A method and device for predictive control of cooperative operation model of virtual marshaling train

By constructing a virtual marshalling train model and predicting the state space equation in the time domain, combined with the tracking differentiator and the expanded state observer, the control variables are optimized to solve the problem of large tracking intervals between virtual marshalling trains, and achieve the shortening of train intervals and improvement of transportation efficiency. promote.

CN118567239BActive Publication Date: 2024-10-22EAST CHINA JIAOTONG UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411052383.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-10-22
Estimated Expiration
2044-08-02

AI Technical Summary

Technical Problem

In the existing technology, the cooperative operation model predictive control method of virtual marshalling trains is difficult to effectively shorten the tracking interval between trains, affecting transportation efficiency.

Method used

By constructing a virtual marshalling train model, establish the train state space equation in the prediction time domain, design the objective function to minimize the cost function, solve the optimal control sequence, and use the tracking differentiator and expanded state observer to deal with interference, and optimize the control variables to shorten the time Train intervals.

Benefits of technology

It achieves shortening of train intervals and flexibly adjusts train formation, improves control accuracy and anti-disturbance capabilities, and improves transportation efficiency and energy efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118567239B_ABST
    Figure CN118567239B_ABST
Patent Text Reader

Abstract

The present invention discloses a method and device for predicting and controlling the cooperative operation model of a virtual marshaling train, and relates to the technical field of rail transit signal control. The method comprises: constructing a virtual marshaling train model; constructing a train state space equation of the virtual marshaling train model in a prediction time domain; according to the constraints in the operation process of the virtual marshaling train, taking the minimum cost function of the marshaling train as the objective function, solving the objective function, and obtaining an optimal control sequence; constructing a tracking differentiator and an extended state observer; taking the reference speed curve as the speed input curve of the leader train, determining the output control force of the leader train, and the follower train determining the input state variable according to the output control force of the leader train; obtaining the output control variable according to the input state variable; obtaining the control variable of the current marshaling train according to the output control variable and the control variable after compensation for interference. The present invention can improve transportation efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of rail transit signal control, and in particular to a method and device for predicting and controlling a collaborative operation model of a virtual marshaled train. Background Art

[0002] The characteristic of virtual train formation is that it uses wireless communication to realize information transmission between the front and rear trains. In the existing technology, in the control method adopted, since model predictive control has good tracking performance and can solve the cost function of the controlled variables and manipulated variables with constraints through online rolling optimization, obtain the optimal control force and act on the controlled object, a large number of scholars choose to use model predictive control method to realize multi-vehicle cooperative operation. How to apply virtual train formation, adopt cooperative operation model predictive control, and achieve the purpose of improving transportation efficiency by reducing the tracking interval between trains is a technical problem that needs to be solved urgently. Summary of the invention

[0003] The purpose of the present invention is to provide a method and device for predictive control of a collaborative operation model of a virtual train formation, so as to improve the transportation efficiency by reducing the tracking interval between trains.

[0004] To achieve the above object, the present invention provides the following solutions:

[0005] A model predictive control method for cooperative operation of a virtual marshaling train, the method comprising:

[0006] Construct a virtual train model;

[0007] Constructing a train state space equation of the virtual marshaling train model in a prediction time domain;

[0008] According to the constraints in the operation process of the virtual marshaling train, the cost function of the marshaling train is minimized as the objective function, and the objective function is solved to obtain the optimal control sequence;

[0009] Constructing a tracking differentiator and an extended state observer; the tracking differentiator takes a preset transition reference speed curve as input and a reference speed curve as output; the extended state observer takes a control variable of the current marshaling train as input and a control variable after compensation for interference as output;

[0010] The reference speed curve output by the tracking differentiator is used as the speed input curve of the leader train to determine the output control force of the leader train, and the follower train determines the input state variable of the optimal control sequence according to the output control force of the leader train;

[0011] According to the input state variables, an output control variable of the optimal control sequence is obtained;

[0012] The control variable of the current train formation is obtained according to the output control variable and the control variable after compensating for the interference.

[0013] Optionally, the virtual train formation model is:

[0014] ;

[0015] ;

[0016] ;

[0017] ;

[0018] ;

[0019] ;

[0020] ;

[0021] ;

[0022] in, is the state variable; is the delay coefficient of the control action; is the time constant; is the control variable; , , is the coefficient; is the acceleration of the i-1th follower train at time t; is the displacement error variable of the follower train; is the speed error of the follower train; is the acceleration error of the follower train; is the displacement of the i-1th follower train; is the displacement of the i-th follower train; is the speed of the i-th follower train; is the speed of the i-1th follower train; For trains exist The acceleration of the moment; To find the derivative of the state quantity; is the minimum safety margin.

[0023] Optionally, the train state space equation in the prediction time domain is:

[0024] ;

[0025] ;

[0026] ;

[0027] ;

[0028] ;

[0029] ;

[0030] ;

[0031] in, For the i-th train The state quantity at the moment; For the i-th train +1 state quantity at the moment; For the i-th train The control quantity at each moment; M, N, and F are all coefficient matrices; For the i-1th train The acceleration of the moment; for The prediction time domain of the moment; A is the prediction time domain of the moment; The coefficient matrix after discretization; B is the The coefficient matrix after discretization; R is the The discretized coefficient matrix; is the sampling period; , , is the coefficient matrix.

[0032] Optionally, the objective function is:

[0033] ;

[0034] The constraints are:

[0035] ;

[0036] ;

[0037] ;

[0038] ; ;

[0039] ;

[0040] ;

[0041] ;

[0042] ;

[0043] ;

[0044] ;

[0045] in, For the i-th train The state quantity at the moment; For the i-th train Control variables at time; is the objective function; For the i-th train The acceleration of the moment; is the speed of the i-th follower train; is the displacement of the i-1th follower train at time k; is the displacement of the i-th follower train at time k; is the speed of the i-th follower train; M, N, and F are all coefficient matrices; For the i-th train The state quantity at the moment; For the i-th train The amount of control at any moment; For the i-1th train The acceleration of the moment; for The prediction time domain of the moment; is the maximum deceleration; is the maximum acceleration; , , are the weight coefficients of various indicators; is the output of the actual system; is the expected system output; for curve tracking performance; To control the amount; is the energy consumption suppression item; is the difference in acceleration between the front and rear trains; is the total traction energy consumption; The speed limit for train operation; is the minimum braking force; is the maximum traction; is the minimum safety margin; is the output of the train at time k+1; A, B, and R are all discretized coefficient matrices; To establish control weight matrix elements for establishing train spacing; To establish the control weight matrix elements of the train in terms of speed; To establish the control weight matrix elements of the train in terms of acceleration; , , are weight coefficients of various indicators; H is the weight coefficient of each indicator in the prediction time domain The number of control weight matrix elements in ; is the second-order state quantity of train i; C is the output coefficient matrix; diag is the diagonal matrix.

[0046] Optionally, the optimal control sequence is:

[0047] ;

[0048] in, for The optimal control sequence at time The first control quantity of for The optimal control sequence at time The second control quantity of for The optimal control sequence at time No. A control quantity.

[0049] Optionally, the tracking differentiator is a linear tracking differentiator.

[0050] Optionally, the linear tracking differentiator is:

[0051] ;

[0052] in, is the calculation cycle; is the speed factor; is the speed of the transition reference speed curve at time k; is the displacement of the leader train at time k+1; is the displacement of the leader train at time k; is the speed of the leader train at time k; is the speed of the leader train at time k+1.

[0053] Optionally, the extended state observer is a Lumberg observer.

[0054] Optionally, the extended state observer is:

[0055] ;

[0056] ;

[0057] in, is the observed value of the deviation between the expected distance between the trains at time k and the trains ahead and behind Observed value of is the speed difference of the train before and after time k Observed value of is the observed value of the total disturbance term at time k; is the sampling time; is the observed value of the deviation between the expected distance between the trains before and after at time k+1 Observed value of is the speed difference of the train before and after time k+1 Observed value of is the observed value of the total disturbance term at time k+1; is the difference between the observed value of the front and rear train spacing difference and the expected spacing displacement error under interference and the actual value of the front and rear train spacing difference and the expected spacing displacement error under interference; is the difference in acceleration between the front and rear trains; are the observer parameters set.

[0058] A computer device comprises: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement any of the above-mentioned methods for predicting and controlling the collaborative operation model of a virtual train assembly.

[0059] According to the specific embodiments provided by the present invention, the present invention discloses the following technical effects:

[0060] The present invention proposes a model predictive control method for the coordinated operation of virtual marshaled trains, which achieves the purpose of shortening the running interval and flexibly adjusting the train marshaling. First, a three-order train formation model with a discrete distributed model predictive control structure considering action delay and variable spacing is established to achieve the purpose of shortening the running interval and flexibly adjusting the train marshaling; an objective function containing the requirements of accurate marshaling and reduced energy consumption is designed, and the objective function is solved to obtain the optimal control sequence; secondly, the marshaling operation status of the train under interference is considered, and a linear tracking differentiator is added to transition the reference curve mutation stage in a smoother form, and an extended state observer is added in the feedforward path to estimate and compensate for the interference caused by the inaccurate model and the disturbance in the environment in real time, thereby improving the control accuracy of the train. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0062] Figure 1 It is the virtual grouping cooperative operation diagram of the present invention;

[0063] Figure 2 This is the block diagram of the model predictive control structure based on the active disturbance rejection algorithm;

[0064] Figure 3 It is a schematic diagram of the leader-follower speed tracking curve in simulation experiment 1;

[0065] Figure 4 It is a schematic diagram of the leader-follower acceleration tracking curve in simulation experiment 1;

[0066] Figure 5 Schematic diagram of leader-follower distance deviation curve in simulation experiment 1;

[0067] Figure 6 It is a schematic diagram of the leader-follower speed difference curve in simulation experiment 1;

[0068] Figure 7 Schematic diagram of the moving distance between trains in simulation experiment 1;

[0069] Figure 8 Schematic diagram of the fixed interval between trains in simulation experiment 1;

[0070] Fig. 9 It is a schematic diagram of the speed curves of each train in simulation experiment 2;

[0071] Fig.10 Schematic diagram of the displacement curves of each train in simulation experiment 2;

[0072] Fig.11 This is a schematic diagram of the reference speed curve processed by the tracking differentiator in simulation experiment 3;

[0073] Fig.12 This is a schematic diagram of the reference acceleration curve processed by the tracking differentiator in simulation experiment 3;

[0074] Fig.13 This is a schematic diagram of the error curve between the actual interference value and the observed value in simulation experiment 3;

[0075] Fig.14 This is a schematic diagram of the error curve between the actual value and the observed value of the spacing deviation in simulation experiment 3;

[0076] Fig.15 It is a schematic diagram of the error curve between the actual value and the observed value of the speed difference in simulation experiment 3;

[0077] Fig.16 Schematic diagram of leader-follower speed curve under interference in simulation experiment 3;

[0078] Fig.17Schematic diagram of leader-follower velocity curve after dynamic compensation in simulation experiment 3;

[0079] Fig.18 A schematic flow chart of the model predictive control method for the collaborative operation of virtual marshaled trains provided by the present invention. DETAILED DESCRIPTION

[0080] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0081] The purpose of the present invention is to provide a method and device for predictive control of a collaborative operation model of a virtual train formation, aiming to improve transportation efficiency by reducing the tracking interval between trains.

[0082] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0083] Example 1

[0084] like Figures 1 to 18 As shown, the collaborative operation model predictive control method of the virtual marshaling train in this embodiment includes:

[0085] Step S1: Construct a virtual train model.

[0086] Step S2: constructing the train state space equation of the virtual train model in the prediction time domain.

[0087] Step S3: According to the constraints during the operation of the virtual marshaling train, the cost function of the marshaling train is minimized as the objective function, and the objective function is solved to obtain the optimal control sequence.

[0088] Step S4: construct a tracking differentiator and an extended state observer; the tracking differentiator takes a preset transition reference speed curve as input and a reference speed curve as output; the extended state observer takes the control variable of the current train formation as input and the control variable after compensation for interference as output.

[0089] Step S5: Taking the reference speed curve output by the tracking differentiator as the speed input curve of the leader train, the output control force of the leader train is determined, and the follower train determines the input state variable of the optimal control sequence according to the output control force of the leader train.

[0090] Step S6: Obtain the output control variable of the optimal control sequence according to the input state variable.

[0091] Step S7: obtaining the control variable of the current train formation according to the output control variable and the control variable after compensating for the interference.

[0092] In practical applications, the implementation process of the model predictive control method for the cooperative operation of virtual trains includes three parts: virtual train model establishment, distributed model predictive controller design and active disturbance rejection control system design.

[0093] 1. Establishment of virtual train model.

[0094] 1.1 Traditional train dynamics formula.

[0095] The radial dynamics of the unit train are analyzed by taking into account the effects of traction, basic resistance and slope resistance. Due to the delay of the control action, the acceleration will not change immediately. Therefore, the dynamic equation of the unit train is shown in Equation (1).

[0096] (1)

[0097] Where: For trains exist Position at the moment ; For trains exist The speed of time ; For trains exist The acceleration of the moment; For trains The command acceleration; Train for Leaders At the moment Speed ; , , is the Davis coefficient, which is related to the type of rolling stock and line conditions; is the delay of the control action, which is a set fixed constant; is the number of trains in the formation; is the mass of the trains in the formation, for The derivative of for The derivative of for The present invention assumes that each vehicle has the same mass.

[0098] 1.2 State space model of virtual train formation.

[0099] The present invention adopts a "leader-follower" topology and a single-particle model to study the tracking control problem of virtual marshaling trains on straight tracks. The leading train is used as the leader to track the train automatic driving reference curve issued by the control center and transmit its own operating status information to the following train in real time through wireless communication; the remaining trains in the formation are regarded as followers and control their own operation through distributed controllers, so as to achieve the purpose of coordinated operation of multiple trains. The process of coordinated operation of virtual marshaling trains is as follows. Figure 1 The present invention selects is the state variable, is the control variable, where the displacement error variable of the follower train is defined as , the velocity error is defined as , the acceleration error is defined as Therefore, the train The continuous linear state equation can be written as:

[0100] (2)

[0101] In the formula, , , .

[0102] in, is the delay coefficient of the control action and is a fixed constant. It is a time constant, expressed as the headway, that is, the time difference between the front ends of the front and rear unit trains passing the same place. To find the derivative of the state quantity, since ,so It is expressed as the derivative of the error between the front and rear train interval and the expected interval, the derivative of the front and rear speed difference, and the derivative of the front and rear train acceleration; by setting the fixed train expected tracking interval becomes the time-varying expected spacing , so the train spacing can be adjusted flexibly and timely, shortening the interval between trains to a certain extent.

[0103] Use sampling period The discrete state space equation obtained by discretizing equation (2) is as follows:

[0104] (3)

[0105] in, , , . is the sampling period; , , is the coefficient matrix.

[0106] The train needs to meet certain safety constraints during operation. For each unit train, the speed limit must be met:

[0107] (4)

[0108] In order to ensure the comfort of passengers and the traction and braking performance of the unit train, the acceleration of the unit train must meet the following constraints:

[0109] (5)

[0110] in, Indicates the maximum deceleration, Expressed as maximum acceleration.

[0111] In addition, the constraint of safety interval is the key to ensure the safety of platooning vehicles. Different from the traditional fixed interval, a variable interval related to the headway is selected. , under the premise of ensuring operational safety, the train spacing can be adjusted flexibly and timely and the interval between trains can be shortened to a certain extent. The constraints are as follows:

[0112] (6)

[0113] 2. Distributed model predictive controller design.

[0114] The present invention designs a distributed model prediction controller to control each train. The front train transmits its own state information to the rear train in real time, and solves the optimization problem of each train separately by rolling optimization, so as to realize the stable coordinated tracking operation of the train formation and establish the train state space equation in the prediction time domain:

[0115] (7)

[0116] Where: For Predicted at the moment State quantity at the moment , For Predicted at the moment State quantity at the moment , For Predicted at the moment Control variables at time ; For Predicted at the moment Acceleration of time ; then in the current Prediction time domain The system state vector in It is formula (8).

[0117] (8)

[0118] In a train tracking control system, predicting control inputs in the time domain for:

[0119] ;

[0120] in, For the i-th train set Predicted at the moment Control variables at time .

[0121] Set the current State quantity at the moment and control volume Acting on the system, through iteration in the prediction time domain, equation (7) is rewritten into matrix form as follows:

[0122] (9)

[0123] in, , , .

[0124] According to the constraints during the operation of the virtual marshaling train, in order to keep the spacing between unit trains in the virtual marshaling at the expected spacing, and the speed difference between adjacent unit trains is zero.

[0125] Therefore, the output of the future prediction time domain is:

[0126] (10)

[0127] in, .

[0128] in, The output of the i-th train set at time k in the future prediction time domain; is the predicted value of the i-th train set at time k Output at the moment; is the predicted value of the i-th train set at time k Output at the moment.

[0129] At the same time, in order to meet the requirement of low energy consumption during the operation of virtual marshaling trains, the present invention does not consider the transmission process of electric energy, but only considers the mechanical energy consumed by the train, thereby establishing the energy consumption equation:

[0130] (11)

[0131] in, For trains The traction force, Represented as a train running speed.

[0132] The energy consumption equation of the train in the prediction time domain is:

[0133] (12)

[0134] in is the total traction energy consumption of the train, expressed as the integral of power over time; is the total runtime; It's a train exist The instantaneous output power at the moment; this formula ignores the energy loss in the train transmission system and assumes that the train cannot recover braking energy, so the traction energy consumption during active braking of the train is not considered.

[0135] In order to meet the above requirements of precise control and energy saving, the cost function of train formation is designed as follows:

[0136] (13)

[0137]

[0138] in, , , is the weight coefficient of each indicator, To predict the ideal output of the system in the time domain. To establish control weight matrix elements for establishing train spacing; To establish the control weight matrix elements of the train in terms of speed; is the control weight matrix element for establishing the train acceleration; H is the control weight matrix element for establishing the train acceleration in the prediction time domain. The number of control weight matrix elements in the actual calculation process; the value of H is The values ​​of are equal; is the second-order state quantity of train i, which represents the error between the interval and the expected interval between train i and the preceding train i-1, and the speed difference between the preceding and following trains; C is the output coefficient matrix; diag is the diagonal matrix. The first term of the cost function represents the curve tracking performance, the second term represents the control quantity, and the third term represents the energy consumption suppression term. During the operation of the train, various indicators such as safe operation, passenger comfort, and energy saving need to be considered at the same time, so different requirements can be achieved by adjusting the weight coefficient.

[0139] The cost function is optimized by the quadratic programming method and obtained The optimal control sequence at the moment ,Will The optimal control sequence at time The first control quantity Acting on trains , update its own status information, in At this moment, the system The above-mentioned solving process is repeated for the state quantity at each moment, and the solution is optimized in real time. Ultimately, the optimal control of the train formation is achieved within the entire running time.

[0140] 3. Design of self-disturbance control system.

[0141] In actual situations, the operation of the platoon is disturbed by the external environment. The continuous state is:

[0142] (14)

[0143] in, , , .

[0144] Where: It means that the train is subject to various uncertain interferences from the outside world during its operation. The interference and the interference caused by the inaccurate model within the system are collectively referred to as "total disturbance".

[0145] Among them, the total disturbance term is expressed as:

[0146] (15)

[0147] In order to facilitate the implementation of MPC, the above continuous state equation needs to be discretized. Therefore, a zero-order holder is used to discretize the state equation:

[0148] (16)

[0149] in, .

[0150] 3.1 Tracking Differentiator TD.

[0151] Using the tracking differentiator to transition the reference speed curve And its differentiated reference acceleration curve In order to make the reference curve tracked by the leader change in a smoother form in the face of mutations, , As the new input tracking signal. The discrete linear tracking differentiator is:

[0152] (17)

[0153] in, Real-time tracking , h is the calculation period, speed factor Determines the tracking speed. The larger the value, the faster the tracking. On the contrary, the smaller the value, the slower the tracking.

[0154] 3.2 Extended State Observer ESO.

[0155] During the actual operation of the train, it will be subject to real-time interference from the external environment, which will affect the accuracy of train tracking to a certain extent, causing a decline in controller performance. In addition, the inaccurate model will also affect the accuracy of train tracking. The extended state observer can observe the interference in real time and mitigate the impact of the interference on the control of train operation through compensation, thereby improving the controller's anti-disturbance ability.

[0156] Distractors Expand to a new state , so the expanded state space equation is established as:

[0157] (18)

[0158] in, is the difference in acceleration between the front and rear trains; is the speed difference between the front and rear trains; is the acceleration difference between the front and rear trains; is the derivative of the expanded new state quantity; is the speed difference between the front and rear trains; is the derivative of the total disturbance term; is the difference between the distance between the front and rear trains and the expected distance.

[0159] In order to ensure the convergence of the observer, external interference is set is bounded. The extended state observer selects the basic form of the Lumberg observer, which can quickly and accurately estimate the various states of the system. Since the model predictive control is used in discrete conditions, the discrete linear ESO is designed as:

[0160] (19)

[0161] Where: and They are and The observed value of the deviation from the expected spacing between the front and rear trains The speed difference between the front and rear trains The observed value of is the observed value of the total disturbance term, is the sampling time. The bandwidth method is used to define the gain value of the observer. The gain of the observer is:

[0162] ;

[0163] The extended state observer estimates the state quantity and disturbance value in real time at each sampling moment, and feeds forward compensation to the MPC control model, finally completing the design of the model predictive controller based on the extended observer.

[0164] 3.3 Dynamic compensation linearization process.

[0165] In order to improve the tracking performance of the platoon, it is necessary to transform the input by compensating the total disturbance and take the control quantity as , is the control force applied without disturbance, then the system described in formula (18) becomes:

[0166] (20)

[0167] in, is the observed value of the total disturbance term; b is the compensation coefficient; is the error between the train spacing before and after time k+1 and the expected spacing; is the error between the train spacing before and after time k and the expected spacing; is the speed difference of the trains before and after time k; is the speed difference of the trains before and after time k+1; is the total disturbance term.

[0168] The above steps complete the design of the ADRC algorithm. Its control block diagram is as follows: Figure 2 As shown, this control method can improve the accuracy of control tracking and make the virtual train set run more stably.

[0169] 4. Control system simulation.

[0170] In order to prove the effectiveness of the proposed control algorithm, CRH380 A high-speed train is selected as the research object, and the simulation scenario is the train tracking operation scenario. The present invention sets three virtual marshaling trains to run in coordination, a leader train tracks the reference curve issued by the control center, and the following two follower trains track the leading train. MATLAB simulation experiment is used to test the tracking effect of virtual marshaling trains, and the simulation parameters are shown in Table 1.

[0171] Table 1 Simulation parameter statistics

[0172]

[0173] The present invention designs three simulation experiments, all of which adopt the same initial state, with the initial positions of the three trains set to -5m, -45m, and -115m, and the initial speeds set to 5m / s, 0m / s, and 5m / s.

[0174] The first simulation experiment is to consider the time delay and the moving distance of the platoon vehicles. Figures 3 to 8 As shown. Figure 3 It can be seen that the leader train and the follower train can track and run well according to the reference curve. The partial enlarged upper right figure shows the tracking effect when the train runs at a constant speed. The tracking will fluctuate, but the speed error can be kept within 0.3m / s. Figure 3 The local enlargement of the upper left picture shows that the speed starts from the 1st second. Figure 7 The figure shows the moving distance between adjacent trains in a virtual marshaling, which is changed from a fixed interval of 350m to a variable interval that changes with the train speed. This greatly shortens the distance between marshaled trains and allows for flexible adjustment of the interval between trains.

[0175] Simulation Experiment 2 In order to verify the effectiveness of adding energy consumption items in the cost function to achieve energy saving, different energy consumption optimization weight coefficients are set up. (No energy saving items), , , ,The results of energy consumption are shown in Table 2. By comparison, it can be seen that as the energy consumption optimization weight increases, the actual energy consumption during the operation of the marshaling train will decrease accordingly, and the lowest energy saving rate is 2% for the leader and the highest is 77.44% for the follower. Fig. 9 and Fig.10 is the weight coefficient From the simulation diagram of the speed and displacement curves of each train, it can be seen that after adding the energy consumption term to the cost function, the control accuracy of the train is reduced compared with the result of only precise marshaling purpose, but it can still maintain stable operation with a small error.

[0176] Table 2 Train energy consumption

[0177]

[0178] Simulation experiment 3 shows the simulation results after adding the ADAS system. Figures 11 to 17 First, a tracking differentiator is used to process the input signal, so that the originally set reference curve becomes a smoother curve when it changes suddenly. The effect is shown in Fig.11 , Fig.12 As shown in the figure, it can be seen that at the turning point, the reference curve transitions in a smooth form, making the train more stable and safe during operation and improving the riding comfort.

[0179] After adding the extended state observer, the total disturbance and state quantity are observed respectively, and real-time compensation is performed in the feedforward loop to reduce the influence of disturbance on tracking accuracy. The algorithm comparison experiment after adding the self-disturbance rejection system using the model predictive control method proves that this algorithm can reduce the influence of disturbance on curve tracking ability. To ensure the accuracy of the experiment, the same simulation conditions are used for comparison. The actual disturbance of the system and its observed value are shown in the figure. Fig.13 It can be seen that there is a slight overshoot in the early stage of the disturbance observation, resulting in a large error. After that, the observed value of the total disturbance is close to the actual value. The error between the actual value and the observed value is as follows: Fig.14 As shown, the error after interference stabilization estimation is close to 0.025, Fig.15 , Fig.16 is the error between the actual value and the observed value of the expected distance from the preceding vehicle and the error between the actual value and the observed value of the speed difference from the preceding vehicle. It can be seen that the error is small, and the error accuracy of the actual value and the observed value of the estimated stable interval deviation is within The error between the actual value and the observed value of the speed deviation is controlled within It can be seen that the observed value is relatively accurate and can be used as the state quantity for subsequent dynamic compensation.

[0180] The speed curve tracking of the train after the system real-time dynamic compensation of the disturbance is: Fig.17 By comparing the two algorithms, it can be seen that in the case of interference, the speed of each train is maintained at After adding the extended state observer, the speed of each train is within 0.4m / s. The fluctuations were within the range of 0.062m / s, and the control accuracy was improved by 84.5%, which slowed down the fluctuation of train speed. This proved that the impact of interference on train operation was reduced to a certain extent, making the coordinated operation of marshaled trains more stable.

[0181] The present invention adopts the model predictive control method to study the tracking operation problem of virtual marshaling trains and draws the following conclusions:

[0182] 1. The present invention takes into account the situation involving control action delays and changes the traditional fixed interval between trains into a mobile interval, thereby establishing a new virtual marshaling train model. The simulation results can prove the feasibility of this model and control method, thereby reducing the distance between trains.

[0183] 2. Under the premise of ensuring accurate tracking of the marshaled train, in order to reduce the energy consumption of the virtual marshaled train during operation, the present invention chooses to add energy consumption items in the cost function for simulation experiments, and selects different weight coefficients for comparative studies. When the energy consumption weight coefficient increases, the energy consumption of the train will decrease accordingly, verifying the effectiveness of energy saving.

[0184] 3. The present invention analyzes the running tracking of the train under interference conditions, adds an anti-disturbance system, and reduces the sudden change of the reference curve by adjusting the tracking differentiator. An extended state observer is added to observe and estimate the total disturbance and the state of the train and compensate in real time. The results show that this algorithm can improve the accuracy of control tracking and make the virtual train run more stably.

[0185] Compared with the prior art, the present invention has the following advantages:

[0186] During the operation of virtual marshaling trains, the existing technology only considers the requirements of accurate marshaling and anti-collision, and there is little research on energy saving. Therefore, the present invention adds energy saving links to the cost function on the basis of considering control accuracy and variable spacing. At the same time, the present invention also considers the operation of virtual marshaling trains under interference conditions, uses a tracking differentiator to process the sudden change stage of the input signal transition reference curve, and uses an extended state observer to estimate and compensate for the disturbance caused by the inaccurate model and external interference in real time, thereby improving the system's anti-interference ability and tracking accuracy.

[0187] Example 2

[0188] A computer device includes: a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the collaborative operation model predictive control method of a virtual train assembly in Example 1.

[0189] Example 3

[0190] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the collaborative operation model predictive control method of a virtual train assembly in Example 1.

[0191] Example 4

[0192] A computer program product includes a computer program, which, when executed by a processor, implements the collaborative operation model predictive control method of virtual train formation in Example 1.

[0193] Example 5

[0194] A computer device, which may be a database. The computer device includes a processor, a memory, an input / output interface (Input / Output, referred to as I / O) and a communication interface. The processor, the memory and the input / output interface are connected via a system bus, and the communication interface is connected to the system bus via the input / output interface. The processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store pending transactions. The input / output interface of the computer device is used to exchange information between the processor and an external device. The communication interface of the computer device is used to communicate with an external terminal via a network connection. When the computer program is executed by the processor, the collaborative operation model prediction control method of the virtual marshaling train in Example 1 is implemented.

[0195] It should be noted that the object information (including but not limited to object device information, object personal information, etc.) and data (including but not limited to data used for analysis, stored data, displayed data, etc.) involved in the present invention are all information and data authorized by the object or fully authorized by all parties, and the collection, use and processing of relevant data must comply with relevant laws, regulations and standards of relevant countries and regions.

[0196] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to the memory, database or other medium used in the embodiments provided by the present invention can include at least one of non-volatile and volatile memory. Non-volatile memory can include read-only memory (ROM), magnetic tape, floppy disk, flash memory, optical memory, high-density embedded non-volatile memory, resistive random access memory (ReRAM), magnetoresistive random access memory (MRAM), ferroelectric random access memory (FRAM), phase change memory (PCM), graphene memory, etc. Volatile memory can include random access memory (RAM) or external cache memory, etc. As an illustration and not limitation, RAM can be in various forms, such as static random access memory (SRAM) or dynamic random access memory (DRAM). The database involved in each embodiment provided by the present invention may include at least one of a relational database and a non-relational database. Non-relational databases may include distributed databases based on blockchains, etc., but are not limited to this. The processor involved in each embodiment provided by the present invention may be a general-purpose processor, a central processing unit, a graphics processor, a digital signal processor, a programmable logic device, a data processing logic device based on quantum computing, etc., but are not limited to this.

[0197] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0198] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of ​​the present invention. At the same time, for those skilled in the art, according to the idea of ​​the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.

Claims

1. A model predictive control method for cooperative operation of virtual trains. It is characterized in that The method comprises: Construct a virtual train model; Constructing a train state space equation of the virtual marshaling train model in a prediction time domain; According to the constraints in the operation process of the virtual marshaling train, the cost function of the marshaling train is minimized as the objective function, and the objective function is solved to obtain the optimal control sequence; Constructing a tracking differentiator and an extended state observer; the tracking differentiator takes a preset transition reference speed curve as input and a reference speed curve as output; the extended state observer takes a control variable of the current marshaling train as input and a control variable after compensation for interference as output; the tracking differentiator is a linear tracking differentiator; The reference speed curve output by the tracking differentiator is used as the speed input curve of the leader train to determine the output control force of the leader train, and the follower train determines the input state variable of the optimal control sequence according to the output control force of the leader train; According to the input state variables, an output control variable of the optimal control sequence is obtained; Obtaining a control variable of a current train formation according to the output control variable and the control variable after compensating for the interference; Wherein, the virtual train formation model is: ; ; ; ; ; ; ; ; in, is the state variable; is the delay coefficient of the control action; is the time constant; is the control variable; , , is the coefficient matrix; is the acceleration of the i-1th follower train at time t; is the displacement error variable of the follower train; is the speed error of the follower train; is the acceleration error of the follower train; is the displacement of the i-1th follower train; is the displacement of the i-th follower train; is the speed of the i-th follower train; is the speed of the i-1th follower train; For trains exist The acceleration of the moment; To find the derivative of the state quantity; is the minimum safety margin; The objective function is: ; The constraints are: ; ; ; ; ; ; ; ; in, For the i-th train The state quantity at the moment; For the i-th train Control variables at time; is the objective function; For the i-th train The acceleration of the moment; is the speed of the i-th follower train; is the displacement of the i-1th follower train at time k; is the displacement of the i-th follower train at time k; M, N, and F are all coefficient matrices; For the i-th train The amount of control at any moment; For the i-1th train The acceleration of the moment; for The prediction time domain of the moment; is the maximum deceleration; is the maximum acceleration; is the output of the actual system; is the expected system output; for curve tracking performance; To control the amount; is the energy consumption suppression item; is the difference in acceleration between the front and rear trains; is the total traction energy consumption; The speed limit for train operation; is the minimum braking force; is the maximum traction; is the output of the train at time k+1; A, B, and R are all discretized coefficient matrices; To establish control weight matrix elements for establishing train spacing; To establish the control weight matrix elements of the train in terms of speed; To establish the control weight matrix elements of the train in terms of acceleration; , , are weight coefficients of various indicators; H is the The number of control weight matrix elements in ; is the second-order state quantity of train i; C is the output coefficient matrix; diag is the diagonal matrix.

2. The collaborative operation model predictive control method of a virtual train set according to claim 1, It is characterized in that The train state space equation in the prediction time domain is: ; ; ; ; ; ; ; in, For the i-th train The state quantity at the moment; For the i-th train +1 state quantity at the moment; For the i-th train The control quantity at each moment; M, N, and F are all coefficient matrices; For the i-1th train The acceleration of the moment; for The prediction time domain of the moment; A is the prediction time domain of the moment; The coefficient matrix after discretization; B is the The coefficient matrix after discretization; R is the The discretized coefficient matrix; is the sampling period; , , is the coefficient matrix.

3. The collaborative operation model predictive control method of a virtual train set according to claim 1, It is characterized in that The optimal control sequence is: ; in, for The optimal control sequence at time The first control quantity of for The optimal control sequence at time The second control quantity of for The optimal control sequence at time No. A control quantity.

4. The collaborative operation model predictive control method of a virtual train set according to claim 1, It is characterized in that The linear tracking differentiator is: ; in, is the calculation cycle; is the speed factor; is the speed of the transition reference speed curve at time k; is the displacement of the leader train at time k+1; is the displacement of the leader train at time k; is the speed of the leader train at time k; is the speed of the leader train at time k+1.

5. The collaborative operation model predictive control method of a virtual train set according to claim 1, It is characterized in that The extended state observer is a Lumberg observer.

6. The collaborative operation model predictive control method of virtual train formation according to claim 5, It is characterized in that The extended state observer is: ; ; ; in, is the observed value of the deviation between the expected distance between the trains before and after at time k Observed value of is the speed difference of the train before and after time k Observed value of is the observed value of the total disturbance term at time k; is the sampling time; is the observed value of the deviation between the expected distance between the trains before and after at time k+1 Observed value of is the speed difference of the train before and after time k+1 Observed value of is the observed value of the total disturbance term at time k+1; is the difference between the observed value of the front and rear train spacing difference and the expected spacing displacement error under interference and the actual value of the front and rear train spacing difference and the expected spacing displacement error under interference; is the difference in acceleration between the front and rear trains; are the observer parameters set.

7. A computer device, include: A memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor executes the computer program to implement the collaborative operation model predictive control method for a virtual train assembly as described in any one of claims 1 to 6.