Building curtain wall with spliced ​​frame structure and construction method

By designing a building curtain wall with a spliced ​​frame structure, combining adjustment panels and cleaning mechanisms, the problems of installation flexibility and dirt cleaning inconvenient cleaning of existing glass building curtain walls are solved, and higher installation flexibility and cleaning convenience are achieved.

CN118498581BInactive Publication Date: 2025-03-18CHINA RAILWAY CONSTR GROUP CO LTD +2
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410774041.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2025-03-18
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Due to the limitation of fixed size during installation, existing glass building curtain walls have low flexibility to adapt to different installation environments, and it is inconvenient to clean the outer dirt after long-term use.

Method used

A architectural curtain wall with a spliced ​​frame structure is designed. By setting up installation frames, glass plates, adjustment plates, threaded holes and locking bolts, the structure between the installation frames is adjusted, and a cleaning mechanism is integrated on the installation frames, and a magnet slab and a magnet strip drive wipe board to clean the outside of the glass plate.

Benefits of technology

It improves the flexibility of glass building curtain walls during installation, can be adjusted according to different installation needs, and simplifies the cleaning process on the outside of the glass plate through an integrated cleaning mechanism, improving the convenience of cleaning.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118498581B_ABST
    Figure CN118498581B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of building technology, specifically to a building curtain wall with a spliced ​​frame structure and a construction method. The present invention includes two glass curtain walls, the glass curtain wall includes a mounting frame, the inner wall of the mounting frame is embedded with a glass plate, the side wall on the upper side of the mounting frame is fixedly connected with a first mounting plate, the first mounting plate is connected with a first adjustment plate, the first adjustment plate and the first mounting plate are both provided with a plurality of first threaded holes, the plurality of first threaded holes are evenly distributed on the first adjustment plate and the first mounting plate, the first threaded hole is threadedly sleeved with a first locking bolt, and the first adjustment plate is evenly fixedly connected with a plurality of first T-shaped plug plates on one side close to the first mounting plate. The present invention can adjust the structure between the two mounting frames according to actual installation requirements, effectively improving the flexibility of the installation of the glass building curtain wall.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction, in particular to a building curtain wall with a spliced ​​frame structure and a construction method. Background Art

[0002] Building curtain wall refers to the non-load-bearing outer wall enclosure of a building, which is usually composed of panels and the supporting structure behind. In order to improve the daylighting rate, modern office buildings will use glass panels as the panels of building curtain walls. Glass building curtain walls have the advantages of good lighting and good vision. They use the transparency of glass to pursue the circulation and integration of the internal and external spaces of the building, so that people can clearly see the entire structural system of the glass through the glass, so that the structural system changes from a simple supporting role to showing its visibility, thereby showing the artistic sense, layering and three-dimensional sense of architectural decoration. It has the characteristics of light weight, simple material selection, factory processing, fast construction, convenient maintenance and repair, and easy cleaning.

[0003] When installing existing glass building curtain walls, different installation environments have different installation size requirements, but the size of the glass building curtain walls is fixed, resulting in poor adaptability of the glass building curtain walls to different installation environments. The different sizes required for installation will cause the glass building curtain walls to be unable to be accurately spliced, resulting in low installation flexibility of the glass building curtain walls. In addition, the existing glass building curtain walls will absorb a lot of dirt on the outside after long-term use, and it is very inconvenient to clean the dirt on the outside. Summary of the invention

[0004] The object of the present invention is to provide a building curtain wall with a spliced ​​frame structure and a construction method to solve the problems raised in the above background technology.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] The present invention provides

[0007] A building curtain wall with a spliced ​​frame structure includes two glass curtain walls, the glass curtain wall includes a mounting frame, the inner wall of the mounting frame is embedded with a glass plate, the side wall on the upper side of the mounting frame is fixedly connected with a first mounting plate, the first mounting plate is connected with a first adjusting plate, the first adjusting plate and the first mounting plate are both provided with a plurality of first threaded holes, the plurality of first threaded holes are evenly distributed on the first adjusting plate and the first mounting plate, the first threaded holes are threadedly sleeved with first locking bolts, a side of the first adjusting plate close to the first mounting plate is evenly fixedly connected with a plurality of first T-shaped plug-ins, a vertical side wall of the first mounting plate is provided with a plurality of first T-shaped slots matching the first T-shaped plug-ins, the first T-shaped plug-ins are movably plugged into the first T-shaped slots, and an upper connecting plate is fixedly connected to the upper side of the first adjusting plate , the lower side of the mounting frame is fixedly connected to the second mounting plate, the second mounting plate is connected to the second adjusting plate, the second adjusting plate and the second mounting plate are both provided with a plurality of second threaded holes, the plurality of second threaded holes are evenly distributed on the second adjusting plate and the second mounting plate, the second threaded holes are threadedly sleeved with a second locking bolt, the second adjusting plate is evenly fixedly connected to a side of the second mounting plate close to the second mounting plate, the vertical side wall of the second mounting plate is provided with a plurality of second T-shaped slots matching the second T-shaped slots, the second T-shaped slots are movably inserted in the second T-shaped slots, the lower side of the second adjusting plate is fixedly connected to the lower connecting plate, the side walls located on the opposite side of the upper connecting plate and the lower connecting plate of the two mounting frames are both provided with two card slots, and the same card plate is movably inserted in the two card slots.

[0008] In the above-mentioned building curtain wall with a spliced ​​frame structure, a cleaning mechanism is fixedly connected to the installation frame, and the cleaning mechanism includes two sliding grooves symmetrically opened on the installation frame, and the same magnetic plate is slidably connected in the two sliding grooves, and two guide rods are symmetrically fixedly connected to the installation frame, and the same sliding plate is movably sleeved outside the two guide rods, and two guide holes are symmetrically opened on the sliding plate, and the guide rods penetrate the sliding plate through the guide holes, and a wiping plate is fixedly connected to the side of the sliding plate close to the glass plate, and the wiping plate is tightly fitted with the glass plate, and a magnetic strip is fixedly connected to the side of the sliding plate close to the glass plate, and the polarity of the magnetic strip opposite to the magnetic plate is opposite.

[0009] In the above-mentioned building curtain wall with a spliced ​​frame structure, a push block is fixedly connected to the side wall of the magnetic plate away from the glass plate. The push block is located in the middle position of the magnetic plate. A plurality of anti-slip grooves are provided on the push block, and the plurality of anti-slip grooves are evenly distributed on the push block.

[0010] In the above-mentioned building curtain wall with a spliced ​​frame structure, two sealing strips are symmetrically fixedly connected to the inner wall of the installation frame, the glass plate is located between the two sealing strips, and the sealing strip fits tightly with the installation frame and the glass plate.

[0011] In the above-mentioned building curtain wall with a spliced ​​frame structure, both ends of the guide rod are fixedly connected with fixed blocks, the two fixed blocks are fixedly connected to the installation frame, a gap is set between the guide rod and the installation frame, and the sliding plate is located between the two fixed blocks.

[0012] In the above-mentioned building curtain wall with a spliced ​​frame structure, the specific shape of the clamping plate is an I-shape, and the upper and lower clamping grooves form an I-shaped groove structure.

[0013] In the above-mentioned building curtain wall with a spliced ​​frame structure, the installation frame includes two vertical plates, two horizontal plates are symmetrically fixedly connected between the two vertical plates, and the two vertical plates and the two horizontal plates form a rectangular frame structure.

[0014] In the above-mentioned building curtain wall with a spliced ​​frame structure, the size of the magnetic strip is smaller than the size of the wiping plate, and a gap is provided between the magnetic strip and the glass plate.

[0015] In the above-mentioned building curtain wall with a spliced ​​frame structure, the sides of the upper connecting plate and the lower connecting plate opposite to each other are both ground and polished.

[0016] The construction method of a building curtain wall with a spliced ​​frame structure includes the following steps: during installation, pull the lower connecting plate of the upper installation frame and the upper connecting plate on the lower installation frame to make the lower connecting plate fit with the upper connecting plate, insert the card plate into the card slots on the lower connecting plate and the upper connecting plate, the provided card plate can stably connect the lower connecting plate and the upper connecting plate together, and the positions of the upper connecting plate and the lower connecting plate can be adjusted by the provided first adjustment plate and the second adjustment plate, so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole is opened on the first adjustment plate and the first installation plate, and a second threaded hole is opened on the second adjustment plate and the second installation plate, and then the first locking bolt is screwed into the first threaded hole, and the second locking bolt is screwed into the second threaded hole to complete the construction and installation of the glass building curtain wall.

[0017] Compared with the prior art, the present invention has the following beneficial effects:

[0018] 1. The present invention is provided with an installation frame, a glass plate, a first installation plate, a first adjustment plate, a first threaded hole, a first locking bolt, a first T-shaped plug plate, a first T-shaped slot, an upper connecting plate, a second installation plate, a second adjustment plate, a second threaded hole, a second locking bolt, a second T-shaped plug plate, a second T-shaped slot, a lower connecting plate, a slot and a card. During installation, the lower connecting plate of the upper installation frame is pulled together with the upper connecting plate on the lower installation frame, so that the lower connecting plate and the upper connecting plate are fitted together, and the card plate is inserted into the slots on the lower connecting plate and the upper connecting plate. The card plate provided can stabilize the lower connecting plate and the upper connecting plate. The upper connecting plate and the lower connecting plate are connected together in a fixed manner, and the positions of the upper connecting plate and the lower connecting plate can be adjusted by setting the first adjusting plate and the second adjusting plate, so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole is opened on the first adjusting plate and the first mounting plate, and a second threaded hole is opened on the second adjusting plate and the second mounting plate, and then the first locking bolt is screwed into the first threaded hole, and the second locking bolt is screwed into the second threaded hole to complete the construction and installation of the glass building curtain wall. The structure between the two mounting frames can be adjusted according to actual installation requirements, which effectively improves the flexibility of the installation of the glass building curtain wall.

[0019] 2. The present invention has a cleaning mechanism, and when the outer side of the glass plate needs to be cleaned, the magnetic plate is pulled, and the magnetic plate cooperates with the magnetic strip, the magnetic plate drives the magnetic strip to slide on the two guide rods, and the magnetic strip drives the wiping plate to slide on the glass plate. The wiping plate can wipe and clean the outer side of the glass plate, thereby quickly and effectively cleaning the outside of the glass building curtain wall, effectively improving the convenience of cleaning the glass building curtain wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a schematic diagram of the overall structure of the present invention;

[0021] Figure 2 It is a structural schematic diagram of another aspect of the present invention;

[0022] Figure 3 It is a front view of the present invention;

[0023] Figure 4 is a side view of the present invention;

[0024] Figure 5 for Figure 1 Structural diagram of the glass curtain wall in the middle;

[0025] Figure 6 for Figure 1 Schematic diagram of the connection structure between the upper middle connecting plate and the lower connecting plate;

[0026] Figure 7 for Figure 1 Schematic diagram of the installation structure of the cleaning mechanism;

[0027] Figure 8 for Figure 7 A schematic diagram of the structure in another direction;

[0028] Fig. 9 for Figure 1 Schematic diagram of the structure of the cleaning mechanism.

[0029] In the figure: 1. mounting frame; 2. glass plate; 3. first mounting plate; 4. first adjusting plate; 5. first threaded hole; 6. first locking bolt; 7. first T-type plug plate; 8. first T-type slot; 10. upper connecting plate; 11. second mounting plate; 12. second adjusting plate; 13. second threaded hole; 14. second locking bolt; 15. second T-type plug plate; 16. second T-type slot; 17. lower connecting plate; 18. card slot; 19. card plate; 20. sliding slot; 21. magnet plate; 22. guide rod; 23. sliding plate; 24. guide hole; 25. wiping plate; 26. magnet strip; 27. push block; 28. sealing strip; 29. ​​fixing block; 30. vertical plate; 31. horizontal plate. DETAILED DESCRIPTION

[0030] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] See also Figure 1-9The present invention provides a building curtain wall with a spliced ​​frame structure, including two glass curtain walls, the glass curtain wall includes a mounting frame 1, the inner wall of the mounting frame 1 is embedded with a glass plate 2, the side wall on the upper side of the mounting frame 1 is fixedly connected with a first mounting plate 3, the first mounting plate 3 is connected with a first adjusting plate 4, the first adjusting plate 4 and the first mounting plate 3 are both provided with a plurality of first threaded holes 5, the plurality of first threaded holes 5 are evenly distributed on the first adjusting plate 4 and the first mounting plate 3, the first threaded holes 5 are internally threaded with first locking bolts 6, the first adjusting plate 4 is evenly fixedly connected with a plurality of first T-shaped plug-in plates 7 on one side close to the first mounting plate 3, the vertical side wall of the first mounting plate 3 is provided with a plurality of first T-shaped slots 8 matching the first T-shaped plug-in plates 7, the first T-shaped plug-in plates 7 are movably plugged into the first T-shaped slots 8, the upper side of the first adjusting plate 4 is fixedly connected with an upper connecting plate 10, the lower side of the mounting frame 1 is fixed A second mounting plate 11 is fixedly connected, a second adjusting plate 12 is connected to the second mounting plate 11, a plurality of second threaded holes 13 are provided on the second adjusting plate 12 and the second mounting plate 11, and the plurality of second threaded holes 13 are evenly distributed on the second adjusting plate 12 and the second mounting plate 11, a second locking bolt 14 is threadedly sleeved on the inner thread of the second threaded hole 13, a plurality of second T-shaped plug plates 15 are evenly fixedly connected to the side of the second adjusting plate 12 close to the second mounting plate 11, a plurality of second T-shaped slots 16 matching the second T-shaped plug plates 15 are provided on the vertical side wall of the second mounting plate 11, and the second T-shaped plug plates 15 are movably inserted in the second T-shaped slots 16, a lower connecting plate 17 is fixedly connected to the lower side of the second adjusting plate 12, and two card slots 18 are provided on the side walls on the opposite side of the upper connecting plate 10 and the lower connecting plate 17 of the two mounting frames 1, and the same card plate 19 is movably inserted in the two card slots 18.

[0032] In the above embodiment, during installation, the lower connecting plate 17 of the upper mounting frame 1 is pulled together with the upper connecting plate 10 on the lower mounting frame 1, so that the lower connecting plate 17 fits with the upper connecting plate 10, and the card plate 19 is inserted into the card slots 18 on the lower connecting plate 17 and the upper connecting plate 10. The card plate 19 can stably connect the lower connecting plate 17 and the upper connecting plate 10 together, and the positions of the upper connecting plate 10 and the lower connecting plate 17 can be adjusted by the first adjusting plate 4 and the second adjusting plate 12, so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole 5 is opened on the first adjusting plate 4 and the first mounting plate 3, and a second threaded hole 13 is opened on the second adjusting plate 12 and the second mounting plate 11, and then the first locking bolt 6 is screwed into the first threaded hole 5, and the second locking bolt 14 is screwed into the second threaded hole 13, so as to complete the construction and installation of the glass building curtain wall, and the structure between the two mounting frames 1 can be adjusted according to actual installation requirements, which effectively improves the flexibility of the installation of the glass building curtain wall.

[0033] A cleaning mechanism is fixedly connected to the mounting frame 1, and the cleaning mechanism includes two sliding grooves 20 symmetrically opened on the mounting frame 1, and the same magnetic plate 21 is slidably connected in the two sliding grooves 20, and two guide rods 22 are symmetrically fixedly connected to the mounting frame 1, and the same sliding plate 23 is movably sleeved outside the two guide rods 22, and two guide holes 24 are symmetrically opened on the sliding plate 23, and the guide rods 22 penetrate the sliding plate 23 through the guide holes 24, and a wiping plate 25 is fixedly connected to the side of the sliding plate 23 close to the glass plate 2, and the wiping plate 25 is tightly fitted with the glass plate 2, and a magnetic strip 26 is fixedly connected to the side of the sliding plate 23 close to the glass plate 2, and the polarity of the magnetic strip 26 and the side opposite to the magnetic plate 21 are opposite.

[0034] In this embodiment, when it is necessary to clean the outside of the glass plate 2, the magnetic plate 21 is pulled, and the magnetic plate 21 cooperates with the magnetic strip 26, so that the magnetic plate 21 drives the magnetic strip 26 to slide on the two guide rods 22, and the magnetic strip 26 drives the wiping plate 25 to slide on the glass plate 2. The wiping plate 25 can wipe and clean the outside of the glass plate 2, thereby quickly and effectively cleaning the outside of the glass building curtain wall, effectively improving the convenience of cleaning the glass building curtain wall.

[0035] A push block 27 is fixedly connected to the side wall of the magnetic plate 21 away from the glass plate 2 . The push block 27 is located in the middle of the magnetic plate 21 . A plurality of anti-skid grooves are formed on the push block 27 . The plurality of anti-skid grooves are evenly distributed on the push block 27 .

[0036] In this embodiment, the push block 27 provided can improve the convenience of operating the magnetic plate 21. Pushing the push block 27 can drive the magnetic plate 21 to move, thereby improving the convenience of using the cleaning mechanism. The multiple anti-slip grooves provided can improve the anti-slip performance of the push block 27 and improve the comfort of using the push block 27.

[0037] Two sealing strips 28 are symmetrically fixedly connected to the inner wall of the installation frame 1 , and the glass plate 2 is located between the two sealing strips 28 . The sealing strip 28 fits tightly with the installation frame 1 and the glass plate 2 .

[0038] In the above embodiment, the two sealing strips 28 are provided to seal both sides of the glass plate 2, thereby improving the sealing performance of the connection between the glass plate 2 and the mounting frame 1, thereby improving the sealing performance of the glass building curtain wall.

[0039] Both ends of the guide rod 22 are fixedly connected with fixing blocks 29 , and the two fixing blocks 29 are fixedly connected to the installation frame 1 . A gap is provided between the guide rod 22 and the installation frame 1 , and the sliding plate 23 is located between the two fixing blocks 29 .

[0040] In the above embodiment, the two fixed blocks 29 are arranged to create a gap between the guide rod 22 and the mounting frame 1, thereby avoiding a large friction between the sliding plate 23 and the mounting frame 1, thereby improving the smoothness of the sliding of the sliding plate 23, reducing the wear rate of the sliding plate 23, and increasing the service life of the sliding plate 23.

[0041] The specific shape of the clamping plate 19 is an I-shape, and the upper and lower clamping grooves 18 form an I-shaped groove structure.

[0042] In this embodiment, the I-shaped clamping plate 19 can be easily matched with the clamping groove 18, so as to improve the matching effect between the upper connecting plate 10 and the lower connecting plate 17 and improve the stability when the two installation frames 1 are connected.

[0043] The installation frame 1 includes two vertical plates 30 , and two horizontal plates 31 are symmetrically fixedly connected between the two vertical plates 30 . The two vertical plates 30 and the two horizontal plates 31 form a rectangular frame structure.

[0044] In the above embodiment, the vertical plate 30 and the horizontal plate 31 cooperate with each other to form a complete installation frame 1. When installing the glass plate 2, the installation frame 1 can be disassembled, thereby facilitating the installation of the glass plate 2 and improving the convenience of assembling the glass building curtain wall.

[0045] The size of the magnetic strip 26 is smaller than that of the wiping plate 25 , and a gap is provided between the magnetic strip 26 and the glass plate 2 .

[0046] In this embodiment, the size of the magnetic strip 26 is smaller than that of the wiping plate 25 to avoid the magnetic strip 26 from scratching the surface of the glass plate 2 , thereby improving the safety of the use of the magnetic strip 26 .

[0047] The sides of the upper connecting plate 10 and the lower connecting plate 17 that are opposite to each other are both ground and polished.

[0048] In the above embodiment, the upper connecting plate 10 and the lower connecting plate 17 are ground and polished, so as to improve the sealing between the upper connecting plate 10 and the lower connecting plate 17 , thereby improving the sealing between the two installation frames 1 .

[0049] The construction method of a building curtain wall with a spliced ​​frame structure includes the following steps: during installation, pull the lower connecting plate 17 of the upper installation frame 1 and the upper connecting plate 10 on the lower installation frame 1 to make the lower connecting plate 17 fit with the upper connecting plate 10, insert the clamping plate 19 into the clamping groove 18 on the lower connecting plate 17 and the upper connecting plate 10, the provided clamping plate 19 can stably connect the lower connecting plate 17 and the upper connecting plate 10 together, and the positions of the upper connecting plate 10 and the lower connecting plate 17 can be adjusted by the provided first adjustment plate 4 and the second adjustment plate 12, so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole 5 is opened on the first adjustment plate 4 and the first mounting plate 3, and a second threaded hole 13 is opened on the second adjustment plate 12 and the second mounting plate 11, and then the first locking bolt 6 is screwed into the first threaded hole 5, and the second locking bolt 14 is screwed into the second threaded hole 13, so as to complete the construction and installation of the glass building curtain wall.

[0050] Working principle: During installation, pull the lower connecting plate 17 of the upper installation frame 1 and the upper connecting plate 10 on the lower installation frame 1 so that the lower connecting plate 17 fits with the upper connecting plate 10, and insert the card plate 19 into the card slots 18 on the lower connecting plate 17 and the upper connecting plate 10. The card plate 19 can stably connect the lower connecting plate 17 and the upper connecting plate 10 together. The positions of the upper connecting plate 10 and the lower connecting plate 17 can be adjusted by the first adjusting plate 4 and the second adjusting plate 12, so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole 5 is opened on the first adjusting plate 4 and the first mounting plate 3, and a second threaded hole 13 is opened on the second adjusting plate 12 and the second mounting plate 11. Then, the first locking bolt 6 is screwed into the first threaded hole 5, and the second locking bolt 14 is screwed into the second threaded hole 13. The construction and installation of the glass building curtain wall are completed. The structure between the two mounting frames 1 can be adjusted according to actual installation requirements, which effectively improves the flexibility of the installation of the glass building curtain wall.

[0051] When it is necessary to clean the outside of the glass plate 2, the magnetic plate 21 is pulled, and the magnetic plate 21 cooperates with the magnetic strip 26, so that the magnetic plate 21 drives the magnetic strip 26 to slide on the two guide rods 22, and the magnetic strip 26 drives the wiping plate 25 to slide on the glass plate 2, and the wiping plate 25 can wipe and clean the outside of the glass plate 2, so that the outside of the glass building curtain wall can be cleaned quickly and effectively, which effectively improves the convenience of cleaning the glass building curtain wall;

[0052] The push block 27 can improve the convenience of operating the magnetic plate 21. Pushing the push block 27 can drive the magnetic plate 21 to move, thereby improving the convenience of using the cleaning mechanism. The multiple anti-skid grooves can improve the anti-skid performance of the push block 27 and improve the comfort of using the push block 27.

[0053] The two sealing strips 28 can seal both sides of the glass plate 2, thereby improving the sealing of the connection between the glass plate 2 and the mounting frame 1, thereby improving the sealing of the glass building curtain wall;

[0054] The two fixed blocks 29 are arranged to allow a gap to exist between the guide rod 22 and the mounting frame 1, thereby avoiding a large friction between the sliding plate 23 and the mounting frame 1, thereby improving the smoothness of the sliding of the sliding plate 23, reducing the wear rate of the sliding plate 23, and increasing the service life of the sliding plate 23;

[0055] The I-shaped card plate 19 can be easily matched with the card slot 18, so as to improve the matching effect between the upper connecting plate 10 and the lower connecting plate 17, and improve the stability when the two installation frames 1 are connected;

[0056] The vertical plate 30 and the horizontal plate 31 cooperate with each other to form a complete installation frame 1. When installing the glass plate 2, the installation frame 1 can be disassembled, so as to facilitate the installation of the glass plate 2 and improve the convenience of assembling the glass building curtain wall.

[0057] The size of the magnetic strip 26 is smaller than that of the wiping plate 25 to prevent the magnetic strip 26 from scratching the surface of the glass plate 2, thereby improving the safety of the use of the magnetic strip 26;

[0058] Grinding and polishing the upper connecting plate 10 and the lower connecting plate 17 can improve the sealing between the upper connecting plate 10 and the lower connecting plate 17 , thereby improving the sealing between the two installation frames 1 .

[0059] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.

[0060] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A building curtain wall with a spliced ​​frame structure, characterized in that: The invention comprises two glass curtain walls, the glass curtain walls comprising a mounting frame (1), the inner wall of the mounting frame (1) being embedded with a glass plate (2), the upper side wall of the mounting frame (1) being fixedly connected with a first mounting plate (3), the first mounting plate (3) being connected with a first adjustment plate (4), the first adjustment plate (4) and the first mounting plate (3) being both provided with a plurality of first threaded holes (5), the plurality of first threaded holes (5) being evenly distributed on the first adjustment plate (4) and the first mounting plate (3), the first threaded holes (5) being provided with a plurality of first threaded holes (5) and a plurality of ... A first locking bolt (6) is threadedly sleeved, a plurality of first T-shaped plug plates (7) are evenly fixedly connected to one side of the first adjustment plate (4) close to the first mounting plate (3), a plurality of first T-shaped slots (8) matching the first T-shaped plug plates (7) are opened on the vertical side wall of the first mounting plate (3), the first T-shaped plug plates (7) are movably inserted into the first T-shaped slots (8), an upper connecting plate (10) is fixedly connected to the upper side of the first adjustment plate (4), and a second mounting plate (10) is fixedly connected to the lower side of the mounting frame (1). 1), the second mounting plate (11) is connected to a second adjustment plate (12), the second adjustment plate (12) and the second mounting plate (11) are both provided with a plurality of second threaded holes (13), the plurality of second threaded holes (13) are evenly distributed on the second adjustment plate (12) and the second mounting plate (11), the second threaded holes (13) are internally threadedly sleeved with second locking bolts (14), and a side of the second adjustment plate (12) close to the second mounting plate (11) is evenly fixedly connected with a plurality of second T-shaped plug plates (15), The vertical side wall of the second mounting plate (11) is provided with a plurality of second T-shaped slots (16) matching with the second T-shaped plug plate (15), the second T-shaped plug plate (15) being movably plugged into the second T-shaped slots (16), the lower side of the second adjustment plate (12) being fixedly connected with a lower connecting plate (17), the side walls on the opposite side of the upper connecting plate (10) and the lower connecting plate (17) of the two mounting frames (1) are provided with two card slots (18), and the same card plate (19) is movably plugged into the two card slots (18); The installation frame (1) is fixedly connected with a cleaning mechanism, the cleaning mechanism comprising two sliding grooves (20) symmetrically arranged on the installation frame (1), the two sliding grooves (20) being slidably connected with a same magnetic plate (21), the installation frame (1) being symmetrically fixedly connected with two guide rods (22), the two guide rods (22) being movably sleeved with a same sliding plate (23), the sliding plate (23) being symmetrically provided with two guide holes (24), the guide rods (22) passing through the sliding plate (23) through the guide holes (24), the sliding plate (23) being fixedly connected with a wiping plate (25) on one side close to the glass plate (2), the wiping plate (25) being tightly fitted with the glass plate (2), the sliding plate (23) being fixedly connected with a magnetic strip (26) on one side close to the glass plate (2), the magnetic strip (26) having a polarity opposite to that of the magnetic plate (21).

2. The building curtain wall with a spliced ​​frame structure according to claim 1, characterized in that: A push block (27) is fixedly connected to the side wall of the magnetic plate (21) away from the glass plate (2); the push block (27) is located in the middle of the magnetic plate (21); a plurality of anti-skid grooves are formed on the push block (27); and the plurality of anti-skid grooves are evenly distributed on the push block (27).

3. The building curtain wall with a spliced ​​frame structure according to claim 2, characterized in that: Two sealing strips (28) are symmetrically fixedly connected to the inner wall of the installation frame (1); the glass plate (2) is located between the two sealing strips (28); and the sealing strip (28) is tightly fitted to the installation frame (1) and the glass plate (2).

4. The building curtain wall with a spliced ​​frame structure according to claim 3, characterized in that: Both ends of the guide rod (22) are fixedly connected to fixed blocks (29), the two fixed blocks (29) are fixedly connected to the installation frame (1), a gap is provided between the guide rod (22) and the installation frame (1), and the sliding plate (23) is located between the two fixed blocks (29).

5. The building curtain wall with a spliced ​​frame structure according to claim 4, characterized in that: The specific shape of the clamping plate (19) is an I-shape, and the upper and lower clamping grooves (18) form an I-shaped groove structure.

6. The building curtain wall with a spliced ​​frame structure according to claim 5, characterized in that: The installation frame (1) comprises two vertical plates (30), two horizontal plates (31) are symmetrically fixedly connected between the two vertical plates (30), and the two vertical plates (30) and the two horizontal plates (31) form a rectangular frame structure.

7. The building curtain wall with a spliced ​​frame structure according to claim 6, characterized in that: The size of the magnetic strip (26) is smaller than the size of the wiping plate (25), and a gap is provided between the magnetic strip (26) and the glass plate (2).

8. The building curtain wall with a spliced ​​frame structure according to claim 7, characterized in that: The sides of the upper connecting plate (10) and the lower connecting plate (17) opposite to each other are both ground and polished.

9. A construction method for a building curtain wall having a spliced ​​frame structure, characterized in that: The invention comprises the following steps: during installation, pulling the lower connecting plate (17) of the upper installation frame (1) and the upper connecting plate (10) on the lower installation frame (1) to make the lower connecting plate (17) fit with the upper connecting plate (10); inserting the card plate (19) into the card slots (18) on the lower connecting plate (17) and the upper connecting plate (10); the card plate (19) can stably connect the lower connecting plate (17) and the upper connecting plate (10); and adjusting the lower connecting plate (17) and the upper connecting plate (10) by means of the first adjusting plate (4) and the second adjusting plate (12). ) can adjust the positions of the upper connecting plate (10) and the lower connecting plate (17) so as to adapt to different installation requirements. After the adjustment is completed, a first threaded hole (5) is opened on the first adjusting plate (4) and the first mounting plate (3), and a second threaded hole (13) is opened on the second adjusting plate (12) and the second mounting plate (11). Then, the first locking bolt (6) is screwed into the first threaded hole (5), and the second locking bolt (14) is screwed into the second threaded hole (13), thereby completing the construction and installation of the glass building curtain wall.

Citation Information

Patent Citations

  • Building curtain wall mounting structure

    CN114908909A

  • Intelligent splicing method for green building curtain wall

    CN115613746A