Switchgear integrated protection measurement and control method and measurement and control system based on fault diagnosis

By constructing a directional relationship network of operating status and identifying key intelligent components, the problem of low fault diagnosis efficiency and data privacy in the existing technology is solved, rapid and accurate fault diagnosis of the switch cabinet system is achieved, and the stability and safety of the power system are improved. sex.

CN118611271BActive Publication Date: 2024-10-18GUANGDONG ZHONGXING ELECTRIC SWITCH
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202411077521.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-10-18
Estimated Expiration
2044-08-07

AI Technical Summary

Technical Problem

Existing fault diagnosis methods have poor diagnostic results in complex fault scenarios, and due to the high complexity of the model, it is difficult to execute them in real time and efficiently, and there is a risk of data privacy leakage.

Method used

By obtaining the data exchange sequence of the smart components of the switch cabinet, we can build a directional relationship network of operating status, identify key smart components, conduct fault diagnosis, ensure data privacy, simplify the diagnosis process, and reduce computing power consumption.

Benefits of technology

It achieves fast and accurate fault diagnosis of the switch cabinet system, reduces fault diagnosis time, improves the operational stability and security of the power system, and avoids data privacy leakage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118611271B_ABST
    Figure CN118611271B_ABST
Patent Text Reader

Abstract

The present application provides a switch cabinet integrated protection measurement and control method and measurement and control system based on fault diagnosis, which can analyze the operation exchange data between each switch cabinet intelligent component, obtain the operation status directional relationship network composed of each switch cabinet intelligent component, and obtain the key intelligent component based on the analysis of the composition architecture of the operation status directional relationship network. Under the premise of protecting data privacy, only the architecture of the operation status directional relationship network is diagnosed. The diagnosis method of each intelligent component is simple, the data processing computing power consumption is small, and the diagnosis speed is improved. In addition, the cost is low. By determining the key intelligent component, only the key intelligent component information in the key intelligent component is diagnosed, and the fault diagnosis of the power system operation process can be completed, which further reduces the computing power consumption of the fault diagnosis of the power system operation process, further improves the fault diagnosis speed, and helps to timely troubleshoot faults and restore normal production and life.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of data processing technology, and in particular to a switch cabinet comprehensive protection measurement and control method and measurement and control system based on fault diagnosis. Background Art

[0002] With the continuous development and improvement of the intelligent level of power systems, switchgear, as an important part of the power system, its operating status is directly related to the safety and stability of the entire system. Traditional switchgear monitoring and protection methods often rely on the monitoring data of a single component, which is difficult to fully reflect the complex interactive relationship between switchgear and each other, resulting in one-sided information and low diagnostic efficiency during fault diagnosis.

[0003] In recent years, with the rapid development of the Internet of Things, big data and artificial intelligence technologies, the intelligence level of switchgear has been significantly improved. More and more switchgears are equipped with intelligent components, which can not only monitor their own status in real time, but also exchange data with other components to form a complex data interaction network. However, how to effectively use these massive data to accurately and quickly identify the source of faults in the switchgear system has become a technical problem that needs to be solved in the current power system operation and maintenance field. Existing fault diagnosis methods mostly focus on the status monitoring and analysis of a single intelligent component, ignoring the interaction and influence between components, resulting in poor diagnosis results in complex fault scenarios. In addition, although some methods attempt to build association models between components, they are often difficult to execute in real time and efficiently in practical applications due to the high complexity of the model and the large amount of calculation. At the same time, these methods may also involve direct access to the internal data of intelligent components, which poses a risk of data privacy leakage. Summary of the invention

[0004] In view of this, the present application at least provides a switch cabinet comprehensive protection measurement and control method and measurement and control system based on fault diagnosis. The technical solution of the present application is implemented as follows: In the first aspect, the embodiment of the present application provides a switch cabinet comprehensive protection measurement and control method based on fault diagnosis, the method comprising: obtaining a data exchange sequence that occurs in the operation link of the power system for X switch cabinet intelligent components, creating X operation status network vertices with the X switch cabinet intelligent components, and using the data exchange sequence to create directional connection lines between the X operation status network vertices to obtain an operation status directional relationship network; wherein X≥1; taking the operation status network vertex that is fully connected with other switch cabinet intelligent components in the operation status directional relationship network as the first operation status network vertex; obtaining the target dominant intelligent components corresponding to the X operation status network vertices in the operation status directional relationship network, and connecting the X The switch cabinet smart components corresponding to the operating status network vertices have the largest number of target dominant smart components corresponding to the operating status network vertices, which serve as the key smart components among the X switch cabinet smart components; the target dominant smart components corresponding to any operating status network vertex represent the smart components included in the connection route from the first operating status network vertex to the operating status network vertex; fault diagnosis is performed on the key smart component information included in the key smart components to determine the first fault information of the power system operation link; in the second aspect, the present application provides a measurement and control system, including a memory and a processor, the memory stores a computer program that can be run on the processor, and the processor implements the steps in the above method when executing the program.

[0005] The beneficial effects of the present application include at least: the present application obtains a data exchange sequence occurring in the operation link of the power system by X switch cabinet intelligent components, creates X operation status network vertices with the X switch cabinet intelligent components, and creates directional connection lines between the X operation status network vertices with the data exchange sequence occurring in the X switch cabinet intelligent components, thereby obtaining an operation status directional relationship network; wherein X≥1; the operation status network vertex that is fully connected with other switch cabinet intelligent components in the operation status directional relationship network is used as the first operation status network vertex; the target dominant intelligent components corresponding to the X operation status network vertices are obtained from the operation status directional relationship network, and the switch cabinet intelligent components corresponding to the operation status network vertices with the largest number of target dominant intelligent components corresponding to the X operation status network vertices are used as the key intelligent components among the X switch cabinet intelligent components; the target dominant intelligent components corresponding to any operation status network vertex represent the intelligent components included in the connection route from the first operation status network vertex to the operation status network vertex; fault diagnosis is performed on the key intelligent component information included in the key intelligent components to determine the first fault information of the operation link of the power system. Based on this, the operation exchange data between the intelligent components of each switch cabinet can be analyzed to obtain the operation status directional relationship network composed of the intelligent components of each switch cabinet. Based on the analysis of the composition architecture of the operation status directional relationship network, the key intelligent components are obtained. Under the premise of protecting data privacy, only the architecture of the operation status directional relationship network is diagnosed. Then, the diagnosis method of each intelligent component is simple, the data processing computing power consumption is small, and the diagnosis speed is improved. In addition, there is no need to introduce additional auxiliary diagnosis methods for the intelligent components of the switch cabinet, and the cost is low. By determining the key intelligent components and only performing fault diagnosis on the key intelligent component information in the key intelligent components, the fault diagnosis of the power system operation process can be completed, further reducing the computing power consumption of the fault diagnosis of the power system operation process, further improving the fault diagnosis speed, helping to timely troubleshoot faults and restore normal production and life. BRIEF DESCRIPTION OF THE DRAWINGS

[0006] Figure 1 A schematic diagram of the implementation flow of a switch cabinet comprehensive protection measurement and control method based on fault diagnosis provided in an embodiment of the present application;

[0007] Figure 2 A hardware entity schematic diagram of a measurement and control system provided in an embodiment of the present application. DETAILED DESCRIPTION

[0008] The embodiment of the present application provides a switch cabinet integrated protection measurement and control method based on fault diagnosis, which can be executed by a processor of a measurement and control system. The measurement and control system can refer to a server, a laptop, a tablet computer, a desktop computer, a mobile device (such as a mobile phone, a portable video player, a personal digital assistant, a dedicated messaging device, a portable gaming device) and other devices with data processing capabilities.

[0009] Figure 1 A schematic diagram of the implementation flow of a switch cabinet comprehensive protection measurement and control method based on fault diagnosis provided in an embodiment of the present application is shown in FIG. Figure 1 As shown, the method includes: step S100: obtaining a data exchange sequence occurring in the operation link of the power system of X switch cabinet intelligent components, creating X operation status network vertices with the X switch cabinet intelligent components, and creating directional connection lines between the X operation status network vertices with the data exchange sequence to obtain an operation status directional relationship network; wherein X≥1.

[0010] In the switchgear, intelligent components refer to those that integrate a variety of intelligent electronic devices to realize the monitoring, control, protection and communication functions of the switchgear. These intelligent components can significantly improve the intelligence level of the switchgear and enhance the safety and reliability of the power system. The following are some types of intelligent components that may exist in the switchgear: intelligent circuit breakers, intelligent protectors, intelligent telemetry terminals (an intelligent component used to realize remote monitoring and control of electrical equipment. It can collect various operating data in the switchgear, such as current, voltage, temperature, etc., and upload these data to the monitoring center through the communication network), intelligent control devices, sensors (such as current sensors, voltage sensors, temperature sensors, etc.) and controllers, etc.

[0011] Step S100 focuses on the X switch cabinet smart components actually running in the power system. These smart components are not only responsible for monitoring the status of the power lines or equipment they are responsible for, but also exchange data with other smart components through internal communication mechanisms to achieve collaborative work and fault warning. Specifically, assume that five switch cabinet smart components (X=5) are deployed in a power system, marked as components A, B, C, D and E. In the daily operation of the power system, these components will send instructions or data to other components according to the state changes they monitor, so as to achieve remote control of the switch cabinet and rapid transmission of fault information. For example, when component A detects an abnormal current in a certain line, it can send a tripping command to component B (responsible for the circuit breaker control of the line) to prevent the fault from expanding; at the same time, it may also report this abnormal information to component C (as the system monitoring center).

[0012] When the measurement and control system executes step S100, it collects all data exchange sequences generated by the five switch cabinet intelligent components during operation. These data exchange sequences may include instruction flows, exchanged data, fault alarms, etc. between components, which record in detail how the components work together through data exchange. Next, the measurement and control system logically creates five corresponding operation status network vertices based on the five switch cabinet intelligent components, and each vertex represents a specific intelligent component. These vertices will become the cornerstone for the subsequent construction of the operation status directional relationship network. Subsequently, the measurement and control system establishes directional connection lines between these operation status network vertices based on the collected data exchange sequences. Each directional connection line represents the direction and content of data exchange, thereby constructing a complete operation status directional relationship network. This relationship network is essentially a directed graph, which intuitively shows the data exchange relationship and degree of dependence between the switch cabinet intelligent components. For example, if component A sends a trip command to component B, then in the operation status directional relationship network, there will be a directional connection line from vertex A to vertex B. Similarly, if component C receives fault reports from multiple components, then vertex C will have multiple directional connection lines pointing to it.

[0013] Step S200: taking the operating status network vertex that is fully connected with other switch cabinet intelligent components in the operating status directional relationship network as the first operating status network vertex.

[0014] In the embodiment of the present application, step S200 aims to identify the operating status network vertices with special status from the constructed operating status directional relationship network, that is, those vertices that have direct connection relationships with all other switch cabinet intelligent components, and these vertices are designated as the first operating status network vertices. Specifically, the measurement and control system first examines the entire operating status directional relationship network, which is composed of multiple operating status network vertices and directional connection lines between them. Each vertex represents a switch cabinet intelligent component, and each connection line represents the data exchange relationship between components. The goal of the measurement and control system is to find those vertices that serve as data exchange hubs, that is, those vertices that can communicate directly or indirectly with all other vertices in the network.

[0015] Take a power system containing multiple switchgear intelligent components as an example. Assume that these components are interconnected through a complex data exchange network to jointly monitor and protect the stable operation of the power system. By analyzing this network, the measurement and control system finds that one of the switchgear intelligent components (such as component M) has a special position: starting from component M, there is a direct or indirect route to any other component in the network (such as component N, O, P, etc.). In other words, component M maintains some form of data exchange relationship with all other components, whether this relationship is direct or indirectly realized through other components. At this time, the operating state network vertex corresponding to component M is identified as the first operating state network vertex. In this way, the state change or failure of the first operating state network vertex can have a profound impact on the operation of the entire network. Therefore, identifying such a vertex helps the measurement and control system to give more attention and priority in subsequent fault diagnosis and comprehensive protection strategy formulation.

[0016] By executing step S200, the measurement and control system not only simplifies the analysis process of the complex network, but also provides an important reference point for subsequent fault diagnosis. Once the first operating state network vertices are determined, the measurement and control system can conduct a more in-depth analysis around these vertices to identify potential fault sources or risk points, so as to take corresponding protection measures to ensure the safe and stable operation of the power system.

[0017] Step S300: Obtain target dominant smart components corresponding to X operating status network vertices in the operating status directional relationship network, and use the switch cabinet smart component corresponding to the operating status network vertex with the largest number among the target dominant smart components corresponding to the X operating status network vertices as the key smart component among the X switch cabinet smart components; the target dominant smart component corresponding to any operating status network vertex represents the smart component included in the connection route from the first operating status network vertex to the operating status network vertex.

[0018] In step S300 of the embodiment of the present application, the measurement and control system aims to extract key vertices, i.e., key intelligent components, that have an important impact on the overall operating state from a complex network structure. First, the measurement and control system clarifies the dominant position of each operating state network vertex (representing a switch cabinet intelligent component) in the network, that is, starting from the first operating state network vertex (usually the center or core vertex of the network), the other vertices that must be passed through in the process of reaching the vertex. These vertices that must be passed are regarded as target-dominant intelligent components, which play a bridging role in data exchange and state transfer. Taking the switch cabinet intelligent component network in a certain power system as an example, assuming that the first operating state network vertex is component A, it has a direct or indirect data exchange relationship with all other components (such as B, C, D, etc.). The measurement and control system analyzes all possible connection routes from A to B, from A to C, and from A to D, and determines which components are indispensable in these routes, that is, which components appear on all or most routes starting from A. These components are regarded as their respective corresponding target-dominant intelligent components. Next, the measurement and control system counts the number of times each switch cabinet intelligent component appears as a target-dominant intelligent component. Since some components may occupy a more central position in the network, they will be reused on multiple key routes, so the number of occurrences will be relatively high. The measurement and control system identifies the switch cabinet intelligent components corresponding to the operating status network vertices with the highest number of occurrences as key intelligent components. For example, during the analysis process, if component B is used as a must-pass vertex on multiple routes from A to other components, then the number of occurrences of component B will be very high, and it may be identified as a key intelligent component. This means that the status and performance of component B have a vital impact on the stable operation of the entire network. Once B fails, it can trigger a chain reaction and affect the normal operation of multiple other components.

[0019] Through the execution of step S300, the measurement and control system not only identifies key intelligent components, but also reveals their importance and dominance in the directional relationship network of operating status. This provides key information for subsequent fault diagnosis and comprehensive protection strategies, allowing operation and maintenance personnel to more accurately locate potential risk points and take corresponding measures to ensure the safe and stable operation of the power system.

[0020] Step S400: performing fault diagnosis on key intelligent component information included in the key intelligent component to determine first fault information of the power system operation link.

[0021] In step S400 of the embodiment of the present application, the measurement and control system focuses on analyzing the key intelligent components identified in the previous steps at this stage, diagnoses potential faults in the operation of the power system by deeply mining the key information in these components, and determines the first fault information accordingly. Specifically, the measurement and control system extracts all relevant key intelligent component information from the key intelligent components. This information includes but is not limited to the operating status data of the components, historical fault records, real-time data exchange records, and any external factors that may affect the normal operation of the components. This information is an important basis for fault diagnosis, and they reflect the current working status, historical performance, and possible problems of the components. Next, the measurement and control system uses advanced fault diagnosis algorithms and technologies to conduct in-depth analysis of these key information. These algorithms may include rule-based diagnosis, model-based diagnosis, data mining-based diagnosis, and other methods, and the specific selection depends on the actual needs and application scenarios of the system. Through analysis, the measurement and control system can identify possible abnormalities or failure modes in key intelligent components, such as parameter deviations from normal values, data exchange anomalies, communication interruptions, etc.

[0022] Taking a specific intelligent component of a switch cabinet as an example, it is assumed that the component is identified as a key intelligent component, and during the analysis process, it is found that some parameters in its operating status data are abnormally high, and the data exchange records related to the component also show communication delays or packet loss. These abnormal information will be captured by the measurement and control system and used as an important basis for fault diagnosis. Based on these abnormal information, the measurement and control system further infers possible causes of the fault, such as aging of components inside the component, communication line failure, external environmental interference, etc. Then, the measurement and control system combines these causes of the fault to form the first fault information, which describes in detail the specific location, nature and possible impact range of the fault. Finally, the measurement and control system reports the first fault information to the operation and maintenance personnel or related systems in a timely manner so that they can take corresponding measures to repair the fault and restore the normal operation of the power system. This step not only improves the accuracy and efficiency of fault diagnosis, but also provides a strong guarantee for the safe and stable operation of the power system. Through the execution of step S400, the measurement and control system realizes accurate fault diagnosis of key intelligent components, providing important support for the comprehensive protection measurement and control of the power system. This will not only help reduce the impact of faults on the power system, but also improve the efficiency and accuracy of operation and maintenance, laying a solid foundation for the long-term stable operation of the power system.

[0023] As an implementation mode, step S200, taking the operating status network vertex that is fully connected with other switch cabinet intelligent components in the operating status directional relationship network as the first operating status network vertex, can specifically include: step S210: in the operating status directional relationship network, taking X operating status network vertices as starting vertices respectively, and wandering to obtain the connection route of each operating status network vertex in the operating status directional relationship network.

[0024] In the embodiment of the present application, step S210 is an important step in the process of determining the first operating state network vertex. The execution subject of this step is the measurement and control system, which is responsible for deeply exploring the connection relationship between each operating state network vertex (i.e., switch cabinet intelligent component) in the constructed operating state directional relationship network.

[0025] Specifically, step S210 requires the measurement and control system to start from each operating state network vertex of the operating state directional relationship network and walk. The walk here means that the measurement and control system visits all other vertices connected to the starting vertex in turn along the directional connection lines between the vertices, and records the visited routes until it can no longer be expanded. This process is similar to the depth first search (DFS) or breadth first search (BFS) in graph theory, but the purpose is not to find all the routes in the graph, but to build a connection route map of all vertices that can be reached from each vertex.

[0026] Taking a specific power system as an example, assuming that the system contains four switch cabinet intelligent components A, B, C, and D, the data exchange relationship between them constitutes a directional relationship network of operation status. In this network, A may send instructions to B, and B sends instructions to C, and A may also send instructions directly to D. At this time, the measurement and control system executes step S210 and walks with A, B, C, and D as the starting point respectively.

[0027] When A is taken as the starting point, the measurement and control system first visits B along the connection line from A, records the route "A→B", and then continues with B as the current vertex, visits C that can be reached by B, and records the expanded route "A→B→C". If B has other connection lines pointing to unvisited vertices, the measurement and control system will continue to wander and record them. At the same time, the measurement and control system will also visit D directly from A, and record the route "A→D". Similarly, the measurement and control system takes B, C, and D as starting points, repeats the above wandering process, and records the routes of all vertices that can be reached from each vertex.

[0028] Through the execution of step S210, the measurement and control system can fully grasp the connection relationship between each vertex in the operating status directional relationship network, and provide the necessary information basis for the subsequent determination of the first operating status network vertex. This information not only helps to understand the overall structure of the system, but also provides an important reference for subsequent fault diagnosis and comprehensive protection strategy formulation. It is worth noting that during the wandering process, the measurement and control system may encounter a circular connection, that is, a vertex eventually points to itself through a series of connecting lines. In order to avoid infinite loops, the measurement and control system adopts appropriate strategies to detect and handle this situation, such as marking the visited vertices to avoid repeated visits. At the same time, the measurement and control system also needs to record all non-repeated vertices encountered during the wandering process for subsequent analysis.

[0029] Step S220: If the connection routes obtained by walking include a connection route including X running status network vertices, the corresponding running status network vertex is used as the first running status network vertex.

[0030] In an embodiment of the present application, the execution of step S220 depends on the comprehensive analysis of all possible connection routes in the operation status directional relationship network by the measurement and control system. In step S210, the measurement and control system has taken each operation status network vertex (i.e., each switch cabinet intelligent component) as the starting point, wandered the network, and recorded the connection routes of all other vertices that can be reached from each vertex. Now, the measurement and control system checks these connection routes to see if there is at least one route that includes all X operation status network vertices in the network. If there is such a route, that is, there is at least one vertex from which you can wander to all other vertices in the network, then the measurement and control system will identify this vertex as the first operation status network vertex. This vertex plays a vital role in the network because it is a bridge connecting all other components, and its state changes or failures are likely to have a significant impact on the operation of the entire system.

[0031] To illustrate this more specifically, we can imagine a power system containing five switchgear intelligent components (A, B, C, D, E). In this system, the data exchange relationship between the components is intricate, but the measurement and control system has mastered all possible connection routes through the wandering operation of step S210. Now, the measurement and control system checks these routes and finds that there is a route "A→B→C→D→E" starting from component A, which happens to cover all five operating state network vertices in the network. Therefore, according to the judgment criteria of step S220, the measurement and control system identifies component A as the first operating state network vertex.

[0032] It should be noted that in actual situations, there may be multiple routes that meet the condition of including all X operating state network vertices. In this case, the measurement and control system can further screen according to preset rules (such as selecting the vertex with the shortest route, the vertex with the highest connectivity, etc.) to determine the final first operating state network vertex. However, in most application scenarios based on fault diagnosis, as long as a vertex that meets the conditions can be found as the first operating state network vertex, it is sufficient to support subsequent fault analysis and protection strategy formulation.

[0033] Through the execution of step S220, the measurement and control system provides a clear starting point for the subsequent fault diagnosis and comprehensive protection measurement and control process. The selection of this starting point is not only based on the in-depth analysis of the network structure, but also fully considers the relative importance and connectivity of each component in the network, thereby providing a strong guarantee for the stable operation of the entire system.

[0034] Step S230: If the connection routes obtained by wandering do not have a connection route including X running status network vertices, a dummy smart component is created in the running status directional relationship network, and a dummy connection line is created between the dummy smart component and the running status directional relationship network, with the dummy smart component as the first running status network vertex.

[0035] In the embodiment of the present application, step S230 ensures that no matter how complex the structure of the operation status directional relationship network is, the measurement and control system can find a first operation status network vertex to support subsequent fault analysis and protection strategy formulation. When the measurement and control system executes to step S230, it means that in the previous steps S210 and S220, a connection route containing all X operation status network vertices has not been found. This usually occurs when the network structure is particularly complex or dispersed, and no vertex can be directly or indirectly connected to all other vertices.

[0036] To deal with this situation, the measurement and control system has adopted a creative solution: introducing "fake intelligent components" and "fake connection lines" into the operation status directional relationship network. These fake elements are not actual physical components or data exchange relationships, but logical entities temporarily created by the measurement and control system for analysis purposes. Their main function is to act as a bridge to connect those operation status network vertices that were not directly connected, thereby allowing the measurement and control system to construct a virtual central vertex containing all vertices, namely the first operation status network vertex.

[0037] In the specific implementation, the measurement and control system analyzes the connection routes corresponding to each running state network vertex and calculates the number of non-repeated running state network vertices contained in each route. This number reflects the connection breadth and importance of the vertex in the network. The measurement and control system finds the vertex with the largest number of non-repeated vertices in the connection route as the "first intended connected intelligent component". Although this vertex may not be directly connected to all other vertices, its position in the network is relatively central and connects more other components. Next, the measurement and control system identifies those running state network vertices that do not appear in the connection route of the first intended connected intelligent component. These vertices are called "second intended connected intelligent components". These vertices may be located at the edge of the network or in relatively isolated areas and have no direct connection with the first intended connected intelligent component. In order to connect all these vertices, a fake intelligent component is created in the running state directed relationship network, and fake connection lines are created between the fake component and the first intended connected intelligent component and all second intended connected intelligent components. In this way, the fake intelligent component becomes a virtual central vertex, which can be indirectly connected to all other vertices in the network through fake connection lines.

[0038] Taking the switch cabinet smart component as an example, assume that the switch cabinet smart component 4 is the first to-be-connected smart component with the largest number of non-repeated vertices in the connection route, but its connection route does not cover all other components. The measurement and control system identifies the uncovered components, then creates a fake smart component and connects the fake component to the switch cabinet smart component 4 and all uncovered components through a fake connection line. In this way, the fake smart component is regarded as the first operating state network vertex for subsequent fault analysis and protection strategy formulation.

[0039] By executing step S230, the measurement and control system ensures that a first operating state network vertex can be found in any network structure, thereby improving the convenience and flexibility of parsing the operating state directional relationship network structure. This creative solution not only solves the analysis problem under complex network structure, but also provides a solid foundation for subsequent fault diagnosis and comprehensive protection measurement and control process.

[0040] As another implementation method, step S200, taking the operating status network vertex that is fully connected with other switch cabinet intelligent components in the operating status directional relationship network as the first operating status network vertex, can specifically include: step S210': obtaining the u-th operating status network vertex in the operating status directional relationship network, taking the u-th operating status network vertex as the starting vertex, and performing an exhaustive branch search on the operating status directional relationship network to obtain the u-th original data exchange hierarchical graph; wherein, 1≤u≤X; the starting vertex of the u-th original data exchange hierarchical graph is the u-th operating status network vertex.

[0041] In the embodiment of the present application, step S210' reflects how the measurement and control system deeply explores the structure of the directional relationship network of the operating state. The execution of this step depends on an efficient search strategy adopted by the measurement and control system - exhaustive branch search, which is essentially similar to the depth-first walk algorithm. Specifically, the execution process of step S210' is as follows: First, the measurement and control system selects the u-th operating state network vertex from the directional relationship network of the operating state as the starting point. Here, u is an index value, which identifies the position of the vertex currently being examined in the network, and the value range of u is from 1 to X, where X represents the total number of switch cabinet intelligent components in the network. Starting from the u-th operating state network vertex, the measurement and control system is ready for an in-depth exploration journey. Next, the measurement and control system starts the exhaustive branch search process. This process is similar to finding a way out in a maze, but here, the "maze" is the directional relationship network of the operating state, and the "way out" is all the vertices that can be reached from the starting point. The measurement and control system explores in depth along the first connection line starting from the starting point, and whenever it reaches a new vertex, it checks whether there are any unexplored connection lines for the vertex. If there is, the measurement and control system continues to go deeper along this new connection line; if not, or the current connection line has been explored, the measurement and control system goes back to the previous vertex and tries other unexplored connection lines. This search process will continue until the measurement and control system has explored all reachable vertices from the starting point and there are no new connection lines to explore. At this point, the measurement and control system stops searching and builds a tree structure based on the explored vertices and the connection lines between them, that is, the u-th original data exchange hierarchical graph. This hierarchical graph takes the u-th operating status network vertex as the starting vertex and shows the route relationship of all vertices that can be reached from this vertex.

[0042] For example, assume that in a power system containing five switch cabinet intelligent components (A, B, C, D, E), the operating status directional relationship network is intricate. The measurement and control system first selects component A as the u-th operating status network vertex (i.e., u=1) for search. During the search process, the measurement and control system can find that A can communicate directly with B and C, and B can further communicate with D, and C is directly connected to E. Through exhaustive branch search, the measurement and control system constructs an original data exchange hierarchical graph with A as the starting vertex, which clearly shows the route relationship from A to B, C, D, and E. It should be noted that although A is explained as the first search starting point here, in actual applications, the measurement and control system can try every operating status network vertex in the network as a starting point for search until an original data exchange hierarchical graph that meets specific conditions (such as containing all vertices) is found. However, step S210' itself only focuses on the search process and its results starting from a single starting point.

[0043] Step S220': If there is an operating status network vertex among the X operating status network vertices that is not included in the u-th original data exchange hierarchical graph, then use the v-th operating status network vertex as the starting vertex, perform an exhaustive branch search on the operating status directional relationship network, and obtain the v-th original data exchange hierarchical graph, where v=u+1.

[0044] In the embodiment of the present application, step S220' is an iterative step in the process of determining the first operating state network vertex, which reflects the flexibility and systematicness of the measurement and control system when facing a complex network structure. When the measurement and control system executes step S220', it means that the u-th original data exchange hierarchy diagram constructed by the exhaustive branch search (step S210') with the u-th operating state network vertex as the starting point does not contain all X operating state network vertices. Therefore, the measurement and control system adjusts the strategy and tries to search with other vertices in the network as new starting points.

[0045] Specifically, the execution process of step S220' is as follows: First, the measurement and control system checks whether any operating status network vertices have been missed in the previous search process, that is, whether there are some vertices that do not appear in the u-th original data exchange hierarchy diagram. This is the key to determining whether the search needs to continue. If there are indeed unincluded operating status network vertices, the measurement and control system regards these vertices as targets for subsequent searches. However, in order to maintain the orderliness and efficiency of the search, the measurement and control system will not randomly select an unincluded vertex as a new starting point, but follow a predetermined order. In this order, the next vertex after the u-th vertex (i.e., v=u+1) will be selected as the new starting point.

[0046] Next, the measurement and control system takes the vth running state network vertex as a new starting point and repeats the exhaustive branch search process in step S210'. This means that the measurement and control system deeply explores along all the connection lines starting from the vth vertex and constructs a new original data exchange hierarchical graph with the vth vertex as the starting vertex. This new hierarchical graph will show the route relationship of all vertices that can be reached from the vth vertex.

[0047] For example, suppose that in a power system containing five switchgear intelligent components (A, B, C, D, E), the measurement and control system first selects component A as the starting point for search, but the constructed original data exchange hierarchy diagram does not include component E. At this time, the measurement and control system selects the next component (assuming it is B) as the new starting point in a predetermined order and repeats the search process. If the search starting from B still fails to include E, the measurement and control system continues to select C and D (if they have not been tried before) until an original data exchange hierarchy diagram is found that can include all the running state network vertices. It should be noted that although the measurement and control system tries every running state network vertex in the network as a starting point for search, this process is not disordered or random. Each vertex is tried one by one in a certain order (such as the vertex number, the position in the network, etc.) until the conditions are met. This orderliness ensures the efficiency and controllability of the search process. At the same time, the measurement and control system will also record the results of each search for comparison and analysis in subsequent steps.

[0048] Step S230': if the u-th original data exchange hierarchical graph includes X running status network vertices, the u-th running status network vertex is used as the first running status network vertex.

[0049] In the embodiment of the present application, step S230' is a key decision point in the process of determining the first operating state network vertex. The execution of this step indicates that the measurement and control system has found an original data exchange hierarchical graph that meets specific conditions through exhaustive branch search, that is, the hierarchical graph contains all X operating state network vertices in the network. At this time, the measurement and control system determines the starting vertex of the hierarchical graph (that is, the u-th operating state network vertex) as the first operating state network vertex based on this result.

[0050] Specifically, when the measurement and control system executes step S230', it has completed the exhaustive branch search with the u-th operating status network vertex as the starting point, and constructed the corresponding original data exchange hierarchical graph. In this process, the measurement and control system checks whether the hierarchical graph contains all the vertices in the network. If the check result shows that the hierarchical graph does contain all X operating status network vertices, then the measurement and control system can be sure that starting from the u-th vertex, it can wander to any other vertex in the network. This means that the u-th vertex plays the role of a central connection point in the network, which is of great significance to the operating status and fault diagnosis of the entire network. Therefore, the measurement and control system uses the u-th operating status network vertex as the first operating status network vertex. This decision is based on an in-depth analysis and understanding of the network structure. It ensures that the subsequent fault diagnosis and integrated protection measurement and control process can be carried out around a core vertex, thereby improving the accuracy and efficiency of fault location.

[0051] For example, suppose that in a power system containing five switchgear intelligent components (A, B, C, D, E), the measurement and control system, through a series of exhaustive branch searches, finally finds that the original data exchange hierarchy diagram starting from component C contains all the operating state network vertices. This means that starting from component C, any of components A, B, D, and E can be reached directly or indirectly. Therefore, the measurement and control system determines component C as the first operating state network vertex and gives it special attention in the subsequent fault diagnosis and integrated protection measurement and control process.

[0052] By executing step S230', the measurement and control system not only determines a key vertex in the network, but also provides an important reference for subsequent fault analysis and protection strategy formulation. This makes the entire fault diagnosis and comprehensive protection measurement and control process more systematic and efficient, helps to quickly and accurately locate the fault source, and ensure the stable operation of the power system.

[0053] As an implementation mode, step S300, obtaining target dominant intelligent components corresponding to X operating status network vertices in the operating status directional relationship network, may specifically include: step S310: obtaining Y connection routes g from the first operating status network vertex to the g-th operating status network vertex in the operating status directional relationship network, and obtaining the connection vertices respectively included in the Y connection routes g; wherein, 1≤g≤X, 1≤Y.

[0054] In the embodiment of the present application, step S310 is a key step to determine the relative importance of each operating state network vertex (i.e., each switch cabinet intelligent component) in the network. In this step, the measurement and control system mainly focuses on all possible connection routes from the first operating state network vertex to all other operating state network vertices, as well as the specific connection vertices on these routes.

[0055] Specifically, the measurement and control system first identifies the core position of the first running state network vertex in the network. This vertex is usually determined through a series of analyses in the previous steps, and it has high connectivity and centrality in the network. Then, the measurement and control system begins to walk all possible routes from this vertex to each other running state network vertex in the network. For the g-th running state network vertex (where g ranges from 1 to X, and X is the total number of running state network vertices in the network), the measurement and control system finds all the connection routes from the first running state network vertex to this vertex. These routes may have multiple, assuming that the number is Y (Y is also an integer greater than or equal to 1, indicating the diversity of routes). During the walking process, the measurement and control system records in detail all the connection vertices on each connection route. These vertices are not just simple route vertices, they actually represent the key links in the data transmission or instruction delivery process. By collecting this information, the measurement and control system can build a detailed map of the data flow within the network and the interaction between components.

[0056] For example, suppose that in a power system containing five switchgear intelligent components (A, B, C, D, E), component A is determined as the first operating state network vertex. The measurement and control system now needs to find all possible connection routes from A to component B (i.e., the g-th operating state network vertex, where g=2). By walking the network, the measurement and control system may find two such routes: "A→C→B" and "A→D→E→B". For these two routes, the measurement and control system records their connection vertices respectively: "A, C, B" and "A, D, E, B".

[0057] By executing step S310, the measurement and control system not only collects all possible connection routes from the first operating state network vertex to each other operating state network vertex in the network, but also records the connection vertices on each route in detail. This information is crucial for the subsequent analysis of the target leading intelligent components of the operating state network vertices, and also provides a solid foundation for the final determination of the key intelligent components.

[0058] Step S320: Among the connection vertices respectively included in the Y connection routes g, the connection vertices common to the Y connection routes g are used as the target dominant intelligent components corresponding to the g-th running status network vertex.

[0059] In this step of the embodiment of the present application, an in-depth analysis is performed on the connection routes and their connection vertices collected in the previous step S310 to determine which vertices play an indispensable role in all relevant routes. Specifically, the measurement and control system reviews the Y connection routes g from the first operating status network vertex to the g-th operating status network vertex obtained in step S310, as well as the connection vertices contained in each route. Next, the measurement and control system performs a comparison and screening process to find out those connection vertices that must appear in all Y connection routes. These vertices, because they exist in all possible transmission routes, are considered to be target-dominant intelligent components that are critical to the g-th operating status network vertex.

[0060] To illustrate this process more clearly, a detailed example is given below. Assume that in a power system containing five switchgear intelligent components (A, B, C, D, E), the measurement and control system has determined two connection routes from the first operating state network vertex A to the fourth operating state network vertex D: "A→B→D" and "A→C→D". In these two routes, the connection vertices are "A, B, D" and "A, C, D" respectively. According to the requirements of step S320, the measurement and control system compares the connection vertices in the two routes and searches for common vertices. In this example, "A" and "D" obviously appear in both routes, but "A" as the starting point is usually not regarded as the target dominant intelligent component (unless it is a key intelligent component in a specific case). Therefore, the measurement and control system identifies the vertices before "B" and "C" (if any) and the common vertex after them (which does not exist in this simple example), but in this example, it is more direct to confirm that "D" is the target vertex itself, and no additional intermediate vertices appear in all routes. However, for the purpose of illustration, it can be assumed that there is a virtual monitoring or relay component "F" that actually participates in some way in all routes from A to D (although it may not be directly visible in the physical connection), then "F" will be identified as the target-leading intelligent component corresponding to the g-th running state network vertex D. But according to the given scenario and step description, it is more common that if there is no such intermediate virtual component and there are differences in the routes before the target vertex, the measurement and control system can conclude that in some cases there is no direct target-leading intelligent component (except for the starting and target points themselves), or further analysis of other characteristics in the network (such as data traffic, communication delay, etc.) is required to determine potential key intermediate links. However, in most cases, the measurement and control system focuses on those components or links that appear stably in all relevant routes as candidates for the target-leading intelligent component.

[0061] As another implementation, step S300, obtaining target dominant intelligent components corresponding to X operating status network vertices in the operating status directional relationship network, may specifically include: step S310': taking the first operating status network vertex as the target dominant intelligent component of the first operating status network vertex.

[0062] In an embodiment of the present application, the measurement and control system first clarifies the special status of the first operating state network vertex in the network. This vertex is usually analyzed through the previous steps (such as step S200). It plays the role of a center or hub in the network and can be directly or indirectly connected to all other vertices in the network. Due to this high degree of connectivity and importance, the first operating state network vertex itself reflects its dominant position in the network without the need for indirect proof through other vertices. Therefore, in step S310', the measurement and control system directly regards the first operating state network vertex as its own target dominant intelligent component. This means that in the subsequent fault analysis and protection strategy formulation process, the measurement and control system pays special attention to this vertex because its state changes or failures are likely to have a significant impact on the operation of the entire network.

[0063] Step S320': obtain the first order predecessor vertex of the second operating status network vertex, and use the semi-dominant intelligent component of the first order predecessor vertex of the second operating status network vertex and the second operating status network vertex as the target dominant intelligent component of the second operating status network vertex; the second operating status network vertex is the operating status network vertex other than the first operating status network vertex among the X operating status network vertices.

[0064] In the embodiment of the present application, step S320' is a key step to determine the target dominant intelligent component of the non-first operating state network vertex (i.e., the second operating state network vertex). In this step, the measurement and control system constructs a target dominant intelligent component set for each second operating state network vertex by deeply analyzing the relationship between the second operating state network vertex and its first-order predecessor vertex (i.e., the predecessor vertex), as well as the semi-dominant intelligent component of the first-order predecessor vertex. Specifically, the measurement and control system first identifies all first-order predecessor vertices that directly point to the vertex for each second operating state network vertex. These predecessor vertices play a key intermediary role in the data flow or instruction transmission process, and their state changes or failures may also have an impact on the second operating state network vertex. Next, the measurement and control system determines the semi-dominant intelligent component of each first-order predecessor vertex. The concept of semi-dominant intelligent component is relatively special here. It does not simply refer to a specific vertex, but is defined based on the importance and hierarchical relationship of the vertex in the network. Simply put, for vertex 1 of the running state network (in this context, it can be regarded as an instance of the first-order predecessor vertex), its semi-dominant intelligent component means that there is a connection route from a certain connection point to vertex 1. On this route, except for vertex 1 and the connection point, the importance of all the vertices passed in the network (or the size under some metric) is greater than that of vertex 1, and the connection point is the least important one among these vertices. However, it should be noted that the definition here may need to be adjusted according to specific scenarios in actual applications to ensure its rationality and practicality. To simplify the understanding, the concept of semi-dominant intelligent components can be understood as one or more important vertices that are above the first-order predecessor vertex and closest to the vertex in the network hierarchy. These vertices play a key supporting role in data transmission or instruction delivery.

[0065] After determining the semi-dominant intelligent components of each first-order predecessor vertex, the measurement and control system regards these semi-dominant intelligent components together with the corresponding second operating state network vertex as the target dominant intelligent components of the second operating state network vertex. This means that in the subsequent fault analysis and protection strategy formulation process, the measurement and control system pays special attention to the state changes of these target dominant intelligent components, because they are crucial to maintaining the normal operation of the second operating state network vertex.

[0066] For example, suppose that in a power system containing multiple switchgear intelligent components, component A is determined as the first operating state network vertex, and component B is one of the second operating state network vertices. The measurement and control system identifies component C as a first-order predecessor vertex of component B (i.e., C directly points to B). When analyzing the semi-dominant intelligent components of C, the measurement and control system finds that there is a connection route from component D to component C, and on this route, except for C and D, no other vertex is more important than C (here, in order to simplify the explanation, it is assumed that the importance of vertices in the network can be directly compared). Therefore, in this simplified example, component D can be regarded as the semi-dominant intelligent component of component C (although more complex judgment logic may be required in actual applications). Ultimately, the measurement and control system regards component D (as the semi-dominant intelligent component of C) and component B together as the target dominant intelligent component set of component B. This means that in the subsequent fault analysis, the measurement and control system pays special attention to the state changes of components D and B.

[0067] As an implementation mode, the method further includes: Step S301: obtaining a second-order predecessor vertex of a first-order predecessor vertex in a running status directional relationship network, and obtaining a first connection route including the first-order predecessor vertex and the second-order predecessor vertex in the running status directional relationship network.

[0068] In the embodiment of the present application, step S301 is an important step to deeply explore the structure of the directional relationship network of the operating state and refine the hierarchical relationship between components. The main task of the measurement and control system at this stage is to find the second order predecessor vertex of the first order predecessor vertex of each second operating state network vertex (i.e., non-first operating state network vertex) and construct a first connection route connecting these vertices.

[0069] Specifically, the measurement and control system identifies the first-order predecessor vertices that directly point to each second-running state network vertex. These predecessor vertices play a key intermediary role in the data flow or instruction transmission process, and their state changes or failures can have an impact on the second-running state network vertex. However, in order to more comprehensively understand the dependencies and fault propagation routes in the network, the measurement and control system continues to trace back to find the upstream vertices of these first-order predecessor vertices, that is, the second-order predecessor vertices.

[0070] In the process of finding the second-order predecessor vertex, the measurement and control system walks the operating state directed relationship network and checks all the connection lines of each first-order predecessor vertex to determine whether there are connections to other vertices that form a route from an upstream vertex to the first-order predecessor vertex. Once such an upstream vertex is found, the measurement and control system will mark it as a second-order predecessor vertex and record all possible routes from the second-order predecessor vertex to the first-order predecessor vertex. Among these routes, the most direct and branchless one (or several, if there are multiple equivalent routes) will be regarded as the first connection route.

[0071] For example, suppose that in the power system, component C is a second operating state network vertex, and component B is the first-order predecessor vertex directly pointing to C. When the measurement and control system executes step S301, it will first confirm the identity and position of B. Then, the measurement and control system checks all the connection lines of B to find the vertex pointing to B. Assuming that component A is the only vertex pointing to B (in actual applications, there may be multiple vertices pointing to B, but the measurement and control system handles them separately), then A is regarded as the second-order predecessor vertex of B. Next, the measurement and control system records the first connection route from A to B. This route may be direct (that is, A is directly connected to B) or it may pass through other intermediate vertices (if the network structure allows), but in this example, it is assumed to be direct.

[0072] By executing step S301, not only the direct upstream vertex (first order predecessor vertex) of each second operation status network vertex is identified, but also the upstream of these upstream vertices (second order predecessor vertex) is further traced back, and the connection route between them is constructed. This information is conducive to the subsequent analysis of the interaction relationship between components, identification of key components and formulation of fault response strategies.

[0073] Step S302: Obtain a second connection route in the first connection route, and use the second-order predecessor vertex corresponding to the second connection route as a semi-dominant intelligent component of the first-order predecessor vertex; the second connection route represents that the first-order predecessor vertex is adjacent to the second-order predecessor vertex, and the first-order predecessor vertex does not have a branch line of a sequence predecessor vertex other than the second-order predecessor vertex.

[0074] In the embodiment of the present application, step S302 is a key step for further detailed analysis of the network structure, which is intended to determine the semi-dominant intelligent component of each first-order predecessor vertex. The execution subject of this step is the measurement and control system, which identifies the semi-dominant intelligent component that has a significant impact on the first-order predecessor vertex by deeply analyzing the specific structure in the first connection route.

[0075] Specifically, in step S301, the measurement and control system has constructed a first connection route from the second-order predecessor vertex to the first-order predecessor vertex. These routes represent the flow routes of data or instructions in the network and are the basis for understanding the interaction relationship between components. However, in order to more accurately identify key components, the measurement and control system further screens these first connection routes to find second connection routes that meet specific conditions. The so-called second connection routes refer to those routes that directly connect the first-order predecessor vertex and the second-order predecessor vertex in the first connection route, and the first-order predecessor vertex has no other branch lines on the route. In other words, the second connection route represents the most direct and non-redundant connection method from the second-order predecessor vertex to the first-order predecessor vertex. The measurement and control system regards the second-order predecessor vertex corresponding to such a second connection route as a semi-dominant intelligent component of the first-order predecessor vertex. For example, assume that in an electric power system, component A is the second-order predecessor vertex of component B, and component B is the first-order predecessor vertex of a second operating state network vertex. In step S301, the measurement and control system has constructed a first connection route from A to B. Now, the measurement and control system executes step S302, which checks the specific structure in the first connection route. If the first connection route is direct, that is, A is directly connected to B, and B has no other connection lines pointing to other vertices (except the connection lines pointing to the downstream vertex), then this direct connection route is regarded as the second connection route, and A is determined to be the semi-dominant intelligent component of B.

[0076] However, in actual applications, the first connection route may be more complex, containing multiple intermediate vertices or branch lines. In this case, the measurement and control system carefully analyzes each branch line to find a second connection route that meets the conditions. For example, if there is a route from A to a certain intermediate vertex C and then from C to B, but B has other connection lines pointing to other vertices, and the route from C to B is the only unbranched route for B (that is, B has no other connection lines directly pointing to other vertices after C), then this route from C to B is regarded as the second connection route, and C (although it is not the original second-order predecessor vertex A, it can be regarded as A's representative on a specific route in this case) is regarded as B's semi-dominant intelligent component (or more precisely, B's semi-dominant intelligent component about the specific route from A to B).

[0077] As an implementation mode, the method further includes: Step S3A: using X running status network vertices as original leading intelligent components of the second running status network vertex.

[0078] In the embodiment of the present application, step S3A is the starting point of the entire iterative process to determine the second running state network vertex target leading intelligent component. This step is performed by the measurement and control system, which embodies a conservative but comprehensive initial assumption without specific information guidance.

[0079] Specifically, step S3A requires the measurement and control system to temporarily regard all X operating state network vertices (including the first operating state network vertex and the remaining second operating state network vertices) in the network as the original dominant intelligent components of each second operating state network vertex. The "dominant intelligent component" here refers to the component that has an important influence or control effect on the second operating state network vertex during the data flow or instruction transmission process. However, in the initial stage of the iteration, the measurement and control system does not have enough information to determine which components actually play such a role, so it adopts a comprehensive strategy, which is to assume that all components may be potential dominant intelligent components.

[0080] Although this assumption is conservative, it provides a broad search space for subsequent iterative analysis. As the iteration proceeds, the measurement and control system gradually collects more information about the interaction between components and modifies and refines the original assumptions based on this information. Ultimately, the measurement and control system is able to identify the true target-dominant intelligent components of each second operating state network vertex, which play the most critical role in the data flow or instruction transmission process.

[0081] For example, suppose that in a power system containing five switch cabinet intelligent components (A, B, C, D, E), component A is determined as the first operating state network vertex, and components B, C, D, and E are analyzed as the second operating state network vertices. In step S3A, the measurement and control system temporarily regards the five components A, B, C, D, and E as the original dominant intelligent components of each second operating state network vertex. For example, for component D, its original dominant intelligent component set includes the five components A, B, C, D, and E. However, in the actual data flow or instruction transmission process, only some components may have an important impact on D. Therefore, in the subsequent iteration process, the measurement and control system gradually excludes those components with less impact and finally determines the true target dominant intelligent component of D.

[0082] Step S320', obtain the first-order predecessor vertex of the second operating status network vertex, and use the semi-dominant intelligent component of the first-order predecessor vertex of the second operating status network vertex and the second operating status network vertex as the target dominant intelligent component of the second operating status network vertex, which may specifically include: Step S320'1: In the sth dominant intelligent component acquisition link, obtain e first-order predecessor vertices of the second operating status network vertex in the operating status directional relationship network; s and e are both natural numbers greater than 0.

[0083] In the embodiment of the present application, step S320'1 is an important step in the process of iteratively determining the second operation state network vertex target leading intelligent component. This step is performed by the measurement and control system to collect key information from the operation state directional relationship network and provide basic data for subsequent analysis.

[0084] Specifically, step S320'1 occurs in the sth dominant intelligent component acquisition link, where s is a natural number greater than 0, representing the number of iterations. In this step, the goal of the measurement and control system is to find all the first-order predecessor vertices for the second operating state network vertex currently being analyzed. The so-called first-order predecessor vertices refer to those vertices that directly point to the current analysis vertex during data flow or instruction transmission, and they are in the direct upstream position of the current analysis vertex in the network structure.

[0085] To accomplish this task, the measurement and control system walks the operating state directed relationship network and checks all incoming edges (i.e., connecting lines pointing to the vertex) of the current analysis vertex. For each incoming edge, the measurement and control system determines its starting point, which is a first-order predecessor vertex. Through this process, the measurement and control system collects all first-order predecessor vertices of the current analysis vertex and records their number e, where e is also a natural number greater than 0, representing the total number of first-order predecessor vertices. For example, suppose that in a power system containing multiple switchgear intelligent components, the measurement and control system is analyzing the target dominant intelligent component of component D (a second operating state network vertex). During the sth iteration, the measurement and control system checks the operating state directed relationship network and finds all vertices that directly point to D. Assuming that components B and C both point directly to D through connecting lines, then B and C are the two first-order predecessor vertices of D, and e=2 at this time. The measurement and control system records the information of B and C so that it can use this information in subsequent steps to determine the target dominant intelligent component of D.

[0086] Through the execution of step S320'1, the measurement and control system lays a solid foundation for subsequent iterative analysis. It ensures that the measurement and control system can accurately obtain all the direct upstream vertex information of the current analysis vertex in each iteration, which is crucial for understanding the interaction relationship between components, identifying key components, and formulating fault response strategies.

[0087] Step S320'2: Obtain the semi-dominant intelligent components corresponding to the e first-order predecessor vertices of the second operating status network vertex, and use the common part of the semi-dominant intelligent components corresponding to the e first-order predecessor vertices and the second operating status network vertex as the sth iterative dominant intelligent component of the second operating status network vertex.

[0088] In the embodiment of the present application, step S320'2 is a core step in the process of iteratively determining the target dominant intelligent component of the second running state network vertex. This step is performed by the measurement and control system, and aims to gradually refine and determine the iterative dominant intelligent component of the current analysis vertex by analyzing the semi-dominant intelligent component of the first-order predecessor vertex.

[0089] Specifically, in step S320'1, the measurement and control system has obtained e first-order predecessor vertices of the second operating state network vertex currently analyzed. Next, in step S320'2, the measurement and control system searches for the corresponding semi-dominant intelligent component for each first-order predecessor vertex. Semi-dominant intelligent component is a relatively complex concept. It usually refers to an upstream vertex or a set of vertices in the network structure that have an important influence on a vertex but do not directly dominate the vertex. In practical applications, the determination of semi-dominant intelligent components may need to rely on specific algorithms or rules. These algorithms or rules will take into account multiple factors such as the connectivity, importance, and data transmission routes of the vertices.

[0090] After obtaining the semi-dominant intelligent components of all first-order predecessor vertices, the measurement and control system further analyzes the common parts of these semi-dominant intelligent components, that is, finds the intersection between them. The common part represents the upstream vertex or vertex set that is recognized by all first-order predecessor vertices and has an important influence on the current analysis vertex. Finally, the measurement and control system uses this intersection together with the second operating state network vertex currently being analyzed as the sth iteration dominant intelligent component of the vertex.

[0091] For example, suppose the measurement and control system is analyzing the iterative dominant intelligent component of component D (a second operating state network vertex), and has determined D's two first-order predecessor vertices B and C. When searching for the semi-dominant intelligent components of B and C, suppose the measurement and control system finds that the semi-dominant intelligent component of B is component A, and the semi-dominant intelligent component of C is also component A (here, for simplicity, it is assumed that A is the only common upstream vertex of B and C). At this time, the measurement and control system believes that A is the intersection of the semi-dominant intelligent components of B and C. Therefore, in the sth iteration, the measurement and control system uses {A, D} as the iterative dominant intelligent component of component D.

[0092] By executing step S320'2, the measurement and control system can gradually narrow the search scope of the target leading intelligent component and improve the accuracy and efficiency of the analysis, laying the foundation for the subsequent iterative process, so that the measurement and control system can more accurately identify key components and formulate corresponding fault response strategies.

[0093] Step S320'3: If the s-th iteration dominant intelligent component of the second operating status network vertex is the same as the r-th iteration dominant intelligent component of the second operating status network vertex, then the s-th iteration dominant intelligent component of the second operating status network vertex is used as the target dominant intelligent component of the second operating status network vertex; if s is the default value, the r-th iteration dominant intelligent component of the second operating status network vertex is the original dominant intelligent component of the second operating status network vertex, where r=s-1.

[0094] In the embodiment of the present application, step S320'3 is performed by the measurement and control system, which is responsible for determining whether the iteration process has converged and determining the final target dominant intelligent component accordingly. Specifically, after each iteration, the measurement and control system obtains the sth iteration dominant intelligent component of the second operating state network vertex currently analyzed. At this time, the measurement and control system compares this iteration result with the previous iteration result to determine whether a stable state has been reached. If the sth iteration dominant intelligent component is exactly the same as the iteration dominant intelligent component obtained in the previous iteration (i.e., the rth iteration, where r=s-1), then the measurement and control system can consider that the iteration process has converged, that is, further iteration will not change the result. In this case, the measurement and control system uses the sth iteration dominant intelligent component as the final target dominant intelligent component for subsequent fault diagnosis and protection strategy formulation. However, if the current iteration is the first iteration (i.e., s is the default value and there is no previous iteration result for comparison), then the measurement and control system compares the sth iteration dominant intelligent component with the initial set original dominant intelligent component. In step S3A, the measurement and control system has used all X operating state network vertices in the network as the original dominant intelligent components of each second operating state network vertex. Therefore, after the first iteration, if the sth iteration dominant intelligent component is different from the original dominant intelligent component, the measurement and control system continues to the next iteration; if they are the same, it may mean that the network structure is relatively simple, or the second operating state network vertex currently analyzed is directly or indirectly associated with all other vertices, making the original hypothesis directly valid. But usually, the result after the first iteration will be different from the original dominant intelligent component, and further iteration and refinement are required. For example, suppose that the measurement and control system is analyzing the target dominant intelligent component of component D and has completed multiple iterations. After the sth iteration, the measurement and control system finds that the iteration dominant intelligent component of component D is {A, D}, and the iteration dominant intelligent component obtained in the s-1th iteration is also {A, D}. Since the results of the two iterations are the same, the measurement and control system determines that the iteration process has converged and takes {A, D} as the final target dominant intelligent component of component D. This means that in the process of data flow or instruction transmission, component A has an important influence on component D, and this influence has been confirmed in multiple iteration analyses.

[0095] By executing step S320'3, the measurement and control system can ensure timely stop during the iteration process, avoid unnecessary waste of computing resources, and accurately determine the target leading intelligent component of each second operating state network vertex. This step provides reliable basic data support for subsequent fault diagnosis and protection strategy formulation.

[0096] As an implementation mode, the number of vertices of the second operating state network is f, f≥1; the method further includes: step S3I: taking the first operating state network vertex as the starting vertex, performing a post-order mirror walk on the operating state directional relationship network to obtain a vertex group chain corresponding to X operating state network vertices.

[0097] In the embodiment of the present application, step S3I provides an orderly data basis for the subsequent determination of the target leading intelligent component of each second operating state network vertex. In this step, the measurement and control system conducts an in-depth analysis of the operating state directional relationship network through a specific wandering method-post-order mirror wandering. Specifically, the core position of the first operating state network vertex in the network is first clarified. This vertex is directly or indirectly connected to all other vertices as the starting point or center of the entire network, so it is selected as the starting vertex during the wandering process. Next, the measurement and control system starts the post-order mirror wandering mechanism. This algorithm mechanism is different from the traditional pre-order wandering, in-order wandering and post-order wandering. It wanders in the direction from the "end" to the "source", that is, first visits the end vertex, and then gradually traces back to the starting vertex. In the post-order mirror wandering process, the measurement and control system starts from the first operating state network vertex along the connecting line, but does not immediately visit its directly connected vertices. Instead, it will first explore the downstream vertices of these directly connected vertices (that is, vertices farther away from the first operating state network vertex) until it reaches the "end" of the network. Then, it will start to backtrack, visit and record the vertices along the way according to a certain rule (such as right first then left or left first then right, depending on the structure of the network and the implementation of the walking algorithm). This process will continue until the measurement and control system returns to the first running state network vertex, at which time it has walked all the vertices in the network and recorded them in reverse order, forming an ordered vertex group chain.

[0098] For example, suppose that in a power system, the operating state directional relationship network consists of five switch cabinet intelligent components A, B, C, D, and E, where A is the first operating state network vertex. When the measurement and control system executes step S3I, it will take A as the starting vertex for post-order mirror walking. Assuming that the order and result of the walking depend on the connection relationship of the vertices and the specific implementation of the walking algorithm, in any case, the measurement and control system will eventually obtain an ordered vertex group chain, such as {D, C, E, B, A} (please note that this is just an example and the actual result may be different). In this group chain, D, C, and E may be end vertices or vertices close to the end vertices in the network, which are first visited and recorded during the walking process; then B, which may be directly connected to A and located upstream of D, C, and E; and finally A, as the starting point and end point of the walking. Through the execution of step S3I, not only an ordered vertex group chain is constructed, but also important data support is provided for subsequent steps. This vertex group chain reflects the hierarchical relationship and relative position of the vertices in the operation status directional relationship network, so that the measurement and control system can process each second operation status network vertex one by one in a certain order, so as to more accurately determine their target dominant intelligent components.

[0099] Step S320', obtaining the first-order predecessor vertex of the second operating status network vertex, and using the semi-dominant intelligent component of the first-order predecessor vertex of the second operating status network vertex and the second operating status network vertex as the target dominant intelligent component of the second operating status network vertex, may include: Step S320'I: obtaining the first-order predecessor vertex of the c-th second operating status network vertex in the vertex group chain, and using the semi-dominant intelligent component of the first-order predecessor vertex of the c-th second operating status network vertex and the c-th second operating status network vertex as the target dominant intelligent component of the c-th second operating status network vertex; wherein, 1≤c≤f.

[0100] In the embodiment of the present application, step S320'I accurately constructs the target dominant intelligent component set of each vertex by deeply analyzing the first-order predecessor vertex and its semi-dominant intelligent component of each second operating state network vertex in the vertex group chain. Specifically, the measurement and control system obtains the cth second operating state network vertex from the vertex group chain (where c is an integer from 1 to f, and f is the total number of second operating state network vertices). Then, the measurement and control system checks all the incoming edges of this vertex (i.e., the connecting lines pointing to the vertex) and finds all the vertices that directly point to it. These vertices are the first-order predecessor vertices of the vertex.

[0101] Next, for each first-order predecessor vertex, the measurement and control system performs an additional step to determine its semi-dominant intelligent component. Semi-dominant intelligent component is a relatively complex concept, which usually refers to an upstream vertex or vertex set that has an important influence on a vertex in the network structure but does not directly dominate the vertex. The measurement and control system calculates the semi-dominant intelligent component of each first-order predecessor vertex according to specific algorithms or rules (these algorithms or rules may take into account multiple factors such as the connectivity, importance, and data transmission route of the vertex). Once the semi-dominant intelligent components of all first-order predecessor vertices are obtained, the measurement and control system further analyzes the intersection of these components. However, in practical applications, due to the complexity of the network structure, it may not always be feasible or necessary to directly calculate the intersection. Therefore, the measurement and control system can adopt a more flexible strategy, such as taking the semi-dominant intelligent component of each first-order predecessor vertex together with the second operating state network vertex itself as the candidate target dominant intelligent component of the vertex. Then, the measurement and control system can select the final target dominant intelligent component from these candidate components according to certain priority rules (such as the importance ranking of components, the position of components in the network, etc.).

[0102] But here, in order to simplify the explanation, it is assumed that the measurement and control system directly takes the set of semi-dominant intelligent components of all first-order predecessor vertices (if there is an intersection between them, the intersection is considered; if there is no intersection, the union is considered) together with the second operating state network vertex itself as the target dominant intelligent component of the vertex. For example, assume that in the power system, the vertex group chain is {D, C, E, B, A}, where A is the first operating state network vertex, and D, C, E, and B are the second operating state network vertices. The measurement and control system now processes the second vertex C in the vertex group chain (that is, c=2). The measurement and control system first finds all the first-order predecessor vertices of C (assuming that they are B and another vertex F, but please note that F may not exist in the actual scenario and is only introduced here for explanation). Then, the measurement and control system determines the semi-dominant intelligent components of B and F respectively (assuming that the semi-dominant intelligent component of B is A, and the semi-dominant intelligent component of F is also A or another component, but here only A is considered as the intersection). Finally, the measurement and control system uses {A, C} (i.e., B's semi-dominant intelligent component A and vertex C itself) as the target dominant intelligent component of vertex C. It should be noted that the intersection and union operations in the above examples may need to be adjusted according to specific circumstances in actual applications. In addition, if a first-order predecessor vertex does not have a clear semi-dominant intelligent component (for example, it is an isolated vertex in the network or the connection relationship with other vertices is unclear), the measurement and control system may need to adopt special processing strategies to deal with this situation.

[0103] By executing step S320'I, the measurement and control system can gradually construct a target leading intelligent component set for each second operation state network vertex, providing an important basis for subsequent key intelligent component identification and fault diagnosis.

[0104] Step S320'II: If the cth second operating status network vertex is not the last operating status network vertex in the vertex group chain, then obtain the dth second operating status network vertex in the vertex group chain, and obtain the target dominant intelligent component of the dth second operating status network vertex, where d=c+1.

[0105] In the embodiment of the present application, step S320'II is a loop control step in the process of iteratively determining the second operating state network vertex target leading intelligent component. It ensures that the measurement and control system can process each second operating state network vertex one by one according to the order in the vertex group chain until all vertices are processed.

[0106] Specifically, when executing step S320'I, the measurement and control system has determined the target leading intelligent component of the c-th second running state network vertex in the vertex group chain. Then, step S320'II checks whether this vertex is the last vertex in the vertex group chain. If not (that is, there are more vertices to be processed), the measurement and control system performs a series of operations to continue processing the next vertex.

[0107] First, the measurement and control system calculates the index d of the next vertex to be processed, where d is equal to c plus 1 (d=c+1). This operation actually moves forward one position in the vertex group chain so that the measurement and control system can access and process the next vertex.

[0108] Next, the measurement and control system uses the same method as step S320'I to determine the target dominant intelligent component of the d-th second operating state network vertex. This means that the measurement and control system once again searches for all first-order predecessor vertices of the vertex, determines the semi-dominant intelligent components of these predecessor vertices, and constructs a set of target dominant intelligent components for the vertex according to certain rules (such as intersection, union, or priority sorting). This process will be repeated until the measurement and control system has processed the last second operating state network vertex in the vertex group chain. In each loop, the value of c will increase until it is equal to the total number of vertices f in the vertex group chain, at which time the measurement and control system stops iterating.

[0109] For example, suppose that in the power system, the vertex group chain is {D, C, E, B, A}, where A is the first operating state network vertex, and D, C, E, and B are the second operating state network vertices. The measurement and control system has determined the target leading intelligent component of vertex D (i.e., the first vertex, c=1) and is ready to continue processing the next vertex.

[0110] In step S320'II, the measurement and control system calculates d=c+1=2, that is, the next vertex to be processed is C. Then, the measurement and control system determines the target dominant intelligent component of vertex C according to the method of step S320'I. This process will be repeated until the measurement and control system has processed vertex B (that is, when c=4 and d=5, but note that A is the first running state network vertex and is not within the scope of this iteration), at which time c is equal to the total number of vertices in the vertex group chain minus one (because A does not participate in this iteration), and the measurement and control system stops iterating.

[0111] By executing step S320'II, the measurement and control system can ensure that each second operating state network vertex is processed in an orderly manner, and gradually construct their respective target leading intelligent component sets, which provides an important data basis for subsequent key intelligent component identification and fault diagnosis.

[0112] Step S320'III: if the c-th second operating status network vertex is the last operating status network vertex in the vertex group chain, then the step of using the switch cabinet smart component corresponding to the operating status network vertex with the largest number of target dominant smart components corresponding to the X operating status network vertices as the key smart component among the X switch cabinet smart components is executed.

[0113] In the embodiment of the present application, step S320'III marks the end of the process of iteratively determining the second running state network vertex target leading intelligent component, and triggers the subsequent step of determining the key intelligent component. The execution subject of this step is the measurement and control system, which is responsible for identifying the key vertices in the network based on the wandering results of the vertex group chain.

[0114] Specifically, when the measurement and control system processes the last second operating state network vertex in the vertex group chain (i.e., the cth vertex, where c is equal to the total number of second operating state network vertices in the vertex group chain f), the condition of step S320'III is met. At this time, the measurement and control system suspends further processing of the current vertex and performs a key task: counting and comparing the number of times all operating state network vertices (including the first operating state network vertex and the second operating state network vertex, a total of X) were determined as target dominant intelligent components in the previous iteration process.

[0115] This statistical process is very important because it helps the measurement and control system identify vertices that play a key role in the network. These vertices are key because they frequently appear in multiple data flows or instruction delivery routes and have an important impact on maintaining the overall operation of the network. By comparing the number of times each vertex appears as a target dominant intelligent component, the measurement and control system can find the vertex with the most appearances, and the switch cabinet intelligent component corresponding to this vertex is the key intelligent component.

[0116] For example, suppose that in the power system, the vertex group chain is {D, C, E, B}, which implicitly assumes that there is a first operating state network vertex A (although A does not directly participate in this iterative process, the determination of its target dominant intelligent component may be completed in other steps). The measurement and control system has determined the target dominant intelligent components of the four second operating state network vertices D, C, E, and B one by one. Now, the measurement and control system executes step S320'III, and it statistically finds that vertex A appears in the target dominant intelligent components of multiple second operating state network vertices (because A may be the semi-dominant intelligent component of the first-order predecessor vertex of these vertices), and it appears the most times. Therefore, the measurement and control system determines that the switch cabinet intelligent component corresponding to A is a key intelligent component.

[0117] It should be noted that in practical applications, the determination of key intelligent components may not only be based on the statistics of the number of occurrences. The measurement and control system may also consider other factors, such as the connectivity of the vertex, the importance score, the historical fault record, etc., to comprehensively evaluate the criticality of each vertex. However, in the context of this embodiment, the statistics of the number of occurrences are the main basis for determining the key intelligent components.

[0118] Through the execution of step S320'III, the measurement and control system not only completes the iterative determination process of the target leading intelligent component of the second operating state network vertex, but also successfully identifies the key intelligent components in the network. This provides an important information basis for subsequent fault diagnosis and comprehensive protection measurement and control, and helps to quickly locate the source of the fault and take effective countermeasures.

[0119] As an implementation method, the first fault information includes a faulty intelligent component; step S400, performing fault diagnosis on the key intelligent component information included in the key intelligent component to determine the first fault information of the power system operation link, including: step S410: obtaining the key intelligent component information in the key intelligent component, the key intelligent component information including the operation exchange data corresponding to X switch cabinet intelligent components respectively.

[0120] In step S410 of the embodiment of the present application, the measurement and control system focuses on extracting key intelligent component information from previously determined key intelligent components, which is crucial for subsequent fault diagnosis.

[0121] Specifically, the measurement and control system locks on key intelligent components, which are identified in the previous analysis process as occupying an important position in the network structure and playing a key role in maintaining the stable operation of the system. Once the key intelligent components are identified, the measurement and control system will begin to collect key intelligent component information from these components. The core component of this information is the operation exchange data generated by X switch cabinet intelligent components (including the key intelligent components themselves and other components that they directly or indirectly interact with) during operation.

[0122] Operation exchange data is the carrier of communication between intelligent components of switch cabinets. It records various types of information such as command transmission, status report, measurement parameters, etc. between components. These data are of great significance for understanding the working status of components, evaluating their performance, and diagnosing potential faults. In step S410, the measurement and control system comprehensively collects these operation exchange data, including but not limited to key parameters and event records such as current, voltage, temperature, switch status, communication log, etc.

[0123] For example, suppose that in a power system containing multiple switch cabinet intelligent components, the measurement and control system determines that component A is a key intelligent component through a series of complex analysis processes. In step S410, the measurement and control system immediately turns to component A and extracts key intelligent component information from its internal storage or real-time transmission data stream. At the same time, since component A has an interactive relationship with other components (such as B, C, D, etc.) in the network, the measurement and control system will also collect the operation exchange data between these components and A. These data may include the tripping command sent by A to B, the status information reported by B to A, the current and voltage changes related to A monitored by C and D, etc.

[0124] By executing step S410, the measurement and control system not only obtains the operating data of the key intelligent component itself, but also understands its interaction with surrounding components. This valuable information provides a solid foundation for subsequent fault diagnosis, allowing the measurement and control system to more accurately identify the source of the fault and formulate corresponding countermeasures.

[0125] Step S420: Based on the operation exchange data respectively corresponding to the X switch cabinet smart components, create smart component operation status data respectively corresponding to the X switch cabinet smart components.

[0126] In the embodiment of the present application, step S420 is a key link in data processing and analysis, which is directly related to the accuracy and efficiency of fault diagnosis. In this step, the measurement and control system further processes the operation exchange data of the X switch cabinet smart components collected in step S410 to create the smart component operation status data corresponding to each component.

[0127] Specifically, the measurement and control system conducts in-depth analysis of the collected operation exchange data. These data contain rich information, such as current, voltage, temperature, switch status, communication log, etc., which directly reflect the real-time working status of the switch cabinet intelligent components. However, these data are often raw and unprocessed, and it is difficult to use them directly for fault diagnosis. Therefore, the measurement and control system uses a series of data processing technologies, such as data cleaning, conversion, aggregation, etc., to extract valuable information for fault diagnosis. Through in-depth analysis and processing of the operation exchange data, the measurement and control system can create a complete set of intelligent component operation status data for each switch cabinet intelligent component. These data not only contain the real-time operation status information of the component, but may also include historical operation records, performance evaluation results, fault warning information, etc. They provide a comprehensive and quantifiable basis for subsequent fault diagnosis.

[0128] For example, suppose that the measurement and control system is diagnosing a fault in an electric power system that includes multiple switch cabinet intelligent components. In step S410, the measurement and control system has collected the operation exchange data of each component. Now, in step S420, the measurement and control system processes these data in depth. Taking component A as an example, the measurement and control system first cleans up the noise and abnormal values ​​in the data, and then converts and aggregates the remaining current and voltage data to calculate their effective values ​​and fluctuation ranges. At the same time, the measurement and control system also monitors the temperature change trend of component A and tracks the change process of its switch state. Finally, the measurement and control system creates a set of intelligent component operation status data for component A, which contains key parameter information such as real-time current, voltage, temperature information and switch status records of component A. These data will serve as an important basis for subsequent fault diagnosis.

[0129] Step S430: The switch cabinet smart component with abnormal smart component operation status data is regarded as a faulty smart component.

[0130] In the embodiment of the present application, step S430 is a key step to determine the fault source and implement targeted maintenance measures. In this step, the measurement and control system plays a core role. It accurately identifies the abnormal switch cabinet smart components by comparing the operating status data of the smart components with the preset standards or thresholds, and marks them as faulty smart components.

[0131] Specifically, the measurement and control system comprehensively evaluates the operating status of each switch cabinet smart component based on the smart component operating status data created in step S420. These operating status data cover multiple key parameters such as current, voltage, temperature, and switch status, which together constitute an important indicator system for evaluating the health status of components. Next, the measurement and control system compares and analyzes these real-time operating status data with the preset standard range or threshold. These preset standards are usually formulated based on factors such as the normal working characteristics of the components, historical operating data, and industry specifications, and are intended to accurately reflect the normal performance of the components under different working conditions.

[0132] During the comparative analysis process, if the measurement and control system finds that the operating status data of a switch cabinet intelligent component exceeds the preset standard range or triggers a specific fault warning condition, then the component will be preliminarily judged to be abnormal. In order to further confirm the existence and nature of the fault, the measurement and control system can combine other diagnostic methods (such as expert systems, neural networks, etc.) for comprehensive analysis to improve the accuracy and reliability of fault diagnosis. Once the fault is confirmed, the measurement and control system immediately marks the switch cabinet intelligent component as a faulty intelligent component and records the relevant fault information (such as fault type, occurrence time, impact range, etc.). This information is of great significance for subsequent fault handling, system recovery, and prevention of similar faults from happening again.

[0133] For example, suppose that in an electric power system, the measurement and control system is performing real-time monitoring and fault diagnosis on a group of switch cabinet intelligent components. In step S420, the measurement and control system has created detailed operating status data for these components. Now, in step S430, the measurement and control system begins to compare and analyze these data. Taking component A as an example, if the measurement and control system finds that its temperature data continues to rise and exceeds the preset safety threshold, and the current and voltage data also show abnormal fluctuations, then component A may be preliminarily determined to be faulty. To further confirm this, the measurement and control system can call the relevant rules in the expert system for reasoning analysis, and finally determine that component A is a faulty intelligent component and record its fault information. Subsequently, the operation and maintenance personnel can take corresponding maintenance measures based on these fault information to ensure the safe and stable operation of the power system.

[0134] As an implementation mode, the method further includes: Step S500: disconnecting the faulty smart component to maintain the operation state of the power system.

[0135] In the embodiment of the present application, step S500 is intended to isolate the faulty intelligent component from the power system by physical or logical means to prevent the fault from spreading further, while trying to maintain the rest of the power system in normal operation. Specifically, when the measurement and control system determines that a switch cabinet intelligent component is a faulty intelligent component through step S400, it will immediately evaluate the impact of the fault on the overall operation of the power system. If it is determined that the fault may trigger a chain reaction, resulting in a larger range of power supply interruptions or equipment damage, the measurement and control system decisively executes step S500.

[0136] During the execution process, the measurement and control system first sends a disconnection command to the faulty intelligent component. This command may be sent through a remote communication interface or by directly controlling the relay or circuit breaker inside the switch cabinet. Regardless of the method used, the purpose is to quickly cut off the electrical connection between the faulty intelligent component and the rest of the power system and isolate it from the network. At the same time, the measurement and control system also monitors the overall operating status of the power system to ensure that the rest of the system can maintain stable operation during the disconnection of the faulty intelligent component. This includes monitoring changes in key parameters such as current, voltage, and power factor, as well as checking whether the working status of other switch cabinet intelligent components is normal.

[0137] Or; as an implementation mode, the method further includes: Step S600: obtaining a component connection structure adopted during the operation of the power system.

[0138] In the embodiment of the present application, step S600 aims to fully understand and grasp the connection relationship between the components in the power system, and provide necessary basic data for subsequent diagnosis and response measures.

[0139] Specifically, when the measurement and control system identifies a faulty smart component through step S400 and may decide to take further action (such as disconnecting the faulty component or deeply analyzing the impact of the fault), it will first execute step S600 to obtain the component connection structure of the power system. This connection structure not only includes the physical connection information between the smart components of the switch cabinet (such as cable direction, wiring terminals, etc.), but also may include the logical connection relationship between them (such as data communication protocol, instruction transmission route, etc.).

[0140] In order to obtain this information, the measurement and control system can use a variety of data sources and technical means. For example, it can obtain the physical layout and connection information of components by accessing the digital model of the power system (such as CAD drawings, BIM models, etc.); it can also infer the logical relationship and interaction mode between components by analyzing the real-time operation data of the power system (such as current, voltage, switch status, etc.). In addition, the measurement and control system may also use specialized software tools or algorithms to automatically generate and update component connection structure diagrams so as to keep abreast of the latest status of the power system.

[0141] For example, suppose that in a complex power system, the measurement and control system determines through step S400 that a key switch cabinet intelligent component has failed. In order to evaluate the impact of the failure on the entire system, the measurement and control system executes step S600 to obtain the component connection structure of the system. In this process, the measurement and control system first accesses the digital model library of the power system and finds the local or global model containing the key component. Through model analysis, the measurement and control system clearly sees the physical connection relationship between the key component and other components, including which cables are connected to which terminals, and how these connections constitute the route for power transmission and distribution. At the same time, the measurement and control system also obtains the current operating status information of the system through the real-time operation data monitoring platform, and further confirms the logical relationship and interaction mode between the components. Based on this information, the measurement and control system can construct a detailed component connection structure diagram, which provides strong support for subsequent diagnosis and response measures.

[0142] Step S700: Obtain the first component line corresponding to the faulty smart component under the component connection structure.

[0143] In the embodiment of the present application, step S700 is an important part of the measurement and control system in deeply analyzing the scope of fault impact. After obtaining the component connection structure of the power system in step S600, the measurement and control system further focuses on the faulty intelligent component, determines its specific location in the entire connection structure, and identifies the first component line directly connected to the component.

[0144] Specifically, the measurement and control system carefully analyzes the connection relationship between the faulty intelligent component and other components based on the component connection structure diagram constructed in step S600. These connection relationships may include physical connections (such as cables, busbars, etc.) and logical connections (such as data communication links, control instruction transmission routes, etc.). The measurement and control system pays special attention to those parts that are directly connected to the faulty intelligent component, because they are most likely to be affected by the fault, or they are themselves the key routes for the fault to propagate.

[0145] After identifying all the connection points directly connected to the faulty smart component, the measurement and control system further determines the lines formed by these connection points, namely the first component lines. These lines are channels for power or data to be transmitted between the faulty smart component and other components, and their status and performance are directly related to the scope and degree of the fault impact. For example, assume that in a power system containing multiple switch cabinet smart components, the measurement and control system determines that component A is a faulty smart component through step S400, and obtains the component connection structure of the system in step S600. Now, the measurement and control system executes step S700 to obtain the first component line corresponding to component A. By viewing the connection structure diagram, the measurement and control system finds that component A is connected to component C through cable B, and also exchanges information with component E through data communication link D. These two connection routes (cable B and data communication link D) are the first component lines corresponding to component A. The measurement and control system pays special attention to the status and performance of these two lines because they may be affected by the fault of component A or are propagating fault signals to other components. To further verify this, the measurement and control system can start a real-time monitoring and analysis program for these two lines to timely discover and deal with potential fault risks.

[0146] Step S800: obtaining the involved line corresponding to the first component line in the power system operation link, performing fault diagnosis on the first component line in the process of processing the involved line, and determining the second fault information of the power system operation process.

[0147] In the embodiment of the present application, step S800 is a key step for the measurement and control system to thoroughly investigate the scope of the fault and ensure the overall safety of the power system. After determining the faulty intelligent component and its corresponding first component line, the measurement and control system further analyzes other lines that may be involved in the operation of the power system, i.e., involved lines, and performs fault diagnosis on these lines to determine whether there is a second fault information caused by the original fault.

[0148] Specifically, the measurement and control system first identifies other lines that the first component line may interact with during power transmission, distribution or control based on the operating logic of the power system and the component connection structure. These lines may be located in different switch cabinets, different voltage levels or different functional areas, but they all have direct or indirect electrical or data connections with the first component line. Since the fault of the faulty intelligent component may have propagated to these involved lines through the first component line, the measurement and control system performs comprehensive fault diagnosis on them. During the diagnosis process, the measurement and control system uses a variety of technical means and algorithms to analyze the state parameters, historical data and interaction records of the involved lines with other components. These technical means may include real-time data monitoring, signal processing technology, pattern recognition algorithms, etc. Through analysis, the measurement and control system can identify abnormal signals, performance degradation or potential fault risks that may exist in the involved lines. Once these problems are found, the measurement and control system immediately records and reports them as second fault information so that the operation and maintenance personnel can take timely measures to deal with them.

[0149] For example, suppose that in a complex power system, the measurement and control system determines the faulty intelligent component A and its corresponding first component line (including cable B and data communication link D) through steps S400 to S700. Now, the measurement and control system executes step S800 to analyze other lines that these lines may involve and perform fault diagnosis. By deeply analyzing the operation logic and component connection structure of the power system, the measurement and control system finds that cable B not only connects components A and C, but also connects to multiple other components through bus E. At the same time, although data communication link D is mainly used for information exchange, the control instructions it transmits can affect the automatic protection equipment related to component E. Therefore, the measurement and control system regards bus E and the lines connected to the automatic protection equipment related to component E as involved lines. Next, the measurement and control system uses real-time data monitoring and pattern recognition algorithms to perform comprehensive fault diagnosis on these involved lines. After analysis, the measurement and control system finds that there is abnormal fluctuation in the current on bus E, and this fluctuation is highly correlated with the fault time of component A. At the same time, the automatic protection equipment related to component E also responds to the abnormal signal, but fails to isolate the fault in time. Based on this information, the measurement and control system identified the second fault information: bus E had a potential short circuit risk, and the automated protection equipment might have improper configuration or delayed response. Based on this information, the operation and maintenance personnel quickly developed a targeted maintenance plan to ensure the comprehensive, safe and stable operation of the power system.

[0150] An embodiment of the present application provides a measurement and control system, including a memory and a processor, wherein the memory stores a computer program that can be executed on the processor, and when the processor executes the program, some or all of the steps in the above method are implemented. Figure 2 A schematic diagram of the hardware entity of the measurement and control system provided in the embodiment of the present application is shown in FIG. Figure 2 As shown, the hardware entity of the measurement and control system 1000 includes: a processor 1001 and a memory 1002, wherein the memory 1002 stores a computer program that can be run on the processor 1001, and the processor 1001 implements the steps in the method of any of the above embodiments when executing the program.

[0151] The above is only an implementation method of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application.

Claims

1. A switch cabinet comprehensive protection measurement and control method based on fault diagnosis, characterized in that: The method comprises: Acquire a data exchange sequence of X switch cabinet intelligent components in the operation link of the power system, create X operation status network vertices with the X switch cabinet intelligent components, and create directional connection lines between the X operation status network vertices with the data exchange sequence to obtain an operation status directional relationship network; wherein X≥1; Taking the operating state network vertex that is fully connected with other switch cabinet intelligent components in the operating state directional relationship network as the first operating state network vertex; The target leading intelligent components corresponding to the X operating state network vertices are obtained in the operating state directional relationship network, and the switch cabinet intelligent components corresponding to the operating state network vertices with the largest number among the target leading intelligent components corresponding to the X operating state network vertices are used as the key intelligent components among the X switch cabinet intelligent components; the target leading intelligent component corresponding to any operating state network vertex represents the intelligent component included in the connection route from the first operating state network vertex to the operating state network vertex; Performing fault diagnosis on key intelligent component information included in the key intelligent component to determine first fault information of the power system operation link; The first fault information includes a faulty intelligent component; the fault diagnosis of the key intelligent component information included in the key intelligent component to determine the first fault information of the power system operation link includes: Acquire key intelligent component information in the key intelligent component, wherein the key intelligent component information includes operation exchange data corresponding to each of the X switch cabinet intelligent components; Based on the operation exchange data respectively corresponding to the X switch cabinet intelligent components, create the intelligent component operation status data respectively corresponding to the X switch cabinet intelligent components; The switch cabinet intelligent component with abnormal intelligent component operation status data is regarded as a faulty intelligent component.

2. The method according to claim 1, characterized in that: The step of taking the operating state network vertex that is fully connected with other switch cabinet intelligent components in the operating state directional relationship network as the first operating state network vertex includes: In the running state directional relationship network, the X running state network vertices are respectively used as starting vertices, and a connection route of each running state network vertex in the running state directional relationship network is obtained by walking; If the connection routes obtained by the walking include the connection routes including the X running status network vertices, the corresponding running status network vertex is used as the first running status network vertex; If the connection routes obtained by the wandering do not include the connection routes including the X running state network vertices, then creating a fake intelligent component in the running state directional relationship network, and creating a fake connection line between the fake intelligent component and the running state directional relationship network, and using the fake intelligent component as the first running state network vertex; or; The step of taking the operating state network vertex that is fully connected with other switch cabinet intelligent components in the operating state directional relationship network as the first operating state network vertex includes: Obtaining the u-th running status network vertex in the running status directional relationship network, taking the u-th running status network vertex as the starting vertex, performing an exhaustive branch search on the running status directional relationship network, and obtaining the u-th original data exchange hierarchical graph; wherein 1≤u≤X; the starting vertex of the u-th original data exchange hierarchical graph is the u-th running status network vertex; If there is an operating status network vertex among the X operating status network vertices that is not included in the u-th original data exchange hierarchical graph, then the v-th operating status network vertex is used as the starting vertex, and an exhaustive branch search is performed on the operating status directional relationship network to obtain the v-th original data exchange hierarchical graph, where v=u+1; If the u-th original data exchange hierarchical graph includes the X running status network vertices, the u-th running status network vertex is used as the first running status network vertex.

3. The method according to claim 1, characterized in that: The step of obtaining target-dominant intelligent components corresponding to the X running status network vertices in the running status directional relationship network includes: Obtaining Y connection routes g from the first operation status network vertex to the g-th operation status network vertex in the operation status directional relationship network, and obtaining connection vertices respectively included in the Y connection routes g; wherein 1≤g≤X, 1≤Y; Among the connection vertices respectively included in the Y connection routes g, the connection vertices common to the Y connection routes g are used as the target dominant intelligent components corresponding to the g-th running status network vertex.

4. The method according to claim 1, characterized in that: The step of obtaining target-dominant intelligent components corresponding to the X running status network vertices in the running status directional relationship network includes: Using the first running state network vertex as a target leading intelligent component of the first running state network vertex; The first-order predecessor vertex of the second operating state network vertex is obtained, and the semi-dominant intelligent component of the first-order predecessor vertex of the second operating state network vertex and the second operating state network vertex are used as the target dominant intelligent component of the second operating state network vertex; the second operating state network vertex is the operating state network vertex other than the first operating state network vertex among the X operating state network vertices.

5. The method according to claim 4, characterized in that The method further comprises: Acquire a second order predecessor vertex of the first order predecessor vertex in the running status directional relationship network, and acquire a first connection route including the first order predecessor vertex and the second order predecessor vertex in the running status directional relationship network; A second connection route is obtained in the first connection route, and a second-order predecessor vertex corresponding to the second connection route is used as a semi-dominant intelligent component of the first-order predecessor vertex; the second connection route represents that the first-order predecessor vertex is adjacent to the second-order predecessor vertex, and the first-order predecessor vertex does not have a branch line of a sequence predecessor vertex other than the second-order predecessor vertex.

6. The method according to claim 4, characterized in that The method further comprises: Using the X running state network vertices as original leading intelligent components of the second running state network vertex; The step of obtaining a first order predecessor vertex of a second operating state network vertex and using a semi-dominant intelligent component of the first order predecessor vertex of the second operating state network vertex and the second operating state network vertex as a target dominant intelligent component of the second operating state network vertex includes: In the sth leading intelligent component acquisition phase, e first-order predecessor vertices of the second operating state network vertex are acquired in the operating state directional relationship network; s and e are both natural numbers greater than 0; Obtaining the semi-dominant intelligent components corresponding to the e first-order predecessor vertices of the second operating state network vertex, and using the common part of the semi-dominant intelligent components corresponding to the e first-order predecessor vertices and the second operating state network vertex as the s-th iteration dominant intelligent component of the second operating state network vertex; If the s-th iteration dominant intelligent component of the second operating status network vertex is the same as the r-th iteration dominant intelligent component of the second operating status network vertex, then the s-th iteration dominant intelligent component of the second operating status network vertex is used as the target dominant intelligent component of the second operating status network vertex; if s is the default value, the r-th iteration dominant intelligent component of the second operating status network vertex is the original dominant intelligent component of the second operating status network vertex, where r=s-1.

7. The method according to claim 4, characterized in that The number of vertices of the second running state network is f, where f≥1; and the method further includes: Taking the first running state network vertex as the starting vertex, performing post-order mirror walking on the running state directional relationship network to obtain a vertex group chain corresponding to the X running state network vertices; The step of obtaining a first order predecessor vertex of a second operating state network vertex and using a semi-dominant intelligent component of the first order predecessor vertex of the second operating state network vertex and the second operating state network vertex as a target dominant intelligent component of the second operating state network vertex includes: Obtaining the first order predecessor vertex of the cth second operating state network vertex in the vertex group chain, and using the semi-dominant intelligent component of the first order predecessor vertex of the cth second operating state network vertex and the cth second operating state network vertex as the target dominant intelligent component of the cth second operating state network vertex; wherein 1≤c≤f; If the c-th second operating state network vertex is not the last operating state network vertex in the vertex group chain, then obtain the d-th second operating state network vertex in the vertex group chain, and obtain the target leading intelligent component of the d-th second operating state network vertex, where d=c+1; If the c-th second operating status network vertex is the last operating status network vertex in the vertex group chain, then the step of using the switch cabinet smart component corresponding to the operating status network vertex with the largest number of target dominant smart components corresponding to the X operating status network vertices as the key smart component among the X switch cabinet smart components is executed.

8. The method according to claim 1, characterized in that The method further comprises: Disconnecting the faulty intelligent component to keep the power system in operation; or; Acquire the component connection structure adopted during the operation of the power system, acquire the first component line corresponding to the faulty intelligent component under the component connection structure, acquire the involved line corresponding to the first component line in the operation link of the power system, perform fault diagnosis on the first component line in the process of processing the involved line, and determine the second fault information of the operation process of the power system.

9. A measurement and control system, comprising a memory and a processor, wherein the memory stores a computer program that can be run on the processor, characterized in that: When the processor executes the program, the steps in the method according to any one of claims 1 to 8 are implemented.

Citation Information

Patent Citations

  • Fault early warning method and device

    CN115086143A

  • Local power switching control subsystem

    US4663539A