An integrated dispatching method for passenger and freight railway transport resources

Through the integrated dispatching method of railway transportation resources for passengers and freight, a collaborative dispatching model of technical station line resources is constructed, which solves the problem of insufficient "point-line" coordination ability of the railway system under emergencies and improves transportation efficiency and dispatching coordination. , enhancing the resilience of the rail freight system.

CN118627853BActive Publication Date: 2024-10-22SHANDONG UNIV OF SCI & TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411087375.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-10-22
Estimated Expiration
2044-08-09

AI Technical Summary

Technical Problem

The railway system's "point-line" coordination ability is weak during emergencies, resulting in low transportation efficiency, and poor planning synergy between technical stations and lines, resulting in uncoordinated allocation of transportation resources.

Method used

Adopting the integrated dispatching method of railway transportation resources for both passengers and freight, by obtaining train operation plans and technical station resource data, a technical station line resource collaborative dispatching model is constructed, and optimal dispatching is carried out according to the disturbance parameters of emergencies to ensure that train operation is consistent with the technical station The collaborative nature of operations enables minimal interference adjustments to line and station resources.

Benefits of technology

Under emergencies, the efficiency and rationality of transportation resource dispatching of the railway system are improved, real-time dynamic dispatching is achieved, the recovery capability of the railway freight system is enhanced, and more real-time and accurate dispatching suggestions are provided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118627853B_ABST
    Figure CN118627853B_ABST
Patent Text Reader

Abstract

The present invention provides a method for integrated dispatching of passenger and freight shared railway transport capacity resources, which relates to the technical field of train operation plan adjustment, and specifically includes the following steps: obtaining various key resource data or operation parameters of all train operation plans, section stations or technical stations within the adjustment time period or line range; setting different disturbance parameters for train operation and technical station operation according to the emergencies encountered in the actual operation of the train; using the disturbance parameters as input, and constructing a technical station line resource collaborative dispatching model according to constraints with the goal of minimizing the impact of interference on the line and the station; using the technical station line resource collaborative dispatching model, adjusting the operation diagram and the technical station operation plan to obtain the optimized operation diagram and the technical station operation plan. The technical solution of the present invention overcomes the problem in the prior art that the "point-line" coordination ability of the railway system is weak and the transportation efficiency is low under emergencies.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of train operation plan adjustment, and in particular to a method for integrated dispatching of passenger and freight railway transport capacity resources. Background Art

[0002] Railway freight transportation is an important part of modern transportation and has played a vital role in the transportation field for many years. Since freight trains have a lower operating level and are easily affected by passenger trains, it is inevitable that daily transportation scheduling becomes more difficult and wastes resources related to railway transportation capacity.

[0003] From the perspective of the structure of the railway network, it consists of two major parts: points (stations, hubs) and lines (routes). When carrying out transportation production, the relationship between these two subsystems must be coordinated, that is, the "point-line" capabilities must be matched as much as possible. With the widespread use and continuous improvement of computer-compiled train operation diagrams and TDCS systems in railway bureaus and stations, the intelligence of the "line" has reached a considerable level; while the intelligence of the "point" is still quite different from the actual needs, resulting in relatively low coordination capabilities between the "point" and the "line".

[0004] As an important production unit of the railway, the technical station is a key link to ensure the smooth operation of railway hubs and trunk lines. At present, in the daily operation of railway freight in my country, the technical station operation plan and the line train operation plan are often compiled and adjusted separately, with poor coordination. In the event of an emergency, the two plans affect each other. At the station level, it is necessary to complete the train marshaling operation in the technical station as soon as possible and convert the arriving train flow into the line departure train flow; at the railway bureau level, it is necessary to adjust the line train operation plan as soon as possible to ensure that the freight trains of the technical station arrive and depart on time. However, due to the current situation of hierarchical scheduling between bureaus and stations, the technical station often needs to adjust the entire stage plan before applying to the railway bureau for the departure train route. When dealing with emergencies, due to the poor real-time communication between plans, it is inevitable that there will be problems such as uncoordinated allocation of capacity resources.

[0005] Therefore, there is a need for an integrated dispatching method for passenger and freight shared railway capacity resources with strong "point-line" coordination capabilities in emergency situations. Summary of the invention

[0006] The main purpose of the present invention is to provide an integrated dispatching method for passenger and freight co-line railway transport resources to solve the problem in the prior art that the "point-line" coordination ability of the railway system is weak and the transportation efficiency is low under emergencies.

[0007] To achieve the above object, the present invention provides a method for integrated dispatching of passenger and freight shared railway transport capacity resources, which specifically includes the following steps:

[0008] S1, obtain the key resource data or operation parameters of all train operation plans, section stations or technical stations within the adjustment period or line range.

[0009] S2, setting different disturbance parameters for train operation and technical station operation according to the emergencies encountered during the actual operation of the train.

[0010] S3, taking the disturbance parameters in step S2 as input, according to the constraints, including: train technical station arrival constraints, arrival and dismantling constraints, vehicle flow assembly constraints, vehicle marshaling operation constraints, departure-related constraints, train line operation constraints, and train operation and technical station operation coordination constraints, with the goal of minimizing the impact of interference on lines and stations, a technical station line resource collaborative scheduling model is constructed.

[0011] S4, using the technical station line resource collaborative scheduling model obtained in step S3, adjust the operation diagram and the technical station operation plan to obtain an optimized operation diagram and technical station operation plan.

[0012] Furthermore, the train operation plan in step S1 includes: train type, arrival and departure time and priority; various key resource data or operation parameters include: number of tracks at section stations, storage capacity, number of humps at technical stations, number of arrival and departure lines, number of shunting lines, technical inspection time and marshalling time.

[0013] Furthermore, the train technical station arrival constraints include: the train arrival time at the technical station is greater than the scheduled time, the arrival interval and arrival sequence constraints of two trains, and the arrival line capacity constraints;

[0014] ;

[0015] ;

[0016] ;

[0017] ;

[0018] ;

[0019] ;

[0020] in, For trains The actual time of arrival at the marshalling yard, is the planned arrival time, It is a 0-1 variable, indicating the train Grouping operation sequence, =1 means train First, unpack. is the minimum interval for trains to arrive at a technical station, is an integer, is a 0-1 variable, Indicates train At the moment Arrived at the technical station, is a 0-1 variable, =1 means train At the moment Complete the dismantling work. The maximum capacity of the arrival area.

[0021] Furthermore, the arrival and disassembly constraints are: after the train arrives at the technical station, it needs to pass the technical inspection before the disassembly operation can be carried out, and each disassembly operation takes a certain time, and the disassembly order and disassembly interval of the two trains must also meet certain constraints;

[0022] ;

[0023] ;

[0024] ;

[0025] ;

[0026] ;

[0027] ;

[0028] in, For trains The time to start disintegration, For trains The time when the disintegration ends, They are the minimum technical inspection time, minimum disassembly time and minimum disassembly interval of the train, is a 0-1 variable, Indicates train Than Train Perform the decompilation operation first.

[0029] Furthermore, the vehicle flow assembly constraints are: the cumulative number of arriving and departing vehicles on the shunting line satisfies the flow balance constraint, and the number of vehicles in the shunting line cannot exceed its capacity at any time;

[0030] ;

[0031] ;

[0032] ;

[0033] ;

[0034] ;

[0035] ;

[0036] in, Respectively indicate the end of At that time, the cumulative number of vehicles arriving and departing from the shunting line, Indicates train Include destination The number of vehicles, is a 0-1 variable, Indicates shunting line Gathering destination of vehicles, is a 0-1 variable, express Time shunting line Start grouping. is a 0-1 variable, express Time shunting line Start work, where ; The minimum time of marshalling operation, the discrete length of model time and the maximum capacity of shunting line are respectively.

[0037] Furthermore, the vehicle marshaling operation constraints are as follows: the marshaling operation satisfies the input-output flow balance constraint, and the marshaled train needs to satisfy the full axle constraint;

[0038] ;

[0039] ;

[0040] ;

[0041] ;

[0042] ;

[0043] in, Indicated in Start grouping processing at the moment The number of cars going to the destination, Indicated in Start marshaling operation processing and enter the departure train The number of vehicles going to Indicates that it is incorporated into the departure train and Always waiting to depart The number of vehicles going to Indicates that it is incorporated into the departure train and Always on the move The number of vehicles going to is a 0-1 variable, =1 indicates the destination Vehicles allowed to be included A train departs at a certain time. They are the minimum and maximum marshaling numbers of departing trains respectively.

[0044] Furthermore, the departure constraints are as follows: the departure operation mainly refers to the process in which the marshaled train matches the departure locomotive and undergoes the final technical inspection at the departure yard and waits for departure. The marshaling destination must match the locomotive destination and meet the technical inspection time constraint. The actual departure time cannot be earlier than the scheduled time. The number of trains waiting to depart at the same time must be less than the maximum capacity of the departure yard.

[0045] ;

[0046] ;

[0047] ;

[0048] ;

[0049] ;

[0050] ;

[0051] ;

[0052] ;

[0053] ;

[0054] ;

[0055] in, is a 0-1 variable, express Time direction Trains Set off, is a 0-1 variable, =1 means train Send to direction, Indicates train The actual time of leaving the technical station, is a 0-1 variable, =1 means train At the moment Departure, They respectively represent the train departure technical inspection time, scheduled departure time and maximum capacity of the departure yard.

[0056] Furthermore, the train line operation constraints are as follows: the arrival and departure time of the adjusted train at each station must not be earlier than the planned time, and the train's stop time at the station and the running time in the section must be greater than the minimum stop time and the minimum section running time; the arrival and departure activities of two trains at the same station must have a certain interval, and at the same time, the number of trains stopping at the station must meet the station capacity limit;

[0057] ;

[0058] ;

[0059] ;

[0060] ;

[0061] ;

[0062] ;

[0063] ;

[0064] ;

[0065] ;

[0066] ;

[0067] in, , For trains At the station The actual arrival and departure time, , The planned arrival and departure time, is the minimum running interval, , Train and At the station The actual arrival and departure order, To plan the arrival and departure order, Indicates train Arrival at the station With train Leaving the station The order of Indicates train The operating level, For the station The maximum capacity.

[0068] Furthermore, the coordination constraints between train operation and technical station operation are as follows: the arrival time of the line train at the technical station is directly related to the start time of the train technical station operation, and the end time of the technical station operation is directly related to the departure time of the line-related vehicles, which need to meet certain coordination constraints;

[0069] ;

[0070] ;

[0071] in, Represents marshalling yard.

[0072] Furthermore, the goal is to minimize the impact of interference on the line and the station, that is, the optimization goal is:

[0073] ;

[0074] in, , , is the weight coefficient of each sub-objective function, Penalties for line train operation, including passenger train timetable deviation and freight train arrival plan fulfillment rate penalties; Indicates departure deviation of train technical station. Indicates the number of cars in the train formation when the train departs from the technical station.

[0075] The present invention has the following beneficial effects:

[0076] The method proposed in the present invention closely couples the operation status of line trains with the operation status of technical stations under emergencies, and in view of the current transportation mode of passenger and freight co-line on my country's railway trunk lines, fully considers the impact of passenger trains on freight trains, coordinates the resources of line sections, stations, arrival lines, humps, shunting lines, departure lines, etc. in technical stations, breaks through the current status of hierarchical scheduling between technical stations and lines in the freight system, and coordinates the line train operation plan and the technical station operation plan to ensure the fulfillment rate of the freight train arrival plan. Using the discrete time method, various types of railway transport resources are monitored and scheduled in real time, weakening the role of the hourly shift plan and stage plan of railway freight, realizing dynamic scheduling in minutes, greatly improving the coordination speed of scheduling plans between bureaus and stations, and providing dispatchers with more real-time and accurate suggestions to improve the recovery capacity of the railway freight system under emergencies. BRIEF DESCRIPTION OF THE DRAWINGS

[0077] In order to more clearly illustrate the specific implementation of the present invention or the technical solutions in the prior art, the following will briefly introduce the drawings required for the specific implementation or the prior art description. Obviously, the drawings described below are some implementations of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:

[0078] Figure 1 A flow chart of a method for integrated dispatching of passenger and freight shared railway transport capacity resources of the present invention is shown.

[0079] Figure 2 A schematic diagram of a double-track railway disturbance scenario is shown. DETAILED DESCRIPTION

[0080] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0081] like Figure 1 The integrated dispatching method of passenger and freight shared railway transport capacity resources shown in the figure specifically comprises the following steps:

[0082] S1, obtain the key resource data or operation parameters of all train operation plans, section stations or technical stations within the adjustment time period or line range. Collect and organize the train operation diagram information and technical station related data within a certain period of time on the passenger and freight shared railway, and convert them into corresponding mathematical expressions. Then, combined with the corresponding railway capacity resource scheduling logic, modeling is carried out through the discretization time method to obtain the original model.

[0083] S2, setting different disturbance parameters for train operation and technical station operation according to the emergencies encountered during the actual operation of the train.

[0084] S3, taking the disturbance parameters in step S2 as input, inputs them into the original model, and constructs a technical station line resource collaborative scheduling model based on the constraints, including: train technical station arrival constraints, arrival and dismantling constraints, vehicle flow assembly constraints, vehicle marshaling operation constraints, departure-related constraints, train line operation constraints, and train operation and technical station operation coordination constraints, with the goal of minimizing the impact of interference on lines and stations. Figure 2 shows a double track railway disturbance scenario, Figure 2The up and down directions of the train are specified in the , each station is regarded as a section station, station i is a technical station, and station n is a boundary station. The disturbance occurs between two section stations, that is, between two stations, and disturbances such as section interruption may occur, which in turn affects the train operation. The disturbance parameters simulate the impact of emergencies on train operation in actual situations.

[0085] S4, using the technical station line resource collaborative scheduling model obtained in step S3, adjust the operation diagram and the technical station operation plan to obtain an optimized operation diagram and technical station operation plan.

[0086] Specifically, the train operation plan in step S1 includes: train type, arrival and departure time and priority; various key resource data or operation parameters include: number of tracks at section stations, storage capacity, number of humps at technical stations, number of arrival and departure lines, number of shunting lines, technical inspection time and marshalling time.

[0087] The present invention couples the technical station operation constraints with the line train operation constraints and realizes real-time dynamic adjustment under emergencies to improve the efficiency and rationality of railway transport resource dispatching.

[0088] Specifically, the train technical station arrival constraints include: the train arrival operation mainly refers to a series of operations performed after the train arrives at the technical station arrival yard. The present invention involves arrival constraints mainly including the train arrival time at the technical station greater than the scheduled time, the arrival interval and arrival sequence constraints of two trains, and the arrival line capacity constraints;

[0089] ;

[0090] ;

[0091] ;

[0092] ;

[0093] ;

[0094] ;

[0095] in, For trains The actual time of arrival at the marshalling yard, is the planned arrival time, It is a 0-1 variable, indicating the train Grouping operation sequence, =1 means train First, unpack. is the minimum interval for trains to arrive at a technical station, is an integer, is a 0-1 variable, Indicates train At the moment Arrived at the technical station, is a 0-1 variable, =1 means train At the moment Complete the dismantling work. The maximum capacity of the arrival area.

[0096] Specifically, the arrival and disassembly constraints are: after the train arrives at the technical station, it needs to pass the technical inspection before the disassembly operation can be carried out, and each disassembly operation takes a certain amount of time, and the disassembly order and disassembly interval of the two trains must also meet certain constraints. The minimum operation interval constraint also ensures that there is no overlap in the time of the two disassembly operations, that is, in actual operations, the two operations are completed successively by a disassembly and adjustment machine, and there is no mutual interference. For the two groups of decision variables related to the disassembly operation, there is also a logical constraint that there is a certain relationship between the disassembly operation end time variable and the disassembly operation end state variable.

[0097] ;

[0098] ;

[0099] ;

[0100] ;

[0101] ;

[0102] ;

[0103] in, For trains The time to start disintegration, For trains The time when the disintegration ends, They are the minimum technical inspection time, minimum disassembly time and minimum disassembly interval of the train, is a 0-1 variable, Indicates train Than Train Perform the decompilation operation first.

[0104] Specifically, the vehicle flow assembly constraint is: in the arrival yard of the technical station, the assembly operation is mainly to organize the vehicle flow that has completed the disassembly operation in the arriving train according to the direction of the vehicle flow, and enter the corresponding shunting lines respectively. The use plan of the shunting line is arranged according to the set requirements. This patent adopts the cumulative flow modeling method. The vehicle flow that has completed the disassembly operation and the vehicle flow input and output of the assembly operation, that is, the cumulative number of vehicles arriving and departing from the shunting line, need to meet certain flow balance constraints, and the number of vehicles in the shunting line at any time cannot exceed its capacity.

[0105] ;

[0106] ;

[0107] ;

[0108] ;

[0109] ;

[0110] ;

[0111] in, Respectively indicate the end of At that time, the cumulative number of vehicles arriving and departing from the shunting line, Indicates train Include destination The number of vehicles, is a 0-1 variable, Indicates shunting line Gathering destination of vehicles, is a 0-1 variable, express Time shunting line Start grouping. is a 0-1 variable, express Time shunting line Start work, where ; The minimum time of marshalling operation, the discrete length of model time and the maximum capacity of shunting line are respectively.

[0112] Specifically, the vehicle marshaling operation constraints are as follows: Train marshaling operation refers to the process of marshaling and shunting the vehicles assembled on the shunting line into trains. Each departure train often requires multiple marshaling operations to be fully assembled. Similar to the assembly operation, the marshaling operation also needs to meet certain input-output flow balance constraints, and the marshaling operation output flow needs to be divided into two parts to describe multiple marshaling operations of the same departure train. At the same time, the marshaled train needs to meet certain full axle constraints.

[0113] ;

[0114] ;

[0115] ;

[0116] ;

[0117] ;

[0118] in, Indicated in Start grouping processing at the moment The number of cars going to the destination, Indicated in Start marshaling operation processing and enter the departure train The number of vehicles going to Indicates that it is incorporated into the departure train and Always waiting to depart The number of vehicles going to Indicates that it is incorporated into the departure train and Always on the move The number of vehicles going to is a 0-1 variable, =1 indicates the destination Vehicles allowed to be included A train departs at a certain time. They are the minimum and maximum marshaling numbers of departing trains respectively.

[0119] Specifically, the constraints related to departure are: departure operation mainly refers to the process of matching the departure locomotive and the final technical inspection of the completed train at the departure yard and waiting for departure. The destination of the marshaling must match the destination of the locomotive, and it needs to meet certain technical inspection time constraints. Under normal circumstances, the actual departure time cannot be earlier than the scheduled time. In addition, the departure yard of the technical station also has a certain capacity, and the number of trains waiting to depart at the same time needs to be less than the maximum capacity of the departure yard. And the departure time of the train at the technical station is directly related to the operation of the line train, so the decision variables related to the operation of the line train must also meet certain logical relationships with the variables related to the operation of the technical station:

[0120] ;

[0121] ;

[0122] ;

[0123] ;

[0124] ;

[0125] ;

[0126] ;

[0127] ;

[0128] ;

[0129] ;

[0130] in, is a 0-1 variable, express Time direction Trains Set off, is a 0-1 variable, =1 means train Send to direction, Indicates train The actual time of leaving the technical station, is a 0-1 variable, =1 means train At the moment Departure, They respectively represent the train departure technical inspection time, scheduled departure time and maximum capacity of the departure yard.

[0131] Specifically, the train line operation constraints are: the arrival and departure time of the adjusted train at each station must not be earlier than the planned time, and the train's stop time at the station and the running time in the section must be greater than the minimum stop time and the minimum section running time. Since passenger and freight trains have different priorities, the arrival and departure of the two trains at a certain station after adjustment must have a certain order. This order is determined by the actual operation of the trains when the train interference occurs and the train's own operation level, and the arrival and departure activities of the two trains at the same station must have a certain interval. At the same time, the number of trains stopping at the station must meet the station capacity limit.

[0132] ;

[0133] ;

[0134] ;

[0135] ;

[0136] ;

[0137] ;

[0138] ;

[0139] ;

[0140] ;

[0141] ;

[0142] in, , For trains At the station The actual arrival and departure time, , The planned arrival and departure time, is the minimum running interval, , Train and At the station The actual arrival and departure order, To plan the arrival and departure order, Indicates train Arrival at the station With train Leaving the station The order of Indicates train The operating level, For the station The maximum capacity.

[0143] Specifically, the coordination constraints between train operation and technical station operation are as follows: the arrival time of the line train at the technical station is directly related to the start time of the train technical station operation, and the end time of the technical station operation is directly related to the departure time of the line-related vehicles, which need to meet certain coordination constraints;

[0144] ;

[0145] ;

[0146] in, Represents marshalling yard.

[0147] Specifically, the present invention coordinates various resources in the operation of passenger and freight shared railway trains, with the aim of achieving reasonable scheduling of resources between lines and technical stations under emergency conditions. The main optimization indicators include train line delays, vehicle turnover speed at technical stations, departure time deviations at technical stations, etc., with the goal of minimizing the impact of interference on lines and stations. The specific objective function is:

[0148] ;

[0149] in, , , is the weight coefficient of each sub-objective function, Penalties for line train operation, including passenger train timetable deviation and freight train arrival plan fulfillment rate penalties; It represents the departure deviation of train technical stations. The reason for designing this optimization target is that in the technical station line resource collaborative scheduling model, not only the trains on the lines selected in the train line operation adjustment model are considered, but also all the trains arriving at the technical station within the adjustment period are considered. The purpose of setting this indicator is to minimize the impact of the lines selected in the model on other lines. Indicates the number of cars in the train formation when the train departs from the technical station.

[0150] Finally, the optimized operation diagram and technical station operation plan obtained in step S4 are converted into a train operation diagram and a technical station operation schedule.

[0151] In order to verify the beneficial effects of the present invention, a technical station line resource collaborative scheduling model was constructed in combination with the actual operation data of a railway, and the commercial solution software CPLEX was used to solve the problem in several delay scenarios. As shown in Table 1, according to the method provided by the present invention, passenger and freight trains are scheduled. In the scenario without interference, the objective function weight coefficients are set to 1, 1, 10, the passenger train delay time is 0, the freight train schedule offset time is 0, and the number of train vehicles is 316; in the scenario where train 1 is delayed for 35 minutes at station 15, the objective function weight coefficients are set to 1, 1, 10, the passenger train delay time is 0, the freight train schedule offset time is 341min, and the number of train vehicles is 316. The number of vehicles in the train is 272; in the scenario where train 1 is delayed for 35 minutes at station 15, the objective function weight coefficient is set to 1, 1, 100, the passenger train delay time is 0, the freight train schedule offset time is 443 minutes, and the number of vehicles in the train is 325; in the scenario where train 1 is delayed for 20 minutes at station 15, the objective function weight coefficient is set to 1, 1, 10, the passenger train delay time is 0, the freight train schedule offset time is 215 minutes, and the number of vehicles in the train is 316; In the scenario where train 1 is delayed for 20 minutes at station 15, the objective function weight coefficients are set to 1, 1, 100, the passenger train delay time is 0, the freight train schedule offset time is 270 minutes, and the train vehicle number is 325; in the scenario where train 4 is delayed for 30 minutes at station 18, the objective function weight coefficients are set to 1, 1, 10, the passenger train delay time is 178 minutes, the freight train schedule offset time is 10 minutes, and the train vehicle number is 316; In the scenario where train 4 is delayed for 40 minutes at station 18, the objective function weight coefficients are set to 1, 1, 10, the passenger train delay time is 216 minutes, the freight train schedule deviation time is 71 minutes, and the number of train vehicles is 316; in the scenario where train 4 is delayed for 40 minutes at station 18, the objective function weight coefficients are set to 1, 10, 10, the passenger train delay time is 216 minutes, the freight train schedule deviation time is 60 minutes, and the number of train vehicles is 301.

[0152] Table 1 Adjustment results

[0153] .

[0154] The technical station line resource collaborative scheduling model proposed in the present invention can break the current hierarchical scheduling status between railway bureaus and technical stations, and between line train operation and technical station operation in the event of an emergency, and realize the real-time dynamic scheduling of passenger and freight shared-line railway capacity resources with bureau-station integration and "point-line" coordination, improve the feasibility, rationality and coordination of the adjustment results, and provide dispatchers with more specific and effective suggestions for handling emergencies, which is conducive to improving the recovery capability and operation efficiency of the railway system.

[0155] Of course, the above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Changes, modifications, additions or substitutions made by technicians in this technical field within the essential scope of the present invention should also fall within the protection scope of the present invention.

Claims

1. A method for integrated dispatching of passenger and freight railway transport resources, characterized in that: The specific steps include: S1, obtain key resource data or operation parameters of all train operation plans, section stations or technical stations within the adjustment period or line range; S2, setting different disturbance parameters for train operation and technical station operations according to the emergencies encountered during the actual operation of the train; S3, taking the disturbance parameters in step S2 as input, and building a technical station line resource collaborative scheduling model according to the constraints, including: train technical station arrival constraints, arrival and dismantling constraints, vehicle flow assembly constraints, vehicle marshaling operation constraints, departure-related constraints, train line operation constraints, and train operation and technical station operation coordination constraints, with the goal of minimizing the impact of the disturbance on the line and the station; S4, using the technical station line resource collaborative scheduling model obtained in step S3, adjusting the operation diagram and the technical station operation plan to obtain an optimized operation diagram and technical station operation plan; The train technical station arrival constraints include: the train arrival time at the technical station is greater than the scheduled time, the arrival interval and arrival sequence constraints of two trains, and the arrival line capacity constraints; ; ; ; ; ; ; in, For trains The actual time of arrival at the marshalling yard, is the planned arrival time, It is a 0-1 variable, indicating the train Grouping operation sequence, =1 means train First, unpack. is the minimum interval for trains to arrive at a technical station, is an integer, is a 0-1 variable, Indicates train At the moment Arrived at the technical station, is a 0-1 variable, =1 means train At the moment Complete the dismantling work. The maximum capacity of the arrival site; The arrival and disassembly constraints are: after the train arrives at the technical station, it needs to pass the technical inspection before the disassembly operation can be carried out, and each disassembly operation takes a certain time, and the disassembly order and disassembly interval of the two trains must also meet certain constraints; ; ; ; ; ; ; in, For trains The time to start disintegration, For trains The time when the disintegration ends, They are the minimum technical inspection time, minimum disassembly time and minimum disassembly interval of the train, is a 0-1 variable, Indicates train Than Train First, perform the decompilation operation; The vehicle flow assembly constraints are: the cumulative number of vehicles arriving and departing from the shunting line meets the flow balance constraint, and the number of vehicles in the shunting line at any time cannot exceed its capacity; ; ; ; ; ; ; in, Respectively indicate the end of At that time, the cumulative number of vehicles arriving and departing from the shunting line, Indicates train Include destination The number of vehicles, is a 0-1 variable, Indicates shunting line Gathering destination of vehicles, is a 0-1 variable, express Time shunting line Start grouping. is a 0-1 variable, express Time shunting line Start work, where ; The minimum time of marshaling operation, the discrete length of model time and the maximum capacity of shunting line are respectively; The vehicle marshaling operation constraints are: the marshaling operation meets the input-output flow balance constraint, and the marshaled train needs to meet the full axle constraint; ; ; ; ; ; in, Indicated in Start grouping processing at the moment The number of cars going to the destination, Indicated in Start marshaling operation processing at the moment and enter the departure train The number of vehicles going to Indicates that it is incorporated into the departure train and Always waiting to depart The number of vehicles going to Indicates that it is incorporated into the departure train and Always on the move The number of vehicles going to is a 0-1 variable, =1 indicates the destination Vehicles allowed to be included A train departs at a certain time. They are the minimum and maximum marshaling numbers of the departing train respectively; The departure constraints are as follows: the departure operation mainly refers to the process in which the marshaled train matches the departure locomotive and undergoes the final technical inspection at the departure yard and waits for departure. The marshaling destination must match the locomotive destination and meet the technical inspection time constraint. The actual departure time cannot be earlier than the scheduled time. The number of trains waiting to depart at the same time must be less than the maximum capacity of the departure yard. ; ; ; ; ; ; ; ; ; ; in, is a 0-1 variable, express Time direction Trains Set off, is a 0-1 variable, =1 means train Send to direction, Indicates train The actual time of leaving the technical station, is a 0-1 variable, =1 means train At the moment Departure, They represent the train departure technical inspection time, scheduled departure time and the maximum capacity of the departure yard respectively; The train line operation constraints are as follows: the arrival and departure time of the adjusted train at each station must not be earlier than the planned time, and the train's stop time at the station and the running time in the section must be greater than the minimum stop time and the minimum section running time; the arrival and departure activities of two trains at the same station must have a certain interval, and at the same time, the number of trains stopping at the station must meet the station capacity limit; ; ; ; ; ; ; ; ; ; ; in, , For trains At the station The actual arrival and departure time, , The planned arrival and departure time, is the minimum running interval, , Train and At the station The actual arrival and departure order, To plan the arrival and departure order, Indicates train Arrival at the station With train Leaving the station The order of Indicates train The operating level, For the station Maximum capacity; The coordination constraints between train operation and technical station operation are as follows: the arrival time of the line train at the technical station is directly related to the start time of the train technical station operation, and the end time of the technical station operation is directly related to the departure time of the line-related vehicles, which need to meet certain coordination constraints; ; ; in, represents the marshaling yard; The goal is to minimize the impact of interference on the line and stations, that is, the optimization objectives are: ; in, , , is the weight coefficient of each sub-objective function, Penalties for line train operation, including passenger train timetable deviation and freight train arrival plan fulfillment rate penalties; Indicates departure deviation of train technical station. Indicates the number of cars in the train formation when the train departs from the technical station.

2. The integrated dispatching method for passenger and freight shared railway capacity resources according to claim 1 is characterized in that: The train operation plan in step S1 includes: train type, arrival and departure time and priority; various key resource data or operation parameters include: number of tracks at section stations, storage capacity, number of humps at technical stations, number of arrival and departure lines, number of shunting lines, technical inspection time and marshaling time.