A method and device for processing data of winch hoist operation status monitoring

By clustering and time-series analysis of the hoisting speed, mineral weight, and motor torque data of the winch hoist, a hoisting anomaly index is constructed, which solves the problem of low detection accuracy in the existing technology and realizes comprehensive monitoring and fault identification of the winch hoist's operating status.

CN118708909BActive Publication Date: 2024-11-05SHENYANG KEWANGTONG INFORMATION TECH CO LTD
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411155332.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-05
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

Existing methods for monitoring the operation of winch hoists have failed to conduct in-depth analysis, resulting in insufficient data utilization and low detection accuracy. This may lead to the misjudgment of abnormal hoisting processes as normal, posing a safety hazard.

Method used

By collecting data on the hoisting speed, mineral weight, and motor torque of the winch hoist, cluster analysis and time-series segmentation are performed to construct speed duration differences, uniform speed anomalies, and speed-torque correlations. The hoisting anomaly index is then calculated to achieve comprehensive monitoring of the winch hoist's operating status.

Benefits of technology

It improves the accuracy of winch hoist operation status detection, enabling timely identification of potential faults and preventing safety accidents and production interruptions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118708909B_ABST
    Figure CN118708909B_ABST
Patent Text Reader

Abstract

The present application relates to the field of data processing technology, and specifically to a method and device for processing data for monitoring the operating status of a winch hoist, which specifically includes: constructing the speed duration difference of the hoist in each cycle according to the speed characteristics of the winch hoist during the lifting process, when the weight of the lifted mineral is relatively consistent; constructing the uniform lifting anomaly of the hoist in each cycle according to the speed consistency characteristics of the hoist during the uniform lifting process; constructing the speed-torque correlation according to the correlation characteristics between the lifting speed and the output torque; and finally constructing the lifting anomaly index of each cycle, and detecting the operating status of the winch hoist based on the anomaly degree of the lifting anomaly index of each cycle. Thereby, the winch hoist operating status monitoring data processing is realized, a more comprehensive monitoring of the hoist is achieved, the recognition accuracy of potential faults is improved, and the detection accuracy of the winch hoist operating status is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of data processing, and in particular to a method and device for processing data for monitoring the operating status of a winch hoist. Background Art

[0002] In the modern mining production process, mining winch hoists are key equipment for underground material transportation, and their operating status directly affects the safety and production efficiency of mine operations. With the continuous extension of mining depth, the underground working environment of winch hoists is becoming more and more complex, making it easy for mining winch hoists to fail in application. Through in-depth mining and analysis of data during the operation of winch hoists, it is not only helpful to grasp the health status of equipment in real time and timely warn of potential failures, but also to provide a scientific basis for equipment maintenance decisions, effectively avoiding safety accidents and production interruptions caused by equipment failures.

[0003] However, the existing winch hoist operation monitoring method usually only directly evaluates the overall duration of each lifting, and does not conduct a more in-depth analysis. It is possible that an abnormality occurs during the lifting process, but the lifting process with a consistent overall duration is evaluated as normal. There are problems such as insufficient data utilization and low accuracy in the detection of the winch hoist operation status. Summary of the invention

[0004] In order to solve the above technical problems, the purpose of this application is to provide a winch hoist operation status monitoring data processing method and device, the technical solution adopted is as follows:

[0005] In a first aspect, an embodiment of the present application provides a method for processing winch hoist operation status monitoring data, the method comprising the following steps:

[0006] (1) Collect the lifting speed, weight of lifted minerals, and output torque data of the lifting motor at each moment during the operation of the winch hoist;

[0007] (2) All cycles are clustered based on the mean value of the mineral weight data in each cycle to obtain each cluster; based on all the lifting speed data in each cycle combined with the time series segmentation algorithm, various speed subsequences and the duration of each speed subsequence are obtained for each cycle;

[0008] (3) Based on the difference in duration of similar speed subsequences in different periods in the same cluster, the duration difference of various speed subsequences in each period is obtained, and the speed duration difference of the elevator in each period is calculated;

[0009] (4) Based on the data changes and data dispersion in various speed subsequences of each period in the same cluster, the uniform speed lifting anomaly of the elevator in each period is obtained; based on the speed duration difference and the uniform speed lifting anomaly, the speed deviation coefficient of the elevator in each period is obtained;

[0010] (5) Based on the correlation between the lifting speed data and the output torque data in each cycle, the speed-torque correlation of the hoist in each cycle is obtained; based on the speed deviation coefficient and the speed-torque correlation, the lifting abnormality index of the hoist in each cycle is obtained;

[0011] (6) The operation status of the elevator is detected based on the abnormal lifting index of the elevator in each cycle.

[0012] In one embodiment, all the cycles are clustered based on the mean value of the mineral weight data in each cycle to obtain each cluster cluster; various speed subsequences and the duration of various speed subsequences in each cycle are obtained according to all the lifting speed data in each cycle in combination with the time series segmentation algorithm, including:

[0013] Calculating the mean of all mineral weight data of each period, inputting the mean of the mineral weight data of all periods into a clustering algorithm to cluster all periods to obtain clusters;

[0014] The various speed subsequences of each cycle include acceleration subsequence, high-speed uniform subsequence, deceleration subsequence, low-speed uniform subsequence and deceleration stop subsequence. The acquisition process of various speed subsequences is as follows:

[0015] In each cycle, the sequence composed of all the lifting speed data is recorded as the speed data sequence of the cycle; the speed data sequence is input into the time series segmentation algorithm to be divided into each subsequence; all the subsequences are arranged from large to small according to the subsequence length, and the top five subsequences are recorded as the acceleration subsequence, the high-speed uniform subsequence, the deceleration subsequence, the low-speed uniform subsequence and the deceleration stop subsequence according to the corresponding data collection time sequence;

[0016] The data length of each subsequence is taken as the duration of each subsequence.

[0017] In one embodiment, the duration difference of each type of speed subsequence in each period is obtained based on the duration difference of the same type of speed subsequences in different periods in the same cluster, and the speed duration difference of the elevator in each period is calculated, including:

[0018] The durations of the acceleration subsequence, high-speed uniform subsequence, deceleration subsequence, low-speed uniform subsequence, and deceleration stop subsequence are recorded as acceleration duration, high-speed uniform duration, deceleration duration, low-speed uniform duration, and deceleration stop duration, respectively;

[0019] In each cluster, the difference between the acceleration duration of any cycle and the acceleration duration of each of the remaining cycles is recorded as the first difference; the forward fusion result of all the first differences of any cycle is taken as the first acceleration duration difference of any cycle;

[0020] Record the forward fusion result of the first acceleration time difference of all the remaining cycles except the any one cycle as the first difference fusion value; record the difference between the first acceleration time difference of any one cycle and the first difference fusion value as the second acceleration time difference of any one cycle; determine the acceleration time difference degree of the elevator in any one cycle based on the first acceleration time difference and the second acceleration time difference of any one cycle, and the acceleration time difference degree of the elevator in any one cycle is positively correlated with the first acceleration time difference and the second acceleration time difference of any one cycle respectively;

[0021] Based on the differences in high-speed uniform speed duration, deceleration duration, low-speed uniform speed duration and deceleration stop duration in different periods in the same cluster, the high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and deceleration stop duration difference of the elevator in each period are obtained in the same way as the acceleration duration difference of the elevator in each period;

[0022] The forward fusion results of the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction stop duration difference of the elevator in each cycle are taken as the speed duration difference of the elevator in each cycle.

[0023] In one embodiment, the process of obtaining the abnormality of uniform lifting of the hoist in each cycle is as follows:

[0024] Based on the value range of the lifting speed data in the high-speed uniform speed subsequence of each period in the same cluster, the range standard of each period is obtained; based on the range standard of each period and the discrete degree of all elements in the high-speed uniform speed subsequence of each period, the high-speed uniform speed failure rate of the hoist in each period is constructed;

[0025] Based on the low-speed uniform speed subsequences of all cycles in the same cluster, the low-speed uniform speed unqualified rate of the elevator in each cycle is obtained by using the same calculation method as the high-speed uniform speed unqualified rate of the elevator in each cycle; the forward fusion result of the low-speed uniform speed unqualified rate and the high-speed uniform speed unqualified rate of the elevator in each cycle is recorded as the uniform speed lifting anomaly of the elevator in each cycle;

[0026] The speed deviation coefficient of the elevator in each cycle is determined based on the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly; the speed deviation coefficient of the elevator in each cycle is positively correlated with the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly.

[0027] In one embodiment, the process of obtaining the high-speed uniform speed unqualified rate of the elevator in each cycle is as follows:

[0028] In each cluster, the maximum and minimum values ​​of all the lifting speed data in the high-speed uniform speed subsequence of all the remaining cycles except any cycle are recorded as the upper speed limit and the lower speed limit respectively;

[0029] The maximum value and the minimum value of the speed data in the high-speed uniform speed subsequence of any period are recorded as the first maximum speed and the first minimum speed respectively;

[0030] The difference between the first maximum speed and the upper speed limit is recorded as a first difference; the difference between the first minimum speed and the lower speed limit is recorded as a second difference;

[0031] If the first difference and the second difference are both greater than or equal to 0, the sum of the first difference and the second difference is used as the range standard of any period; otherwise, the numerical control factor is used as the range standard of any period;

[0032] Calculate the discreteness of all elements in the high-speed uniform subsequence of each period;

[0033] The high-speed uniform speed failure rate of the elevator in each cycle is positively correlated with the discrete degree of each cycle, and negatively correlated with the range standard degree of each cycle.

[0034] In one embodiment, the process of obtaining the abnormality of uniform lifting of the hoist in each cycle is as follows:

[0035] Based on the low-speed uniform speed subsequences of all cycles in the same cluster, the low-speed uniform speed unqualified rate of the elevator in each cycle is obtained by adopting the same calculation method as the high-speed uniform speed unqualified rate of the elevator in each cycle; the forward fusion result of the low-speed uniform speed unqualified rate and the high-speed uniform speed unqualified rate of the elevator in each cycle is recorded as the uniform speed lifting anomaly of the elevator in each cycle.

[0036] In one embodiment, the process of obtaining the speed-torque correlation of each cycle is as follows:

[0037] In each cycle, the sequence composed of all output torque data is recorded as the torque data sequence of the cycle; the correlation between the speed data sequence and the torque data sequence in each cycle is calculated by a correlation algorithm;

[0038] For each cycle, the sequence composed of the torque data at the collection time corresponding to all elements in the acceleration subsequence is used as the torque increase subsequence of the torque data sequence; the sequence composed of the torque data at the collection time corresponding to all elements in the deceleration subsequence is used as the torque reduction subsequence of the torque data sequence; the sequence composed of the torque data at the collection time corresponding to all elements in the deceleration stop subsequence is used as the torque pre-stop subsequence of the torque data sequence;

[0039] Calculate the ratio between the range of speed data in the acceleration subsequence and the range of torque data in the torque increase subsequence, which is recorded as the first range ratio; calculate the ratio between the range of speed data in the deceleration subsequence and the range of torque data in the torque reduction subsequence, which is recorded as the second range ratio; calculate the ratio between the range of speed data in the speed reduction stop subsequence and the range of torque data in the torque pre-stop subsequence, which is recorded as the third range ratio; use the forward fusion results of the first, second and third range ratios as the increase ratio between speed and torque in each cycle;

[0040] For any one cycle, the forward fusion result of the increase ratio between the speed and the torque in all other cycles except the any one cycle is recorded as a second forward fusion value;

[0041] The absolute value of the correlation between the speed data sequence and the torque data sequence of any one period is recorded as the first absolute value; the absolute value of the difference between the increase ratio between the speed and torque of any one period and the second forward fusion value is calculated and recorded as the second absolute value; the sum of the second absolute value and the preset parameter adjustment coefficient is calculated and recorded as the first sum; the ratio of the first absolute value to the first sum is used as the speed-torque correlation of the elevator in any one period.

[0042] In one embodiment, the lifting abnormality index of the hoist in each cycle is: the ratio of the speed deviation coefficient of the hoist in each cycle to the speed-torque correlation.

[0043] In one embodiment, the detection of the operation state of the hoist based on the hoist abnormality index of the hoist in each cycle includes:

[0044] The latest data collection cycle is recorded as the detection cycle;

[0045] The lifting anomaly index of all cycles is used as the input of the LOF anomaly detection algorithm, and the output is the local outlier factor of the lifting anomaly index of each cycle; the normalized value of the local outlier factor corresponding to the detection cycle is obtained; if the normalized value is greater than the preset anomaly threshold, there is an anomaly in the winch hoist during the latest operation; otherwise, the winch hoist operates normally during the latest operation.

[0046] In the second aspect, an embodiment of the present application also provides a winch hoist operation status monitoring data processing device, including a memory, a processor, and a computer program stored in the memory and running on the processor, and when the processor executes the computer program, the steps of any one of the above methods are implemented.

[0047] The embodiments of the present application have at least the following beneficial effects:

[0048] The present application constructs the speed duration difference of the winch hoist in each cycle based on the speed characteristics of the winch hoist during the lifting process, under the condition that the weight of the lifted minerals is relatively consistent, so as to evaluate whether the lifting duration of each cycle meets the duration standard; constructs the uniform lifting anomaly of the hoist in each cycle based on the speed consistency characteristics of the hoist during the uniform lifting process, so as to evaluate whether the uniform speed in each cycle meets the speed standard; constructs the speed-torque correlation based on the correlation characteristics between the lifting speed and the output torque, and realizes the evaluation of the correlation between the speed and the torque; finally, constructs the lifting anomaly index of each cycle, and detects the operating status of the winch hoist based on the anomaly degree of the lifting anomaly index of each cycle; through in-depth analysis of the lifting speed data and evaluation of the correlation between the lifting speed and the output torque data, a more comprehensive monitoring of the hoist is achieved, the recognition accuracy of potential faults is improved, and the detection accuracy of the operating status of the winch hoist is improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present application or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0050] Figure 1 A flowchart of a method for processing data of winch hoist operation status monitoring provided by one embodiment of the present application;

[0051] Figure 2 It is a schematic diagram of lifting speed;

[0052] Figure 3 Schematic diagram of the steps for obtaining the speed duration difference of the elevator in each cycle. DETAILED DESCRIPTION

[0053] In order to further explain the technical means and effects adopted by the present application to achieve the predetermined invention purpose, the following is a detailed description of a winch hoist operation status monitoring data processing method and device proposed in the present application, its specific implementation method, structure, features and effects, in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.

[0054] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

[0055] The specific scheme of a winch hoist operation status monitoring data processing method and device provided by the present application is described in detail below with reference to the accompanying drawings.

[0056] See also Figure 1 , which shows a flowchart of a method for processing winch hoist operation status monitoring data provided by an embodiment of the present application, the method comprising the following steps:

[0057] Step S1, obtaining the operating data of the winch hoist at each moment during operation, including the hoisting speed of the hoist, the weight of the lifted mineral, and the output torque data of the lifting motor, constructing the speed data sequence and torque data sequence of each cycle based on the hoisting speed and output torque data of each cycle, and constructing the average weight sequence of the hoist based on the average weight of all minerals in each cycle.

[0058] The speed acquisition module, pressure acquisition module and torque measurement module of the winch hoist are all connected to the control system of the winch hoist, and are used to collect the lifting speed of the winch hoist, the weight of the lifted mineral, and the output torque data of the lifting motor at each moment. The time interval for data collection is y, and the operation process of lifting the mineral from underground to the ground is regarded as a data collection cycle, and a total of Y cycles of data collection are performed. It should be noted that the implementer can set the time interval and number of cycles of data collection according to the on-site environment when the winch hoist is operating. In this embodiment, the time interval and number of cycles of data collection are set to 1 second and 300 respectively.

[0059] The sequence of all lifting speed data obtained in each collection cycle in chronological order is recorded as the speed data sequence of each collection cycle; the sequence of all output torque data obtained in each collection cycle in chronological order is recorded as the torque data sequence of each collection cycle; the mean of the mineral weights at all times in each collection cycle is taken as the average mineral weight of each collection cycle, and the sequence composed of the average mineral weights of all collection cycles is recorded as the average weight sequence of the elevator.

[0060] Step S2, clustering all the cycles based on the average mineral weight to obtain clusters; segmenting the speed data sequence of each cycle to obtain the acceleration subsequence, high-speed uniform subsequence, deceleration subsequence, low-speed uniform subsequence and deceleration stop subsequence of each cycle, and the corresponding duration of each subsequence.

[0061] As an example, the step may include the following steps:

[0062] The winch hoist (hereinafter referred to as the hoist) has the following processes during the hoisting process: starting, accelerating, reaching the operating speed, stable operation, decelerating, running at a low and uniform speed, and decelerating and stopping. Figure 2As shown, the ordinate s is the lifting speed and the abscissa t is the time. Since the mining conditions and transport materials of each mine are different, the actual operating speed of each mine hoist will be determined by the manufacturer's technicians and the mine operators based on the actual conditions on site after the installation of the hoist. Once determined, it will be operated strictly in accordance with the regulations. Therefore, although the speed of the hoist will change during operation, the lifting time of each stage will not change significantly, and the maximum speed of each uniform operation is also relatively consistent, with strict requirements on time and speed.

[0063] (1) All periods are clustered based on their average mineral weight to obtain clusters:

[0064] When the weight of the mineral increases, the motor in the elevator must output a greater torque to overcome the increased gravity in order to lift the mineral. At the same time, when the weight of the mineral increases, it will also affect the acceleration time of the elevator, which is Figure 2 Therefore, the mineral weight can be clustered to achieve more accurate operation status monitoring.

[0065] The average mineral weight of all cycles is input into the K-means clustering algorithm to cluster all cycles to obtain each cluster cluster, wherein the optimal number of cluster clusters is obtained by the silhouette coefficient. Among them, the K-means clustering algorithm and the silhouette coefficient are well-known technologies, and the specific process is not repeated here. It should be noted that for the clustering of the average mineral weight of all cycles, this embodiment only provides a clustering method. There are many existing clustering methods. As other implementation methods, the implementer may also select other clustering algorithms for clustering, and this application does not impose any special restrictions on this.

[0066] (2) The speed data sequence of each cycle is divided into subsequences through the time series segmentation algorithm; based on the length of each subsequence and the data collection sequence, the acceleration subsequence, high-speed uniform speed subsequence, deceleration subsequence, low-speed uniform speed subsequence and deceleration stop subsequence of each cycle are obtained, and the corresponding duration of each subsequence is obtained:

[0067] (2.1) The speed data sequence of each cycle is used as the input of the BG (Bernaola Galvan) segmentation algorithm. The mutation data in the speed data sequence of each cycle is obtained through the BG segmentation algorithm. The mutation data is used as the segmentation point to segment the speed data sequence of each cycle to obtain each subsequence. Among them, the BG segmentation algorithm is a well-known technology, and the specific process is not repeated here. It should be noted that this embodiment only provides a time series segmentation method for the segmentation of the speed data sequence. There are many existing time series segmentation methods. As other implementation methods, the implementer can also select other time series segmentation algorithms to segment the speed data sequence. This application does not impose any special restrictions on this.

[0068] (2.2) For all subsequences of the speed data sequence of each period, all subsequences are arranged from large to small according to the subsequence length, and the first five subsequences are taken as the required subsequences; these five required subsequences are recorded as acceleration subsequence, high-speed uniform speed subsequence, deceleration subsequence, low-speed uniform speed subsequence and deceleration stop subsequence in ascending order of data acquisition time; the data length of each subsequence is taken as the duration of each subsequence, where the duration of these five required subsequences is recorded as acceleration duration, high-speed uniform speed duration, deceleration duration, low-speed uniform speed duration and deceleration stop duration.

[0069] Step S3, based on the differences in acceleration duration, high-speed uniform speed duration, deceleration duration, low-speed uniform speed duration and speed reduction and stop duration of different periods in the same cluster, obtain the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction and stop duration difference of the elevator in each period, and calculate the speed duration difference of the elevator in each period.

[0070] (1) Based on the difference between the acceleration durations of different cycles in the same cluster, the difference in the first acceleration duration of each cycle is obtained:

[0071] When the weight of the minerals is relatively consistent, the acceleration time of the elevator during operation should be relatively consistent.

[0072] In each cluster, the difference between the acceleration duration of any cycle and the acceleration duration of each of the remaining cycles is recorded as the first difference; and the forward fusion result of all the first differences of any cycle is taken as the first acceleration duration difference of any cycle.

[0073] Preferably, as an embodiment of the present application, the first difference may be the absolute value of the difference between the acceleration duration of any cycle and the acceleration duration of each of the remaining cycles; the forward fusion result of the first difference may be the average value of all the first differences of any cycle;

[0074] In other embodiments of the present application, the first difference may be the ratio of the acceleration duration corresponding to any cycle to the acceleration duration corresponding to each of the remaining cycles; the forward fusion result of the first difference may be the sum of all the first differences of any cycle.

[0075] (2) Based on the difference in the first acceleration time of each cycle, the difference in the acceleration time of the elevator in each cycle is obtained:

[0076] In each cluster, the forward fusion result of the first acceleration time difference of all the remaining cycles except the any one cycle is recorded as the first difference fusion value; the difference between the first acceleration time difference of any one cycle and the first difference fusion value is recorded as the second acceleration time difference of any one cycle; the acceleration time difference degree of the elevator in any one cycle is positively correlated with the first acceleration time difference and the second acceleration time difference of any one cycle, respectively.

[0077] Preferably, as an embodiment of the present application, the first difference fusion value may be an average value of the first acceleration time differences of all remaining cycles except the any cycle; the second acceleration time difference in any cycle may be an absolute value of the difference between the first acceleration time difference of any cycle and the first difference fusion value; the acceleration time difference degree of the elevator in any cycle may be the product of the first acceleration time difference and the second acceleration time difference of any cycle;

[0078] In other embodiments of the present application, the first difference fusion value may be a normalized value of the sum of the first acceleration duration differences of all remaining cycles except any one of the cycles; the second acceleration duration difference within any one of the cycles may be an absolute value of the ratio between the first acceleration duration difference of any one of the cycles and the first difference fusion value; the acceleration duration difference degree of the elevator in any one of the cycles may be the sum of the first acceleration duration difference and the second acceleration duration difference of any one of the cycles.

[0079] If the difference in the first acceleration time of any cycle is larger, it means that when the weight of the mineral is relatively consistent, the difference between the acceleration time of any cycle and the acceleration time in the previous data is larger, the less it meets the stability requirements of the lifting speed under standard conditions, and the possibility of problems is greater; if the difference in the second acceleration time is larger, the deviation between the acceleration time of any cycle and the acceleration time of the previous hoist is greater; at this time, if the difference in the acceleration time of the hoist in any cycle is larger, it means that the possibility of problems in the acceleration time stage of the acceleration data of the hoist in any cycle is greater.

[0080] (3) Based on the differences in high-speed uniform speed duration, deceleration duration, low-speed uniform speed duration and speed reduction and stop duration in different periods in the same cluster, the same acquisition method as the acceleration duration difference of the elevator in each period is adopted to obtain the high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction and stop duration difference of the elevator in each period.

[0081] (4) The forward fusion results of the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction stop duration difference of the elevator in each cycle are taken as the speed duration difference of the elevator in each cycle.

[0082] Preferably, as an embodiment of the present application, the speed duration difference of the elevator in each cycle can be the average value of the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and deceleration stop duration difference of the elevator in each cycle;

[0083] In other embodiments of the present application, the speed duration difference of the elevator in each cycle can be the normalized value of the sum of the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction and stop duration difference of the elevator in each cycle.

[0084] When the weight of the mineral is consistent, if there is no abnormality in the elevator, the lifting speed of each stage should be relatively consistent with the previous lifting speed, and the speed-duration difference of the elevator should be small; if there is an abnormality, the lifting speed may be inconsistent at a certain stage, which will lead to a large difference in the speed-duration of the elevator. If the speed-duration difference of the elevator is greater, it means that the lifting speed of each stage may be inconsistent, and the possibility of problems is greater.

[0085] The speed-duration difference of the hoist is used to evaluate whether the hoisting duration within the detection cycle meets the duration standard.

[0086] Step S4, based on the data changes and data discreteness in the high-speed uniform subsequence and the low-speed uniform subsequence of each period in the same cluster, the uniform lifting anomaly of the elevator in each period is obtained; according to the speed duration difference of the elevator in each period and the uniform lifting anomaly, the speed deviation coefficient of the elevator in each period is obtained.

[0087] Since the hoist has strict requirements on the lifting speed during operation, the lifting speed of the hoist is not allowed to fluctuate greatly during the uniform lifting process and must be within a certain speed range.

[0088] (1) Based on the value range of the speed data in the high-speed uniform subsequence of each period in the same cluster, the range standard of each period is obtained:

[0089] In each cluster, the maximum and minimum values ​​of all the lifting speed data in the high-speed uniform speed subsequence of all the remaining cycles except any cycle are recorded as the upper speed limit and the lower speed limit respectively;

[0090] The maximum value and the minimum value of the speed data in the high-speed uniform speed subsequence of any period are recorded as the first maximum speed and the first minimum speed respectively;

[0091] The difference between the first maximum speed and the upper speed limit is recorded as a first difference; the difference between the first minimum speed and the lower speed limit is recorded as a second difference;

[0092] If the first difference and the second difference are both greater than or equal to 0, it means that the lifting speed data in the high-speed uniform speed subsequence of any period is within the standard speed range, and the sum of the first difference and the second difference is used as the range standard of any period; if the first difference and the second difference are not greater than or equal to 0 at the same time, the numerical control factor is used as the range standard of any period, wherein the numerical control factor is a manually preset number less than 0. It should be noted that the implementer of the numerical control factor can set it by himself. In this embodiment, the numerical control factor is set to -10.

[0093] (2) Based on the range standard of each cycle and the discrete degree of all elements in the high-speed uniform speed subsequence of each cycle, the high-speed uniform speed failure rate of the elevator in each cycle is constructed:

[0094] Calculate the degree of dispersion of all elements in the high-speed uniform subsequence of each period. It should be noted that the degree of dispersion can be obtained by standard deviation, distribution variance, coefficient of variation, etc. In this embodiment, the distribution variance is used to calculate the degree of dispersion;

[0095] The high-speed uniform speed failure rate of the elevator in each cycle is positively correlated with the discrete degree of each cycle, and negatively correlated with the range standard degree of each cycle.

[0096] Preferably, as an embodiment of the present application, the calculation result of an exponential function with a natural constant as the base and a standard degree of each cycle range as the exponent is calculated; the high-speed uniform speed failure rate of the elevator in each cycle can be the ratio of the discrete degree of each cycle to the calculation result;

[0097] In other embodiments of the present application, the normalized value of the range standard of each cycle is calculated; the high-speed uniform speed failure rate of the elevator in each cycle can also be the ratio of the discrete degree of each cycle to the normalized value of the range standard.

[0098] If the speed of the high-speed uniform speed subsequence is not within the speed range of uniform speed lifting, the value of the high-speed uniform speed failure rate is extremely large; if it is within the range but the degree of fluctuation is large, it may also be a potential abnormality and further detection is required. At this time, the larger the value of the high-speed uniform speed failure rate, the greater the possibility of abnormality of the elevator during high-speed uniform speed lifting.

[0099] (3) Based on the low-speed uniform speed subsequences of all cycles in the same cluster, the low-speed uniform speed unqualified rate of the elevator in each cycle is obtained by using the same calculation method as the high-speed uniform speed unqualified rate of the elevator in each cycle; the forward fusion result of the low-speed uniform speed unqualified rate and the high-speed uniform speed unqualified rate of the elevator in each cycle is recorded as the uniform speed lifting anomaly of the elevator in each cycle. The larger the uniform speed lifting anomaly, the greater the possibility that the elevator has a problem.

[0100] It should be noted that the forward fusion result of the low-speed uniform speed failure rate and the high-speed uniform speed failure rate can be any result of multiplying, adding or averaging the two to achieve the forward fusion of the low-speed uniform speed failure rate and the high-speed uniform speed failure rate. In this embodiment, the average value of the low-speed uniform speed failure rate and the high-speed uniform speed failure rate is taken as the forward fusion result of the two.

[0101] (4) The speed deviation coefficient of the elevator in each cycle is positively correlated with the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly.

[0102] Preferably, as an embodiment of the present application, the speed deviation coefficient of the hoist in each cycle may be the product of the speed duration difference of the hoist in each cycle and the uniform speed lifting anomaly;

[0103] In some other embodiments of the present application, the speed deviation coefficient of the elevator in each cycle may also be the sum of the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly.

[0104] The larger the speed deviation coefficient is, the greater the possibility that the speed of the elevator will be abnormal during the lifting process. The speed deviation coefficient of the elevator is used to judge the lifting time and uniform lifting speed in each cycle to evaluate whether the lifting speed in each cycle meets the speed standard.

[0105] Step S5, based on the correlation between the speed data sequence and the torque data sequence in each cycle, the speed-torque correlation of the hoist in each cycle is obtained; based on the speed deviation coefficient and speed-torque correlation of the hoist in each cycle, the lifting abnormality index of the hoist in each cycle is obtained.

[0106] (1) Calculate the correlation between the speed data sequence and the torque data sequence in each cycle using the correlation algorithm:

[0107] There is a certain correlation between the torque of the hoist motor and the lifting speed. Specifically, when the weight of the mineral is consistent, if the lifting speed is to be increased, the motor needs to output a larger torque to accelerate the rotation of the drum, thereby increasing the lifting speed; when the lifting speed is uniform, the torque output by the motor will also be smooth to keep the drum rotating at a uniform speed; when the lifting speed gradually decreases to zero, the torque output by the motor also gradually decreases and eventually tends to zero. Therefore, there is a correlation between the speed data sequence and the torque data sequence, and the correlation is strong.

[0108] It should be noted that the correlation can be obtained by Pearson correlation coefficient, Spearman correlation coefficient and the like. In this embodiment, Pearson correlation coefficient is used to calculate the correlation.

[0109] (2) Based on the acceleration subsequence, deceleration subsequence and speed reduction stop subsequence in each cycle, combined with the corresponding relationship between the torque data and the speed data in each cycle, the torque increase subsequence, torque reduction subsequence and torque pre-stop subsequence in the torque data sequence are obtained:

[0110] For each cycle, the sequence composed of the torque data at the collection moment corresponding to all elements in the acceleration subsequence is used as the torque increase subsequence of the torque data sequence; the sequence composed of the torque data at the collection moment corresponding to all elements in the deceleration subsequence is used as the torque reduction subsequence of the torque data sequence; the sequence composed of the torque data at the collection moment corresponding to all elements in the speed reduction and stop subsequence is used as the torque pre-stop subsequence of the torque data sequence.

[0111] (3) Based on the torque increase subsequence, torque decrease subsequence and torque pre-stop subsequence, the increase ratio between the speed and torque of each cycle is obtained:

[0112] In each cycle, the ratio between the range of speed data in the acceleration subsequence and the range of torque data in the torque increase subsequence is calculated, which is recorded as the first range ratio; the ratio between the range of speed data in the deceleration subsequence and the range of torque data in the torque reduction subsequence is calculated, which is recorded as the second range ratio; the ratio between the range of speed data in the speed reduction stop subsequence and the range of torque data in the torque pre-stop subsequence is calculated, which is recorded as the third range ratio; the forward fusion results of the first, second and third range ratios are used as the increase ratio between speed and torque in each cycle.

[0113] Preferably, as an embodiment of the present application, the forward fusion result of the first, second and third range ratios may be an average value of the first, second and third range ratios.

[0114] The increase ratio can be used to evaluate the corresponding change degree between torque and speed.

[0115] (4) Based on the correlation between the speed data sequence and the torque data sequence of each cycle and the increase ratio between speed and torque, the speed-torque correlation of the hoist in each cycle is constructed:

[0116] For any one cycle, the forward fusion result of the increase ratio between the speed and the torque in all other cycles except the any one cycle is recorded as a second forward fusion value;

[0117] The absolute value of the correlation between the speed data sequence and the torque data sequence of any period is recorded as the first absolute value; the absolute value of the difference between the increase ratio of the speed and torque of any period and the second forward fusion value is calculated and recorded as the second absolute value; the sum of the second absolute value and the adjustment parameter coefficient is calculated and recorded as the first sum, wherein the adjustment parameter coefficient is an artificial preset value with a value greater than 0, and its function is to prevent the denominator from being 0 when the second absolute value is used as the denominator; the ratio of the first absolute value to the first sum is used as the speed-torque correlation of the elevator in any period.

[0118] Preferably, as an embodiment of the present application, the second forward fusion value may be an average value of the increase ratio between the speed and the torque in all the remaining cycles except the any one cycle.

[0119] When the speed-torque correlation is greater, it means that there is still a certain correlation between the speed and torque in the detection cycle, and the increase ratio between the speed and torque in any cycle is relatively consistent with the value of the second forward fusion value. The smaller the difference with the previous data, the greater the possibility of normal operation and no fault. When the torque-speed correlation is smaller, it means that the correlation between the speed and torque in the detection cycle is smaller, and the greater the difference with the previous data, the greater the possibility of problems.

[0120] (5) Based on the speed deviation coefficient and speed-torque correlation of the elevator in each cycle, the lifting abnormality index of the elevator in each cycle is obtained:

[0121] The ratio of the speed deviation coefficient of the hoist in each cycle to the speed-torque correlation is taken as the lifting abnormality index of the hoist in each cycle.

[0122] The larger the lifting abnormality index is, the greater the possibility that the hoist will have abnormal conditions during the lifting process, and timely warning and maintenance are required.

[0123] Step S6, performing detection based on the lifting abnormality index of the hoist in each cycle and the standard operation data of the hoist in a normal state.

[0124] (1) The latest data collection cycle is recorded as the detection cycle.

[0125] (2) The lifting anomaly index of all cycles is used as the input of the LOF anomaly detection algorithm, and the output is the local outlier factor of the lifting anomaly index of each cycle; the local outlier factor corresponding to the detection cycle is obtained, and the local outlier factor is normalized. If the normalized value is greater than the abnormal threshold, it is determined that a potential fault has occurred in the winch hoist during the latest operation, and an abnormal problem has occurred. An early warning and lifting stop processing are carried out in time, and the technicians are notified to carry out maintenance; if it is less than or equal to the abnormal threshold, it is determined that the winch hoist is operating normally during the latest operation. In this way, the operating status of the winch hoist is monitored. It should be noted that the implementer of the abnormal threshold can set it by himself. In this embodiment, the abnormal threshold can be set to 0.5.

[0126] The schematic diagram of lifting speed is as follows Figure 2 As shown; the schematic diagram of the steps for obtaining the speed duration difference of the elevator in each cycle is as follows Figure 3 shown.

[0127] Based on the same inventive concept as the above method, an embodiment of the present application also provides a winch hoist operating status monitoring data processing device, including a memory, a processor, and a computer program stored in the memory and running on the processor, and when the processor executes the computer program, it implements the steps of any one of the above-mentioned winch hoist operating status monitoring data processing methods.

[0128] In summary, the embodiment of the present application provides a method for processing data for monitoring the operating status of a winch hoist. According to the speed characteristics of the winch hoist during the lifting process, when the weight of the lifted mineral is relatively consistent, the speed duration difference of the hoist in each cycle is constructed to evaluate whether the lifting duration of each cycle meets the duration standard; according to the speed consistency characteristics of the hoist during the uniform lifting process, the uniform lifting anomaly of the hoist in each cycle is constructed to evaluate whether the uniform speed in each cycle meets the speed standard; according to the correlation characteristics between the lifting speed and the output torque, the speed-torque correlation is constructed to achieve the evaluation of the correlation between the speed and the torque; finally, the lifting anomaly index of each cycle is constructed, and the operating status of the winch hoist is detected based on the anomaly degree of the lifting anomaly index of each cycle; through in-depth analysis of the lifting speed data and evaluation of the correlation between the lifting speed and the output torque data, a more comprehensive monitoring of the hoist is achieved, the recognition accuracy of potential faults is improved, and the detection accuracy of the operating status of the winch hoist is improved.

[0129] It should be noted that the above-mentioned sequence of the embodiments of the present application is only for description and does not represent the advantages and disadvantages of the embodiments. The above-mentioned specific embodiments of the present application are described. In addition, the processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0130] The various embodiments in the present application are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

[0131] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the principles of the present application should be included in the protection scope of the present application.

Claims

1. A method for processing winch hoist operation status monitoring data, characterized in that: The method comprises the following steps: (1) Collect the lifting speed, weight of lifted minerals, and output torque data of the lifting motor at each moment during the operation of the winch hoist; (2) All cycles are clustered based on the mean value of the mineral weight data in each cycle to obtain each cluster; based on all the lifting speed data in each cycle combined with the time series segmentation algorithm, various speed subsequences and the duration of each speed subsequence are obtained for each cycle; (3) Based on the difference in duration of similar speed subsequences in different periods in the same cluster, the duration difference of various speed subsequences in each period is obtained, and the speed duration difference of the elevator in each period is calculated; (4) Based on the data changes and data dispersion in various speed subsequences of each period in the same cluster, the uniform speed lifting anomaly of the elevator in each period is obtained; based on the speed duration difference and the uniform speed lifting anomaly, the speed deviation coefficient of the elevator in each period is obtained; (5) Based on the correlation between the lifting speed data and the output torque data in each cycle, the speed-torque correlation of the hoist in each cycle is obtained; based on the speed deviation coefficient and the speed-torque correlation, the lifting abnormality index of the hoist in each cycle is obtained; (6) The operation status of the elevator is detected based on the abnormal lifting index of the elevator in each cycle.

2. A winch hoist operation status monitoring data processing method according to claim 1, characterized in that: The clustering is performed on all the periods based on the mean value of the mineral weight data in each period to obtain each cluster; According to all the speed data in each cycle combined with the time series segmentation algorithm, various speed subsequences and the duration of various speed subsequences in each cycle are obtained, including: Calculating the mean of all mineral weight data of each period, inputting the mean of the mineral weight data of all periods into a clustering algorithm to cluster all periods to obtain clusters; The various speed subsequences of each cycle include acceleration subsequence, high-speed uniform subsequence, deceleration subsequence, low-speed uniform subsequence and deceleration stop subsequence. The acquisition process of various speed subsequences is as follows: In each cycle, the sequence composed of all the lifting speed data is recorded as the speed data sequence of the cycle; the speed data sequence is input into the time series segmentation algorithm to be divided into each subsequence; all the subsequences are arranged from large to small according to the subsequence length, and the top five subsequences are recorded as the acceleration subsequence, the high-speed uniform subsequence, the deceleration subsequence, the low-speed uniform subsequence and the deceleration stop subsequence according to the corresponding data collection time sequence; The data length of each subsequence is taken as the duration of each subsequence.

3. A winch hoist operation status monitoring data processing method according to claim 2, characterized in that: The duration difference of each type of speed subsequence in each cycle is obtained based on the duration difference of the same type of speed subsequences in different cycles in the same cluster, and the speed duration difference of the elevator in each cycle is calculated, including: The durations of the acceleration subsequence, high-speed uniform subsequence, deceleration subsequence, low-speed uniform subsequence, and deceleration stop subsequence are recorded as acceleration duration, high-speed uniform duration, deceleration duration, low-speed uniform duration, and deceleration stop duration, respectively; In each cluster, the difference between the acceleration duration of any cycle and the acceleration duration of each of the remaining cycles is recorded as the first difference; the forward fusion result of all the first differences of any cycle is taken as the first acceleration duration difference of any cycle; Record the forward fusion result of the first acceleration time difference of all the remaining cycles except the any one cycle as the first difference fusion value; record the difference between the first acceleration time difference of any one cycle and the first difference fusion value as the second acceleration time difference of any one cycle; determine the acceleration time difference degree of the elevator in any one cycle based on the first acceleration time difference and the second acceleration time difference of any one cycle, and the acceleration time difference degree of the elevator in any one cycle is positively correlated with the first acceleration time difference and the second acceleration time difference of any one cycle respectively; Based on the differences in high-speed uniform speed duration, deceleration duration, low-speed uniform speed duration and deceleration stop duration in different periods in the same cluster, the high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and deceleration stop duration difference of the elevator in each period are obtained in the same way as the acceleration duration difference of the elevator in each period; The forward fusion results of the acceleration duration difference, high-speed uniform speed duration difference, deceleration duration difference, low-speed uniform speed duration difference and speed reduction stop duration difference of the elevator in each cycle are taken as the speed duration difference of the elevator in each cycle.

4. A method for processing winch hoist operation status monitoring data according to claim 2, characterized in that: The acquisition process of the uniform lifting anomaly of the hoist in each cycle is as follows: Based on the value range of the lifting speed data in the high-speed uniform speed subsequence of each period in the same cluster, the range standard of each period is obtained; based on the range standard of each period and the discrete degree of all elements in the high-speed uniform speed subsequence of each period, the high-speed uniform speed failure rate of the hoist in each period is constructed; Based on the low-speed uniform speed subsequences of all cycles in the same cluster, the low-speed uniform speed unqualified rate of the elevator in each cycle is obtained by using the same calculation method as the high-speed uniform speed unqualified rate of the elevator in each cycle; the forward fusion result of the low-speed uniform speed unqualified rate and the high-speed uniform speed unqualified rate of the elevator in each cycle is recorded as the uniform speed lifting anomaly of the elevator in each cycle; The speed deviation coefficient of the elevator in each cycle is determined based on the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly; the speed deviation coefficient of the elevator in each cycle is positively correlated with the speed duration difference of the elevator in each cycle and the uniform speed lifting anomaly.

5. A winch hoist operation status monitoring data processing method as claimed in claim 4, characterized in that: The process of obtaining the high-speed uniform speed failure rate of the elevator in each cycle is as follows: In each cluster, the maximum and minimum values ​​of all the lifting speed data in the high-speed uniform speed subsequence of all the remaining cycles except any cycle are recorded as the upper speed limit and the lower speed limit respectively; The maximum value and the minimum value of the speed data in the high-speed uniform speed subsequence of any period are recorded as the first maximum speed and the first minimum speed respectively; Recording a difference between the first maximum speed and the speed upper limit as a first difference; Recording the difference between the first minimum speed and the speed lower limit as a second difference; If the first difference and the second difference are both greater than or equal to 0, the sum of the first difference and the second difference is used as the range standard of any period; Otherwise, the numerical control factor is used as the range standard of any period; Calculate the discreteness of all elements in the high-speed uniform subsequence of each period; The high-speed uniform speed failure rate of the elevator in each cycle is positively correlated with the discrete degree of each cycle, and negatively correlated with the range standard degree of each cycle.

6. A winch hoist operation status monitoring data processing method as claimed in claim 4, characterized in that: The acquisition process of the uniform lifting anomaly of the hoist in each cycle is as follows: Based on the low-speed uniform speed subsequences of all cycles in the same cluster, the low-speed uniform speed unqualified rate of the elevator in each cycle is obtained by adopting the same calculation method as the high-speed uniform speed unqualified rate of the elevator in each cycle; the forward fusion result of the low-speed uniform speed unqualified rate and the high-speed uniform speed unqualified rate of the elevator in each cycle is recorded as the uniform speed lifting anomaly of the elevator in each cycle.

7. A winch hoist operation status monitoring data processing method according to claim 2, characterized in that: The process of obtaining the speed-torque correlation of each cycle is as follows: In each cycle, the sequence composed of all output torque data is recorded as the torque data sequence of the cycle; the correlation between the speed data sequence and the torque data sequence in each cycle is calculated by a correlation algorithm; For each cycle, a sequence composed of torque data at the acquisition time corresponding to all elements in the acceleration subsequence is used as a torque increase subsequence of the torque data sequence; a sequence composed of torque data at the acquisition time corresponding to all elements in the deceleration subsequence is used as a torque decrease subsequence of the torque data sequence; The sequence composed of the torque data at the acquisition time corresponding to all elements in the deceleration stop subsequence is used as the torque pre-stop subsequence of the torque data sequence; The ratio between the range of the speed data in the acceleration subsequence and the range of the torque data in the torque increase subsequence is calculated, which is recorded as the first range ratio; the ratio between the range of the speed data in the deceleration subsequence and the range of the torque data in the torque reduction subsequence is calculated, which is recorded as the second range ratio; Calculate the ratio between the range of speed data in the deceleration stop subsequence and the range of torque data in the torque pre-stop subsequence, and record it as the third range ratio; use the forward fusion result of the first, second and third range ratios as the increase ratio between speed and torque in each cycle; For any one cycle, the forward fusion result of the increase ratio between the speed and the torque in all other cycles except the any one cycle is recorded as a second forward fusion value; The absolute value of the correlation between the speed data sequence and the torque data sequence of any one period is recorded as the first absolute value; the absolute value of the difference between the increase ratio between the speed and torque of any one period and the second forward fusion value is calculated and recorded as the second absolute value; the sum of the second absolute value and the preset parameter adjustment coefficient is calculated and recorded as the first sum; the ratio of the first absolute value to the first sum is used as the speed-torque correlation of the elevator in any one period.

8. A method for processing winch hoist operation status monitoring data according to claim 2, characterized in that: The lifting abnormality index of the hoist in each cycle is: the ratio of the speed deviation coefficient of the hoist in each cycle to the speed-torque correlation.

9. A method for processing winch hoist operation status monitoring data according to claim 1, characterized in that: The detection of the operation state of the hoist based on the hoist abnormality index of the hoist in each cycle includes: The latest data collection cycle is recorded as the detection cycle; The lifting anomaly index of all cycles is used as the input of the LOF anomaly detection algorithm, and the output is the local outlier factor of the lifting anomaly index of each cycle; the normalized value of the local outlier factor corresponding to the detection cycle is obtained; if the normalized value is greater than the preset anomaly threshold, there is an anomaly in the winch hoist during the latest operation; otherwise, the winch hoist operates normally during the latest operation.

10. A winch hoist operation status monitoring data processing device, comprising a memory, a processor, and a computer program stored in the memory and running on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 9 are implemented.

Citation Information

Patent Citations

  • Mechanical arm dynamic offset monitoring system based on three-dimensional model coordinates

    CN116277161A

  • Unmanned elevator fault analysis and prediction system based on data analysis

    CN117105032A

  • Air compressor running state monitoring data processing method and device

    CN118332293A

  • Elevator control device and control method

    JP2018193161A

  • System monitoring method and apparatus

    US20170371757A1