimizer and the standard delay time corresponding to each PV module, and the distance correlation coefficient H1 corresponding to the optimizer and the PV module is set to 0;

[0054] Step 4: According to the transmission distance between the PV module and the optimizer with the change of the working point and the corresponding distance correlation coefficient, the advance transmission time Q1 of the control signal is analyzed and obtained. The specific method is as follows:

[0055] Obtain the average value Bp of the standard delay time length Bn corresponding to each photovoltaic component as the calculation time length K;

[0056] According to the formula K-(K×H1×V)=R1, the corresponding optimizer compensation duration R1 is calculated. When R1 is a positive value, the value corresponding to R is used as the advance transmission duration Q1 of the optimizer control signal. When R3 is less than or equal to 0, no processing is performed, where V is the transmission distance between the PV module with the changed working point and the optimizer.

[0057] In order to reduce the time delay between the operating point change moment and the corresponding optimizer control signal adjustment moment caused by the transmission distance between each PV module and the optimizer, and optimize the rate of tracking the maximum power point, so as to achieve a rapid response to the change of the PV module operating point and improve the efficiency of tracking the maximum power point.

[0058] Embodiment 2

[0059] As the second embodiment of the present invention, when the present application is implemented, compared with the first embodiment, the technical solution of the present embodiment is different from that of the first embodiment only in that,

[0060] The device temperature corresponding to each control signal adjustment moment of the optimizer is obtained, and the correlation analysis is performed between the device temperature and the standard delay time corresponding to each photovoltaic module. The temperature correlation coefficient corresponding to the optimizer and the device temperature is obtained according to the analysis result. The specific method is as follows;

[0061] S11: Obtain the temperature state values ​​corresponding to the control signal adjustment moments of the optimizer at the preset number of times j, and obtain the temperature values ​​that meet the preset condition Q1 as the analysis temperature value Fb. The preset condition Q1 is that the maintenance time corresponding to the temperature state value is greater than T1, where b is the number corresponding to the analysis temperature value, b≥1, T1 is the preset value, and the specific value is formulated by relevant personnel according to actual needs, j≥1;

[0062] S12: obtaining a preset number of times a of the optimizer control signal adjustment at each analysis temperature value, respectively corresponding to the optimizer control signal adjustment moment and the corresponding working point change moment, and obtaining the difference between the two, and at the same time taking the average of the differences in the a times of the optimizer control signal adjustment at each analysis temperature value as the delay time Wb corresponding to the optimizer at each analysis temperature value, a≥1;

[0063] S12: adopting the same analysis method as that used in steps S01-S02 to obtain the distance correlation coefficient between the optimizer and the PV module, a correlation analysis is performed on the delay time Wb corresponding to each analysis temperature value of the optimizer and each analysis temperature value Fb, and according to the analysis results, a temperature correlation coefficient M1 corresponding to the optimizer and the device temperature is obtained;

[0064] Obtain the average value Bp of the standard delay time Bn corresponding to each photovoltaic module as the calculation time K;

[0065] According to the formula K-(K×M1×U)=R2, the corresponding optimizer compensation duration R2 is calculated. When R2 is a positive value, the value corresponding to R2 is used as the advance sending duration Q2 of the optimizer control signal. When R2 is less than or equal to 0, no processing is performed, where U is the real-time device temperature corresponding to the optimizer.

[0066] In order to reduce the time delay between the change of the working point of the photovoltaic module and the corresponding adjustment of the optimizer control signal caused by the optimizer's own equipment temperature, and optimize the rate of tracking the maximum power point, so as to achieve a rapid response to the change of the working point of the photovoltaic module and improve the efficiency of tracking the maximum power point.

[0067] Embodiment 3

[0068] As the third embodiment of the present invention, when the present application is implemented, compared with the first and second embodiments, the technical solution of this embodiment is to combine the solutions of the first and second embodiments, and the difference between the technical solution of this embodiment and the first and second embodiments is only in this embodiment;

[0069] According to the transmission distance and corresponding distance correlation coefficient between the PV module and the optimizer with the change of the working point, as well as the real-time device temperature corresponding to the optimizer, the advance sending time E of the optimizer control signal is obtained. The specific method is as follows:

[0070] Obtain the average value Bp of the standard delay time length Bn corresponding to each photovoltaic component as the calculation time length K;

[0071] According to the formula K-[K×(H1×V)+(M1×U)]=R3, the corresponding optimizer compensation duration R3 is calculated. When R3 is a positive value, the value corresponding to R3 is used as the advance sending duration Q3 of the optimizer control signal. When R3 is less than or equal to 0, no processing is performed, where V is the transmission distance between the PV module with the working point change and the optimizer, and U is the real-time device temperature corresponding to the optimizer.

[0072] When the operating points of different PV modules change, the sending time of the PV optimizer control signal is self-corrected according to the advance sending time of the optimizer control signal, so as to reduce the delay time of the optimizer control signal sending, realize adaptive correction of the control signal, and quickly track the maximum power point of each PV module. The optimizer adjusts the sending time of the control signal according to the transmission distance between the PV module and its own equipment temperature, thereby reducing the delay, realizing rapid response to changes in the operating point of the PV module, and improving the efficiency of tracking the maximum power point.

[0073] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters and thresholds in the formula are set by technicians in this field according to actual conditions.

[0074] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A self-correction processing method based on a photovoltaic optimizer, characterized in that: The following steps are involved: Step 1: Obtain the historical operating point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time; Step 2: Analyze the difference between the historical working point change time of each photovoltaic module and the corresponding optimizer control signal adjustment time to obtain the standard delay time corresponding to each photovoltaic module: Step 3: Analyze the transmission distance between each PV module and the optimizer in combination with the standard delay time corresponding to each PV module to obtain the distance correlation coefficient between the optimizer and the PV module; Step 4: Perform correlation analysis on the device temperature corresponding to each control signal adjustment moment of the optimizer and the standard delay time corresponding to each photovoltaic module to obtain the temperature correlation coefficient between the optimizer and the device temperature; Step 5: Obtain the advance sending time of the optimizer control signal according to the transmission distance and the corresponding distance correlation coefficient between the PV module with the change of the working point and the optimizer and the corresponding real-time device temperature of the optimizer; The specific method for obtaining the standard delay time corresponding to each photovoltaic module between the optimizer and each photovoltaic module is as follows: S1: designate an analysis component from each photovoltaic component, obtain the difference Yn between the working point change moment of the analysis component for a preset number of times n and the corresponding optimizer control signal adjustment moment, and use the mode in Yn as the standard delay time B1 corresponding to the analysis component, where n is greater than or equal to 1; S2: Repeat step S1 to obtain the standard delay time Bn corresponding to each photovoltaic module; The specific method for obtaining the distance correlation coefficient between the optimizer and the photovoltaic module is: S01: Obtain the transmission distance between each photovoltaic module and the optimizer, and mark it as Ln; S02: Take the transmission distance Ln between each PV module and the optimizer as the horizontal coordinate, take the standard delay time Bn corresponding to each PV module as the vertical coordinate, draw the scatter plot corresponding to the PV module, and obtain the correlation value G between the delay time of the PV module and the corresponding distance between the optimizer through the correlation formula, and compare and analyze it with 0.58 or -0.58 to obtain the distance correlation coefficient H1 between the optimizer and the PV module; When the correlation value G is greater than 0.58 or less than -0.58, the standard delay times D1 and D2 corresponding to the maximum and minimum values ​​of the transmission distance Ln between each PV module and the optimizer are obtained, and then the distance correlation coefficient H1 between the optimizer and the PV module is calculated according to the formula: H1=(D1-D2) / (Lmax-Lmin), where Lmax is the maximum value in Ln and Lmin is the minimum value in Ln; when the correlation value G is less than or equal to -0.58 and greater than or equal to 0.58, no processing is performed; Get the temperature correlation coefficient between the optimizer and the device temperature. The specific method is: The same analysis method as that used in S01-S02 to obtain the distance correlation coefficient between the optimizer and the PV module is adopted to perform correlation analysis on the delay time Wb corresponding to each analysis temperature value of the optimizer and each analysis temperature value Fb, and based on the analysis results, obtain the temperature correlation coefficient M1 corresponding to the optimizer and the device temperature; The specific method for obtaining the advance sending duration of the optimizer control signal is: According to the formula K-[K×(H1×V)+(M1×U)]=R3, the corresponding optimizer compensation duration R3 is calculated. When R3 is a positive value, the value corresponding to R3 is used as the advance sending duration Q3 of the optimizer control signal. When R3 is less than or equal to 0, no processing is performed. V is the transmission distance between the PV module with the change of the working point and the optimizer, U is the real-time device temperature corresponding to the optimizer, and K is the calculation duration.

2. The self-correction processing method based on photovoltaic optimizer according to claim 1, characterized in that: The way to obtain the various analysis temperatures of the optimizer is: The temperature state values ​​corresponding to the control signal adjustment moments of the optimizer at the preset number of j times are obtained, and the temperature values ​​that meet the preset condition Q1 are obtained as the analysis temperature value Fb, where b is the number corresponding to the analysis temperature value, b≥1.

3. The self-correction processing method based on photovoltaic optimizer according to claim 2, characterized in that: The specific method for obtaining the delay time corresponding to each analysis temperature value of the optimizer is: Obtain a preset number of optimizer control signal adjustments of the optimizer at each analysis temperature value, which correspond to the optimizer control signal adjustment moment and the corresponding working point change moment, and obtain the difference between the two. At the same time, take the average of the differences in a optimizer control signal adjustments at each analysis temperature value as the delay time Wb corresponding to the optimizer at each analysis temperature value, a≥1.

4. The self-correction processing method based on photovoltaic optimizer according to claim 2, characterized in that: The preset condition Q1 is specifically: taking the temperature state value corresponding to the temperature state value having a maintenance time longer than the preset value T1 as the analysis temperature value.

5. The self-correction processing method based on photovoltaic optimizer according to claim 4, characterized in that: The specific method for obtaining the calculation duration is: The average of the standard delay time lengths Bn corresponding to each photovoltaic module is used as the calculation time length K.