Decoupling production method for automobile factories
Through the order decoupling production method, the multi-objective optimization algorithm is used to decompose orders and adjust the body tasks, which solves the problem of strong binding between the body and the production plan, and achieves the stability and high order rate of order delivery, meets the demand for high beats, and reduces materials Waste and delivery time fluctuate.
Patent Information
- Application Number
- CN202411070332.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-01
- Estimated Expiration
- 2044-08-06
AI Technical Summary
In order production, automobile factories are prone to scrapping and quality problems due to the strong binding of the vehicle body and production plan, which leads to unstable order delivery time, and severe interference from multiple models and small color types, affecting the production rhythm and delivery order.
The order decoupling production method is adopted, and the car body information is obtained, and the car body information is decomposed into welding, coating, and total binding orders. The color change frequency, delivery sequence, and manufacturing path optimization functions are constructed based on the multi-objective optimization algorithm, and the body task and the car body task are dynamically adjusted. Process, update information in real time, and realize loose coupling and binding between the body and order.
It achieves the stability and high order rate of order delivery, meets high beat demand, reduces material waste, improves efficiency, ensures the balance between personalized and batch operations of vehicles, and reduces fluctuations in delivery time.
Smart Images

Figure CN118586685B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of automobile production management, and in particular to an order decoupling production method for automobile factories. Background Art
[0002] At present, when automobile factories produce cars according to orders, the upstream manufacturing execution system (MES) generally guides production by writing car body information through barcodes or RFID according to the production schedule of the advanced planning and scheduling system (APS).
[0003] For example, the body of the welding workshop carries a barcode or tag, which specifies the paint color and detailed configuration of the vehicle from the beginning of welding production. MES receives the welding line sequence plan from APS; the MES system sends the production body to the welding PLC; the welding PLC writes the production plan to the tag through RFID and binds it to the body. When the vehicle passes through the key process, the PLC obtains the vehicle information through RFID.
[0004] When welding is executed, the key process is manufactured according to the tag information, and the PLC sends the vehicle passing point information of the key process to MES; when painting is executed, the key process is manufactured according to the tag information, and the PLC sends the vehicle passing point information of the key process to MES; when final assembly is executed, when the vehicle passes the key process, the PLC obtains the vehicle information of the vehicle passing the key process through RFID; the key process is manufactured according to the tag information, and the PLC sends the vehicle passing point information of the vehicle passing the key process to MES. For example, in the paint shop, when color separation is carried out, color agglomeration is carried out passively. A queue is formed according to the color of the car that comes in, and the number of spraying queues with the minimum number of color changes is often not enough; multiple models and small colors cause great interference to the queue. If the production rhythm is to be met, the agglomeration effect will be destroyed. If the color agglomeration is to be met, it will seriously interfere with the order of vehicles entering and leaving, thereby greatly reducing the time (OTD) from the receipt of the order to the delivery of the car company. The standard OTD of a single vehicle = workshop production time / (daily rhythm*working hours).
[0005] After the car body is strongly bound to the production plan, it may be scrapped due to various problems, resulting in the failure to deliver the plan. Due to quality issues, the returned car body and the orders bound to it will also be delayed, which will disrupt the production scheduling operations of multiple conveyor lines and offline workstations and cause chaos in the order sequence.
[0006] The execution logic of MES is simple, and production and manufacturing are carried out according to the body binding information from beginning to end. However, order delivery will be affected by special vehicles such as scrapped vehicles and stranded vehicles, making it difficult to meet the delivery needs of the final assembly plan and to cooperate with the vertical warehouse scheduling system. Summary of the invention
[0007] In order to solve the above problem, the present invention provides an automobile factory order decoupling production method to solve the problem.
[0008] In order to achieve the above objectives, this application provides the following technical solutions:
[0009] The automobile factory order decoupling production method includes the following steps:
[0010] Get order information and vehicle body information;
[0011] Decomposing the order information into welding order, painting order and final assembly order;
[0012] Execute the order decoupling model according to the welding order, the painting order, the final assembly order and the vehicle body information, and obtain the execution result;
[0013] Dynamically adjust the tasks and processes of the car body on the production line according to the execution results, and update the corresponding information of the car body in real time;
[0014] Bind the car bodies leaving the factory with the corresponding orders to realize order delivery.
[0015] It is further configured as follows: the welding order includes an order number and a vehicle model;
[0016] The painting order includes order number, vehicle model, and color;
[0017] The final assembly order includes order number, vehicle model, color, and configuration.
[0018] It is further configured as follows: the establishment of the order decoupling model includes:
[0019] Constructing color-changing frequency optimization function based on decomposition multi-objective optimization algorithm , Delivery order optimization function , manufacturing path optimization function ;
[0020] The color change frequency optimization function ;
[0021] The delivery order optimization function ;
[0022] The manufacturing path optimization function ;
[0023] In the formula, is the sum function of the number of orders for the color of the car model, is the color acceleration coefficient, is the delivery sequence number of the first order to be executed, For the The sequence number of the first order that matches the body, Number the production line. Produce color coefficients for the production line, is the sum function of the number of car bodies of various colors in the storage area, is the number of car bodies, A collection of order types to be executed.
[0024] Sum function of the number of orders for the color of the model The build is as follows: ;
[0025] In the formula, Indicates A Boolean value indicating whether the order belongs to the current model. If yes, The value is 1, otherwise The value is 0; Indicates Whether the order belongs to the current model color, if so The value is 1, otherwise The value is 0; is the number of orders, A collection of color categories for production planning;
[0026] The sum function of the number of car bodies of various colors in the storage area The build is as follows: , ;
[0027] In the formula, Indicates Number of car bodies in different colors, is the car body color number, The set of color categories that have been assigned to the current shop floor storage area.
[0028] The order decoupling model is constructed as follows:
[0029] ;
[0030] ;
[0031] In the formula, , represents the decision vector of the optimization function, Represents the color change frequency optimization function , Delivery order optimization function , manufacturing path optimization function The set of decision variables; Indicates the weight coefficient corresponding to the optimization function; represents the optimization function; is the theoretical minimum value of the optimization function, is the theoretical maximum value of the optimization function, is the compensation constant.
[0032] The automobile factory order decoupling production system includes: order management module, plan receiving module, storage module, APS module, model building module, output module, production execution module, dynamic allocation module and order binding module.
[0033] It is further configured as follows: the order management module is used to manage customer orders, including receiving, recording, tracking, coordinating production, inventory management, logistics arrangements and ensuring accurate and timely delivery of orders; the plan receiving module is used to regularly receive production plans; the storage module is used to store data information including order information, vehicle body information, production plans and inventory status; the APS module is used to decompose orders into welding orders, painting orders and assembly orders; the model building module is used to build an order decoupling model; the output module is used to output the production plan and scheduling information generated according to the order decoupling model for the production execution module to execute production; the production execution module is responsible for executing the production plan and updating the production status in real time; the dynamic allocation module is used to dynamically allocate vehicle body operations according to the production plan and the order decoupling model; the order binding module is used for the production workshop management system to bind the vehicle body shipped out of the factory with the corresponding order when the operation is completed and shipped out of the factory.
[0034] Compared with the prior art, the beneficial technical effects of the present invention are:
[0035] After the production workshop management system receives the production plan, the present invention decouples the order model according to the production plan, dynamically allocates the body operation, and dynamically adjusts the binding relationship between the order and the body in real time; when the operation is completed and the vehicle is delivered from the factory, the production management system binds the vehicle body shipped from the factory with the corresponding order to realize order delivery, meet the OTD indicators to the greatest extent, ensure delivery according to the order sequence, and the OTD duration is relatively stable without large fluctuations.
[0036] Therefore, the present invention can meet high cycle times and high order delivery sequence rates under a variety of production conditions, and form a complete order management system within the production workshop. It can ensure the personalization of the delivered vehicles while meeting batch operations as much as possible, improve efficiency, and reduce material waste. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0038] Figure 1 It is a schematic diagram of the process of the automobile factory order decoupling production method in the present invention;
[0039] Figure 2 It is a schematic diagram of the execution result of the order decoupling model in the present invention;
[0040] Figure 3 It is another schematic diagram of the execution result of the order decoupling model in the present invention;
[0041] Figure 4 It is a schematic diagram of the framework of the automobile factory order decoupling production system in the present invention;
[0042] Figure 5 The structure of an electronic device in the present invention is schematically shown;
[0043] Figure 6 This is an algorithm flow chart of the order decoupling model in the present invention. DETAILED DESCRIPTION
[0044] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0045] Reference Figure 1-Figure 6 In one embodiment, the automobile factory order decoupling production method disclosed in the present invention includes the following steps:
[0046] S101, obtaining order information and vehicle body information;
[0047] In this embodiment, the order information includes each order code or order digital sequence with a unique identifier, order date, delivery date, order status, and production parameters, and the vehicle body information includes vehicle model information, color information, configuration options, and production status.
[0048] S102, decomposing the order information into welding orders, painting orders, and final assembly orders;
[0049] Among them, the welding order includes the order number and vehicle model; the painting order includes the order number, vehicle model, and color; and the final assembly order includes the order number, vehicle model, color, and configuration.
[0050] S103, establishing an order decoupling model;
[0051] Step 1: Construct the color change frequency optimization function based on the decomposed multi-objective optimization algorithm , Delivery order optimization function , manufacturing path optimization function ;
[0052] Specifically, ;
[0053] ;
[0054] ;
[0055] in, ; ;
[0056] In the formula, This is a function to sum the number of orders for the color of the model, which is used to count the number of orders for the color of the current model. The color expedited coefficient is used to expedite the calculation results of the color increase for urgent production. is the delivery sequence number of the first order to be executed, For the The sequence number of the first order that matches the body, is the number of car bodies, A collection of order types to be executed. Number the production line, Produce color coefficients for the production line, is the summation function of the number of car bodies of various colors in the storage area, which is used to count the number of car bodies of various colors in the storage area. Indicates A Boolean value indicating whether the order belongs to the current model (if it does, then =1, otherwise =0), Indicates Whether the order belongs to the current model color, if it is the current model color, then =1, if not, then =0; is the number of orders, A collection of color categories for production planning, Indicates Number of car bodies in different colors, is the car body color number, The set of color categories that have been assigned to the current shop floor storage area.
[0057] Step 2: Optimize the function according to the color change frequency , Delivery order optimization function , manufacturing path optimization function , the order decoupling model is constructed as follows:
[0058] ;
[0059] ;
[0060] In the formula, , represents the decision vector of the optimization function, Represents the color change frequency optimization function , Delivery order optimization function , manufacturing path optimization function The set of decision variables; Indicates the weight coefficient corresponding to the optimization function; Represents the optimization function. Specifically, when i is 1, represents the color change frequency optimization function. When i is 2, represents the delivery order optimization function. When i is 3, represents the manufacturing path optimization function; is the theoretical minimum value of the optimization function, is the theoretical maximum value of the optimization function, is the compensation constant and its value is 0.6.
[0061] S104, executing the order decoupling model according to the welding order, the painting order, the final assembly order and the vehicle body information, and obtaining an execution result;
[0062] Specifically, when i is 1, the execution result of the minimum color change frequency is obtained through the order decoupling model. The value is , represents the color change frequency optimization function The decision vector of The value is , represents the color change frequency optimization function The weight coefficient of
[0063] When i is 2, the execution result of the maximum delivery sequence is obtained through the order decoupling model. The value is , represents the delivery order optimization function The decision vector of The value is , represents the delivery order optimization function The weight coefficient of
[0064] When i is 3, the order decoupling model obtains the execution result of the optimal manufacturing path. The value is , represents the manufacturing path optimization function The decision vector of The value is , represents the manufacturing path optimization function The weight coefficient of
[0065] In this embodiment, the production plan is always consistent with the actual number of car bodies entering the paint shop to be painted. Every time a plan is issued, one car enters the workshop for production, and the color of the car body spraying is strictly executed according to the plan. The execution result of the order decoupling model mainly plays a role in adjusting the execution plan order in this process.
[0066] For example, if 5 vehicles of model A and 5 vehicles of model B are put into the welding workshop, and 5 corresponding production plans of vehicle A and 5 production plans of vehicle B are issued at the same time, the production plans specifically include the painting serial number, order number (the expected delivery order of the painting serial number is: Order No. 1, Order No. 2 and Order No. 3 respectively) and spray color (respectively: red, white, black), the order decoupling model is executed to obtain the following Figure 2 and Figure 3 The operation results are shown.
[0067] Specifically, by executing the order decoupling model combined with the current inventory and production plan, the execution result of the minimum color change frequency is obtained, so as to give priority to the spraying queues with multiple colors and form the most economical spraying queue with the minimum number of color changes; it can adapt to the storage advantages of the stereoscopic warehouse, reduce the interference of color matching, multiple models, and small colors on the spraying queue, and under the condition of meeting the beat, it can adapt to various complex spray room requirements, meet the color agglomeration, topcoat production line spraying configuration and stereoscopic storage locking scheme. At the same time, according to the painting serial number of the production plan, the colors are sorted and allocated again to meet the OTD index to the greatest extent, laying the foundation for high-sequence rate order delivery.
[0068] S105, dynamically adjusting the tasks and processes of the vehicle body on the production line according to the execution results, and updating the information corresponding to the vehicle body in real time;
[0069] The execution result of each vehicle is passed to the spraying robot, and the planned delivery order is adjusted, and the vehicles leaving the workshop are given priority in the delivery order with higher ranking. In this embodiment, the order of delivery priority is order No. 1> order No. 2> order No. 3;
[0070] In this process, the car bodies and orders are not bound one by one, but the orders are dynamically matched with the corresponding cars of the car bodies on the premise of meeting the number of corresponding cars in the production plan, and the cars are updated and rolled with the cars. The cars enter the corresponding workshops and the delivery status is updated with the cars. The number of car bodies on the production line is dynamically consistent with the number of orders in the production plan, so that the production plan and the actual number of car operations are always in a relatively balanced state, so as to achieve loosely coupled order delivery. In this way, the order sequence requirements are met, thereby preventing the previous orders from being unable to be delivered on time due to production failures.
[0071] In one embodiment, the mid-coating process of the paint shop is a double-line merge into a single line, and there is an offline workstation. Therefore, through the execution result of the order decoupling model, the first delivery sequence adjustment regarding the color change upper limit production plan can be made. When the color change upper limit is reached, the order decoupling model is executed according to the production plan to obtain the minimum color change frequency of the next batch of spraying queues. For example, the calculated color is whether black mid-coat priority or white mid-coat priority, so as to minimize the number of color changes to improve efficiency.
[0072] If a trial production vehicle or project vehicle that requires special treatment is encountered during the spraying process, it is necessary to force a color change according to the production plan to ensure that the color spraying is strictly carried out according to the plan. The subsequent spraying queue will be arranged in a loosely coupled spraying queue based on the existing color.
[0073] In the loosely coupled dynamic allocation of vehicle body operations, if a vehicle body is offline, the subsequent vehicle body to be operated on the same production line will be bound to the order with the highest priority and the status according to the production plan, and production will continue, thereby dynamically ensuring that the production plan and the actual vehicle operation quantity are always in a relatively balanced state, and ensuring that the corresponding orders are not delayed in delivery, thus overcoming the problem in the prior art that when a vehicle body is offline due to a malfunction, its corresponding order is also postponed, resulting in the inability to guarantee the delivery of vehicles in the order of orders.
[0074] Generally, there are one or two production lines in a production workshop, and a maintenance room or maintenance area is arranged outside the production line to repair the cars that have been taken offline due to failure. After the repair is completed, the cars will return to the end of the car body queue on the production line to go online. Therefore, the car bodies to be worked on in the latter order can come from the cars that have passed the repair inspection after being taken offline or from the cars that have left the factory in the upstream workshop. Furthermore, if there is a repaired car body that can go online and it meets the time requirements, the repaired car body will go online, otherwise the same car body from the factory in the upstream workshop stored in the storage area will be used as a replacement or standby car body to go online.
[0075] When producing in the loosely coupled order mode of the embodiment of the present invention, even if the corresponding vehicle is scrapped due to quality problems, there will be no scrapping in the overall production plan, and there is no need to make any changes to the production plan. It is only necessary to rearrange the production of similar bodies. For example, if there is a quality problem with the paint batch, loose coupling can flexibly handle the freezing of the plan for the related colors with quality problems, reduce maintenance pressure, and resume spraying of the color after the large-scale paint problem is solved.
[0076] In this embodiment, the order decoupling model is combined with the actual production conditions to guide production using the production plan, which can maximize the satisfaction of the OTD index and ensure delivery in the order in which the orders are received. By optimizing the production process and enhancing supply chain management, the continuous stability of the OTD index is ensured and the volatility of the delivery time is reduced.
[0077] S106, binding the vehicle body shipped out of the factory with the corresponding order to realize order delivery.
[0078] When binding the car bodies leaving the factory with the corresponding orders, the car body information leaving the factory is bound with the order information in the earliest issued and unfinished production plan, so as to bind the order of the orders pressed with the order of the car bodies leaving the factory.
[0079] Specifically, when binding for delivery, the production plan is queried, and the qualified delivery bodies produced according to the production plan are bound to the orders in the order of the orders in the production plan, from first to last, and delivered to the factory. When the orders are delivered in the loosely coupled order mode, the production plan will be bound according to the delivery order of the vehicles, which can effectively improve the OTD index and the order delivery sequence rate, and reduce the sorting pressure on the body distribution center before the white body of the final assembly workshop goes online.
[0080] In another embodiment, the present invention also provides an automobile factory order decoupled production management system, including an order management module, a plan receiving module (vehicle body recognition system), a storage module, an APS module (advanced planning and scheduling system), a model building module, an output module, a production execution module, a dynamic allocation module, and an order binding module.
[0081] Among them, the order management module is used to manage the entire life cycle of customer orders, including receiving, recording, tracking, coordinating production, inventory management, logistics arrangements, and all related activities to ensure accurate and timely delivery of orders.
[0082] The plan receiving module is used to receive production plans regularly.
[0083] The storage module is used to store data information including order information, vehicle body information, production plan, inventory status, etc.
[0084] APS module is used to decompose orders into welding orders, painting orders, and final assembly orders.
[0085] Model building module, used to build order decoupling model.
[0086] The output module is used to output the production plan and scheduling information generated according to the order decoupling model for the production execution module to execute production.
[0087] The production execution module is responsible for executing the production plan and updating the production status in real time.
[0088] The dynamic allocation module is used to decouple the order model according to the production plan and dynamically allocate body operations, so that orders are always updated and rolled out with the vehicles, and the production plan and the actual vehicle operation quantity are always in a relatively balanced state.
[0089] The order binding module is used for factory delivery after the operation is completed. The production workshop management system binds the car body shipped out of the factory with the corresponding order to realize order delivery.
[0090] Specifically, the plan receiving module receives the production plan, and the APS module decomposes the plan, decomposing the production plan of the whole vehicle into production plans for welding, painting and assembly. At the beginning of the welding line, a paper barcode is printed with the body information on the paper barcode. The paper barcode is attached to the body to identify the bound body. When the vehicle passes through the key process, the paper barcode information is obtained; the key process is manufactured according to the barcode information; the vehicle passing point information of the vehicle passing the key process is sent to the storage module. During the production stage, the order management module receives the production plan from the storage module at a scheduled time every day, and sends the painting plan to the production execution module after the welding exit passes the point.
[0091] Specifically, when a vehicle passes through the entrance of the paint shop, the basic information of the vehicle is obtained through a barcode scanner and written to the skid carrier. The order decoupling model is executed, and the production execution module writes key information such as color and routing number to the carrier through RFID for related process manufacturing. The order binding module performs the final plan and binds it to the actual vehicle body and transmits it back.
[0092] In the third embodiment, the present invention further provides an electronic device. It is worth mentioning that the specific embodiment of the present application does not limit the specific implementation of the electronic device. The electronic device may include: a processor, a communication interface, a memory, and a communication bus.
[0093] The processor, the communication interface, and the memory communicate with each other via a communication bus.
[0094] Communication interface, used to communicate with other electronic devices or servers.
[0095] The processor is used to execute the program, and specifically can execute the relevant steps in the above-mentioned ecological landscape corridor construction method embodiment.
[0096] Specifically, the program may include program codes including computer operation instructions.
[0097] The processor may be a CPU, or an application specific integrated circuit ASIC (Application Specific Integrated Circuit), or one or more integrated circuits configured to implement the embodiments of the present application. The one or more processors included in the smart device may be processors of the same type, such as one or more CPUs; or processors of different types, such as one or more CPUs and one or more ASICs.
[0098] Memory is used to store programs. The memory may include high-speed RAM memory and may also include non-volatile memory, such as at least one disk storage.
[0099] The program may include multiple computer instructions. Specifically, the program may enable the processor to execute operations corresponding to the ecological landscape corridor construction method described in any of the aforementioned method embodiments through multiple computer instructions.
[0100] The specific implementation of each step in the program can refer to the corresponding description of the corresponding steps and units in the above method embodiment, and has corresponding beneficial effects, which will not be repeated here. Those skilled in the art can clearly understand that for the convenience and simplicity of description, the specific working process of the above-described devices and modules can refer to the corresponding process description in the above method embodiment, which will not be repeated here.
[0101] In a fourth embodiment, the present invention further provides a computer storage medium having a computer program stored thereon, wherein the computer program, when executed by a processor, implements the steps of the method for decoupling production of automobile factory orders, and the computer storage medium includes but is not limited to: a compact disc read-only memory (CD-ROM), a random access memory (RAM), a floppy disk, a hard disk or a magneto-optical disk, etc.
[0102] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein by equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. The production method of decoupling orders from automobile factories, It is characterized in that The following steps are involved: Get order information and vehicle body information; Decomposing the order information into welding order, painting order and final assembly order; Establish order decoupling model; Execute the order decoupling model according to the welding order, the painting order, the final assembly order and the vehicle body information, and obtain the execution result; Dynamically adjust the tasks and processes of the car body on the production line according to the execution results, and update the corresponding information of the car body in real time; Bind the car bodies shipped out of the factory with the corresponding orders to realize order delivery; Wherein, establishing the order decoupling model includes: Constructing color-changing frequency optimization function f based on decomposition multi-objective optimization algorithm 1 , delivery order optimization function f 2 , manufacturing path optimization function f 3 ; According to the color-changing frequency optimization function f 1 , delivery order optimization function f 2 , manufacturing path optimization function f 3 , build an order decoupling model; The color change frequency optimization function The delivery order optimization function f 2 =O 1 -X (g) ,g∈h; The manufacturing path optimization function In the formula, is the sum function of the number of orders for the color of the car model, Q is the color expedited coefficient, O 1 is the delivery sequence number of the first order to be executed, X (g) is the sequence number of the first order matching the g-th car body, k is the production line number, W k is the production line color coefficient, C (e) is the sum function of the number of car bodies of various colors in the storage area, g is the number of car bodies, and h is the set of order types to be executed; The order decoupling model is constructed as follows: In the formula, x i ∈Ω,x i represents the decision vector of the optimization function, and Ω represents the color change frequency optimization function f 1 , delivery order optimization function f 2 , manufacturing path optimization function f 3 The set of decision variables; w i represents the weight coefficient corresponding to the optimization function; f(i) represents the optimization function; is the theoretical minimum value of the optimization function, is the theoretical maximum value of the optimization function, and c is the compensation constant.
2. The automobile factory order decoupling production method according to claim 1, It is characterized in that The welding order includes the order number and vehicle model; The painting order includes order number, vehicle model, and color; The final assembly order includes order number, vehicle model, color, and configuration.
3. The automobile factory order decoupling production method according to claim 1, It is characterized in that Sum function of the number of orders for the color of the model The build is as follows: In the formula, O i A Boolean value indicating whether the i-th order belongs to the current model. If yes, O i The value is 1, otherwise O i The value is 0; δ indicates whether the i-th order belongs to the current car model color. If so, δ takes the value of 1, otherwise δ takes the value of 0; i is the number of orders, and b is the color type set of the production plan; The sum function C of the number of car bodies of various colors in the storage area (e) The build is as follows: In the formula, q e Indicates the number of car bodies of the eth color, where e is the number of car body colors and m is the set of color types allocated to the current workshop storage area.
4. A production system for decoupling orders from automobile factories, applied to the production method for decoupling orders from automobile factories as claimed in any one of claims 1 to 3, It is characterized in that include: Order management module, plan receiving module, storage module, APS module, model building module, output module, production execution module, dynamic allocation module and order binding module.
5. The automobile factory order decoupling production system according to claim 4, It is characterized in that The order management module is used to manage customer orders, including receiving, recording, tracking, coordinating production, inventory management, logistics arrangements, and ensuring accurate and timely delivery of orders; The plan receiving module is used to regularly receive the production plan; The storage module is used to store data information including order information, vehicle body information, production plan and inventory status; The APS module is used to decompose the order into welding order, painting order and final assembly order; The model building module is used to build an order decoupling model; The output module is used to output the production plan and scheduling information generated according to the order decoupling model for the production execution module to execute production; The production execution module is responsible for executing the production plan and updating the production status in real time; The dynamic allocation module is used to dynamically allocate body operations according to the production plan and the order decoupling model; The order binding module is used for binding the vehicle body shipped out of the factory with the corresponding order when the vehicle body is shipped out of the factory after the operation is completed.
6. An electronic device, include: A processor, a memory, a communication interface and a communication bus, wherein the processor, the memory and the communication interface communicate with each other via the communication bus; The memory is used to store at least one executable instruction, and the executable instruction enables the processor to perform an operation corresponding to the method according to any one of claims 1 to 3.
7. A computer storage medium having a computer program stored thereon, wherein when the program is executed by a processor, the method according to any one of claims 1 to 3 is implemented.