A method for controlling output of multi-channel combined power supply
Through the multi-channel combined power output control method, the feasibility of power output and sub-power combinations are evaluated and analyzed to solve the problem of low power operating efficiency, ensure the normal operation of electrical appliances and improve the overall efficiency of the power supply.
Patent Information
- Application Number
- CN202410977816.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-22
AI Technical Summary
The existing technology cannot effectively evaluate the feasibility of power supply output, resulting in low power supply operating efficiency, unable to ensure the normal operation of electrical appliances, and unable to perform synchronous delay and distributed delay operation analysis, affecting the overall efficiency of the power supply.
Using a multi-channel combined power output control method, the power output feasibility evaluation unit, multi-combination circuit analysis unit, separate operation analysis unit and synchronous operation analysis unit are connected through the output control platform to conduct power output feasibility evaluation, sub-power combination analysis, separation Delayed operation analysis and synchronous delayed operation analysis generate corresponding signals for regulation and monitoring.
Ensure that the feasibility of power output meets actual needs, improve the operating efficiency of electrical appliances, reduce the risk of equipment wear, avoid inefficiencies caused by abnormal power combinations, and improve the overall efficiency of power supply operations.
Smart Images

Figure CN118508539B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power supply output control, in particular to a multi-channel combined power supply output control method. Background Art
[0002] Common power sources are dry batteries (DC) and household 110V-220V AC power. The power source is based on the principle of "magnetoelectricity", and is generated by renewable energy sources such as water power, wind power, sea tides, water pressure difference in dams, solar energy, and burning coal, oil residue, etc.
[0003] However, in the prior art, the feasibility cannot be evaluated when the power supply is outputting, and the corresponding combination circuit of the power supply cannot be analyzed when the feasibility analysis is qualified, so that the power supply operation efficiency cannot be guaranteed and the normal operation of the electrical appliances cannot be ensured; in addition, the power supply cannot be analyzed for synchronous delay operation and distributed delay operation, resulting in reduced power supply operation efficiency.
[0004] In view of the above technical defects, a solution is now proposed. Summary of the invention
[0005] The purpose of the present invention is to solve the above-mentioned problem and to provide a multi-channel combined power supply output control method.
[0006] The purpose of the present invention can be achieved through the following technical solutions:
[0007] A multi-channel combined power supply output control method, the multi-channel combined power supply output control method relates to an output control platform, wherein the output control platform is communicatively connected with a power supply output feasibility assessment unit, a multi-combination circuit analysis unit, a circuit operation analysis unit, a separate operation analysis unit and a synchronous operation analysis unit;
[0008] The power supply output feasibility assessment unit performs output feasibility assessment and analysis on the power supply, analyzes the power supply, and divides the power supply into i sub-power supplies, where i is a natural number greater than 1, obtains the output feasibility assessment coefficient within the power supply operation period, generates an output high-risk signal or an output low-risk signal based on the output feasibility assessment coefficient, and sends it to the output control platform;
[0009] The multi-combination circuit analysis unit performs sub-power supply combination circuit analysis during the real-time operation of the power supply, combines sub-power supplies according to the specifications of the sub-power supplies in the current power supply, arbitrarily selects two sub-power supplies as different circuit combinations, and divides the combined sub-power supplies in different circuit combinations into high-quantity power supplies and low-quantity power supplies according to the voltage specifications of the sub-power supplies corresponding to different circuit combinations. Based on the analysis, a circuit operation risk signal, a circuit operation detection signal and a circuit operation safety signal are generated and sent to the output control platform.
[0010] As a preferred embodiment of the present invention, the circuit operation analysis unit generates a separate operation analysis signal and a synchronous operation analysis signal, and sends the separate operation analysis signal and the synchronous operation analysis signal to the separate operation analysis unit and the synchronous operation analysis unit respectively; the separate operation analysis unit performs a sub-power supply separate delayed operation analysis on the power supply, and at the same time the synchronous operation analysis unit performs a sub-power supply synchronous delayed operation analysis on the power supply.
[0011] As a preferred embodiment of the present invention, the operation process of the power output feasibility evaluation unit is as follows:
[0012] Obtain the increase in the average power constant duration floating frequency when the adjacent sub-power supplies output at the same time during the power supply operation period, and the rising span value of the operating starting ambient temperature of the subsequent sub-power supply when the adjacent sub-power supplies output at non-simultaneous times; obtain the excess of the actual operating environment peak voltage and rated voltage of each sub-power supply during the power supply operation period; obtain the output feasibility assessment coefficient during the power supply operation period through analysis;
[0013] Compare the output feasibility assessment coefficient within the power supply operation period with the output feasibility assessment coefficient threshold:
[0014] If the output feasibility assessment coefficient during the power supply operation period exceeds the output feasibility assessment coefficient threshold, the output feasibility assessment coefficient analysis during the power supply operation period is judged to be abnormal, an output high-risk signal is generated and the output high-risk signal is sent to the output control platform; if the output feasibility assessment coefficient during the power supply operation period does not exceed the output feasibility assessment coefficient threshold, the output feasibility assessment coefficient analysis during the power supply operation period is judged to be normal, an output low-risk signal is generated and the output low-risk signal is sent to the output control platform.
[0015] As a preferred embodiment of the present invention, the operation process of the multi-combinatorial circuit analysis unit is as follows:
[0016] The maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination is obtained, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation is obtained, and the maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation are compared with the maximum time difference threshold and the output task demand threshold respectively:
[0017] If the maximum time difference for the voltage to rise to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination exceeds the maximum time difference threshold, and the output task demand due to the sub-power supply combination rising order being inconsistent with the actual sub-power supply circuit operation order during the power supply operation exceeds the output task demand threshold, a circuit operation risk signal is generated and sent to the output control platform.
[0018] As a preferred embodiment of the present invention, if the maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination exceeds the maximum time difference threshold, and the output task demand that is inconsistent with the sub-power supply combination rising sequence and the actual sub-power supply circuit operation sequence during the power supply operation exceeds the output task demand threshold, if any one of the situations and only one of them occurs, a circuit operation detection signal is generated and sent to the output control platform;
[0019] If the maximum time difference for the voltage to rise to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination does not exceed the maximum time difference threshold, and the output task demand in which the rising order of the sub-power supply combination is inconsistent with the actual sub-power supply circuit operation order during the power supply operation does not exceed the output task demand threshold, a circuit operation safety signal is generated and sent to the output control platform.
[0020] As a preferred embodiment of the present invention, the operation process of the separate operation analysis unit is as follows:
[0021] The maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the first operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuits of adjacent sub-power supplies when the sub-power supply is separated and delayed and the sub-power supply combination alternating operation moment are obtained, and the maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the first operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuits of adjacent sub-power supplies when the sub-power supply is separated and delayed and the sub-power supply combination alternating operation moment are compared with the maximum temperature difference threshold and the overlapping frequency threshold, respectively.
[0022] As a preferred embodiment of the present invention, if the maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply and the average temperature floating span during the previous operation of the same sub-power supply when the sub-power supply is separately delayed exceeds the maximum temperature difference threshold, or the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the moment of the alternating operation of the sub-power supply combination when the sub-power supply is separately delayed exceeds the overlapping frequency threshold, then a separate delayed operation inefficiency signal is generated and sent to the circuit operation analysis unit;
[0023] If the maximum temperature difference between the average temperature floating span during the output process of the later running sub-power supply and the average temperature floating span during the earlier running of the same sub-power supply during the separate delayed operation of the sub-power supply does not exceed the maximum temperature difference threshold, and the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the alternating operation moment of the sub-power supply combination during the separate delayed operation of the sub-power supply does not exceed the overlapping frequency threshold, then a separate delayed operation high-efficiency signal is generated and sent to the output control platform.
[0024] As a preferred embodiment of the present invention, the operation process of the synchronous operation analysis unit is as follows:
[0025] Obtain the shortened amount of the time difference between the real-time delay duration of adjacent operating moments of the sub-power supply and the preset delay duration during the sub-power supply synchronous delay operation, as well as the temperature rise rate increase frequency of the sub-power supply corresponding circuit when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, and compare the shortened amount of the time difference between the real-time delay duration of adjacent operating moments of the sub-power supply and the preset delay duration during the sub-power supply synchronous delay operation, as well as the temperature rise rate increase frequency of the sub-power supply corresponding circuit when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation with the time difference shortened amount threshold and the temperature rise rate increase frequency threshold, respectively.
[0026] As a preferred embodiment of the present invention, if the shortening amount of the time difference between the real-time delay time of the adjacent operation moments of the sub-power supply and the preset delay time during the sub-power supply synchronous delay operation exceeds the shortening amount threshold of the time difference, or the temperature rise rate of the sub-power supply corresponding circuit exceeds the temperature rise rate threshold when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, then a synchronous delay operation inefficiency signal is generated and sent to the power supply operation analysis unit;
[0027] If the shortening amount of the time difference between the real-time delay time at the adjacent operating moments of the sub-power supply and the preset delay time during the sub-power supply synchronous delay operation does not exceed the time difference shortening amount threshold, and the temperature rise rate frequency of the sub-power supply corresponding circuit does not exceed the temperature rise rate rising frequency threshold when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, a synchronous delay operation high-efficiency signal is generated and sent to the power supply operation analysis unit.
[0028] Compared with the prior art, the present invention has the following beneficial effects:
[0029] 1. In the present invention, an output feasibility evaluation and analysis is performed on the power supply to determine whether the output feasibility analysis during the actual use of the current power supply meets the actual needs, thereby ensuring that the power supply feasibility meets the actual needs and ensuring the normal operating efficiency of the electrical equipment. At the same time, the power supply output is evaluated and detected to facilitate operation and maintenance when the power supply is abnormal; a sub-power supply combination circuit analysis is performed during the real-time operation of the power supply, and an operation analysis is performed based on sub-power supply combinations of different specifications to avoid inefficient operation of different circuits caused by abnormal sub-power supply combinations, thereby affecting the overall operating efficiency of the power supply, while reducing the operating qualification rate of electrical appliances and increasing the risk of wear and tear on the life of electrical appliances.
[0030] 2. In the present invention, the power supply is subjected to a delayed operation analysis of the separate sub-power supplies to determine whether the sub-power supply components in the current power supply are operating properly, thereby ensuring the operating efficiency of the power supply, ensuring the feasibility of circuit operation, and improving the operating efficiency of electrical appliances to avoid equipment wear caused by power supply abnormalities; the power supply is subjected to a synchronous delayed operation analysis of the sub-power supplies to monitor the operation of the power supply circuit in real time to avoid a reduction in circuit delay efficiency during the synchronous delay process, which can prevent the electrical appliances from operating at the expected time. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.
[0032] Figure 1 It is a principle block diagram of the present invention. DETAILED DESCRIPTION
[0033] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0035] See also Figure 1As shown, a multi-channel combined power supply output control method, the multi-channel combined power supply output control method involves an output control platform, wherein the output control platform is communicatively connected with a power supply output feasibility assessment unit, a multi-combination circuit analysis unit, a circuit operation analysis unit, a separate operation analysis unit, and a synchronous operation analysis unit; wherein the above units are all composed of sensors and other equipment required by the corresponding method;
[0036] Example 1
[0037] The output control platform generates a feasibility assessment signal and sends the feasibility assessment signal to the power supply output feasibility assessment unit. After receiving the feasibility assessment signal, the power supply output feasibility assessment unit performs an output feasibility assessment and analysis on the power supply to determine whether the output feasibility analysis during the actual use of the current power supply meets the actual needs, ensures that the power supply feasibility meets the actual needs, ensures the normal operation efficiency of the power-consuming equipment, and at the same time evaluates and detects the power supply output to facilitate operation and maintenance when the power supply is abnormal;
[0038] Analyze the power supply and divide it into i sub-power supplies, where i is a natural number greater than 1, obtain the average power constant duration floating frequency growth when the power of adjacent sub-power supplies is output at the same time in the power supply operation period, and the operation start ambient temperature rise span value of the subsequent sub-power supply when the power of adjacent sub-power supplies is output at non-simultaneous times, and mark the average power constant duration floating frequency growth when the power of adjacent sub-power supplies is output at the same time in the power supply operation period, and the operation start ambient temperature rise span value of the subsequent sub-power supply when the power of adjacent sub-power supplies is output at non-simultaneous times as FP and KD respectively;
[0039] Obtain the excess of the actual operating environment peak voltage of each sub-power supply during the power supply operation period and the rated voltage, and mark the excess of the actual operating environment peak voltage of each sub-power supply during the power supply operation period and the rated voltage as VC;
[0040] By formula The output feasibility evaluation coefficient G during the power supply operation period is obtained, where erw1, erw2 and erw3 are preset proportional coefficients of the constant-duration floating frequency increase, the ambient temperature rise span value and the voltage excess, respectively, and e is a natural constant with a value of 1.5;
[0041] Compare the output feasibility assessment coefficient G during the power supply operation period with the output feasibility assessment coefficient threshold:
[0042] If the output feasibility assessment coefficient G during the power supply operation period exceeds the output feasibility assessment coefficient threshold, the output feasibility assessment coefficient analysis during the power supply operation period is determined to be abnormal, an output high-risk signal is generated and the output high-risk signal is sent to the output control platform. After receiving the output high-risk signal, the output control platform adjusts the output workload of each sub-power supply in the power supply, and at the same time resets the specifications of each sub-power supply, and controls the output of the sub-power supply before the specification reset is qualified;
[0043] If the output feasibility assessment coefficient G during the power supply operation period does not exceed the output feasibility assessment coefficient threshold, it is determined that the output feasibility assessment coefficient analysis during the power supply operation period is normal, an output low risk signal is generated and sent to the output control platform, and a multi-combination circuit analysis signal is generated and sent to the multi-combination circuit analysis unit;
[0044] After receiving the multi-combination circuit analysis signal, the multi-combination circuit analysis unit performs sub-power combination circuit analysis during the real-time operation of the power supply, and performs operation analysis according to sub-power combinations of different specifications to avoid inefficient operation of different circuits caused by abnormal sub-power combinations, affecting the overall operation efficiency of the power supply, while reducing the operation qualification rate of electrical appliances and increasing the risk of wear and tear of electrical appliances;
[0045] Combining sub-power supplies according to the specifications of the sub-power supplies in the current power supply, arbitrarily selecting two sub-power supplies as different circuit combinations, and dividing the combined sub-power supplies in the different circuit combinations into high-quantity power supplies and low-quantity power supplies, that is, relatively high-voltage power supplies and relatively low-voltage power supplies according to the voltage specifications of the sub-power supplies corresponding to the different circuit combinations;
[0046] The maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination is obtained, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation is obtained, and the maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation are compared with the maximum time difference threshold and the output task demand threshold respectively:
[0047] If the maximum time difference between the voltage rising to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination exceeds the maximum time difference threshold, and the output task demand in which the rising order of the sub-power supply combination is inconsistent with the actual sub-power supply circuit operation order during the power supply operation exceeds the output task demand threshold, then it is determined that the current sub-power supply combination has a circuit operation risk, a circuit operation risk signal is generated and sent to the output control platform, and after the output control platform receives the circuit operation risk signal, the output task of the sub-power supply circuit is regulated;
[0048] If during the operation of the sub-power combination, the maximum time difference between the voltage rising to the rated voltage when the high-power supply and the low-power supply are running at the same time exceeds the maximum time difference threshold, and the output task demand that is inconsistent with the sub-power combination rising sequence and the actual sub-power circuit operation sequence during the power supply operation exceeds the output task demand threshold, if any one of these situations occurs only once, it is determined that the current sub-power combination has a circuit operation hazard, a circuit operation detection signal is generated and sent to the output control platform, and after the output control platform receives the circuit operation detection signal, it conducts real-time monitoring and regulation of the sub-power combination when performing the output task;
[0049] If the maximum time difference between the voltage rising to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination does not exceed the maximum time difference threshold, and the output task demand that is inconsistent with the sub-power supply combination rising sequence and the actual sub-power supply circuit operation sequence during the power supply operation does not exceed the output task demand threshold, it is determined that the current sub-power supply combination has circuit operation safety, a circuit operation safety signal is generated and the circuit operation safety signal is sent to the output control platform;
[0050] Example 2
[0051] On the basis of Example 1, this embodiment analyzes and evaluates the delayed operation of the power supply corresponding circuit, so as to determine whether the delayed operation of the power supply is qualified during the current circuit operation, thereby improving the efficiency of power supply output monitoring and control; in this embodiment, synchronization and separation are represented as sub-power supplies processing the same task and non-same tasks;
[0052] The output control platform generates a circuit operation analysis signal and sends the circuit operation analysis signal to the circuit operation analysis unit; the circuit operation analysis unit generates a separate operation analysis signal and a synchronous operation analysis signal, and sends the separate operation analysis signal and the synchronous operation analysis signal to the separate operation analysis unit and the synchronous operation analysis unit respectively;
[0053] After receiving the separate operation analysis signal, the separate operation analysis unit performs a separate delayed operation analysis on the power supply to determine whether the sub-power supply components in the current power supply are operating properly, thereby ensuring the operating efficiency of the power supply, ensuring the feasibility of circuit operation, improving the operating efficiency of electrical appliances and avoiding equipment wear caused by power supply abnormalities;
[0054] The maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the previous operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the sub-power supply combination alternating operation moment when the sub-power supply is separated and delayed are obtained, and the maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the previous operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the sub-power supply combination alternating operation moment when the sub-power supply is separated and delayed are compared with the maximum temperature difference threshold and the overlapping frequency threshold respectively:
[0055] If the maximum temperature difference between the average temperature floating span during the output process of the subsequent sub-power supply and the average temperature floating span during the previous operation of the same sub-power supply during the separate delayed operation of the sub-power supply exceeds the maximum temperature difference threshold, or the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply during the separate delayed operation of the sub-power supply and the moment of the alternating operation of the sub-power supply combination exceeds the overlapping frequency threshold, then it is determined that the separate delayed operation analysis of the sub-power supply is abnormal, and a separate delayed operation inefficiency signal is generated and sent to the circuit operation analysis unit;
[0056] If the maximum temperature difference between the average temperature floating span during the output process of the later-running sub-power supply and the average temperature floating span during the earlier-running operation of the same sub-power supply during the separate delayed operation of the sub-power supply does not exceed the maximum temperature difference threshold, and the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply during the separate delayed operation of the sub-power supply and the moment of the alternating operation of the sub-power supply combination does not exceed the overlapping frequency threshold, then it is determined that the separate delayed operation analysis of the sub-power supply is normal, and a separate delayed operation high-efficiency signal is generated and sent to the output control platform;
[0057] After receiving the synchronous operation analysis signal, the synchronous operation analysis unit performs sub-power supply synchronous delay operation analysis on the power supply, and monitors the operation of the power supply circuit in real time to avoid the circuit delay efficiency being reduced during the synchronous delay process, which makes it impossible to ensure that the electrical appliances can operate at the expected time;
[0058] Obtain the shortened amount of the time difference between the real-time delay duration of the adjacent operating moments of the sub-power supply and the corresponding time difference between the preset delay duration during the sub-power supply synchronization delay operation, as well as the temperature rise rate increase frequency of the sub-power supply corresponding circuit when the number of sub-power supply synchronization delay alternating operations increases during the sub-power supply synchronization delay operation, and compare the shortened amount of the time difference between the real-time delay duration of the adjacent operating moments of the sub-power supply and the corresponding time difference between the preset delay duration and the temperature rise rate increase frequency threshold when the number of sub-power supply synchronization delay alternating operations increases during the sub-power supply synchronization delay operation with the time difference shortened amount threshold and the temperature rise rate increase frequency threshold respectively:
[0059] If the shortening amount of the time difference between the real-time delay time of the adjacent operation moments of the sub-power supply and the preset delay time during the sub-power supply synchronous delay operation exceeds the shortening amount threshold of the time difference, or the temperature rise rate of the sub-power supply corresponding circuit exceeds the temperature rise rate threshold when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, then it is determined that the power supply synchronous delay operation analysis is abnormal, and a synchronous delay operation inefficiency signal is generated and sent to the power supply operation analysis unit;
[0060] If the shortening amount of the time difference between the real-time delay time of the adjacent operation moments of the sub-power supply and the preset delay time during the sub-power supply synchronous delay operation does not exceed the shortening amount threshold of the time difference, and the temperature rise rate of the sub-power supply corresponding circuit does not exceed the temperature rise rate rise frequency threshold when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, then it is determined that the power supply synchronous delay operation analysis is normal, and a synchronous delay operation high-efficiency signal is generated and sent to the power supply operation analysis unit;
[0061] After receiving the synchronous delayed operation inefficiency signal or the separate delayed operation inefficiency signal, the power supply operation analysis unit generates a circuit operation control signal and sends the circuit operation control signal to the output control platform. After receiving the circuit operation control signal, the output control platform performs delayed task execution regulation on the sub-power supply and replans the sub-power supply combination when the current delayed task needs to be executed.
[0062] The above formulas are obtained by collecting a large amount of data and performing software simulation, and a formula close to the actual value is selected. The coefficients in the formula are set by technicians in this field according to actual conditions;
[0063] When the present invention is in use, the power supply output feasibility assessment unit performs output feasibility assessment analysis on the power supply, obtains the output feasibility assessment coefficient within the power supply operation period, generates an output high-risk signal or an output low-risk signal based on the output feasibility assessment coefficient comparison, and sends it to the output control platform; the multi-combination circuit analysis unit performs sub-power supply combination circuit analysis on the real-time operation of the power supply, combines the sub-power supplies according to the specifications of the sub-power supplies in the current power supply, arbitrarily selects two sub-power supplies as different circuit combinations, and divides the combined sub-power supplies in different circuit combinations into high-quantity power supplies and low-quantity power supplies according to the voltage specifications of the sub-power supplies corresponding to different circuit combinations, generates a circuit operation risk signal, a circuit operation detection signal and a circuit operation safety signal based on the analysis, and sends them to the output control platform.
[0064] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A method for controlling the output of a multi-channel combined power supply, characterized in that: The multi-channel combined power supply output control method involves an output control platform, a power supply output feasibility evaluation unit, a multi-combination circuit analysis unit, a circuit operation analysis unit, a separate operation analysis unit, and a synchronous operation analysis unit; the specific control method is as follows: The power supply output feasibility assessment unit performs output feasibility assessment and analysis on the power supply, analyzes the power supply, and divides the power supply into i sub-power supplies, where i is a natural number greater than 1, obtains the output feasibility assessment coefficient within the power supply operation period, generates an output high-risk signal or an output low-risk signal based on the output feasibility assessment coefficient, and sends it to the output control platform; The multi-combination circuit analysis unit performs sub-power combination circuit analysis during the real-time operation of the power supply, combines sub-power supplies according to the specifications of the sub-power supplies in the current power supply, arbitrarily selects two sub-power supplies as different circuit combinations, and divides the combined sub-power supplies in different circuit combinations into high-volume power supplies and low-volume power supplies according to the voltage specifications of the sub-power supplies corresponding to different circuit combinations. Based on the analysis, a circuit operation risk signal, a circuit operation detection signal, and a circuit operation safety signal are generated and sent to the output control platform; The operation method of the power output feasibility assessment unit is as follows: Obtain the increase in the average power constant duration floating frequency when the adjacent sub-power supplies output at the same time during the power supply operation period, and the rising span value of the operating starting ambient temperature of the subsequent sub-power supply when the adjacent sub-power supplies output at non-simultaneous times; obtain the excess of the actual operating environment peak voltage and rated voltage of each sub-power supply during the power supply operation period; obtain the output feasibility assessment coefficient during the power supply operation period through analysis; Compare the output feasibility assessment coefficient within the power supply operation period with the output feasibility assessment coefficient threshold: If the output feasibility assessment coefficient during the power supply operation period exceeds the output feasibility assessment coefficient threshold, the output feasibility assessment coefficient analysis during the power supply operation period is determined to be abnormal, an output high risk signal is generated and the output high risk signal is sent to the output control platform; If the output feasibility assessment coefficient during the power supply operation period does not exceed the output feasibility assessment coefficient threshold, it is determined that the output feasibility assessment coefficient analysis during the power supply operation period is normal, an output low risk signal is generated and sent to the output control platform; The operation method of the multi-combinatorial circuit analysis unit is as follows: The maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination is obtained, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation is obtained, and the maximum time difference between the voltage rising to the rated voltage when the high power supply and the low power supply are running at the same time during the operation of the sub-power supply combination, and the output task demand when the sub-power supply combination rising sequence is inconsistent with the actual sub-power supply circuit operation sequence during the power supply operation are compared with the maximum time difference threshold and the output task demand threshold respectively: If the maximum time difference between the voltage rising to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination exceeds the maximum time difference threshold, and the output task demand that is inconsistent with the sub-power supply combination rising sequence and the actual sub-power supply circuit operation sequence during the power supply operation exceeds the output task demand threshold, a circuit operation risk signal is generated and sent to the output control platform; If the maximum time difference between the voltage rising to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination exceeds the maximum time difference threshold, and the output task demand that is inconsistent with the sub-power supply combination rising sequence and the actual sub-power supply circuit operation sequence during the power supply operation exceeds the output task demand threshold, if any one of the situations only occurs, a circuit operation detection signal is generated and sent to the output control platform; If the maximum time difference for the voltage to rise to the rated voltage when the high-power supply and the low-power supply are running at the same time during the operation of the sub-power supply combination does not exceed the maximum time difference threshold, and the output task demand in which the rising order of the sub-power supply combination is inconsistent with the actual sub-power supply circuit operation order during the power supply operation does not exceed the output task demand threshold, a circuit operation safety signal is generated and sent to the output control platform.
2. A method for controlling the output of a multi-channel combined power supply according to claim 1, characterized in that: The circuit operation analysis unit generates a separate operation analysis signal and a synchronous operation analysis signal, and sends the separate operation analysis signal and the synchronous operation analysis signal to the separate operation analysis unit and the synchronous operation analysis unit respectively; The separate operation analysis unit performs a sub-power supply separate delayed operation analysis on the power supply, and the synchronous operation analysis unit performs a sub-power supply synchronous delayed operation analysis on the power supply.
3. A method for controlling the output of a multi-channel combined power supply according to claim 2, characterized in that: The method of running the analysis unit separately is as follows: The maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the first operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuits of adjacent sub-power supplies when the sub-power supply is separated and delayed and the sub-power supply combination alternating operation moment are obtained, and the maximum temperature difference between the average temperature floating span during the output of the subsequent sub-power supply when the sub-power supply is separated and delayed and the average temperature floating span during the first operation of the same sub-power supply, as well as the overlapping frequency of the power supply fluctuation moment of the corresponding circuits of adjacent sub-power supplies when the sub-power supply is separated and delayed and the sub-power supply combination alternating operation moment are compared with the maximum temperature difference threshold and the overlapping frequency threshold, respectively.
4. A method for controlling the output of a multi-channel combined power supply according to claim 3, characterized in that: If the maximum temperature difference between the average temperature floating span during the output process of the later-running sub-power supply and the average temperature floating span during the earlier-running sub-power supply when the sub-power supply is separately delayed exceeds the maximum temperature difference threshold, or the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the moment of the alternating operation of the sub-power supply combination when the sub-power supply is separately delayed exceeds the overlapping frequency threshold, then a separate delayed operation inefficiency signal is generated and sent to the circuit operation analysis unit; If the maximum temperature difference between the average temperature floating span during the output process of the later running sub-power supply and the average temperature floating span during the earlier running of the same sub-power supply during the separate delayed operation of the sub-power supply does not exceed the maximum temperature difference threshold, and the overlapping frequency of the power supply fluctuation moment of the corresponding circuit of the adjacent sub-power supply and the alternating operation moment of the sub-power supply combination during the separate delayed operation of the sub-power supply does not exceed the overlapping frequency threshold, then a separate delayed operation high-efficiency signal is generated and sent to the output control platform.
5. A method for controlling the output of a multi-channel combined power supply according to claim 2, characterized in that: The operation method of the synchronous operation analysis unit is as follows: Obtain the shortened amount of the time difference between the real-time delay duration of adjacent operating moments of the sub-power supply and the preset delay duration during the sub-power supply synchronous delay operation, as well as the temperature rise rate increase frequency of the sub-power supply corresponding circuit when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, and compare the shortened amount of the time difference between the real-time delay duration of adjacent operating moments of the sub-power supply and the preset delay duration during the sub-power supply synchronous delay operation, as well as the temperature rise rate increase frequency of the sub-power supply corresponding circuit when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation with the time difference shortened amount threshold and the temperature rise rate increase frequency threshold, respectively.
6. A method for controlling the output of a multi-channel combined power supply according to claim 5, characterized in that: If the difference between the real-time delay duration of the adjacent operation moments of the sub-power supply and the preset delay duration during the sub-power supply synchronization delay operation is shortened by more than the time difference shortening threshold, or the temperature rise rate of the sub-power supply corresponding circuit exceeds the temperature rise rate rising frequency threshold when the number of sub-power supply synchronization delay alternating operations increases during the sub-power supply synchronization delay operation, a synchronization delay operation inefficiency signal is generated and sent to the power supply operation analysis unit; If the shortening amount of the time difference between the real-time delay time at the adjacent operating moments of the sub-power supply and the preset delay time during the sub-power supply synchronous delay operation does not exceed the time difference shortening amount threshold, and the temperature rise rate frequency of the sub-power supply corresponding circuit does not exceed the temperature rise rate rising frequency threshold when the number of sub-power supply synchronous delay alternating operations increases during the sub-power supply synchronous delay operation, a synchronous delay operation high-efficiency signal is generated and sent to the power supply operation analysis unit.