A substation drone inspection path planning method and system

By constructing the substation environment model and equipment operation data, calculating the inspection priority, and combining with the image recognition model, the intelligent dynamic adjustment of the substation drone inspection path is realized, which solves the static nature and insufficient power of path planning in the existing technology, and improves the efficiency Inspection efficiency and coverage of important equipment.

CN118623893BActive Publication Date: 2024-10-15NANCHANG POWER SUPPLY BRANCH OF STATE GRID JIANGXI ELECTRIC POWER CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411089020.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-10-15
Estimated Expiration
2044-08-09

AI Technical Summary

Technical Problem

In the existing technology, the substation drone inspection path planning lacks the ability to dynamically adjust, and fails to fully consider the importance of equipment and inspection priority. As a result, some important equipment cannot be inspected with priority, and the drone flight time is limited by battery capacity. , there may be a problem of insufficient battery.

Method used

Build an environment model by collecting laser point cloud data, obtain equipment operation data, calculate equipment inspection priority, generate initial and real-time inspection paths, and monitor UAV power in real time to adjust inspection paths and tasks; combine with image recognition models to perform anomaly identification and adjustment Equipment weight and path planning adopt a combination of weight distribution layer, path recording layer and path planning layer to achieve intelligent dynamic path adjustment.

Benefits of technology

The intelligent dynamic adjustment capability of path planning is improved to ensure priority inspection of important equipment, effectively prevent the drone from running out of power, and improve the continuity and efficiency of inspection tasks.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118623893B_ABST
    Figure CN118623893B_ABST
Patent Text Reader

Abstract

The present invention discloses a substation UAV patrol path planning method and system, and relates to the field of patrol path planning. A substation UAV patrol path planning system includes: an environment construction module, a data acquisition module, an initial path planning module, a real-time path adjustment module, and a patrol feedback module. The present invention models the substation environment, generates a three-dimensional obstacle model with environmental obstacles and a two-dimensional patrol map with equipment locations, which facilitates dynamic adjustment of the patrol path; obtains initial weights and real-time weights through equipment performance information and real-time operation data, and calculates equipment patrol priority, thereby realizing sequential patrols of different equipment, and adjusting the initial weights through the feedback results of the number of patrols of the equipment in each patrol task, thereby improving the dynamic evaluation capability of equipment importance and failure probability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to patrol path planning, and in particular to a method and system for planning patrol paths of substation unmanned aerial vehicles. Background Art

[0002] As an important part of the power system, the safe and stable operation of the substation is crucial to the normal operation of the entire power grid. Traditional substation inspections are mainly carried out manually. There are a large number of equipment in the substation, and manual inspections require a lot of time and human resources. The efficiency of manual inspections is limited by human factors, and it is impossible to carry out high-frequency and high-coverage inspections. The environment in the substation is complex and the equipment is dense. Manual inspections have potential risks such as electric shock, high temperature, and mechanical damage. In severe weather conditions, the safety of manual inspections is difficult to guarantee. The quality of manual inspections depends on the professional level and working status of the staff, and it is difficult to ensure consistency. Factors such as staff fatigue and distraction may lead to inspection omissions or misjudgments.

[0003] With the rapid development of drone technology, drones are gradually being introduced into substation inspections due to their flexibility, efficiency, and remote control capabilities. Compared with traditional manual inspections, drones can quickly reach every corner of the substation, with a wide coverage area and fast inspection speed. The inspection task of large-area equipment can be completed efficiently through a predetermined flight path. Drones can inspect equipment at a safe distance, avoiding personnel from contacting high-risk areas. In severe weather conditions, drones can replace manual inspections to improve safety. Drones are equipped with high-definition cameras, infrared sensors and other equipment to obtain high-definition images and data such as equipment temperature. Through data analysis, equipment abnormalities can be discovered in a timely manner and preventive maintenance can be performed.

[0004] Most existing path planning methods are static planning, lacking the ability to dynamically adjust to the actual environment. Path planning does not fully consider the importance of equipment and inspection priority, resulting in some important equipment not being inspected first. There is a lack of intelligent adjustment mechanism, and it is impossible to dynamically adjust the inspection path based on the real-time equipment status data to improve inspection efficiency. Energy consumption and battery life issues: The flight time of drones is limited by battery capacity, and path planning fails to fully optimize energy consumption, affecting the sustainability of inspection tasks. Energy consumption issues are not fully considered in path planning, resulting in the possibility of low battery power during the inspection process. Summary of the invention

[0005] The present invention provides a substation unmanned aerial vehicle patrol path planning method and system to solve the problems existing in the prior art.

[0006] In order to achieve the above object, the present invention is implemented by the following technical solutions:

[0007] A substation UAV patrol path planning method, comprising:

[0008] S1. Collect laser point cloud data of the substation and use the laser point cloud data to build a substation environment model;

[0009] S2. Obtain real-time data of substation equipment operation, and generate equipment operation weights based on the real-time data of substation equipment operation;

[0010] S3. Calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path;

[0011] S4. During the inspection process, the operation weight of the equipment is obtained regularly and the real-time equipment inspection priority is calculated. The area that has been inspected in a single round of inspection mission of the drone is recorded. The real-time equipment inspection priority and the inspected area are sent to the path planning model to generate a real-time inspection path, and the inspection task is continued according to the real-time inspection path;

[0012] S5. Monitor the remaining power and power consumption of the drone in real time, and adjust the patrol path and patrol mission of the drone according to the remaining power and power consumption;

[0013] S6. Obtain visible light image data and infrared image data during the substation inspection process through the installed imaging equipment, send the visible light image data and infrared image data into the image recognition model for abnormality identification, obtain the abnormality identification result, and choose whether to perform detailed data recording according to the abnormality identification result, record the number of inspections of different equipment for each inspection task, and generate feedback weights according to the number of inspections and abnormality identification results and adjust the initial weights of the substation equipment.

[0014] As a preferred technical solution of the present invention, the patrol path planning model is divided into a weight allocation layer, a path recording layer and a path planning layer;

[0015] The weight allocation layer is used to divide the weights according to the model mode. The model modes include traversal patrol, shortest patrol and intelligent patrol. The traversal patrol sets the patrol priority of all substation equipment to the same value to obtain a path planning for patrolling all substation equipment once. The shortest patrol sets the patrol priority of all substation equipment to zero to obtain the shortest path planning back to the destination. The intelligent patrol provides intelligent patrol path planning for the equipment through the patrol priority of the equipment.

[0016] The path record layer is used to record the patrolled areas during patrol tasks;

[0017] The path planning layer is used to plan the patrol path based on the substation environment model, equipment patrol priority and patrolled areas.

[0018] As a preferred technical solution of the present invention, patrol path planning includes the following specific steps:

[0019] A1. Obtain the substation environment model, determine the starting and ending positions, and obtain parameters, including the population size N, the maximum number of iterations t max , the number of devices m and the priority of device inspection;

[0020] A2. Use Bernoulli mapping to initialize the population, generate N initial paths, and calculate the fitness value of each initial path according to the objective function;

[0021] A3. Update and record the optimal path according to the fitness value of each initial path, determine the location of the device according to the patrol formula, patrol the device, and update the path point location;

[0022] A4. Perform refraction reverse learning on the optimal path point to obtain the optimal path point;

[0023] A5. Determine whether the maximum number of iterations t has been reached max If it is reached, the optimal path points are connected and output as the optimal patrol path, otherwise steps A3 and A4 are looped.

[0024] As a preferred technical solution of the present invention, the substation environment model includes a three-dimensional obstacle model of the substation and a two-dimensional patrol map from a bird's-eye view, wherein the two-dimensional patrol map includes patrollable paths and locations of substation equipment and corresponding numbers.

[0025] As a preferred technical solution of the present invention, the equipment inspection priority is calculated according to the initial weight and operation weight of the substation equipment;

[0026] The initial weight of the substation equipment is calculated by the importance assessment value and the failure rate weight of the equipment. The operation weight of the substation equipment is calculated by the difference between the real-time operation data of the equipment and the dynamic standard operation data. The dynamic standard operation data is obtained by matching the ambient temperature data and ambient humidity data obtained by the temperature sensors and humidity sensors configured around the equipment. The initial weight of the substation equipment is calculated using the feedback weight. After the initial weight and operation weight of the substation equipment are standardized, the equipment patrol priority is obtained by adding them together.

[0027] As a preferred technical solution of the present invention, feedback weights are used to calculate the initial weights of substation equipment; the feedback weights are obtained through the number of patrols and the results of abnormality identification, and patrol tasks for a device with more than or equal to three patrols and no abnormality identified are recorded as weak patrols for the device, and feedback weight A is obtained based on the proportion of weak patrols for the device within a recent prescribed number of times; patrol tasks for which the number of patrols in weak patrols exceeds five times and no abnormality identified are recorded as invalid patrols for the device, and feedback weight B is obtained based on the proportion of invalid patrols for the device within a long-term prescribed number of times, and the product of feedback weight A and feedback weight B is calculated as the feedback weight.

[0028] As a preferred technical solution of the present invention, the patrol path and patrol mission of the UAV are adjusted according to the remaining power and power consumption; the remaining patrol mileage of the UAV is obtained through the power consumption of the UAV, and the patrol path and patrol mission are determined by comparing the mileage with the remaining mileage in the real-time patrol path.

[0029] As a preferred technical solution of the present invention, an abnormality recognition result is obtained, and whether to record detailed data is selected according to the abnormality recognition result. The abnormality recognition result is obtained through an image recognition model, and the image recognition model is obtained by training a convolutional neural network using historical image data. The goals of the model are equipment numbering, equipment appearance damage recognition, infrared temperature anomaly recognition, flame and smoke recognition, and foreign object recognition.

[0030] A substation drone inspection path planning system, comprising:

[0031] The environment construction module is used to collect the laser point cloud data of the substation and use the laser point cloud data to build a three-dimensional substation environment model;

[0032] The data acquisition module is used to obtain the real-time data of the substation equipment operation and generate the equipment operation weight according to the real-time data of the substation equipment operation;

[0033] The initial path planning module is used to calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path;

[0034] The real-time path adjustment module is used to obtain the operation weight of the equipment at regular intervals during the patrol process and calculate the real-time equipment patrol priority, record the areas patrolled by the drone in a single round of patrol missions, send the real-time equipment patrol priority and the patrolled areas into the path planning model, generate a real-time patrol path, and continue the patrol mission according to the real-time patrol path; monitor the remaining power and power consumption of the drone in real time, and adjust the drone's patrol path and patrol mission according to the remaining power and power consumption;

[0035] The patrol feedback module is used to obtain visible light image data and infrared image data during the substation patrol process through the installed imaging equipment, send the visible light image data and infrared image data into the image recognition model for abnormality recognition, obtain the abnormality recognition result, and choose whether to perform detailed data recording according to the abnormality recognition result, record the number of patrols of different equipment for each patrol task, and adjust the initial weight of the substation equipment according to the number of patrols and the abnormality recognition result.

[0036] The present invention has the following advantages:

[0037] 1. The present invention models the substation environment to generate a three-dimensional obstacle model with environmental obstacles and a two-dimensional patrol map with equipment locations, which is convenient for dynamic adjustment of the patrol path; the initial weight and real-time weight are obtained through the performance information and real-time operation data of the equipment and the equipment patrol priority is calculated, thereby realizing the sequential patrol of different equipment, and adjusting the initial weight through the feedback result of the patrol number of the equipment in each patrol task, thereby improving the dynamic evaluation capability of the equipment importance and failure probability.

[0038] 2. The present invention improves the intelligent dynamic adjustment capability of path planning by collecting real-time operation data of equipment during the patrol process and performing path planning again during the operation process.

[0039] 3. The present invention effectively prevents the problem of insufficient current in the UAV during the patrol mission by real-time monitoring of the power status of the UAV during the patrol mission and adjusting the patrol path.

[0040] 4. The present invention improves the processing capability of patrol path planning for multiple tasks by setting three patrol modes: traversal patrol, shortest patrol and intelligent patrol. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 A schematic diagram of the structure of a substation drone patrol path planning system adopted in an embodiment of the present invention. DETAILED DESCRIPTION

[0042] In order to enable persons skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0043] Embodiment 1, a substation drone inspection path planning method, comprising:

[0044] A substation UAV patrol path planning method, comprising:

[0045] S1. Collect laser point cloud data of the substation and use the laser point cloud data to build a substation environment model;

[0046] The substation environment model includes a three-dimensional obstacle model of the substation and a two-dimensional inspection map from a bird's-eye view. The two-dimensional inspection map includes the inspectable paths and the locations and corresponding numbers of the substation equipment.

[0047] S2. Obtain real-time data of substation equipment operation, and generate equipment operation weights based on the real-time data of substation equipment operation;

[0048] S3. Calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path;

[0049] Initial weight K of substation equipment a The importance of the equipment is evaluated by I a and the failure rate weight F a Calculated, K a =I a +F a , the importance assessment value of the equipment I a The failure rate weight is determined by the estimated failure probability p of the equipment and the number of failures n during the operation of the equipment. The calculation formula for the failure rate weight is F a =α1*p+α2*n / t, where t represents the time period of fault statistics, α1 and α2 are the initial value of the fault weight and the distribution weight of the long-term dependent value, α1+α2=1, where , T is time, V is the set decay rate; by adjusting the value of the assigned weight, the proportion of the equipment failure rate affected by the early and later influences can be dynamically adjusted. For example, in the early stage of equipment use, the value of α1 is large to avoid a small amount of fault data affecting the overall weight; after the equipment has been used for a long time, the value of α2 is large to avoid the failure of the predicted probability of the equipment after aging;

[0050] The importance evaluation value of the equipment and the time period of the failure statistics change with the season to obtain the initial weight of the equipment in different environments;

[0051] Operation weight K of substation equipment b The difference D between the real-time operation data of the equipment and the dynamic standard operation data x Calculated, x is the number of parameters of the equipment's operating data, and γ is the weight corresponding to each parameter;

[0052] ;

[0053] Dynamic standard operation data is obtained by matching the ambient temperature data and ambient humidity data obtained by the temperature sensors and humidity sensors configured around the equipment;

[0054] The initial weight of the substation equipment is calculated using the feedback weight. After the initial weight and operation weight of the substation equipment are standardized, the equipment inspection priority H is obtained by adding them. The calculation formula is:

[0055] ;

[0056] Where Sigmid is the normalization function, θ is the feedback weight, which is obtained by feedback from the number of patrol processes, β1 is the initial weight, and β2 is the weight of the running weight.

[0057] The patrol path planning model is divided into a weight allocation layer, a path recording layer, and a path planning layer;

[0058] The weight allocation layer is used to divide the weights according to the model mode. The model modes include traversal patrol, shortest patrol and intelligent patrol. The traversal patrol sets the patrol priority of all substation equipment to the same value to obtain a path planning for patrolling all substation equipment once. The shortest patrol sets the patrol priority of all substation equipment to zero to obtain the shortest path planning back to the destination. The intelligent patrol provides intelligent patrol path planning for the equipment through the patrol priority of the equipment.

[0059] The path record layer is used to record the patrolled areas during patrol tasks;

[0060] The path planning layer is used to plan the patrol path based on the substation environment model, equipment patrol priority and patrolled areas.

[0061] The specific steps of patrol route planning are as follows:

[0062] A1. Obtain the substation environment model, determine the starting and ending locations, and obtain parameters, including the population size N, which is used to determine the number of initial paths and the maximum number of iterations t. max , the number of devices m and the priority of device inspection;

[0063] A2. Use Bernoulli mapping to initialize the population, generate N initial paths, and calculate the fitness value of each initial path according to the objective function;

[0064] Objective function: minf=λ1*f1+λ2*f2+λ3*f3, where λ1, λ2 and λ3 are weight parameters, and λ1+λ2+λ3=1;

[0065] The drone should ensure that it can achieve the shortest path as much as possible under safe conditions, and the weight parameters are set to 0.3, 0.5, and 0.2 respectively;

[0066] f1, f2 and f3 are the cost functions of path planning, which are range cost, threat cost and stability cost respectively;

[0067] The voyage cost is a sum of the Euclidean distances between adjacent points and is used to find the shortest path to save time and resources. The formula is:

[0068] ;

[0069] Where px, py and pz represent the xyz coordinates of the path points;

[0070] The threat cost is obtained by comparing the difference between the UAV flight altitude and the terrain altitude. It is an indicator used to evaluate the risk or danger level of the UAV flight path. The formula is:

[0071] ;

[0072] Among them, z i is the height corresponding to the i-th path point;

[0073] The stability cost is obtained by calculating the RMSE root mean square error of the altitude, which is used to ensure that the UAV can continue to fly on the predetermined flight trajectory to minimize changes in different directions and altitude fluctuations, improve flight quality and reduce energy consumption. The formula is:

[0074] ;

[0075] Among them, h ave is the average height of the path, is the height of the i-th path point in the path;

[0076] A3. Update and record the optimal path according to the fitness value of each initial path, determine the location of the device according to the patrol formula, patrol the device, and update the path point location;

[0077] The patrol formula is used to determine the next device to be patrolled. It is obtained by calculating the device patrol priority and the weighted value of the objective function. The formula is:

[0078] ;

[0079] in To determine the devices to be inspected, r is the selection factor, and its value is a random number between (0,1). By selecting the factor, we can avoid falling into the local optimum.

[0080] A4. Perform refraction reverse learning on the optimal path point to obtain the optimal path point;

[0081] A5. Determine whether the maximum number of iterations t has been reached max If it is reached, the optimal path points are connected and output as the optimal patrol path, otherwise steps A3 and A4 are looped.

[0082] The path planning algorithm used is the improved OOA algorithm (AOOA). The OOA algorithm has the characteristics of fewer parameters, fast iteration speed, and strong global search ability. However, the convergence accuracy of the OOA algorithm is not enough and it is easy to fall into the local optimum. The present invention uses Bernoulli chaotic mapping to initialize the population, combines the cosine adaptive Levy flight strategy and the refraction direction learning strategy to solve the problem of being easily trapped in the local optimum.

[0083] The Bernoulli mapping initializes the population, and based on its good ergodicity, it makes the population distribution more uniform and improves the population diversity; combined with the cosine adaptive Levy flight strategy, it dynamically adjusts the balance between global search and local development, and at the same time promotes the algorithm's ability to jump out of the local optimum; the refraction direction learning strategy obtains more solutions of different degrees by autonomously controlling the learning range, thereby increasing the probability of converging to a high-quality solution, and to a certain extent improves the convergence accuracy and accelerates the convergence speed;

[0084] Bernoulli mapping formula: , where q i ∈(0,1), λ is the control parameter;

[0085] In the process of OOA path planning behavior, there are limitations in using random numbers generated by the rand function to control position offsets, which may lead to insufficient coverage of the search space in the early stage of the algorithm and miss the optimal solution; the cosine adaptive factor c is introduced to replace the random numbers generated by the rand function to optimize the balance between the global search and local development of the algorithm; in the initial stage of iteration, the factor c is stable at a higher value, which helps to expand the global search range; in the later stage of iteration, the factor c is stable at a lower value, which can perform local search more accurately, accelerate convergence, and help find a more accurate solution; the calculation formula of the factor c is as follows:

[0086] ;

[0087] Where t is the current iteration number;

[0088] Levy flight is a random search method whose step length follows Levy distribution. It combines the cosine adaptive factor with the Levy flight strategy to form a comprehensive optimization scheme. By adaptively adjusting the step length of Levy flight, the algorithm has a higher probability of making large step length moves in the early iteration, increasing the ability of global search; while in the later iteration, it is more inclined to make small step length moves to search for local optimal solutions more finely. In addition, Levy flight itself has the characteristic of making large step length moves with a small probability. By combining it with the adaptability of the factor, it helps the algorithm to make large-step random moves with a higher probability when approaching the local optimal solution, helping the algorithm to jump out of the local optimum.

[0089] Refraction reverse learning is a reverse learning strategy based on the principle of light refraction. By introducing the refraction reverse learning strategy at the end of each iteration, on the one hand, it can ensure the balance between exploration and development, and dynamically adjust the search radius according to the number of iterations and the global best solution, so that the search range in the early iteration stage is larger, increasing the possibility of global search; while in the later iteration stage, the search range is gradually reduced, which is conducive to more refined development of high-quality solutions; on the other hand, due to the increase in the number of feasible solutions, the diversity of the algorithm is improved, and the accuracy and convergence speed of the algorithm are improved to a certain extent;

[0090] S4. During the inspection process, the operation weight of the equipment is obtained regularly and the real-time equipment inspection priority is calculated. The area that has been inspected in a single round of inspection mission of the drone is recorded. The real-time equipment inspection priority and the inspected area are sent to the path planning model to generate a real-time inspection path, and the inspection task is continued according to the real-time inspection path;

[0091] S5. Monitor the remaining power and power consumption of the drone in real time, and adjust the patrol path and patrol mission of the drone according to the remaining power and power consumption;

[0092] Adjust the patrol path and patrol mission of the UAV according to the remaining power and power consumption; obtain the remaining patrol mileage of the UAV through the power consumption of the UAV, and determine the patrol path and patrol mission by comparing the mileage with the remaining mileage in the real-time patrol path.

[0093] S6. Obtain visible light image data and infrared image data during the substation inspection process through the mounted imaging device, send the visible light image data and infrared image data into the image recognition model for abnormality identification, obtain abnormality identification results, choose whether to perform detailed data recording according to the abnormality identification results, record the number of inspections of different equipment for each inspection task, and generate feedback weights according to the number of inspections and abnormality identification results and adjust the initial weights of substation equipment;

[0094] The abnormality recognition results are obtained through the image recognition model, which is obtained by training the convolutional neural network with historical image data. The model's objectives are equipment serial number, equipment appearance damage recognition, infrared temperature abnormality recognition, flame and smoke recognition, and foreign object recognition.

[0095] The feedback weight is obtained through the number of inspections and the results of abnormality identification. Inspection tasks for a device with more than or equal to three inspections and no abnormality identified are recorded as weak inspections for the device. Feedback weight A is obtained based on the proportion of weak inspections for the device within the recent specified number of times. Inspection tasks for a device with more than five inspections and no abnormality identified are recorded as invalid inspections for the device. Feedback weight B is obtained based on the proportion of invalid inspections for the device within the long-term specified number of times. The product of feedback weight A and feedback weight B is calculated as the feedback weight.

[0096] Example 2, a substation drone inspection path planning system, see Figure 1 As shown, including:

[0097] The environment construction module is used to collect the laser point cloud data of the substation and use the laser point cloud data to build a three-dimensional substation environment model;

[0098] The data acquisition module is used to obtain the real-time data of the substation equipment operation and generate the equipment operation weight according to the real-time data of the substation equipment operation;

[0099] The initial path planning module is used to calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path;

[0100] The real-time path adjustment module is used to obtain the operation weight of the equipment at regular intervals during the patrol process and calculate the real-time equipment patrol priority, record the areas patrolled by the drone in a single round of patrol missions, send the real-time equipment patrol priority and the patrolled areas into the path planning model, generate a real-time patrol path, and continue the patrol mission according to the real-time patrol path; monitor the remaining power and power consumption of the drone in real time, and adjust the drone's patrol path and patrol mission according to the remaining power and power consumption;

[0101] The patrol feedback module is used to obtain visible light image data and infrared image data during the substation patrol process through the installed imaging equipment, send the visible light image data and infrared image data into the image recognition model for abnormality recognition, obtain the abnormality recognition result, and choose whether to perform detailed data recording according to the abnormality recognition result, record the number of patrols of different equipment for each patrol task, and adjust the initial weight of the substation equipment according to the number of patrols and the abnormality recognition result.

[0102] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all such improvements and changes should fall within the scope of protection of the appended claims of the present invention. Parts not described in detail in this specification belong to the prior art known to those skilled in the art.

Claims

1. A substation drone inspection path planning method, characterized in that: include: S1. Collect laser point cloud data of the substation and use the laser point cloud data to build a substation environment model; S2. Obtain real-time data of substation equipment operation, and generate equipment operation weights based on the real-time data of substation equipment operation; S3. Calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path; S4. During the inspection process, the operation weight of the equipment is obtained regularly and the real-time equipment inspection priority is calculated. The area that has been inspected in a single round of inspection mission of the drone is recorded. The real-time equipment inspection priority and the inspected area are sent to the path planning model to generate a real-time inspection path, and the inspection task is continued according to the real-time inspection path; S5. Monitor the remaining power and power consumption of the drone in real time, and adjust the patrol path and patrol mission of the drone according to the remaining power and power consumption; S6. Obtain visible light image data and infrared image data during the substation inspection process through the installed imaging equipment, send the visible light image data and infrared image data into the image recognition model for abnormality identification, obtain the abnormality identification result, and choose whether to perform detailed data recording according to the abnormality identification result, record the number of inspections of different equipment for each inspection task, and generate feedback weights according to the number of inspections and abnormality identification results and adjust the initial weights of the substation equipment.

2. A substation drone patrol path planning method according to claim 1, characterized in that: The patrol path planning model is divided into a weight allocation layer, a path recording layer, and a path planning layer; The weight allocation layer is used to divide the weights according to the model mode. The model modes include traversal patrol, shortest patrol and intelligent patrol. The traversal patrol sets the patrol priority of all substation equipment to the same value to obtain a path planning for patrolling all substation equipment once. The shortest patrol sets the patrol priority of all substation equipment to zero to obtain the shortest path planning back to the destination. The intelligent patrol provides intelligent patrol path planning for the equipment through the patrol priority of the equipment. The path record layer is used to record the patrolled areas during patrol tasks; The path planning layer is used to plan the patrol path based on the substation environment model, equipment patrol priority and patrolled areas.

3. A substation drone patrol path planning method according to claim 2, characterized in that: Patrol route planning, the specific steps are as follows: A1. Obtain the substation environment model, determine the starting and ending positions, and obtain parameters, including the population size N, the maximum number of iterations t max , the number of devices m and the priority of device inspection; A2. Use Bernoulli mapping to initialize the population, generate N initial paths, and calculate the fitness value of each initial path according to the objective function; A3. Update and record the optimal path according to the fitness value of each initial path, determine the location of the device according to the patrol formula, patrol the device, and update the path point location; A4. Perform refraction reverse learning on the optimal path point to obtain the optimal path point; A5. Determine whether the maximum number of iterations t has been reached max If it is reached, the optimal path points are connected and output as the optimal patrol path, otherwise steps A3 and A4 are looped.

4. A substation drone patrol path planning method according to claim 1, characterized in that: The substation environment model includes a three-dimensional obstacle model of the substation and a two-dimensional inspection map from a bird's-eye view. The two-dimensional inspection map includes the inspectable paths and the locations and corresponding numbers of the substation equipment.

5. A substation drone patrol path planning method according to claim 1, characterized in that: Calculate equipment inspection priority based on the initial weight and operation weight of substation equipment; The initial weight of the substation equipment is calculated by the importance assessment value and the failure rate weight of the equipment. The operation weight of the substation equipment is calculated by the difference between the real-time operation data of the equipment and the dynamic standard operation data. The dynamic standard operation data is obtained by matching the ambient temperature data and ambient humidity data obtained by the temperature sensors and humidity sensors configured around the equipment. The initial weight of the substation equipment is calculated using the feedback weight. After the initial weight and operation weight of the substation equipment are standardized, the equipment patrol priority is obtained by adding them together.

6. A substation drone patrol path planning method according to claim 5, characterized in that: The initial weight of the substation equipment is calculated using the feedback weight; the feedback weight is obtained through the number of patrols and the abnormality recognition results. A patrol task in which a device has been patrolled three times or more and no abnormality has been recognized is recorded as a weak patrol of the device. The feedback weight A is obtained based on the proportion of the number of weak patrols of the device within the recent prescribed number of times. A patrol task in which the number of patrols in the weak patrol is more than five times and no abnormality has been recognized is recorded as an invalid patrol of the device. The feedback weight B is obtained based on the proportion of the number of invalid patrols of the device within the long-term prescribed number of times. The product of the feedback weight A and the feedback weight B is calculated as the feedback weight.

7. A substation drone inspection path planning method according to claim 1, characterized in that: Adjust the patrol path and patrol mission of the UAV according to the remaining power and power consumption; obtain the remaining patrol mileage of the UAV through the power consumption of the UAV, and determine the patrol path and patrol mission by comparing the mileage with the remaining mileage in the real-time patrol path.

8. A substation drone inspection path planning method according to claim 1, characterized in that: Get the abnormality recognition result, and choose whether to record detailed data according to the abnormality recognition result. The abnormality recognition result is obtained through the image recognition model. The image recognition model is obtained by training the convolutional neural network with historical image data. The model's goals are equipment numbering, equipment appearance damage recognition, infrared temperature anomaly recognition, flame and smoke recognition, and foreign object recognition.

9. A substation drone patrol path planning system, characterized in that: The system applies a substation drone patrol path planning method as described in any one of claims 1 to 8, comprising: The environment construction module is used to collect the laser point cloud data of the substation and use the laser point cloud data to build a three-dimensional substation environment model; The data acquisition module is used to obtain the real-time data of the substation equipment operation and generate the equipment operation weight according to the real-time data of the substation equipment operation; The initial path planning module is used to calculate the equipment inspection priority according to the initial weight and operation weight of the substation equipment, send the equipment inspection priority into the inspection path planning model, and generate the initial inspection path; The real-time path adjustment module is used to obtain the operation weight of the equipment at regular intervals during the patrol process and calculate the real-time equipment patrol priority, record the areas patrolled by the drone in a single round of patrol missions, send the real-time equipment patrol priority and the patrolled areas into the path planning model, generate a real-time patrol path, and continue the patrol mission according to the real-time patrol path; monitor the remaining power and power consumption of the drone in real time, and adjust the drone's patrol path and patrol mission according to the remaining power and power consumption; The patrol feedback module is used to obtain visible light image data and infrared image data during the substation patrol process through the installed imaging equipment, send the visible light image data and infrared image data into the image recognition model for abnormality recognition, obtain the abnormality recognition result, and choose whether to perform detailed data recording according to the abnormality recognition result, record the number of patrols of different equipment for each patrol task, and adjust the initial weight of the substation equipment according to the number of patrols and the abnormality recognition result.