A waterproof structure with cantilever end of pile foundation at high and low spans and its construction method
By using a waterproof structure in the high and low span pile foundation, the waterproof layer damage and tear caused by the difference in settlement is solved, and the structural stability and the integrity of the waterproof layer are achieved.
Patent Information
- Application Number
- CN202411186561.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-08-28
AI Technical Summary
The settlement of high and low span foundations under shallow foundations and deep foundations leads to the risk of damage and tearing of the waterproof layer, and the protective layer of the steel bars on the outer side of the structural exterior wall is uneven, which easily leads to stress changes and cracks.
Adopt a waterproof structure with high and low spans of pile foundation cantilever ends, including shallow foundation area, deep foundation area, pile foundation, leveling layer, bonding layer, extruded polystyrene plate layer, crack-resistant layer and waterproof layer, through the pile foundation Set up the counter-sticking method of waterproofing layer to solve the problems of settlement difference and damage to waterproofing layer.
The bearing capacity of the shallow foundation area is improved through the installation of pile foundations, and the sliding design of the waterproof layer and the crack-resistant layer avoids tearing of the waterproof layer, which is convenient to construct and ensures the integrity of the waterproof layer.
Smart Images

Figure CN118704528B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground waterproofing, and in particular to a cantilever end reverse-sticking waterproofing structure of a pile foundation at a high-low span and a construction method thereof. Background Art
[0002] As the shelf life of waterproofing projects increases, the projects need to fully consider the hidden dangers of waterproofing in the future and design them in advance during structural construction. The high-low span foundation setting can meet the needs of different underground spaces of adjacent buildings, but due to the different settlements under shallow foundations and deep foundations, there will be settlement differences, which will cause damage to the waterproof layer and may cause the risk of waterproof tearing. In addition, the steel bar protective layer on the outside of the structural exterior wall is uneven, and some places are too thick, which changes the stress on the structure and easily causes the outside of the protective layer to crack. Summary of the invention
[0003] The invention provides a high-low span pile foundation cantilever end reverse-sticking waterproof structure and a construction method thereof, which are used to solve the technical problems of high-low span foundation treatment, waterproof layer installation and settlement difference treatment.
[0004] To achieve the above object, the present invention adopts the following technical solutions:
[0005] A cantilever end reverse-attached waterproof structure of a pile foundation at a high-low span, comprising a shallow foundation area, a deep foundation area arranged on one side of the shallow foundation area, a pile foundation arranged in the shallow foundation area, a leveling layer arranged outside the pile foundation, a bonding layer arranged outside the leveling layer, an extruded polystyrene board layer arranged outside the bonding layer, an anti-cracking layer arranged outside the extruded polystyrene board layer, a waterproof layer arranged outside the anti-cracking layer, and an underground outer wall arranged outside the waterproof layer;
[0006] The top surfaces of the shallow foundation area and the deep foundation area are arranged in a step-like manner;
[0007] The pile foundations are arranged at intervals in the shallow foundation area, and at least one row of pile foundations is arranged at a location where the shallow foundation area and the deep foundation area change in height, and the pile foundations of this row of pile foundations at the location where the height changes also serve as slope protection piles;
[0008] The waterproof layer is fixedly connected to the anti-cracking layer, and the anti-cracking layer and the extruded polystyrene board layer can slide against each other under foundation settlement.
[0009] Furthermore, the top plate of the top surface of the shallow foundation area and the underground outer wall below are in a reinforced structure, and the shallow foundation area and the deep foundation area are integrally reinforced and connected by pile foundations.
[0010] Furthermore, the pile foundation is divided into two categories: inner pile foundation and outer pile foundation; the outer pile foundation is set at the height change point between the shallow foundation area and the deep foundation area, and the inner pile foundation is set on the inner side of the outer pile foundation; the outer pile foundation also serves as slope protection piles.
[0011] Furthermore, the pile foundation is a CFG pile, a concrete pile or a gravel pile; the bottom of the pile foundation extends downward into the deep foundation area.
[0012] Furthermore, the outer pile foundation includes a pile fixing section and a pile cantilever section. The pile fixing section is the outer pile foundation located within the deep foundation area, and the pile cantilever section is the height change section between the shallow foundation area and the deep foundation area. The horizontal spacing between the pile cantilever section and the underground outer wall is not less than 300 mm.
[0013] Furthermore, the leveling layer is a fine stone concrete layer, the inner side of the leveling layer is fixedly connected to the outer pile foundation, and the outer side of the leveling layer is flush with and connected to a bonding layer; a steel mesh or a reinforcing rib layer is also provided in the leveling layer;
[0014] An anti-cracking layer is arranged on the outside of the extruded polystyrene board layer, and a waterproof layer is arranged on the outside of the anti-cracking layer; the waterproof layer comprises a self-adhesive layer and a modified asphalt waterproof coiled material layer; and a plain cement slurry roughening and throwing slurry layer is arranged on the outside of the waterproof layer.
[0015] Furthermore, a brick wall layer is provided between the extruded polystyrene board layer and the waterproof layer. The brick wall layer is formed by stacking blocks and includes structural columns arranged at intervals. Steel bars are also provided between the blocks.
[0016] Furthermore, when the outer pile foundation is cast in the corresponding leveling layer, a tension bolt assembly is also connected accordingly, and a gap is reserved between the supported formwork and the underground outer wall.
[0017] Furthermore, the construction method of the cantilever end of the pile foundation at the high and low spans is specifically carried out in the following steps:
[0018] Step 1: First construct the shallow foundation area and deep foundation area of the high-low span building. The shallow foundation area is constructed with pile foundation according to the foundation treatment design requirements; the outer row of pile foundations is the outer pile foundation, which is located at the change point between the shallow foundation area and the deep foundation area and also serves as slope protection piles;
[0019] Step 2: Support a template outside the external pile foundation, and connect a tension bolt assembly between the template on one side and the external pile foundation; wherein the template is a multi-layer board and is supported and cast in layers in the vertical direction; the tension bolt assembly comprises a tension screw and a tension nut, wherein one end of the tension screw is fixed on the external pile foundation, and the other end passes through the template and is fixed by the tension nut;
[0020] Step 3: Pour fine stone concrete between the formwork and the external pile foundation to construct a leveling layer. The leveling layer is flush with the side of the underground external wall and the flatness meets the design requirements;
[0021] Step 4: an adhesive layer is arranged on the outside of the leveling layer, and an extruded polystyrene board layer is connected at the adhesive layer, and an anti-cracking layer is arranged on the outside of the extruded polystyrene board layer; the anti-cracking layer and the extruded polystyrene board layer are relatively slidably arranged, and the sliding displacement size corresponds to the settlement difference of the shallow foundation area and the deep foundation area;
[0022] Step 5: A waterproof layer is arranged outside the anti-cracking layer. The waterproof layer extends from the top surface of the deep foundation along the change between the shallow foundation area and the deep foundation area to the top surface of the shallow foundation; the top plate of the top surface of the shallow foundation area and the underground outer wall plus axil structure below are arranged in an inverted triangle;
[0023] Step six: the waterproof layer includes a self-adhesive layer and a modified asphalt waterproof membrane layer. The self-adhesive layer is first fixedly connected to the anti-cracking layer, and the modified asphalt waterproof membrane layer is connected to the self-adhesive layer; then a plain cement slurry roughening and throwing layer is arranged on the outside of the modified asphalt waterproof membrane layer, and then the underground exterior wall is constructed.
[0024] Furthermore, when the distance between the inner side surface of the underground outer wall and the inner side surface of the pile foundation is greater than 300 mm, a brick wall layer is arranged outside the extruded polystyrene board layer; the brick wall layer is formed by stacking blocks and includes structural columns arranged at intervals, and steel bars are also arranged between the blocks.
[0025] The beneficial effects of the present invention are embodied in:
[0026] 1) The present invention is conducive to ensuring the bearing capacity of the bottom of the shallow foundation by setting the pile foundation below the shallow foundation area; and the outermost layer of the pile foundation also serves as a slope protection pile, which is conducive to ensuring the force at the change point of the shallow foundation and the deep foundation; in addition, the outer pile foundation is also used to fix the tension bolt assembly of the support formwork;
[0027] 2) The present invention not only compensates for the uneven surface of the structure at the outer pile foundation by setting the leveling layer, but also provides a basis for the flatness of the extruded polystyrene board layer; in addition, reinforcing ribs can be set in the leveling layer to ensure the overall strength;
[0028] 3) The present invention provides an extruded polystyrene board layer, which is conducive to forming a sliding layer when uneven settlement of high and low foundations occurs, thereby avoiding tearing and damage to the waterproof layer;
[0029] 4) The present invention can be carried out without waiting for the exterior wall to be constructed by pasting the waterproof layer on the anti-cracking layer, which is not only convenient for construction but also conducive to ensuring the integrity of the waterproof layer; and the waterproof layer and the extruded polystyrene board layer can slide and move relative to each other on the anti-cracking layer and are not easily damaged.
[0030] Other features and advantages of the present invention will be set forth in the following description, and in part will become apparent from the description, or may be understood by practicing the present invention; the main purpose and other advantages of the present invention may be realized and obtained through the solutions particularly pointed out in the description. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a vertical section view of the waterproof structure with the cantilever end of the pile foundation at the high and low spans;
[0032] Figure 2 It is a horizontal cross-section of the waterproof structure of the cantilever end of the pile foundation at the high and low spans;
[0033] Figure 3 It is a vertical section view of the formwork, tension bolt assembly and its connection structure;
[0034] Figure 4 It is a horizontal section view of the formwork, tension bolt assembly and its connection structure;
[0035] Figure 5 It is a schematic diagram of the horizontal section of the reverse-sticking waterproof structure including the brick wall layer.
[0036] Figure numbers: 1-shallow foundation area, 2-deep foundation area, 3-pile foundation, 31-pile fixing section, 32-pile cantilever section, 4-underground exterior wall, 5-leveling layer, 6-extruded polystyrene board layer, 7-adhesive layer, 8-anti-cracking layer, 9-waterproof layer, 10-formwork, 11-tension bolt assembly, 111-tension screw, 112-tension nut, 12-brick wall layer. DETAILED DESCRIPTION
[0037] Take a high-low span building as an example. Part of the main building is connected to the underground garage, with 2 underground floors and 3 underground floors, and part of the structure has only 1 underground floor. This structure forms a gusset structure at the top plate and wall position of the underground floor structure to support the shallow foundation structure under the natural foundation. In order to ensure the stability of the structure at the shallow foundation position, this project sets the natural foundation as a CFG pile foundation, and changes the pile at the intersection with the deep foundation to a cantilever pile to increase its depth. For the structural safety of the shallow foundation, the distance between the pile and the deep foundation is shortened to 300mm. This project is a high-low span foundation. The shallow foundation position at the underground floor is a CFG pile, which has a settlement difference with the natural foundation of the underground floor 3. In order to avoid side friction and damage to the waterproof layer due to uneven settlement, the waterproof structure is constructed by the cantilever end of the pile foundation at the high-low span.
[0038] Combination Figures 1 to 5As shown, a cantilevered end reverse-sticking waterproof structure of a pile foundation at a high-low span comprises a shallow foundation area 1, a deep foundation area 2 arranged on one side of the shallow foundation area 1, a pile foundation 3 arranged in the shallow foundation area 1, a leveling layer 5 arranged on the outside of the pile foundation 3, a bonding layer 7 arranged on the outside of the leveling layer 5, an extruded polystyrene board layer 6 arranged on the outside of the bonding layer 7, an anti-cracking layer 8 arranged on the outside of the extruded polystyrene board layer 6, a waterproof layer 9 arranged on the outside of the anti-cracking layer 8, and an underground outer wall 4 arranged on the outside of the waterproof layer 9; the top surfaces of the shallow foundation area 1 and the deep foundation area 2 are arranged in a step-like shape; the pile foundations 3 are arranged at intervals in the shallow foundation area 1, and at least one row of pile foundations 3 is arranged at a height change position between the shallow foundation area 1 and the deep foundation area 2, and the pile foundations 3 of this row of pile foundations 3 at the height change position also serve as slope protection piles; the waterproof layer 9 and the extruded polystyrene board layer 6 can slide against each other under foundation settlement.
[0039] In this embodiment, the top plate of the top surface of the shallow foundation area 1 and the underground outer wall 4 below are in a reinforced structure, and the shallow foundation area 1 and the deep foundation area 2 are integrally reinforced and connected by pile foundations 3 .
[0040] In this embodiment, the pile foundation 3 is divided into two types: inner pile foundation 3 and outer pile foundation 3; the outer pile foundation 3 is arranged at the height change position of the shallow foundation area 1 and the deep foundation area 2, and the inner pile foundation 3 is arranged on the inner side of the outer pile foundation 3; the outer pile foundation 3 also serves as a slope protection pile; the pile foundation 3 is a CFG pile, a concrete pile or a gravel pile; the bottom of the pile foundation 3 extends downward into the deep foundation area 2.
[0041] In this embodiment, the outer pile foundation 3 includes a pile fixing section 31 and a pile cantilever section 32. The pile fixing section 31 is the outer pile foundation 3 located within the deep foundation area 2, and the pile cantilever section 32 is the height change section between the shallow foundation area 1 and the deep foundation area 2; the horizontal spacing between the pile cantilever section 32 and the underground outer wall 4 is not less than 300 mm.
[0042] In this embodiment, the leveling layer 5 is a fine stone concrete layer, the inner side of the leveling layer 5 is fixedly connected to the outer pile foundation 3, and the outer side of the leveling layer 5 is flush and connected with a bonding layer 7; a steel mesh or a reinforcing rib layer is also provided in the leveling layer 5; the leveling layer 5 is made of 230mm thick C20 fine stone concrete. The bonding layer 7 is formed by 8mm thick special bonding mortar.
[0043] In this embodiment, an anti-cracking layer 8 is arranged on the outside of the extruded polystyrene board layer 6, and a waterproof layer 9 is arranged on the outside of the anti-cracking layer 8; the waterproof layer 9 includes a self-adhesive layer and a modified asphalt waterproof membrane layer; the outside of the waterproof layer 9 is arranged with a plain cement slurry roughening and throwing slurry layer. The extruded polystyrene board layer 6 is a 50mm thick B1 grade extruded polystyrene board 20kg / m 3 The anti-cracking layer 8 is made of 5mm thick anti-cracking mortar. The self-adhesive layer is 3mm thick, and the modified asphalt waterproofing membrane layer is 4mm thick SBS modified asphalt waterproofing membrane. The modified asphalt waterproofing membrane is hot-melt pasted, and then a 2mm waterproofing cement slurry protective layer is sprayed, and then the underground exterior wall is constructed by single-sided formwork.
[0044] In this embodiment, a brick wall layer 12 is provided between the extruded polystyrene board layer 6 and the waterproof layer 9. The brick wall layer 12 is formed by stacking blocks and includes structural columns arranged at intervals. Steel bars are also provided between the blocks.
[0045] In this embodiment, when the outer pile foundation 3 is cast in the corresponding leveling layer 5, a tension bolt assembly 11 is also connected, and a gap is reserved between the supported formwork 10 and the underground outer wall 4. The tension bolt assembly 11 includes a tension screw rod 111 and a tension nut 112, wherein the tension screw rod 111 is made of M16 bolts, with a horizontal spacing of @1000 and a vertical spacing of @400; the tension of a single bolt is 16.847kN.
[0046] In this embodiment, the template 10 is a multilayer board with a thickness of 18 mm, and a secondary keel is arranged on the outside of the template 10. The secondary keel includes 40×80 wooden square @250 and φ48×3.0 double steel pipe @400.
[0047] Combination Figures 1 to 5 As shown in the figure, the construction method of the waterproof structure of the cantilever end of the pile foundation at the high and low spans is as follows:
[0048] Step 1: First construct the shallow foundation area 1 and the deep foundation area 2 of the high-low span building, wherein the shallow foundation area 1 is constructed with pile foundation 3 according to the foundation treatment design requirements; the outer row of pile foundation 3 is the outer pile foundation 3, which is located at the change point of the shallow foundation area 1 and the deep foundation area 2 and also serves as slope protection piles.
[0049] Step 2: Support the template 10 outside the external pile foundation 3, and connect the template 10 on one side to the external pile foundation 3 with a tension bolt assembly 11; wherein the template 10 is a multi-layer board and is supported and cast in layers in the vertical direction. The tension bolt assembly 11 includes a tension screw rod 111 and a tension nut 112, wherein one end of the tension screw rod 111 is fixed to the external pile foundation 3, and the other end passes through the template 10 and is fixed by the tension nut 112.
[0050] Step 3: pour fine stone concrete between the formwork 10 and the outer pile foundation 3 to construct a leveling layer 5. The leveling layer 5 is flush with the side surface adjacent to the underground outer wall 4 and the flatness meets the design requirements.
[0051] Step 4: an adhesive layer is arranged on the outside of the leveling layer 5, and an extruded polystyrene board layer 6 is connected at the adhesive layer; an anti-cracking layer 8 is arranged on the outside of the extruded polystyrene board layer 6; the anti-cracking layer 8 and the extruded polystyrene board layer 6 are slidably arranged relative to each other, and the size of the sliding displacement corresponds to the settlement difference of the shallow foundation area 1 and the deep foundation area 2.
[0052] Among them, when the distance between the inner side of the underground outer wall 4 and the inner side of the pile foundation 3 is greater than 300 mm, a brick wall layer 12 is arranged on the outside of the extruded polystyrene board layer 6; the brick wall layer 12 is made of stacked blocks and includes structural columns arranged at intervals, and steel bars are also arranged between the blocks.
[0053] like Figure 5 As shown, a 30mm thick B1 grade extruded polystyrene board of 20kg / m3 is set on the back of the brick wall layer 12; the brick wall layer 12 is a 240 thick lime sand brick wall; the size of the structural column is 240×240mm, the spacing is 4 meters, the main reinforcement is 4φ12, and the stirrups are φ8@200; the ring beam is 240×240mm, the spacing is 4 meters; a 20mm thick premixed mortar plaster layer is also set on the outside of the brick wall layer 12.
[0054] Step 5. A waterproof layer 9 is arranged outside the anti-cracking layer 8. The waterproof layer 9 extends from the top surface of the deep foundation along the change point between the shallow foundation area 1 and the deep foundation area 2 to the top surface of the shallow foundation; the top plate of the top surface of the shallow foundation area 1 and the axil structure of the underground outer wall 4 below are arranged in an inverted triangle.
[0055] Step six, the waterproof layer 9 includes a self-adhesive layer and a modified asphalt waterproof membrane layer. The self-adhesive layer is first fixedly connected to the anti-cracking layer 8, and the modified asphalt waterproof membrane layer is connected to the self-adhesive layer; then a plain cement slurry roughening and throwing layer is arranged on the outside of the modified asphalt waterproof membrane layer, and then the underground exterior wall 4 is constructed.
[0056] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that a technician familiar with the technical field can think of within the technical scope disclosed in the present invention should be covered within the protection scope of the present invention.
Claims
1. A construction method for a waterproof structure with a cantilever end of a pile foundation at a high and low span, characterized in that: The invention comprises a shallow foundation area (1), a deep foundation area (2) arranged on one side of the shallow foundation area (1), a pile foundation (3) arranged in the shallow foundation area (1), a leveling layer (5) arranged on the outside of the pile foundation (3), an adhesive layer (7) arranged on the outside of the leveling layer (5), an extruded polystyrene board layer (6) arranged on the outside of the adhesive layer (7), an anti-cracking layer (8) arranged on the outside of the extruded polystyrene board layer (6), a waterproof layer (9) arranged on the outside of the anti-cracking layer (8), and an underground exterior wall (4) arranged on the outside of the waterproof layer (9); The top surfaces of the shallow foundation area (1) and the deep foundation area (2) are arranged in a stepped shape; The pile foundations (3) are arranged at intervals in the shallow foundation area (1), and at least one row of pile foundations (3) is arranged at a location where the shallow foundation area (1) and the deep foundation area (2) have different heights, and the pile foundations (3) in this row of pile foundations (3) at the location where the heights change also serve as slope protection piles; The waterproof layer (9) is fixedly connected to the anti-cracking layer (8), and the anti-cracking layer (8) and the extruded polystyrene board layer (6) can slide against each other under foundation settlement; An anti-cracking layer (8) is arranged on the outside of the extruded polystyrene board layer (6), and a waterproof layer (9) is arranged on the outside of the anti-cracking layer (8); the waterproof layer (9) comprises a self-adhesive layer and a modified asphalt waterproof coiled material layer; a plain cement slurry roughening and throwing slurry layer is arranged on the outside of the waterproof layer (9); A brick wall layer (12) is also provided between the extruded polystyrene board layer (6) and the waterproof layer (9), wherein the brick wall layer (12) is formed by stacking blocks and comprises structural columns arranged at intervals, and steel bars are also provided between the blocks; The bottom of the pile foundation (3) extends downward into the deep foundation area (2); the pile foundation (3) is divided into two types: an inner pile foundation and an outer pile foundation; the outer pile foundation is arranged at a location where the height of the shallow foundation area (1) and the deep foundation area (2) changes, and the inner pile foundation is arranged on the inner side of the outer pile foundation; the outer pile foundation also serves as a slope protection pile; The external pile foundation comprises a pile fixing section (31) and a pile cantilever section (32); the pile fixing section (31) is the external pile foundation located within the deep foundation area (2), and the pile cantilever section (32) is the height variation section between the shallow foundation area (1) and the deep foundation area (2); The construction method of the waterproof structure of the cantilever end of the pile foundation at the high and low spans is characterized by the following specific steps: Step 1: First, construct the shallow foundation area (1) and the deep foundation area (2) of the high-low span building, wherein the shallow foundation area (1) is constructed with pile foundations (3) according to the design requirements of the foundation treatment; the outer row of pile foundations (3) is the outer pile foundation, which is located at the transition point between the shallow foundation area (1) and the deep foundation area (2) and also serves as slope protection piles; Step 2: supporting a template (10) outside the external pile foundation, and connecting a tension bolt assembly (11) between the template (10) on one side and the external pile foundation; wherein the template (10) is a multi-layer board and is supported and cast in layers in the vertical direction; the tension bolt assembly (11) comprises a tension screw rod (111) and a tension nut (112), wherein one end of the tension screw rod (111) is fixed to the external pile foundation, and the other end passes through the template (10) and is fixed by the tension nut (112); Step 3: pour fine stone concrete between the formwork (10) and the external pile foundation to construct a leveling layer (5), wherein the leveling layer (5) is flush with the side surface of the underground external wall (4) and the flatness meets the design requirements; Step 4: an adhesive layer is arranged on the outside of the leveling layer (5), and an extruded polystyrene board layer (6) is connected to the adhesive layer, and an anti-cracking layer (8) is arranged on the outside of the extruded polystyrene board layer (6); the anti-cracking layer (8) and the extruded polystyrene board layer (6) are slidably arranged relative to each other, and the size of the slidable displacement corresponds to the settlement difference between the shallow foundation area (1) and the deep foundation area (2); Step 5: a waterproof layer (9) is arranged outside the anti-cracking layer (8); the waterproof layer (9) extends from the top surface of the deep foundation along the change point between the shallow foundation area (1) and the deep foundation area (2) to the top surface of the shallow foundation; the top plate of the top surface of the shallow foundation area (1) and the axil structure of the underground outer wall (4) below are arranged in an inverted triangle; Step 6: The waterproof layer (9) includes a self-adhesive layer and a modified asphalt waterproofing membrane layer. The self-adhesive layer is first fixedly connected to the anti-cracking layer (8), and the modified asphalt waterproofing membrane layer is connected to the self-adhesive layer; then a plain cement slurry roughening and throwing layer is arranged on the outer side of the modified asphalt waterproofing membrane layer, and then the underground exterior wall (4) is constructed.
2. The construction method of a high-low span pile foundation cantilever end reverse-attached waterproof structure as claimed in claim 1, characterized in that: The top plate of the top surface of the shallow foundation area (1) and the underground outer wall (4) below form a gusseted structure, and the shallow foundation area (1) and the deep foundation area (2) are integrally reinforced and connected via pile foundations (3).
3. The construction method of a high-low span pile foundation cantilever end reverse-attached waterproof structure as claimed in claim 1, characterized in that: The pile foundation (3) is a CFG pile, a concrete pile or a gravel pile.
4. The construction method of a high-low span pile foundation cantilever end reverse-attached waterproof structure as claimed in claim 1, characterized in that: The horizontal distance between the pile cantilever section (32) and the underground outer wall (4) is not less than 300 mm.
5. The construction method of a high-low span pile foundation cantilever end reverse-attached waterproof structure as claimed in claim 1, characterized in that: The leveling layer (5) is a fine stone concrete layer, the inner side of the leveling layer (5) is fixedly connected to the outer pile foundation, and the outer side of the leveling layer (5) is flush with and connected to a bonding layer (7); a reinforcing rib layer is also provided in the leveling layer (5).
6. The construction method of the cantilever end reverse-attached waterproof structure of the pile foundation at high and low spans as claimed in claim 1, characterized in that: When the outer pile foundation is cast in the corresponding leveling layer (5) and the formwork is supported, a tension bolt assembly (11) is also connected in a corresponding manner, and a gap is reserved between the supported formwork (10) and the underground outer wall (4).
7. A construction method for a high-low span pile foundation cantilever end reverse-attached waterproof structure as claimed in claim 1, characterized in that: When the distance between the inner side surface of the underground outer wall (4) and the inner side surface of the pile foundation (3) is greater than 300 mm, a brick wall layer (12) is arranged outside the extruded polystyrene board layer (6); the brick wall layer (12) is formed by stacking blocks and includes structural columns arranged at intervals, and steel bars are also arranged between the blocks.
Citation Information
Patent Citations
Construction method of basement outer wall
CN104452812A
Basement exterior wall waterproof slidable protection architecture
CN205857416U
Inner support deep foundation pit fertilizer groove under complex working conditions
CN212427108U