A method for processing an impeller

Through the combination of fixture and CNC milling technology, the problems of difficult clamping and low efficiency in impeller processing are solved, efficient and precise impeller processing is achieved, and production efficiency and finished product quality are improved.

CN118517433BActive Publication Date: 2024-10-11潍坊富源增压器有限公司
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202410971168.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-10-11
Estimated Expiration
2044-07-19

AI Technical Summary

Technical Problem

In the existing technology, there are difficulties in clamping and multiple installations and disassemblies during the processing of impellers, which results in low production efficiency. Moreover, the complex shape of the impeller results in complicated processing techniques, which affects production efficiency.

Method used

Clamps 1 and 2 are used for clamping and fixation. Combined with CNC milling technology, the machining process is rough turning first and then fine turning. The impeller is processed using cutting tools, chamfering tools and special reamers. The setting of the fixed rod and the elastic clamping The use of claws ensures clamping strength and processing accuracy.

Benefits of technology

It improves the efficiency and accuracy of impeller processing, reduces production time, ensures the mechanical strength and integrity of the finished product, and improves production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118517433B_ABST
    Figure CN118517433B_ABST
Patent Text Reader

Abstract

The present invention is applicable to the field of impeller production and processing, and provides a processing method for an impeller, wherein the impeller is integrally formed and comprises a wheel disc; a plurality of long blades and splitter blades are fixedly connected to the wheel disc, and the plurality of long blades and splitter blades are distributed on the wheel disc at intervals; the long blades are in the shape of a three-dimensional curved surface, the top of the long blades adopts a leading edge curve structure, the shape of the splitter blades is a swept leading edge blade type, and the long blades and the splitter blades are arranged in a radial curve with the central axis of the wheel disc as the center; a fixing rod is fixedly connected to the top of the wheel disc; thereby, a clamp 1 fixes the impeller by clamping the fixing rod, and a clamp 2 fixes the wheel disc by using an elastic claw, which can ensure firm clamping and complete the turning of the wheel disc by the tool, and can also cause no mechanical damage to the impeller, and the setting of the fixing rod is convenient for processing, and the subsequent cutting of the fixing rod eliminates the clamping marks, thereby ensuring the overall integrity of the impeller finished product.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention is applicable to the field of impeller production and processing, and provides an impeller processing method. Background Art

[0002] The compressor impeller is an important part of the compressor. It is a rotating part composed of multiple blades. The function of the compressor impeller is to generate airflow through rotation, compress the air and push it to the next working part, such as the combustion chamber or turbine. The design and rotation speed of the impeller can affect the performance and efficiency of the compressor. In aircraft engines, turbochargers and other equipment that compresses air, compressor impellers play an important role.

[0003] In the prior art, the cast impeller blank is not easy to clamp. At the same time, since the impeller is formed in one piece and the impeller itself has a complex shape, the impeller needs to be installed, clamped and disassembled many times during multi-process processing. The processing technology is complicated, which leads to bottlenecks or unnecessary waiting time in the production process, affecting production efficiency. Summary of the invention

[0004] In view of the above-mentioned defects, the object of the present invention is to provide a method for processing an impeller, the purpose of which is to solve the problems raised in the background technology, comprising the following steps:

[0005] S1. Casting the impeller blank, and heat treating and testing the performance of the impeller casting blank;

[0006] S2. Clamp the impeller blank and CNC mill the wheel disc; process the circumference of the wheel disc and the end face of the wheel disc away from the fixed rod;

[0007] S3. Clamp the impeller blank and CNC mill the long blades and splitter blades;

[0008] The step S3 comprises:

[0009] S31. Use a cutting tool to cut the fixed rod evenly, leaving a 0.2mm finishing margin, so that the inner hole passes through the impeller;

[0010] S32. Use a chamfering cutter to turn the inner hole on the side of the wheel away from the rear chamfer to obtain a front chamfer; the spindle speed is 2400r / min;

[0011] S33. Fine-turn the end surface of the impeller away from the wheel disc and control the length of the impeller;

[0012] S34. Rough turning of the impeller R arc; use an external rough turning tool to rough turn the impeller R arc and leave a 0.2mm finishing allowance;

[0013] S35. Fine turning of impeller R arc; speed: 2000r / min, feed rate: 0.1mm / rpt;

[0014] S36. Turn the fixed rod to obtain the leading edge of the impeller;

[0015] The impeller includes a wheel disc, on which a plurality of long blades and splitter blades are fixedly connected, and the plurality of long blades and splitter blades are distributed on the wheel disc at intervals;

[0016] The long blade is in the shape of a three-dimensional curved surface, the top of the long blade adopts a leading edge curve structure, the shape of the splitter blade is a curved leading edge blade type, and the long blade and the splitter blade are arranged in a radial curve with the central axis of the wheel disc as the center;

[0017] A fixing rod is fixedly connected to the top of the wheel disc; the wheel disc, long blades, splitter blades and fixing rod are integrally formed, an inner hole penetrating the wheel disc is provided inside the wheel disc, a front chamfer is provided at the first end of the inner hole, and a rear chamfer is provided at the second end of the inner hole.

[0018] Furthermore, the step S1 includes:

[0019] S11. The blank and the sample block are heat treated, and the blank and the sample block are removed after the heat treatment;

[0020] The heat treatment method is:

[0021] S111. The blank and the sample block are placed in a heating furnace with a starting temperature of 300-350°C. The blank and the sample block are slowly heated to 580°C by high temperature normalizing. The continuous heating time is controlled to be 10 minutes. When the temperature reaches 580°C, the blank and the sample block are taken out for full annealing treatment.

[0022] S112. Take out the hot blank and the sample block and put them into the holding furnace. The holding furnace temperature is maintained at 180°C. Keep the temperature for 3 hours to allow the blank and the sample block to cool slowly. Then take them out and slowly put the blank and the sample block into a clean water pool with still water under the support of mechanical equipment.

[0023] S12. Testing the mechanical properties of the specimen;

[0024] The mechanical properties of the sample block should meet the following requirements: hardness 130~140HB, yield strength 450~500MPa, and tensile strength greater than or equal to 400MPa.

[0025] Furthermore, the step S112 of slowly placing the blank and the sample block into a clean water pool with still water also includes the following steps: when the impeller blank enters the water, the impeller disc faces downward and touches the water first, and the time for the impeller blank to gradually enter the water until the top is submerged is 5-8 seconds, and after the pool water completely submerges the impeller blank, the equipment is started to stir the pool water to quickly cool the blank and the sample block to room temperature.

[0026] Furthermore, in step S2, the impeller blank is clamped using a clamp; the clamp comprises a fixed plate and a pull rod installed on the rotating part of the machine tool, the fixed plate is fixedly connected to a clamp body at one end away from the machine tool, and a guide positioning sleeve and a guide sleeve are sleeved inside the clamp body; the pull rod, the guide positioning sleeve and the guide sleeve are fixedly connected; a positioning sleeve is fixedly connected inside the clamp body, and a positioning end cover is fixedly connected to the end of the guide sleeve away from the pull rod; one end of the positioning sleeve is fixedly connected to the clamp body, and the other end is fixedly connected to a plurality of elastic clamps, and the elastic clamps are abutted against the positioning end cover, and the abutting portion is an inclined surface.

[0027] Furthermore, the step S2 comprises:

[0028] S21. Rough turn the outer circle of the wheel disc; use an external cylindrical cutter to rough turn the outer circle and leave a 0.2mm finishing allowance;

[0029] S22. Roughen the wheel back of the wheel disc; use an external cylindrical cutter to roughen the wheel back and leave a 0.2mm finishing allowance;

[0030] S23. Drill the center hole to obtain the inner hole. The drilling depth is the total height of the impeller + 3.5 mm with a 0.1 mm margin. The drill speed is 1500 r / min and the feed rate is 0.15 mm / rpt.

[0031] S24. Finish turning the outer circle and wheel back;

[0032] S25. Ream the inner hole; according to the requirements of the inner hole size of the impeller, a special reamer is customized. The front 2mm of the reamer is for rough reaming, and the rear part is for fine reaming, so as to achieve rough and fine reaming at the same time; reamer speed: 1000r / min, feed rate 0.1m / rpt.

[0033] Further, the step S23 includes:

[0034] S231. Turn the inner hole away from the fixed rod, use an internal coolant straight groove drill to control the chamfer size of the hole, and obtain a back chamfer;

[0035] S232. Check the drill bit for broken bits to prevent drilling without an alarm due to drill bit damage, which would cause the reamer to become scrapped.

[0036] Furthermore, in step S3, the impeller blank is clamped using a second clamp; the second clamp includes a second fixed plate and a second pull rod fixedly connected to the rotating part of the machine tool; a second clamp is installed at one end of the second fixed plate away from the rotating part of the machine tool; the interior of the second fixed plate is through-connected, and the second pull rod is arranged inside the second fixed plate, and the interior of the second clamp is sleeved with a second guide positioning sleeve and a second guide sleeve, and the second pull rod, the second guide positioning sleeve and the second guide sleeve are fixedly connected by bolts; the end of the second guide sleeve away from the second guide positioning sleeve is fixedly connected with no less than two elastic claws; the outer side of the elastic claw abuts against the second clamp, and the abutting portion is an inclined surface.

[0037] The advantages of processing the impeller through the above process are:

[0038] 1. The setting of the fixing rod can facilitate the processing of the impeller in step S2. The fixture fixes the impeller by clamping the fixing rod, which can not only ensure the clamping is firm and complete the turning of the impeller by the tool, but also prevent mechanical damage to the impeller and ensure the mechanical strength of the finished impeller.

[0039] 2. The second clamp uses elastic claws to fix the impeller, which can apply the clamping force to the part with the highest overall strength of the impeller. It can not only ensure the clamping strength, but also ensure that the impeller finished product will not be mechanically damaged when the impeller end is processed.

[0040] 3. The setting of the fixing rod is convenient for processing in step S2, and the fixing rod is cut evenly by the cutting tool in the subsequent step S3, which eliminates the clamping marks in step S2 and ensures the overall integrity of the impeller product.

[0041] 4. In both steps S2 and S3, the processing technology of rough turning first and then fine turning is adopted, which can ensure both the processing accuracy and processing efficiency, greatly shorten the production time and improve the production efficiency.

[0042] 5. Special reamer, the front 2mm of the reamer is for rough reaming, and the rear part is for fine reaming, so as to achieve rough and fine reaming at the same time, reducing the original two processing steps to one processing, further improving production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 is a schematic diagram of the impeller structure;

[0044] Figure 2 is a schematic diagram of the impeller cross section;

[0045] Figure 3 This is a schematic diagram of the first end of the finished impeller;

[0046] Figure 4 This is a schematic diagram of the second end of the finished impeller;

[0047] Figure 5 This is an internal cross-sectional view of the fixture;

[0048] Figure 6 is a cross-sectional view of positioning jacket 1;

[0049] Figure 7 for Figure 6 Schematic diagram of AA direction;

[0050] Figure 8 This is the internal cross-sectional view of the second fixture;

[0051] Fig. 9 is a cross-sectional view of the guide sleeve 2;

[0052] In the figure: 11-fixed rod; 121-long blade; 122-dividing blade; 13-wheel disc; 14-inner hole; 141-front chamfer; 142-rear chamfer; 15-impeller leading edge;

[0053] 21-a fixed plate; 22-a pull rod; 23-a guide sleeve; 24-a guide sleeve; 25-a clamping body; 26-a positioning end cover; 27-a positioning sleeve; 271-an elastic clamp;

[0054] 31-two fixed plates; 32-two pull rods; 33-two guide and positioning sleeves; 34-two guide sleeves; 341-elastic claws; 342-sealing oil ring; 35-two clamp bodies; 36-positioning seat. DETAILED DESCRIPTION

[0055] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0056] In the description of the invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0057] In the description of the invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the invention can be understood according to specific circumstances.

[0058] See also Figure 1-9 The object of the present invention is to provide an impeller, comprising a wheel disc 13, on which a plurality of long blades 121 and splitter blades 122 are arranged, and the plurality of long blades 121 and splitter blades 122 are distributed on the wheel disc 13 at intervals;

[0059] The long blade 121 is in the shape of a three-dimensional curved surface, and the top of the long blade 121 adopts a leading edge curved structure. The shape of the splitter blade 122 is a curved leading edge blade type. The curved leading edge blade type design can ensure that its outlet flow field is more uniform, thereby making the airflow more stable. The long blade 121 and the splitter blade 122 are arranged in a radial curve with the central axis of the wheel disc 13 as the center. The top of the wheel disc 13 is fixedly connected with a fixing rod 11. The wheel disc 13, the long blade 121, the splitter blade 122 and the fixing rod 11 are integrally formed and connected.

[0060] The above impeller is processed by the following method:

[0061] S1. Cast the impeller blank, and perform heat treatment and performance testing on the impeller casting blank. The impeller is made of high-strength, wear-resistant special aluminum alloy material, with good wear resistance, corrosion resistance and high temperature performance, which can meet the requirements of the compressor under high-speed rotation and high temperature and high pressure environment. It includes the following steps:

[0062] S11. Heat-treat the blank and the sample block, and take out the blank and the sample block after the heat treatment; the sample block is a test sample block produced in the same batch as the blank.

[0063] The heat treatment method is:

[0064] S111. The blank and the sample block are sent into a heating furnace with an initial furnace temperature of 300-350°C. Both are slowly heated to 580°C through high-temperature normalizing. The continuous heating time is controlled to be about 10 minutes. When the temperature reaches 580°C, the blank and the sample block are taken out for full annealing treatment.

[0065] S112. Take out the high-temperature blank and sample block and put them into a heat-insulating furnace. The temperature of the heat-insulating furnace is maintained at about 180°C. The temperature is maintained for 3 hours to allow the blank and the sample block to cool slowly. Then both are taken out and slowly placed into a clean water pool with still water under the support of mechanical equipment. Here, it is emphasized that when the impeller blank enters the water, the wheel 13 facing downward touches the water first. The time for the impeller blank to gradually enter the water until the top is submerged is 5-8 seconds. After the pool water completely submerges the impeller blank, start the equipment to stir the pool water to quickly cool the blank and the sample block to room temperature.

[0066] S12. Testing the mechanical properties of the specimen;

[0067] The mechanical properties of the sample block should meet the following requirements: hardness 130~140HB, yield strength 450~500MPa, and tensile strength greater than or equal to 400MPa.

[0068] The above heat treatment method for the impeller blank has the following beneficial effects:

[0069] The slow normalizing heating method in step S111 can make the overall temperature of the material uniform. Usually, the initial temperature of the heating furnace for high-temperature normalizing heating is set at about 500°C. Since the connection between the impeller blades and the wheel disc 13 is at a stress concentration point, an excessively high initial furnace temperature at this time will cause slight deformation due to stress divergence at the connection between the blades and the wheel disc 13. However, through this method, after the blank is placed in a 300-350°C environment for a period of time using mechanical equipment, the internal stress of the material during heat treatment is uniformly diverged, preventing the material from being slightly deformed by heat at the stress concentration point, and ensuring the high precision requirements of the material.

[0070] The annealing method for the blank and the sample block in step S112 is full annealing treatment using an incubator. In the process of full annealing with an incubator, the stress and crystal defects in the metal material can be further eliminated, and the comprehensive properties of the material such as ductility and plasticity can be improved. In the final stage of the full annealing treatment, that is, after the temperature is slowly reduced to 180°C, the blank and the sample block are slowly placed in a clean water pool with still water under the support of mechanical equipment. This step can be generally called low-temperature quenching of the workpiece, which is essentially the same as low-temperature tempering. The purpose is to maintain the high hardness and wear resistance of the workpiece and reduce the residual stress and brittleness of the workpiece. The stress was sufficiently diverged in the previous slow normalizing heating method. This step of tempering treatment at 180°C can save the tempering process of the workpiece while strengthening the hardness and wear resistance of the workpiece, and can save a lot of processing time. At the same time, during the low-temperature quenching process, the wheel disc 13 first touches the water downward to quench the water temperature slightly. The hardness and wear resistance of the wheel disc 13 structure increase under quenching, and the quenching degree when the blade is gradually immersed in clean water will reduce the effect. This is to ensure that the blade has a certain softness and reduce the rigidity of the blade tip, which can effectively avoid the blade from breaking during use due to excessive rigidity. After the pool water completely submerges the impeller blank, start the equipment to stir the pool water. This method can quickly cool the blank and the sample block to room temperature.

[0071] Specifically, the hardness of the blank and the specimen tends to 140HB, the yield strength tends to 500MPa, and the tensile strength is greater than or equal to 400MPa.

[0072] S2. Clamp the impeller blank and CNC mill the wheel disc 13 structure.

[0073] See also Figure 5-7 The impeller blank is clamped using a fixture, and the wheel disc 13 is turned.

[0074] The clamp 1 includes a fixed plate 21 and a pull rod 22 installed on the rotating part of the machine tool. The fixed plate 21 is connected to the output end of the machine tool by bolts, the middle part of the fixed plate 21 is passed through, and the end of the pull rod 22 away from the machine tool passes through the fixed plate 21 from the middle part; the end of the fixed plate 21 away from the machine tool is fixedly connected with a clamp body 25 by bolts, the middle part of the clamp body 25 is passed through, and the pull rod 22 is arranged inside the clamp body 25, and the inside of the clamp body 25 is sleeved with a guide positioning sleeve 23 and a guide sleeve 24.

[0075] The pull rod 22 , the guide and positioning sleeve 23 and the guide sleeve 24 are connected as a whole by bolts, and the guide and positioning sleeve 23 and the guide sleeve 24 are both slidably connected inside the clamp body 25 .

[0076] A positioning sleeve 27 is fixedly connected inside the clamp body 25, and one end of the guide sleeve 24 away from the pull rod 22 is connected to the positioning end cover 26 through bolts. One end of the positioning sleeve 27 is fixedly connected to the clamp body 25, and the other end is fixedly connected to four elastic clamps 271 with elasticity. The elastic clamps 271 abut against the positioning end cover 26, and the abutment is an inclined surface. When the pull rod 22 is pulled backward, it can drive the guide positioning sleeve 23 to move backward, and the guide positioning sleeve 23 drives the guide sleeve 24 to move backward. The guide sleeve 24 drives the positioning end cover 26 to pull backward. The inclined surface of the positioning end cover 26 will squeeze the elastic clamps 271 abutting against it toward the axial direction of the impeller, so that the positioning sleeve 27 clamps the fixed rod 11 of the impeller, thereby completing the clamping. The advantage of this clamping processing method is that clamping the fixed rod 11 will not affect the overall shape of the impeller.

[0077] After the clamping is completed, the circumference of the wheel disc 13 and the end surface of the wheel disc 13 away from the fixing rod 11 are processed. The specific steps are:

[0078] S21. Rough-turn the outer circle of the wheel disc 13; use an outer circle cutter to rough-turn the outer circle and leave a 0.2mm finishing allowance.

[0079] S22. Roughen the wheel back of the wheel disc 13; use an external cylindrical cutter to rough turn the wheel back and leave a 0.2mm finishing allowance.

[0080] S23. Drilling center hole, see Figure 2 After drilling, an inner hole 14 is obtained. The drilling depth is the total height of the impeller + 3.5 mm with a 0.1 mm margin. The drill speed is 1500 r / min and the feed rate is 0.15 mm / rpt.

[0081] S231.See Figure 4 , the inner hole 14 located on the side of the wheel disc 13 away from the fixed rod 11 is turned, and the chamfer size of the hole is controlled by an internal cooling straight groove drill to obtain a rear chamfer 142;

[0082] S232. Check the drill bit for broken bits to prevent drilling without an alarm due to drill bit damage, which would cause the reamer to become scrapped.

[0083] S24. Finish turning the outer circle and wheel back.

[0084] S25. Ream the inner hole.

[0085] According to the requirements of the inner hole size of the impeller, a special reamer is customized. The front 2mm of the reamer is for rough reaming, and the rear part is for fine reaming, so as to achieve rough and fine reaming at the same time. Speed: 1000r / min, feed rate 0.1m / rpt.

[0086] S3. Clamp the impeller blank and perform CNC milling to process the long blades 121 and the splitter blades 122.

[0087] See also Figure 6 The long blades 121 and the splitter blades 122 are processed and clamped using a second fixture.

[0088] The second clamp includes a second fixed plate 31 and a second pull rod 32 fixedly connected to the rotating part of the machine tool. The end of the second fixed plate 31 away from the rotating part of the machine tool is fixedly connected to a second clamp body 35 by bolts; a positioning seat 36 is installed inside the second clamp body 35 by bolts.

[0089] The middle of the second fixed plate 31 is through, and the second pull rod 32 is arranged inside the second fixed plate 31. The second guide sleeve 33 and the second guide sleeve 34 are sleeved inside the second clamp body 35. One end of the second guide sleeve 33 is fixedly connected to the second pull rod 32, and the other end is fixedly connected to the second guide sleeve 34. The second pull rod 32, the second guide sleeve 33 and the second guide sleeve 34 are fixedly connected by bolts; the positioning seat 36 is sleeved inside the second guide sleeve 34. Two sealing oil rings 342 are sleeved on the second guide sleeve 34, one of which is arranged between the second guide sleeve 34 and the second clamp body 35, and the other is arranged between the second guide sleeve 34 and the positioning seat 36; the end of the second guide sleeve 34 away from the second guide sleeve 33 is fixedly connected with no less than two elastic claws 341.

[0090] The outer side of the elastic claw 341 abuts against the clamp body 35, and the abutment between the elastic claw 341 and the clamp body 35 is a conical surface. When the pull rod 32 is pulled backward, it can drive the guide positioning sleeve 33 to move backward, and the guide positioning sleeve 33 drives the guide sleeve 34 and the elastic claw 341 to move backward. The abutting conical surface will squeeze the elastic claw 341 toward the axial direction of the impeller, so that the elastic claw 341 clamps the impeller disc 13, thereby completing the clamping.

[0091] S31. Use a cutting tool to cut the fixed rod 11 evenly, leaving a 0.2mm finishing allowance, so that the inner hole 14 passes through the impeller.

[0092] S32. See Figure 3 , a chamfering cutter is used to turn the inner hole 14 on the side of the wheel disc 13 away from the rear chamfer 142 to obtain a front chamfer 141; the spindle speed is 2400r / min.

[0093] S33. Fine-turn the impeller away from one end surface of the wheel disc 13 and control the length of the impeller.

[0094] S34. Rough turn the impeller R arc; use an external rough turning tool to rough turn the impeller RR arc and leave a 0.2mm finishing allowance.

[0095] S35. Fine turning of impeller R arc; speed: 2000r / min, feed rate: 0.1mm / rpt.

[0096] S36.See Figure 3 , the fixed rod 11 is turned to obtain the impeller leading edge 15.

[0097] The advantages of processing the impeller through the above process are:

[0098] 1. The setting of the fixing rod 11 can facilitate the processing of the wheel disc 13 in step S2. The fixture fixes the impeller by clamping the fixing rod 11, which can ensure firm clamping and complete the turning of the wheel disc 13 by the tool, and can also prevent mechanical damage to the impeller, thereby ensuring the mechanical strength of the finished impeller.

[0099] 2. The second clamp uses the elastic claws 341 to fix the wheel disc 13, and can apply the clamping force to the part of the impeller with the highest overall strength, which can not only ensure the clamping strength, but also ensure that the impeller product is not mechanically damaged when the impeller end is processed.

[0100] 3. The arrangement of the fixing rod 11 is convenient for processing in step S2, and the fixing rod 11 is cut evenly by the cutting tool in the subsequent step S3, thereby eliminating the clamping marks in step S2 and ensuring the overall integrity of the finished impeller.

[0101] 4. In both steps S2 and S3, the processing technology of rough turning first and then fine turning is adopted, which can ensure both the processing accuracy and processing efficiency, greatly shorten the production time and improve the production efficiency.

[0102] 5. Special reamer, the front 2mm of the reamer is for rough reaming, and the rear part is for fine reaming, so as to achieve rough and fine reaming at the same time, reducing the original two processing steps to one processing, further improving production efficiency.

[0103] It is obvious to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above, and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects.

[0104] Of course, the present invention may have many other embodiments. Without departing from the spirit and essence of the present invention, technicians familiar with the field may make various corresponding changes and deformations based on the present invention, but these corresponding changes and deformations should all fall within the scope of protection of the present invention.

Claims

1. A method for processing an impeller, characterized in that: The following steps are involved: S1. Casting the impeller blank, and heat treating and testing the performance of the impeller casting blank; S2. Clamping the impeller blank, CNC milling the disc (13); processing the circumference of the disc (13) and the end surface of the disc (13) away from the fixed rod (11); S3. Clamp the impeller blank and perform CNC milling on the long blades (121) and the splitter blades (122); The step S3 comprises: S31. Use a cutting tool to cut the fixing rod (11) evenly, leaving a 0.2 mm finishing margin, so that the inner hole (14) passes through the impeller; S32. Using a chamfering cutter, the inner hole (14) is turned on the side of the wheel (13) away from the rear chamfer (142) to obtain a front chamfer (141); the spindle speed is 2400r / min; S33. Fine turning the impeller away from one end surface of the wheel disc (13), and controlling the length of the impeller; S34. Rough turning of the impeller R arc; use an external rough turning tool to rough turn the impeller R arc and leave a 0.2mm finishing allowance; S35. Fine turning of impeller R arc; speed: 2000r / min, feed rate: 0.1mm / rpt; S36. Turning the fixed rod (11) to obtain the impeller leading edge (15); The impeller comprises a wheel disc (13), a plurality of long blades (121) and splitter blades (122) being fixedly connected to the wheel disc (13), and the plurality of long blades (121) and splitter blades (122) being distributed on the wheel disc (13) at intervals; The long blade (121) is in the shape of a three-dimensional curved surface, the top of the long blade (121) adopts a leading edge curved structure, the shape of the splitter blade (122) is a swept leading edge blade type, and the long blade (121) and the splitter blade (122) are both arranged in a radial curved line with the central axis of the wheel disc (13) as the center; A fixing rod (11) is fixedly connected to the top of the wheel disc (13); the wheel disc (13), the long blades (121), the splitter blades (122) and the fixing rod (11) are integrally formed; an inner hole (14) penetrating the wheel disc (13) is provided inside the wheel disc (13); a front chamfer (141) is provided at a first end of the inner hole (14); and a rear chamfer (142) is provided at a second end of the inner hole (14).

2. The impeller processing method according to claim 1, characterized in that: The step S1 comprises: S11. The blank and the sample block are heat treated, and the blank and the sample block are removed after the heat treatment; The heat treatment method is: S111. The blank and the sample block are sent to a heating furnace, the starting temperature of the heating furnace is 300-350°C, and the two are slowly heated to 580°C by high-temperature normalizing. The continuous heating time is controlled to be 10 minutes. When the temperature reaches 580°C, the blank and the sample block are taken out for full annealing treatment; S112. Take out the hot blank and the sample block and put them into the holding furnace. The holding furnace temperature is maintained at 180°C. Keep the temperature for 3 hours to allow the blank and the sample block to cool slowly. Then take them out and slowly put the blank and the sample block into a clean water pool with still water under the support of mechanical equipment. S12. Testing the mechanical properties of the specimen; The mechanical properties of the sample block should meet the following requirements: hardness 130~140HB, yield strength 450~500MPa, and tensile strength greater than or equal to 400MPa.

3. The impeller processing method according to claim 2, characterized in that: The step S112 of slowly placing the blank and the sample block into a clean water tank with still water also includes the following steps: When the impeller blank enters the water, the wheel disc (13) faces downward and touches the water first. The time for the impeller blank to gradually enter the water until the top is submerged is 5-8 seconds. After the pool water completely submerges the impeller blank, the equipment is started to stir the pool water so that the blank and the sample block are quickly cooled to room temperature.

4. The impeller processing method according to claim 1, characterized in that: In step S2, the impeller blank is clamped using a clamp 1; The clamping device comprises a fixed plate (21) and a pull rod (22) mounted on a rotating part of a machine tool; an end of the fixed plate (21) away from the machine tool is fixedly connected to a clamping body (25); a guide positioning sleeve (23) and a guide sleeve (24) are sleeved inside the clamping body (25); the pull rod (22), the guide positioning sleeve (23) and the guide sleeve (24) are fixedly connected; A positioning sleeve (27) is fixedly connected inside the clamp body (25), and a positioning end cap (26) is fixedly connected at one end of the guide sleeve (24) away from the pull rod (22); One end of the positioning clamp sleeve (27) is fixedly connected to the clamp body (25), and the other end is fixedly connected to a plurality of elastic clamp heads (271) having elasticity, and the elastic clamp heads (271) are in contact with the positioning end cover (26), and the contact portion is an inclined surface.

5. The impeller processing method according to claim 4, characterized in that: The step S2 comprises: S21. Rough turning the outer circle of the wheel (13); rough turning the outer circle with an outer cylindrical cutter and leaving a 0.2mm finishing allowance; S22. Roughing the wheel back of the wheel disc (13); using an external cylindrical cutter to rough turn the wheel back and leaving a 0.2mm finishing allowance; S23. Drill the center hole, and obtain the inner hole (14) after drilling. The drilling depth is the total height of the impeller + 3.5 mm and a 0.1 mm margin is left. The drill speed is 1500 r / min and the feed rate is 0.15 mm / rpt. S24. Finish turning the outer circle and wheel back; S25. Ream the inner hole; according to the requirements of the inner hole size of the impeller, a special reamer is customized. The front 2mm of the reamer is for rough reaming, and the rear part is for fine reaming, so as to achieve rough and fine reaming at the same time; reamer speed: 1000r / min, feed rate 0.1m / rpt.

6. The impeller processing method according to claim 5, characterized in that: The step S23 comprises: S231. Turning the inner hole (14) away from the fixed rod (11) side, using an internal coolant straight groove drill to control the chamfer size of the hole, to obtain a rear chamfer (142); S232. Check the drill bit for broken bits to prevent the drill bit from being damaged without an alarm and causing the reamer to be scrapped.

7. The impeller processing method according to claim 1, characterized in that: In step S3, the impeller blank is clamped by a second clamp; the second clamp comprises a second fixed plate (31) and a second pull rod (32) fixedly connected to the rotating part of the machine tool; A second clamping body (35) is installed at one end of the second fixed plate (31) away from the rotating part of the machine tool; the interior of the second fixed plate (31) is connected, and the second pull rod (32) is arranged inside the second fixed plate (31); the interior of the second clamping body (35) is sleeved with a second guide positioning sleeve (33) and a second guide sleeve (34); the second pull rod (32), the second guide positioning sleeve (33) and the second guide sleeve (34) are fixedly connected by bolts; One end of the second guide sleeve (34) away from the second guide positioning sleeve (33) is fixedly connected to at least two elastic claws (341); the outer sides of the elastic claws (341) abut against the second clamp body (35), and the abutting part is an inclined surface.

Citation Information

Patent Citations

  • Machining method of compressor impeller

    CN108067634A

  • Machining method for precision inner cavity thin-wall integral centrifugal impeller of aerospace engine

    CN109759791A

  • Impeller machining method

    CN112894283A

  • Impeller of gas compressor

    CN116591988A

  • Adjustable tool clamp for five-axis machining of compressor wheel

    CN203738437U