A dam deformation monitoring method, device and equipment

By processing and regional division of dam deformation monitoring data and adjusting monitoring frequency and cycle, the problem of unreasonable dam deformation monitoring in the existing technology has been solved, the accuracy and safety of monitoring have been improved, resource waste has been reduced, and the realization of More reasonable monitoring resource allocation.

CN118708991BActive Publication Date: 2024-11-01SICHUAN JINGHENGXIN CONSTR ENG TESTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411203466.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-01
Estimated Expiration
2044-08-30

AI Technical Summary

Technical Problem

The existing dam deformation monitoring methods are unreasonable, resulting in serious deformation in some areas and mismatch in monitoring frequency and periods, and insufficient resource waste and monitoring accuracy.

Method used

By obtaining historical data of each monitoring point, eliminating the roughness, determining the historical damage degree and dividing the dam sub-region, adjusting the monitoring frequency and period according to the real-time damage degree and historical setting frequency, high-frequency short-term monitoring is carried out for high-deformed areas, low The deformation area is monitored for long-term periods of low frequency, and the monitoring point positions are adjusted for even distribution.

Benefits of technology

It improves the accuracy and safety of dam deformation monitoring, reduces resource waste, optimizes the allocation of monitoring resources, and enhances the convenience and safety of monitoring.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118708991B_ABST
    Figure CN118708991B_ABST
Patent Text Reader

Abstract

The present invention discloses a dam deformation monitoring method, device and equipment, including: obtaining the historical data to be processed of each monitoring point in the target dam within the historical time period, eliminating the gross errors in the historical data to be processed of each monitoring point, and obtaining the historical processed data of each monitoring point within the historical time period; determining the historical damage degree of the target dam according to the historical processed data of each monitoring point in the target dam within the historical time period; dividing the target dam according to the historical processed data of each monitoring point in the target dam within the historical time period, and obtaining a plurality of target dam sub-areas; determining the target monitoring frequency of the target dam sub-area; determining the target monitoring period of the target sub-dam; step S153, performing deformation monitoring of the target dam sub-area at the target monitoring frequency within the target monitoring period. The present invention belongs to the field of dam deformation monitoring. The present invention can improve the rationality of dam deformation monitoring.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of dam deformation monitoring, and in particular to a dam deformation monitoring method, device and equipment. Background Art

[0002] A dam is a man-made structure used to intercept and regulate water flow. Dams are usually built on rivers, streams or other water channels to block water flow, regulate water levels, generate electricity or irrigate. Dams can be made of concrete, earth and stone, reinforced concrete and other materials, and have important functions such as fixing water levels, controlling floods, and providing hydroelectric power.

[0003] At present, the monitoring of dams is usually an overall inspection. In other words, a unified monitoring frequency and monitoring cycle are used for each monitoring point of the dam, but the deformation (extreme degree of compression) of each part of the dam is different. Some areas are severely deformed, while some areas are not deformed to a small extent. It is obvious that it is not reasonable to use the same similar monitoring. Therefore, this application proposes a dam deformation monitoring method to monitor the dam more reasonably. Summary of the invention

[0004] The embodiments of the present application solve the technical problem of unreasonable monitoring methods in the prior art by providing a dam deformation monitoring method, device and equipment, and achieve the technical effect of improving the rationality of dam monitoring.

[0005] In a first aspect, the present application provides a dam deformation monitoring method, the method comprising:

[0006] Obtain the historical data to be processed of each monitoring point in the target dam within the historical time period, the historical data to be processed includes historical deformation and the mean value of environmental factors, the mean value of environmental factors includes the daily average point temperature and the daily average point pressure;

[0007] Eliminate the gross errors in the historical data to be processed at each monitoring point to obtain the historical processed data of each monitoring point in the historical time period;

[0008] Determine the historical damage degree of the target dam based on the historical processed data of each monitoring point in the target dam within the historical time period;

[0009] According to the historical processed data of each monitoring point in the target dam in the historical time period, the target dam is divided to obtain several target dam sub-areas;

[0010] For each target dam sub-area, steps S151-S153 are executed, including:

[0011] Step S151, determining a target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam;

[0012] Step S152, determining a target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam;

[0013] Step S153, performing deformation monitoring on the target dam sub-area at a target monitoring frequency within a target monitoring period.

[0014] Furthermore, according to the historical processed data of each monitoring point in the target dam in the historical time period, the target dam is divided into several target dam sub-areas, including:

[0015] Determine the monitoring scope of each monitoring point;

[0016] Determine the historical damage degree of each monitoring point based on the historical processed data of each monitoring point in the target dam within the historical time period;

[0017] According to the historical damage degree of each monitoring point and the historical damage degree of the target dam, the damage similarity corresponding to each monitoring point is determined;

[0018] According to the damage similarity corresponding to each monitoring point, the monitoring range of each monitoring point and the preset rules for similarity level division, the target dam sub-area corresponding to each similarity level is determined.

[0019] Furthermore, according to the historical processed data of each monitoring point in the target dam in the historical time period, the target dam is divided to obtain several target dam sub-areas, including:

[0020] Determine the monitoring scope of each monitoring point;

[0021] Determine the historical damage degree of each monitoring point based on the historical processed data of each monitoring point in the target dam within the historical time period;

[0022] When the sum of the historical damage degrees of several adjacent monitoring points in the target dam is within the preset damage degree division range, the target dam is divided once according to the monitoring ranges of several adjacent monitoring points to obtain a target dam sub-area.

[0023] Furthermore, it also includes:

[0024] Obtain an initial monitoring point location map of the target dam and determine the maximum adjustable range of each monitoring point, wherein the initial monitoring point location map includes the initial position of each monitoring point;

[0025] According to the initial position of the monitoring point and the real-time position of the monitoring point, determining whether there is a need to adjust the position of the monitoring point;

[0026] If it exists, then in the maximum adjustable range of the monitoring point, according to the positional relationship between the monitoring point and several adjacent monitoring points, with the goal of uniform adjacent distances and the shortest adjustment distance, determine the target adjustment position of the monitoring point in the maximum adjustable range;

[0027] The real-time position of the monitoring point in the target dam is adjusted to the target adjustment position.

[0028] Furthermore, the gross errors in the historical data to be processed of each monitoring point are eliminated to obtain the historical processed data of each monitoring point in the historical time period, including:

[0029] Determine the correlation relationship between each monitoring point in the target dam, the correlation relationship includes similar correlation relationship and non-similar correlation relationship;

[0030] Determine the data distances corresponding to the historical data to be processed of several monitoring points with similar correlation relationships;

[0031] The historical data to be processed corresponding to the data distance greater than the preset data distance is regarded as a gross error.

[0032] Furthermore, the formula for historical damage degree includes:

[0033]

[0034] Where R is the historical damage degree of the target dam, m is the number of monitoring points, is the maximum historical deformation, is the minimum historical deformation, is the historical deformation of the ith monitoring point, is the temperature damage degree of the ith monitoring point on the jth day, n is the number of days in the historical time period, is the pressure damage degree of the ith monitoring point on the jth day, , , are all weight factors.

[0035] Furthermore, regarding The formula includes:

[0036]

[0037] Where A is a constant, The average temperature of the i-th monitoring point in the historical period, is the daily average point temperature of the ith monitoring point on the jth day, is the highest temperature of the ith monitoring point in the historical time period.

[0038] Furthermore, regarding The formula includes:

[0039]

[0040] Where B is a constant, The average pressure of the i-th monitoring point in the historical time period, is the daily average point pressure of the ith monitoring point on the jth day, is the highest pressure of the ith monitoring point in the historical time period.

[0041] In a second aspect, the present application provides a dam deformation monitoring device, the device comprising:

[0042] An acquisition module is used to acquire historical data to be processed at each monitoring point in the target dam within a historical time period. The historical data to be processed include historical deformation and mean values ​​of environmental factors. The mean values ​​of environmental factors include daily average point temperature and daily average point pressure.

[0043] The elimination module is used to eliminate the gross errors in the historical data to be processed of each monitoring point, and obtain the historical processed data of each monitoring point in the historical time period;

[0044] A damage degree determination module is used to determine the historical damage degree of the target dam based on the historical processed data of each monitoring point in the target dam within a historical time period;

[0045] A division module is used to divide the target dam according to the historical processed data of each monitoring point in the target dam within the historical time period to obtain a number of target dam sub-areas;

[0046] The monitoring module is used to execute steps S151-S153 for each target dam sub-area, including:

[0047] Step S151, determining a target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam;

[0048] Step S152, determining a target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam;

[0049] Step S153, performing deformation monitoring on the target dam sub-area at a target monitoring frequency within a target monitoring period.

[0050] In a third aspect, the present application provides an electronic device, including:

[0051] processor;

[0052] a memory for storing processor-executable instructions;

[0053] The processor is configured to execute to implement a dam deformation monitoring method as provided in the first aspect.

[0054] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:

[0055] This application determines the monitoring range of each monitoring point and obtains the target dam sub-area through two ways of dividing the area, so that targeted monitoring can be carried out. Specifically, higher-frequency and shorter-period monitoring is carried out on areas affected by environmental factors and with higher deformation, thereby improving the safety of this area; for areas affected by environmental factors and with higher deformation, lower monitoring frequencies and longer monitoring periods are adopted, which reduces the waste of resources and improves the purpose of reasonable allocation of monitoring resources.

[0056] In addition, the present application can accurately determine the target monitoring frequency of the target dam sub-area through the real-time damage degree, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam. The monitoring period of the target dam sub-area can also be accurately determined through the target monitoring frequency, and the target dam sub-area is monitored at the target detection frequency and the target monitoring period, thereby improving the accuracy of dam deformation monitoring.

[0057] In addition, the dam is divided by [Method 1]. Although the sub-areas of the dam of the same level are not continuous, the monitoring points in the sub-areas of the same level are similarly affected by the environment and have similar deformation amounts. The same monitoring frequency and monitoring period are used for monitoring points with similar characteristics, and the accuracy and precision of deformation monitoring are higher.

[0058] By dividing the dam using [Method 2], the overall damage degree of each dam sub-area is similar. Although its accuracy may not be as good as that of Method 1, since the sub-areas are divided based on adjacent monitoring points, the accuracy difference is not large (the deformation degree of adjacent monitoring points is usually not too large, and it is also limited by the similarity of the overall damage degree). In addition, dividing according to Method [2] can connect the sub-areas of the target dam to form a whole, which can be convenient for relevant personnel to view and operate, and its convenience is higher.

[0059] This application also determines whether the monitoring point needs to be rearranged based on the location distance, and by setting the maximum adjustable range and taking the uniform adjacent distance and the shortest adjustment distance as the adjustment target, the monitoring point can determine the target adjustment position within the maximum adjustable range, thereby meeting the dam monitoring needs, ensuring the safety of dam monitoring, and reducing the work difficulty of relevant personnel.

[0060] In addition, the present application also provides a method for eliminating gross data errors. The neural network algorithm inputs the mean value of environmental factors to predict the deformation curve of each monitoring point of the target dam. It emphasizes the classification of the mean value of environmental factors, and predicts the deformation curve based on the classification of environmental factors, and eliminates gross data errors based on data distance. BRIEF DESCRIPTION OF THE DRAWINGS

[0061] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0062] Figure 1 A schematic flow chart of a dam deformation monitoring method provided for the application;

[0063] Figure 2 A schematic diagram of the layout of the monitoring points of the dam provided for the application;

[0064] Figure 3 A schematic diagram of the structure of a dam deformation monitoring device provided for the application;

[0065] Figure 4 A schematic diagram of the structure of an electronic device provided for application. DETAILED DESCRIPTION

[0066] The embodiment of the present application solves the technical problem of unreasonable dam deformation monitoring in the prior art by providing a dam deformation monitoring method.

[0067] The technical solution of the embodiment of the present application is to solve the above technical problems, and the overall idea is as follows:

[0068] A dam deformation monitoring method, the method comprising: obtaining historical data to be processed of each monitoring point in a target dam within a historical time period, the historical data to be processed including historical deformation and environmental factor mean values, the environmental factor mean values ​​including daily average point temperature and daily average point pressure; eliminating gross errors in the historical data to be processed of each monitoring point to obtain historical processed data of each monitoring point within a historical time period; determining the historical damage degree of the target dam according to the historical processed data of each monitoring point in the target dam within a historical time period; dividing the target dam according to the historical processed data of each monitoring point in the target dam within a historical time period to obtain a number of target dam sub-areas ; For each target dam sub-area, execute steps S151-S153, including: step S151, determining the target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time length, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam; step S152, determining the target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historical set monitoring frequency of the target dam, and the historical set monitoring period of the target dam; step S153, performing deformation monitoring on the target dam sub-area at the target monitoring frequency within the target monitoring period.

[0069] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0070] First of all, the term "and / or" in this article is only a description of the association relationship of the associated objects, indicating that there can be three relationships. For example, A and / or B can mean: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.

[0071] This application provides Figure 1 A dam deformation monitoring method shown includes steps S11-S15:

[0072] Regarding step S11, historical data to be processed at each monitoring point in the target dam within a historical time period is obtained, and the historical data to be processed includes historical deformation and mean values ​​of environmental factors, and the mean values ​​of environmental factors include daily average point temperature and daily average point pressure.

[0073] A target dam refers to a dam that requires deformation monitoring. There are usually several monitoring points on the target dam, and the monitoring points are generally evenly distributed. After the dam is built, data from each monitoring point can be obtained based on the monitoring points arranged on the dam.

[0074] The historical data to be processed in the historical time period refers to the data of the target dam in a certain period in the past. The length of the historical time period can be one year, half a year, etc. The historical data to be processed includes the historical deformation and the mean value of environmental factors. It should be understood that the historical deformation refers to the total deformation (total displacement) obtained by the monitoring point during the historical time period. A certain period in the past when the geological activities are relatively stable and the environmental factors are relatively stable can be selected as the historical time period.

[0075] The mean values ​​of environmental factors include the daily average point temperature and the daily average point pressure, that is, the daily average temperature and the daily average pressure at the monitoring point obtained during the historical period.

[0076] Regarding step S12, gross errors in the historical data to be processed of each monitoring point are eliminated to obtain the historical processed data of each monitoring point in the historical time period.

[0077] At present, there are several ways to eliminate gross errors in various monitoring data of the target dam. This application provides the following methods, including:

[0078] Determine the correlation relationship between each monitoring point in the target dam, the correlation relationship includes a similar correlation relationship and a non-similar correlation relationship; determine the data distances corresponding to the historical data to be processed of several monitoring points with similar correlation relationships; and take the historical data to be processed corresponding to the data distance greater than the preset data distance as a gross error.

[0079] Specifically, the deformation curve of each monitoring point of the target dam can be predicted by inputting the mean value of the environmental factor based on the neural network algorithm, and the monitoring points corresponding to the curves with a certain similarity are regarded as several monitoring points with similar correlation relationships. Then, the data distance of the historical data to be processed of several monitoring points with similar correlation relationships is calculated (for example, based on the OPTICS algorithm), and the historical data to be processed corresponding to the data distance greater than the preset data distance is regarded as gross error and eliminated.

[0080] The method for eliminating gross errors provided in the present application actually emphasizes the classification of the mean values ​​of environmental factors, and achieves the prediction of the deformation curve based on the classification of environmental factors.

[0081] Regarding step S13, the historical damage degree of the target dam is determined based on the historical processed data of each monitoring point in the target dam within the historical time period.

[0082] The historical damage degree of the target dam during the historical time period can be determined in the following way.

[0083] The formula for historical damage includes:

[0084]

[0085] Where R is the historical damage degree of the target dam, m is the number of monitoring points, is the maximum historical deformation, is the minimum historical deformation, is the historical deformation of the ith monitoring point, is the temperature damage degree of the ith monitoring point on the jth day, n is the number of days in the historical time period, is the pressure damage degree of the ith monitoring point on the jth day, , , They are all weight factors, which can be determined according to the actual situation of the target dam.

[0086] about The formula includes:

[0087]

[0088] Where A is a constant, The average temperature of the i-th monitoring point in the historical period, is the daily average point temperature of the ith monitoring point on the jth day, is the highest temperature of the ith monitoring point in the historical time period.

[0089] about The formula includes:

[0090]

[0091] Where B is a constant, The average pressure of the i-th monitoring point in the historical time period, is the daily average point pressure of the ith monitoring point on the jth day, is the highest pressure of the ith monitoring point in the historical time period.

[0092] This application can accurately determine the historical damage degree of the target dam through the mean value of environmental factors and the deformation. In other words, it can determine the degree to which the target dam is affected by the environment and the degree of deformation every day during the historical period, which is equivalent to providing standard values ​​for the target dam's daily environmental impact and deformation.

[0093] Regarding step S14, the target dam is divided according to the historical processed data of each monitoring point in the target dam within the historical time period to obtain a number of target dam sub-areas.

[0094] This application provides two division methods:

[0095]

Method 1

[0096] Determine the monitoring scope of each monitoring point; determine the historical damage degree of each monitoring point based on the historical processed data of each monitoring point in the target dam within the historical time period; determine the damage similarity corresponding to each monitoring point based on the historical damage degree of each monitoring point and the historical damage degree of the target dam; determine the sub-area of ​​the target dam corresponding to each similarity level based on the damage similarity corresponding to each monitoring point, the monitoring scope of each monitoring point and the preset rules for similarity level division.

[0097] It is understandable that the data obtained by the monitoring point on the target dam refers to the data of the monitoring point, but it is unrealistic to cover the entire target dam with monitoring points. Therefore, when initially designing the monitoring points, they are usually arranged evenly so that the data of the dam can be obtained more comprehensively. The present application divides the monitoring range of the monitoring point according to the initial layout position of the monitoring on the dam to obtain the monitoring range of each monitoring point. In other words, the present application determines the monitoring range of each monitoring point so that the monitoring data obtained by each monitoring point represents the monitoring data of the monitoring range within the monitoring point.

[0098] Specifically, when there are adjacent monitoring points around a monitoring point, the distance between the two adjacent monitoring points is evenly divided, and multiple divisions are performed around the monitoring point to obtain the monitoring range of the monitoring room.

[0099] For example, Figure 2 In the figure, there are adjacent monitoring points B, C and D at monitoring point A. The midpoint line between monitoring points A and B is a1, the midpoint line between monitoring points A and C is a2, and the midpoint line between monitoring points A and D is a3, thereby constructing the monitoring range Q1 of monitoring point A.

[0100] According to the historical processed data of each monitoring point in the target dam within the historical time period, determining the historical damage degree of each monitoring point can be similar to determining the damage degree of the target dam as described above, with the only difference being that the number of monitoring points m is 1.

[0101] The damage similarity corresponding to each monitoring point can be determined based on the historical damage degree of each monitoring point and the historical damage degree of the target dam, including:

[0102]

[0103] in, is the damage similarity of the ith monitoring point, is the historical damage degree of the monitoring point.

[0104] The target dam sub-area corresponding to each similarity level can be determined according to the damage similarity corresponding to each monitoring point, the monitoring range of each monitoring point and the preset rules for similarity level division.

[0105] The preset rule for similarity level division is to divide the monitoring ranges of monitoring points with high similarity in daily average deformation and daily average environmental impact together to form an area with high similarity in daily average deformation and daily average environmental impact.

[0106] The preset rules for similarity level division can specifically be to divide the damage similarity into 100-98%, 98%-96%, 96%-94%, etc., and the preset rules for similarity level division can be set according to the actual situation of the target dam, and there is no restriction here. (For example, the monitoring range corresponding to the monitoring points with damage similarity of 100-98% constitutes a sub-area of ​​the target dam).

[0107] For example, Figure 2 The damage similarities of monitoring points A, B, C, D, and E are all between 98% and 96%, and 98% to 96% is a similarity level. According to the monitoring ranges corresponding to the monitoring points A, B, C, D, and E, they jointly form a target dam sub-area W1. In addition, Figure 2 The target dam in also has target dam sub-regions W2, W2 and W3. It can be understood that W2, W2 and W3 represent different similarity levels respectively.

[0108] This application determines the monitoring range of each monitoring point and divides the monitoring range of monitoring points with high similarity into a target dam sub-area, which can provide an accurate basis for determining the target monitoring frequency and target monitoring period of each target dam sub-area later.

[0109] It is understandable that, although the target dam sub-regions obtained by dividing according to [Method 1] have high similarity, the target dam sub-regions may not be continuously distributed. For example, Figure 2 W1 in Figure 2 In two places.

[0110]

Method 2

[0111] Determine the monitoring range of each monitoring point; determine the historical damage degree of each monitoring point in the target dam based on the historical processed data of each monitoring point in the historical time period; when the sum of the historical damage degrees of several adjacent monitoring points in the target dam is within the preset damage degree division range, divide the target dam once according to the monitoring range of several adjacent monitoring points to obtain a target dam sub-area.

[0112] In [Method 2], the monitoring range of each monitoring point is determined; based on the historical processed data of each monitoring point in the target dam within the historical time period, the method for determining the historical damage degree of each monitoring point is the same as in [Method 1] and will not be repeated here.

[0113] The preset damage degree division range can be determined according to the actual situation of the dam. For example, when the sum of the historical damage degrees of adjacent monitoring points is in the range of [1.0-1.5], the division is in order. In other words, whenever the sum of the historical damage degrees of adjacent monitoring points reaches the range of [1.0-1.5], the monitoring range of this part of the monitoring points constitutes a target dam sub-area.

[0114] It can be understood that according to [Method 2], the target dam sub-areas are continuous and the total historical damage degree between the target dam sub-areas is similar.

[0115] Regarding step S15, for each target dam sub-area, steps S151-S153 are executed, including:

[0116] Step S151, determining the target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam.

[0117] The preset duration can be 15, 20, 30 days, etc. The real-time average damage degree of the target dam sub-area can be determined based on the real-time damage degree of each monitoring point in the target dam sub-area within the preset duration (the calculation method is similar to the above, the maximum pressure, maximum temperature, maximum and minimum deformation are all within the historical time period, n is determined based on the preset duration, and m is the number of monitoring points in the target dam sub-area); the target monitoring frequency of the target dam sub-area is determined based on the real-time average damage degree of the target dam sub-area, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam, including:

[0118]

[0119] in, is the target monitoring frequency for the target dam sub-area, is the real-time average damage degree of the target dam, Set monitoring frequency for history.

[0120] The deviation degree between the monitoring point and the “standard value” can be determined by the ratio of the real-time average damage degree of the target dam sub-area to the historical damage degree of the target dam. When the ratio is less than 1, it means that the deformation of the target dam sub-area is low, and this part is a low-risk area, which can be monitored at a lower monitoring frequency; When the ratio is greater than 1, it means that the target dam sub-area has a high deformation. This part is a high-risk area and can be monitored at a higher monitoring frequency.

[0121] Step S152, determining the target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam.

[0122] The monitoring cycle of a dam is usually fixed, such as once every six months or once a year.

[0123] The target monitoring period for the target sub-dams determined in this application includes:

[0124]

[0125] in, is the target monitoring period of the target sub-dam, Set monitoring periods for the history of the target sub-dam, It is a preset adjustment parameter, which is usually less than 1 and can be determined according to the actual situation of the dam, for example, set to 0.8, 0.9, or 0.95.

[0126] It is understandable that when When the ratio is less than 1, the deformation of the target dam sub-area is low. In addition to monitoring at a lower monitoring frequency, it can also be monitored at a longer monitoring period; when the deformation of the target dam sub-area is high, the opposite is true.

[0127] It is understandable that the current monitoring of dams is usually an overall detection without dividing the area, and the detection frequency and monitoring cycle are unified, but the environmental impact and deformation degree of each part of the dam are different. This application determines the monitoring range of each monitoring point and obtains the target dam sub-area through two ways of dividing the area, so that targeted monitoring can be carried out, specifically for the area affected by environmental factors and with higher deformation, a higher frequency and shorter period of monitoring is carried out, which improves the safety of this area; for the area affected by environmental factors and with higher deformation, a lower monitoring frequency and a longer monitoring cycle are adopted, which reduces the waste of resources and improves the purpose of rationally allocating monitoring resources. And this application can accurately determine the target monitoring frequency of the target dam sub-area through the real-time damage degree, the historical damage degree of the target dam, and the historical setting monitoring frequency of the target dam. The monitoring cycle of the target dam sub-area can also be accurately determined through the target monitoring frequency, and the target dam sub-area is monitored with the target detection frequency and the target monitoring cycle, which improves the accuracy of dam deformation monitoring.

[0128] In addition, the dam is divided by [Method 1]. Although the sub-areas of the dam of the same level are not continuous, the monitoring points in the sub-areas of the same level are similarly affected by the environment and have similar deformation amounts. The same monitoring frequency and monitoring period are used for monitoring points with similar characteristics, and the accuracy and precision of deformation monitoring are higher.

[0129] By dividing the dam using [Method 2], the overall damage degree of each dam sub-area is similar. Although its accuracy may not be as good as that of Method 1, since the sub-areas are divided based on adjacent monitoring points, the accuracy difference is not large (the deformation degree of adjacent monitoring points is usually not too large, and it is also limited by the similarity of the overall damage degree). In addition, dividing according to Method [2] can connect the sub-areas of the target dam to form a whole, which can be convenient for relevant personnel to view and operate, and its convenience is higher.

[0130] Step S153, performing deformation monitoring on the target dam sub-area at a target monitoring frequency within a target monitoring period.

[0131] After the target monitoring frequency and target monitoring period of each target dam sub-region are determined, deformation monitoring of each target dam sub-region may be performed at the target monitoring frequency and target monitoring period corresponding to each target dam sub-region.

[0132] It is understandable that when geological activities occur in the geological area where the target dam is located, the dam may undergo large deformation and displacement. In other words, the monitoring points on the target dam will also undergo large displacements, which means that the monitoring points may be seriously unevenly distributed. At this time, the monitoring effect is poor and the monitoring points need to be rearranged. If the monitoring point setting map is redesigned, it will be time-consuming, labor-intensive and inefficient.

[0133] This application is aimed at dams with severe deformation and also includes:

[0134] The initial monitoring point location setting diagram of the target dam is obtained, and the maximum adjustable range of each monitoring point is determined, wherein the initial monitoring point location setting diagram includes the initial position of each monitoring point; based on the initial position of the monitoring point and the real-time position of the monitoring point, it is determined whether there is a need for position adjustment of the monitoring point; if so, within the maximum adjustable range of the monitoring point, based on the positional relationship between the monitoring point and several adjacent monitoring points, with the goal of uniform adjacent distances and shortest adjustment distance, the target adjustment position of the monitoring point within the maximum adjustable range is determined; the real-time position of the monitoring point in the target dam is adjusted to the target adjustment position.

[0135] The initial monitoring point setting diagram refers to the setting diagram for the arrangement of monitoring points for the target dam, which includes the initial three-dimensional coordinates of the monitoring points. The maximum adjustable range of each monitoring point needs to be determined based on the actual situation of the dam and the spacing between adjacent monitoring points. Specifically, the maximum adjustable range of the monitoring point can be constructed with a radius of 1 / 3, 1 / 4 or 1 / 5 of the spacing between adjacent monitoring points.

[0136] The maximum adjustable range should not be too large. A larger range will not only reduce the calculation efficiency, but may also cause a large gap between the final target adjustment position and the initial position of the monitoring point, making it difficult for relevant personnel to operate.

[0137] Whether adjustment is needed is determined based on the difference between the initial position of the monitoring point and the real-time position of the monitoring point. When the difference is greater than a threshold, it indicates that the real-time position of the monitoring point has moved too much and the monitoring point can no longer be effectively monitored.

[0138] Uniform adjacent distances means that the spacing between the monitoring points that need to be adjusted and the adjacent monitoring points is evenly distributed (or the sum of the spacing between the monitoring points that need to be adjusted and the adjacent monitoring points is the smallest), so that the target dam can be monitored more comprehensively; the shortest adjustment distance means that the monitoring points that need to be adjusted are adjusted at the shortest distance, which is convenient for relevant personnel to operate.

[0139] After determining the target adjustment position according to the above two adjustment targets, relevant personnel can adjust the real-time position of the monitoring point in the target dam to the target adjustment position.

[0140] In summary, the present application provides a dam deformation monitoring method, including: obtaining historical data to be processed at each monitoring point in the target dam within a historical time period, the historical data to be processed including historical deformation and environmental factor averages, the environmental factor averages including daily average point temperature and daily average point pressure; eliminating gross errors in the historical data to be processed at each monitoring point to obtain historical processed data at each monitoring point within a historical time period; determining the historical damage degree of the target dam based on the historical processed data at each monitoring point in the target dam within a historical time period; dividing the target dam based on the historical processed data at each monitoring point in the target dam within a historical time period to obtain a number of target dams. Dam sub-area; for each target dam sub-area, execute steps S151-S153, including: step S151, determine the target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within the preset time, the historical damage degree of the target dam, and the historical setting monitoring frequency of the target dam; step S152, determine the target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historical setting monitoring frequency of the target dam, and the historical setting monitoring period of the target dam; step S153, monitor the deformation of the target dam sub-area at the target monitoring frequency within the target monitoring period. The present application determines the monitoring range of each monitoring point and obtains the target dam sub-area through two ways of dividing the area, so as to carry out targeted monitoring, specifically, carry out higher frequency and shorter period monitoring for the area affected by environmental factors and with higher deformation, thereby improving the safety of this area; for the area affected by environmental factors and with higher deformation, a lower monitoring frequency and a longer monitoring period are adopted, thereby reducing the waste of resources and improving the purpose of reasonable allocation of monitoring resources.

[0141] This application also determines whether the monitoring point needs to be rearranged based on the location distance, and by setting the maximum adjustable range and taking the uniform adjacent distance and the shortest adjustment distance as the adjustment target, the monitoring point can determine the target adjustment position within the maximum adjustable range, thereby meeting the dam monitoring needs, ensuring the safety of dam monitoring, and reducing the work difficulty of relevant personnel.

[0142] In addition, the present application also provides a method for eliminating gross data errors. The neural network algorithm inputs the mean value of environmental factors to predict the deformation curve of each monitoring point of the target dam. It emphasizes the classification of the mean value of environmental factors, and predicts the deformation curve based on the classification of environmental factors, and eliminates gross data errors based on data distance.

[0143] Based on the same inventive concept, the present application also provides Figure 3 A dam deformation monitoring device is shown, the device comprising:

[0144] An acquisition module 31 is used to acquire historical data to be processed at each monitoring point in the target dam within a historical time period, wherein the historical data to be processed includes historical deformation and environmental factor mean values, wherein the environmental factor mean values ​​include daily average point temperature and daily average point pressure;

[0145] The elimination module 32 is used to eliminate gross errors in the historical data to be processed of each monitoring point, and obtain the historical processed data of each monitoring point in the historical time period;

[0146] A damage degree determination module 33 is used to determine the historical damage degree of the target dam based on the historical processed data of each monitoring point in the target dam within the historical time period;

[0147] A division module 34 is used to divide the target dam according to the historical processed data of each monitoring point in the target dam within the historical time period to obtain a plurality of target dam sub-areas;

[0148] The monitoring module 35 is used to execute steps S151-S153 for each target dam sub-area, including:

[0149] Step S151, determining a target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam;

[0150] Step S152, determining a target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam;

[0151] Step S153, performing deformation monitoring on the target dam sub-area at a target monitoring frequency within a target monitoring period.

[0152] Based on the same inventive concept, the present application also provides Figure 4 An electronic device as shown includes:

[0153] Processor 41;

[0154] A memory 42 for storing instructions executable by the processor 41;

[0155] The processor 41 is configured to execute to implement a dam deformation monitoring method as provided above.

[0156] Since the electronic device introduced in this embodiment is an electronic device used to implement the information processing method in the embodiment of the present application, based on the information processing method introduced in the embodiment of the present application, a person skilled in the art can understand the specific implementation of the electronic device of the present embodiment and its various variations, so how the electronic device implements the method in the embodiment of the present application is not described in detail here. As long as a person skilled in the art implements the electronic device used by the information processing method in the embodiment of the present application, it belongs to the scope of protection of this application.

[0157] It will be appreciated by those skilled in the art that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Furthermore, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0158] The present invention is described with reference to flowcharts and / or block diagrams of methods, devices (systems), and computer program products according to embodiments of the present invention. It should be understood that each process and / or block in the flowchart and / or block diagram, as well as the combination of processes and / or blocks in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0159] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0160] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1The steps for the functions specified in one or more boxes.

[0161] Although the preferred embodiments of the present invention have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present invention.

[0162] Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the spirit and scope of the present invention. Thus, if these modifications and variations of the present invention fall within the scope of the claims of the present invention and their equivalents, the present invention is also intended to include these modifications and variations.

Claims

1. A dam deformation monitoring method, characterized in that: The method comprises: Obtaining historical data to be processed at each monitoring point in the target dam within a historical time period, wherein the historical data to be processed includes historical deformation and environmental factor mean values, wherein the environmental factor mean values ​​include daily average point temperature and daily average point pressure; Eliminate the gross errors in the historical data to be processed at each monitoring point to obtain the historical processed data of each monitoring point in the historical time period; According to the historical processed data of each monitoring point in the target dam in the historical time period, the historical damage degree of the target dam is determined, wherein the formula for the historical damage degree includes: Where R is the historical damage degree of the target dam, m is the number of monitoring points, is the maximum historical deformation, is the minimum historical deformation, is the historical deformation of the ith monitoring point, is the temperature damage degree of the ith monitoring point on the jth day, n is the number of days in the historical time period, is the pressure damage degree of the ith monitoring point on the jth day, , , All are weight factors; Among them, about The formula includes: Where A is a constant, The average temperature of the i-th monitoring point in the historical period, is the daily average point temperature of the ith monitoring point on the jth day, is the highest temperature of the i-th monitoring point in the historical time period; Among them, about The formula includes: Where B is a constant, The average pressure of the i-th monitoring point in the historical time period, is the daily average point pressure of the ith monitoring point on the jth day, is the highest pressure of the i-th monitoring point in the historical time period; According to the historical processed data of each monitoring point in the target dam within the historical time period, the target dam is divided to obtain a plurality of target dam sub-areas; For each target dam sub-area, steps S151-S153 are executed, including: Step S151, determining a target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam; Step S152, determining a target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam; Step S153: Perform deformation monitoring on the target dam sub-area at the target monitoring frequency within the target monitoring period.

2. A dam deformation monitoring method according to claim 1, characterized in that: According to the historical processed data of each monitoring point in the target dam within the historical time period, the target dam is divided to obtain a number of target dam sub-areas, including: Determine the monitoring scope of each monitoring point; Determine the historical damage degree of each monitoring point according to the historical processed data of each monitoring point in the target dam within the historical time period; Determine the damage similarity corresponding to each monitoring point according to the historical damage degree of each monitoring point and the historical damage degree of the target dam; According to the damage similarity corresponding to each monitoring point, the monitoring range of each monitoring point and the preset rules for similarity level division, the target dam sub-area corresponding to each similarity level is determined.

3. A dam deformation monitoring method according to claim 1, characterized in that: The target dam is divided according to the historical processed data of each monitoring point in the target dam within the historical time period to obtain a plurality of target dam sub-areas, and further includes: Determine the monitoring scope of each monitoring point; Determine the historical damage degree of each monitoring point according to the historical processed data of each monitoring point in the target dam within the historical time period; When the sum of the historical damage degrees of several adjacent monitoring points in the target dam is within the preset damage degree division range, the target dam is divided once according to the monitoring ranges of several adjacent monitoring points to obtain a target dam sub-area.

4. A dam deformation monitoring method according to claim 1, characterized in that: The method further comprises: Obtaining an initial monitoring point location setting diagram of the target dam, and determining a maximum adjustable range of each monitoring point, wherein the initial monitoring point location setting diagram includes an initial position of each monitoring point; According to the initial position of the monitoring point and the real-time position of the monitoring point, determining whether there is a need to adjust the position of the monitoring point; If it exists, then in the maximum adjustable range of the monitoring point, according to the positional relationship between the monitoring point and several adjacent monitoring points, with the goal of uniform adjacent distances and the shortest adjustment distance, determine the target adjustment position of the monitoring point in the maximum adjustable range; The real-time position of the monitoring point in the target dam is adjusted to the target adjustment position.

5. A dam deformation monitoring method according to claim 1, characterized in that: The step of removing gross errors from the historical data to be processed at each monitoring point to obtain the historical processed data of each monitoring point within the historical time period includes: Determine the association relationship of each monitoring point in the target dam, wherein the association relationship includes a similar association relationship and a non-similar association relationship; Determine the data distances corresponding to the historical data to be processed of several monitoring points with similar correlation relationships; The historical data to be processed corresponding to the data distance greater than the preset data distance is regarded as a gross error.

6. A dam deformation monitoring device, characterized in that: A dam deformation monitoring method applied to any one of claims 1 to 5, the device comprising: An acquisition module is used to acquire historical data to be processed at each monitoring point in the target dam within a historical time period, wherein the historical data to be processed includes historical deformation and an average value of environmental factors, wherein the average value of environmental factors includes an average daily point temperature and an average daily point pressure; The elimination module is used to eliminate the gross errors in the historical data to be processed of each monitoring point, and obtain the historical processed data of each monitoring point in the historical time period; A damage degree determination module, used to determine the historical damage degree of the target dam according to the historical processed data of each monitoring point in the target dam within a historical time period; A division module, used for dividing the target dam according to the historical processed data of each monitoring point in the target dam within a historical time period, to obtain a plurality of target dam sub-areas; The monitoring module is used to execute steps S151-S153 for each target dam sub-area, including: Step S151, determining a target monitoring frequency of the target dam sub-area according to the real-time damage degree of each monitoring point in the target dam sub-area within a preset time period, the historical damage degree of the target dam, and the historical set monitoring frequency of the target dam; Step S152, determining a target monitoring period of the target sub-dam according to the target monitoring frequency of the target dam sub-area, the historically set monitoring frequency of the target dam, and the historically set monitoring period of the target dam; Step S153: Perform deformation monitoring on the target dam sub-area at the target monitoring frequency within the target monitoring period.

7. An electronic device, characterized in that: include: processor; a memory for storing instructions executable by the processor; The processor is configured to execute to implement a dam deformation monitoring method as described in any one of claims 1 to 5.